You are on page 1of 7

CONCRETE WORKS

COMPUTATION SHEET

ITEM COMPUTATION CEMENT SAND GRAVEL


40 m³ m³
kg/bag
COLUMN Length= 1.8 m
FOOTING Width= 1.8 m
Thickness= 0.40 m
No. of column footings= 24
Plus 10% wastage= 1.10

V=(length)(width)(thickness)(#CF)(wastage)
=(1.8)(1.8)(0.4)(24)(1.10)
V= 34.2144 m³

Using “Class A” mixture:


Cement= 34.2144(9)= 307.93 bags 308
Sand= 34.2144(.5)= 17.11 m³ 17.50
Gravel= 34.2144(1)= 34.21 m³ 34.50

TOTAL 308 17.50 34.50

COLUMN Length= 0.40 m


Width= 0.40 m
Height= (1.50-0.40)+0.15+.05+9= 10.3 m
No. of columns= 24
Plus 5% wastage= 1.05

V=(length)(width)(height)(#columns)(wastage)
=(0.40)(0.40)(10.3)(24)(1.05)
V= 41.5296 m³

Using “Class A” mixture:


Cement= 41.5296(9)= 373.77 bags 374
Sand= 41.5296(.5)= 20.76 m³ 21
Gravel= 41.5296(1)= 41.53 m³ 42

TOTAL 374 21 42

TIE BEAM Height= 0.40 m


Width= 0.25 m
Net length= [(20)(3)-(0.40)(6)(3)]+[(7)(4)- (0.40)
(3)(4)]+[(2)(2)-(0.20)(2)] = 79.60 m
Plus 5% wastage= 1.05

V= (height)(width)(net length)(wastage)
=(0.40)(0.25)((79.60)(1.05)
V= 8.358 m³

Using “Class A” mixture:


Cement= 8.358(9)= 75.22 bags 75.5
Sand= 8.358(.5)= 4.18 m³ 4.5
Gravel= 8.358(1)= 8.36 m³ 8.5

TOTAL 75.5 4.5 8.5

WALL Width= 0.40 m


FOOTING Depth= 0.25 m
Net Length= [(4)(2)-(0.40)(3)]+[(7)(2)-(0.40)(6)]
+4+2.30= 24.70 m
Plus 5% wastage= 1.05

V= (width)(depth)(net length)(wastage)
=(0.40)(0.25)(24.70)(1.05)
V=2.5935 m³

Using “Class B” mixture:


Cement= 2.5935(7.5)= 19.45 bags
Sand= 2.5935(.5)= 1.30 m³ 19.5
Gravel= 2.5935(1)= 2.59 m³ 1.5
3

TOTAL 19.5 1.5 3

BEAM At Second Floor:

FB -1: Width= 0.30m Depth= 0.45m


FB-2: Width= 0.20m Depth= 0.45m
CB-1: Width= 0.30m Depth= 0.45m
SB-1: Width= 0.20m Depth= 0.40m
Plus 5% wastage

Vn=(width)(depth)(net length)(# of beams)

FB-1: V1=(0.30)(0.45)(3.60)(14)= 6.804


V2=(0.30)(0.45)(3.10)(12)= 5.022
FB-2: V3=(0.20)(0.45)(3.60)(5)= 1.62
CB-1: V4=(0.30)(0.45)(1.60)(6)= 1.296
SB-1: V5=(0.20)(0.40)(3.80)(1)= 0.304
V6=(0.20)(0.40)(2.10)(1)= 0.168
V= 15.214 m³

VT=(volume)(wastage)
=(15.214)(1.05)
VT=15.9747 m³

Using “Class A” mixture:


Cement=15.9747(9)= 143.77 bags 144
Sand= 15.9747(.5)= 7.99 m³ 8
Gravel= 15.9747(1)= 15.97 m³ 16

At Third Floor (same as Second Floor):

V= 15.214 m³

VT=(volume)(wastage)
=(15.214)(1.05)
VT=15.9747 m³

Using “Class A” mixture:


Cement=15.9747(9)= 143.77 bags 144
Sand= 15.9747(.5)= 7.99 m³ 8
Gravel= 15.9747(1)= 15.97 m³ 16

At Roof Deck:

FB -1: Width= 0.30m Depth= 0.45m


FB-2: Width= 0.20m Depth= 0.45m
CB-1: Width= 0.30m Depth= 0.45m
Plus 5% wastage

Vn=(width)(depth)(net length)(# of beams)

FB-1: V1=(0.30)(0.45)(3.60)(15)= 7.29


V2=(0.30)(0.45)(3.10)(12)= 5.022
FB-2: V3=(0.20)(0.45)(3.60)(5)= 1.62
CB-1: V4=(0.30)(0.45)(1.60)(6)= 1.296
V= 15.228 m³

VT=(volume)(wastage)
=(15.228)(1.05)
VT=15.9894 m³

Using “Class A” mixture:


Cement=15.9894(9)= 143.90 bags 144
Sand=15.9894(.5)= 7.99 m³ 8
Gravel=15.9894(1)= 15.99 m³ 16

