Professional Documents
Culture Documents
Site clearance 7
Excavation 7
Vehicle movements 8
Fabrication 8
Decoration 8
Cleaning 8
Site services 8
Landscaping 9
Time pressure 9
Weather conditions 10
Duty holders 12
Client duties 13
Designer duties 13
Coordinator duties 14
Contractor duties 15
Notification 17
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
2
IC9 1.1 Contents
Site access 23
Method statements 27
Permits-to-work (PTW) 27
Falsework 45
Work-positioning systems 51
Roof work 55
Fragile roofs 55
Short-duration work 60
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
3
IC9 1.1 Contents
Pre-demolition surveys 63
Pre-demolition processes 63
Hazards 66
Precautions 67
Exclusion zones 67
9.6 Excavations 70
Surcharging 75
Underground services 76
Overhead lines 79
Quick hitches 83
Trenchless technologies 84
References 87
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
4
9.0 9.0 Learning outcomes
XX Outline the principle duties and specific responsibilities for the effective management of
health and safety risks on construction sites.
XX Explain the appropriate site control measures that should be adopted to protect
employees and others during construction work.
XX Outline the hazards associated with working at heights from fixed work or temporary
platforms and the necessary precautions and safe working practices.
XX Explain the hazards and control measures associated with demolition work.
XX Explain the hazards and control measures associated with excavation work.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
5
9.1 9.1 The scope and nature of construction activities
The International Labour Organization (ILO) Safety and Health in Construction Convention, 1988
(C167) applies to all construction activities, namely building, civil engineering, and erection and
dismantling work, including any process, operation or transport on a construction site, from
the preparation of the site to the completion of the project.
Construction covers:
2 civil engineering, including excavation and the construction, structural alteration, repair,
maintenance and demolition of, for example, airports, docks, harbours, inland waterways,
dams, river and avalanche and sea defence works, roads and highways, railways, bridges,
tunnels, viaducts and works related to the provision of services such as communications,
drainage, sewerage, water and energy supplies
3 the erection and dismantling of prefabricated buildings and structures, as well as the
manufacturing of prefabricated elements on the construction site.
XX each year there are at least 60 000 fatal accidents on construction sites around the world,
i.e. a fatal accident occurs once every ten minutes
XX construction site activities are responsible for 1/6th of all fatal accidents at work
XX in some countries, it is estimated that 30% of construction workers suffer from back
pains or other musculoskeletal disorders.
In the UK the construction industry typically contributes around £100 billion (8.5%) to gross
domestic product (GDP). There are around two million people working in the UK construction
industry (4% of UK working population). Almost 90% work in small companies employing ten
workers or fewer. Around 70 000 workers are truly self-employed.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
6
The construction sector has the largest number of fatal injuries, of the main industry groups,
and third highest overall (after agriculture and extraction).
700 construction workers have been killed in workplace accidents since 2000/01. Since 1981
there have been more than 2 700 fatalities. In 2009/10 there were 42 fatal injuries (2.2 per
100 000 workers).
With the exception of fatalities it is known that there is significant amount of under-reporting of
accidents and occupational illnesses. The UK’s Health and Safety Executive (HSE) has estimated
the figure for reportable construction accidents each year at approximately 30 000, but only
around 12 000 are actually reported.
The range of activities involved in a construction project will vary between projects, but will
typically include:
Site clearance
May involve demolition, removal of overgrowth and groundworks, removal of waste and
ground remediation.
Excavation
Excavations include any earthwork, trench, well, shaft, tunnel or underground working.
Excavations are used for laying foundations and installing site utilities. Excavation hazards and
controls are discussed in Section 9.5.
The delivery of structural materials and the removal of wastes, the manual and mechanical
handling activities, and the storage of valuable, flammable or otherwise hazardous materials,
all present safety management challenges on a construction site.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
7
Vehicle movements
Movement of heavy plant and other site vehicles presents a danger to site workers and others.
Ground and weather conditions and the dynamic nature of a construction project can make
this more challenging than in industrial workplaces as discussed in Element IC10.
The particular hazards associated with site dumpers, 360o excavators and all-terrain fork lift
trucks are discussed elsewhere in this element or in Element IC7.
Fabrication
Steel erecting, welding and form-working are common in commercial construction. Mechanical
lifting of structural steels, welding and working at height are all hazardous activities.
Decoration
Painting of internal and external surfaces involves working at height. Paint and other finishes
may be hazardous on skin contact or by inhalation.
Cleaning
Cleaning as you go and good standards of housekeeping are important during a construction
project. In preparing a completed building for occupation and sale, cleaning activities may
involve working at height, the use of high pressure water jetting, and hazardous cleaning
chemicals. The use of shot-blasting for cleaning structural stonework or timber creates a
hazardous silicate dust.
Site services
Site utilities (such as electricity, gas, water and telecommunications) will usually be delivered to
a new structure underground. Fitting cables and pipework throughout a building involves work
at height, and confined space work.
Decommissioning, whereby an area is brought from its fully operational status to one where all
live or charged systems are rendered dead or inert and reduced to the lowest possible hazard
level, is an essential early stage of a demolition project.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
8
Landscaping
Groundworks to modify site levels and contours ready for lawning, and the introduction of
trees and shrubs, etc. is one of the last stages of a project, readying the site for occupation
or sale. Landscaping will involve the use of earthmoving plant, and mechanical and manual
handling activities.
Construction projects are relatively short term and construction workers are used to travelling
around the country from project to project (see also notes on migrant workers below). Workers
may be self-employed or working on short term contracts with different contractors. Problems
arising include inconsistencies in approach, difficulty in ensuring effective consultation,
cooperation and coordination of activities, and a lack of ‘ownership’ of a project.
Each stage of a building project involves different skills with workers often working for different
contractors. Effective project planning is critical to ensure smooth handovers of work areas,
to avoid congestion, and to prevent the hazardous activities of one contractor exposing third
parties to risk.
Time pressure
As mentioned the timeline for a project can easily be disrupted by the weather or other variables
such as the availability of specialist contractors. Missed deadlines for transitional handovers
and completion can result in the imposition of severe contractual penalties.
Contractors are also challenged to price ‘competitively’ for work and can also lose money if
projects overrun.
There can therefore be pressures at all levels to get the job done on time, leading to corner
cutting and rushing, which can impact on health, safety and quality.
As discussed in Section 9.2, the client has overall accountability for ensuring the project is
adequately resourced.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
9
Weather conditions
Most construction projects involve working outdoors and extremes of weather can pose
problems, such as UV radiation from sunlight and heat stress issues in the summer, the cold in
the winter as well as high winds and heavy rain. Interruptions to scheduled work can also cause
knock on problems (rushing / corner cutting) to keep a project on schedule.
All safety critical information has to be comprehensible and readily understood. If levels of
literacy and numeracy are low, alternative means of sharing information need to be available:
Migrant workers may have a more limited ability to communicate effectively with other
workers, particularly in understanding risks and how to avoid them. Many may have very
limited vocabularies. Communicating necessary health and safety information where there is
no common language presents challenges to employers. It is imperative that employers make
early efforts to establish the needs of a particular workforce, and provide a range of methods
to communicate (translators, pictorial information, etc.).
