MASONRY WORKS

COMPUTATION SHEET

ITEM COMPUTATION CHB CEMENT SAND


6”THK 4”THK bags m3
CHB Depth= 0.45 m
From WALL Net Length= 2(4-0.4-0.2)+2[7-0.4(3)]+(4-
FOOTINGTOP 0.15)+(2.30-0.15-.05)= 24.35 m
to NGL
Net Area= (net length)(depth)
=(24.35)(0.45)
Net Area= 10.9575 m2

Use 6” THK CHB:


# of CHB= (net area)(12.5)
=10.9575(12.5)
# of CHB= 136.97 137

CHB Exterior Wall:


GROUND
FLOOR Net Area equals;
Area of Walln=(length-widthcolumn)(height-
depthbeam)
Less Window Openings(Wo)
Less Door Openings(Do)

Wall1+2=[14-6(0.40)](3-0.45)= 29.58
-Wo= 4(1.60x1.20)= -7.68
Wall 1+2= 21.90 m2

Wall3=[20-6(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)+2(1.0x0.6)= -8.88
Wall 3= 36 m2

Wall4=[16-5(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)= - 7.68
- Do= 2(0.90x1.20)= -3.78
Wall 4= 24.24 m2

Wall5=[14-6(0.40)](3-0.45)= 29.58
-Wo= 2(0.65x2.10)=-2.73
Wall 5= 26.85 m2

Total Wall Area=


21.90+36+24.24+26.85= 108.99 m2
Use 6” THK CHB:
# of CHB= (total wall area)(12.5)
=108.99(12.5)
# of CHB= 1362. 375 1363

Interior Wall:

Net Area equals;


Area of Walln=(length-widthcolumn)(height-
depthbeam)
Less Door Openings(Do)

Wall6=[14-6(0.40)](3-0.45)= 29.58
-Do= 4(0.80X2.10)= -6.72
Wall 6= 22. 86 m2

Wall7=[8-3(0.4)](3-0.45)= 17.34 m2

Wall8=[4-1(0.15)](3-0.40)= 10.01 m2

Wall9=[4-1(0.15)](3-0.40)= 5.46m2

Total Wall Area=


22.86+17.34+10.01+5.46= 55.67 m2

Use 4” THK CHB:


# of CHB= (total wall area)(12.5)
=(55.67) (12.5)
# of CHB= 695.88 696

CHB Exterior Wall:


SECOND
FLOOR Net Area equals;
(same as Area of Walln=(length-widthcolumn)(height-
Ground depthbeam)
Floor) Less Window Openings(Wo)
Less Door Openings(Do)

Wall1+2=[14-6(0.40)](3-0.45)= 29.58
-Wo= 4(1.60x1.20)= -7.68
Wall 1+2= 21.90 m2

Wall3=[20-6(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)+2(1.0x0.6)= -8.88
Wall 3= 36 m2

Wall4=[16-5(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)= - 7.68
- Do= 2(0.90x1.20)= -3.78
Wall 4= 24.24 m2

Wall5=[14-6(0.40)](3-0.45)= 29.58
-Wo= 2(0.65x2.10)=-2.73
Wall 5= 26.85 m2

Total Wall Area=


21.90+36+24.24+26.85= 108.99 m2

Use 6” THK CHB:


# of CHB= (total wall area)(12.5)
=108.99(12.5)
# of CHB= 1362. 375 1363

Interior Wall:

Net Area equals;


Area of Walln=(length-widthcolumn)(height-
depthbeam)
Less Door Openings(Do)

Wall6=[14-6(0.40)](3-0.45)= 29.58
-Do= 4(0.80X2.10)= -6.72
Wall 6= 22. 86 m2

Wall7=[8-3(0.4)](3-0.45)= 17.34 m2

Wall8=[4-1(0.15)](3-0.40)= 10.01 m2

Wall9=[4-1(0.15)](3-0.40)= 5.46m2

Total Wall Area=


22.86+17.34+10.01+5.46= 55.67 m2

Use 4” THK CHB:


