Professional Documents
Culture Documents
Fired heater tubes are difficult to clean, but a sequence of operations can remove
unwanted material from the tubes’ external surfaces and raise the heater’s efficiency
A
lmost every refinery and pet- ily accessed and cleaned by workers
rochemical company in the using scaffolding during a turna-
world suffers from lower round. Therefore it is relatively easy
efficiency than the design condi- to maintain the designed heat trans-
tion after long, continuous opera- fer from the outside surface of the
tion. There are many attempts to tube. But this excludes heat transfer
increase the turnaround cycle these inside the tube. Radiant tubes are
days, and the continuous operation exposed to relatively high temper-
period is getting longer, with 3-5 atures, creating coke in the tubes,
years being common. The mechani- which leads to low heat transfer
cal integrity of equipment is impor- efficiency.
tant for long periods of continuous The structure of convection tubes
operation, but it is equally impor- makes them difficult to access for
tant to maintain the efficiency of the cleaning, but it is important to clean
plant’s design. the convection tube effectively to
The fired heater is a typical item improve the heater’s efficiency.
of equipment that becomes less effi- Normally, heaters consuming liq-
cient as time goes by. One of the uid fuel should be fitted with soot
main reasons for a decrease in the blowers which should be operated
efficiency of a heater is that foreign periodically to prevent foreign sub-
substances build up between the stances from accumulating between
tubes, little by little over the long the tubes. Even so, if the equipment
term. Because the gap between fins operates for a long time (usually 3-5
is narrow, foreign substances are years), these substances will none-
likely to stick in a structural fashion. theless accumulate.
In particular, the burning of liq- In addition, environmental regu-
uid fuels is more likely to produce lations make it necessary to reduce
incomplete combustion than gas NOx, hence selective non-catalytic
fuels, resulting in much higher lev- reduction is often installed in fired
els of unburned hydrocarbons and
heaters. This equipment is installed
ash. Ash and unburned hydrocar- as a nozzle between the radiant sec-
bons deposited in the heater’s con- tion and the convection section, and
vection tube disturb effective heat the chemical sprayed through the
transfer between hot flue gas and nozzle flows directly to the convec-
the convection tube surface (see tion tube. Such chemicals make for-
Figure 1). Subsequently, this makes eign substances in the convection
the heater’s efficiency lower than tube become more firmly fixed. As
the design condition. a result, this makes tube cleaning
Fired heaters are among the most Figure 1 Convection tube status after even more difficult.
fuel consuming items of equip- three years’ operation Even if foreign substances accu-
ment in refineries and petrochemi- mulated during operation are una-
cal plants. If their efficiency is low, tubes absorb more heat (60~70% voidable, it is necessary to find a
higher fuel costs cannot be avoided. of total fired heat duty) than con- way to completely clean them from
In addition, other risk factors can vection tubes (30~40%) in heaters. the tube by opening up the equip-
arise, such as overheating of the Therefore, a radiant tube may be ment during a maintenance period.
tube by increasing the load of the more important than a convection More than 100 fired heaters are
burner to maintain output. tube in terms of heat absorption. in operation in our plant; the larg-
Generally speaking, radiant However, a radiant tube can be eas- est among them was selected to
6725
725 mm
row (minimum 396mm) to provide
approach space for cleaning work-
Manifold 2450
17440
396 mm increase capacity has been carried
132 mm out, but this meant that the fired
725 mm heater was becoming short of heat-
ing capacity. To overcome these
Radiant tube Manhole
396 mm
difficulties, we tried to apply two
types of cleaning equipment. The
first of these was a portable tube
Figure 2 Convection tube layout cleaning machine (see Figure 3).
This machine is specially designed
for cleaning convection tubes and
is commercially available. It moves
along a rail and cleans the tube by
orienting in four directions (for-
ward/backward/right/left). It can
be operated with a maximum pres-
sure of 1000 bar and is designed to
physically separate foreign sub-
stances from the tube by means of
a high pressure water spray. The
machine has several small noz-
zles and each nozzle has a particu-
lar spray angle to enable it to clean
Figure 3 Portable tube cleaning machine Figure 4 Simulation test large surfaces.
A simulation test was conducted
apply a new cleaning method. This Previously, only simple cleaning to identify problems and to check
heater consumes $60 million worth was carried out by spraying chem- the machine’s effectiveness at clean-
of fuel annually (heat duty of 179 icals onto the surface of the tubes, ing before application in the field.
MM kcal/h). It is a CCR heater for followed by cleaning with spray Scaffolding and temporary tubes
the aromatics plant in which four water. This was not very effective; were used to make a structure simi-
heaters share one convection section in particular, when the tube con- lar to a convection tube (see Figure 4).
(see Figure 2). sists of several lines the tube in The tube fin of the fired heater is
sufficiently thick to avoid the risk of
deformation or damage caused by
396 mm high pressure water.
The water jet machine cleaned
1000 mm
300 mm
725 mm the tubes well. High pressure water
spraying can reach between the
924 mm tubes, so the lower tube also had a
cleaning effect. However, it seems
to be difficult for the water jet to
725 mm
have more than three rows of clean-
396 mm ing effects past the tube. Observing
the surface of the cleaned tube, the
725 mm
scale was completely removed and
looked almost like a new tube.
132 mm
725 mm
In addition, the machine is only
396 mm about 300mm high, so it can move
in a narrow space (see Figure 5).
Thus, the operator can do the clean-
Figure 5 Cleaning plan for a portable tube cleaning machine ing by remote control without