Ferrocement Tank
( 10 m3 )
Ref.No.: QTY.FER-ST-10
S. Description No. Radius Length Breadth
No.
1 Site Clearance (Excavation) 1 4 5
(Q=1/2*L*B*H), Assuming Slop = 5 0
2 Earthwork excavation for foundation in boulder
mixed soil for :
Valve Chamber 1 1.7 1.5
Storage Tank 1 2.3
(Q=PI*r2*h, r=d/2+.05+.75, d = 1.5 m )
Washout pipe trench 1 10 0.6
3 Refilling of trench with soil including water
sprinkling and ramming
[Q=PI*(R2-r2)*h,R=d/2+.05+.75,r=d/2+.05] 9.07
4 Boulder Soling with Sand, for
Valve Chamber 1 1.7 1.5
Storage Tank 1 1.85
(Q=PI*r2*h, r=d/2+0.05+0.3)
Deduction for valve chamber portion 1 1.7 0.4
5 Stone masonry in mud mortar for
Valve Chamber 1 5 0.35
6 Plain cement concrete 1:2:4 for,
Cover slab of valve chamber 1 1.7 1.5
Deduction for manhole opening 1 0.3
(Q=PI*r *h, r=0.6/2=0.3)
2
Manhole cover 2 0.3
(Q=PI*r2*h, r=0.6/2=0.3)
Pipe embedment block 2 1 0.35
7 Plain cement concrete 1:1.5:3 for tank base. 1 1.65
(Q=PI*r2*h, r=d/2+.05+0.1)
8 Steel work for
Valve Chamber, 6 mm dia.bar @10 cm c/c
both ways. Longer span 18 1.5 0.22
Shorter span 16 1.7 0.22
Deduction for manhole opening 12 0.45 0.22
Prepared By Checked By
9 Centering & Shuttering work for Cover slab
Bottom 1 1 0.8
Sides 1 6.4
Deduction for manhole opening 1 0.3
(Q=PI*r2, r=0.6/2=0.3)
10 3 mm thick Punning in 1:1 for
Floor portion of storage tank 1 1.5
(Q=PI*r , r=d/2)
2
Wall portion of storage tank inside 1 1.5
11 12.5 mm thick plaster in 1:2 for ferrocement
(4 layers) Wall portion of tank 4 1.525
Roof portion of tank [Q=4*2*PI*R*h, 4 2.31
R=(D2+4h2 )/8h ,D=d+0.05, h=d/5-0.05/2]
Deduction manhole opening 4 0.3
12 12.5 mm thick plaster in 1:3 for tank floor 1 1.5
13 20 mm thick plaster in 1:4 for
Floor of valve chamber 1 1 0.8
Wall of valve chamber 1 3.6
14 Bitumen paint on the buried surface of tank 1 1.55
(Q=2*PI*r*h, r=d/2+0.05)
15 Snowcem paint on the exposed surface of
tank Wall (Q=2*PI*r*h, r=d/2+0.05) 1 1.55
Roof [Q=2*PI*R*h, R=(D2+4h2)/8h, 1 2.30
D=d+0.1, h=d/5]
16 Installation of pipe & fittings
17 Polythene sheet 500 gauge for tank 1 1.65
(Q=PI*r2, r=d/2+0.05+0.1)
18 Formswork for tank, for
Wall 1 1.525
Roof 1 2.31
Deduction for manhole opening 1 0.3
19 Reinforcement for tank, including chicken
wire mesh, MS Rods, GI Wire etc.for
Wall 1 1.525
Roof 1 2.31
Deduction for manhole opening 1 0.3
2O vertical bars 1Omm
Total Wt. of 10mm dia @ 0.62 Kg/m =
21 600 mm circular metal manhole cover for
ferrocement tank as per standard details 2
0
Drawing No. :-
Height Quantity Unit Remarks
0.35 3.50 m3
1.3 3.32
1 16.62
0.9 5.4
25.34 m3
0.8 7.26 m3
0.15 0.38
0.2 2.15
0.2 -0.14
2.40 m3
1.15 2.01 m3
0.1 0.255
0.1 -0.028
0.05 0.028
0.2 0.14
0.395 m3
0.13 1.112 m3
kg/m 5.94
kg/m 5.98
kg/m -1.19
10.736 Kg
Approved By
0.8
0.1 0.64
-0.28
1.16 m2
7.07
1.5 14.14
21.21 m2
1.5 57.50
0.375 21.77
-1.13
78.14 m2
7.07 m2
0.8
1.15 4.14
4.94 m2
0.8 7.79 m2
0.7 6.82
0.4 5.79
12.60 m2
L.S.
