You are on page 1of 10

COMPUTATION OF DURATION

EXCAVATION OF FOUNDATION
depth = 2m
volume = area x depth 112.00 m3
production rate = 120.00 m3/day
duration= quantity/production rate 2.09 days
3.00 days

LAYOUT OF REINFORCING BARS

For founddation F-1


length= 6.00 m
weight= 1.58 kgs
no of bars= 114.00 pcs
total weight of bars for F1= 1080.72 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 3.46 days
For foundation F-2
length= 6.00 m
weight= 1.58 m
no of bars= 114.00 pcs.
total weight of steel for F-2= 1080.72 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 1.12 days
TOTAL DURATIION FOR FOUNDATION: 5.00 days

POURING OF CONCRETE
Volume = Area of foundation x depth x no.of footing
F-1 6.00 m2
F-2 2.40 m2
depth for all foundation= 2.00 m2
Total Volume= 16.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day
GROUND FLOOR
INSTALLATION OF FORMWORKS FOR COLUMNS
perimeter= 1.80 m
height= 3.00 m
total surface area of columns= 54.00 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 5.00 days

INSTALLATION OF REBAR FOR COLUMNS


Number of main reinforcement for columns= 10.00 pcs
length for main reinforcement= 3.00 m
total length for each column= 30.00 m
total length for 10 columns= 300.00 m
mass for main reinforcement= 741.00 kgs
Number of ties for each column= 34.00 pcs
length of each stirrup= 1.08 m
total length for each column= 36.72 m
total length for 10 columns= 367.20 m
mass for stirrups= 227.66 kgs
TOTAL MASS OF REBAR FOR COLUMNS= 968.66 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days

POURING OF CONCRETE FOR COLUMNS


Area= 0.16 m2
height= 3.00 m
volume for 1 column= 0.48 m3
total volume for 10 columns= 4.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day

INSTALLATION OF REBAR FOR TIE BEAMS


depth= 0.40 m
width= 0.30 m
length of main reinforcement= 6.00 m
number of main reinf. per beam= 83.00 pcs
total length of reinforcement of beam= 498.00 m
total mass for reinforcement= 786.84 kgs
length of each stirrup= 1.12 m
number of stirrups= 192.00 pcs
total length of stirrups= 215.04 m
total mass for stirrups= 133.32 kgs
TOTAL MASS OF REBAR FOR TIE BEAMS= 920.16 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days
INSTALLATION OF FORMWORKS FOR TIE BEAMS
perimeter of formworks= 2.30 m
total area for formworks= 28.67 m2
production rate= 1.50 m2/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 days

INSTALLATION OF SLAB ON GRADE


number of bars (longitudinal)(6m length) 50.00 pcs
total length for longitudinal bars= 300.00 m
number of bars (transverse)(6m length) 50.00 pcs
total length for transverse bars= 300.00 m
total length= 600.00 m
total mass= 372.00 kgs
production rate= 185.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 3.00 days

FORMWORKS FOR SLABS


perimeter= 41.60 m
thickness of slab= 0.12 m
area for formworks= 28.67 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 day

POURING OF CONCRETE FOR BEAM AND SLAB


area of slab= 59.47 m2
thickness of slab= 0.12 m2
volume for slab= 6.96 m3
area for beam= 0.12 m2
total length of beam= 56.70 m
volume for tie beam= 6.80 m3
total volume of concrete= 13.76 m3
production rate= 5.20 m3/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 2.00 day
SECOND FLOOR
INSTALLATION OF FORMWORKS FOR COLUMNS
perimeter= 1.80 m
height= 3.00 m
total surface area of columns= 54.00 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 5.00 days

INSTALLATION OF REBAR FOR COLUMNS


Number of main reinforcement for columns= 10.00 pcs
length for main reinforcement= 3.00 m
total length for each column= 30.00 m
total length for 10 columns= 300.00 m
mass for main reinforcement= 741.00 kgs
Number of ties for each column= 34.00 pcs
length of each stirrup= 1.08 m
total length for each column= 36.72 m
total length for 10 columns= 367.20 m
mass for stirrups= 227.66 kgs
TOTAL MASS OF REBAR FOR COLUMNS= 968.66 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days

POURING OF CONCRETE FOR COLUMNS


Area= 0.16 m2
height= 3.00 m
volume for 1 column= 0.48 m3
total volume for 10 columns= 4.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day

INSTALLATION OF REBAR FOR BEAMS


depth= 0.40 m
width= 0.30 m
length of main reinforcement= 6.00 m
number of main reinf. per beam= 83.00 pcs
total length of reinforcement of beam= 498.00 m
total mass for reinforcement= 786.84 kgs
length of each stirrup= 1.12 m
number of stirrups= 192.00 pcs
total length of stirrups= 215.04 m
total mass for stirrups= 133.32 kgs
TOTAL MASS OF REBAR FOR TIE BEAMS= 920.16 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days
INSTALLATION OF FORMWORKS FOR TIE BEAMS
perimeter of formworks= 2.30 m
total area for formworks= 28.67 m2
production rate= 1.50 m2/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 days

INSTALLATION OF SLAB ON GRADE


number of bars (longitudinal)(6m length) 50.00 pcs
total length for longitudinal bars= 300.00 m
number of bars (transverse)(6m length) 50.00 pcs
total length for transverse bars= 300.00 m
total length= 600.00 m
total mass= 372.00 kgs
production rate= 185.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 3.00 days

FORMWORKS FOR SLABS


perimeter= 41.60 m
thickness of slab= 0.12 m
area for formworks= 28.67 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 day

