Professional Documents
Culture Documents
PROGRAM OF WORKS
PROJECT TITLE: TWO(2) STOREY RESIDENTIAL BUILDING SOURCE OF FUNDS: PROJECT OWNER
LOCATION : BRGY. TABAWAN, CALBAYOG CITY,6710, SAMAR PROJECT DURATION: ------ DAYS
QUANTITY TAKE-OFF
I. EARTHWORKS COMPUTATION
Wall Footing
Total Length = 80m
Total Volume = 80 x 0.8 x 0.35 = 22.4 m3
B. Excavation
Septic Tank (1pc)
Volume = 1.5 x 3 x 1.5 = 6.75 m3
Backfill
Footing = 1.2 x 1.2 x 0.5 x 20 = 14.4 m3
Column = 3 x 0.3 x 1.5 x 1.8 = 2.43 m3
C. Earthfill Wall Footing = 80 x 0.35 x 0.2 = 5.6 m3
Masonry Wall = 80 x 0.15 x 0.6 = 7.2 m3
TOTAL Back Fill = 29.63 m3
= 49.6 - 29.63 = 20 m3
Total Weight of Bars = [(240pcs x 6m) + (120pcs x 7.5m)] 1.58 kg/m = 3698 kg
Quantity of Wire:
Main Bars:
Reinforcing Bar: 16 mm Ø, 6m commercial length
L. Beam Reinforcement
NO. of Bars = (187.3 x 1.1 x 6)/6 = 206.03 pcs say 206 pcs
(with 10% allowance for splicing and wastage)
Total Weight of Bars = (173 +115 +10) (6) 0.62 kg/m = 1108.56 kg say 1109 kg
II. STRUCTURAL
COMPUTATION
CONCRETE
FOOTING:
Volume of Column Footing = 1.2 x 1.2 x 0.5 x 20 = 14.4 m3
Volume of Wall Footing = 80 x 0.35 x 0.2 = 5.6 m3
Total Concrete Volume = 20 m3
Gravel Fill:
Column Footing = 1.2 x 1.2 x 0.1 x 20 = 2.88 m3
Wall Footing = 0.35 x 0.1 x 80 = 2.8 m 3
Total = 5.68 m3
COLUMN: 20 pcs
Volume of Column = 0.3 x 0.3 x 7.8 x 20 = 14.04 m3
Total Concrete Volume = 14.04 m3
E. Concreting of
Column
Using Class A Concrete Mixture:
Cement = 14.04 x 7.85 = 110.21 bags say 111 bags
Sand = 14.04 x 0.42 = 5.90 m3 say 6 m3
Gravel = 14.04 x 0.84 = 11.79 m 3 say 12 m3
BEAMS:
Volume of Beam 1 = 89.8 m x 0.3 x 0.4 = 10.78 m 3 2nd floor beams
Volume of Beam 2 = 88.4 m x 0.3 x 0.3 = 7.96 m3 roof beams
Volume of Beam 3 = 9.1 m x 0.3 x 0.35 = 0.96 m3 cantiliver beams
F. Concreting of Beams Total Volume = 19. 7 m3
SECOND FLOOR
Area = 90.94 m2
G. Concreting of
SLAB Volume = 90.94 x 0.1 = 9.09 m3
I. Footing
Reinforcement Total Weight of Bars = 115pcs x 6m x 1.58kg/m = 1090.5 kg
WALL FOOTING :
Longitudinal Bar : 12 mm Ø , 6m commercial length
Total Length = 90 m
Required = 3 pcs
No. of Rebars = 97.21m2 X 1.980 pcs/m2 = 192.48 pcs say 193 pcs
No. of Rebars = 90.94 m2 X 1.980 pcs/m2 = 180.06 pcs say 181 pcs
O. STAIR
Chain Bars: using 10 mmØ - 6m commercial length
REINFORCEMENT
Cut Length = 1.3 m
Req'd = 16 pcs
No. of pcs / Bar = 6m / 1.94 = 5 pcs
No. of Bars = 16pcs/5 pcs per bar = 3.2 say 3.5 pcs
EQUIVALENT WEIGHT:
12 mmØ bar = 7pcs x 6m x 0.89 kg/m = 37.38 kg
10 mmØ bar = 10 pcs x 6m x 0.62 kg/m = 37.2kg
Total Weight = 74.58kg
2" x 3" x 16" lumber = 1326 x 6.013 bd.ft. = 7973.24 bd.ft. say 7974 bd.ft.
P. Scaffoldings
In Pieces:
2" x 3" x 16" lumber = 7974 / 8 = 997 pcs
FOR COLUMNS:
C-1 = 2(0.3x0.3) + 0.20 = 1.4m
Area = 1.4m x 9m x 20pcs = 252 m2
In Pieces:
2" x 3" x 16" lumber = 2193 bd.ft. / 5.33 bd.ft. per pieces = 411.44 pcs say 412 pcs
FOR BEAMS:
BEAM 1: length = 89.8 m
Area = 89.8 x [0.2+(0.3x2)] = 71.84 m2
BEAM 2: length = 88.4 m
Area = 88.4 x [0.2+(0.3x2)] = 70.72 m2
BEAM 3: length = 9.1 m
Q. FORMS AND Area = 9.1 x [0.2+(0.3x2)] = 7.28 m2
FRAMES TOTAL = 149.84 m2
2" x 3" x 16" lumber = 1304 bd.ft. / 5.33 bd.ft. per pieces = 244.65 pcs say 245 pcs
FOR SLAB:
Area = 188.14 m2
Required Plywood = 188.14 sq m/2.88 sq m per pieces = 66 pcs
Wood Frame = 66 pcs x 25.06 bd.ft. /pc = 1653.96 say 1654 bd.ft.