More information and advice translated into a range of languages is available at the UK’s Health
and Safety Executive (HSE) Migrant Workers site.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
10
WEB LINKS
Safety and Health in Construction Convention 1988 (C167) from the International
Labour Organization (ILO)
www.ilo.org/dyn/normlex/en/f?p=NORMLEXPUB:12100:0::NO::P12100_ILO_
CODE:C167
Working in Great Britain from overseas webpages from the UK’s Health and Safety
Executive (HSE)
www.hse.gov.uk/migrantworkers
Health and safety in the construction industry webpages from the UK's Health and
Safety Executive (HSE)
www.hse.gov.uk/construction
Construction Industry webpages from the USA’s Occupational Safety and Health
Administration (OSHA)
www.osha.gov/doc/index.html
DISCUSS
It is a common perception that construction is the most hazardous area of work and
has the worst reputation for safety. Do you agree? Why is this? Are things changing?
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
11
9.2 9.2 Management of health and safety on construction sites
XX a realistic project programme with adequate time allowed for planning, preparation and
the work itself
XX competent duty holders with sufficient resources to meet their legal duties
XX provision of health and safety information through every stage of a project, from design
to demolition and disposal
XX health and safety resources proportionate to the risk and complexity of the project.
Processes for risk management, provision of information and the cooperation and coordination
of duty holders are managed through clearly defined roles and responsibilities, and the use of
two key documents – the health and safety plan and the health and safety file (discussed later).
Duty holders
The NEBOSH International Diploma syllabus has been influenced by the UK Construction
(Design and Management) Regulations (CDM) and the International Labour Organization (ILO)
Code of Practice for Safety and Health in Construction.
Five specific duty holders are identified. They may be organisations rather than individuals, and
may be within the same organisation:
1 client
2 designer(s)
3 coordinator
4 principal contractor
5 contractors.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
12
Client duties
Clients should:
XX inform all contractors on the project of special risks to health and safety of which the
clients are or should be aware
XX require those submitting tenders to make provision for the cost of safety and health
measures during the construction process
XX take account of safety and health requirements during the construction process when
estimating the periods for completion of work stages and overall completion, to ensure
that sufficient time and resources are available overall
XX ensure that construction work does not commence until suitable welfare facilities and
the construction phase plan are in place
XX retain the health and safety file at completion of the project and provide access to it
as required.
Designer duties
Designers, including architects, engineers and quantity surveyors should eliminate health and
safety hazards and reduce risks during design (whether they present in the construction phase
of the project or during subsequent use). This would include:
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
13
Coordinator duties
The primary role of the coordinator is to advise and assist the client with his/her duties and
to coordinate risk management activities before commencement of the construction phase.
This may involve:
XX coordinating the health and safety aspects of design work and cooperate with others
involved with the project
Note: In April 2015, with the introduction of a new set of CDM Regulations in the UK, the role
of the CDM coordinator has been removed and the duties allocated to the principal designer.
A principal designer is a designer that is appointed by the client to a project involving more than
one contractor.
XX planning, managing, monitoring and coordinating health and safety in the pre-
construction phase of a project (this involves identifying and eliminating or controlling
foreseeable risks; and ensuring designers carry out their duties
XX providing relevant information to the principal contractor to help them plan, manage,
monitor and coordinate health and safety in the pre-construction phase of a project.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
14
XX planning, managing and monitoring the construction phase in liaison with other
contractors
XX preparation, development and implementation of a written health and safety plan and
site rules before the construction phase begins
XX ensuring that suitable welfare facilities are provided from the start and maintained
throughout the construction phase of the project
XX ensuring that all workers have site inductions and any further information and training
needed for the work
XX communicating relevant parts of the health and safety plan to the contractors
XX ensuring that the workers are consulted on health and safety arrangements
Contractor duties
XX planning, managing and monitoring their own work and that of their workers
XX informing the principal contractor of any problems with the health and safety plan
XX providing any information needed for the health and safety file.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
15
WEB LINKS
The Construction (Design and Management) Regulations 2015 webpages from the UK’s
Health and Safety Executive (HSE)
www.hse.gov.uk/construction/cdm/2015/index.htm
Safety and health in construction code of practice from the International Labour
Organization (ILO)
www.ilo.org/safework/info/standards-and-instruments/codes/WCMS_107826/lang--
en/index.htm
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
16
Notification
The ILO advocates that national laws or regulations should provide for the notification by the
client to the enforcing authority of construction sites of prescribed size, duration or other
relevant characteristics.
In the UK under CDM Regulations a project is notifiable if the construction phase is:
a longer than 30 days and have more than twenty workers working simultaneously at any
point of the project, or
b involves more than 500 person days of construction work.
The information that has to be sent to the Health and Safety Executive (HSE) is set out in the
regulations, and a prescribed form, F10 (rev) is available for use.
The actual form is not needed as long as the following information is provided:
1 date of forwarding
2 exact address of the construction site
3 the name of the local authority where the site is located
4 a brief description of the project and the construction work which it includes
5 contact details of the client (name, address, telephone number and any email address)
6 contact details of the principal designer (name, address, telephone number and
any email address)
7 contact details of the principal contractor (name, address, telephone number and any
email address)
8 date planned for the start of the construction phase
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
17
Health and safety plan
The client provides the principal contractor with pre-construction information regarding the:
The principal contractor prepares a detailed response to the contents of the pre-construction
information, which becomes the health and safety plan.
The health and safety plan provides a general framework for the management of health and
safety. The plan is altered and modified in line with contract progress, and also provides a
focus for on-going communications with sub-contractors, designers and others involved in the
execution of the project.
The level of detail should be proportionate to the risks involved in the project. The basic
contents are summarised in Table 9.1.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
18
XX Project description
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
19
Arrangements XX Safety risks, for example:
for controlling
• delivery and removal of materials (including waste) and work
significant site
equipment
risks
• dealing with services – water, electricity and gas, including
overhead power lines and temporary electrical installations
• stability of structures whilst carrying out construction
work, including temporary structures and existing unstable
structures
• preventing falls
The health and safety file should include the following information, where this may be relevant
to the health and safety of any future construction work.
The level of detail should be proportionate to the risks likely to be involved in such work.
b Residual hazards and how they have been dealt with, for example, surveys or other
information concerning asbestos, contaminated land, or buried services.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
20
c Key structural principles incorporated in the design of the structure, for example, bracing
and safe working loads for floors and roofs, particularly where these may preclude placing
scaffolding or heavy machinery there.
d Any hazards associated with the materials used, for example, hazardous substances, lead
paint and special coatings which should not be burned off.
e Information regarding the removal or dismantling of installed plant and equipment, such
as lifting arrangements.
f Health and safety information about equipment provided for cleaning or maintaining
the structure.
g The nature, location and markings of significant services, including fire-fighting services.
h Information and as-built drawings of the structure, its plant and equipment, for example,
the means of safe access to and from service voids fire doors and compartmentation.
WATCH. LISTEN
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
21
Protecting employees and others during construction
9.3
9.3
work
The ILO considers a badly planned site to be the underlying cause of many accidents resulting
from falls of material and collisions between workers and plant or equipment.
Space constraints, particularly urban work sites, are nearly always the biggest limiting factor
and proper management planning is essential in ensuring the safe and efficient running of a
construction project.
XX The sequence or order in which work will be done and to any especially hazardous
operations or processes.
XX Access for workers on and around the site with routes kept be free from obstruction
and from exposure to hazards such as falling materials, materials-handling equipment
and vehicles.