# of CHB= (total wall area)(12.5)
=(55.67) (12.5)
# of CHB= 695.88 696

CHB Exterior Wall:


THIRD
FLOOR Net Area equals;
Area of Walln=(length-widthcolumn)(height-
depthbeam)
Less Window Openings(Wo)
Less Door Openings(Do)

Wall1+2=[14-6(0.40)](3-0.45)= 29.58
-Wo= 4(1.60x1.20)= -7.68
Wall 1+2= 21.90 m2

Wall3=[20-6(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)+2(1.0x0.6)= -8.88
Wall 3= 36 m2

Wall4=[16-5(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)= - 7.68
- Do= 2(0.90x1.20)= -3.78
Wall 4= 24.24 m2

Wall5=[14-6(0.40)](3-0.45)= 29.58
-Wo= 2(0.65x2.10)=-2.73
Wall 5= 26.85 m2

Total Wall Area=


21.90+36+24.24+26.85= 108.99 m2

Use 6” THK CHB:


# of CHB= (total wall area)(12.5)
=108.99(12.5)
# of CHB= 1362. 375 1363

Interior Wall:

Net Area equals;


Area of Walln=(length-widthcolumn)(height-
depthbeam)
Less Door Openings(Do)

Wall6=[14-6(0.40)](3-0.45)= 29.58
-Do= 4(0.80X2.10)= -6.72
Wall 6= 22. 86 m2

Wall7=[8-3(0.4)](3-0.45)= 17.34 m2

Wall8=[4-(0.15)](3)= 11.55 m2

Wall9=[2.30-.05-0.15](3)= 6.3 m2
Total Wall Area=
22.86+17.34+11.55+6.3= 58.05 m2

Use 4” THK CHB:


# of CHB= (total wall area)(12.5)
=(58.05) (12.5)
# of CHB= 725.63 726

TOTAL 4226 2118

CHB FILLER At Ground Floor:

Total # of CHB= 137+1363+696


=2196 pcs. CHB

Cell Vol./CHB=(0.05)(0.075)(0.2)(4)
=.003 m3

Total Cell Volume=(0.003)(2196)


=6.588 m3

Using” Class B” mixture:


Cement=6.588(12)=79.06 bags 79.5
Sand=6.588(1)= 6.59 m3 7

At Second Floor:

Total # of CHB=1363+696
=2059 pcs. CHB

Cell Vol./CHB=(0.05)(0.075)(0.2)(4)
=.003 m3

Total Cell Volume=(0.003)(2059)


=6.177 m3

Using” Class B” mixture:


Cement=6.177(12)=74.12 bags 74.5
Sand=6.177(1)= 6.18 m3 6.5
At Third Floor:

Total # of CHB=1363+726
=2089 pcs. CHB

Cell Vol./CHB=(0.05)(0.075)(0.2)(4)
=.003 m3

Total Cell Volume=(0.003)(2089)


=6.267 m3

Using” Class B” mixture:


Cement=6.267(12)= 75.20 bags 76
Sand=6.267(1)= 6.27 m3 6.5

TOTAL 230 20

CHB Binder Thickness= 12 mm


BINDER Width= 150 mm
From WALL Net Length= 24.35 m
FOOTINGTOP Height= 0.45 m
to NGL
# of layers=0.45÷0.20=2.25-1=2 layers

Volume=(width)(net length)(binder
thickness)(# of layers)
=(0.15)(24.35)(.012)(2)
V= 0.8766 m3

Using” Class B” mixture:


Cement=0.8766(12)= 10.52 bags 11
Sand=0.8766(1)= .88 m3 1

CHB Exterior wall(6” THK CHB)


BINDER Binder Thickness= 12 mm
Ground Floor Width= 150 mm
Net Length= 54.8 m
Height= 3-0.45= 2.55 m