2" x 3" x 16" lumber = 1654 bd.ft. / 5.33 bd.ft. per pieces = 310.32pcs say 311 pcs
V. MASONRY
COMPUTATION
WORKS
CHB
Wall Area = 90m x 6.4m = 576 m2
Septic Vault = 8m x 1.2m = 9.6 m2
TOTAL = 585.6 m2
EQUIVALENT VOLUME:
Constant Value
Lauaan Lumber Lumber (pcs) Volume (bd.ft.)
(bd.ft.)
Roof Nails:
Nails in kg = ( 65 x 18 ) pcs ÷ 120 pcs = 9.75 kg say 10 kg
roof
ridge rolls fascia Gutter roof nails C.W. nails Lumber
Item of Works sheets(pc
(pcs) flash (pcs) (pcs) (kg) (kg) (bd. Ft.)
s)
Truss and Purlins 2413
Roofing 65 42 29 27 10 53
TOTAL 65 42 29 27 10 53 2413
VII. Plumbing
COMPUTATION
Works
By DIRECT COUNTING :
Structural Concrete:
Slab Volume = 0.2 m x 1 m x 3 m = 0.6 m3
Rebars:
For CHB Wall: Using 10 mm Ø x 6 m commercial length
Items Area m2 Constant Length No. of bars say
Vertical bars 24 2.13 51.12 8.52 9pcs 10mmØ
Horizontal bars 24 2.15 51.6 8.6 9pcs 10mmØ
TOTAL 18 pcs 10 mm Ø
Equivalent Weight:
bars pcs kg per pcs Weight
10 mm Ø 18 3.7 66.6
12 mm Ø 6 5.33 31.98
Total 98.58 kg
Factor
Total Factor board feet REQ.
(bd.ft./pcs say (pcs)
Area (m2) (bd.ft./m2) bd.ft. LUMBER
Z. CEILING )
213.76 8.75 1870.4 5.33 350.9193 356
Wood Mouldings:
Req. No. = Total Length ÷ length/ pcs
Req. No. = ( 83.85 m x 4) ÷ 4.80 m / pcs = 69.88 pcs say 70 pcs
Direct Counting:
TOTAL : 19 units
Direct Counting:
TOTAL: 26 units
TOTAL 45 sets
X. Electrical
COMPUTATION
Works
Direct Counting:
Switches:
S1 = 9 sets
S2 = 13 sets
S3 = 3 sets
Direct Counting:
Total Area:
Masonry Wall: 1152 m2
Structural Concrete: 523.45 m2
Ceiling: 213.76 m 2
GI Sheets: 175.35 m 2
TOTAL = 2064.56 m2
Primer Paint :
With Coverage of 37 m2 per gallon first coat
e. PAINTS With Coverage of 20.80 m2 per gallon second coat
MATERIAL TAKE-OFF
Program of Works
I. EARTHWORKS
Coco Lumber
(2" x 3" x 16")
13125 bd. ft. 11.25 147,656.25
Marine Plywood
(6mm x 1.20m x 2.40m)
205.5 pcs 475.00 97,612.50
Common Wire Nails 165.5 kg 60.00 9,930.00
Hand Saw 4 pcs 159.00 636.00
Hammer 4 pcs 119.00 476.00
Tape Measure 3 roll 99.00 297.00
Assorted Nails 25 kg 85.00 2,125.00
TOTAL 258,732.75
V. Masonry Works
Good Lumber,
Lauaan Lumber
2413 bd.ft. 40.00 96,520.00
TOTAL 145,275.00
TOTAL 113,915.00
TOTAL 116,631.00
WINDOWS
X. ELECTRICAL WORKS
Electrical Wirings:
13 mm Dia. X 3.00 m
Moulding 63 pcs 150.00 9,450.00
2-20 m2 Electrical Wire
14 role 800.00 11,200.00
2-35 m2 Electrical Wire 8 role 900.00 7,200.00
Switches:
S1 9 pcs 80.00 720.00
S2 13 pcs 120.00 1,560.00
S3 3 pcs 170.00 510.00
Outlets:
Convenience Outlet 4,650.00
31 pcs 150.00
TOTAL 69,190.00
XI. PAINTING WORKS
LABOR TAKE-OFF
PROGRAM OF WORKS
I. EARTHWORKS
Ouput Labor Cost
No. of Duration
ITEM OF WORKS Workers Quantity Unit per Day Total Cost per
Workers (Days) Cost per Day
(Unit) Worker
PhP 1,200.00
PhP 1,200.00
PhP 2,400.00
PhP 800.00
PhP 800.00
PhP 1,600.00
PhP 3,457.14
PhP 10,371.43
PhP 13,828.57
PhP 833.33
PhP 1,666.67
PhP 2,500.00
PhP 20,328.57
TOTAL COST
PhP 3,465.00
PhP 6,237.00
PhP 5,197.50
PhP 3,300.00
PhP 5,940.00
PhP 4,950.00
PhP 29,089.50
PhP 10,315.00
PhP 18,567.00
PhP 15,472.50
PhP 2,383.70
PhP 4,290.65
PhP 3,575.54
PhP 9,823.81
PhP 17,682.86
PhP 14,735.71
PhP 3,936.89
PhP 7,086.39
PhP 5,905.33
PhP 113,775.38
PhP 3,583.16
PhP 6,449.68
PhP 12,541.05
PhP 22,573.89
PhP 1,171.59
PhP 2,108.86
PhP 1,757.39
PhP 1,288.75
PhP 2,319.75
PhP 1,933.13
PhP 972.00
PhP 1,749.60
PhP 1,944.00
PhP 15,245.07
TOTAL COST
PhP 3,245.70
PhP 5,842.26
PhP 4,868.55
PhP 1,358.33
PhP 2,445.00
