COMPUTATION SHEET
V=(length)(width)(thickness)(#CF)(wastage)
=(1.8)(1.8)(0.4)(24)(1.10)
V= 34.2144 m³
V=(length)(width)(height)(#columns)(wastage)
=(0.40)(0.40)(10.3)(24)(1.05)
V= 41.5296 m³
TOTAL 374 21 42
V= (height)(width)(net length)(wastage)
=(0.40)(0.25)((79.60)(1.05)
V= 8.358 m³
V= (width)(depth)(net length)(wastage)
=(0.40)(0.25)(24.70)(1.05)
V=2.5935 m³
VT=(volume)(wastage)
=(15.214)(1.05)
VT=15.9747 m³
V= 15.214 m³
VT=(volume)(wastage)
=(15.214)(1.05)
VT=15.9747 m³
At Roof Deck:
VT=(volume)(wastage)
=(15.228)(1.05)
VT=15.9894 m³
TOTAL 432 24 48
GROUND Length= 20 m
FLOOR Width= 9 m
SLAB Thickness= 0.15 m
Less Area of Interior columns= (0.40)(0.40)(8)
= 1.28 m2
Plus 10% wastage= 1.10
VT=(volume)(wastage)
=(22.6895)(1.05)
VT= 23.8240 m³
VT=(volume)(wastage)
=(22.6895)(1.05)
VT= 23.8240 m³
ROOF Length= 20 m
DECK Width= 9 m
SLAB Thickness= 0.15 m
Less Area of Interior columns= (0.40)(0.40)(8)
= 1.28 m2
Plus 5% wastage= 1.05
Widthstair= 1.85 m
Lengthstair= 3.85 m
Thicknessstair= 0.15 m
Plus 5% wastage= 1.05
VT= (volume)(wastage)
=(4.827)(1.05)
VT= 5.0684 m³
TOTAL 46 3 5.5
SEPTIC Length= 5 m
TANK Width= 2.5 m
VAULT Thickness= 0.125 m
COVER Plus 5% wastage= 1.05
V=(length)(width)(thickness)(wastage)
=(5)(2.5)(0.125)(1.05)
V=1.6406 m³
V=(length)(width)(thickness)(wastage)
=(2.7)(2.5)(0.10)(1.10)
V= 0.7425 m³
V=(length)(width)(thickness)(wastage)
=(17.5)(0.40)(0.20)(1.10)
V= 1.54 m³
CONCRETE WORKS
TOTAL 2150 125.5 252.5
bags cu. m. cu. m.