You are on page 1of 5

Cleaning heater convection tubes

Fired heater tubes are difficult to clean, but a sequence of operations can remove
unwanted material from the tubes’ external surfaces and raise the heater’s efficiency

BYUNGMOON JEONG and SEOKRYONG JEON


SK Energy

A
lmost every refinery and pet- ily accessed and cleaned by workers
rochemical company in the using scaffolding during a turna-
world suffers from lower round. Therefore it is relatively easy
efficiency than the design condi- to maintain the designed heat trans-
tion after long, continuous opera- fer from the outside surface of the
tion. There are many attempts to tube. But this excludes heat transfer
increase the turnaround cycle these inside the tube. Radiant tubes are
days, and the continuous operation exposed to relatively high temper-
period is getting longer, with 3-5 atures, creating coke in the tubes,
years being common. The mechani- which leads to low heat transfer
cal integrity of equipment is impor- efficiency.
tant for long periods of continuous The structure of convection tubes
operation, but it is equally impor- makes them difficult to access for
tant to maintain the efficiency of the cleaning, but it is important to clean
plant’s design. the convection tube effectively to
The fired heater is a typical item improve the heater’s efficiency.
of equipment that becomes less effi- Normally, heaters consuming liq-
cient as time goes by. One of the uid fuel should be fitted with soot
main reasons for a decrease in the blowers which should be operated
efficiency of a heater is that foreign periodically to prevent foreign sub-
substances build up between the stances from accumulating between
tubes, little by little over the long the tubes. Even so, if the equipment
term. Because the gap between fins operates for a long time (usually 3-5
is narrow, foreign substances are years), these substances will none-
likely to stick in a structural fashion. theless accumulate.
In particular, the burning of liq- In addition, environmental regu-
uid fuels is more likely to produce lations make it necessary to reduce
incomplete combustion than gas NOx, hence selective non-catalytic
fuels, resulting in much higher lev- reduction is often installed in fired
els of unburned hydrocarbons and
heaters. This equipment is installed
ash. Ash and unburned hydrocar- as a nozzle between the radiant sec-
bons deposited in the heater’s con- tion and the convection section, and
vection tube disturb effective heat the chemical sprayed through the
transfer between hot flue gas and nozzle flows directly to the convec-
the convection tube surface (see tion tube. Such chemicals make for-
Figure 1). Subsequently, this makes eign substances in the convection
the heater’s efficiency lower than tube become more firmly fixed. As
the design condition. a result, this makes tube cleaning
Fired heaters are among the most Figure 1 Convection tube status after even more difficult.
fuel consuming items of equip- three years’ operation Even if foreign substances accu-
ment in refineries and petrochemi- mulated during operation are una-
cal plants. If their efficiency is low, tubes absorb more heat (60~70% voidable, it is necessary to find a
higher fuel costs cannot be avoided. of total fired heat duty) than con- way to completely clean them from
In addition, other risk factors can vection tubes (30~40%) in heaters. the tube by opening up the equip-
arise, such as overheating of the Therefore, a radiant tube may be ment during a maintenance period.
tube by increasing the load of the more important than a convection More than 100 fired heaters are
burner to maintain output. tube in terms of heat absorption. in operation in our plant; the larg-
Generally speaking, radiant However, a radiant tube can be eas- est among them was selected to

www.digitalrefining.com/article/1002414 PTQ Q1 2020 67


the middle was almost impossible
23174 to clean.
Convection
396 mm In addition, the space between
tube convection tube bundles is too nar-

6725
725 mm
row (minimum 396mm) to provide
approach space for cleaning work-
Manifold 2450

924 mm ers, and the length of a convection


tube (23m, 75ft) makes it difficult for
P–H2504R 725 mm
workers to access them.
P–H2508R P–H2501R Following long-term operation,
P–H2502R 396 mm more than 50 years, a project to

17440
396 mm increase capacity has been carried
132 mm out, but this meant that the fired
725 mm heater was becoming short of heat-
ing capacity. To overcome these
Radiant tube Manhole
396 mm
difficulties, we tried to apply two
types of cleaning equipment. The
first of these was a portable tube
Figure 2 Convection tube layout cleaning machine (see Figure 3).
This machine is specially designed
for cleaning convection tubes and
is commercially available. It moves
along a rail and cleans the tube by
orienting in four directions (for-
ward/backward/right/left). It can
be operated with a maximum pres-
sure of 1000 bar and is designed to
physically separate foreign sub-
stances from the tube by means of
a high pressure water spray. The
machine has several small noz-
zles and each nozzle has a particu-
lar spray angle to enable it to clean
Figure 3 Portable tube cleaning machine Figure 4 Simulation test large surfaces.
A simulation test was conducted
apply a new cleaning method. This Previously, only simple cleaning to identify problems and to check
heater consumes $60 million worth was carried out by spraying chem- the machine’s effectiveness at clean-
of fuel annually (heat duty of 179 icals onto the surface of the tubes, ing before application in the field.
MM kcal/h). It is a CCR heater for followed by cleaning with spray Scaffolding and temporary tubes
the aromatics plant in which four water. This was not very effective; were used to make a structure simi-
heaters share one convection section in particular, when the tube con- lar to a convection tube (see Figure 4).
(see Figure 2). sists of several lines the tube in The tube fin of the fired heater is
sufficiently thick to avoid the risk of
deformation or damage caused by
396 mm high pressure water.
The water jet machine cleaned
1000 mm

