Project Starting Date Acc. Days Accident Crew Man-Hr Health Safety Environment
08/13/2022 83 - 21 168 - - -
Remaining Days 10 Cuaca : Sunny / Cloudly
1. HSE Activity : Stop Card Safe :- Accident: :-
- Pre Job Safety Meeting Unsafe :-
Jumlah :-
Jumlah Kerja Jam Aman :-
Komulatif Stopcard :-
Jumlah Permit to Work :2
Continue :-
Suspend :-
Closed :-
2. Job Activity :
- Pre-Job Safety Meeting & Material Preparation with Activity Planning
- Installing Production Line from Header Manifold to Production Separator (100.00%)
- Installing Outlet Test Separator to Test Tank (100.00%)
- Installing Test Line from Header Manifold to Test Separator (100.00%)
- Installing Production Separator to Tank Manifold (100.00%)
- Installing Ball Valve on Bypass Outlet Test Separator Line to Outlet Production Separator Line (100%)
- Installing Shut Down Valve (SDV) on Production Line (100%)
- Installing Outlet Gas Production Separator to Vertical Gas Scrubber (100.00%)
- Installing Oil Inlet Manifold (100.00%)
- Installing Outlet Production Scrubber to KO Drum (100.00%)
- Installing Outlet Gas Test Separator to Vertical Test Gas Scrubber (100.00%)
- Installing Oil Outlet from Storage Tank 400 bbl to Oil Outlet Manifold (100.00%)
- Installing Oil Outlet Manifold (100.00%)
- Installing Outlet Vertical Test Gas Scrubber to KO Drum (100.00%)
- Installing Drain Line Header from Equipment to Skimmer (40%)
- Installing Flare Line / Outlet KO Drum to Flare (87.10%) remain 12.90%
- Installing Venting Line (100.00%)
- Installing Hydrant Line (75.61%) remain 24.39%
- Installing Suction, Discharge, and Metering System Oil Transfer Pump (82.35%) remain 17.65%
- Installing Suction, Discharge Oil Recycle Pump Return to Storage Tank (45.45%) Remain 54.55%
- Installing Air Supply Line (50.00%) remain 50.00%
2.1 Time Spot Report
Time Description
07:00 - 08:00 - Pre-Job Safety Meeting & Material Sorting and Preparing with Activity Planning
08:00 - 09:00 - Installing Flare Line (Outlet KO Drum to Flare (87.10% *by the end of day) remain 12.90%
09:00 - 10:00 - Installing Cable Tray and Repoisitioning Fire Water Pump
10:00 - 11:00 - Painting Flare Line
11:00 - 12:00 - Installing and Painting Discharge Oil Transfer Pump (Metering System)
12:00 - 13:00 - Break
13:00 - 14:00 - Installing Air Supply Line from Air Compressor to Air Receiver (50.00% *by the end of day)
14:00 - 15:00 - Continue Installing Flare Line
15:00 - 16:00 - Installing Discharge Oil Recycle Pump
16:00 - 17:00 - Installing Fire Water Pump Suction and Discharge Line
17:00 -18:00 - Installing Pipe Support for Outlet Gas KO Drum
18:00 - 19:00 - Continue Installing Discharge Oil Recycle Pump and House Keeping / Cleaning Area
3. Kendala :
Plan : Installing Pipe Line from KO Drum to Flare Pit
Actual : Concrete Slab have not casted yet, ended making temporary support for gas line to flare pit
4. Next Plan:
- Continue Installing Air Supply Line
- Installing Return Oil from Skimmer to Tank Interconnection
- Drain Line from Equipment to Skimmer
- Installing Fire Water Pump Panel
- Continue Installing Fire Water Line
Project Starting Date Acc. Days Accident Crew Man-Hr Health Safety Environment
08/13/2022 83 - 21 168 - - -
Deskripsi : - Installing and Painting Oil Transfer Pump Metering System Deskripsi : - Installing Hydrant Line from Fire Water Pump
Deskripsi : - Repositioning Fire Water Pump Panel Deskripsi : - installing Cable Tray to Fire Water Pump