0% found this document useful (0 votes)
60 views30 pages

Ferrocement Tank Construction Estimate

The document provides details for constructing a 10 cubic meter ferrocement storage tank including a bill of quantities. It lists 21 line items with descriptions of materials and labor needed, including quantities for excavation, concrete, plaster, paint and other finishing materials. Dimensions and calculations are provided for items like the tank base, walls and roof. Charts summarize the cement, sand, gravel and stone required totaling over 30 bags of cement, 3.7 cubic meters of sand and 4.85 cubic meters of stone.

Uploaded by

kavita adhikari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views30 pages

Ferrocement Tank Construction Estimate

The document provides details for constructing a 10 cubic meter ferrocement storage tank including a bill of quantities. It lists 21 line items with descriptions of materials and labor needed, including quantities for excavation, concrete, plaster, paint and other finishing materials. Dimensions and calculations are provided for items like the tank base, walls and roof. Charts summarize the cement, sand, gravel and stone required totaling over 30 bags of cement, 3.7 cubic meters of sand and 4.85 cubic meters of stone.

Uploaded by

kavita adhikari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Ferrocement Tank

( 10 m3 )

Ref.No.: QTY.FER-ST-10
S. Description No. Radius Length Breadth
No.
1 Site Clearance (Excavation) 1 4 5
(Q=1/2*L*B*H), Assuming Slop = 5 0

2 Earthwork excavation for foundation in boulder


mixed soil for :
Valve Chamber 1 1.7 1.5
Storage Tank 1 2.3
(Q=PI*r2*h, r=d/2+.05+.75, d = 1.5 m )
Washout pipe trench 1 10 0.6

3 Refilling of trench with soil including water


sprinkling and ramming
[Q=PI*(R2-r2)*h,R=d/2+.05+.75,r=d/2+.05] 9.07

4 Boulder Soling with Sand, for


Valve Chamber 1 1.7 1.5
Storage Tank 1 1.85
(Q=PI*r2*h, r=d/2+0.05+0.3)
Deduction for valve chamber portion 1 1.7 0.4

5 Stone masonry in mud mortar for


Valve Chamber 1 5 0.35

6 Plain cement concrete 1:2:4 for,


Cover slab of valve chamber 1 1.7 1.5
Deduction for manhole opening 1 0.3
(Q=PI*r *h, r=0.6/2=0.3)
2

Manhole cover 2 0.3


(Q=PI*r2*h, r=0.6/2=0.3)
Pipe embedment block 2 1 0.35

7 Plain cement concrete 1:1.5:3 for tank base. 1 1.65


(Q=PI*r2*h, r=d/2+.05+0.1)

8 Steel work for


Valve Chamber, 6 mm dia.bar @10 cm c/c
both ways. Longer span 18 1.5 0.22
Shorter span 16 1.7 0.22
Deduction for manhole opening 12 0.45 0.22

Prepared By Checked By
9 Centering & Shuttering work for Cover slab
Bottom 1 1 0.8
Sides 1 6.4
Deduction for manhole opening 1 0.3
(Q=PI*r2, r=0.6/2=0.3)

10 3 mm thick Punning in 1:1 for


Floor portion of storage tank 1 1.5
(Q=PI*r , r=d/2)
2

Wall portion of storage tank inside 1 1.5

11 12.5 mm thick plaster in 1:2 for ferrocement


(4 layers) Wall portion of tank 4 1.525
Roof portion of tank [Q=4*2*PI*R*h, 4 2.31
R=(D2+4h2 )/8h ,D=d+0.05, h=d/5-0.05/2]
Deduction manhole opening 4 0.3

12 12.5 mm thick plaster in 1:3 for tank floor 1 1.5

13 20 mm thick plaster in 1:4 for


Floor of valve chamber 1 1 0.8
Wall of valve chamber 1 3.6

14 Bitumen paint on the buried surface of tank 1 1.55


(Q=2*PI*r*h, r=d/2+0.05)

15 Snowcem paint on the exposed surface of


tank Wall (Q=2*PI*r*h, r=d/2+0.05) 1 1.55
Roof [Q=2*PI*R*h, R=(D2+4h2)/8h, 1 2.30
D=d+0.1, h=d/5]

