BILL OF MATERIALS

PROJECT: EXTENSION OF KITCHEN, BALCONY AND PORCH

OWNERS: JOAN MAE KRISTINE G. PAGUIRIGAN and OHMEL CUNANAN PAGUIRIGAN

LOCATION: BLK 18 LOT 47 PHASE 3 EXTENSION GREEN ESTATE IMUS CAVITE

Item to be Materials & Estimated Quantities Required


Estimated CALCULATIONS CHB Cement Sand Gravel
(bags)
Area of wall = 2m x 3.5m = 7m2
CHB for Net CHB wall area = 7m2 88 pcs
porch wall No. of CHB required = 7 x 12.5 = 87.5m 2; say
Area of wall = 10.5m x 3.5m = 36.75m 2
CHB for Less: (Door) .80m x 2.10m = 1.68m2 423 pcs.
kitchen Less: (Door) .60m x 2.10m = 1.26m2
Net CHB wall area = 33.81m2
No. of CHB required = 33.81 x 12.5 = 422.625; say
Area of wall = 10.25m x 1.80m = 18.45m 2
CHB for Less: (Entrance) 1.00m x .90m =0.9m2 220 pcs.
porch Net CHB wall area = 17.55m2
No. of CHB required = 17.55 x 12.5 = 219.375; say
Area of wall = 11.25m x .90m = 10.125m 2
CHB for Less: (for aluminum design) .85m x 1.40m = 1.19m 2
balcony 1.19 m2 x 4 = 4.76m2 68 pcs.
Net CHB wall area = 5.365m2
No. of CHB required = 5.365 x 12.5 =67.0625; say
Materials Length of footing for kitchen wall = 10.50m
for CHB Length of footing for porch = 10.25m
wall Porch wall = 2m
Footings Total length of all footings = 22.75m
Volume of concrete = .20m x .45m x 22.75m = 2.0475m 3
Plus: 10% allowance for wastage = .10m3
Total volume of concrete = 2.1475m3
For class A concrete mix: 50kg
2.1475 x 7.0 = 15 23 bags
2.1475 x .50= 1 2m3
2.1475 x 1.0 = 2.1475 2.20m3
Materials
for 711 pcs CHB x 0.0734 = 52.18, say 52 bags
cement 711 pcs CHB x 0.0059 = 4.19, say 4m3
mortar
TOTAL: 711 pcs 75bags 6m3 2.20m3

PREPARED BY:

ENGINEER
BILL OF MATERIALS

PROJECT: EXTENSION OF KITCHEN, BALCONY AND PORCH

OWNERS: JOAN MAE KRISTINE G. PAGUIRIGAN and OHMEL CUNANAN PAGUIRIGAN

LOCATION: BLK 18 LOT 47 PHASE 3 EXTENSION GREEN ESTATE IMUS CAVITE

Item to be Materials & Estimated Quantities Required


Estimated CALCULATIONS 10mm x 12mm x 16mm x
6.00m 7.60m 6.00m
Footings 5 footings x 12 bars/footings = 60 bars
bars 60 footings bars 9 pcs.
Column 7 pcs. F/L bar = 8.57; say
No. of hor.: bars 3.5/.80m = 4.40 pcs or 5 pcs
Length of all hor. Bars: 4.40 x 10.50 = 46.2m
No/ of full – length bars req. with allowance for splices:
46.20 x 1.10 / 8.47; say 9 pcs.
Reinf. Bars (Wall A) no. of vert. bars:
for CHB 4.50 / .80 = 5.625; say 6 pcs.
walls (wall B) 2 / .80 = 2.5; say 3 pcs. Same with wall C and wall D
Total no. vert. bars = 15 pcs
Length of all verts. Bars: 15 x 3.5 = 52.5
No/ of full – length bars req. with allowance for splices:
52.5 x 1.20 / .6 = 10.5; say 11 pcs.
Total length of walls: 22.75m
Reinf. Bars Transverse bars: 15 pcs
for CHB No. of full-length bars required:
walls 22.75 / .30x 15 = 5.55; say 5pcs.
Longitudinal bars
3 x 22.75 / 7.60 x 1.2 = 10.78; say 11 pcs.
Spiral
column Total length of columns 3.6m x 2(columns) = 7.2m
(kitchen 7.20m x 2.60 pcs. = 18.72 pcs.; say 19 pcs.
area)
Spiral
column Total length of columns 3.20m x 3(columns) = 9.60m
(porch 9.60m x 2.60 pcs. = 24.96 pcs.; say 25 pcs.
area)
Vertical Total length of columns 3.60m + .35= 3.95m
bars for 5pcs x 3.95m = 19.75m
column 19.75m x 2pcs of columns = 39.50m 8 pcs.
39.50m / 6 x 1.10m = 7.24 pcs; say
Vertical Total length of columns 3.20m + .35= 3.55m
bars for 5pcs x 3.55m = 17.75m
column 17.75m x 3pcs of columns = 53.25m 10pcs.
53.25m / 6 x 1.10m = 9.76 pcs; say
TOTAL: 69 pcs. 11 pcs. 9 pcs.