• have firm surfaces, adequate drainage and safe profiles to allow safe vehicle
movements.
XX Storage areas for materials and equipment should be as close as possible to the appropriate
work area e.g. Sand and gravel close to the cement-batching plant, and timber close to
the joinery shop.
XX Delivery times for materials should be scheduled to minimise disruption to site activities
and traffic on adjacent highways.
XX The location of trade workshops – these are not usually moved after they are built.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
22
XX The location of medical and welfare facilities. On large sites sanitary facilities for both
sexes should be provided at several locations.
XX Artificial lighting at places where work continues or workers pass after dark.
XX Site security (see notes on site access and protecting the public below).
XX Arrangements to keep the site tidy and for the collection, storage and removal of waste.
XX The need for low-voltage electric power supplies for temporary lighting, portable tools
and equipment.
Site access
There should be safe access onto and around the site for people and vehicles. Plan how vehicles
will be kept clear of pedestrians, especially at site entrances where it may be necessary to
provide doors or gates to achieve this segregation. Doors that open onto traffic routes may
need viewing panels or windows.
Plans should also address segregation of vehicles and pedestrians at vehicle loading/unloading
areas, parking and manoeuvring places and areas where drivers’ vision may be obstructed.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
23
Safety Barrier Pedestrian Security office Pedestrian Safety
signs route fence entrance signs
The precautions which need to be taken to adequately protect the public and visitors may differ
significantly from those taken to protect those working on the site as the public are likely to be
less aware of the dangers involved with the construction process than those working on site.
This lack of awareness can be bridged through good communication and the sharing of
relevant information.
Even experienced construction workers visiting a site may also require additional information if
they are unsure of the site layout, specific groups, such as children, need special consideration
because of their vulnerability, and consideration should also be given to the safety of trespassers
on site.
Determining the site perimeter is an important aspect of managing public risk. For most sites
the perimeter is a clearly defined geographical area within which construction work will be
carried out. Once the site perimeter is established consideration can be given to:
XX activities presenting risk on site within the perimeter (such as scaffolds, excavations and
vehicle movements)
XX activities which can create risks outside the site perimeter (e.g. noise, dust , and mud on
the public highway).
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
24
Consideration must be given to:
A 2 m high fence is an effective site barrier for most sites, however larger hoardings may be
appropriate where there have been previous attempts by children to gain access to the site.
Perimeter fences can be constructed from a range of materials, including metal mesh or
plywood or other sheeting materials.
If a fence is to be used then it should be difficult to climb. Using a small gauge mesh which
prevents children getting their hands and feet through should mean that no one can gain
handholds or footholds.
Sectional fencing should be locked together and not easily separated without using a tool from
the inside of the site.
Gaps underneath perimeter fencing and gates should be kept as small as possible to stop
anyone gaining access under the fence. On uneven ground the gaps can be quite considerable
if steps are not taken to level the surface.
The feet of sectional fencing should be highlighted wherever they protrude into pedestrian
areas to help prevent tripping accidents.
Wind loading can be considerable where timber sheeting is used and the perimeter fencing
(including the support and fixing arrangements for the structures) should be designed and
constructed to withstand foreseeable wind loads.
It can be useful to provide public vision panels. These requirements need to be reflected in its
design and construction.
Securable gates should be provided at access points. The gates should form part of the fence
and be of the same size. The gate should be lockable for site security purposes but must not
impede the ability to escape in an emergency.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
25
Arrangements for site inductions
Each contractor must provide any person employed by that contractor or working under
the contractor’s control on the construction site any information and instruction so that
construction work can be carried out without risk to health and safety. This includes:
XX a suitable site induction, where not already provided by the principal contractor
XX the procedures to be followed in the event of serious and imminent danger to health and
safety
All site induction training should be recorded, and general matters for training include:
XX PPE requirements
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
26
Use of method statements and permits-to-work
Method statements
Method statements can be an effective and practical health and safety management tool
for communicating a safe system of work to those undertaking it, especially for higher-risk
complex or unusual work such as steel and formwork erection, demolition or the use of
hazardous substances.
The method statement draws together the information compiled about the various hazards
and the ways in which they are to be controlled for any particular job from the conclusions of
the risk assessments.
A method statement also takes account of the company’s health and safety organisation and
training procedures and may include arrangements to deal with serious or imminent danger.
The method statement describes in a logical sequence exactly how a job is to be carried out in
a safe manner and without risks to health, and includes all the control measures/precautions
to be taken. The most effective health and safety method statements often have a number of
diagrams to make it clear how work should be carried out.
It ensures that the job is to be properly planned and resourced. It can also provide information
for other contractors working at the site about any effects the work will have on them and help
the principal contractor to develop an overall health and safety plan for the construction phase
of a project.
If a similar operation is repeated, the statement will be similar from job to job, however it
will need to be adapted to suit local conditions. If circumstances change markedly, e.g. with
demolition, a more comprehensive revision may be required ahead of the job.
Monitoring/auditing arrangements are required to check that the working methods set out in
the statement are actually put into practice on site.
Permits-to-work (PTW)
As discussed in Element IA6 a permit-to-work (PTW) system is a formal recorded process used
to control work which is identified as potentially hazardous. It is also a means of communication
between the various parties who carry out the hazardous work.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
27
The essential features of permit-to-work systems and the basic process are summarised below:
Clear and standardised identification of: Hand-back of the PTW, by the performing
authority, confirming that the work has
XX tasks
been completed to plan.
XX risk assessments
XX permitted task duration
XX supplemental or simultaneous
activity and control measures.
Training and instruction in the issue, use Cancellation of the PTW by the issuing
and closure of permits. authority confirming the work has been
tested and the work area returned to
normal use.
Monitoring and auditing to ensure that Additional procedures are required for
the system works as intended. extension of agreed time limits if necessary
and for managing shift handovers.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
28
WEB LINKS
Protecting the public web pages from the UK’s Health and Safety Executive (HSE)
www.hse.gov.uk/construction/safetytopics/publicprotection.htm
Site Security web pages from the UK’s Health and Safety Executive (HSE)
www.hse.gov.uk/comah/sragtech/techmeassecurity.htm
Protecting the Public Near Construction Sites briefing from ASSE (USA)
www.asse.org/broadcasts/a10-34-brief5-27-09.html
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
29
9.4 9.4 Working at height from fixed or temporary platforms
Falls from height within the construction industry, account for a high percentage of work-
related fatalities. In the United States, 33% of all fatalities in construction are caused by falls
from height, and in the UK, the figure is 52%.
As discussed in Element IC1, Section 4 some attempts to regulate work at height are designed
around a notional safe height such as 1.8 metres above which protection must be provided.
Historically in the UK work at height in the construction sector utilised the ‘two metre rule’,
however it was known that around 2/3 of all fall injuries were as a result of falls of less than
2 metres, and safeguarding on the basis of an arbitrary height was considered inconsistent
with the principles of risk assessment embodied in European Directives for working at height
(2001/45/EC) and the use of work equipment (89/655/EEC).
The current UK approach is embodied in the Work at Height Regulations 2005, which apply to
all work at height where there is a risk of a fall liable to cause personal injury.
