Professional Documents
Culture Documents
D : EARTHWORKS
Telegrams : Comparator, P r e t o r i a
Telex : 321308SA
Fax : 3441560
5. CONSTRUCTION ....................................................... 7
5.1 Precautlons ........................................................ 7
5.1.1 Safety ............................................................. 7
5.1.2 E x i s t l n services .................................................. 8
5.1.3 Stormwa!er and groundwater ......................................... 9
5.1.4 Nuisance ........................................................... 9
5.1.5 Reinstatement and maintenance o f roads ............................. 9
5.1.6 Road t r a f f l c control ............................................... 9
5.2 Methods and Procedures ............................................. 9
5.2.1 S I t e preparation ................................................... 9
5.2.2 Excavation ......................................................... 10
5.2.3 P l a c l n and compaction ............................................. 10
5.2.4 F in i sh! n .......................................................... 11
5.2.5 Transpor! f o r earthworks ........................................... 11
6. TOLERANCES ......................................................... 11
6.1 Position. Dimensions. Levels. e t c.................................. 11
6.2 Moisture Content and Density ....................................... 12
7 . TESTING ............................................................ 12
7.1 Exploratory Holes .................................................. 12
7.2 Takin and Testing o f Samples ...................................... 13
7.3 Matereal o r Conpaction Standard n o t t o S p e c i f i c a t i o n ............... 13
8. MEASUREMENT AND PAYMENT ............................................ 13
8.1 Basic P r i n c i p l e s................................................... 13
8.2 Computation o f Quantities .......................................... 13
8.3 Scheduled Items .................................................... 14
DRAW I NGS
Drawing D-1 Classes o f Excavation : Measurement and Payment .................... 17
Drawing 0-2 Bulk and Restricted Excavation Measurement ......................... 18
APPENDIX A . APPLICABLE STANDARDS ............................................... 19
I I
STANDARDIZED SPECIFICATION
for
1. SCOPE
1.1 This s p e c i f i c a t i o n covers earthworks c a r r i e d o u t w i t h heavy p l a n t o r l i g h t p l a n t ,
o r by hand, f o r general excavations, s h o r t .trenches, t e r r a c i n g and landscaping. I t
covers t h e requirements f o r siteworks, excavations f o r foundations f o r bridges,
b u i l d i n g s and general s t r u c t u r e s . I t d e a l s w i t h s a f e t y precautions, c l a s s i f i c a t i o n
o f materials, excavation, f i l l i n g , compaction and f i n i s h i n g .
NOTE: The standards r e f e r r e d t o i n t h e s p e c i f i c a t i o n are l i s t e d i n Appendix A.
2. INTERPRETATIONS
2.1 SUPPORTING SPECIFICATIONS
2.1 - 1 Where t h i s s p e c i f i c a t i o n i s r e q u i r e d f o r a p r o j e c t , t h e f o l l o w i n g s p e c i f i c a t i o n s
s h a l l , inter a l i a , form p a r t o f t h e c o n t r a c t document:
a) P r o j e c t s p e c i f i c a t i o n ;
b ) SABS 1200 A o r SABS 1200 AA, as a p p l i c a b l e .
2.1.2 I n a d d i t i o n t o the s p e c i f i c a t i o n s r e f e r r e d t o i n 2.1.1, t h e f o l l o w i n g s p e c i f i c a -
t i o n s may be r e q u i r e d f o r t h e p r o j e c t :
a) SABS 1200 C;
b ) SABS 1200 DB;
c ) SABS 1200 DK.
NOTE: Items 2.1.1(b) and 2.1.2(a)-(c) above may o r may n o t be bound i n t h e
document.
2.2 APPLICATION. T h i s s p e c i f i c a t i o n c o n t a i n s c l a u s e s t h a t a r e g e n e r a l l y a p p l i c a b l e t o
earthworks. I n t e r p r e t a t i o n s and v a r i a t i o n s o f t h i s s p e c i f i c a t i o n are s e t out: i n
P o r t i o n 2 o f t h e p r o j e c t s p e c i f i c a t i o n (see 2.1.1).
