EXCAVATION OF FOUNDATION
depth = 2m
volume = area x depth 112.00 m3
production rate = 120.00 m3/day
duration= quantity/production rate 2.09 days
3.00 days
POURING OF CONCRETE
Volume = Area of foundation x depth x no.of footing
F-1 6.00 m2
F-2 2.40 m2
depth for all foundation= 2.00 m2
Total Volume= 16.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day
GROUND FLOOR
INSTALLATION OF FORMWORKS FOR COLUMNS
perimeter= 1.80 m
height= 3.00 m
total surface area of columns= 54.00 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 5.00 days
FINISHING WORKS
area to be layouted by tiles= 410.51 m2
production rate= 4.75 sq.m/man-day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 15.00 days