Duty holders (employers, the self-employed, and any person that controls the work of others,
such as facilities managers or building owners who may contract others to work at height),
must ensure:
Duty holders must also adhere to the following hierarchy for managing and selecting equipment
for work at height.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
30
Element IC1 considered the following control measures.
• guard rails
• work restraint.
• landing systems.
WEB LINKS
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
31
Common access equipment
In the UK a third of all reported fall-from-height incidents involve ladders and stepladders,
typically accounting for 14 deaths and 1 200 major injuries to workers each year.
A ladder should only be used for work at height if a risk assessment has demonstrated that the
use of more suitable work equipment is not justified because of:
XX Three points of contact (hands and feet) can be maintained at the working position.
XX The short duration of use (maximum of 30 minutes in one position).
XX Existing features on site which cannot be altered.
XX overloading – the maximum load stated on the ladder should not be exceeded
XX overreaching – the workers body should remain between the stiles, and both feet should
be planted on the same rung throughout the task.
Figure 9.2: Overreaching
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
32
Carrying of tools and equipment should be avoided (by wearing a tool belt, for example) so that
three point contact can be maintained.
Where the job means that a handhold cannot be maintained other access equipment should
be used. For some work off a stepladder, such as loading or unloading from shelves, the use of
a stepladder may still be justified by a risk assessment, taking into account:
Side loading should be avoided on stepladders, by having the steps facing the work activity.
Where side-on loadings cannot be avoided the steps should be tied to a suitable point, or a
more suitable type of access equipment should be used.
Figure 9.3: Avoiding side loading a stepladder
Selecting a ladder
XX suitable for worst case surface conditions, such as smooth, wet floor tiles
XX suitable for the task/environment, for example, non-conducting ladder for electrical work
XX Class 3 (industrial) or EN 131 ladders or stepladders for use at work
XX suitable size for the work
XX used with the manufacturer’s recommended stability devices
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
33
Safe positioning / setting up
Levelling
device
16°
6°
Securing a ladder
XX Tie the ladder to a suitable point, making sure both stiles are tied.
XX Where this is not practical, use a safe, unsecured ladder or a ladder supplemented with
an effective ladder stability device.
XX If this is not possible, then securely wedge the ladder, against a wall, for example.
XX If none of the above can be achieved, foot the ladder. Note: footing is the last resort and
should be avoided, where reasonably practicable, by the use of other access equipment.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
34
Figure 9.5: Securing a ladder
Ladders, stepladders and stability devices should only be used by people who are competent
to do so.
Users should be trained and instructed to use the equipment safely, in accordance with the
following rules:
For ladders:
For stepladders:
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
35
Figure 9.7: Stepladder – don’t use top steps
2 Ensure the ladder or stepladder rungs or steps are level for use:
• judged by naked eye
• adjusted by specially designed devices.
5 Know how to prevent members of the public and unauthorised workers from using them.
6 Know that certain medical conditions or medication, alcohol or drug abuse could stop
them from using ladders.
WEB LINKS
Using ladders safely webpages from the UK’s Health and Safety Executive (HSE)
www.hse.gov.uk/work-at-height/using-ladders-safely.htm
Stairways and Ladders guide from the USA’s Occupational Safety and Health
Administration (OSHA)
www.osha.gov/Publications/ladders/osha3124.html
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
36
Trestles and staging platforms
Trestles are made with a swing back similar to stepladders, but both halves have heavy cross
bearers to support a working platform. Platforms should be of lightweight staging. Access to
trestle platforms should be by means of a stepladder.
Trestles can be used if the risk assessment shows that the risk of a person falling and injuring
themselves is low, and the work on top of the trestle is of short duration.
Steel or aluminium trestles are used in conjunction with scaffold boards or staging. Guardrail
systems are available for trestles and if they are not used the decision would need to be justified
by risk assessment.
Other supports, such as bandstands, are used with staging and are often referred to as trestles.
Figure 9.8: A frame trestle and extending trestles with working platform
An independent scaffold is constructed with two rows of standards (vertical tubes), both
internal (close to the structure) and external. The distance between the standards, parallel
with the face of the building, is called the bay-length. A shorter bay length means that the
scaffold is stronger and capable of supporting heavier loads. The components are illustrated in
Figure 9.9 (a simplified illustration) and described in Table 9.2.
Provided the scaffold is properly designed, constructed, maintained and used it provides a safe
means of access and a safe working platform which, through the provision of guard rails and
toe boards, prevents falls and falling objects.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
37
Guard rail
Bay Standard
width
Ledger
bracing
Ledger
Base plate
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
38
Component Description
Raker Load-bearing tube inclined at 75o and coupled to the second lift. Used
where normal ties are inappropriate.
Base plate Metal plate used to spread the load from a standard (base plates with
vertical adjustment are called base jacks).
Sole board Timber plank positioned beneath two or more base plates to evenly
distribute the scaffold load over the ground.
Tie Means of securing the scaffold to the building (see Figure 9.10).
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
39
Eye bolt
55
Anchor
Reveal tie
Through tie
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
40
Scaffolding – hazards and precautions
Hazards Precautions
People walking into the scaffold XX Highlighted with hazard warning tape and
lighting.
XX Workers
XX Guide rail for visually impaired (if on
XX Public–pedestrians if scaffold highway).
on pavement/highway
XX Padding of tube ends.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
41
General advice for scaffolds
XX Scaffolds should not be overloaded and should be designed for the appropriate class of
use (See Table 9.4).
XX Working platforms should be fully boarded and edge protected, and be wide enough for
the class of use (Table 9.4).
a Immediately after it has been constructed (the scaffold contractor should provide a
hand-over certificate within 24 hours of completing the scaffold).
b Before anybody goes on to it (this may be some time after it has been built).
c After any incident that may have damaged it, for example, after a storm or vehicle impact.
d Every 7 days (a formal report must be completed and entered into the site register).
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
42
A written report should be made following inspection and before the end of the working shift.
Within 24 hours the report, or a copy, should be provided to the person on whose behalf the
inspection was carried out.
XX name and address of person on whose behalf the inspection was carried out
XX details of any matter identified that could lead to a health or safety risk
XX details of any action taken as a result of any identified health or safety risk.
WEB LINKS
Scaffold checklist webpage from the UK’s Health and Safety Executive (HSE)
www.hse.gov.uk/construction/safetytopics/scaffoldinginfo.htm
Scaffolding webpage from the USA’s Occupational Safety and Health Administration (OSHA)
www.osha.gov/SLTC/scaffolding/index.html
EXAM QUESTIONS
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
43
EXAM QUESTIONS
The International Labour Organization’s Standard R175 and its associated Code of
Practice sets out general principles for ‘Safety and Health in Construction’.
Minor repairs need to be carried out to the sloping roof of a large two storey property.
A scaffold is to be erected in order to gain access to the work area.
Using the guidance in R175, outline the precautions necessary for carrying (20 marks)
out the repairs.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
44
Falsework
Falsework is any temporary structure used to support a permanent structure while it is not
self-supporting, either in new construction or refurbishment. Any failure of falsework may lead
to the collapse of the permanent structure.
The causes of many past failures were foreseeable and could have been prevented by proper
consideration when planning, erecting, loading or dismantling the falsework.
Failures often occur on fairly simple structures erected by smaller falsework contractors, who
may not employ design staff.
All practicable steps should be taken to ensure that any new or existing structure or any part of
such structure which may become unstable or in a temporary state of weakness or instability
due to the carrying out of construction work does not collapse.