3. MATERIALS
3.1 CLASSIFICATION FOR EXCAVATION PURPOSES
3.1.1 Method o f C l a s s i f y i n g . The C o n t r a c t o r may use any method he chooses t o excavate any
c l a s s o f m a t e r i a l b u t h i s chosen method o f e x c a v a t i o n s h a l l n o t determine t h e
c l a s s i f i c a t i o n o f t h e excavation. The Engineer w i l l decide on t h e c l a s s i f i c a t i o n o f
t h e m a t e r i a l s . The c l a s s i f i c a t i o n w i l l be based on i n s p e c t i o n o f t h e m a t e r i a l t o be
excavated and on t h e c r i t e r i a g i v e n i n 3.1.2(a)-(e), as a p p l i c a b l e . A l l equipment
s p e c i f i e d i n 3.1.2(a)-(C) s h a l l be i n good mechanical c o n d i t i o n . " E f f i c i e n t l y " as
used i n 3.1.2(a)-(c) s h a l l be taken t o mean " i n a manner t h a t can reasonably be
expected o f a c o n t r a c t o r , having regard t o t h e p r o d u c t i o n achieved".
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.
In the event of disagreement between the Contractor and the Engineer, it shall be
the responsibility of the Contractor, if so required and sllbject to the terms of
4.1, to make available at his own expense such mechanical equipment as is specified
in 3.1.2(a)-(c), in order to assess the reasonable removability or otherwise of the
material. The Engineer's decision on the classification shell then, subject to the
relevant provisions of the contract, be final and binding.
3.1.2 Classes of Excavation (see Drawing D-1). The excavation of material will be
classified as follows for purposes of measurement and payment:
a Soft excavation
11 Soft excavation, other than in restricted excavation, shall be excavation in
material that can be efficiently removed or loaded, without prior ripping, . by. any
o f the following plant:
i ) a bulldozer of mass (including mass of ripper if fitted) approximately 22 t and
flywheel power approximately 145 kW, or
i i ) a tractor-scraper unit of total mass approximately 28 t and flywheel power
approximately 245 kW, pushed during loading by a bulldozer equivalent to that spe-
cified in (b)(l) below, or
i i i ) a track type front-erid loader of mass approximately 22 t and flywheel power
approximately 145 kW -
2) In the case of restricted excavation, soft excavation shall be excavation in
material that can be efficiently removed by a back-acting excavator of flywheel
ately 0,lO kW per millimetre of tined-bucket width, without the use
001s such as paving breakers.
b) Intermediate excavation
1 ) Intermediate excavation, other than in restricted excavation, shall be excava-
tion (excluding soft excavation) in material that can be efficiently ripped by a
bulldozer of mass approximately 35 t, fitted with a single-tine ripper suitable for
heavy ripping, and of flywheel power approximately 220 kW .
2) In the case of restricted excavation, intermediate excavation shall be excava-
tion (excluding soft excavation) in material that requires a back-acting excavator
of flywheel power exceeding 0,lO kW per millimetre of tined-bucket width or the use
of pneumatic tools before removal by equipment equivalent to that specified in
(a)(2) above.
c) Hard rock excavation
1) Hard rock excavation, other than in restricted excavation, shall be excavation
(excluding boulder excavation) in material that cannot, before removal, be effi-
ciently ripped by a bulldozer equivalent to that specified in (b)(l) above.
NOTE: Such excavation generally includes material such as formations of unweathered
rock that can be re oved only after blasting.
2) In the case of r stricted excavation, hard rock excavation shall be excavation
aterial (excluding boulder excavation) that cannot be efficiently removed
without blasting or without wedging and splitting.
d ) Boulder excavation Class A. Boulder excavation Class A shall be excavation in
material containing more than 40 % by volume of boulders of size in the range
0,03-20 m3, in a matrix of soft material or smaller boulders.