16 Installation of pipe & fittings

17 Polythene sheet 500 gauge for tank 1 1.65


(Q=PI*r2, r=d/2+0.05+0.1)

18 Formswork for tank, for


Wall 1 1.525
Roof 1 2.31
Deduction for manhole opening 1 0.3

19 Reinforcement for tank, including chicken


wire mesh, MS Rods, GI Wire etc.for
Wall 1 1.525
Roof 1 2.31
Deduction for manhole opening 1 0.3

2O vertical bars 1Omm


Total Wt. of 10mm dia @ 0.62 Kg/m =

21 600 mm circular metal manhole cover for


ferrocement tank as per standard details 2
0

Drawing No. :-
Height Quantity Unit Remarks

0.35 3.50 m3

1.3 3.32
1 16.62

0.9 5.4
25.34 m3

0.8 7.26 m3

0.15 0.38
0.2 2.15

0.2 -0.14
2.40 m3

1.15 2.01 m3

0.1 0.255
0.1 -0.028

0.05 0.028

0.2 0.14
0.395 m3

0.13 1.112 m3
kg/m 5.94
kg/m 5.98
kg/m -1.19
10.736 Kg

Approved By

0.8
0.1 0.64
-0.28
1.16 m2

7.07

1.5 14.14
21.21 m2

1.5 57.50
0.375 21.77

-1.13
78.14 m2

7.07 m2

0.8
1.15 4.14
4.94 m2

0.8 7.79 m2

0.7 6.82
0.4 5.79
12.60 m2

L.S.

8.55 m2
1.5 14.37
0.35 5.08
-0.28
19.17 m2

1.5 14.37
0.375 5.44
-0.28
19.53 m2

84.50 m
52.39 kg

2 Set
FERROCEMENT STORAGE TANK (10 cu

Ref :- QNT. Ferro - 10


Cement Sand Stone
S.N. Description Quantity Unit (bags) (m3) (m3)
1 Site Clearance 3.50 m³
2 Earthwork in Excavation 25.34 m³
3 Refilling of Trenches 7.26 m³
4 Boulder Soling With Sand 2.40 m³ 1.70 2.64
5 Stone Masonry Work in Mud Mortar 2.01 m³ 2.21
6 PCC (1:1.5:3) 1.11 m³ 8.90 0.47
7 Cement Concrete (1:2:4) in RCC 0.395 m³ 2.53 0.18
8 Steel Work in RCC 10.74 Kg.
9 Centering & Shuttering Work for RCC 1.16 m²
10 3 mm thick Cement Punning (1:1) 22.62 m² 1.52 0.05
11 Cement plaster 12.5 mm thick (1:2) 89.70 m² 16.15 1.09
12 Cement Plaster 12.5 mm thick (1:3) 7.07 m² 0.88 0.09
13 Cement Plaster 20 mm thick (1:4) 4.94 m² 0.80 0.11
14 Bitumen Paint on Under Ground Surface 7.79 m²
15 Cement Paint on Exposed Surface 15.51 m²
16 Formwork for Ferrocement 22.06 m²
17 Polythene Sheet 500 Gauge 8.55 m²
18 Reinforcement Including Wire & Rod etc. 22.42 m²
19 600 mm Circular Metal Manhole Cover 2.00 no

Total : 30.77 3.70 4.85

S.N. Descriptions Quantity Unit Rate Total Cost


1 Cement 30.77 Bags 800.00 24,618.87
2 Sand 3.70 m3 4000.00 14,783.53
3 Gravel 1.29 m 3
3000.00 3,876.29
4 Stone
Chicken wire 0.5mm withh 10mm opening 4.85 m3 3000.00 14,543.76
5 40.50 m 2
250.00 10,124.35
6 GI wire 20.18 kg 125.00 2,522.68
7 Binding wire 4.43 kg 100.00 442.75
8 Reinfoecement 69.42 kg 78.00 5,414.58
9 Skilled Labour 31.51 Nos. 1000.00 31,512.78
1O Unskilled Labour 96.22 Nos. 800.00 76,978.17
11 Installation of Pipe & Fittings 7,960.00
12 Painting work 7.76 kg 400 3,102.46
13 Formwork Pipe 8.82 coil 3855 34,017.97
14 Bamboo 7.35 Nos. 100 734.63
15 Polythene sheet 500 gauge 8.55 m 2 57 487.58
16 600 mm circular metal 2.00 set 4000 8,000.00
17 Transport of materials
18 Miscellaneous
Total 239120.41
AGE TANK (10 cu.m)

