SPECIFICATIONS
Number of structure: 30
Volume to be excavated: 1.90 x 30 units = 57 cubic meter.
MATERIALS:
PARTICULARS QUANTITY UNIT UNIT COST AMOUNT
LABOR:
PARTICULARS NO. OF MEN NO. OF WORKING DAYS RATE AMOUNT
Skilled worker 3 30 580
Unskilled worker 9 30 480
II. GRAVEL BEDDING
Number of structure: 30
Width: 1.0 meter
Depth: 0.10 meter
Area: 1.0 x 1.0 = 1.0 sq.m.
Volume: 1.0 x 0.1 = 0.10 cu.m.
Total Volume: 0.10 x 30 units = 3 cu.m. + 10 wastage = 3.3 cu.m
MATERIALS:
PARTICULARS QUANTITY UNIT UNIT COST AMOUNT
Washed G-1, 3.3 cu.m 1800.00 5940.00
Gravel
LABOR:
PARTICULARS NO. OF MEN NO. OF WORKING DAYS RATE AMOUNT
Skilled worker 3 30 580
Unskilled worker 9 30 480
III. FORMWORKS
Number of structure: 30
Number of Plywood: 2 x 30 = 60 pcs
MATERIALS:
PARTICULARS QUANTITY UNIT UNIT COST AMOUNT
1/2’’x4’x8’ Ord. 30 pcs 674.00 20, 220.00
Plywood
2’’x2’’x10’ Coco Lumber 150 pcs 85.00 12,750.00
2-1/2 CWN 30 kgs 51.00 1,530.00
1-1/2 CWN 15 kgs 54.00 810.00
TOTAL AMOUNT 35, 310.00
LABOR:
PARTICULARS NO. OF MEN NO. OF WORKING DAYS RATE AMOUNT
Skilled worker 3 30 580
Unskilled worker 9 30 480
MATERIALS:
PARTICULARS QUANTITY UNIT UNIT COST AMOUNT
16 mm dia Deformed Steel 150 length 355 53, 250.00
Bars
10 mm dia Deformed Steel 90 length 175 15, 750.00
Bars
Ga 16 GI Tie Wire 36 kg 71.37 2569.32
Hacksaw Blade 6 pcs 60 360.00
TOTAL AMOUNT 71,929.32
LABOR:
PARTICULARS NO. OF MEN NO. OF WORKING DAYS RATE AMOUNT
Skilled worker 3 30 580
Unskilled worker 9 30 480
V. STRUCTURAL CONCRETE
MATERIALS:
PARTICULARS QUANTITY UNIT UNIT COST AMOUNT
Cement, Portland 181 bags 261.00 47, 241.00
Sand, Washed 13 cu.m. 1,365.00 17, 745.00
Gravel, Washed 3/4 19 cu.m 1,310.00 24, 890.00
TOTAL AMOUNT 89, 876.00
LABOR:
PARTICULARS NO. OF MEN NO. OF WORKING DAYS RATE AMOUNT
Skilled worker 3 30 580
Unskilled worker 9 30 480
VI. BACKFILLING
MATERIALS:
PARTICULARS QUANTITY UNIT UNIT COST AMOUNT
LABOR:
PARTICULARS NO. OF MEN NO. OF WORKING DAYS RATE AMOUNT
Skilled worker 3 30 580
Unskilled worker 9 30 480
MATERIALS:
PARTICULARS POLE NO. QUANTITY UNIT UNIT COST AMOUNT
LED chip: 5050 LED with High
Brightness, low light decay.
Luminous
effieciency:>150Lm/w LED
power: 120W DC24V,
CCT: 5500-6000k white, 1
CRI>85,Light sets
angle:70x 140 degrees
Lighting flux: 15600 lumens
Protection: IP66
Lifetime: 100000hours 30
Professionals 5050 LED Street
Light Lens for wider and
brighter lighting.
1. Pole Height:10m(existed
pole)
2. Top diameter: 80mm
3. Bottom Diameter: 7" 1 sets
4. Thickness: 3.5mm 5. Flange:
350x350x18mm
6. Color: White Body
7. Materials: Hot-dip
galvanized steel and power
paint finish
8. Anchor
bolts:260*260*1000mm,
1pcs(existed)
LABOR:
PARTICULARS NO. OF MEN NO. OF WORKING DAYS RATE AMOUNT
Skilled worker 3 45 580
Unskilled worker 9 45 480
MATERIALS:
PARTICULARS QUANTITY UNIT UNIT COST AMOUNT
1-1/2” dia Pipe S-40 2 length 2, 662.38 5, 324.76
1-1/2” x 16 Flat Bar 2 length 3, 200.00 6, 400.00
8’ x 8’ Plain GI Sheet 1 sheet 1,736.00 1, 736.00
Metal Primer Paint 1 gallon 509.00 509.00
Paint Brush 2 pcs 55.00 110.00
Welding Rod 5 kgs 78.00 390.00
Portland Cement 2 bags 261.00 522.00
Sand, Washed 1 cu.m 1,365.00 1, 365.00
8’ x 8’ Tarpaulin with 2 pcs 1,000 2, 000.00
Print
TOTAL AMOUNT 18, 356.00
LABOR:
PARTICULARS NO. OF MEN NO. OF WORKING DAYS RATE AMOUNT
Skilled worker 3 30 580
Unskilled worker 9 30 480
IX. COMMUNITY BILLBOARD
MATERIALS:
PARTICULARS QUANTITY UNIT UNIT COST AMOUNT
2 X 3 X 12’ Coco Lumber 2 pc 168.00 336.00
2 X 2 X 12’ Coco Lumber 3 pc 112.00 336.00
1 X 3 X 12’ Coco Lumber 2 pc 134.00 268.00
Assorted Nails 1 kgs 85.00 85.00
4’ x 8’ Tarpaulin with 1 pc 320.00 320.00
Print
TOTAL AMOUNT 1, 345.00
LABOR:
PARTICULARS NO. OF MEN NO. OF WORKING DAYS RATE AMOUNT
Skilled worker 3 30 580
Unskilled worker 9 30 480