Excavation in doiomite formations other than solid dolomite will be classed as
boulder excavation Class A if the formation contains more than 40 % by volume of
lumps of hard dolomite of size in the range 0,03-20 m3, in a matrix of soft
material or smaller lumps of hard dolomite.
Excavation of solid boulders or lumps of size exceeding 20 ms will be classed as
hard rock excavat ion.
Excavation of fissured or fractured rock will not be classed as boulder excavation
but as hard rock or intermediate excavation, according to the nature of the
material.
e) Boulder excavation Class B. Boulder excavation Class B shall be excavation of
boulders only, which
I ) are in a material containing 40 % or less by volume of boulders of size in the
range Qf 0,03-20 m5, in a matrix of soft material or smaller boulders, and which
2 ) require individual drilling and blasting in order to be loaded by a track type
front-end loader or back-acting excavator, as the case may be, as specified in
(a)(l) or (a)(2) above.
The excavation of the rest of the material will be classed as soft or intermediate
excavation, according to the nature of the material.
3.2 CLASSIFICATION FOR PLACING PURPOSES
3.2.1 Material Suitable for Embankments and Terraces. The following materials are, in
general, suitable for embankments and terraces:
a) Material having a CBR of at least 3 % at the minimum specified density
(Compacted at OMC) and a PI not exceeding 18;
b) hard or rock material having a maximum dimension of 300 mm;
c) both clay or clayey material of liquid limit exceeding 40 or PI exceeding 18 (or
both), and rock or boulders having a maximum diQenSiOn greater than 300 mm, pro-
vided that they
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.
7 SABS 1200 0-1988
Earthworks
Amendment No. 1 : 23 August 1990
1) a r e n o t p l a c e d a g a i n s t s t r u c t u r e s , and
2 ) a r e p l a c e d i n predetermined q u a n t i t i e s and i n s p e c i f i e d p a r t s of t h e f i l l , as
directed.
3.2.2 M a t e r i a l S u i t a b l e f o r Replacing Overbreak i n Excavations f o r Foundations. Where, i n
excavations f o r Toundations, replacement o f overbreak with b a c k f i l l i s authorized,
t h e b a c k f i l l s h a l l be caDable o f s u f f i c i e n t comDaction t o a v o i d settlement and
capable o f placement w i t h o u t s i g n i f i c a n t voids.' The b a c k f i l l s h a l l n o t c o n t a i n
appreciable q u a n t i t i e s o f organic matter o r stones of average dimension exceeding
t h e l e s s e r o f 150 mm o r t w o - t h i r d s o f t h e thickness o f t h e l a y e r being compacted.
I n a d d i t i o n , t h e b a c k f i l l s h a l l be approved graded m a t e r i a l having a P I n o t
exceeding 10 and a CBR o f a t l e a s t 10 % a t t h e minimum s p e c i f i e d d e n s i t y compacted
a t OMC.
3.2.3 M a t e r i a l S u i t a b l e f o r B a c k f i l l o r f o r F i l l a g a i n s t Structures. Unless a p a r t i c u l a r
m a t e r i a l i s s p e c i f i e d i n t h e p r o j e c t s p e c i f i c a t i o n f o r t h e r e l e v a n t zone shown on
t h e drawings o r s p e c i f i e d i n t h e p r o j e c t s p e c i f i c a t i o n f o r use against s t r u c t u r e s ,
t h e m a t e r i a l p l a c e d as b a c k f i l l o r as f i l l w i t h i n 500 mm o f s t r u c t u r e s s h a l l comply
w i t h 3.2.1 except t h a t i t s h a l l n o t c o n t a i n more than 10 % rock o r hard fragments
r e t a i n e d on a s i e v e o f nominal aperture s i z e 50 mm .
