The tabulation below shows the no.

of workers per activity:

Activities No. of Workers


I. Preliminary Works
a. Fencing 10
b. Clearing and grubbing 10
c. installation of temporary housing (bunkhouse) 10
d. Layouting and staking  
II. Earthworks  
a. Excavation 45
b. Backfilling 30
c. Embankment 10
d. Gravel bedding 5
e. Termite control 15
III. Foundation  
a. Installation of footing and wall footing rebars 15
b. Installation of tie beams and column (Footing level - Level 0) rebars 30
c. Concreting of footing and wall footing 25
d. Concreting of tie beams 5
e. Concreting of columns (Footing level - Level 0) 15
IV. Ground Floor  
a. Installation of slab rebars 35
b. Installation of stair (Level 0-1) and ramp rebars 10
c. Installation of column rebars (Level 0-1) 5
d. Concreting of slab and ramp 15
e. Concreting of stairs (Level 0-1) 5
f. Concreting of columns (Level 0-1) 35
V. Second Floor  
a. Installation of column (Level 1-2) rebars 5
b. Installation of beam and girder rebars 10
c. Installation of slab rebars 25
d. Installation of stair (Level 1-2) rebars 5
e. Concreting of slab 12
f. Concreting of beams and girders 13
g. Concreting of stairs (Level 1-2) 10
h. Concreting of column (Level 1-2) 20
VI. Third Floor  
a. Installation of column (Level 2-3) rebars 12
b. Installation of beam and girder rebars 25
c. Installation of slab rebars 20
d. Installation of stair (Level 2-3) rebars 10
e. Concreting of slab 25
f. Concreting of beams and girders 15
g. Concreting of stairs (Level 2-3) 15
h. Concreting of column (Level 2-3) 20
VII. Roofing  
a. Installation of roof beam rebars 25
b. Concreting of roof beams 20
c. Installation of roof trusses 25
d. Installation of ceiling and ceiling support 20
e. Installation of purlins and channel beam 25
f. Installation of sag rods 20
g. Installation of roof sheets 25
h. Installation of roof gutters 20
VIII. Masonry works  
a. Wall Masonry (Level 0-1) 25
b. Wall masonry (Level 1-2) 20
c. Wall masonry (Level 2-3) 25
IX. Plumbing  
a. Installation of water supply pipes (First Floor) 20
b. Installation of water supply pipes (Second Floor) 25
c. Installation of water supply pipes (Third Floor) 20
d. Installation of sanitary pipes (First Floor) 25
e. Installation of sanitary pipes (Second Floor) 20
f. Installation of sanitary pipes (Third Floor) 25
g. Installation of utilities (First Floor) 20
h. Installation of utilities (Second Floor) 25
i. Installation of utilities (Third Floor) 20
X. Electrical  
a. Installation of wires and conduits (First Floor) 25
b. Installation of wires and conduits (Second Floor) 20
c. Installation of wires and conduits (Third Floor) 25
d. Installation of lighting fixtures and fire alarms (First Floor) 20
e. Installation of lighting fixtures and fire alarms (Second Floor) 25
f. Installation of lighting fixtures and fire alarms (Third Floor) 20
XI. Finishing  
a. Cement and plaster finishing (First Floor) 25
a. Cement and plaster finishing (Second Floor) 20
a. Cement and plaster finishing (Third Floor) 25
d. Wall and floor tiles (First Floor) 20
d. Wall and floor tiles (Second Floor) 25
d. Wall and floor tiles (Third Floor) 20
XI. Materials and Hardware  
a. Installtion of door jambs and window jambs (First Floor) 25
a. Installtion of door jambs and window jambs (Second Floor) 20
a. Installtion of door jambs and window jambs (Third Floor) 25
b. Installation of doors and windows (First Floor) 20
b. Installation of doors and windows (Second Floor) 25
b. Installation of doors and windows (Third Floor) 20
c. Installation of blackboards (First Floor) 25
c. Installation of blackboards (Second Floor) 20
c. Installation of blackboards (Third Floor) 25
XII. Painting  
a. Panting of walls and ceiling (First Floor) 20
b. Panting of walls and ceiling (Second Floor) 25
c. Panting of walls and ceiling (Third Floor) 45