REBARS

Labor Cost = Total No. of Days x Rate per Day


Rate
Floor Structure Total No. of Days Labor Cost
per day
Column 62.997 = 63 600.00 ₱ 37,800.00
2F Beam 21.387 = 22 600.00 ₱ 13,200.00
Slab 37.1462 = 38 600.00 ₱ 22,800.00
Subtotal ₱ 73,800.00
Column 62.997 = 63 600.00 ₱ 37,800.00
3F Beam 21.387 = 22 600.00 ₱ 13,200.00
Slab 37.1462 = 38 600.00 ₱ 22,800.00
Subtotal ₱ 73,800.00
Column 62.997 = 63 600.00 ₱ 37,800.00
4F Beam 21.387 = 22 600.00 ₱ 13,200.00
Slab 37.1462 = 38 600.00 ₱ 22,800.00
Subtotal ₱ 73,800.00
Column 62.997 = 63 600.00 ₱ 37,800.00
5F Beam 21.387 = 22 600.00 ₱ 13,200.00
Slab 37.1462 = 38 600.00 ₱ 22,800.00
Subtotal ₱ 73,800.00
Column 62.997 = 63 600.00 ₱ 37,800.00
RD Beam 21.387 = 22 600.00 ₱ 13,200.00
Slab 37.1462 = 38 600.00 ₱ 22,800.00
Subtotal ₱ 73,800.00
TOTAL ₱ 369,000.00

FORMWORKS
a.) Labor Cost = No. of Manpower x Rate x Duration

Area No. of Rate Duration


Floor Labor Cost
(sq.m.) Manpower per day (days)

2F 331.9 33 600.00 6 ₱ 118,800.00


3F 331.9 33 600.00 6 ₱ 118,800.00
4F 331.9 33 600.00 6 ₱ 118,800.00
5F 331.9 33 600.00 6 ₱ 118,800.00
RD 331.9 33 600.00 6 ₱ 118,800.00
TOTAL ₱ 594,000.00
CHB WALL
a.) Labor Cost = No. of Manpower x Rate x Duration
Rate Duration
Floor Activity Manpower No. of Manpower Labor Cost
per day (days)
Mason 12 600.00 5 ₱ 36,000.00
CHB Laying
Helper 3 500.00 5 ₱ 7,500.00
2F
Mason 21 600.00 6 ₱ 75,600.00
Plastering
Helper 3 500.00 6 ₱ 9,000.00
Subtotal 11 ₱ 128,100.00
Mason 12 600.00 5 ₱ 36,000.00
CHB Laying
Helper 3 500.00 5 ₱ 7,500.00
3F
Mason 21 600.00 6 ₱ 75,600.00
Plastering
Helper 3 500.00 6 ₱ 9,000.00
Subtotal 11 ₱ 128,100.00
Mason 12 600.00 5 ₱ 36,000.00
CHB Laying
Helper 3 500.00 5 ₱ 7,500.00
4F
Mason 21 600.00 6 ₱ 75,600.00
Plastering
Helper 3 500.00 6 ₱ 9,000.00
Subtotal 11 ₱ 128,100.00
Mason 12 600.00 5 ₱ 36,000.00
CHB Laying
Helper 3 500.00 5 ₱ 7,500.00
5F
Mason 21 600.00 6 ₱ 75,600.00
Plastering
Helper 3 500.00 6 ₱ 9,000.00
Subtotal 11 ₱ 128,100.00
Mason 10 600.00 2 ₱ 12,000.00
CHB Laying
Helper 3 500.00 2 ₱ 3,000.00
RD
Mason 13 600.00 3 ₱ 23,400.00
Plastering
Helper 3 500.00 3 ₱ 4,500.00
Subtotal 5 ₱ 42,900.00
TOTAL ₱ 555,300.00

Computation

b.) Total No. of Days = Area x Accomplishment/day


Area Accomplishment per
Floor Activity Total No. of Days
(sq.m.) day
CHB Laying 464.27 8 sq.m./day 58.03 = 59 days
2F
Plastering 1206.37 10 sq.m./day 120.64 = 121 days
CHB Laying 464.27 8 sq.m./day 58.03 = 59 days
3F
Plastering 1206.37 10 sq.m./day 120.64 = 121 days
CHB Laying 464.27 8 sq.m./day 58.03 = 59 days
4F
Plastering 1206.37 10 sq.m./day 120.64 = 121 days
CHB Laying 464.27 8 sq.m./day 58.03 = 59 days
5F
Plastering 1206.37 10 sq.m./day 120.64 = 121 days
CHB Laying 144.2 8 sq.m./day 18.03 = 19 days
RD
Plastering 377.2 10 sq.m./day 37.72 = 38 days

c.) Total No. of Mason = Total No. of Days / Target Duration


Total No. of Helper
Floor Activity Target Duration Total No. of Masons
Days (for bagger mixer)
CHB Laying 59 days 5 days 11.80 = 12 masons + 3 helpers
2F
Plastering 121 days 6 days 20.17 = 21 masons + 3 helpers
CHB Laying 59 days 5 days 11.80 = 12 masons + 3 helpers
3F
Plastering 121 days 6 days 20.17 = 21 masons + 3 helpers
CHB Laying 59 days 5 days 11.80 = 12 masons + 3 helpers
4F
Plastering 121 days 6 days 20.17 = 21 masons + 3 helpers
CHB Laying 59 days 5 days 11.80 = 12 masons + 3 helpers
5F
Plastering 121 days 6 days 20.17 = 21 masons + 3 helpers
CHB Laying 19 days 2 days 9.50 = 10 masons + 3 helpers
RD
Plastering 38 days 3 days 12.67 = 13 masons + 3 helpers
49 days