POURING OF CONCRETE FOR BEAM AND SLAB


area of slab= 59.47 m2
thickness of slab= 0.12 m2
volume for slab= 6.96 m3
area for beam= 0.12 m2
total length of beam= 56.70 m
volume for tie beam= 6.80 m3
total volume of concrete= 13.76 m3
production rate= 5.20 m3/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 2.00 day
THIRD FLOOR
INSTALLATION OF FORMWORKS FOR COLUMNS
perimeter= 1.80 m
height= 3.00 m
total surface area of columns= 54.00 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 5.00 days

INSTALLATION OF REBAR FOR COLUMNS


Number of main reinforcement for columns= 10.00 pcs
length for main reinforcement= 3.00 m
total length for each column= 30.00 m
total length for 10 columns= 300.00 m
mass for main reinforcement= 741.00 kgs
Number of ties for each column= 34.00 pcs
length of each stirrup= 1.08 m
total length for each column= 36.72 m
total length for 10 columns= 367.20 m
mass for stirrups= 227.66 kgs
TOTAL MASS OF REBAR FOR COLUMNS= 968.66 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days

POURING OF CONCRETE FOR COLUMNS


Area= 0.16 m2
height= 3.00 m
volume for 1 column= 0.48 m3
total volume for 10 columns= 4.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day

INSTALLATION OF REBAR FOR BEAMS


depth= 0.40 m
width= 0.30 m
length of main reinforcement= 6.00 m
number of main reinf. per beam= 83.00 pcs
total length of reinforcement of beam= 498.00 m
total mass for reinforcement= 786.84 kgs
length of each stirrup= 1.12 m
number of stirrups= 192.00 pcs
total length of stirrups= 215.04 m
total mass for stirrups= 133.32 kgs
TOTAL MASS OF REBAR FOR TIE BEAMS= 920.16 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days
INSTALLATION OF FORMWORKS FOR TIE BEAMS
perimeter of formworks= 2.30 m
total area for formworks= 28.67 m2
production rate= 1.50 m2/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 days

INSTALLATION OF SLAB ON GRADE


number of bars (longitudinal)(6m length) 50.00 pcs
total length for longitudinal bars= 300.00 m
number of bars (transverse)(6m length) 50.00 pcs
total length for transverse bars= 300.00 m
total length= 600.00 m
total mass= 372.00 kgs
production rate= 185.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 3.00 days

FORMWORKS FOR SLABS


perimeter= 41.60 m
thickness of slab= 0.12 m
area for formworks= 28.67 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 day

POURING OF CONCRETE FOR BEAM AND SLAB


area of slab= 59.47 m2
thickness of slab= 0.12 m2
volume for slab= 6.96 m3
area for beam= 0.12 m2
total length of beam= 56.70 m
volume for tie beam= 6.80 m3
total volume of concrete= 13.76 m3
production rate= 5.20 m3/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 2.00 day
FOURTH FLOOR
INSTALLATION OF FORMWORKS FOR COLUMNS
perimeter= 1.80 m
height= 3.00 m
total surface area of columns= 54.00 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 5.00 days

INSTALLATION OF REBAR FOR COLUMNS


Number of main reinforcement for columns= 10.00 pcs
length for main reinforcement= 3.00 m
total length for each column= 30.00 m
total length for 10 columns= 300.00 m
mass for main reinforcement= 741.00 kgs
Number of ties for each column= 34.00 pcs
length of each stirrup= 1.08 m
total length for each column= 36.72 m
total length for 10 columns= 367.20 m
mass for stirrups= 227.66 kgs
TOTAL MASS OF REBAR FOR COLUMNS= 968.66 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days

POURING OF CONCRETE FOR COLUMNS


Area= 0.16 m2
height= 3.00 m
volume for 1 column= 0.48 m3
total volume for 10 columns= 4.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day

INSTALLATION OF REBAR FOR BEAMS


depth= 0.40 m
width= 0.30 m
length of main reinforcement= 6.00 m
number of main reinf. per beam= 83.00 pcs
total length of reinforcement of beam= 498.00 m
total mass for reinforcement= 786.84 kgs
length of each stirrup= 1.12 m
number of stirrups= 192.00 pcs
total length of stirrups= 215.04 m
total mass for stirrups= 133.32 kgs
TOTAL MASS OF REBAR FOR TIE BEAMS= 920.16 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days
INSTALLATION OF FORMWORKS FOR TIE BEAMS
perimeter of formworks= 2.30 m
total area for formworks= 28.67 m2
production rate= 1.50 m2/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 days

INSTALLATION OF SLAB ON GRADE


number of bars (longitudinal)(6m length) 50.00 pcs
total length for longitudinal bars= 300.00 m
number of bars (transverse)(6m length) 50.00 pcs
total length for transverse bars= 300.00 m
total length= 600.00 m
total mass= 372.00 kgs
production rate= 185.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 3.00 days

FORMWORKS FOR SLABS


perimeter= 41.60 m
thickness of slab= 0.12 m
area for formworks= 28.67 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 day

POURING OF CONCRETE FOR BEAM AND SLAB


area of slab= 59.47 m2
thickness of slab= 0.12 m2
volume for slab= 6.96 m3
area for beam= 0.12 m2
total length of beam= 56.70 m
volume for tie beam= 6.80 m3
total volume of concrete= 13.76 m3
production rate= 5.20 m3/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 2.00 day
MASONRY WORKS WITH PLASTERING
height= 3.00 m
area to be installed of CHB= 604.38 m2
no of CHB/m2= 13.00 pcs
total number of CHB to be installed= 7554.75 pcs
production rate= 250.00 pcs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
Total duration= 31.00 days

FINISHING WORKS
area to be layouted by tiles= 410.51 m2
production rate= 4.75 sq.m/man-day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 15.00 days

You might also like