Question text

Enables you to view your requirements hierarchically in a tree.

Select one:
a. Requirement Details
b. Coverage Analysis
c. Requirements Grid
d. Requirement Tree

Question 2
Complete
Mark 1.00 out of 1.00

Flag question

Question text

A good test plan enables you to assess the quality of your application at any point in the
application management process.

Select one:
True
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
False

Question 3
Complete
Mark 1.00 out of 1.00

Flag question

Question text

You run tests ________ from ALM using HP Sprinter.

Select one:
a. None of the choices
b. Automatically
c. Manually and Automatically
d. Manually

Question 4
Complete
Mark 1.00 out of 1.00

Flag question

Question text

This scanner, relevant only for web applications, checks your application for broken
hyperlinks and missing referenced content.

Select one:
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
a. Location scanner
b. Web standards scanner
c. Broken links scanner
d. Spell check scanner

Question 5
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Enables you to create and edit tests or components directly in Sprinter and save them to
ALM.

Select one:
a. Button Plan mode
b. ALM Plan mode
c. Sprinter's Plan mode
d. None of the choices

Question 6
Complete
Mark 1.00 out of 1.00

Flag question

Question text
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Sprinter runs auto tests in ALM from the Test Lab module.

Select one:
True
False

Question 7
Complete
Mark 1.00 out of 1.00

Flag question

Question text

You start building a requirements tree by creating a requirement within the Requirements
______at the root level.

Select one:
a. Files
b. Folder
c. None of the choices
d. Tree

Question 8
Complete
Mark 1.00 out of 1.00

Flag question
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Question text

To create the Test Plan tree in the Test Plan module, you manually create folders and add
tests to these folders.

Select one:
True
False

Question 9
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Enables you to control the execution of automated tests by setting test run conditions and
creating a schedule.

Select one:
a. Run the tests
b. Develop the Test Set Tree
c. Set automation options
d. Organize test runs

Question 10
Complete
Mark 1.00 out of 1.00
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael

Flag question

Question text

Which of the following new features allows you to perform testing with a single motivation
of identifying defects?

Select one:
a. View the storyboard
b. None of the choices
c. Exploratory testing
d. Access the storyboard

Question 11
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Provides a clear picture of the test building blocks and assists in the execution of the actual
tests.

Select one:
a. Organize test runs
b. Develop the Test Sets tree
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
c. Run the tests
d. Set automation options

Question 12
Complete
Mark 1.00 out of 1.00

Flag question

Question text

You can _______ to a Word or PDF file. This file contains the run summary, step status, and
defect information for the run session.

Select one:
a. Access the Storyboard
b. Export a Storyboard
c. None of the choices
d. View the Storyboard

Question 13
Complete
Mark 1.00 out of 1.00

Flag question

Question text

A _______ is a variable that can be assigned a value during test execution.


CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Select one:
a. Test planning
b. Template
c. Test
d. Parameter

Question 14
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Enables you to create links between requirements and other entities.

Select one:
a. Requirements Grid
b. Coverage Analysis
c. Requirement Tree
d. Requirements Details

Question 15
Complete
Mark 1.00 out of 1.00

Flag question

Question text
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Enables you to view traceability relationships between requirements and other requirements
or tests in a matrix.

Select one:
a. Traceability Matrix
b. Coverage Analysis
c. Requirements Grid
d. Requirements Details

Question 16
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Enables you to associate the selected requirement with other requirements in the
requirements tree

Select one:
a. Risk assessment
b. Requirements Traceability
c. Details
d. Test Coverage

Question 17
Complete
Mark 1.00 out of 1.00
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael

Flag question

Question text

You use the ________ to add an existing test or component to the Tests and Components list.

Select one:
a. Save button
b. New button
c. Open button
d. None of the choices

Question 18
Complete
Mark 1.00 out of 1.00

Flag question

Question text

A _______ contains the actions that must be performed during test execution.

