Synch-Check: Manual 37615B SPM-D2-10 - Synchronizing Unit
Synch-Check: Manual 37615B SPM-D2-10 - Synchronizing Unit
Synch-Check
The controller can be utilized as a Synch-check module. Control functions are not performed. The "CB close" re-
lay remains energized as long as the following conditions are met:
Isolated Operation
Isolated operation is only possible if the discrete input "Release isolated operation / dead bus start" (terminal 5) is
energized. To enable the frequency controller, the parameter "frequency controller in isolated operation" must be
configured as "ON". The voltage controller is only enabled if the parameter "voltage controller in isolated opera-
tion" is configured as "ON". Once the generator voltage and frequency have been adjusted to the configured set
point values, the GCB will be closed.
If the LED is flashing, verify that terminal 4 is wired correctly. Terminal 4 will be de-energized when the power
circuit breaker is closed if the wiring is correct.