You are on page 1of 4

The APPEA Journal 2020, 000, 000–000

Extended abstract
https://doi.org/10.1071/AJ19023

Progressive cavity pump tubing drain valves: operator-


savings illustration

Peter Mark Smith

Baker Hughes, 2 Benoi Road, 629876 Singapore. Email: PeterMark.Smith@bakerhughes.com

Abstract. Three case studies show how three progressive cavity pump (PCP) operators used Zenith® (Baker
Hughes) tubing drain valves to protect problematic PCPs from blockage and damage, reducing downtime and
avoiding cost of backflush operations. The efficient solids management system incorporated in the Zenith PCP tubing
drain valve (PCP-TDV) reliably safeguards pumping equipment from damage or blockage caused by descending
solids when the pump is shut down, eliminating unplanned downtime and costly equipment replacement. Addressing
the failings of alternative valves, the Zenith PCP-TDV effectively reduces the requirement for well workover,
preventing pump-off, increasing uptime and lift system run-life, even in heavy oil and high viscosity fluid operations.
The Zenith PCP-TDV provides an innovative solution to costly pump damage, while preventing recirculation and
simplifying backflush operations. The addition of backflush capability is designed to allow the pump rotor to be
retracted and reset without running out of hole. A further addition specific to the coal seam gas market is the inclusion
of a tubing pressure-activated, single-use locking piston, so as to allow external pressure to be subjected to the
PCP-TDV without pumping being open, thus allowing the string to be set with no well fluid ingress into the
production string and pump before operation.

Keywords: backflush, CBM, coal seam gas, downtime, PCP optimisation, PCP-TDV, pump damage, sand, solids, well
fluid ingress.

Accepted 24 February 2020, published online dd mmm yyyy

Introduction Figure 1 shows a cut-away drawing of a PCP-TDV. Figure 2


shows a diagram of the operational sequences of a PCP-TDV.
The progressive cavity pump tubing drain valve (PCP-TDV)
is a tubing-mounted downhole tool installed as part of a Case study 1
PCP completion. The PCP-TDV protects the pump from sand Introduction
and debris settlement and prevents rod torque-off situations
by diverting fluid and entrained solids from the production A Latin American operator who was operating 14 PCPs was
tubing to the annulus when flow to surface stops (i.e. when experiencing problems caused by solids blockage and
the pump stops rotating or fluid production ceases). The PCP- subsequent pump damage. The effect of this untreated
TDV with backflush capability is designed to allow the pump situation was an increase in downtime and backflush costs.
rotor to be retracted and reset without running out of hole. The installation of the Zenith PCP-TDV in these 14 wells was
In addition, outer connections that form part of the tool are shown to improve the economics of the well operation through
locked together with locking plates to prevent back-off and the reduction of production downtime and reduction of cost of
allow reverse torque. The design has a maximised bore- backflush operations.
through tool to allow a larger range of stators and, specific for
coal bed methane wells, an inclusion of a tubing pressure- Study data
activated, single-use, locking piston to allow external pressure Refer to Table 1 for the cost of PCP backflushing for 14 wells.
to be subjected to the PCP-TDV without pumping being open. Refer to Table 2 for the cost of lost or deferred production owing
The Zenith PCP-TDV is available in 2 7/800 and 3 1/200 sizes. to shut in pumps because of damage.

Journal compilation Ó APPEA 2020 CSIRO PUBLISHING www.publish.csiro.au/journals/appea


B The APPEA Journal P. M. Smith

Fig. 1. Progressive cavity pump tubing drain valve (PCP-TDV) cut-away drawing.

Pump on Pump shut down


The valve is installed Valve immediately shuts
above the pump stator off flow path through the
allowing passage of well pump, opening annular
fluids upward through ports to divert fluid column
production tubing to from upper tubing into
surface. annulus along with any
solids.

!
!

Backflush Natural flow


Retract rotor to clear the Retract rotor to clear the
stator then flush fluids and stator allowing natural flow
chemicals down tubing through stator and tubing
through stator. to surface.
On completion of To return to artificial lift
backflush, run rotor back operation, run rotor back
to depth. Pump operation to depth.
can recommence.

Fig. 2. Progressive cavity pump tubing drain valve (PCP-TDV) operation sequence drawing.