Select one:
a. Test script
b. Designing test
c. Test planning
d. None of the choices
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Question 19
Complete
Mark 1.00 out of 1.00

Flag question

Question text

A test can cover more than one______ and a requirement can be covered by more than one
test.

Select one:
a. Requirement
b. Activity
c. None of the choices
d. Plan

Question 20
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Enables you to add and remove traceability links between requirements

Select one:
a. Impact Analysis
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
b. Comments
c. Description
d. Relationships

Question 21
Complete
Mark 1.00 out of 1.00

Flag question

Question text

The save options are disabled when more than one test or component is selected.

Select one:
True
False

Question 22
Complete
Mark 1.00 out of 1.00

Flag question

Question text

After finalizing the testing policy for your requirements, you can ______ a risk report that
details your testing strategy for the analysis requirement.

Select one:
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
a. Generate
b. Start
c. Plan
d. None of the choices

Question 23
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Enables you to view requirements in a flat non-hierarchical view.

Select one:
a. Traceability Matrix
b. Requirements Details
c. Coverage analysis
d. Requirements Grid

Question 24
Complete
Mark 1.00 out of 1.00

Flag question

Question text
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Sprinter software gives you the ability to test web or native applications using a cloud
mobile provider.

Select one:
True
False

Question 25
Complete
Mark 1.00 out of 1.00

Flag question

Question text

The ______ module allows you to view all test runs for your project in a grid.

Select one:
a. Test Set
b. Test Runs
c. Test Set Tree
d. None of the choices

Question 26
Complete
Mark 1.00 out of 1.00

Flag question
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Question text

Enables you to instruct ALM to automatically send a status alert email to the author when
the test set completes execution.

Select one:
a. Organize test runs
b. Develop the Test Sets tree
c. Run the tests
d. Set automation options

Question 27
Complete
Mark 1.00 out of 1.00

Flag question

Question text

This scanner checks your application for errors resulting from translating the application’s UI
into different languages.

Select one:
a. Broken links scanner
b. Localization scanner
c. Web standards scanner
d. Spell check scanner

Question 28
Complete
Mark 1.00 out of 1.00
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael

Flag question

Question text

Contains tests that you can assign to cycles in the Management module. This association
allows you to review the progress of tests, determine the number of resolved and
outstanding defects, and enhance your reporting ability.

Select one:
a. Test Set folder
b. Test Set
c. Test Sets Tree
d. None of the choices

Question 29
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Enables you to analyze the breakdown of child requirements according to test coverage
status.

Select one:
a. Requirements Details
b. Requirements Grid
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
c. Coverage analysis
d. Traceability Matrix

Question 30
Complete
Mark 1.00 out of 1.00

Flag question

Question text

This tab enables you to determine the business criticality, failure probability, and functional
complexity of a requirement by assigning it values directly or by assigning values to a set of
criteria.

Select one:
a. Assessment plan tab
b. Assessment Questions tab
c. Assessment tab
d. Assessment Results tab

Question 31
Complete
Mark 1.00 out of 1.00

Flag question

Question text

After you select an automatic method for conversion, you cannot customize the conversion.
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael

Select one:
True
False

Question 32
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Enables you to record additional details about the actual test execution results.

Select one:
a. Actual Field
b. Compact View Button
c. Status Column
d. None of the choices

Question 33
Complete
Mark 1.00 out of 1.00

Flag question

Question text

What is the third stage of the testing process?


CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael

Select one:
a. None of the choices
b. Test Planning
c. Test Control
d. Test Execution

Question 34
Complete
Mark 1.00 out of 1.00

Flag question

Question text

This allows you to design a scanner that detects the desired items in your application.

Select one:
a. web standards scanner
b. Broken links scanner
c. Custom scanner
d. spell check scanner

Question 35
Complete
Mark 1.00 out of 1.00

Flag question
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Question text

A group of tests designed to achieve specific testing goals.