8.55 m2
1.5 14.37
0.35 5.08
-0.28
19.17 m2
1.5 14.37
0.375 5.44
-0.28
19.53 m2
84.50 m
52.39 kg
2 Set
FERROCEMENT STORAGE TANK (10 cu
Ref :- QNT. Ferro - 10
Cement Sand Stone
S.N. Description Quantity Unit (bags) (m3) (m3)
1 Site Clearance 3.50 m³
2 Earthwork in Excavation 25.34 m³
3 Refilling of Trenches 7.26 m³
4 Boulder Soling With Sand 2.40 m³ 1.70 2.64
5 Stone Masonry Work in Mud Mortar 2.01 m³ 2.21
6 PCC (1:1.5:3) 1.11 m³ 8.90 0.47
7 Cement Concrete (1:2:4) in RCC 0.395 m³ 2.53 0.18
8 Steel Work in RCC 10.74 Kg.
9 Centering & Shuttering Work for RCC 1.16 m²
10 3 mm thick Cement Punning (1:1) 22.62 m² 1.52 0.05
11 Cement plaster 12.5 mm thick (1:2) 89.70 m² 16.15 1.09
12 Cement Plaster 12.5 mm thick (1:3) 7.07 m² 0.88 0.09
13 Cement Plaster 20 mm thick (1:4) 4.94 m² 0.80 0.11
14 Bitumen Paint on Under Ground Surface 7.79 m²
15 Cement Paint on Exposed Surface 15.51 m²
16 Formwork for Ferrocement 22.06 m²
17 Polythene Sheet 500 Gauge 8.55 m²
18 Reinforcement Including Wire & Rod etc. 22.42 m²
19 600 mm Circular Metal Manhole Cover 2.00 no
Total : 30.77 3.70 4.85
S.N. Descriptions Quantity Unit Rate Total Cost
1 Cement 30.77 Bags 800.00 24,618.87
2 Sand 3.70 m3 4000.00 14,783.53
3 Gravel 1.29 m 3
3000.00 3,876.29
4 Stone
Chicken wire 0.5mm withh 10mm opening 4.85 m3 3000.00 14,543.76
5 40.50 m 2
250.00 10,124.35
6 GI wire 20.18 kg 125.00 2,522.68
7 Binding wire 4.43 kg 100.00 442.75
8 Reinfoecement 69.42 kg 78.00 5,414.58
9 Skilled Labour 31.51 Nos. 1000.00 31,512.78
1O Unskilled Labour 96.22 Nos. 800.00 76,978.17
11 Installation of Pipe & Fittings 7,960.00
12 Painting work 7.76 kg 400 3,102.46
13 Formwork Pipe 8.82 coil 3855 34,017.97
14 Bamboo 7.35 Nos. 100 734.63
15 Polythene sheet 500 gauge 8.55 m 2 57 487.58
16 600 mm circular metal 2.00 set 4000 8,000.00
17 Transport of materials
18 Miscellaneous
Total 239120.41
AGE TANK (10 cu.m)
Drawing No. G - 10/11/12
Gravel Wood MS bar Skilled Unskilled
(m3) (m3) (kg) Labour Labour Miscellaneous Items
5.57
40.28 HDPE Pipe (coil) 8.82
1.81 Bitumen Paint (l) 0.94
2.40 8.39 Cement Paint (Kg) 7.76
2.01 4.52 Chickenwire (m2) 40.50
0.96 0.89 7.78 Plain Wire (m2) 20.18
0.34 0.32 2.77 Bamboo (No.) 7.35
11.27 0.1 0.13 Nails (kg) 0.60
0.06 0.20 0.30 Binding wire (kg) 4.43
2.26 2.26
10.76 14.35
0.85 1.13
0.69 0.94
0.19 0.16
1.01 1.01
3.68 2.45
0.51 0.51
58.14 5.61 1.86
1.29 0.06 69.42 31.51 96.22
Water Connection Program
ICD NEPAL
Kavre Banepa
QUANTITY ESTIMATE
Intake work t
S. Description No. Length Breadth Height Quantity
No.