PhP 2,037.50
PhP 2,885.07
PhP 5,193.12
PhP 7,212.67
PhP 2,774.81
PhP 4,994.67
PhP 4,162.22
PhP 47,019.90
PhP 1,208.75
PhP 1,087.88
PhP 1,813.13
PhP 1,722.92
PhP 3,101.25
PhP 2,584.38
PhP 1,074.44
PhP 1,934.00
PhP 2,686.11
PhP 3,484.07
PhP 3,135.67
PhP 5,226.11
PhP 29,058.70
PhP 1,041.50
PhP 937.35
PhP 1,874.70
PhP 4,686.75
PhP 8,540.30
TOTAL COST
PhP 186.45
PhP 167.81
PhP 279.68
PhP 450.97
PhP 811.74
PhP 450.97
PhP 162.13
PhP 291.83
PhP 243.20
PhP 1,217.80
PhP 2,192.04
PhP 1,217.80
PhP 225.56
PhP 406.00
PhP 563.89
PhP 8,867.85
PhP 274,170.59
TOTAL COST
PhP 8,013.68
PhP 21,636.95
PhP 8,013.68
PhP 8,638.67
PhP 7,774.80
PhP 7,774.80
PhP 8,638.67
PhP 7,222.22
PhP 6,500.00
PhP 7,222.22
PhP 4,264.71
PhP 11,514.71
PhP 4,264.71
PhP 5,703.75
PhP 5,133.38
PhP 2,851.88
PhP 125,168.81
TOTAL COST
PhP 2,600.00
PhP 8,320.00
PhP 1,900.00
PhP 4,560.00
PhP 17,380.00
TOTAL COST
PhP 2,740.00
PhP 4,384.00
PhP 7,124.00
PhP 3,016.25
PhP 5,429.25
PhP 4,524.38
PhP 12,969.88
PhP 1,753.50
PhP 3,156.30
PhP 2,630.25
PhP 7,540.05
PhP 2,600.00
PhP 2,340.00
PhP 2,600.00
PhP 7,540.00
PhP 2,500.00
PhP 2,250.00
PhP 2,500.00
PhP 7,250.00
5,344.00
9,619.20
8,016.00
PhP 22,979.20
5,161.40
13,935.78
7,742.10
PhP 26,839.28
PROJECT TITLE: TWO STOREY RESIDENTIAL BUILDING
LOCATION: BRGY. TABAWAN, CALBAYOG CITY
OWNER: JONATHAN A. OROT
DETAILED ESTIMATE
DIRECT COST
ITEMS
MATERIAL COST LABOR COST
Quantity : 116.8 m 3
No. of Duration
Item of Works Workers Daily Rate Cost
OPERATION METHOD : MANUAL Workers (days)
Quantit Foreman 1 500.00 PhP 1,200.00
Materials Unit Unit Cost Total Cost a.Clearing and Grabbing 2.4
y Labor (Unskilled) 2 250.00 PhP 1,200.00
Spade 7 pcs 250.00 1,750.00 SUBTOTAL PhP 2,400.00
2" x 2" x 16' 10,000.00
500 bd.ft. 20.00 Foreman 1 500.00 PhP 800.00
Lumber b. Staking 1.6
Nylon 8 roll 199.00 1,592.00 Labor (Unskilled) 2 250.00 PhP 800.00
Shovel 7 pcs 119.00 833.00 SUBTOTAL PhP 1,600.00
Tagad 4 pcs 199.00 796.00 Foreman 1 500.00 PhP 3,455.00
c. Excavation 6.91
Measuring Tape 2 roll 369.00 738.00 Labor (Unskilled) 6 250.00 PhP 10,365.00
Cart 2 pcs 865.00 1,730.00 SUBTOTAL PhP 13,820.00
Plumbob 2 pcs 69.00 138.00 Foreman 1 500.00 PhP 835.00
d. Earthfill 1.67
SUBTOTAL 17,577.00 Labor (Unskilled) 4 250.00 PhP 1,670.00
TOTAL 17, 577.00 SUBTOTAL PhP 2,505.00
INDIRECT COST
EARTHWORKS 17,577.00 20,325.00 37,902.00 4,169.22 3,790.20 1,895.10 1,895.10 1,895.10 PhP 13,644.72
DIRECT COST
ITEMS
MATERIAL COST LABOR COST
Quantity : 116.8 m3
No. of Daily
Item of Works Workers
OPERATION METHOD : MANUAL Workers Rate
Materials Quantity Unit Unit Cost Total Cost a.Structural Work of Column and Footing
Foreman 1 500.00
8.Cutting and
Bending of Bars Steelman 2 450.00
Labor (Unskilled) 3 250.00
Foreman 1 500.00
9.Installation of
Bars Steelman 2 450.00
Labor (Unskilled) 3 250.00
Foreman 1 500.00
10.Concreting of
Slab on Ground
Mason 2 450.00
Labor (Unskilled) 4 250.00
SUBTOTAL
DIRECT COST
LABOR COST
Designation of No. of Ouput per Day Duration Labor Cost
ITEM OF WORKS Quantity Unit Total Cost per TOTAL COST
Labor Workers (Unit) (Days) Cost per Day
Worker
e. BEAMS
Foreman 1 500.00 500.00 PhP
e1. Cutting and Bending of Bars Steelman 2 2596.56 kg 400 6.49 450.00 900.00 PhP
Labor (Unskilled) 3 250.00 750.00 PhP
Foreman 1 500.00 500.00 PhP
e2. Installation of Scaffoldings Carpenter 2 1304 bd.ft. 480 2.72 450.00 900.00 PhP
Labor (Unskilled) 3 250.00 750.00 PhP
Foreman 1 500.00 500.00 PhP