# of layers= 2.55÷0.20= 12.75-1= 11.75=12


layers

Vbinder Wall=(width)(net length)(binder


thickness)(# of layers)
= (0.15)(54.8)(.012)(12)
Vbinder Wall= 1.1837 m3
Windows:
W1 : Length=12(1.60)=19.20 m
Layers= 1.2÷0.20= 6-1= 5 layers
W2: Length=2(1.0)= 2 m
Layers= 0.60÷0.20= 3-1= 2 layers

Vbinder W1=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(19.20)(.012)(5)
Vbinder W1= 0.1728 m3

Vbinder W2=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(2)(.012)(2)
Vbinder W2=0 .0072 m3

Doors:
D1: Length=2(0.90)= 1.8 m
Layers=2.1÷0.20= 10.5-1= 9.5=10 layers
D3: Length= 2(0.65)= 1.3 m
Layers= 2.1÷0.20= 10.5-1= 9.5=10 layers

Vbinder D1=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(1.8)(.012)(10)
Vbinder D1= 0.0324 m3

Vbinder D3=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(1.3)(.012)(10)
Vbinder D3= 0.0234 m3

Total Volume binder= Vbinder Wall-(Vbinder


Windows +Vbinder Doors)
=1.1837-0.1728-0.0072-0.0324-0.0234
Total Volume binder= 0.9479 m3

Using” Class B” mixture:


Cement=0.9479(12)= 11.37 bags 11.5
Sand=0.9479(1)= 0.95 m3 1

Interior wall(4” THK CHB)


Binder Thickness= 12 mm
Width= 100 mm
Net Length= 24.70 m
Height= 3-0.45= 2.55 m
# of layers= 2.55÷0.20= 12.75-1= 11.75=12
layers

Vbinder Wall=(width)(net length)(binder


thickness)(# of layers)
= (0.10)(24.70)(.012)(12)
Vbinder Wall= 0.3557 m3

Doors:
D2: Length=4(0.80)= 3.2 m
Layers=2.1÷0.20= 10.5-1= 9.5=10 layers

Vbinder D2=(width)(net length)(binder


thickness)(# of layers)
=(0.10)(3.2)(.012)(10)
Vbinder D2= 0.0384 m3

Total Volume binder= Vbinder Wall-Vbinder Doors


=0.3557-0.0384
Total Volume binder= 0.3173 m3

Using” Class B” mixture:


Cement=0.3173(12)= 3.81 bags 4
Sand=0.3173(1)= 0.32 m3 .5

CHB Exterior wall(6” THK CHB)


BINDER Binder Thickness= 12 mm
Second Floor Width= 150 mm
Net Length= 54.8 m
Height= 3-0.45= 2.55 m

# of layers= 2.55÷0.20= 12.75-1= 11.75=12


layers

Vbinder Wall=(width)(net length)(binder


thickness)(# of layers)
= (0.15)(54.8)(.012)(12)
Vbinder Wall= 1.1837 m3

Windows:
W1 : Length=12(1.60)=19.20 m
Layers= 1.2÷0.20= 6-1= 5 layers
W2: Length=2(1.0)= 2 m
Layers= 0.60÷0.20= 3-1= 2 layers

Vbinder W1=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(19.20)(.012)(5)
Vbinder W1= 0.1728 m3

Vbinder W2=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(2)(.012)(2)
Vbinder W2=0 .0072 m3

Doors:
D1: Length=2(0.90)= 1.8 m
Layers=2.1÷0.20= 10.5-1= 9.5=10 layers
D3: Length= 2(0.65)= 1.3 m
Layers= 2.1÷0.20= 10.5-1= 9.5=10 layers

Vbinder D1=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(1.8)(.012)(10)
Vbinder D1= 0.0324 m3

Vbinder D3=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(1.3)(.012)(10)
Vbinder D3= 0.0234 m3