Select one:
a. Test Sets Tree
b. Test Set
c. Test Set folder
d. None of the choices

Question 36
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Testing is shifting to adopt Agile and Continuous Integration methodologies.

Select one:
True
False

Question 37
Complete
Mark 1.00 out of 1.00

Flag question
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Question text

To create a _____, click the New button in the Plan area.

Select one:
a. Set Test
b. Application
c. Test
d. New Test

Question 38
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Clearly defined requirements help developers set a target for themselves and the testing
team to identify their testing priorities.

Select one:
a. Saves time and money
b. Helps prevent scope creep
c. Sets clear expectations between teams
d. Aids development and testing

Question 39
Complete
Mark 1.00 out of 1.00
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael

Flag question

Question text

There are three ways to open a test in Sprinter.

Select one:
True
False

Question 40
Complete
Mark 1.00 out of 1.00

Flag question

Question text

You convert requirements to tests to automatically create a one-to-one mapping between


____________ and ______.

Select one:
a. Requirements and activities
b. Requirements and tests
c. Activity and tests
d. Planning and activity

Question 41
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Before defining manual tests, you specify the detailed steps to execute each test.

Select one:
True
False

Question 42
Complete
Mark 1.00 out of 1.00

Flag question

Question text

After defining the subjects in the Test Plan tree, the next step is to add and define the
specific tests to be performed for each subject.

Select one:
True
False

Question 43
Complete
Mark 1.00 out of 1.00
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael

Flag question

Question text

Enables you to manage the execution of manual and automated tests and document their
results.

Select one:
a. Develop the Test Set Tree
b. Set automation options
c. Organize test runs
d. Run the tests

Question 44
Complete
Mark 1.00 out of 1.00

Flag question

Question text

The ________ module addresses the need for a stronger connection between business
process modeling, quality assurance management, and requirement definition.

Select one:
a. ALM Business Models
b. Linked Defects
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
c. Application LifeCycle Intelligence (ALI)
d. Mailing Requirements

Question 45
Complete
Mark 1.00 out of 1.00

Flag question

Question text

The Test Plan module enables you to ____ your application according to functionality.

Select one:
a. Divide
b. Plan
c. None of the choices
d. Multiply

Question 46
Complete
Mark 1.00 out of 1.00

Flag question

Question text

This area displays the assigned or calculated values of the risk and functional complexity of
an assessment requirement.
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
Select one:
a. Assessment tab
b. Assessment Results tab
c. Assessment Questions tab
d. Assessment plan tab

Question 47
Complete
Mark 1.00 out of 1.00

Flag question

Question text

A Requirement tree is a visual ______ of the relationship between requirements.

Select one:
a. Apply
b. Organize
c. Organization
d. Application

Question 48
Complete
Mark 1.00 out of 1.00

Flag question

Question text
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael
When you are in ________, Sprinter keeps a record of all your user actions, which you can
view as a list or in the Storyboard at the end of your run.

Select one:
a. Power mode
b. None of the choices
c. Automatic mode
d. Manual mode

Question 49
Complete
Mark 1.00 out of 1.00

Flag question

Question text

Which of the following is not part of the steps to run in Power mode using injection?

Select one:
a. Click a row of data and click the Injection Data button
b. Click the Data Injection sidebar
c. Click the Run the Active Test button
d. Click the Browse button

Question 50
Complete
Mark 1.00 out of 1.00
CS-6302-2013T(UGRD) Application
Lifecycle Mgt
Midterms Exam by Jacob Rafael

Flag question

Question text

If you know that a test in your test set might fail, but you want to make sure that
subsequent tests in the test set still execute, which of the following should you do?

Select one:
a. All of the choices
b. Disconnect the test from the flow.
c. Ensure that the execution condition for the arrow running out from the test is set to
Finished.
d. Ensure that the execution condition for the arrow running into the test is set to Finished.

You might also like