COMPUTATION SHEET
Wall1+2=[14-6(0.40)](3-0.45)= 29.58
-Wo= 4(1.60x1.20)= -7.68
Wall 1+2= 21.90 m2
Wall3=[20-6(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)+2(1.0x0.6)= -8.88
Wall 3= 36 m2
Wall4=[16-5(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)= - 7.68
- Do= 2(0.90x1.20)= -3.78
Wall 4= 24.24 m2
Wall5=[14-6(0.40)](3-0.45)= 29.58
-Wo= 2(0.65x2.10)=-2.73
Wall 5= 26.85 m2
Interior Wall:
Wall6=[14-6(0.40)](3-0.45)= 29.58
-Do= 4(0.80X2.10)= -6.72
Wall 6= 22. 86 m2
Wall7=[8-3(0.4)](3-0.45)= 17.34 m2
Wall8=[4-1(0.15)](3-0.40)= 10.01 m2
Wall9=[4-1(0.15)](3-0.40)= 5.46m2
Wall1+2=[14-6(0.40)](3-0.45)= 29.58
-Wo= 4(1.60x1.20)= -7.68
Wall 1+2= 21.90 m2
Wall3=[20-6(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)+2(1.0x0.6)= -8.88
Wall 3= 36 m2
Wall4=[16-5(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)= - 7.68
- Do= 2(0.90x1.20)= -3.78
Wall 4= 24.24 m2
Wall5=[14-6(0.40)](3-0.45)= 29.58
-Wo= 2(0.65x2.10)=-2.73
Wall 5= 26.85 m2
Interior Wall:
Wall6=[14-6(0.40)](3-0.45)= 29.58
-Do= 4(0.80X2.10)= -6.72
Wall 6= 22. 86 m2
Wall7=[8-3(0.4)](3-0.45)= 17.34 m2
Wall8=[4-1(0.15)](3-0.40)= 10.01 m2
Wall9=[4-1(0.15)](3-0.40)= 5.46m2
Wall1+2=[14-6(0.40)](3-0.45)= 29.58
-Wo= 4(1.60x1.20)= -7.68
Wall 1+2= 21.90 m2
Wall3=[20-6(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)+2(1.0x0.6)= -8.88
Wall 3= 36 m2
Wall4=[16-5(0.40)](3-0.45)= 44.88
-Wo= 4(1.6 x 1.20)= - 7.68
- Do= 2(0.90x1.20)= -3.78
Wall 4= 24.24 m2
Wall5=[14-6(0.40)](3-0.45)= 29.58
-Wo= 2(0.65x2.10)=-2.73
Wall 5= 26.85 m2
Interior Wall:
Wall6=[14-6(0.40)](3-0.45)= 29.58
-Do= 4(0.80X2.10)= -6.72
Wall 6= 22. 86 m2
Wall7=[8-3(0.4)](3-0.45)= 17.34 m2
Wall8=[4-(0.15)](3)= 11.55 m2
Wall9=[2.30-.05-0.15](3)= 6.3 m2
Total Wall Area=
22.86+17.34+11.55+6.3= 58.05 m2
Cell Vol./CHB=(0.05)(0.075)(0.2)(4)
=.003 m3
At Second Floor:
Total # of CHB=1363+696
=2059 pcs. CHB
Cell Vol./CHB=(0.05)(0.075)(0.2)(4)
=.003 m3
Total # of CHB=1363+726
=2089 pcs. CHB
Cell Vol./CHB=(0.05)(0.075)(0.2)(4)
=.003 m3
TOTAL 230 20
Volume=(width)(net length)(binder
thickness)(# of layers)
=(0.15)(24.35)(.012)(2)
V= 0.8766 m3
Doors:
D1: Length=2(0.90)= 1.8 m
Layers=2.1÷0.20= 10.5-1= 9.5=10 layers
D3: Length= 2(0.65)= 1.3 m
Layers= 2.1÷0.20= 10.5-1= 9.5=10 layers
Doors:
D2: Length=4(0.80)= 3.2 m
Layers=2.1÷0.20= 10.5-1= 9.5=10 layers
Windows:
W1 : Length=12(1.60)=19.20 m
Layers= 1.2÷0.20= 6-1= 5 layers
W2: Length=2(1.0)= 2 m
Layers= 0.60÷0.20= 3-1= 2 layers
Doors:
D1: Length=2(0.90)= 1.8 m
Layers=2.1÷0.20= 10.5-1= 9.5=10 layers
D3: Length= 2(0.65)= 1.3 m
Layers= 2.1÷0.20= 10.5-1= 9.5=10 layers
Windows:
W1 : Length=12(1.60)=19.20 m
Layers= 1.2÷0.20= 6-1= 5 layers
W2: Length=2(1.0)= 2 m
Layers= 0.60÷0.20= 3-1= 2 layers
Doors:
D2: Length=4(0.80)= 3.2 m
Layers=2.1÷0.20= 10.5-1= 9.5=10 layers
Third Floor:
Thickness of plaster= 12 mm on both sides
Area of exterior wall above FFL= 108. 99 m2
Area of interior wall above FFL= 58.05 m2
Area of column to be plastered= (3-0.45)
(30x0.4) = 30.60 m2
Area of beam to be plastered=(0.45)(54.8) =
24.66 m2
Volume=(width)(net length)(binder
thickness)(# of layers)
= (0.10)(19)(.012)(9)
Vbinder Wall= 0.2025 m3
TOTAL 475 20 2
MASONRY WORKS
TOTAL 4226 2593 499 44
pcs pcs bags cu.
m.