DAILY ACTIVITY REPORT

PENGADAAN FASILITAS PRODUKSI AWAL


(EARLY PRODUCTION FACILITIES/EPF) DI WILAYAH KERJA
SELAT PANJANG,SIAK,RIAU
No. Kontrak 001/CTR/BPE-VI/22

Gatot Rahmanto Phone 0852 1706 2762


To : Location : Selat Panjang
PT. Sumatra Global Energy E - Mail gatot.rahmanto@sumatraglobalenergi.com
Cc : Pak Tifano PIC Didi Kurniadi Doc No : EPF-SGE-DR-22

Fr : Project Planning Control PIC Andriansyah Date : 4-September-2022

Project Starting Date Acc. Days Accident Crew Man-Hr Health Safety Environment
08/13/2022 83 - 19 152 - - -
Remaining Days 10 Cuaca : Sunny
1. HSE Activity : Stop Card Safe :- Accident: :-
- Pre Job Safety Meeting Unsafe :-
Jumlah :-
Jumlah Kerja Jam Aman :-
Komulatif Stopcard :-
Jumlah Permit to Work :2
Continue :-
Suspend :-
Closed :-

2. Job Activity :
- Pre-Job Safety Meeting & Material Preparation with Activity Planning
- Installing Production Line from Header Manifold to Production Separator (100.00%)
- Installing Outlet Test Separator to Test Tank (100.00%)
- Installing Test Line from Header Manifold to Test Separator (100.00%)
- Installing Production Separator to Tank Manifold (100.00%)
- Installing Ball Valve on Bypass Outlet Test Separator Line to Outlet Production Separator Line (100%)
- Installing Shut Down Valve (SDV) on Production Line (100%)
- Installing Outlet Gas Production Separator to Vertical Gas Scrubber (100.00%)
- Installing Oil Inlet Manifold (100.00%)
- Installing Outlet Production Scrubber to KO Drum (100.00%)
- Installing Outlet Gas Test Separator to Vertical Test Gas Scrubber (100.00%)
- Installing Oil Outlet from Storage Tank 400 bbl to Oil Outlet Manifold (100.00%)
- Installing Oil Outlet Manifold (100.00%)
- Installing Outlet Vertical Test Gas Scrubber to KO Drum (100.00%)
- Installing Drain Line Header from Equipment to Skimmer (40%)
- Installing Flare Line / Outlet KO Drum to Flare (48.39%) remain 61.61%
- Installing Venting Line (100.00%)
- Installing Hydrant Line (39.02%) remain 60.98%
- Installing Suction, Discharge, and Metering System Oil Transfer Pump (82.35%) remain 17.65%
- Installing Suction, Discharge Oil Recycle Pump Return to Storage Tank (45.45%) Remain 54.55%
2.1 Time Spot Report

Time Description
07:00 - 08:00 - Pre-Job Safety Meeting & Material Sorting and Preparing with Activity Planning
08:00 - 09:00
- Installing Temporary Support for Downstream KO Drum to Flare Pit
09:00 - 10:00

10:00 - 11:00 - Installing Steel Rack fro Control Panel


11:00 - 12:00 - Welding Suction Oil Transfer Pump Pipe Line
12:00 - 13:00 - Break
13:00 - 14:00 - Installing Discharge Oil Transfer Pump and Metering Line
14:00 - 15:00 - Installing TL (Tubular Luminescent) Lamp on Storage Tank Section
15:00 - 16:00

16:00 - 17:00
- Installing Suction and Dischare Oil Recycle Pump
17:00 -18:00

18:00 - 19:00

3. Kendala :
Plan : Installing Pipe Line from KO Drum to Flare Pit
Actual : Concrete Slab have not casted yet, ended making temporary support for gas line to flare pit

4. Next Plan:
- Reposition Air Compressor
- Installing Air Supply Line from Compressor
- Drain Line from Equipment to Skimmer

Prepared : Checked : Approved : User Comment :

Puryantoro Didi Kurniadi Andriansyah Gunawan


Supervisor Installation PIC Project Manager

PT. INEKO MAKMUR ANANTA

E-mail : OPERATION@INECO.NET page 1 of 2


DAILY ACTIVITY REPORT
PENGADAAN FASILITAS PRODUKSI AWAL
(EARLY PRODUCTION FACILITIES/EPF) DI WILAYAH KERJA
SELAT PANJANG,SIAK,RIAU
No. Kontrak 001/CTR/BPE-VI/22

Gatot Rahmanto Phone 0852 1706 2762


To : Location : Selat Panjang
PT. Sumatra Global Energy E - Mail gatot.rahmanto@sumatraglobalenergi.com
Cc : Pak Tifano PIC Didi Kurniadi Doc No : EPF-SGE-DR-22

Fr : Project Planning Control PIC Andriansyah Date : 4-Sep-22

Project Starting Date Acc. Days Accident Crew Man-Hr Health Safety Environment
08/13/2022 83 - 19 152 - - -

5. Attachement : Picture Gallery

- Installing Temporary Support for Gas Line (Downstream KO Drum to


Deskripsi : Deskripsi : - Installing (Welding) Pipeline for Oil Transfer Pump Metering System
Flare Pit)

Deskripsi : - Installing Steel Rack for Control Panel on Office / Lab Cabin Deskripsi : - Installing TL (Tube Luminescent) Lamp on Storage Tank Section

Deskripsi : - Welding Pipeline Suction Transfer Pump Deskripsi : - Installing Suction, Discharge header Oil Recycle Pump

PT. INEKO MAKMUR ANANTA

E-mail : OPERATION@INECO.NET page 2 of 2