300 mm
725 mm the tubes well. High pressure water
spraying can reach between the
924 mm tubes, so the lower tube also had a
cleaning effect. However, it seems
to be difficult for the water jet to
725 mm
have more than three rows of clean-
396 mm ing effects past the tube. Observing
the surface of the cleaned tube, the
725 mm
scale was completely removed and
looked almost like a new tube.
132 mm
725 mm
In addition, the machine is only
396 mm about 300mm high, so it can move
in a narrow space (see Figure 5).
Thus, the operator can do the clean-
Figure 5 Cleaning plan for a portable tube cleaning machine ing by remote control without

68 PTQ Q1 2020 www.digitalrefining.com/article/1002414


having to enter the narrow space
between tube bundles.
Because the convection tubes to
be cleaned were over 23m long,
this made it impossible to install
all of the rails at once, so some sec-
tions were cleaned first, then the
rails were moved to clean the rest
because of the limited length of
the rails.
The second machine selected is a 924 mm

hand jet cleaner, which can spray


water jets at 2700 bar (see Figure
6). This machine can be operated
by cleaning workers and cleans
the surface of a tube by inserting it
between tubes (see Figure 7). Since
the worker must perform the work
by hand with very high pressure
water, individual skill is called for.
This machine can compensate for
the poor cleaning effect of the port-
able tube cleaner for the tube in the Figure 6 Hand jet cleaner
middle of the bundle.
The tip of the hand jet cleaner ation, the portable cleaner was
is designed to rotate while water used to remove foreign substances
is injected at high pressure, so the from the tube surfaces. Inspection
tubes can be cleaned effectively. The of the tubes after portable cleaning
total nozzle length should be long revealed that substances such as ash
enough to reach the centre of a tube and sulphur condensate were com-
bundle to enable all of the tubes to pletely removed from the surface
be cleaned. (see Figure 9).
The cleaning sequence was If substances caused by com-
designed to maximise the cleaning bustion are stuck between the fins
effect and to perform the operation of tubes, simply cleaning with
efficiently. The key to this cleaning water is not effective. By inject-
strategy is to clean the inside of the Figure 7 Cleaning skim ing water with a little chemical,
bundle after removing large debris the substances can be dissolved
at the outset. When using portable addition, the condition of the water to increase the cleaning effect.
and hand jet cleaners, low concen- should be checked to determine Mechanical cleaning and chemical
trations of chemical should be used whether cleaning is complete. cleaning can be carried out at the
first, followed by higher concentra- Initial inspection was performed same time. The portable machine
tions. The cleaning method and pro- immediately after opening the was applied sequentially in the
cedure are summarised in Table 1. heater; a large amount of foreign spaces between the tube bundles
First, a tent was installed to pro- substances and sulphur had accu- at the top of the convection section
tect the internal refractory before mulated. In the first cleaning oper- to clean up and down the surfaces
cleaning began (see Figure 8). Tents
should be installed between the first Cleaning processes and order of operations
tubes next to the refractory. Since
they may be damaged by high pres-
Operation Cleaning process Remark
sure water, they are installed in two 1 Preparatory work Refractory protection and water gathering
layers to prevent water from pen-
etrating. To collect then treat the 2 Portable tube cleaning (chemical)
wastewater used for cleaning, a sep-
3 Hand cleaning (chemical)
arate tank should be installed and
operated next to the heater. 4 Chemical pouring
The operator should always be
by the water tank beneath the con- 5 Water cleaning (water only)
vection tube. As the cleaning pro- 6 Inspection (endoscopy)
gresses, always check for leaks
caused by damage to the tent. In Table 1