XX designing falsework that can be erected, inspected and dismantled safely, including how
striking (dismantling) will be achieved (it may be craned into position in one piece but
could have to be removed piecemeal)
XX stability requirements, lateral restraint and wind uplift on untied decking components
XX providing the information that the temporary works coordinator will need to manage the
interface between the falsework and the permanent structure safely.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
45
Once complete, all falsework should be inspected and certified as ready for use (a written
permit-to-load procedure is strongly recommended). The frequency of subsequent inspections
will depend on the nature of the temporary works. They should be carried out frequently
enough to enable any faults to be rectified promptly.
WEB LINKS
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
46
Mobile tower scaffold
Mobile access towers are widely used and can provide an effective and safe means of gaining
access to work at height. However, aluminium and thin-wall steel towers are light and can
easily overturn if used incorrectly.
Guard rail
Intermediate rail
Toe board
Ladder on
end frame
Outrigger
Lockable castor
Safe erection
Mobile tower scaffolds should be constructed by competent personnel in accordance with the
erection sequence specified in the manufacturer’s instructions.
Towers should not be erected taller than manufacturers’ instructions (maximum height is
usually a multiple of longest base dimension) and should only be constructed with compatible
components, in good order.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
47
The Prefabricated Access Suppliers and Manufacturers Association (PASMA) have worked
with the UK’s Health and Safety Executive (HSE) to develop safe methods of work for tower
scaffold erection.
XX Advance guard rail systems, which use specially designed temporary guard rail units,
which are locked in place from the level below and moved up to the platform level.
XX ‘Through the Trap’ (3T), which makes use of standard tower components with the
operator taking up a working position in the trap door of the platform, from where
they can add or remove the components which act as the guard rails on the level
above the platform.
Safe use
The tower should be used on firm, level ground. The castors should be locked or base
plates properly supported. Outriggers should be used in accordance with the manufacturer’s
recommendations.
Barriers should be erected at ground level to prevent people walking in the area adjacent to
the tower.
The tower should not be over loaded with heavy materials or equipment. Side loading
should also be avoided as this will affect the tower stability, for example, supporting ladders,
trestles and rubbish chutes, and strong winds, especially when sheeted.
Safe access must be provided to the work platform. This is usually by an integral internal
ladder. The rungs on the tower end frames should not be climbed, unless specifically designed
for the purpose.
The working platform must be provided with suitable edge protection, including guard rail,
intermediate rail and toe boards.
The tower height should be reduced to less than 4 m. The route of travel should be checked
for overhead obstructions, poor ground conditions and other hazards such as moving vehicles.
The tower should only be moved by manual force (pushing or pulling) applied at waist to
shoulder height. The tower should never be towed by a vehicle. The tower should not be moved
with people, materials or equipment on it, and should not be moved in high winds.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
48
Inspections and reports
The inspection requirements for mobile towers scaffold depends upon the height of the
scaffold, as in Table 9.5:
XX after any event liable to have XX after any event liable to have
affected its stability affected its stability
The results of the inspection should be recorded and kept until the next inspection.
For towers over 2 m, inspected after assembly or to comply with the seven day regime, the
report must be written in the same shift as the inspection and forwarded to the responsible
person within 24 hours.
The report must be kept on site until construction work is complete and, in any case, be
retained for 3 months.
WEB LINKS
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
49
Temporary access types
Accidents happen during installation, use and dismantling of temporary cradles. Most accidents
happen because of:
XX failure of the cradle platform or component, such as drop-nose pins and bolts
XX failure of winches, climbing devices, safety gear and ropes, usually as a result of poor
maintenance
Equipment should be selected, installed, thoroughly examined and tested to ensure that
it is suitable for its intended purpose. Cradles should only be used by suitably trained and
competent workers.
XX Adequate floor covering, guard rails and toe boards to prevent materials falling from, or
through, the cradle’s base.
XX The equipment should be capable of fitting closely to the building and, where buffers or
rollers are fitted, they should run against suitable features on the building.
Counterweight
Cradle
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
50
XX The building should be capable of carrying the loads placed upon it, particularly under
the counterweights and under the fulcrum (or pivot point) of the outrigger.
XX Jib spacing should match the cradle length and, when the cradle can move, adequate
stops should be provided to prevent the cradle running off the end of the track.
XX Jib length and counterweights should be specified to give a factor of safety against
overturning of no less than three.
XX A secondary safety rope fitted with a fall arrest device should be provided and used.
XX The cradle should not be overloaded, and loads should be placed on the platform as
uniformly as possible.
XX There should be safe access into the cradle, ideally from ground level.
XX There should be a plan for rescuing the operator if there is a cradle fault while at a
high level.
If the motor on a powered cradle fails, it can make the cradle tip, or people may overbalance
and fall while reaching out of the cradle. Safety harnesses with a short lanyard attached to
specially designed anchorage points installed in the cradle help keep the workers in a safe
position within the cradle.
Work-positioning systems
A bosun’s chair should only be used for light, short-duration work where the provision of a
working platform or other mobile access equipment is not practicable. A chair with a seat, a
back and a central suspension point is preferable to a plank seat.
The user should be attached to the suspension system by a harness and lanyard to protect
against falls. A carrying point should be available for tools.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
51
The rope grab must be compatible with the rope type, rope diameter and/or energy-absorbing
lanyard in use.
Rope access and positioning systems normally comprise two ropes, each secured to different
anchors. The working line is used for access, egress and positioning, and the second is the
safety line. The user is connected to both lines.
The working line is equipped with a means of ascent and descent and has a self-locking system
which prevents the user from falling.
The safety line is equipped with a mobile fall protection system that is connected to and travels
with the user of the system.
Rope access is often used to access the sides of tall building when cradles are not suitable.
The technique is suitable for inspection and other similar activities but not for general
construction work.
XX The equipment must be erected and used under the supervision of a competent person
and a pre-use check must be carried out.
XX The working line and safety line should be attached to two separate anchor points.
XX Tools should be attached to the operator with a suitable lanyard so that they cannot
be dropped.
XX Where a risk of dropped tools or falling materials remains, the area beneath the work
should be fenced off or protected by fans, covered walkways, or similar.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
52
Falling materials
Workers and members of the public have been killed or seriously injured after being struck by
falling or ejected materials.
The first priority is to prevent materials falling in the first place. This should be supported with
additional measures to protect people, to prevent them from being struck by any materials
which do fall.
XX Plastic sheeting should be used on scaffolds to retain dust, drips and splashes which may
occur when cleaning building façades.
XX Scaffold fans may be required to protect people below from heavier objects.
XX Covered walkways (tunnels) may also be needed where the risk is particularly high.
XX Toeboards or brick guards should be provided, and materials should not be stored above
the height of the toeboards or brick guards.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
53
XX Protected walkways may be needed in some circumstances, for example, demolition
sites where materials could fall into pedestrian areas.
XX Where the risk of materials falling cannot be eliminated the area should be fenced off,
and access should be controlled to avoid times when there is a risk of being struck.
XX Warning signs should be prominently displayed.
Brickguard
Tarpaulin /
similar
sheeting
Second layer
of boards
Figure 9.14: Protection to scaffold working platform where public are at risk from falling materials (HSG33)
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
54
Roof work
Fragile roofs
Precautions
XX Ensure that platforms are wide enough and long enough to give adequate support across
roof members, and that there are enough platforms.
