You are on page 1of 19

Company Name Logo

Standard
Prequalification Form
For Contractors

D.M.Raveendra M/S AKRUTI BUILDERS


No.25 I cross N.H.Muniyappa layout,V.naganahalli
Name and address of the Contractor: R.T.nagar,Bangalore-560032.

Date :10-09-2010.

N.B. Form to be typed not handwritten.

Page A
Company Name Logo

Prequalification form

Company:

Notes to applicants

1. Please answer all questions.

2. Supplementary pages may be photocopied and inserted if required.

3. If a joint venture is proposed, all parties are to respond to all questions.

4. Project financial data is to be given in INR unless otherwise requested.

Standard pages

A Title page H Resources Sheet 2: personnel B


B Notes I Resources Sheet 3: plant
C Structure and organisation Sheet 1 J Resources Sheet 4: other
D Structure and organisation Sheet 2 K Experience: geographical
E Financial statement L Experience: relevant projects completed
F Joint Venture M Experience: projects in progress
G Resources Sheet 1: personnel A N Additional information Sheet 1
O Additional information Sheet 2

Please list below any additional pages attached to each standard page:

Page B
Company Name Logo

Prequalification form

Company:

Structure and organisation Sheet 1

1. Name of company: AKRUTI BUILDERS


Address: No.25,Ist cross,N.H.Muniappa layout
V.Naganahalli,R.T.Nagar,Bengaluru-560032

Telephone number: 23651083 Telefax number:


Registered office address:

Same E-mail ; raveendradm@yahoo.in

2. Description of company
a) Main field of activity (e.g. Civil, Building, General Civil Engineering
Contractor, etc.) (Specify)
Contractor

b) Experience in High Rise Buildings: List project, year of completion of project


and number of floors

5 floors
c) Other fields of activity (Specify)
Electricals,plumbing

3. Number of years experience as a general contractor - India :20 yrs


4.

International :

5. Number of years experience as a subcontractor - India : Nil

International :

6. Details of licenses, VAT,CST, PAN, Certificate of Incorporation, Authorization


Certificate for carrying out Civil Works and addresses of associated companies to be
involved in projects - and whether parent/subsidiary/other:

Will be furnished later

7. If the company is a subsidiary, what involvement, if any, will the parent company
have in the project
Company Name Logo

As preferred by parent company

Page C
Company Name Logo

Prequalification form

Company:

Structure and organisation Sheet 2

7. List here and give details of all main Sub-Contractors regularly used for project work.

Manohar

Muniraju

8. Please indicate here or attach an organisation chart showing the company structure
including the positions of directors and key personnel, if relevant

NIL

Page D
Company Name Logo

Prequalification form

Company:

Financial statement

1. Capital:
Authorised:
Issued:

2. Annual value of work undertaken for each of the last five years and projected for current
year in INR. Millions (attach a separate sheet showing the type and value of work,
clearly identifying whether Building, Civil, Electrical or Mechanical, etc. and the relevant
values of each type of work:

Year Current
Home 10.5 m 5.0m 4.0m 3.0m 5.0m 7.0m

Abroad

3. Approximate value of work in hand in Millions :3.5m

4. Please attach copies of the company’s previous three years’ accounts (profit/loss,
assets/liabilities) and other financial data which you consider to be useful.
List all attachments below:

Will be furnished later

5. Name and address of bankers from whom references can be obtained:

State bank of India sulthanpalya R.T.nagar

6. List here all company insurances held including Workers Compensation, Plant and
Equipment, Third Party Liability Professional Indemnity.

