B2.10: Unknown services 50,000.00 100% 50,000.00 50,000.00 0.00
B2.12: Inspection nearby properties 50,000.00 100% 50,000.00 50,000.00 0.00
B3.1: Management of works 100,000.00 35% 35,000.00 30,000.00 5,000.00
B3.2: Programming of works 100,000.00 60% 60,000.00 60,000.00 0.00
B4.1: Samples of materials 100,000.00 35% 35,000.00 30,000.00 5,000.00
B4.2: Samples of workmanship 100,000.00 35% 35,000.00 30,000.00 5,000.00
B5.2: Enclosure of works 50,000.00 100% 50,000.00 50,000.00 0.00
B5.6: Special scaffolding 100,000.00 100% 100,000.00 10,000.00 90,000.00
All other scaffolding 50,000.00 35% 17,500.00 15,000.00 2,500.00
B5.9: Office of clerk of works 100,000.00 90% 90,000.00 90,000.00 0.00
B6.1: Water 50,000.00 35% 17,500.00 15,000.00 2,500.00
B6.2: Electricity and lighting 50,000.00 35% 17,500.00 15,000.00 2,500.00
B6.3: Telephone and facsmile 50,000.00 35% 17,500.00 15,000.00 2,500.00
B6.3: Foreman's cell phone 50,000.00 35% 17,500.00 15,000.00 2,500.00
B7.2: Delivery & fixing PC items 150,000.00 0% 0.00 0.00 0.00
B7.3: Sub-contract Agreements 50,000.00 100% 50,000.00 50,000.00 0.00
B7.5: Fuel, power & water for mechanical Wks 100,000.00 0% 0.00 0.00 0.00
B9.4: Site security 200,000.00 35% 70,000.00 60,000.00 10,000.00
C1.14: Temporary access to site 100,000.00 90% 90,000.00 90,000.00 0.00
C1.16: Test and HO specialist installation 200,000.00 0% 0.00 0.00 0.00
C1.17: Drawings and dimensions 200,000.00 80% 160,000.00 160,000.00 0.00
2,000,000.00 48% 962,500.00 835,000.00 127,500.00
GUARD HOUSE
Substructure (Provisional) 23,901.00 103% 24,728.00 24,728.00 0.00
Concrete, Formwork & Reinforcement 8,558.20 100% 8,558.16 8,558.16 0.00
Precast Concrete 6,872.00 6% 400.00 400.00 0.00
Masonry 16,711.00 90% 15,111.00 15,111.00 0.00
Waterproofing 451.00 100% 451.00 136.00 315.00
Roof Covering 3,280.00 100% 3,280.00 2,775.00 505.00
Carpentry and Joinery 9,750.00 123% 12,000.00 12,000.00 0.00
Ceiling, Partitions and Access Flooring 2,720.00 0% 0.00 0.00 0.00
Ironmongery 4,127.00 0% 0.00 0.00 0.00
Metalwork 9,535.58 11% 1,050.00 1,050.00 0.00
Plastering 3,725.00 99% 3,685.00 3,685.00 0.00
Tiling 2,585.00 0% 0.00 0.00 0.00
Plumbing (Provisional) 10,160.00 0% 0.00 0.00 0.00
Glazing 600.00 0% 0.00 0.00 0.00
Painting 3,018.00 14% 425.00 0.00 425.00
Sub-total 3 105,993.78 66% 69,688.16 68,443.16 1,245.00
EXTERNAL WORKS
Site Clearance 574,145.00 67% 381,975.00 381,975.00 0.00
Soil Drainage 83,950.00 0% 0.00 0.00 0.00
Water Supply and Fire Reticulation 45,130.00 0% 0.00 0.00 0.00
Internal Roads and Parking 651,976.00 100% 0.00 0.00 0.00
Palisade Fencing 593,739.00 100% 293,298.50 287,448.50 5,850.00
Stormwater Drainage 344,407.00 100% 0.00 0.00 0.00
Water Tanks Stands 54,060.00 100% 0.00 0.00 0.00
Variations
14,695.90 14,695.90 0.00
Sub-total 13 0.00 0% 14,695.90 14,695.90 0.00