You are on page 1of 2

DAILY ACTIVITY REPORT

PENGADAAN FASILITAS PRODUKSI AWAL


(EARLY PRODUCTION FACILITIES/EPF) DI WILAYAH KERJA
SELAT PANJANG,SIAK,RIAU
No. Kontrak 001/CTR/BPE-VI/22

Gatot Rahmanto Phone 0852 1706 2762


To : Location : Selat Panjang
PT. Sumatra Global Energy E - Mail gatot.rahmanto@sumatraglobalenergi.com
Cc : Pak Tifano PIC Didi Kurniadi Doc No : EPF-SGE-DR-23

Fr : Project Planning Control PIC Andriansyah Date : 5-September-2022

Project Starting Date Acc. Days Accident Crew Man-Hr Health Safety Environment
08/13/2022 83 - 21 168 - - -
Remaining Days 10 Cuaca : Sunny / Cloudly
1. HSE Activity : Stop Card Safe :- Accident: :-
- Pre Job Safety Meeting Unsafe :-
Jumlah :-
Jumlah Kerja Jam Aman :-
Komulatif Stopcard :-
Jumlah Permit to Work :2
Continue :-
Suspend :-
Closed :-

2. Job Activity :
- Pre-Job Safety Meeting & Material Preparation with Activity Planning
- Installing Production Line from Header Manifold to Production Separator (100.00%)
- Installing Outlet Test Separator to Test Tank (100.00%)
- Installing Test Line from Header Manifold to Test Separator (100.00%)
- Installing Production Separator to Tank Manifold (100.00%)
- Installing Ball Valve on Bypass Outlet Test Separator Line to Outlet Production Separator Line (100%)
- Installing Shut Down Valve (SDV) on Production Line (100%)
- Installing Outlet Gas Production Separator to Vertical Gas Scrubber (100.00%)
- Installing Oil Inlet Manifold (100.00%)
- Installing Outlet Production Scrubber to KO Drum (100.00%)
- Installing Outlet Gas Test Separator to Vertical Test Gas Scrubber (100.00%)
- Installing Oil Outlet from Storage Tank 400 bbl to Oil Outlet Manifold (100.00%)
- Installing Oil Outlet Manifold (100.00%)
- Installing Outlet Vertical Test Gas Scrubber to KO Drum (100.00%)
- Installing Drain Line Header from Equipment to Skimmer (40%)
- Installing Flare Line / Outlet KO Drum to Flare (87.10%) remain 12.90%
- Installing Venting Line (100.00%)
- Installing Hydrant Line (75.61%) remain 24.39%
- Installing Suction, Discharge, and Metering System Oil Transfer Pump (82.35%) remain 17.65%
- Installing Suction, Discharge Oil Recycle Pump Return to Storage Tank (45.45%) Remain 54.55%
- Installing Air Supply Line (50.00%) remain 50.00%
2.1 Time Spot Report

Time Description
07:00 - 08:00 - Pre-Job Safety Meeting & Material Sorting and Preparing with Activity Planning
08:00 - 09:00 - Installing Flare Line (Outlet KO Drum to Flare (87.10% *by the end of day) remain 12.90%
09:00 - 10:00 - Installing Cable Tray and Repoisitioning Fire Water Pump
10:00 - 11:00 - Painting Flare Line
11:00 - 12:00 - Installing and Painting Discharge Oil Transfer Pump (Metering System)
12:00 - 13:00 - Break
13:00 - 14:00 - Installing Air Supply Line from Air Compressor to Air Receiver (50.00% *by the end of day)
14:00 - 15:00 - Continue Installing Flare Line
15:00 - 16:00 - Installing Discharge Oil Recycle Pump
16:00 - 17:00 - Installing Fire Water Pump Suction and Discharge Line
17:00 -18:00 - Installing Pipe Support for Outlet Gas KO Drum
18:00 - 19:00 - Continue Installing Discharge Oil Recycle Pump and House Keeping / Cleaning Area

3. Kendala :
Plan : Installing Pipe Line from KO Drum to Flare Pit
Actual : Concrete Slab have not casted yet, ended making temporary support for gas line to flare pit

4. Next Plan:
- Continue Installing Air Supply Line
- Installing Return Oil from Skimmer to Tank Interconnection
- Drain Line from Equipment to Skimmer
- Installing Fire Water Pump Panel
- Continue Installing Fire Water Line

Prepared : Checked : Approved : User Comment :

Puryantoro Didi Kurniadi Andriansyah Gunawan


Supervisor Installation PIC Project Manager

PT. INEKO MAKMUR ANANTA

E-mail : OPERATION@INECO.NET page 1 of 2


DAILY ACTIVITY REPORT
PENGADAAN FASILITAS PRODUKSI AWAL
(EARLY PRODUCTION FACILITIES/EPF) DI WILAYAH KERJA
SELAT PANJANG,SIAK,RIAU
No. Kontrak 001/CTR/BPE-VI/22

Gatot Rahmanto Phone 0852 1706 2762


To : Location : Selat Panjang
PT. Sumatra Global Energy E - Mail gatot.rahmanto@sumatraglobalenergi.com
Cc : Pak Tifano PIC Didi Kurniadi Doc No : EPF-SGE-DR-23

Fr : Project Planning Control PIC Andriansyah Date : 5-Sep-22

Project Starting Date Acc. Days Accident Crew Man-Hr Health Safety Environment
08/13/2022 83 - 21 168 - - -

5. Attachement : Picture Gallery

- Installing Check Valve and Installing Discharge Oil Transfer Pump


Deskripsi : - Installing and Painting Outlet Gas from KO Drum to Flare Pit Deskripsi :
Line

Deskripsi : - Installing and Painting Oil Transfer Pump Metering System Deskripsi : - Installing Hydrant Line from Fire Water Pump

Deskripsi : - Repositioning Fire Water Pump Panel Deskripsi : - installing Cable Tray to Fire Water Pump

PT. INEKO MAKMUR ANANTA

E-mail : OPERATION@INECO.NET page 2 of 2

You might also like