Drawing No. G - 10/11/12


Gravel Wood MS bar Skilled Unskilled
(m3) (m3) (kg) Labour Labour Miscellaneous Items
5.57
40.28 HDPE Pipe (coil) 8.82
1.81 Bitumen Paint (l) 0.94
2.40 8.39 Cement Paint (Kg) 7.76
2.01 4.52 Chickenwire (m2) 40.50
0.96 0.89 7.78 Plain Wire (m2) 20.18
0.34 0.32 2.77 Bamboo (No.) 7.35
11.27 0.1 0.13 Nails (kg) 0.60
0.06 0.20 0.30 Binding wire (kg) 4.43
2.26 2.26
10.76 14.35
0.85 1.13
0.69 0.94
0.19 0.16
1.01 1.01
3.68 2.45
0.51 0.51
58.14 5.61 1.86

1.29 0.06 69.42 31.51 96.22


Water Connection Program
ICD NEPAL
Kavre Banepa
QUANTITY ESTIMATE
Intake work t
S. Description No. Length Breadth Height Quantity
No.
1 Site clearance 1 2.00 1.80 0.5 0.90
(Q=1/2*L*B*H), Assuming Slope = 5 0

2 Earthwork in excavation in foundation


bed 1 1.50 1.65 0.50 1.24
wing wall 2 0.55 1.2 1.00 1.32
2.56

3 Boulder soling 1 1.50 1.65 0.30 0.74


2 0.55 1.2 0.30 0.40
1.14

4 Plain cement concrete 1:2:4


1 1.30 1.1 0.10 0.14
2 0.45 1 0.1 0.09
0.23

5 Stone masonry work 2 1.3 0.35 0.8 0.73


2 0.75 0.35 0.8 0.42
2 1 0.45 0.8 0.72
1 1.3 0.45 0.8 0.47
2.34

7 1:4 cement plaster inner wall 2 1.35 0.80 2.16


outer 1 7.70 0.80 6.16
8.32

8 3mm thick 1:1 cement punning


inner wall 2 1.35 0.80 2.16
bed 1 0.75 0.6 0.45
2.61

9 RCC cover 1:2:4 1 1.30 1.1 0.1 0.14

10 reinforcement @ 200mm c/c both sides 6.5 1.30 8.45


5.5 1.1 6.05
14.5
Total Wt. of 8mm dia @ 0.39 Kg/m = 5.66
11 formwork 1 1.30 1.1 1.43
12 manhole cover 1
0.35
Unit Remarks

m3

m3

m3

m3

m3

m3

m3

m2

m2

m3

m
kg
m2
Material and labor schedule
Activity: Construction of Brick masonry intake
S.N Description Unit Quantity Labour(Nos)
Skilled
1 E/W in excavation m3 2.56
2 Boulder soling with sand m 3
1.14 1.14
3 PCC(1:2:4) in RCC components m3 0.23 0.23
4 Reinforcement bar 1% for RCC kg 5.66 0.06786
5 Cement plaster 12.5 mm thick with (1:4) cement mortar m2 8.32 1.5808
6 3mm thick 1:1 cement punning m2 2.61 0.261
7 Pipes and fitting LS
8 MASONRY WORK IN 1:4 MORTAR m3 2.34 3.504
10 formwork m 2 1.43 0.25025
11 steel cover
total 7.03391

Schedule of Materials & Labours

INTAKE

S.N. Descriptions Quantity Unit Rate


1 Cement 10.526024 Bags 800.00
2 Sand 1.552726 m 3
4000.00
3 Gravel 0.1955 m3 3000.00
4 Stone 3.9376 m3 3000.00
6 Reinfoecement 5.66 kg 78.00
7 Skilled Labour 7.03391 Nos. 1000.00
8 Unskilled Labour 21.55477 Nos. 800.00
9 Installation of Pipe & Fittings
10 Steel cover 1 set 4000
11 Formwork 1.43 m2 540
Total
nry intake
Labour(Nos) Materials
Unskilled Cement Sand Gravel Stone(m3)
4.3264
3.99 1.368
1.15 1.472 0.10235 0.1955
0.06786
1.5808 1.34784 0.121472
0.261 0.277704 0.277704

