UNIT COSTS FOR CONSTRUCTION OF GRAVITY SEWERS (a) (b) (f)

Pipe
Depth (ft)
Diameter
(in) 8 10 12 14 16 18 20 22 24 26 28
6 (c) $33.24 $35.97 $38.18 $40.90 $44.11 $48.87 $54.64 $62.13 $72.07
8 $40.07 $44.46 $47.07 $50.38 $54.28 $60.11 $67.29 $76.48 $88.44
10 $48.36 $55.00 $58.19 $62.17 $66.97 $74.23 $83.10 $94.60 $109.47
12 $64.56 $68.21 $72.88 $78.78 $87.30 $97.78 $111.31 $129.08 $149.12 $176.72
15 $80.07 $84.13 $89.03 $95.36 $104.00 $114.98 $128.33 $145.30 $166.12 $195.28
18 $97.09 $101.27 $106.60 $113.43 $123.17 $134.12 $148.27 $165.49 $186.39 $215.74
21 (e) $117.07 $121.79 $127.32 $134.66 $144.26 $156.31 $171.26 $189.00 $210.00 $240.21
24 (e) $138.18 $145.06 $150.99 $158.87 $169.38 $182.25 $197.43 $215.17 $236.41 $267.65
27 (d) $146.18 $151.83 $159.40 $169.31 $182.30 $197.52 $215.88 $237.61 $260.40
30 $163.92 $170.10 $178.19 $188.63 $201.64 $217.04 $236.54 $259.20 $282.97
33 $175.57 $182.28 $190.51 $201.34 $214.55 $230.41 $250.80 $274.36 $299.46
36 $179.60 $186.41 $195.14 $206.13 $219.45 $236.11 $256.66 $280.72 $307.34
39 $218.80 $226.02 $234.91 $245.97 $259.82 $277.41 $298.85 $324.09 $352.86
42 $238.50 $247.36 $258.24 $271.78 $288.38 $310.66 $337.52 $368.66
48 $261.78 $271.30 $283.54 $298.83 $317.88 $341.21 $370.63 $403.93
54 $303.38 $313.93 $326.80 $342.34 $361.62 $385.57 $416.35 $452.52
60 $352.71 $364.10 $377.30 $395.69 $417.27 $443.69 $476.21 $515.23

(a) Based on Sacramento County Standard Construction Specifications, Type II Bedding and Initial Backfill.

(b) ENR 10573 Average of 20 Cities and San Francisco, January 2015

(c) VCP (24 inch and smaller)

(d) RCP with calcareous aggregate.

(e) If for structural reasons, and with County approval, RCP with calcareous aggregate is required for 21" or 24" pipeline,
the above unit costs shall be reduced $5.08 or $14.01 respectively.

(f) $4.05 per cu.yd. For mechanical compaction of intermediate backfill

ADDITIONAL COST ITEMS:

1. 22% for work outside of undeveloped areas.

2. Cost for pavement removal and replacement


Removal = $4.49 /L.F.
Replacement= Asphaltic Concrete: $180 /ton (1 ton = 160 S.F., 1 inch thick)
Aggregate Base: $41 /ton (1 ton = 20 S.F., 8 inch thick)

3. Temporary pavement = $118 /ton (1 ton = 160 S.F., 1 inch thick)

4. Flagpersons = $482 /day/person

5. Utility Crossings (service lines):


Minor Utility, cross under = $200 ea.
To replace utilities = $596 to $1,008 ea.
6. Cost for crossing a major utility to be added. Amount varies.

7. Manholes:
4' MH = $2,402 for 7' depth plus $200 /ft over 7 ft.
5' MH type A or B = $3,403 for 8' depth plus $350 /ft over 8 ft.
Lining additional = $2,000 for 8' depth plus $200 /ft over 8 ft.

8. Dewatering trench with wells: $40 to $88

9. T-Lock lining for RCP: $7.20 /S.F.