NIL
Company Name Logo

Page E
Company Name Logo

Prequalification form

Company:

Joint Venture

If the company intends to enter into a joint venture for the project/projects, please give the
following information, otherwise state “not applicable”:

1. Names and addresses of joint venture partners:

NIL

2. Name of company leading the joint venture:

NIL

3. Name and address of bankers to the joint venture:

NIL

Page F
Company Name Logo

Prequalification form

Company:

Resources Sheet 1: personnel A

1. Number of staff: 5 Technical: 4 Administ rative 1


2. :

3. Please list present Senior personnel, administrative & technical and attach resumes.

Name Present position Qualifications Years of experience Total relevant


with company experience

B.T.Rajesh site engr D.civil 4 12

Akram site engr D.civil 3 10

R.Aswathaiah site engr B.E. 6 15

Manohar superviser SSLC 8 10


Company Name Logo

Page G
Company Name Logo

Prequalification form

Company:

Resources Sheet 2: personnel B

Resources Labour: Give details of current ‘Block’ allocations and other arrangements for the
supply of labour with evidence to support these.

As per site requirement

Page H
Company Name Logo

Prequalification form

Company:

Resources Sheet 3: Contractor’s/plant


equipment and facilities

Please provide a list of main equipment, machinery and facilities owned by Company

Mixer,vibrator,drilling mashine .centring sheets,scaffolding etc.

Page I
Company Name Logo

Prequalification form

Company:

Resources Sheet 4: other

List
1. Fabrication facilities by type and provide brief description, location, capacity and
annual throughput. Gas welding.arc welding@Rajajinagar.
2. Formwork/ Scaffolding materials available: 4000 Sq.Ft
Company Name Logo

Page J
Company Name Logo

Prequalification form

Company:

Experience: geographical

1. List major projects undertaken with location in India and Value.

See attached form (Page L)

2. List most important projects undertaken with overseas location and Value.

See attached form (Page M)

3. List main projects carried out under design + build contract conditions and provide
details of any design capabilities within the company and details of any arrangements
with Consulting Engineers/Architects for the provision of Design/Supervision services for
Design/Build Contracts. (Attach separate list if required)

Page K
Company Name Logo

Prequalification form
Page of total pages
Company:

Experience: relevant projects completed

Give information about all recent major projects/completed.

Percentage of
Was contract satisfactorily
Name of (consulting) engineer Contract price and participation of
Name of employer Name, location and type of project completed to cost, quality & time
responsible for supervision date company in
provision
project
Kunchitigara women’s Magadi road Gangadhar 7.5m 75% Yes
hostel 2004

Sheshadripuram college Yalahanka Team-2 100% Yes


6.5
1995

Balchand Hebbal Kabra associates 10.5 60% yes


2007

Page L
Company Name Logo

Prequalification form

Company:

Experience: all projects in progress

Give information about all project in progress, including those where the company has received
a letter of intent, but a formal contract has not yet been awarded.

Name of (consulting) Percentage of Percentage of


Name, location and Value completed Scheduled date of
Name of employer engineer responsible for Value of contract participation of practical
type of project and certified completion of work
supervision company in project completion

Ramabhat Vidyaranyapura self 3.5m Under progress 100% _ _

Govind Mavalli Kabra associates 2.5m _____ 100% ____________ ___

Page M
Company Name Logo

Prequalification form

Company:

Additional Information Sheet 1

1 Company’s quality assurance system: (Give details and provide QA manual)

N.A

2 Company’s environmental policy:

N.A.

3 Company Safety Policies (Give details and provide safety manual)

N.A

4 Company’s history of litigation or arbitration from contracts executed in the last six years
or currently under execution. Please indicate for each case year, name of employer,
cause of litigation, matter in dispute, and whether the award was for or against
company.
N.A.

5 State project value range for which you wish to be considered.

20.0M

6 Please add any further information which you consider to be relevant to the evaluation
of your application for prequalification. If you wish to attach other documents and list
these below.

Page N
Company Name Logo

Prequalification form

Company:

Additional Information Sheet 2

7 Company’s cost control system.

By architect

8 Company’s material control system.

By architect

9 Company’s planning and scheduling resources system.

By architect

10 Circumstance where performance bond withdrawn?

NIL

Page O

You might also like