XX Protect against falling through the fragile roof adjacent to the platform by providing:
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
55
Edge protection for flat and sloping roofs
Flat roofs
Flat roofs have a pitch of < 10o and are usually waterproofed with a membrane such as felt.
Where the design of the roof does not provide permanent edge protection, such as a solid
parapet wall of at least 950 mm in height, temporary edge protection will be required to give
protection for the full duration of the work.
This temporary edge protection should be strong and rigid enough to prevent people from
falling and to withstand other loads likely to be placed on it, and be designed in such a way that
it is not necessary to remove it to work at the edge of the roof.
Guard rails should preferably be supported at ground level so they do not obstruct work on
the roof edge. Guard rails can also be supported by an upstand at the edge of the roof, or by
frames, counterweights or scaffolding on the roof.
The structure to which the edge protection is attached should be capable of supporting it.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
56
Toeboard clip
Approx 3.0 m
centres Toeboard
Guard rail
Intermediate rail
Not more
than 5.0 m
Figure 9.17: Flat roof edge protection supported at ground level (HSG33)
Pitched roofs
Traditional pitched roofs have a pitch of > 10o and are typically covered with slates or tiles.
XX the eaves
XX the roof, typically slipping down the roof, then falling from the eaves
XX the roof, falling internally, for example, during roof truss erection, stripping roofs,
installing membranes and re-roofing
XX gable ends.
Falls from sloping roofs are more likely if the pitch is steep, if the surface is slippery from, for
example, moisture, ice, snow, moss or lichens, and in windy conditions.
Unless work is of very short duration, full edge protection is required on all roof elevations to
which access is needed.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
57
The potential loading on edge protection when a person slides down a pitched roof onto it is
much greater than when falling against edge protection on a flat roof. The scaffold supplier
should design the edge protection to be suitable for the pitch of the roof.
If work on the roof requires access within 2 m of gable ends, then edge protection will be
needed at those edges. At gable ends there should be one or more working platforms between
the eaves height and the ridge. The distance from the highest working platform to the ridge
should be no more than one lift high.
A scaffold platform at eaves level provides a good standard of edge protection, a working
platform and storage space for materials. The working platform should be as close as possible
to the eaves, and is recommended to be no greater than 300 mm below eaves level. Brick
guards will be necessary if materials, such as roof slates, are stacked above toeboard height.
They can also reduce gaps between guard rails, but need to be designed for this purpose (taking
account of the pitch of the roof) and securely fixed.
Guard rails
Guard rail
Toe board
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
58
Roof ladders
On most sloping roofs, suitable roof ladders or crawling boards will be required in addition to
edge protection. It may be safe to work without a roof ladder where a high standard of edge
protection is provided, the pitch is shallow, and the surface provides particularly good foothold
and is non-fragile. The decision should be made following a risk assessment.
Roof ladders or crawling boards should be: long enough to span at least three rafters, strong
enough to support workers, and secured or placed to prevent accidental movement.
The top of the roof ladder should not be anchored against the ridge tiles, as they are liable
to break away from the ridge. The weight should bear on the opposite slope by a properly
designed and manufactured ridge hook, or be secured by other means.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
59
Short-duration work
Short-duration work means tasks that take minutes rather than hours, such as inspection,
minor repairs or minor adjustments.
Safeguards such as a full independent scaffold or edge protection are unlikely to be reasonably
practicable for such work. Suitable precautions should be determined following an assessment
of risks considering:
XX weather conditions
• on a flat roof without edge protection, a work restraint system comprising a harness
with a short lanyard attached to a secured anchor, that prevents the wearer from
reaching the roof edge / position from which they could fall.
Mobile access equipment can provide a suitable working platform in some situations, and can
be particularly appropriate for short-duration minor work.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
60
Leading edge protection systems
Purlin trolleys are used as an alternative to fall arrest systems and safety netting during
roofing operations, and are suitable for many industrial roofing situations.
Purlin trolley systems are essentially passive systems and offer collective protection.
The exposed leading edge (i.e. the opposite side to that being worked on) is protected at all
times, prior-to and following roof sheet installation, as the fixed double guardrail is always in
front of the roofing operations.
The systems provide a safety deck for the users to walk on, and to store their hand tools.
No access is required to the area below the roof for the installation and use of purlin
trolley systems.
The working edge is protected by a support framework, positioned between the roof purlins,
which prevent the operative falling into the gap when the trolley is moved along, as the
installation progresses.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
61
WEB LINKS
Health and safety in roof work (HSG33) guide from the UK’s Health and Safety
Executive (HSE)
www.hse.gov.uk/pubns/books/hsg33.htm
Fall Protection webpages from the USA’s Occupational Safety and Health
Administration (OSHA)
www.osha.gov/SLTC/fallprotection/index.html
EXAM QUESTIONS
Outline the advantages and limitations of the following types of fall protection devices
AND give an example where EACH could be used.
(a) Safety harnesses (5 marks)
(b) Safety belts (5 marks)
(c) Safety nets (5 marks)
(d) Air bags (5 marks)
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
62
9.5 9.5 Demolition work
Demolition is one of the most hazardous aspects of the construction industry. The majority of
accidents involve either premature collapse of structures, or falls from height. Fatalities and
severe injuries can result from fairly minor demolition work.
Demolition can be a high profile activity, which often attracts public interest, and usually
requires stringent safety measures. Robust physical isolation is an essential component of
safety management of a demolition project.
Pre-demolition surveys
Pre-demolition processes
Before demolition proper can begin the following will need to be addressed:
XX Gas, electricity, water, telecommunications and other site services need to be isolated
or disconnected before demolition work begins. If this is not possible, pipes and cables
should be labelled clearly, to make sure they are not disturbed.
XX Hazardous substances, such as asbestos, will need to be removed in a controlled manner.
XX Soft-stripping (the removal of non-structural components) and hard-stripping activities
(the salvaging of structural components such as architectural ironwork, dressed stone,
hardwood timbers, etc.) should be completed before structural demolition begins.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
63
XX controlled (deliberate) collapse
XX pre weakening through deliberate removal of structural components.
There are a number of demolition techniques available which may be used in combinations or
at different parts of the demolition site. The techniques broadly fit into one of four categories:
Optional
extension
Equipment
Protective cage
Optional
attachments
Base machine
Figure 9.21: Demolition base machine, equipment and attachments (BS 6187)
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
64
Hydraulic attachments
Grapple Used for bringing steel and concrete beams, columns, walls and floor
sections, and roof joists progressively to ground level.
Non-hydraulic attachments
The maximum ball weight should not exceed 50% of the safe working
load (SWL) of the machine, at the working radius.
Wire rope Wire ropes are attached to a pre-weakened steel structure, and used
pulling to pull it to the ground by winch or tracked plant. Not to be used on
brick or masonry structures.
Drilling and Diamond cutting and drilling techniques, and wet and dry tungsten
sawing cutting methods are used to weaken and/or remove parts of (or
complete) structures, particularly where work is in confined spaces, or
a high degree of accuracy is needed, or noise, dust, smoke, etc. would
be unacceptable.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
65
Hazards
The hazards presented by demolition activities will vary depending upon the techniques used.
The main safety hazards include:
Chemical XX Lead dust and fumes from paint removal, hot cutting, etc.