e3. Installation of Bars Steelman 2 2596.56 kg 450 5.77 450.00 900.00 PhP
Labor (Unskilled) 5 250.00 1,250.00 PhP
Foreman 1 500.00 500.00 PhP
e4. Installation of Forms Carpenter 2 149.84 m2 27 5.55 450.00 900.00 PhP
Labor (Unskilled) 3 250.00 750.00 PhP
SUBTOTAL PhP
f. SLAB on 2nd FLOOR
Foreman 1 500.00 500.00 PhP
b1. Cutting and Bending of Bars Steelman 1 967 kg 400 2.42 450.00 450.00 PhP
Labor (Unskilled) 3 250.00 750.00 PhP
Foreman 1 500.00 500.00 PhP
b2. Installation of Scaffoldings Carpenter 2 1654 bd.ft. 480 3.45 450.00 900.00 PhP
Labor (Unskilled) 3 250.00 750.00 PhP
Foreman 1 500.00 500.00 PhP
b3. Installation of Bars Steelman 2 967 kg 450 2.15 450.00 900.00 PhP
Labor (Unskilled) 5 250.00 1,250.00 PhP
Foreman 1 500.00 500.00 PhP
b4. Installation of Forms Carpenter 1 188.14 m2 27 6.97 450.00 450.00 PhP
Labor (Unskilled) 3 250.00 750.00 PhP
SUBTOTAL PhP
Foreman 1 500.00 500.00 PhP
Carpenter 1 450.00 450.00 PhP
g. CONCRETING OF SLAB AND BEAM 20.83 m 3
10 2.08
Mason 2 450.00 900.00 PhP
Labor (Unskilled) 9 250.00 2,250.00 PhP
SUBTOTAL PhP
DIRECT COST
LABOR COST
Designation of No. of Ouput per Day Duration Labor Cost
ITEM OF WORKS Quantity Unit Total Cost per TOTAL COST
Labor Workers (Unit) (Days) Cost per Day
Worker
h. STAIRS
Foreman 1 500.00 500.00 PhP
h1. Cutting and Bending of Bars Steelman 1 74.58 kg 200 0.37 450.00 450.00 PhP
Labor (Unskilled) 3 250.00 750.00 PhP
Foreman 1 500.00 500.00 PhP
h2. Installation of Scaffoldings Carpenter 2 270.58 bd.ft. 300 0.90 450.00 900.00 PhP
Labor (Unskilled) 2 250.00 500.00 PhP
Foreman 1 500.00 500.00 PhP
h3. Installation of Bars Steelman 2 74.58 kg 230 0.32 450.00 900.00 PhP
Labor (Unskilled) 3 250.00 750.00 PhP
Foreman 1 500.00 500.00 PhP
h4. Installation of Forms Carpenter 2 60.89 m2 25 2.44 450.00 900.00 PhP
Labor (Unskilled) 2 250.00 500.00 PhP
Foreman 1 500.00 500.00 PhP
h5. Concreting of Stairs Mason 2 2.03 m3 4.5 0.45 450.00 900.00 PhP
Labor (Unskilled) 5 250.00 1,250.00 PhP
SUBTOTAL PhP
INDIRECT COST
STRUCTURAL
WORKS
968,258.25 274,173.75 1,242,432.00 136,667.52 124,243.20 62,121.60 62,121.60 62,121.60 PhP 447,275.52
DIRECT COST
ITEMS
MATERIAL COST LABOR COST
Quantity : 585.6 m2 No. of Daily Duration
Item of Works Workers
OPERATION METHOD : MANUAL Workers Rate (days)
Foreman 1 500.00
Materials Quantity Unit Unit Cost Total Cost a. Laying of CHB Mason 3 450.00 16.03
CHB Labor (Unskilled) 2 250.00
7613 pcs 15.00 114,195.00
150 x 200 x 400 mm Foreman 1 500.00
10 mm Ø x 6 m RSB 418 pcs 135.00 56,430.00 Steelman 1 450.00
b. RSB Installation 17.28
Tie Wire 19 kg 65.00 1,235.00 Mason 1 450.00
Portland Cement 389 bags 240.00 93,360.00 Labor (Unskilled) 2 250.00
Sand 33.5 m3 700.00 23,450.00 Foreman 1 500.00
0.3m x 0.3m tiles 2091 pcs 40.00 83,640.00 c. Cement Mortar Mason 1 450.00 14.44
0.2m x 0.2m tiles 1000 pcs 30.00 30,000.00 Labor (Unskilled) 2 250.00
Nylon 3 roll 199.00 597.00 Foreman 1 500.00
TOTAL 402,907.00 d. Plastering Mason 3 450.00 8.53
Labor (Unskilled) 2 250.00
Foreman 1 500.00
III. MASONRY WORKS e. Tiles Installation Mason 1 450.00 11.41
Labor (Unskilled) 1 250.00
INDIRECT COST
MASONRY WORKS 402,907.00 125,178.00 528,085.00 58,089.35 52,808.50 26,404.25 26,404.25 26,404.25 PhP 190,110.60
DIRECT COST
ITEMS
MATERIAL COST LABOR COST
Quantity : 350.7 m2 No. of Daily Duration
Item of Works Workers
OPERATION METHOD : MANUAL Workers Rate (days)
Foreman 1 500.00
Materials Quantity Unit Unit Cost Total Cost a. Truss Fabrication Carpenter 3 450.00 6.03