1 Site clearance 1 2.00 1.80 0.5 0.90
(Q=1/2*L*B*H), Assuming Slope = 5 0
2 Earthwork in excavation in foundation
bed 1 1.50 1.65 0.50 1.24
wing wall 2 0.55 1.2 1.00 1.32
2.56
3 Boulder soling 1 1.50 1.65 0.30 0.74
2 0.55 1.2 0.30 0.40
1.14
4 Plain cement concrete 1:2:4
1 1.30 1.1 0.10 0.14
2 0.45 1 0.1 0.09
0.23
5 Stone masonry work 2 1.3 0.35 0.8 0.73
2 0.75 0.35 0.8 0.42
2 1 0.45 0.8 0.72
1 1.3 0.45 0.8 0.47
2.34
7 1:4 cement plaster inner wall 2 1.35 0.80 2.16
outer 1 7.70 0.80 6.16
8.32
8 3mm thick 1:1 cement punning
inner wall 2 1.35 0.80 2.16
bed 1 0.75 0.6 0.45
2.61
9 RCC cover 1:2:4 1 1.30 1.1 0.1 0.14
10 reinforcement @ 200mm c/c both sides 6.5 1.30 8.45
5.5 1.1 6.05
14.5
Total Wt. of 8mm dia @ 0.39 Kg/m = 5.66
11 formwork 1 1.30 1.1 1.43
12 manhole cover 1
0.35
Unit Remarks
m3
m3
m3
m3
m3
m3
m3
m2
m2
m3
m
kg
m2
Material and labor schedule
Activity: Construction of Brick masonry intake
S.N Description Unit Quantity Labour(Nos)
Skilled
1 E/W in excavation m3 2.56
2 Boulder soling with sand m 3
1.14 1.14
3 PCC(1:2:4) in RCC components m3 0.23 0.23
4 Reinforcement bar 1% for RCC kg 5.66 0.06786
5 Cement plaster 12.5 mm thick with (1:4) cement mortar m2 8.32 1.5808
6 3mm thick 1:1 cement punning m2 2.61 0.261
7 Pipes and fitting LS
8 MASONRY WORK IN 1:4 MORTAR m3 2.34 3.504
10 formwork m 2 1.43 0.25025
11 steel cover
total 7.03391
Schedule of Materials & Labours
INTAKE
S.N. Descriptions Quantity Unit Rate
1 Cement 10.526024 Bags 800.00
2 Sand 1.552726 m 3
4000.00
3 Gravel 0.1955 m3 3000.00
4 Stone 3.9376 m3 3000.00
6 Reinfoecement 5.66 kg 78.00
7 Skilled Labour 7.03391 Nos. 1000.00
8 Unskilled Labour 21.55477 Nos. 800.00
9 Installation of Pipe & Fittings
10 Steel cover 1 set 4000
11 Formwork 1.43 m2 540
Total
nry intake
Labour(Nos) Materials
Unskilled Cement Sand Gravel Stone(m3)
4.3264
3.99 1.368
1.15 1.472 0.10235 0.1955
0.06786
1.5808 1.34784 0.121472
0.261 0.277704 0.277704
9.8112 7.42848 1.0512 2.5696
0.36751
21.55477 10.52602 1.552726 0.1955 3.9376
Total Cost
8,420.82
6,210.90
586.50
11,812.80
441.09
7,033.91
17,243.82