TOTAL 432 24 48
GROUND Length= 20 m
FLOOR Width= 9 m
SLAB Thickness= 0.15 m
Less Area of Interior columns= (0.40)(0.40)(8)
= 1.28 m2
Plus 10% wastage= 1.10

V=[(length)(width)-(area of interior columns)]


(thickness)(wastage)
= [(20)(9)-1.28](0.15)(1.10)
V= 29.4888 m³

Using “Class C” mixture:


Cement=29.4888(6)= 176.93 bags 177
Sand=29.4888(.5)= 14.74 m³ 15
Gravel=29.4888 (1)= 29.49 m³ 29.5

SECOND Slab thickness: Main Area=0.15 m


FLOOR Toilet & Bath= 0.10 m
SLAB Less Wall thickness= 0.15 m
Plus 5% wastage= 1.05

V1= (3.70)(3.70)(0.15)(4)= 8.214


V2= (3.70)(6.70)(0.15)(2)= 7.437
V3= (20)(1.85)(0.15)= 5.55
V4= (1.20)(3.85)(0.15)= 0.693
V5= (1.85)(2.15)(0.10)(2)= 0.7955
V= 22.6895 m³

VT=(volume)(wastage)
=(22.6895)(1.05)
VT= 23.8240 m³

Using “Class A” mixture:


Cement=23.8240(9)= 214.42 bags 214.5
Sand=23.8240(.5)= 11.91 m³ 12
Gravel=23.8240(1)= 23.82 m³ 24

THIRD Slab thickness: Main Area=0.15 m


FLOOR Toilet & Bath= 0.10 m
SLAB Less Wall thickness= 0.15 m
(same as Plus 5% wastage= 1.05
Second
Floor Slab) V= 22.6895 m³

VT=(volume)(wastage)
=(22.6895)(1.05)
VT= 23.8240 m³

Using “Class A” mixture:


Cement=23.8240(9)= 214.42 bags 214.5
Sand=23.8240(.5)= 11.91 m³ 12
Gravel=23.8240(1)= 23.82 m³ 24

ROOF Length= 20 m
DECK Width= 9 m
SLAB Thickness= 0.15 m
Less Area of Interior columns= (0.40)(0.40)(8)
= 1.28 m2
Plus 5% wastage= 1.05

V=[(length)(width)-(area of interior columns)]


(thickness)(wastage)
= [(20)(9)-1.28](0.15)(1.05)
V= 28.1484 m³

Using “Class A” mixture:


Cement= 28.1484(9)= 253.34 bags 254
Sand=28.1484(.5)= 12.07m³ 12.5
Gravel=28.1484 (1)= 28.15 m³ 28.5

TOTAL 860 51.5 106


STAIR Widthlanding= 1.20 m
Lengthlanding= 3.70 m
Thicknesslanding= 0.15 m
No. of Landing= 2

Widthstair= 1.85 m
Lengthstair= 3.85 m
Thicknessstair= 0.15 m
Plus 5% wastage= 1.05

Vlanding = (1.20)(3.85)(0.15)(2)= 1.386


Vstairs = (1.85)(3.10)(0.15)(4)= 3.441
V= 4.827 m³

VT= (volume)(wastage)
=(4.827)(1.05)
VT= 5.0684 m³

Using “Class A” mixture:


Cement= 5.0684(9)= 45.62 bags 46
Sand=5.0684(.5)= 2.53 m³ 3
Gravel=5.0684(1)= 5.07 m³ 5.5

TOTAL 46 3 5.5
SEPTIC Length= 5 m
TANK Width= 2.5 m
VAULT Thickness= 0.125 m
COVER Plus 5% wastage= 1.05

V=(length)(width)(thickness)(wastage)
=(5)(2.5)(0.125)(1.05)
V=1.6406 m³

Using “Class A” mixture:


Cement=1.6406(9)= 14.77 bags 15
Sand=1.6406(.5)= 0.82 m³ 1
Gravel= 1.6406(1)= 1.64 m³ 2

SEPTIC Length= [3.50-2(0.40)]= 2.7 m


TANK Width= 2.50 m
VAULT Thickness= 0.1 m
COVER Plus 10% wastage= 1.10

V=(length)(width)(thickness)(wastage)
=(2.7)(2.5)(0.10)(1.10)
V= 0.7425 m³

Using “Class A” mixture:


Cement=0.7425(9)= 6.68 bags 7
Sand=0.7425(.5)= 0.37 m³ .5
Gravel=0.7425(1)= 0.74 m³ 1

SEPTIC Length= 17.5 m


TANK Width= 0.40 m
FOOTING Thickness= 0.20 m
Plus 10% wastage= 1.10

V=(length)(width)(thickness)(wastage)
=(17.5)(0.40)(0.20)(1.10)
V= 1.54 m³

Using “Class A” mixture:


Cement= 1.54(9)= 13.86 bags 13
Sand= 1.54(.5)= 0.77 m³ 1
Gravel= 1.54(1)= 1.54 m 2
TOTAL 35 2.5 5

CONCRETE WORKS
TOTAL 2150 125.5 252.5
bags cu. m. cu. m.

You might also like