Corr. G.I. Roofing Sheet, Ga. Labor (Unskilled) 2 250.00
26
65 sheet 300.00 19,500.00
Foreman 1 500.00
b. Installation of Trusses
Plain G.I. ridge roll, Ga.26 Carpenter 2 450.00 6.03
450mm x 2.44m
42 pcs 280.00 11,760.00 and Purlins
Labor (Unskilled) 1 250.00
Plain G.I. Flashing, Ga.26 Foreman 1 500.00
450mm x 2.44m
29 pcs 285.00 8,265.00
f. Installation of Roofing Carpenter 2 450.00 6.03
Plain G.I. Gutter, Ga.16 Labor (Unskilled) 1 250.00
450mm x 2.44m
27 pcs 200.00 5,400.00
Foreman 1 500.00
c. Installation of Roof
Carpenter 2 450.00 6.03
Roof Nails 10 kg 65.00 650.00 Accessories
Labor (Unskilled) 1 250.00
TOTAL
Common Wire Nails 53 kg 60.00 3,180.00
Good Lumber,
Lauaan Lumber
2413 bd.ft. 40.00 96,520.00
TOTAL 145,275.00
IV. TRUSS AND ROOFING
INDIRECT COST
TRUSS AND ROOFING 145,275.00 44,019.00 189,294.00 20,822.34 18,929.40 9,464.70 9,464.70 9,464.70 PhP 68,145.84
TRUSS AND ROOFING 145,275.00 44,019.00 189,294.00 20,822.34 18,929.40 9,464.70 9,464.70 9,464.70 PhP 68,145.84
DIRECT COST
ITEMS
MATERIAL COST LABOR COST
Quantity : 26 L.S. Unit Total
Materials Quantity Unit
OPERATION METHOD : MANUAL Cost Cost
Foreman 1 500.00
Materials Quantity Unit Unit Cost Total Cost
a. Installation of PVC Pipe Plumber 2 450.00 5.2
Water Closet 4 set 4,500.00 18,000.00 Labor (Unskilled) 2 250.00
Lavatory 4 set 2,000.00 8,000.00 Foreman 1 500.00
Kitchen Sink 1 set 1,700.00 1,700.00 b. Installation of Plumbing Plumber 2 450.00 5.2
Shower Head, Valve, Accessories
7 set 800.00 5,600.00 Labor (Unskilled) 2 250.00
Faucet
Bath Tub 1 set 6,500.00 6,500.00 SUBTOTAL
TOTAL 113,915.00
V. PLUMBING WORKS
INDIRECT COST
OVER TOTAL INDIRECT
DIRECT TAX PROFIT CONTENGENCIES PHYSICAL RESERVE
MATERIAL COST LABOR COST HEAD COST
COST
11% 10% 5% 5% 5%
113,915.00 33,760.00 147,675.00 16,244.25 14,767.50 7,383.75 7,383.75 7,383.75 PhP 53,163.00
DIRECT COST
ITEMS
MATERIAL COST LABOR COST
Quantity : 45 sets No. of Daily Duration
Item of Works Workers
OPERATION METHOD : MANUAL Workers Rate (days)
a. Installation of Foreman 1 500.00
Materials Quantity Unit Unit Cost Total Cost Windows
5.2
Labor (Skilled) 4 400.00
DOORS Foreman 1 500.00
b.Installation of Doors 3.8
Panel Type Door: Labor (Skilled) 3 400.00
D1, 2.1 m x 0.9 m 1 set 8,500.00 8,500.00 TOTAL
D2, 2.1 m x 0.8 m 8 set 6,000.00 48,000.00
D4, 2.1 m x 0.8 m 2 set 6,000.00 12,000.00
D6, 2.1 m x 0.8 m 2 set 6,000.00 12,000.00
D7, 2.1 m x 0.6 m 1 set 5,500.00 5,500.00
MATERIAL COST LABOR COST DIRECT COST
Flush Type Door:
258,500.00 17,380.00 PhP 275,880.00
D3, 2.1 m x 0.6 m 4 set 6,000.00 24,000.00
WINDOWS
INDIRECT COST
OVER TOTAL INDIRECT
DIRECT TAX PROFIT CONTENGENCIES PHYSICAL RESERVE
MATERIAL COST LABOR COST HEAD COST
COST
11% 10% 5% 5% 5%
258,500.00 17,380.00 275,880.00 30,346.80 27,588.00 13,794.00 13,794.00 13,794.00 PhP 99,316.80
DIRECT COST
ITEMS
MATERIAL COST LABOR COST
Quantity : 136 LS No. of Daily Duration
Item of Works Workers
OPERATION METHOD : MANUAL Workers Rate (days)
Foreman 1 500.00
Materials Quantity Unit Unit Cost Total Cost a. Installation Mouldflex Electrician 2 400.00 5.48
Electrical Lightings and Conduit
Labor (Unskilled) 2 250.00
Accessories:
Pin Lights 62 pcs 150.00 9,300.00 Foreman 1 500.00
Energy Saving Lamp 10 pcs 200.00 2,000.00 b. Wiring Installation Electrician 2 400.00 5.48
Chandelier 3 pcs 4,500.00 13,500.00 Labor (Unskilled) 2 250.00
Wall Lamp 6 pcs 100.00 600.00 Foreman 1 500.00
9 500.00 c. Electrical Accessories