www.digitalrefining.com/article/1002414 PTQ Q1 2020 71


cleaning, so a low concentration of
chemical (1-2%) is required.
Next, in order to maximise the
chemical cleaning effect, apply a
high concentration of chemical com-
ponent to the whole tube. After the
reaction is complete, final cleaning
is performed with pure water.
Chemical used for cleaning the
tube was checked for any problems
such as corrosion by putting metal
of the same material as the tube in
the chemical before use. Detailed
inspection should confirm that there
is no abnormality. During the test,
checks were made to ensure that
foreign substances in the tube were
Scaffold
dissolved by the chemical. A total
Peep door
of three chemicals were tested. The
chemicals with the highest decom-
position effect and no corrosion
problems were selected and used.
This completes the cleaning pro-
cess. Next, check inside the tube
bundle using endoscopy to see how
effective the cleaning is. The result
of the test was good, with dust and
Figure 8 Preparation for cleaning water treatment sulphur at the middle of tube bun-
dle totally removed (see Figure 10).
After visual and endoscopic
inspection, operating data were
collected and analysed over three
months to see how much the effi-
ciency of the heater was improved
by cleaning. The change in efficiency

of the heater was calculated and
compared with the previous turn-
around. Total heater efficiency had
increased by 0.84%, equivalent to

Figure 9 Tube surfaces after portable cleaning an annual saving of $500 000 in fuel
costs. Compared to the cost of clean-
ing (about $100 000) the saving is
considerable. Although the economic
gain is expected to decrease from the
year after cleaning, the cost of fuel
saved is still much higher than the
cleaning cost, considering that the
cleaning effect is not permanent.
The exercise demonstrated that
cleaning a fuel oil consuming fired
heater using portable and hand jet
equipment results in significant fuel
Figure 10 Inspection result (endoscopy) savings. We conclude that this com-
bination of cleaning operations is
of the tubes. Inspecting the waste- After portable cleaning was per- effective and increases heater effi-
water tank showed that, as clean- formed, the surface area of the tube ciency. Heaters using gas as fuel
ing progressed, dirty water flowed had increased, then hand jet clean- are expected to accumulate less
in at first followed by clear water, ing was applied. Hand jetting also foreign material in the tubes so the
so cleaning should continue until used a chemical to clean the tube improvement in efficiency resulting
clear water emerges, signalling that surface. Using the portable cleaner from cleaning is lower than for heat-
cleaning is complete. and hand jet amounts to initial ers using oil.

72 PTQ Q1 2020 www.digitalrefining.com/article/1002414


Heaters burning fuel gas need the water used is gathered sep- External cleaning equipment of
to be checked to establish exactly arately by the protecting tent. In heater tubes is not a long-estab-
how their efficiency changes and conclusion, cleaning with a port- lished process like heat exchanger
whether they are economical. If able cleaner has no effect on the cleaning. Through this test, the per-
there is plenty of time to work dur- working period. formance of equipment for cleaning
ing a turnaround, various cleaning the outer surfaces of heater tubes
sequences can be applied to estab- Cleaning a fuel has been verified.
lish optimal cleaning procedures.
It is recommended that cleaning is oil consuming Byungmoon Jeong is a Stationary Equipment
performed during every turnaround Engineer with SK Energy in South Korea. He has
since foreign matter will accumu- fired heater using more than 14 years of petrochemical industry
late continuously after cleaning experience, specialising in pressure vessel and
and the cleaning effect is expected portable and hand flange leak troubleshooting and maintenance.
He graduated with a BS degree in mechanical
to decrease gradually. It is also rec-
ommended that selection of items
jet equipment engineering from Pusan University, South
Korea. Email: bugbear@sk.com
for cleaning is important; a heater results in significant
with high fuel consumption or heat- Seokryong Jeon is Leader of the stationary
ers considered as bottlenecks in the fuel savings equipment engineering team with SK Energy.
He has more than 24 years of experience in
process could be more economical
the reliability and project management of
to be cleaned. In refineries and petrochemi- refineries and petrochemical plants. He holds
All of the cleaning required 13 cal plants, a heater is a large and an MS degree in metallurgical engineering from
days, for eight hours each day, from important item of equipment that Hanyang University, South Korea.
start to finish. In general, a turna- requires a large investment. It is Email: srjeon@sk.com
round schedule allows for 30 days very difficult to increase its capac-
for the operation, so the work can ity through a revamp after the plant
be completed in a relaxed manner. is constructed. Lower efficiency
Installation of the tent took around heaters not only consume a lot of
LINKS
three to four days, but the clean- fuel, but also become an obstacle to
More articles from the following
ing process did not take long. Also, increasing the capacity of the plant.
categories:
cleaning in the convection section Hence maintaining the plant’s Heat Transfer
does not interfere with working in capacity through efficient cleaning Mass Transfer
the lower radiant section because will be a big help.

www.digitalrefining.com/article/1002414 PTQ Q1 2020 73

You might also like