3.3 SELECTION
3.3.1 General. Where t h e p r e s e r v a t i o n o f t o p s o i l i s r e q u i r e d f o r l a t e r use on t h e S i t e ,
€ i i C E i t r a c t o r s h a l l s e l e c t and s t o c k p i l e such topsoi 1 .
The Contractor need n o t deal s e l e c t i v e l y w i t h m a t e r i a l s from general excavation
unless he i s expressly r e q u i r e d t o do so i n terms o f t h e p r o j e c t s p e c i f i c a t i o n o r
any o t h e r earthworks S D e c i f i c a t i o n t h a t forms p a r t o f t h e c o n t r a c t .
3.3.2 and Embankments. S u f f i c i e n t m a t e r i a l a r i s i n g from excavations f o r
f o o t i n g s and t h e l i k e , and t h a t i s s u i t a b l e f o r b a c k f i l l i n g o r f o r
f i l l i n g a g a i n s t t h e f i n i s h e d s t r u c t u r e s , s h a l l be s t o c k p i l e d i n t h e v i c i n i t y o f t h e
structures.
A l l o t h e r m a t e r i a l from excavations s h a l l be disposed o f on t h e S i t e o r w i t h i n the
freehaul d i s t a n c e as d i r e c t e d and i n such a manner t h a t t h e Contractor can ensure
t h a t m a t e r i a l i s placed i n t h e c o r r e c t p o s i t i o n i n embankments (see 5.2.3.1). Any
m a t e r i a l t h a t i s below t h e f i n i s h e d l e v e l o f an excavation and t h a t t h e Engineer
considers t o b e unsuitable, s h a l l be excavated and disposed o f as d i r e c t e d . The
r e s u l t a n t space s h a l l be r e f i l l e d w i t h b a c k f i l l and compacted as s p e c i f i e d .
4. PLANT
4.1 GENERAL. P l a n t s h a l l be s u i t a b l e f o r t h e p r o d u c t i o n o f t h e end r e s u l t r e q u i r e d
under t h e c o n d i t i o n s a p p l i c a b l e t o t h e S i t e .
Although, f o r t h e purpose of c l a s s i f y i n g excavations, p a r t i c u l a r items o f p l a n t a r e
s p e c i f i e d i n 3.1, t h e Contractor i s n o t o b l i g e d t o p r o v i d e o r use those s p e c i f i e d
items o f p l a n t f o r c a r r y i n g o u t t h e work. However, should those s p e c i f i e d items not
be f r e e l y a v a i l a b l e i n good working order on t h e S i t e , t h e Engineer s h a l l be
e n t i t l e d t o decide t h e c l a s s i f i c a t i o n o f m a t e r i a l s and types o f excavation on t h e
b a s i s o f t h e good-working-order-performance o f t h e items o f p l a n t p r o v i d e d by t h e
Contractor, p r o r a t a t o t h e t h e o r e t i c a l performance o f t h e items s p e c i f i e d (see
3.1.1).
an
7.
ccupa iona
,
sgfh t i ng . I n terms o f t h e a p p l i c a b l e r e g u l a t i o n o f t h e Machinery
a r r i c a d i n and li
a e y Act, 1983 (Act 6 o f 1983), every excavation t h a t i s
accessible t o t h e p u b l i c o r t h a t i s adjacent t o a p u b l i c road o r thoroughfare o r by
which t h e s a f e t y o f persons may be endangered, s h a l l be
a) adequately p r o t e c t e d by a b a r r i e r o r fence o f h e i g h t a t l e a s t 1 000 mm and as
c l o s e t o t h e excavation as p r a c t i c a b l e ; and I
b ) provided w i t h r e d warning l i g h t s a t n i g h t .
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.