Circuit Breaker pcs 4,500.00 Electrician 2 400.00 5.48
Installation
Panel Board 1 pcs 4,000.00 4,000.00 Labor (Unskilled) 2 250.00
TOTAL
Electrical Wirings:
13 mm Dia. X 3.00 m Moulding 63 pcs 150.00 9,450.00
2-20 m2 Electrical Wire 14 role 800.00 11,200.00
2-35 m2 Electrical Wire 8 role 900.00 7,200.00
Switches:
S1 9 pcs 80.00 720.00
S2 13 pcs 120.00 1,560.00
VII. ELECTRICAL 510.00
S3 3 pcs 170.00
WORKS
Outlets:
Convenience Outlet 31 pcs 150.00 4,650.00
TOTAL 69,190.00
INDIRECT COST
69,190.00 29,592.00 98,782.00 10,866.02 9,878.20 4,939.10 4,939.10 4,939.10 PhP 35,561.52
DIRECT COST
ITEMS
MATERIAL COST LABOR COST
Quantity : 213.76 m 2
No. of Daily Duration
Item of Works Workers
OPERATION METHOD : MANUAL Workers Rate (days)
Foreman 1 500.00
Materials Quantity Unit Unit Cost Total Cost a. Installation of Ceiling
Carpenter 2 450.00 10.69
Joist
Marine Plywood Labor (Unskilled) 1 250.00
(6mm x 1.20m x 2.40m)
75 pcs 475.00 35,625.00
Foreman 1 500.00
b. Installation of Ceiling
Good Lumber Carpenter 2 450.00 10.69
(2" x 3" x 16")
1870.4 bd. ft. 40.00 74,816.00 Boards
Labor (Unskilled) 1 250.00
Common Wire Nails 29 kg 60.00 1,740.00 TOTAL
Finishing Nails 5 kg 50.00 250.00
Mouldings 70 kg 60.00 4,200.00
TOTAL 116,631.00
INDIRECT COST
116,631.00 35,277.00 151,908.00 16,709.88 15,190.80 7,595.40 7,595.40 7,595.40 PhP 54,686.88
DIRECT COST
ITEMS
MATERIAL COST LABOR COST
Quantity : 2064.56 m 2
No. of Daily Duration
Item of Works Workers
OPERATION METHOD : MANUAL Workers Rate (days)
Foreman 1 500.00
Materials Quantity Unit Unit Cost Total Cost
a. First Coating Painter 3 450.00 10.32
Masonry Neutralizer 20 gal. 550.00 11,000.00 Labor(Unskilled) 3 250.00
Acrylic Latex Primer 20 gal. 800.00 16,000.00 Foreman 1 500.00
Acrylic Gloss Latex Paint 20 gal. 1,000.00 20,000.00 b. Final Coating Painter 3 450.00 10.32
Interior Primer & Sealer 20 set. 950.00 19,000.00 Labor(Unskilled) 3 250.00
Interior Semi-Gloss Enamel 20 gal. 800.00 16,000.00 TOTAL
Concrete Primer Cement 18 bags 300.00 5,400.00
Davies Roof Paint 7 gal. 800.00 5,600.00
Painting Roller 8 pcs. 60.00 480.00
Painting Brush 8 pcs. 50.00 400.00
TOTAL 93,880.00
INDIRECT COST
93,880.00 53,664.00 147,544.00 16,229.84 14,754.40 7,377.20 7,377.20 7,377.20 PhP 53,115.84
Cost
PhP 1,200.00
PhP 1,200.00
PhP 2,400.00
PhP 800.00
PhP 800.00
PhP 1,600.00
PhP 3,455.00
PhP 10,365.00
PhP 13,820.00
PhP 835.00
PhP 1,670.00
PhP 2,505.00
PhP 20,325.00
PhP 3,465.00
6.93 PhP 6,237.00
PhP 5,197.50
PhP 3,300.00
6.6 PhP 5,940.00
PhP 4,950.00
PhP 10,315.00
20.63 PhP 18,567.00
PhP 15,472.50
PhP 2,385.00
4.77 PhP 4,293.00
PhP 3,577.50
PhP 9,825.00
19.65 PhP 17,685.00
PhP 14,737.50
PhP 3,935.00
PhP 7,083.00
7.87
PhP 5,902.50
PhP 3,585.00
7.17 PhP 6,453.00
PhP 12,547.50
PhP 165,453.00
PhP 1,170.00
2.34 PhP 2,106.00
PhP 1,755.00
PhP 1,290.00
2.58 PhP 2,322.00
PhP 1,935.00
PhP 970.00
1.94 PhP 1,746.00
PhP 1,940.00
PhP 15,234.00
TOTAL COST
PhP 3,245.70
PhP 5,842.26
PhP 4,868.55
PhP 1,358.33
PhP 2,445.00
PhP 2,037.50
PhP 2,885.07
PhP 5,193.12
PhP 7,212.67
PhP 2,774.81
PhP 4,994.67
PhP 4,162.22
PhP 47,019.90
PhP 1,208.75
PhP 1,087.88
PhP 1,813.13
PhP 1,722.92
PhP 3,101.25
PhP 2,584.38
PhP 1,074.44
PhP 1,934.00
PhP 2,686.11
PhP 3,484.07
PhP 3,135.67
PhP 5,226.11
PhP 29,058.70
PhP 1,041.50
PhP 937.35
PhP 1,874.70
PhP 4,686.75
PhP 8,540.30
TOTAL COST
PhP 186.45
PhP 167.81
PhP 279.68
PhP 450.97
PhP 811.74
PhP 450.97
PhP 162.13
PhP 291.83
PhP 243.20
PhP 1,217.80
