Professional Documents
Culture Documents
Workshop 10 – 08Aug19
1. Readings
There are no additional readings for this week.
3. Individual Assignment
Those of you who saw me at the end of the lecture in Week 9 concerning your
Assignments I will have those reviews completed next week.
4. Group Assignment
As Thursday evening between 6-9pm has been the assigned time for the course I will
be available for consultation at my office on the 15th and 22nd August from 6pm to
answer questions at my office, (CE211). I will stay until the last question on each
evening is answered. This will allow students who are undertaking their studies part
time to consult with me.
I would advise that if you have two calculators which have the ‘UNSW APPROVED’
sticker attached, then take them both to the Final Examination, as there will no doubt
be a person who has not brought their own with them on the day and they will value
your assistance.
A student is also able to borrow my calculator on the day of the Final Examination if
they find themselves in the predicament of being without their calculator on the day.
-2-
A mass foundation is to be cast with a surface area of 400 m2. The formwork design on this
foundation design allows only a height of 125 mm of concrete to be poured per hour and the
foundation is 750 mm thick.
a) Determine the duration of the concrete pour and the average placement rate in cubic metres
per hour.
b) Using the tabulated information below, determine how many trucks and pumps would be
needed for this job?
c) The job is designed to operate out of one concrete production plant. Discuss the aspects that
would be in your contingency plan if the concrete production plant broke down during this
job.
Planning Data
Concrete Loading Time: Travel to job : Unloading time: Return to Plant: Total cycle time:
Truck cycle
time 180 seconds 30 minutes 12 minutes 25 minutes 70 minutes
Concrete The selected concrete pump has a throughput of 75 m 3 per hour for a 50 minute
Pump working hour and the concrete pumps are deemed the critical plant item
Allow only 2 concrete trucks per pump to unload at any one time
Allow one spare pump to cover the contingency of concrete pump breakdowns
SOLUTION
= 20.0 loads/ h
= 100 m3/ h
= 50.0 m3/ h
-3-
As plant capacity exceeds the required delivery volume i.e. 100 m3/ h > 50.0 m3/ h; this
means that concrete plant will be able to meet concrete production demand for this job.
= 6.0 h
(i) If there was no restriction on the rate of delivery (i.e. remove the concrete height
placement restriction: 125 mm/ h limitation), then the trucks could be batched
sequentially based on the plant loading time, viz;
Therefore the amount of trucks needed to be batched in the first cycle = 4200 s ÷ 180 s/ truck
= 26 trucks
(ii) By enforcing the 125 mm/ hr concrete height placement limitation the average
concrete placement rate was shown to be 50.0 m3/ h, and therefore 10 trucks could
be loaded at 6-minute intervals, (as 10 trucks/ h × 5 m3/ truck = 50.0 m3/ h).
Therefore the amount of trucks needed to be batched in the first cycle = 60 min ÷ 6 min/ truck
= 10 trucks
As the first truck would return by the 70th minute it would require two (2) more trucks be used
to commence the second hour’s production batching on the 60th minute and the 66th minute.
The first truck returning from the site on the 70th minute would be loaded for the
commencement of the second cycle on the 72nd minute.
= 14 trucks
Each pump has a throughput of 75 m3 per hour for a 50 minute working hour
-4-
The number of pumps required to do the work is 50.0 m3/ h ÷ 75 m3/ h/ pump = 0.7 pumps
= 1 pump
= 2 concrete pumps
c) The concrete plant would have delivery arrangements made for incoming materials of
cement, course and fine aggregates and other additives and admixtures. The plant
contingency arrangements to be made in the case of a plant breakdown would include
having another plant using the same ingredients, being able to load trucks to the job
immediately and then diverting all incoming materials to the substitute production facility
and redirecting trucks coming back from the site to the emergency production plant. It will
require additional trucks being rescheduled for the job since the haul distance has increased.
There will be no formula sheet provided in the Final Examination; however, any
formulae needed in answering a specific question will be given.
Example 2:
Drilling rate using 165 mm bit @ 350 psi for Granite is 30.5 m/ hr = 0.51 m/ min
Data: A 165 mm drill is expected to last for 300 m in drilling High-silica Granite
Change steel: Need to add a 6 m length (1.1 min) and remove same per
hole (1.5 min) = 2.6 min
Blow hole: (use 0.1 min per 3 m hole) = 0.1 min × 8.6m ÷ 3m = 0.29 min
Change bit: 25 min × [8.6 m per hole ÷ 300-m life] = 0.72 min
Summarising:
__________________________________
[∑elements: 3 + 4 + 5 + 6 + 7 + 8 = (9)]
Example 3:
As the drill depth is 8.6m then you would have to add two more 4m
steels (= 2 × 1.1 min = 2.2 min) and remove the same (= 2 × 1.5 min =
3.0 min) Therefore, Total time = 5.2 min
Summarising:
__________________________________
[∑elements: 3 + 4 + 5 + 6 + 7 + 8 = (9)]
Example 4
Five successive rows of blast holes are to be fired in one shot. The rows
are 16 ft apart and it is desired that good relief will be achieved in each
row.
Planning Data