XX Silica dust from stone crushing or shot blasting.
XX Asbestos fibres from insulation materials, etc.
XX Gases vapours and fumes from hot cutting, chemical residues, soil
contamination, organic decomposition, bonfires, etc.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
66
Precautions
Irrespective of the demolition technique(s) used on a particular project, safeguards are designed
around the following key principles:
XX effective work planning through site surveys and effective risk assessment
XX the establishment and maintenance of safe working spaces and exclusion zones
XX the development of safe systems of work, detailing appropriate precautions for the
method of demolition used.
Exclusion zones
An exclusion zone is a designated three-dimensional space from which all persons, including the
public, are excluded during demolition activities. It should be designed to be adequate for the
particular demolition activities. The exclusion zone is made up of four areas:
Structure to be
demolished
Plan area
Exclusion zone
For debris dropping, a radius of 6 m, or half the drop height (whichever is the greater), should
be kept clear.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
67
Where cranes, grabs, balling machines, pusher arms and similar equipment are in operation a
minimum 6 m width from the face of the building to be demolished should be allowed.
For tall structures a distance of not less than twice the total height should be allowed along the
proposed line of fall.
Following hazard identification and risk assessment a demolition method statement should be
developed to specify the necessary precautions to eliminate or adequately control the hazards
(i.e. provide a safe system of work).
The method statement should be easy to understand and should be effectively communicated
to and accepted by the workforce. It is equally important that it is understood and enforced by
supervisors and management.
XX the sequence and method(s) of demolition detailing means for access, provision of safe
working platforms and machinery requirements
XX details for the making safe of electricity, gas and water supplies and site drainage
XX detail methods for dealing with hazardous materials retained on site in machinery,
pipework or tanks
XX methods for identifying the presence of hazardous substances such as asbestos on site
and the methods to be used during its removal and disposal
Many demolition activities will be of sufficiently high risk to warrant permit-to-work controls.
BS 6187:2011 – Code of practice for full and partial demolition gives good practice
recommendations for the demolition (both full and partial) of facilities, including buildings
and structures.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
68
WEB LINKS
Demolition webpages from the UK’s Health and Safety Executive (HSE)
www.hse.gov.uk/construction/safetytopics/demolition.htm
Demolition webpages from the USA’s Occupational Safety and Health Administration (OSHA)
www.osha.gov/doc/topics/demolition/index.html
WATCH. LISTEN. DO
EXAM QUESTIONS
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
69
9.6 9.6 Excavations
Digging foundations and trenches for drains is one of the first jobs carried out on a construction
site. Work in and around any excavation is hazardous and accounts for an average of seven
fatal accidents each year.
Hazards
Excavations in non-cohesive loose sand and gravel, soft clays and silts, will be especially
prone to collapse. Excavations in cohesive soils and in weak rock may stand unsupported for
periods ranging from 30 seconds to 30 days. However there is no way of knowing when such
excavations will collapse.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
70
Ground type markedly affects the probability, timing, and the extent and nature of collapse.
The following factors increase the risk of collapse of excavation sides:
XX loose, uncompacted, granular soils, i.e. sand or gravel, or mixtures containing them
XX excavations through different strata, for example, a weak layer lower down in an
excavated face can undermine more stable layers above, such as layers of sand or
gravel in otherwise stiff clays
XX the presence of groundwater and the effect on the excavation sides from surface
water running into the excavation
XX made-up ground, such as loosely consolidated fill material, old refuse tips, etc.
XX proximity to earlier excavations
XX loose blocks of fractured rock
XX weathering, such as rain, drying out, or freeze/thaw effects
XX vibration from plant, equipment, road or rail traffic
XX surcharging by spoil, stored materials or plant including vehicles
XX proximity of loaded foundations
XX damage to the support system by personnel, or when materials are lowered into
the excavation.
Controls
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
71
Battering or stepping
Angle of repose
The angle measured in degrees to the
horizontal which ground material, if
left, will ultimately form to become
Figure 9.23: Battered trench
completely stable.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
72
Supports
Excavations should be supported with timber, sheeting or proprietary support systems (for
example, hydraulic waling frame, drag box or trench box).
Figure 9.24: Timbered excavation with ladder access and supported services
(guard rails omitted from left hand side for clarity)
Terminology
XX Trench sheeting: Overlapping profiled steel sheets, available in 2-8 m lengths, positioned
vertically to the side walls of the excavation and braced with a hydraulic frame or
traditional timbers with mechanical or hydraulic struts.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
73
Figure 9.25: Trench box, trench box with edge protection and trench sheeting
WEB LINKS
Structural stability during excavations webpages from the UK’s Health and Safety
Executive (HSE)
www.hse.gov.uk/construction/safetytopics/excavations.htm
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
74
Surcharging
Hazards
Surcharging occurs when a load applied to the ground by plant, stored materials, spoil or
structures increases the horizontal load on the excavation sides, causing them to collapse.
Controls
Hazards
Depending on the permeability of the ground, water may flow into any excavation below the
natural groundwater level. Particular attention should be given to areas close to rivers, lakes
and sea.
Controls
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
75
Stability of adjacent structures and services
Hazards
Controls
XX Shoring of structures.
XX Supporting of services.
Underground services
Hazards
XX Contact with any electricity cables can result in explosion and burns.
XX Escaping gas can ignite causing fire or explosion.
XX High pressure water pipes, sewerage, telecommunications conduit, and pipe-work for
conveying chemicals all pose specific hazards.
Controls
Power mode – detects the magnetic field radiated by electricity cables which have a current
flowing through them. They do not respond to:
XX Cables where there is little or no current flowing, such as service connection cables to
unoccupied premises or street lighting cables in the daytime.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
76
XX Direct current (DC) cables, on railways, for example.
XX Deep cables (> 3 metres deep). Note: Most cables are laid in trenches between 450 mm
and 1 m deep, though some high-voltage (HV) cables will be deeper.
Radio mode – detects low-frequency radio signals, which may be picked up and re-emitted by
long metallic pipes and cables. If radio frequency detection is used, other metallic objects may
re-radiate the signal and results may vary appreciably according to locality, length of the buried
cable or pipe and distance from the termination and geographical orientation.
Generator mode – detects conductors radiating a signal applied by the signal generator (genny).
The genny sends a known signal along buried metallic services, either by direct connection to
the service or by signal induction.
Detecting the signal enables the service carrying it to be located, traced and identified.
Identifying services
Sewerage Black
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
77
Utility Duct Pipe Cable Marker / Warning tape
(if used)
WEB LINKS
Excavation and underground services webpages from the UK’s Health and Safety
Executive (HSE)
www.hse.gov.uk/electricity/information/excavations.htm
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
78
Overhead lines
Hazards
Raised tipper truck bodies, cranes or excavators may directly touch, or come close enough to,
overhead power lines to cause arcing.
Controls
Control plant movement beneath and near to overhead power lines (see Element IC8).
Hazards
Controls
XX Provision of a substantial barrier, including guard rail, intermediate rail and toe boards.
XX Provision of safe access.
Hazards
Heavy plant toppling into an excavation can cause serious injury to those working within it and
to the plant operator.
Controls
Hazards
Spoil or stored materials may fall into excavations from the surface injuring (or killing) workers
in the excavation.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
79
Controls
Materials stored away from excavation (min 1.5 m or > depth of excavation).