PhP 2,192.04
PhP 1,217.80
PhP 225.56
PhP 406.00
PhP 563.89
PhP 8,867.85
PhP 274,173.75
DC + IDC
PhP 125,178.00
Cost
PhP 2,600.00
PhP 4,680.00
PhP 2,600.00
PhP 2,600.00
PhP 4,680.00
PhP 2,600.00
PhP 19,760.00
Cost
PhP 2,500.00
PhP 4,500.00
PhP 4,500.00
PhP 2,500.00
PhP 14,000.00
PhP 33,760.00
PhP 2,600.00
PhP 8,320.00
PhP 1,900.00
PhP 4,560.00
PhP 17,380.00
DIRECT COST
275,880.00
TOTAL COST of UNIT COST of
ITEM ITEM
DC + IDC
Cost
PhP 2,740.00
PhP 4,384.00
PhP 2,740.00
PhP 2,740.00
PhP 4,384.00
PhP 2,740.00
PhP 2,740.00
PhP 4,384.00
PhP 2,740.00
PhP 29,592.00
Cost
PhP 5,345.00
PhP 9,621.00
PhP 2,672.50
PhP 5,345.00
PhP 9,621.00
PhP 2,672.50
PhP 35,277.00
PhP 5,160.00
PhP 13,932.00
PhP 7,740.00
PhP 5,160.00
PhP 13,932.00
PhP 7,740.00
PhP 53,664.00
ACTIVITIES p
PROGRAM OF WORKS
I. EARTHWORKS
ITEM OF WORKS
B. STAKING
C. EXCAVATION
D. EARTHFILL
E. FOOTINGS
E1. Cutting and Bending of Bars
E2. Installation of Bars
F. COLUMN
F1. Cutting and Bending of Bars
F2. Installation of Scaffoldings
F3. Installation of Bars
F4. Installation of Forms
G. Concreting of Footing and Column
H. Slab on Ground
H1. Cutting and Bending of Bars
H2. Installation of Bars
I. Concreting of Slab on Ground
J. Beams
J1. Cutting and Bending of Bars
J2. Installation of Scaffoldings
J3. Installation of Bars
J4. Installation of Forms
K. Slab (2nd Floor)
K1. Cutting and Bending of Bars
K2. Installation of Scaffoldings
K3. Installation of Bars
K4. Installation of Forms
L. Concreting of Slab and Beam
M. Stairs
M1. Cutting and Bending of Bars
M2. Installation of Scaffoldings
M3. Installation of Bars
M4. Installation of Forms
N. Concreting of Stairs
O. Column (2nd Floor)
O1. Cutting and Bending of Bars
O2. Installation of Scaffoldings
O3. Installation of Bars
O4. Installation of Forms
P. Concreting of Column
Q. Roof Beams
Q1. Cutting and Bending of Bars
Q2. Installation of Scaffoldings
Q3. Installation of Bars
Q4. Installation of Forms
R.Concreting of Roof Beams
S. Removal of Forms
T. CHB Walling
U. Cement Mortar
V. Plastering (Finishing)
W. Tiles Installation
DURATION OF
PROGRAM OF WORKS
I. EARTHWORKS
No. of
ITEM OF WORKS Workers
Workers
Engineer 1
A. CLEARING AND GRABBING
Foreman 1
Labor (Unskilled) 3
Engineer 1
B. STAKING
Foreman 1
Labor (Unskilled) 3
Engineer 1
C. EXCAVATION
Foreman 1
Labor (Unskilled) 6
Engineer 1
D. EARTHFILL
Foreman 1
Labor (Unskilled) 6
Engineer 1
G. Concreting of Footing and
Foreman 1
Column
Mason 2
Labor (Unskilled) 7
H. SLAB on GROUND
Engineer 1
Foreman 1
H1. Cutting and Bending of Bars
Steelman 2
Labor (Unskilled) 3
Engineer 1
Foreman 1
H2. Installation of Bars
Steelman 2
Labor (Unskilled) 3
Engineer 1
I. Concreting of Slab on Ground Foreman 1
Mason 2
Labor (Unskilled) 7
J. BEAMS
Engineer 1
Foreman 1
J1. Cutting and Bending of Bars
Steelman 2
Labor (Unskilled) 3
Engineer 1
Foreman 1
J2. Installation of Scaffoldings
Carpenter 2
Labor (Unskilled) 3
Engineer 1
Engineer 1
L. Concreting of Beam and Slab Carpenter 1
Mason 2
Labor (Unskilled) 9
M. STAIRS
Engineer 1
Foreman 1
M1. Cutting and Bending of Bars
Steelman 1
Labor (Unskilled) 3
Engineer 1
Foreman 1
M2. Installation of Scaffoldings
Carpenter 2
Labor (Unskilled) 2
Engineer 1
Foreman 1
M3. Installation of Bars
Steelman 2
Labor (Unskilled) 2
Engineer 1
Foreman 1
M4. Installation of Forms
M4. Installation of Forms
Carpenter 2
Labor (Unskilled) 3
Engineer 1
Foreman 1
N. Concreting of Stairs
Carpenter 2
Labor (Unskilled) 5