PREPARED BY:

ENGINEER
BILL OF MATERIALS

PROJECT: EXTENSION OF KITCHEN, BALCONY AND PORCH


OWNERS: JOAN MAE KRISTINE G. PAGUIRIGAN and OHMEL CUNANAN PAGUIRIGAN
LOCATION: BLK 18 LOT 47 PHASE 3 EXTENSION GREEN ESTATE IMUS CAVITE
Item to be Materials & Estimated Quantities Required
Estimated CALCULATIONS Cement Sand Gravel Gravel fill
(bags) (cu.m) (cu.m) (cu.m)
Vol. of conc. = 5.50m x 2m x .10m = 1.1m 3
10% allowance for wastage = .11m3
Total volume of concrete = 1.21m3
Concrete slab Class C concrete:
on fill 1.21 x 5.49 = 6.58; say x 2 = 13.16 14bags
1.21 x .44 = 0.5324; say x 2 = 1.0648 1.10m3
1.21 x 0.89 = 1.07; say x 2 = 2.14 2.20m3
Vol. of conc. = 1m x 2.7m x .10m = .275m 3
10% allowance for wastage = .027m3
Total volume of concrete = .3025m3
Concrete slab Class C concrete:
on fill .3025 x 5.49 = 1.66; say x 2 = 3.32 4bags
.3025 x .44 = 0.133; say x 2 = 2.66 2.70m3
.3025 x 0.89 = .26; say x 2 = .52 .60m3
Concrete slab Vol. of conc. = 4.50m x 2m x .10m = .9m 3
on fill 10% allowance for wastage = .09m3
Total volume of concrete = .99m3
Class C concrete:
.99 x 5.49 = 5.4351; say 6bags
.99 x .44 = 0.4356; say .5m3
.99 x 0.89 = .88; say .90m3
Gravell fill Vol. of gravel = 5.50m x 2m x .10m = 1.1m 3 1m3
Lenth of 5 x 3.60 = 18m3
10% allowance for wastage = 1.8m3
footings Total length = 19.8m3
Circular Class A mix. :
columns 19.8 x 0.55 = 10.989; say 11bags
19.8 x 0.029 = 0.5742; say .60m3
19.8 x 0.059 = 1.1682; say 1.20m3
Total length of beam = 5.20-(3 x .30) = 4.3
5% allowance for wastage = .215
Reinf. Overall length of columns = 4.515
Concrete For 200 x 300mm class A
beams 4.515 x .471 = 2.126 3 bags
4.515 x .025 = .112 .2m3
4.515 x .050 = .225 .30m3
Total length of beam = 4.20-(3 x .30) = 3.3
5% allowance for wastage = .165
Reinf. Overall length of columns = 3.465
Concrete For 200 x 300mm class A
beams 3.465 x .471 = 1.63 2 bags
3.465 x .025 = 0.086 .90m3
3.465 x .050 = 0.173 .20m3
TOTAL: 40 bags. 6m3 5.4m3 1m3

PREPARED BY:

