1. Pekerjaan beton bertulang
e. Ring Balk
V = b x h xp
= (0.15 x 0.20 x 50.5)
= 1,515 𝑚3
WC =hxp
= 1.50 x 7.1
= 10.65 𝑚2
b. Pasangan dinding bata merah 1 : 5
V = (h x p) - ∑ 𝐿𝑝 - ∑ 𝐿𝑗
= (3.40 m x 49.7 m) – 5.544𝑚2 – 5.0025 𝑚2
= 168.98 – 5.544𝑚2 – 5.0025 𝑚2
= 158.43 𝑚2
6. Pekerjaan plafon
a. Kusen Kayu
P2 = (b x h) x p
= (0.05 x 0.15) x (5.25)
= 0.0393 m3
= 0.0393 𝑚3 x ∑ 𝑝 (𝐽𝑢𝑚𝑙𝑎ℎ 𝑃𝑖𝑛𝑡𝑢 𝑃1) = 0.0393 x 3
= 0.1181 𝑚3
P3 = (b x h) x p
= (0.05 x 0.15) x (1,75 + 1,75 + 0,6)
= 0.0075 x 4,1
= 0.030 𝑚3 x ∑ 𝑝 (𝐽𝑢𝑚𝑙𝑎ℎ 𝑃𝑖𝑛𝑡𝑢 𝑃3) = 0.030 x 1
= 0.030 𝑚3
J1 = (b x h) x p
= (0.05 x 0.015) x (1.45 + 1.45 + 0,65 + 0,65)
= 0,0075 x 4.2
= 0.0315 𝑚3 x ∑ 𝐽1 (𝐽𝑢𝑚𝑙𝑎ℎ 𝐽1) = 0.0315 x 1
= 0.0315 𝑚3
J2 = (b x h) x p
= (0.05 x 0.15) x (1.40 + 1.40 + 1.45(3))
= 0.0075 x 7.35
= 0.053 𝑚3 x ∑ 𝐽2 (𝐽𝑢𝑚𝑙𝑎ℎ 𝐽2) = 0.053 x 2
= 0.106 𝑚3
Daun Jendela
V = ∑ 𝐾𝑝 = 4 set
- Grendel jendela
V = (∑ 𝑗 x 1) = 3 x 1 = 3 bh
e. Tarikan jendela
V = (∑ 𝑗 x 1) = 3 x 1 = 3 bh
f. Kaca polos
V = (l x h x ∑ 𝐽1 ) + (l x h x ∑ 𝐽2 )
= (0.48 x 1.2 x 1) + (0.96 x 1.2 x 2 )
= 0.576 + 2.304
= 2.88 𝑚2
9. Pekerjaan PLAT
V = ∑ 𝐿 x Tebal
= 32.55 𝑚2 x 0.12 m
= 3.906 𝑚3
b. Penutup Atap
L =pxl
= 9,85 m x 5 m
= 49,25 𝑚2
Perhitungan Volume Lantai 1 & 2
1. Pekerjaan Sanitair
a. Kloset jongkok = 1 buah
b. Kloset Duduk = 1 buah
c. Kran = 6 buah
d. Floor drain = 2 buah
e. Kitchen Zink = 1 buah
f. Shower = 2 buah
∑ 𝑽𝒐𝒍𝒖𝒎𝒆 = 609,41 𝒎𝟐
b. Pengecatan plafon
∑ 𝑙𝑝 = LT. 1 = gypsum = 60,45 𝑚2
= LT.2 = gypsum = 32.55 𝑚2
∑ 𝑽𝒐𝒍𝒖𝒎𝒆 = 93 𝒎𝟐
Rab perencanaan
Rekap, manmonth, biaya langsung
dan tidak langsung, schedule, kurva
Hitungan praktis
BKF dan biaya perencanaan
Gambar kerja
Rumah 2 lantai