Professional Documents
Culture Documents
: HSE/FRM-22
Rev.: 00
JOB SAFETY ANALYSIS Date:
Page: 1 of 3
Severity Rating: (1) First Aid / Minor Property Damage (2) Recordable Accident / Property Damage
(3) Lost Time Accident / Major Property Loss (4) Catastrophic Accident
Are you aware of, and do you have the correct PPE? What are the risks? How do controlled risks?
_______________________________ __________________________
AREA ENGINEER / SUPERVISOR HSE REPRESENTATIVE
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
5) Locate crane in 1) Crane overturning due to 1) Outriggers must be positioned on a flat surface,
lifting position unstable ground condition 2) Using timbers or suitable material for pads to evenly
2) Personnel being crushed by distribute the load to the ground
on site outriggers 3) Crane to be located within the radius for the loads being
– place timbers Lifted.
(pads) and set 4) Outriggers should only be extended on the side where the
outriggers Operator is positioned or with a suitable spotter.
5) Where space permits, outriggers shall always be fully
extended
6) Where space is limited, crane should be configured to
maximum capacity – this may require the use of reduced
outriggers or on rubber; when permitted by the manufacturer
7) Outriggers shall always be extended to manufacturers
procedures and specifications, including the requirement to fit
manual pins
8) All outriggers-jacks should be utilized at all time
9) Generally Standard Safe Working Load capacity charts are
based on all outriggers fully extended and set with wheels
clear of ground.
10) Outrigger Packing –
11) Additional packing should always be utilized under outrigger
floats
12) Commonly used Outrigger Mats should carry design
information and be subject to periodic inspection
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
13) When timber packing is utilized, it should be in a ‘pigsty
‘packing
14) Arrangement ‘Rule of Thumb’ formulae and calculations
should be observed;
15) Area (m2) = 0.65 x (Cm + L)
-------------
V
Cm = Total mass of crane (KN)
L = Total mass of load (KN)
V = maximum permissible bearing pressure of soil (kpa
6) Attaching Fly Working at heights/falling 1) Follow W/H permit use appropriate attachment point & safety
or Pin harness when walking along crane boom
2) Use an EWP or ladder for this task & follow safe work
Jib to Crane practices
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
7) Position Position 1) Plant to be positioned in area clear of obstruction. Roads
counterweight counterweight truck 2) Traffic control in place if required
3) Once crane is elevated and level, a trial operation should be
truck in an easily completed by the operator; this may include
in an easily accessible spot for 4) Bluffing boom to high angle, and slewing 360 degrees with
accessible the crane to load its spotter in position – purpose to review tail swing and
spot for counterweights outrigger packing suitability
5) Executing ‘dry-run’ where load is required to be picked up
the crane to
and placed – Purpose to ensure crane is capable of task and
load its set required limits
counterweights
8) Re-assessing Changes in weather 1) Continual safe operation can be aided by periodic inspection
Situation conditions throughout the project of the following;
throughout Changes in operators 2) Outrigger Jacks – Leaking oil/retraction of shaft
job Changes in ground suitability 3) Outrigger Mats – excessive settlement and/or sinking into
ground; i.e., loadings increasing beyond estimated capacity
of ground – such as unknown back-filling
4) Outrigger Floats – Cracking or critical damage
5) Evidence of water content in ground
6) Should requirements change during operation, then crew
shall re-assess and review crane capacity and wider
environment to ensure revised work practice is within limits
and safe to continue operation
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
9) 10.Packing up Unauthorised person access 1) Upon completion of project, or specific stage the crane
and/or crane site 2) equipment and site shall be left in a secure and safe manner
leaving crane Damage to crane 3) If the crane is to be left onsite;
onsite Injury to public 4) Retract Boom, remove keys from the ignition and secure/lock
5) Outriggers should be inspected prior to next use
6) Barricading should remain in place around the crane and any
work area deemed necessary
10) Packing up and Trip hazards 1) Use correct manual handling techniques
cleaning up Manual handling injuries 2) Wear appropriate PPE
work site Crush & Pinch injuries 3) Rubbish to be placed in bins
Equipment damage 4) Tools & Equipment to be packed
Counterweights coming off 5) Lifting gear packed
the back of the truck 6) Timbers packed
Crush & pinch injuries 7) Pads loaded
8) Make certain counterweights are stacked on rubber mats and
Falls
correctly tied down for trip
9) Guide counterweights onto the truck tray with taglines
10) Where possible use EWP or Platform Ladder Access
otherwise be cautious of footing
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
11) Exit site and Overhead Powerlines 1) Crane boom to be down when travelling under power lines
return Collision with 2) Maintain site speed limit when exiting work site
to Depot people/personnel and other 3) Communicate with other vehicles onsite is necessary
vehicles/plant when exiting 4) Observe road rules and take into consideration drivers and
site riders who don’t understand the nature of cranes and trucks.
Counterweights sliding off
during travel
Traffic Accident
GS C Job Safety Analysis
PROJECT TITTLE
Company:
Additional approvals (Determine by Job Supervisor in Correlation with HSE Manager) GENERAL JOB REQUIREMENTS: TBM & PPE
1. Pre task tool box meeting everyday.
Name Signature Date
2. Personal Protective Equipment
2.1 Safety Shoes with steel toe.
2.2 Safety glasses
Company Representative 2.3 Hard hat
2.4 Hand gloves
2.5 Cover all to workers
2.6 Full body harness on working at heights
2.7 Chin strap for helmets
2.8 Appropriate mask or respirators
CHANGING CONDITIONS & EMERGENCY PROCEDURE: Stop Work, Switch off equipment, Supervisor Direct Personnel to Nearest and Safety Muster Point considering
wind direction. Supervisor accounts for all workers. In case of emergency contact 911 / 02-425-0911
Job Safety Analysis on Lifting Works
Residual
Initial Risk
Risk
Rating Control Measures Responsible
Task / Activities Initial Risk Rating
H M L H M L
H M L H M L
-Personal Injury or Equipment Failure • Check all the equipment or rigging devices to ensure Work Supervisor
good performance.
-Tumbling of the crane. • Set the barriers around operating area and assign the HSE Officer
watchman to keep non-related persons away.
-Collision of crane to powerlines & other • The equipment operator and riggers shall be qualified Rigger
properties. and certified for competence. (Should have 3rd Party
Certification). Operator
6. Lifting, incl. loading • Riggers should have designated reflective vest &
-Falling of the crane load to workers & H
and unloading whistle. M
other properties.
• Operate as per the lift instruction and load chart.
• Load shall be controlled with taglines during hoisting.
-Strong winds & abnormal weather
• Only rigging devices (sling, chain block, etc.) of correct
conditions. capacity shall be used for hoisting.
• Ground must be even and compacted where the crane is
-Working or passing of workers to to be positioned.
suspended load. • Ensure that the outriggers are fully extended prior to lift.
• Ensure to use proper outrigger pads and proper size.
H M L H M L