Total Volume binder= Vbinder Wall-(Vbinder


Windows +Vbinder Doors)
=1.1837-0.1728-0.0072-0.0324-0.0234
Total Volume binder= 0.9479 m3

Using” Class B” mixture:


Cement=0.9479(12)= 11.37 bags 11.5
Sand=0.9479(1)= 0.95 m3 1

Interior wall(4” THK CHB)


Binder Thickness= 12 mm
Width= 100 mm
Net Length= 24.70 m
Height= 3-0.45= 2.55 m

# of layers= 2.55÷0.20= 12.75-1= 11.75=12


layers

Vbinder Wall=(width)(net length)(binder


thickness)(# of layers)
= (0.10)(24.70)(.012)(12)
Vbinder Wall= 0.3557 m3
Doors:
D2: Length=4(0.80)= 3.2 m
Layers=2.1÷0.20= 10.5-1= 9.5=10 layers

Vbinder D2=(width)(net length)(binder


thickness)(# of layers)
=(0.10)(3.2)(.012)(10)
Vbinder D2= 0.0384 m3

Total Volume binder= Vbinder Wall-Vbinder Doors


=0.3557-0.0384
Total Volume binder= 0.3173 m3

Using” Class B” mixture:


Cement=0.3173(12)= 3.81 bags 4
Sand=0.3173(1)= 0.32 m3 .5

CHB Exterior wall(6” THK CHB)


BINDER Binder Thickness= 12 mm
Third Floor Width= 150 mm
Net Length= 54.8 m
Height= 3-0.45= 2.55 m

# of layers= 2.55÷0.20= 12.75-1= 11.75=12


layers

Vbinder Wall=(width)(net length)(binder


thickness)(# of layers)
= (0.15)(54.8)(.012)(12)
Vbinder Wall= 1.1837 m3

Windows:
W1 : Length=12(1.60)=19.20 m
Layers= 1.2÷0.20= 6-1= 5 layers
W2: Length=2(1.0)= 2 m
Layers= 0.60÷0.20= 3-1= 2 layers

Vbinder W1=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(19.20)(.012)(5)
Vbinder W1= 0.1728 m3

Vbinder W2=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(2)(.012)(2)
Vbinder W2=0 .0072 m3
Doors:
D1: Length=2(0.90)= 1.8 m
Layers=2.1÷0.20= 10.5-1= 9.5=10 layers
D3: Length= 2(0.65)= 1.3 m
Layers= 2.1÷0.20= 10.5-1= 9.5=10 layers

Vbinder D1=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(1.8)(.012)(10)
Vbinder D1= 0.0324 m3

Vbinder D3=(width)(net length)(binder


thickness)(# of layers)
=(0.15)(1.3)(.012)(10)
Vbinder D3= 0.0234 m3

Total Volume binder= Vbinder Wall-(Vbinder


Windows +Vbinder Doors)
=1.1837-0.1728-0.0072-0.0324-0.0234
Total Volume binder= 0.9479 m3

Using” Class B” mixture:


Cement=0.9479(12)= 11.37 bags 11.5
Sand=0.9479(1)= 0.95 m3 1

Interior wall(4” THK CHB)


Binder Thickness= 12 mm
Width= 100 mm
Net Length= 24.70 m
Height= 3-0.45= 2.55 m

# of layers= 2.55÷0.20= 12.75-1= 11.75=12


layers

Vbinder Wall=(width)(net length)(binder


thickness)(# of layers)
= (0.10)(24.70)(.012)(12)
Vbinder Wall= 0.3557 m3

Doors:
D2: Length=4(0.80)= 3.2 m
Layers=2.1÷0.20= 10.5-1= 9.5=10 layers

Vbinder D2=(width)(net length)(binder


thickness)(# of layers)
=(0.10)(3.2)(.012)(10)
Vbinder D2= 0.0384 m3

Total Volume binder= Vbinder Wall-Vbinder Doors


=0.3557-0.0384
Total Volume binder= 0.3173 m3

Using” Class B” mixture:


