Project Starting Date Acc. Days Accident Crew Man-Hr Health Safety Environment
08/13/2022 83 - 19 152 - - -
Remaining Days 10 Cuaca : Sunny
1. HSE Activity : Stop Card Safe :- Accident: :-
- Pre Job Safety Meeting Unsafe :-
Jumlah :-
Jumlah Kerja Jam Aman :-
Komulatif Stopcard :-
Jumlah Permit to Work :2
Continue :-
Suspend :-
Closed :-
2. Job Activity :
- Pre-Job Safety Meeting & Material Preparation with Activity Planning
- Installing Production Line from Header Manifold to Production Separator (100.00%)
- Installing Outlet Test Separator to Test Tank (100.00%)
- Installing Test Line from Header Manifold to Test Separator (100.00%)
- Installing Production Separator to Tank Manifold (100.00%)
- Installing Ball Valve on Bypass Outlet Test Separator Line to Outlet Production Separator Line (100%)
- Installing Shut Down Valve (SDV) on Production Line (100%)
- Installing Outlet Gas Production Separator to Vertical Gas Scrubber (100.00%)
- Installing Oil Inlet Manifold (100.00%)
- Installing Outlet Production Scrubber to KO Drum (100.00%)
- Installing Outlet Gas Test Separator to Vertical Test Gas Scrubber (100.00%)
- Installing Oil Outlet from Storage Tank 400 bbl to Oil Outlet Manifold (100.00%)
- Installing Oil Outlet Manifold (100.00%)
- Installing Outlet Vertical Test Gas Scrubber to KO Drum (100.00%)
- Installing Drain Line Header from Equipment to Skimmer (40%)
- Installing Flare Line / Outlet KO Drum to Flare (48.39%) remain 61.61%
- Installing Venting Line (100.00%)
- Installing Hydrant Line (39.02%) remain 60.98%
- Installing Suction, Discharge, and Metering System Oil Transfer Pump (82.35%) remain 17.65%
- Installing Suction, Discharge Oil Recycle Pump Return to Storage Tank (45.45%) Remain 54.55%
2.1 Time Spot Report
Time Description
07:00 - 08:00 - Pre-Job Safety Meeting & Material Sorting and Preparing with Activity Planning
08:00 - 09:00
- Installing Temporary Support for Downstream KO Drum to Flare Pit
09:00 - 10:00
16:00 - 17:00
- Installing Suction and Dischare Oil Recycle Pump
17:00 -18:00
18:00 - 19:00
3. Kendala :
Plan : Installing Pipe Line from KO Drum to Flare Pit
Actual : Concrete Slab have not casted yet, ended making temporary support for gas line to flare pit
4. Next Plan:
- Reposition Air Compressor
- Installing Air Supply Line from Compressor
- Drain Line from Equipment to Skimmer
Project Starting Date Acc. Days Accident Crew Man-Hr Health Safety Environment
08/13/2022 83 - 19 152 - - -
Deskripsi : - Installing Steel Rack for Control Panel on Office / Lab Cabin Deskripsi : - Installing TL (Tube Luminescent) Lamp on Storage Tank Section
Deskripsi : - Welding Pipeline Suction Transfer Pump Deskripsi : - Installing Suction, Discharge header Oil Recycle Pump