SABS 1200 D-1988 8
Earthworks
5.1.2 Exi s t i n S e r v i L E
5.1.2.1 G G G K h p r o v i s i o n s o f Subclause 5.4 o f SABS 1200 A o r o f Subclause 5.2 o f
sAESs7700 A A . as r e l e v a n t . s h a l l a* m . l"v i n a d d i t i o n t o t h e reauirements o f
5.1.2.2-5.1.2.4 below.
5.1.2.2 -
Detection, l o c a t i o n and ex osure. (The drawin s show t h e p o s i t i o n o f e x i s t i n g ser-
vices based on t h e b e s t in!ormF&ion available!. The C o n t r a c t o r s h a l l v e r i f y t h e
p o s i t i o n o f a l l services and a l l o t h e r obstacles and e x i s t i n g works on t h e S i t e .
Manholes, v a l v e boxes and t h e l i k e w i l l be regarded as known services. Before com-
mencing c o n s t r u c t i o n i n any p a r t i c u l a r area, t h e Contractor s h a l l v e r i f y t h e p o s i -
t i o n s o f services and r e p o r t t o t h e Engineer any t h a t a r e missing.
Where any underground services a r e shown on t h e drawings, t h e Contractor s h a l l have
the equipment r e f e r r e d t o i n 4 . 4 a v a i l a b l e on t h e S i t e f o r as long as i s necessary
t o d e t e c t and l o c a t e such services and, i f so ordered, he s h a l l excavate by hand t o
expose such services i n areas and i n a manner and a t a t i m e agreed upon w i t h t h e
Engineer (see 8.3.8.1).
5.1.2.3 -P r o t e c t i o n o f cables. The Contractor s h a l l advise t h e Engineer a t l e a s t 7 d i n
advance of'Tfi-1 d a t e on which he proposes t o excavate near any cable. He
s h a l l n o t use mechanical equipment t o excavate w i t h i n 3 m o f t h e estimated p o s i t i o n
o f any cable and s h a l l , i f necessary, expose t h e cable by means o f hand excavation
c a r r i e d o u t under proper supervision. When so i n s t r u c t e d , t h e Contractor s h a l l
b a c k f i l l such cable trenches w i t h approved m a t e r i a l t o t h e compaction d e n s i t y
ordered.
5.1.2.4 Ne li ence. Where a s e r v i c e i s damaged because o f t h e C o n t r a c t o r ' s negligence, t h e
+F
pena y payable by t h e Contractor s h a l l be as s p e c i f i e d i n t h e p r o j e c t s p e c i f i c a -
t i o n and he s h a l l make good such damage o r bear t h e c o s t o f t h e r e p a i r s , as
specified.
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.
......................................
1 ) P u b l i s h e d by t h e GSIR, P r e t o r i a .
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.
5.2.2 Excavation
5.2.2.1 Excavations f o r general earthworks and f o r s t r u c t u r e s
a) A f t e r an area has been s t r i p p e d as s p e c i f i e d i n 5.2.1, excavation s h a l l be
c a r r i e d o u t f i r s t t o any general l e v e l s t o which t h e ground has t o be reduced and
then f o r foundations, f o o t i n g s , etc., t o t h e depths i n d i c a t e d o r t o such g r e a t e r
y be r e q u i r e d by t h e Engineer t o ensure a s a t i s f a c t o r y foundation. The
o r d e r o r a u t h o r i z e a d d i t i o n a l excavation f o r any s t a t e d purpose
11
SABS 1200 D-1988
Earthworks
Where shown on t h e drawings o r ordered, a l l trenches and excavations o u t s i d e s t r u c -
t u r e s s h a l l be c a r e f u l l y r e f i l l e d w i t h approved m a t e r i a l i n l a y e r s o f t h i c k n e s s n o t
exceeding 250 mm b e f o r e compaction.
