ADDITIONAL CALENDAR DAYS COMPUTATION

( Intended for proposed VARIATION ORDER No. 1 )

Project:
Location:
Limits:

Output per day as to DUPA

Output / hour
Item No. Description Additional Qty Unit Additional Days
Qty Unit
100(1) Clearing & Grubbing (with Stripping) 1.71 ha. 0.05 ha./hour 4.275 days
104(1)a Embankment from Roadway Excavation 3,440.00 cu.m. 50.00 cu.m./hour 8.60 days
105(1)a Subgrade Preparation (Common Material) 7,247.31 sq.m. 300.00 sq.m./hour 3.02 days
200(1) Aggregate Subbase Course 1,262.00 cu.m. 50.00 cu.m./hour 3.16 days
311(1)e2 PCC Pavement (Unreinforced), 0.28m thick (7 days) 6,324.00 sq.m. 57.50 sq.m./hour 13.75 days
500(1)b4 Pipe Culverts (Class IV,1070 mm dia.) 19.00 m. 1.00 m./hour 2.38 days
600(4) Curb and Gutter (Cast in Place) 1,435.80 l.m. 10.30 l.m./hour 17.42 days
601(1) Sidewalk (100mm thk.) 2,462.39 sq.m. 20.00 sq.m./hour 15.39 days
612(1) Reflectorized Thermoplastic Pavement Markings (White) 192.53 sq.m. 25.00 sq.m./hour 0.96 days
622(1)a Coconet (CN400) 2,404.00 sq.m. 50.00 sq.m./hour 6.01 days
622(3)b Vegetation (Vetiver Grass System) 2,404.00 sq.m. 35.00 sq.m./hour 8.59 days
624(8) Solar LED Street Light 2.00 each 1.00 each/hour 0.25 days
note: output was based from a one-gang of labor force. The contractor 83.80 days
waved to collect any additional compensation for the increase in say 84.00 days
labor force on this Variation Order No. 1

Prepared by: Checked by: Confome:

Project Inspector I Project Engineer I Authorized Managing Office


GVDPM Construction Corp./ Raik Construction & Supply (J/V)