Activities Task Predecessor Duration

A Site Clearing - 3 day(s)


B Excavation for foundation A 3 day(s)
C Installation of Rebars B 5 day(s)
D Pouring of Concrete C 1 day(s)
E Backfill D 4 day(s)
F Placing of Scaffolding E,V 3 day(s)
G Installation of Rebars F 5 day(s)
H Installation of Formworks G 4 day(s)
I Pouring of Concrete H 1 day(s)
J Removal of Formworks I 1 day(s)
K Installation of Rebars G 5 day(s)
L Installation of Formworks K 3 day(s)
M Pouring of Concrete H,L 1 day(s)
N Removal of Formworks M,I 1 day(s)
O Installation of Rebars N 3 day(s)
P Installation of Formworks O 3 day(s)
Q Pouring of Concrete P 1 day(s)
R Removal of Formworks Q 1 day(s)
S Excavation for foundation A 3 day(s)
T Installation of Rebars B 3 day(s)
U Pouring of Concrete C 1 day(s)
V Backfill D 1 day(s)
W Placing of Scaffolding R 3 day(s)
X Installation of Rebars W 5 day(s)
Y Installation of Formworks X 4 day(s)
Z Pouring of Concrete Y 1 day(s)
A' Removal of Formworks Z 1 day(s)
B' Placing of Scaffolding R 3 day(s)
C' Installation of Rebars A' 5 day(s)
D' Installation of Formworks C' 3 day(s)
E' Pouring of Concrete D',H' 1 day(s)
F' Removal of Formworks E',J" 1 day(s)
G' Placing of Scaffolding R 3 day(s)
H' Installation of Rebars C' 3 day(s)
I' Installation of Formworks H' 3 day(s)
J' Pouring of Concrete D',H' 1 day(s)
K' Removal of Formworks & Scaffolds E',J' 1 day(s)
II CHB Laying per level K', 11 day(s)
L' Placing of Scaffolding J',K' 3 day(s)
M' Installation of Rebars L' 5 day(s)
N' Installation of Formworks M' 4 day(s)
O' Pouring of Concrete N' 1 day(s)
P' Removal of Formworks O' 1 day(s)
Q' Placing of Scaffolding J'K' 3 day(s)
R' Installation of Rebars P' 5 day(s)
S' Installation of Formworks R' 3 day(s)
T' Pouring of Concrete S',X' 1 day(s)
U' Removal of Formworks T',Y' 1 day(s)
V' Placing of Scaffolding J',K' 3 day(s)
W' Installation of Rebars R' 3 day(s)
X' Installation of Formworks W' 3 day(s)
Y' Pouring of Concrete S',X' 1 day(s)
Z' Removal of Formworks & Scaffolds T',Y' 1 day(s)
II CHB Laying per level Z' 11 day(s)
A" Placing of Scaffolding Z' 3 day(s)
B" Installation of Rebars A" 5 day(s)
C" Installation of Formworks B" 4 day(s)
D" Pouring of Concrete C" 1 day(s)
E" Removal of Formworks D" 1 day(s)
F" Placing of Scaffolding Z' 3 day(s)
G" Installation of Rebars E" 5 day(s)
H" Installation of Formworks G" 3 day(s)
I" Pouring of Concrete G",L" 1 day(s)
J" Removal of Formworks I",N" 1 day(s)
K" Placing of Scaffolding Z' 3 day(s)
L" Installation of Rebars G" 3 day(s)
M" Installation of Formworks L" 3 day(s)
N" Pouring of Concrete G",L" 1 day(s)
O" Removal of Formworks & Scaffolds I",N" 1 day(s)
II CHB Laying per level O" 11 day(s)
2 angle bars 40x40x6mm top chord
P" O" 5 day(s)
rafter
Q" 2 angle bars 25x25x6mm web member P" 5 day(s)
2 angle bars 25x25x6mm vertical
R" Q" 5 day(s)
member
S" 6mm thik gusset plate R" 3 day(s)
T" 75x50x1.4mm channel pulins S" 5 day(s)
U" Installation of Roofing Materials T" 6 day(s)
II CHB Laying per level U" 11 day(s)
V" Set Electrical Boxes U" 3 day(s)
W" Install Electrical Service Panel V" 4 day(s)
X" Electrical Walkthrough W" 3 day(s)
Y" Electrical Roughwire X" 2 day(s)
Z" Switch and Plugs Y" 2 day(s)
AA Fixtures Z" 2 day(s)
BB Plumbing Sub-slab AA 3 day(s)
CC Plumbing Layout BB 3 day(s)
DD Plumbing Rough-in CC 3 day(s)
EE PVC Pipe Fittings DD 2 day(s)
FF PPR Pipe Fittings EE 2 day(s)
GG Toilet and Bath Fittings FF 2 day(s)
HH Kitchen Fittings GG 2 day(s)
JJ Plastering per level GG 9 day(s)
KK Ceiling finishes JJ 4 day(s)
LL Tile Works Per Level II 15 day(s)
MM Doors Per Level LL 5 day(s)
NN Windows Per Level LL 7 day(s)
OO Painting Works JJ 14 day(s)
PP Cleaning OO 2 day(s)