9.8112 7.42848 1.0512 2.5696


0.36751

21.55477 10.52602 1.552726 0.1955 3.9376

Total Cost
8,420.82
6,210.90
586.50
11,812.80
441.09
7,033.91
17,243.82
7,960.00
4,000.00
772.20
64482.04
QUANTITY ESTIMATE
PUBLIC STANDPOST - Type III
(Pillar with Walls)
Page No. 1 of 2

S.N. Description No. Length Breadth Height Quantity


1 Site Clearance 3.00 2.00 0.26 0.78
(Q = ½ x 3 x 2 x 0.26 Assuming Slope = 5°

2 Earthwork Exavation in boulder mixed soil


Pillar 1.00 1.40 0.35 0.45 0.22
Platform Portion 1.00 1.40 1.30 0.25 0.46
Drain(avg. height) 1.00 5.00 0.45 0.30 0.68
1.35

3 Dry Boulder soling 1.00 1.40 1.30 0.15 0.27


0.27

4 Plain Cement Concrete in (1:2:4)


Pillar 1.00 1.40 0.35 0.05 0.02
Platform 1.00 1.40 1.30 0.10 0.18
Platform border 2.00 1.10 0.10 0.10 0.02
1.00 1.40 0.10 0.10 0.01
Top of Wing Wall 1.00 1.05 0.35 0.05 0.02
Top of Pillar 1.00 0.35 0.35 0.25 0.03
0.27

5 Stone masonry in (1:4) cement mortar


Standpost wall 1.00 1.40 0.35 0.90 0.44
Standpost 1.00 0.35 0.35 0.65 0.08
0.52

6 20 mm thick cement plaster in (1:4) cement mortar


Platform 1.00 1.4 1.3 - 1.82
Platform Boarder 1.00 3.60 - 0.20 0.72
Front of Wingwall 1.00 1.40 - 0.55 0.77
Top of Wingwall 1.00 1.05 - 0.35 0.37
Back of wing wall 1.00 1.40 - 0.55 0.77
Pillar 1.00 1.40 - 0.90 1.26
Wingwall side 2.00 0.35 - 0.55 0.39
6.09
____________________________ ____________________________
Prepared By Checked By

Page No. 2 of 2
Drawing No. G-22
S.N. Description No. Length Breadth Height Quantity
7 3 mm thick cement punning (1:1) cement mortar
Platform 1.00 1.40 1.30 - 1.82
Platform Boarder 1.00 3.60 - 0.20 0.72
Front of Wingwall 1.00 1.40 - 0.55 0.77
Top of Wingwall 1.00 1.05 - 0.35 0.37
Back of wing wall 1.00 1.40 - 0.55 0.77
Pillar 1.00 1.40 - 0.90 1.26
Wingwall side 2.00 0.35 - 0.55 0.39
6.09
8 Centering & Shuttering work for PCC
Pillar 2.00 1.65 - 0.05 0.17
Platform 1.00 3.60 - 0.10 0.36
Platform border 4.00 1.10 - 0.10 0.44
2.00 1.40 - 0.10 0.28
Top of Wing Wall 2.00 1.40 - 0.05 0.14
Top of Pillar 1.00 1.40 - 0.25 0.35
1.74

9 Drain Pipe 5.00


10 L-shaped 8 mm ø MS Rod, 250 mm long 4.00 0.25 0.39 kg/m 0.39

11 Installation of pipes & fittings L.S.

12 Valve Box 1.00 1.00


Unit Remarks

m2
Unit Remarks

m2

m
kg

No.
PUBLIC STAND POST (TYPE III)