Results and conclusions which is an average cost saving of US$43 409 per well. This
cost does not include the cost of installing PCP-TDVs.
Table 1 shows a total cost of US$219 018 for backflush
There are additional savings from
activity. This is an average cost per well per year of
US$15 644. (1) extended pump run-life, saving on equipment replacement
Table 2 shows a total cost of US$388 710 in deferred oil costs,
production (@ US$50/BBL). This is an average cost per well of (2) reduced intervention, saving on manpower and human error
US$27 750. costs, and
The total estimated cost savings in the reduction of both (3) reduced risk, saving on environmental health and safety
backflush activity and deferred oil production are US$607 728, expense owing to less intervention.
PCP-tubing drain valves: operator-savings illustration The APPEA Journal C

Table 1. Cost of pump backflushing Table 2. Lost production


The cost of backflush operations required to repair or clean pumps that The cost of lost production owing to pumps that are shut in. BBL, barrel;
are blocked because of solids BOPD, barrels of oil per day; PCP, progressive cavity pump

Well ID Flushes per Cost per Cost per Well ID BOPD Oil production Lost US$ per
month (avg) flush (US$) year (US$) lost per year due year @ US$50/BBL
to PCP shutdown
Well 1 1.11 2500 33 333
Well 1 163 2176 108 800
Well 2 0.71 2500 21 260
Well 2 148 1260 63 014
Well 3 1.07 2500 31 953
Well 3 58 736 36 809
Well 4 1.23 2500 36 986
Well 4 29 431 21 526
Well 5 0.94 2500 28 125
Well 5 53 591 29 531
Well 6 0.63 2500 19 014
Well 6 74 559 27 951
Well 7 0.45 2500 13 636
Well 7 110 601 30 027
Well 8 0.22 2500 6691
Well 8 191 512 25 615
Well 9 0.13 2500 3965
Well 9 194 307 15 344
Well 10 0.24 2500 7297
Well 10 55 160 8012
Well 11 0.23 2500 6818
Well 11 46 124 6218
Well 12 0.23 2500 6835
Well 12 43 117 5865
Well 13 0.09 2500 2628
Well 13 167 176 8782
Well 14 0.02 2500 477
Well 14 128 24 1216
Total 35 000 219 018
Total 1459 7774 388 710

Case study 2 Case study 3


Introduction Introduction
A second Latin American operator who was operating PCPs An Indonesian pump supplier running PCPs was experiencing
was experiencing short run life caused by solids blockage very short run life caused by sand falling into the pumps when the
resulting in broken rods. The installation of the Zenith PCP- pumps were shut in. The installation of the Zenith PCP-TDV in
TDV in these three wells was shown to improve the run time of the first trial well has proven successful.
the PCPs. In addition, the number of flush interventions was
reduced. Study data
One PCP-TDV was installed.
Study data Well install date, pump run time (3 February 2020) and
expected pump run time were as follows:
Three PCP-TDVs were installed, one was pulled after 170 days
(A) 1 April 2019, 308 days, 180 days
because of a failure where the PCP-TDV disassembled
because of torque and a failed bottom swivel. Changes were
made to the PCP-TDV design to prevent this occurring in the Results and conclusions
future. The PCP-TDV extended the life of the PCP in the trial well and
Well install date, pump run time (3 February 2020) and the trial continues. The pump supplier categorically states that the
expected run time were as follows: life of the PCP has been extended and the trial to be a success,
(A) 1 December 2017, 794 days, 120 days even with a short run time to date.
(B) 22 December 2017, 773 days, 120 days
(C) not known, 170 days, 120 days Conflicts of interest
No conflicts of interest exist.
Results and conclusions
The PCP-TDV extended the life of the PCPs to at least Acknowledgements
twice that expected for two of the three wells and by The author acknowledges the support of his colleagues at Baker Hughes in
50% in the third well. These represent savings of two preparation of this paper. No funding was provided specifically for this paper;
work-overs per year, plus a significant reduction in flush however; development of the PCP-TDV valve was funded by Zenith, a
interventions. subsidiary of Baker Hughes.
D The APPEA Journal P. M. Smith

The author

Peter Mark Smith holds a Bachelor of Business (Ag) from Curtin University, and a Master of Engineering
(Oil and Gas) from UWA. Peter is employed by Baker Hughes as a Sales Manager for Zenith Sensors and
Artificial Lift Equipment for AsiaPac and India. Peter’s previous experience includes product line manager
for wellheads, rod lift systems and flow measurement products. Peter is an author of two patents, a member
of SPE and a founding member of the Global Society of Peace Engineers.

www.publish.csiro.au/journals/aj

You might also like