During t h e p l a c i n g o f each l a y e r , t h e f i l l i n g s h a l l be w e l l r o l l e d and compacted,
s u f f i c i e n t water being added u n i f o r m l y t o ensure t h a t t h e d e n s i t y s p e c i f i e d f o r t h e
p a r t i c u l a r zone i s achieved or, where a d e n s i t y i s n o t s p e c i f i e d , t h a t t h e d e n s i t y
achieved i s a t l e a s t t h a t o f t h e a d j o i n i n g u n d i s t u r b e d m a t e r i a l . Each l a y e r s h a l l
be completed b e f o r e t h e n e x t i s added.
Except w i t h t h e consent o f t h e Engineer, f i l l i n g s h a l l n o t be deposited i n water.
b ) R e s t r i c t e d . Where t h e use o f conventional compaction p l a n t c l o s e t o a s t r u c t u r e
i s n o t possible, t h e m a t e r i a l t o be compacted s h a l l be spread i n loose l a y e r s o f
t h i c k n e s s n o t exceeding 250 mm and compacted by means o f mechanical tampers t o a t
l e a s t t h e d e n s i t y s p e c i f i e d f o r t h a t p a r t i c u l a r zone or, where a d e n s i t y i s n o t
s p e c i f i e d , t o a t l e a s t the d e n s i t y o f t h e a d j o i n i n g u n d i s t u r b e d m a t e r i a l .
5.2.4 F i n is h i n
5.2.4.1 d d i n g . On completion o f earthworks t o t h e f i n i s h e d l e v e l and o f b a c k f i l l i n g
o f a l l holes, trenches and t h e l i k e , t h e whole s u r f a c e s h a l l be graded, shaped and
compacted t o f i n a l grades and l e v e l s . The s u r f a c e s h a l l be l i g h t l y watered as t h e
Engineer may d i r e c t .
5.2.4.2 T o p s o i l i n g . Where scheduled, t o p s o i l s h a l l be placed on l e v e l and s l i g h t l y graded
areas and s h a l l be l i g h t l y compacted by wheeled v e h i c l e s o r by tamping, and trimmed
n e a t l y t o t h e r e q u i r e d l i n e s , grades and l e v e l s . The f i n a l t h i c k n e s s o f t o p s o i l
a f t e r compaction s h a l l be a t l e a s t 75 mm .
5.2.4.3 Grass o r o t h e r vegetation. Where and as scheduled, grass o r o t h e r v e g e t a t i o n s h a l l
be p l a n t e d a f t e r t o p s o i l i n g has been completed. On completion o f p l a n t i n g , t h e
p l a n t e d area s h a l l be n e a t l y trimmed and w e l l watered.
The C o n t r a c t o r s h a l l ensure t h a t t h e p l a n t e d areas are n o t p e r m i t t e d t o d r y o u t .
Any grass o r o t h e r v e g e t a t i o n t h a t f a i l s t o grow s h a l l be r e p l a c e d by t h e Contrac-
t o r , a t h i s expense, w i t h f r e s h grass o r o t h e r v e g e t a t i o n o r seed, as appropriate,
u n t i l s a t i s f a c t o r y cover i s obtained.
5.2.4.4 P i t c h i n g o f surfaces. On completion o f f i n a l grading i n terms o f 5.2.4.1,
designated surfaces s h a l l , where so scheduled, be p i t c h e d w i t h stone o r o t h e r
m a t e r i a l s o f t h e type and i n t h e manner shown on t h e drawings and s p e c i f i e d i n
SABS 1200 DK.
5.2.4.5 Gabions. Where scheduled, gabions s h a l l be c o n s t r u c t e d t o t h e d e t a i l s and i n t h e
manner s p e c i f i e d i n SABS 1200 DK.