7,960.00
4,000.00
772.20
64482.04
QUANTITY ESTIMATE
PUBLIC STANDPOST - Type III
(Pillar with Walls)
Page No. 1 of 2
S.N. Description No. Length Breadth Height Quantity
1 Site Clearance 3.00 2.00 0.26 0.78
(Q = ½ x 3 x 2 x 0.26 Assuming Slope = 5°
2 Earthwork Exavation in boulder mixed soil
Pillar 1.00 1.40 0.35 0.45 0.22
Platform Portion 1.00 1.40 1.30 0.25 0.46
Drain(avg. height) 1.00 5.00 0.45 0.30 0.68
1.35
3 Dry Boulder soling 1.00 1.40 1.30 0.15 0.27
0.27
4 Plain Cement Concrete in (1:2:4)
Pillar 1.00 1.40 0.35 0.05 0.02
Platform 1.00 1.40 1.30 0.10 0.18
Platform border 2.00 1.10 0.10 0.10 0.02
1.00 1.40 0.10 0.10 0.01
Top of Wing Wall 1.00 1.05 0.35 0.05 0.02
Top of Pillar 1.00 0.35 0.35 0.25 0.03
0.27
5 Stone masonry in (1:4) cement mortar
Standpost wall 1.00 1.40 0.35 0.90 0.44
Standpost 1.00 0.35 0.35 0.65 0.08
0.52
6 20 mm thick cement plaster in (1:4) cement mortar
Platform 1.00 1.4 1.3 - 1.82
Platform Boarder 1.00 3.60 - 0.20 0.72
Front of Wingwall 1.00 1.40 - 0.55 0.77
Top of Wingwall 1.00 1.05 - 0.35 0.37
Back of wing wall 1.00 1.40 - 0.55 0.77
Pillar 1.00 1.40 - 0.90 1.26
Wingwall side 2.00 0.35 - 0.55 0.39
6.09
____________________________ ____________________________
Prepared By Checked By
Page No. 2 of 2
Drawing No. G-22
S.N. Description No. Length Breadth Height Quantity
7 3 mm thick cement punning (1:1) cement mortar
Platform 1.00 1.40 1.30 - 1.82
Platform Boarder 1.00 3.60 - 0.20 0.72
Front of Wingwall 1.00 1.40 - 0.55 0.77
Top of Wingwall 1.00 1.05 - 0.35 0.37
Back of wing wall 1.00 1.40 - 0.55 0.77
Pillar 1.00 1.40 - 0.90 1.26
Wingwall side 2.00 0.35 - 0.55 0.39
6.09
8 Centering & Shuttering work for PCC
Pillar 2.00 1.65 - 0.05 0.17
Platform 1.00 3.60 - 0.10 0.36
Platform border 4.00 1.10 - 0.10 0.44
2.00 1.40 - 0.10 0.28
Top of Wing Wall 2.00 1.40 - 0.05 0.14
Top of Pillar 1.00 1.40 - 0.25 0.35
1.74
9 Drain Pipe 5.00
10 L-shaped 8 mm ø MS Rod, 250 mm long 4.00 0.25 0.39 kg/m 0.39
11 Installation of pipes & fittings L.S.
12 Valve Box 1.00 1.00
Unit Remarks
m³
m³
m³
m³
m³
m2
Unit Remarks
m2
m²
m
kg
No.