Cement Sand Stone


S.N. Description Quantity Unit (bags) (m3) (m3)
1 Site Clearance 0.78 m³
2 Earthwork in Excavation 1.35 m³
3 Dry Stone Soling 0.27 m³ 0.33
4 Stone Masonry in (1:6) C/S Mortar 0.52 m³ 1.10 0.24 0.57
5 P.C.C (1:2:4) 0.27 m³ 1.71 0.12
6 Centering & Shuttering Work for PCC 1.74 m²
7 20 mm thick cement plaster in (1:4) 6.09 m² 0.99 0.13
8 3 mm thick cement punning (1:1) 6.09 m² 0.41 0.01
9 8 mm ø MS Rod 250 mm long 0.39 Kg
10 Drain Pipe(HDPE 63mm f) 5.00
11 Installation of Pipes & Fittings L.S.
12 Valve Box 1.00 No
Total : 4.21 0.51 0.90

ESTIMATE OF COST
SN ITEMS QUANTITYUNITS RATE TOTAL COSNo. of taps
1 Cement 4.21 Bags 800 3368
2 Sand 0.51 m3 4000 2040
3 Stone 0.9 m 3
3000 2700
4 Gravel 0.23 m3 3000 690
5 Skilled Labour 2.81 Nos. 1000 2810
6 Unskilled Labour 9.68 Nos. 800 7744
7 Nails 0.43 Kg 100 43
8 MS Bar 0.41 Kg 78 31.98
9 Valve Box 1 Nos. 1000 1000
10 Union 1 Nos. 184 184
11 GI Nipple 1 Nos. 55 55
12 GI Pipe 3 Nos. 750 2250
13 GI Elbow 2 Nos. 53 106
14 GI Scoket 1 Nos. 42 42
15 Brass Tap 1 Nos. 475 475
16 Painting Work L.S. 1259.50
17 Instalation Of pipe and Fitting L.S. 2425.00
TOTAL 27223.48 25
(TYPE III)

Gravel Wood Skilled Unskilled


(m3) (m3) Labour Labour Miscellaneous Items
1.24 Nails (kg) 0.43
2.15 MS Bar(kg) 0.41
0.41 Valve Box(No) - 1
0.78 2.60 HDPE 63mm f -5 m
0.23 0.27 1.07
0.09 0.30 0.45
0.85 1.16
0.61 0.61

0.23 0.09 2.81 9.68

Cost

680587
Pipe Procurement at Champa Devi school
Pipe
Existing
Rate Designed cost of Joinng
SN Description Pipe
(Rs.)/m Length Pipe Works
length m
per m
1 HDPE Pipe 16 mm Dia/10 kg/Sq Cm 28.00 0 3.49
2 HDPE Pipe 20 MM Dia / 10 Kg/Sq Cm 38.50 400 15400 3.49
3 HDPE Pipe 25 MM Dia / 10 Kg/Sq Cm 57.00 4500 256500 3.49
4 HDPE Pipe 32 MM Dia / 6 Kg/Sq Cm 64.00 50 3200 4.31
5 HDPE Pipe 40 MM Dia / 6 Kg/Sq Cm 95.00 0 0 5.23
Sub Total 4950.00 275100

Name of Work: Pipe Networks (Laying with Fittings)


labour
Length Breadth Height
Sn Description of Work No Quantity Remarks for exc
(m) (m) (m)
works
1 E/W in excavation

for pipe laying 1 4950.00 0.30 0.30 445.50


Total 445.50 m3 752.895

3 E/W in backfilling 30% of E/W in excavation 133.65


Total 133.65 m3 33.4125

Cost for the work


hool
cost of
Pipe
Total Amount REMARKS
Joining
works
0.00 0.00
1394.00 16794.00
15682.50 272182.50
215.25 3415.25
0.00 0.00
17291.75 292391.75

rate for
cost
labours

800.00 602316

800.00 26730

total cost 629046

Cost for the work 921437.75


Water Connection Program
ICD NEPAL
Kavre Banepa
QUANTITY ESTIMATE FOR CHAMPA DEVI SCHOOL

S.N. DESCRIPTION TOTAL COST REMARKS


1 INTAKE 64482.04
2 RESERVIOR 239120.41
3 PIPES 292391.75
4 TAPSTAND 680,587.00
5 Material Transpotation 40000
6 PIPE LAYING 629046
SUB TOTAL 1945627.20
5% Contingency 97281.36
TOTAL 2042908.56

You might also like