ENGINEER
BILL OF MATERIALS

PROJECT: EXTENSION OF KITCHEN, BALCONY AND PORCH

OWNERS: JOAN MAE KRISTINE G. PAGUIRIGAN and OHMEL CUNANAN PAGUIRIGAN

LOCATION: BLK 18 LOT 47 PHASE 3 EXTENSION GREEN ESTATE IMUS CAVITE


Item to be Materials & Estimated Quantities Required
Estimated CALCULATIONS 8mm x 10mm x 12mm x 16mm x
6.00m 6mm 7.60m 6mm
Main bar = 5500-(25+25) / 100 + 1 = 55.5 or 56pcs
Distribution bar = 2000-(25+25) / 125 + 1 = 17 bars
Thickness 150-2(25)-12 = 88mm
One way Cutting length = 2000 + (2x40x12) + (1x0.42x88)-(2x1x12)
slab = 2973mm or 2.973m
Distribution length = 5500 + (2x40x8) = 6140mm or 6.140m
Main bar : 56pcsx2.973m = 166.488m / 7.60m = 21.9; say 22 pcs.
Distribution bar = 17pcsx6.140m = 104.38m/6m = 17.39m 18 pcs
Main bar = 2700-(25+25) / 100 + 1 = 27.5 or 28pcs
Distribution bar = 1000-(25+25) / 125 + 1 = 8.6 or 9pcs
Thickness 150-2(25)-12 = 88mm
One way Cutting length = 1000 + (2x40x12) + (1x0.42x88)-(2x1x12)
slab = 1972.96mm or 1.97m
Distribution length = 2700 + (2x40x8) = 3340mm or 3.340m
Main bar : 28pcsx1.97m = 55.16m / 7.60m = 7.25; say 8 pcs.
Distribution bar = 9pcsx3.340m = 30.06m/6m = 5pcs 5 pcs
Reinf. Of A total length of beam = 5.20m
beam continuous bars = 4pcs
short bottom bar = 3.12m
5.20 x 4 + 3.12 = 23.9m
total length = 23.90m
23.9m / 6m = 3.98; say 4 pcs.
A total length of beam = 4.20m
continuous bars = 4pcs
short bottom bar = 2.52m
4.20 x 4 + 2.52 = 19.32m
total length = 19.32m
19.32m / 6m = 3.22; say 4 pcs.
Total 5.20m of beam = total pcs of Stirrups = 26 pcs
Stirrups 26 / 7 = 3.7 pcs
4.20m of beam = total pcs of stirrups = 22 pcs
22 / 7 = 3.14 pcs
3.7 pcs + 3.14 pcs = 6.84 pcs; say 7 pcs.
TOTAL: 23 pcs 7 pcs 30 pcs 8 pcs

PREPARED BY:

ENGINEER
BILL OF MATERIALS

PROJECT: EXTENSION OF KITCHEN, BALCONY AND PORCH

OWNERS: JOAN MAE KRISTINE G. PAGUIRIGAN and OHMEL CUNANAN PAGUIRIGAN

LOCATION: BLK 18 LOT 47 PHASE 3 EXTENSION GREEN ESTATE IMUS CAVITE


Item to be Materials & Estimated Quantities Required
Estimated CALCULATIONS 50mm x 50mm x 50mm x 50mm x
50mm x 75mm x 150mm x 150mm x
4.80m 5.40m 2.40m 5.40m
Roof Framing
For roof Total length of lumber for roof beam
framing = 5300mm; say 2pcs.
(Lumber) Total length of lumber for purlins = 5300mm; say 4pcs.
Total length of lumber for rafters = 2100mm; say 5pcs.
Total length of lumber for cleats = 225mm; say 1pc.
Total: 1pc. 1pc. 5pcs. 4pcs.

Item to be Materials & Estimated Quantities Required


Estimated CALCULATIONS Bags m3 sand
cement
Cement Using class c (1 : 1 : 3)
plaster Total area of the surface = 63.725m2
63.725 x 0.039 = 2.48 3 pcs.
63.725 x 0.012 = 0.76 .80m3

TOTAL: 3pcs. .80m3

Item to be Materials & Estimated Quantities Required


Estimated CALCULATIONS .81m x
2.40m
Roofing
Total length of gutter = 5.30m
roofing Effective width of one roofing = .71m
2.40m long roofing sheets = 1pc
5.30 / .71 = 7.46; say 8pcs.
18 x 1 = 18 pcs 18 pcs
Total: 18pcs.

PREPARED BY:

ENGINEER