5.2.5 Transport f o r Earthworks
5.2.5.1 Freehaul
m a u l o f m a t e r i a l imported from commercial sources o r from borrow p i t s
s e l e c t e d by t h e C o n t r a c t o r w i l l be regarded as f r e e h a u l .
b ) Provided t h a t , where a p p l i c a b l e ,
1 ) t h e drawings c l e a r l y show t h e boundaries of t h e area w i t h i n which t h e whole o f
t h e work ( i n c l u d i n g borrowing and s p o i l i n g ) i s t o be c a r r i e d o u t and t h a t t h i s area
does n o t exceed 1,5 km x 1,5 km;
2) t h e drawings o r mass diagrams ( o r b o t h ) c l e a r l y show t h e distances and t h e quan-
t i t i e s t o be moved i n a s e r i e s o f c u t and f i l l operations ( i n c l u d i n g borrowing and
s p o i l i n g ) w i t h i n a p r e s c r i b e d servitude, wayleave o r reserve;
3) t h e drawings c l e a r l y show t h e l o c a t i o n and distances o f a l l excavations and
designated borrow p i t s , embankments t o be formed and d i s p o s a l areas, as r e l e v a n t ;
and provided t h a t freehaul d i s t a n c e s have n o t been s p e c i f i c a l l y s t a t e d elsewhere i n
t h e c o n t r a c t documents, a l l haul, i n a d d i t i o n t o t h a t o f ( a ) above, w i l l be
regarded as f r e e h a u l .
I n t h e case o f any o f t h e a p p l i c a b l e p r o v i s i o n s l i s t e d i n (b)(l)-(3) above f o r
which i n f o r m a t i o n has n o t been given, and p r o v i d e d t h a t no o t h e r f r e e h a u l d i s t a n c e
has been s p e c i f i e d elsewhere i n t h e c o n t r a c t documents, t h e freehaul d i s t a n c e
w i t h i n which t h e Contractor w i l l be r e q u i r e d t o move m a t e r i a l w i t h o u t separate com-
pensation s h a l l be 0,5 km .
5.2.5.2 Overhaul. T r a n s p o r t a t i o n o f a l l excavated m a t e r i a l beyond the freehaul d i s t a n c e s
a p p l i c a b l e w i l l be regarded as overhaul. Overhaul w i l l be c l a s s i f i e d as e i t h e r
l i m i t e d overhaul o r l i m i t e d overhaul p l u s l o n g overhaul (see 8.3.6) based on t h e
f o l l o w i n g ranges:
6. TOLERANCES
6.1 POSITION, DIMENSIONS, LEVELS, ETC. The work s h a l l be f i n i s h e d t o Degree o f
Accuracy I 1 and t h e p e r m i s s i b l e d e v i a t i o n s (PD) [see Clause 6 o f SABS 1200 A o r
Clause 6 o f SABS 1200 AA, as a p p l i c a b l e ) s h a l l , s u b j e c t t o Subclause 6.3 o f
SABS 1200 A o r AA, as a p p l i c a b l e , be w i t h i n t h e l i m i t s g i v e n below f o r Degree o f
Accuracy 11:
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.
P e r m i s s i b l e d e v i a t i o n (PD)
Degree o f Accuracy
111 I1 I
mm mm mm
a) Excavations f o r s t r u c t u r a l foundations
1) P o s i t i o n on p l a n
PD i n p l a n o f any p o i n t measured f r o m t h e n e a r e s t g r i d l i n e
Dimensions o n p l a n
... P 50 f 35 k 25
PD f r o m t h e d e s i g n d i m e n s i o n s ....................... ......... f 75 i: 50 i: 25
F o u n d a t i o n l e v e l - ( i .e. l e v e l o f u n d e r s i d e o f c o n c r e t e e x c e p t
f l o o r slab)
PD i n l e v e l o f s u r f a c e o f e x c a v a t i o n trimmed t o r e c e ve
concrete ........................................... ......... i: 75 f 50 i: 25
Leve 1
PD f r o m d e s i g n e d l e v e l w i t h r e f e r e n c e t o t h e n e a r e s t
t r a n s f e r r e d bench-mark o f any f l o o r s l a b ........... ......... r 20 k 15 i: 10
T e r r a c e s and embankments
P o s i t i o n o f t o p edge o f t e r r a c e *
PD f r o m d e s i g n a t e d p o s i t i o n o f any p o i n t , measured f r o m
nearest g r i d l i n e ............................................ f 450 P 300 i: 150
A l i g n m e n t o f t o p edge o f t e r r a c e ”
PD f r o m a l i n e j o i n i n g any two p o i n t s 30 in a p a r t on t o p
edge o f t e r r a c e .............................................. 2 200 i: 100 i: 50
Finished l e v e l s
PD f r o m d e s i g n a t e d l e v e l s with r e f e r e n c e t o n e a r e s t tran!?