O. COLUMN (2nd Floor)
Engineer 1
Foreman 1
O1. Cutting and Bending of Bars
Steelman 1
Labor (Unskilled) 3
Engineer 1
Foreman 1
O2. Installation of Scaffoldings
Carpenter 2
Labor (Unskilled) 3
Engineer 1
Foreman 1
O3. Installation of Bars
Steelman 2
Labor (Unskilled) 3
Engineer 1
Foreman 1
O4. Installation of Forms
Carpenter 2
Labor (Unskilled) 3
Engineer 1
Foreman 1
P. Concreting of Column
Carpenter 2
Labor (Unskilled) 5
Q. ROOF BEAMS
Engineer 1
Foreman 1
Q1. Cutting and Bending of Bars
Steelman 1
Labor (Unskilled) 3
Engineer 1
Foreman 1
Q2. Installation of Scaffoldings
Carpenter 2
Labor (Unskilled) 3
Engineer 1
Foreman 1
Q3. Installation of Bars
Steelman 2
Labor (Unskilled) 3
Engineer 1
Foreman 1
Q4. Installation of Forms
Carpenter 2
Labor (Unskilled) 3
Engineer 1
Foreman 1
R. Concreting of Roof Beams
Carpenter 2
Labor (Unskilled) 5
Engineer 1
Foreman 1
S. Removal of FORMS
Carpenter 3
Labor (Unskilled) 5
Ouput
Quantity Unit per Day Duration (Days)
(Unit)
96.8 m3 14 6.91
20 m3 12 1.67
Ouput
Quantity Unit per Day Duration (Days)
(Unit)
124.8 m2 15 8.32
9.72 m3 5 1.94
79.12 m2 14 5.65
90.94 m2 24 3.79
20.83 m3 8 2.60
60.89 m2 25 2.44
60.89 m2 25 2.44
127.2 m2 25 5.09
70.72 m2 25 2.83
7.96 m3 3.75 2.12
Ouput
Quantity Unit per Day Duration (Days)
(Unit)
13 m3 0.9 14.44
228.15 m2 28 8.15
Ouput
Quantity Unit per Day Duration (Days)
(Unit)
16 sets 3 5.33
Ouput
Quantity Unit per Day Duration (Days)
(Unit)
65 pcs 10 6.50
Ouput
Quantity Unit per Day Duration (Days)
(Unit)
26 bd.ft. 3 8.67
19 bd.ft. 2 9.50
Ouput
Quantity Unit per Day Duration (Days)
(Unit)
250 m 70 3.57
Ouput
Quantity Unit per Day Duration (Days)
(Unit)
75 pcs 28 2.68
Ouput
Quantity Unit per Day Duration (Days)
(Unit)
213.76 m2 95 2.25
213.76 m2 95 2.25
175.35 m2 85 2.06
PROJECT TITLE: TWO STOREY RESIDENTIAL BUILDING
LOCATION: BRGY. TABAWAN, CALBAYOG CITY
OWNER: JONATHAN A. OROT
E. FOOTINGS D
E1. Cutting and Bending of Bars 7 D
E2. Installation of Bars 7 E1
F. COLUMN D
F1. Cutting and Bending of Bars 14 D
F2. Installation of Scaffoldings 5 F1
F3. Installation of Bars 11 F2
F4. Installation of Forms 9 F3
G. Concreting of Footing and Column 7 D
H. Slab on Ground E
H1. Cutting and Bending of Bars 3 D
H2. Installation of Bars 3 H1
I. Concreting of Slab on Ground 2 F
J. Beams G
J1. Cutting and Bending of Bars 7 G
J2. Installation of Scaffoldings 2 J1
J3. Installation of Bars 6 J2
J4. Installation of Forms 6 J4
K. Slab (2nd Floor) H, I, J
K1. Cutting and Bending of Bars 3 H, I, J
K2. Installation of Scaffoldings 2 K1
K3. Installation of Bars 3 K2
K4. Installation of Forms 4 K3
L. Concreting of Slab and Beam 3
M. Stairs
M1. Cutting and Bending of Bars 1
M2. Installation of Scaffoldings 1
M3. Installation of Bars 1
M4. Installation of Forms 3
N. Concreting of Stairs 1
O. Column (2nd Floor)
O1. Cutting and Bending of Bars 9
O2. Installation of Scaffoldings 8
O3. Installation of Bars 7
O4. Installation of Forms 6
P. Concreting of Column 2
Q. Roof Beams
Q1. Cutting and Bending of Bars 8
Q2. Installation of Scaffoldings 3
Q3. Installation of Bars 6
Q4. Installation of Forms 3
R.Concreting of Roof Beams 3
S. Removal of Forms 4
PRECEDES FOLLOWS
B
A C
B D
C E, F, G
PRECEDES FOLLOWS
D H, Z
D E1
E1 H
D I
D F2
F1 F3
F2 F4
F3 H
D J
E K
D H2
H1 K
F K
G K
G J2
J1 J3
J2 J4
J4 K
H, I, J L, M
H, I, J K2
K1 K3
K2 K4
K3 L, M
PRECEDES FOLLOWS
PRECEDES FOLLOWS
PRECEDES FOLLOWS
PRECEDES FOLLOWS
PRECEDES FOLLOWS
PRECEDES FOLLOWS
PRECEDES FOLLOWS