The document calculates the materials needed to construct the exterior walls of a ground floor. It estimates the quantities of concrete hollow blocks (CHB) of different sizes, cement bags, sand and gravel required. For each of the 6 exterior walls, it determines the wall area, deducts any door and window areas, calculates the net CHB wall area and number of CHB blocks required after adding a 5% wastage factor. The totals will be used to request supplies for constructing the exterior walls.
The document calculates the materials needed to construct the exterior walls of a ground floor. It estimates the quantities of concrete hollow blocks (CHB) of different sizes, cement bags, sand and gravel required. For each of the 6 exterior walls, it determines the wall area, deducts any door and window areas, calculates the net CHB wall area and number of CHB blocks required after adding a 5% wastage factor. The totals will be used to request supplies for constructing the exterior walls.
The document calculates the materials needed to construct the exterior walls of a ground floor. It estimates the quantities of concrete hollow blocks (CHB) of different sizes, cement bags, sand and gravel required. For each of the 6 exterior walls, it determines the wall area, deducts any door and window areas, calculates the net CHB wall area and number of CHB blocks required after adding a 5% wastage factor. The totals will be used to request supplies for constructing the exterior walls.
Item to be Estimated CALCULATIONS Materials & Estimated Quantities Required
CHB CHB Cement (Sand) Gravel
(150mm) (100mm) (bags) (cu. m) (cu. m) Ground Floor Exterior Walls CHB for Wall 1 Area of wall = 4.90m x 2.70m =13.23 cu. m Less: (Door) 0.80m x 2.10m =1.68 cu. m (Window)0.50m x 0.80m = 0.40 cu. m Net CHB Wall Area= 11.15 cu. m No. CHB required =11.15 cu. m x 13=144.95 or 145 Add 5% Wastage Factor = 145 x 1.05= 152.25; say 153 pcs
CHB for Wall 2 Area of wall = 3.80m x 2.70m =10.26 cu. m
Less: (Window)1.00m x 1.20m = 1.20 cu. m Net CHB Wall Area= 9.06 cu. m No. CHB required = 9.06 cu. m x 13=117.78 or 118 Add 5% Wastage Factor = 118 x 1.05= 123.90; say 124 pcs
CHB for Wall 3 Area of wall = 0.85m x 2.70m =2.29 cu. m
Net CHB Wall Area= 2.29 cu. m No. CHB required = 2.29 cu. m x 13= 29.84 or 30 Add 5% Wastage Factor = 30 x 1.05= 31.5; say 32 pcs
CHB for Wall 4 Area of wall = 1.45m x 2.70m =3.92 cu. m
Net CHB Wall Area= 3.92 cu. m No. CHB required = 3.92 cu. m x 13=50.90 or 51 Add 5% Wastage Factor = 51 x 1.05= 53.55; say 54 pcs
CHB for Wall 5 Area of wall = 4.05m x 2.70m =10.94 cu. m
Less: (Door) 1.20m x 2.10m =2.52 cu. M (Window)1.20m x 1.60m = 1.92 cu. m Net CHB Wall Area= 6.50 cu. m No. CHB required =6.50 cu. m x 13=84.5 or 85 Add 5% Wastage Factor = 85 x 1.05= 89.25; say 89 pcs
CHB for Wall 6 Area of wall = 5.40m x 2.70m =14.58 cu. m
Less: (Window)1.00m x 1.20m = 1.20 cu. m (Window)0.60m x 0.50m = 0.30 cu. m (Window)0.50m x 0.80m = 0.40 cu. m