Hazards
XX Combustion gases from petrol or diesel engine equipment can collect within trenches.
XX Ground such as chalk or limestone in contact with acidic groundwater can liberate
carbon dioxide.
XX Glauconitic sand (such as Thanet sand) can oxidise, causing oxygen deficiency.
XX Gases such as methane or hydrogen sulphide can seep into excavations from
contaminated ground or damaged services.
Controls
Hazards
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
80
Controls
Hazards
The use of pneumatic breakers over even short periods carries serious risk of both noise-
induced hearing loss and hand-arm vibration syndrome.
Controls
WEB LINKS
Excavations webpages from the USA’s Occupational Safety and Health Administration
(OSHA)
www.osha.gov/Publications/OSHA2226/2226.html
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
81
Use of 360o excavators
After ensuring that the right excavator has been selected for the job there are five main
precautions to be implemented:
3 Visibility The driver should have a good all round view and the
excavator should be equipped with adequate visibility aids
to ensure drivers can see areas where people may be at risk
from the operation of the machine.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
82
Training and competence
There are three categories of worker who must be trained and competent regarding the
excavator hazards and precautions:
1 Drivers: should be trained, competent and authorised to operate the specific excavator.
Training certificates from recognised schemes help demonstrate competence and
certificates should be checked for validity.
3 Pedestrians: should be instructed in safe pedestrian routes on site and the procedure for
making drivers aware of their presence.
A programme of daily visual checks, regular inspections and servicing schedules should be
established in accordance with the manufacturer’s instructions and the risks associated with
each vehicle.
Drivers should be encouraged to report defects or problems. Reported problems should be put
right quickly and the excavator taken out of service if the item is safety critical.
Quick hitches
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
83
There were four fatal incidents in the UK in 2007 involved semi-automatic quick hitches, and
there have been many other serious incidents involving manual and automatic types.
All fatalities involving quick hitches have occurred when a bucket or other implement
has become detached and struck someone. The two common themes in all of the fatal
accidents were:
XX A missing retaining pin or bar, which should hold the attachment in place against the
quick hitch and insure against accidental release.
XX The victim was in an unsafe position either under the implement, or on its path as it
became detached whilst slewing, lifting and or lowering.
XX The plant operator must be given sufficient training and information to enable him to
know how to operate and check the quick hitch, and must be authorised to do so.
XX The quick hitch should be regularly inspected and maintained to avoid failure of the quick
hitch or its mechanism as a result of ‘wear and tear’.
High risk activities such as bucket changing should be segregated in clearly defined
exclusion zones.
Trenchless technologies
The need for excavation can be avoided at the design stage by using trenchless technology for
pipe laying, or pipe repair and rehabilitation.
Horizontal directional drilling uses a curved trajectory to enable a pipeline to pass under
an obstacle, such as river or road, without the need for excavations at either end, as with
horizontal boring techniques
Impact moling uses a pneumatic piercing tool to create a bore hole. The approach compacts
and displaces soil rather than excavating and removing it, therefore minimising disruption and
ground reinstatement.
Pipe bursting techniques can be used to replace an existing, damaged pipeline with a new
pipeline of the same (or slightly larger) diameter. The old pipeline can be burst in situ, or
removed piece by piece and broken up as it is pushed out of the tunnel.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
84
Statutory inspections and examinations
Construction work should not be carried out in an excavation where any supports or battering
have been provided unless:
a The excavation and any work equipment and materials which affect its safety, have been
inspected by a competent person:
(1) at the start of the shift in which the work is to be carried out
(2) after any event likely to have affected the strength or stability of the excavation
(3) after any material unintentionally falls or is dislodged.
b The person who carried out the inspection is satisfied that the work can be carried out
there safely.
Following an inspection if the inspector is not satisfied that the construction work can be
carried out safely at the place inspected, he shall, before the end of the shift within which the
inspection is completed inform the person in control of any unsatisfactory matters and prepare
a written report.
Note: Although an excavation must be inspected at the start of every shift, only one report
is needed in any seven-day period. However, if something happens to affect its strength or
stability, and/or an additional inspection is carried out, a report must then be completed.
The person on whose behalf the inspection was carried out shall keep the report, or a copy
of it, available for inspection by a health and safety enforcement officer. The report should be
kept at the site of the place of work in respect of which the inspection was carried out until that
work is completed, and retained for a further 3 months.
1 name and address of the person on whose behalf the inspection was carried out
2 location of the place of work inspected
3 description of the place of work or part of that place inspected (including any work
equipment and materials)
4 date and time of the inspection
5 details of any matter identified that could give rise to a risk to the health or safety of
any person
6 details of any action taken as a result of any matter identified in paragraph 5 above
7 details of any further action considered necessary
8 name and position of the person making the report.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
85
PRACTICE ACTIVITY
You have read about hazards to watch out for with evacuations,
but would you know what they look like? Why not go online
and see if you can decide if it is safe for work to continue in the
Excavation examination activity?
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
86
IC9 References
Arlau J (2011) Falls from Elevations in 58. Safety Applications, Encyclopedia of Occupational
Health and Safety, International Labour Organization, Geneva. www.iloencyclopaedia.org/
part-viii-12633/safety-applications/94-58-safety-applications/falls-from-elevations.
BSI (2005) BS 8437:2005 – Code of practice for selection, use and maintenance of personal fall
protection systems and equipment for use in the workplace, BSI, London.
BSI (2010) BS 6187:2011 – Code of practice for full and partial demolition, BSI, London.
HSE (2003) Safe erection, use and dismantling of falsework CIS56, HSE Books, London.
HSE (2006) Health and safety in construction HSG150 (3rd edition), HSE Books, London.
HSE (2007) Managing health and safety in construction – Construction (Design and Management)
Regulations 2007 Approved Code of Practice, L144, HSE Books, London.
HSE (2009) Protecting the public – Your next move HSG151 (3rd edition), HSE Books, London.
HSE (2009) “The safe use of vehicles on construction sites – A guide for clients, designers,
contractors, managers and workers involved with construction transport”, HSG144 2nd edition,
HSE Books, London.
HSE (2012) Health and safety in roof work HSG33 (4th edition), HSE Books, London.
HSE (2012) Excavation: What you need to know as a busy builder – CIS64, HSE Books, London.
HSE/SFFC (2012) Safe Use of Quick Hitches on Excavators, CPA 1001, Construction Plant Hire
Association, London.
HSE (Not dated) Selecting, using and maintaining personal fall protection equipment ‘Height
Aware’ campaign Information sheet 4, HSE Books, London.
ILO (1988) “Convention concerning Safety and Health in Construction – C167”, ILO, Geneva.
ILO (1992) “Safety and health in construction: An ILO code of practice”, ILO, Geneva.
ILO (1995) “Safety, health and welfare on construction sites: A training manual”, ILO, Geneva.
ILO (not dated) “Facts on health and safety at work”, ILO, Geneva.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
87
© Astutis Ltd.
www.nationalarchives.gov.uk/doc/open-government-licence/
version/3
Whilst every effort has been made to ensure the currency and
accuracy of the information contained within Astutis Ltd. bears
no liability for any omissions or errors; or any concepts and
interpretations advanced by the authors.
© Astutis Ltd Element IC9: Construction and works of a temporary nature – hazards and controls
88