PUBLIC STAND POST (TYPE III)
Cement Sand Stone
S.N. Description Quantity Unit (bags) (m3) (m3)
1 Site Clearance 0.78 m³
2 Earthwork in Excavation 1.35 m³
3 Dry Stone Soling 0.27 m³ 0.33
4 Stone Masonry in (1:6) C/S Mortar 0.52 m³ 1.10 0.24 0.57
5 P.C.C (1:2:4) 0.27 m³ 1.71 0.12
6 Centering & Shuttering Work for PCC 1.74 m²
7 20 mm thick cement plaster in (1:4) 6.09 m² 0.99 0.13
8 3 mm thick cement punning (1:1) 6.09 m² 0.41 0.01
9 8 mm ø MS Rod 250 mm long 0.39 Kg
10 Drain Pipe(HDPE 63mm f) 5.00
11 Installation of Pipes & Fittings L.S.
12 Valve Box 1.00 No
Total : 4.21 0.51 0.90
ESTIMATE OF COST
SN ITEMS QUANTITYUNITS RATE TOTAL COSNo. of taps
1 Cement 4.21 Bags 800 3368
2 Sand 0.51 m3 4000 2040
3 Stone 0.9 m 3
3000 2700
4 Gravel 0.23 m3 3000 690
5 Skilled Labour 2.81 Nos. 1000 2810
6 Unskilled Labour 9.68 Nos. 800 7744
7 Nails 0.43 Kg 100 43
8 MS Bar 0.41 Kg 78 31.98
9 Valve Box 1 Nos. 1000 1000
10 Union 1 Nos. 184 184
11 GI Nipple 1 Nos. 55 55
12 GI Pipe 3 Nos. 750 2250
13 GI Elbow 2 Nos. 53 106
14 GI Scoket 1 Nos. 42 42
15 Brass Tap 1 Nos. 475 475
16 Painting Work L.S. 1259.50
17 Instalation Of pipe and Fitting L.S. 2425.00
TOTAL 27223.48 25
(TYPE III)
Gravel Wood Skilled Unskilled
(m3) (m3) Labour Labour Miscellaneous Items
1.24 Nails (kg) 0.43
2.15 MS Bar(kg) 0.41
0.41 Valve Box(No) - 1
0.78 2.60 HDPE 63mm f -5 m
0.23 0.27 1.07
0.09 0.30 0.45
0.85 1.16
0.61 0.61
0.23 0.09 2.81 9.68
Cost
680587
Pipe Procurement at Champa Devi school
Pipe
Existing
Rate Designed cost of Joinng
SN Description Pipe
(Rs.)/m Length Pipe Works
length m
per m
1 HDPE Pipe 16 mm Dia/10 kg/Sq Cm 28.00 0 3.49
2 HDPE Pipe 20 MM Dia / 10 Kg/Sq Cm 38.50 400 15400 3.49
3 HDPE Pipe 25 MM Dia / 10 Kg/Sq Cm 57.00 4500 256500 3.49
4 HDPE Pipe 32 MM Dia / 6 Kg/Sq Cm 64.00 50 3200 4.31
5 HDPE Pipe 40 MM Dia / 6 Kg/Sq Cm 95.00 0 0 5.23
Sub Total 4950.00 275100
Name of Work: Pipe Networks (Laying with Fittings)
labour
Length Breadth Height
Sn Description of Work No Quantity Remarks for exc
(m) (m) (m)
works
1 E/W in excavation
for pipe laying 1 4950.00 0.30 0.30 445.50
Total 445.50 m3 752.895
3 E/W in backfilling 30% of E/W in excavation 133.65
Total 133.65 m3 33.4125
Cost for the work
hool
cost of
Pipe
Total Amount REMARKS
Joining
works
0.00 0.00
1394.00 16794.00
15682.50 272182.50
215.25 3415.25
0.00 0.00
17291.75 292391.75
rate for
cost
labours
800.00 602316
800.00 26730
total cost 629046
Cost for the work 921437.75
Water Connection Program
ICD NEPAL
Kavre Banepa
QUANTITY ESTIMATE FOR CHAMPA DEVI SCHOOL
S.N. DESCRIPTION TOTAL COST REMARKS
1 INTAKE 64482.04
2 RESERVIOR 239120.41
3 PIPES 292391.75
4 TAPSTAND 680,587.00
5 Material Transpotation 40000
6 PIPE LAYING 629046
SUB TOTAL 1945627.20
5% Contingency 97281.36
TOTAL 2042908.56