Cement=0.3173(12)= 3.81 bags 4
Sand=0.3173(1)= 0.32 m3 .5
TOTAL 57.5 5.5

PLASTER Ground Floor:

Thickness of plaster= 12 mm on both sides


Area of exterior wall above FFL= 108. 99 m2
Area of interior wall above FFL= 55.67 m2
Area of column to be plastered= (3-0.45)
(30x0.4) = 30.60 m2
Area of beam to be plastered=(0.45)(54.8) =
24.66 m2

Total Area= (108.99+55.67+30.6+24.66)(2)


Total Area= 439.84 m2

Total volume = (total area)(thickness of


plaster)
=(439.84)(.012)
Total volume =5.2781 m3

Using “ Class B” mixture:


Cement=5.2781(12)= 63.34 bags 63.5
Sand= 5.2781(1)= 5.28 m3 5.5

Second Floor: (same as Ground Floor)

Thickness of plaster= 12 mm on both sides


Area of exterior wall above FFL= 108. 99 m2
Area of interior wall above FFL= 55.67 m2
Area of column to be plastered= (3-0.45)
(30x0.4) = 30.60 m2
Area of beam to be plastered=(0.45)(54.8) =
24.66 m2

Total Area= (108.99+55.67+30.6+24.66)(2)


Total Area= 439.84 m2
Total volume = (total area)(thickness of
plaster)
=(439.84)(.012)
Total volume =5.2781 m3

Using “ Class B” mixture:


Cement=5.2781(12)= 63.34 bags 63.5
Sand= 5.2781(1)= 5.28 m3 5.5

Third Floor:
Thickness of plaster= 12 mm on both sides
Area of exterior wall above FFL= 108. 99 m2
Area of interior wall above FFL= 58.05 m2
Area of column to be plastered= (3-0.45)
(30x0.4) = 30.60 m2
Area of beam to be plastered=(0.45)(54.8) =
24.66 m2

Total Area= (108.99+58.05+30.6+24.66)(2)


Total Area= 444.60 m2

Total volume = (total area)(thickness of


plaster)
=(444.6)(.012)
Total volume =5.3352 m3

Using “ Class B” mixture:


Cement=5.3352(12)= 64.02 bags 64.5
Sand= 5.3352(1)= 5.34 m3 5.5

TOTAL 191.5 16.5


SEPTIC Height= (2.20 -0.20)= 2 m
TANK CHB Net Length= [5(2)+2.5(3)+1.5]= 19 m
WALL
Net Area= (net length)(height)
=(19)(2)
Net Area= 38 m2

Use 4” THK CHB:


# of CHB= (net area)(12.5)
=(38)(12.5)
# of CHB= 475 pcs
475
SEPTIC Total # of CHB= 475
TANK CHB
FILLER Cell Vol./CHB=(0.05)(0.075)(0.2)(4)
=.003 m3

Total Cell Volume=(0.003)(475)


=1.425 m3

Using” Class B” mixture:


Cement=1.425(12)= 17.1 bags 17.5
Sand=1.425(1)= 1.425 m3 1.5

SEPTIC Binder Thickness= 12 mm


TANK CHB Width= 100 mm
BINDER Net Length= 19 m
Height= 3-0.45= 2 m

# of layers= 2.0÷0.20= 10-1= 9 layers

Volume=(width)(net length)(binder
thickness)(# of layers)
= (0.10)(19)(.012)(9)
Vbinder Wall= 0.2025 m3

Using” Class B” mixture:


Cement=0.2025(12)= 2.43 bags 2.5
Sand=0.2025(1)= 0.20 m3 .5

TOTAL 475 20 2

MASONRY WORKS
TOTAL 4226 2593 499 44
pcs pcs bags cu.
m.