f e r r e d bench mark ............................................ f 150 i: 50 2 50
Slopes o f t o p surfaces
....................................
PD f r o m d i r e c t i o n o f s l o p e ni1 ni1 nil
PD f r o m r a t e o f f a l l :
xx 7
1 i n 100 t o 1 i n 300 .......................................... 20 10 5
1 i n 400 and f l a t t e r .......................................... 10 5 2
“ S u b j e c t t o t h e b r e a k l i n e between i n t e r s e c t i n g s l o p e s b e i n g a c c e p t a b l y s t r a i g h t .
Permissible deviation
Degree o f a c c u r a c y
7. TESTING
7.1 EXPLORATORY HOLES. To d e t e r m i n e f o u n d i n g c o n d i t i o n s o r f o r o t h e r purposes, t h e
E n g i n e e r may r e q u i r e t h e C o n t r a c t o r t o dri.11, auger o r e x c a v a t e h o l e s i n advance o f
t h e s t a r t of c o n s t r u c t i o n . When so r e q u e s t e d by t h e Engineer, t h e C o n t r a c t o r s h a l l
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.
--------------------___r_______
a ) U n t i l SABS 1200 DB, SABS 1200 DM, SABS 1200 ME and SABS 1200 MF a r e amended, those s p e c i f i -
c a t i o n s should be amended i n t h e p r o j e c t s p e c i f i c a t i o n t o a l i g n t h e i r overhaul measurement
with t h a t o f t h i s s p e c i f i c a t i o n .
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.
The r a t e f o r i m p o r t i n g f r o m d e s i g n a t e d b o r r o w p i t s s h a l l c o v e r t h e c o s t , a d d i t i o n a l
t o 8.3.2 o r 8.3.3, o f r o y a l t i e s i f a p p l i c a b l e , e x c a v a t i o n , s e l e c t i o n o f s u i t a b l e
m a t e r i a l , loading, t r a n s p o r t a t i o n ( s e e 5.2.5.1), and o f f l o a d i n g a t p o i n t o f
placing .
b ) Opening up and c l o s i n g down o f d e s i g n a t e d b o r r o w p i t ......................... U n i t : Sum
T h i s i t e m w i l l be scheduled o n l y when a new b o r r o w p i t has t o be e s t a b l i s h e d o r
when access t o an e x i s t i n g borrow p i t has t o be e s t a b l i s h e d . With t h e e x c e p t i o n o f
t h e c o s t s covered by ( c ) below, t h e r a t e s h a l l c o v e r t h e c o s t o f opening up and o f
r e s t o r i n g t h e s i t e as s p e c i f i e d i n 5.2.2.2.
c ) D e a l i n g with overburden ( d e s i g n a t e d b o r r o w p i t s o n l y ) ........................ U n i t : m3
The volume o f overburden w i l l be c a l c u l a t e d bv t h e method o f averaae end a r e a s as
d e t e r m i n e d f r o m t h e p l a n a r e a o f t h e b o r r o w p j t and t h e d e p t h o f m a t e r i a l t o be
removed, measured by means o f t r i a l h o l e s spaced a t i n t e r v a l s o f 10 m o r by s u r -
v e y i n g b e f o r e and a f t e r i t s removal. The r a t e s h a l l c o v e r t h e c o s t o f d i g g i n g t r i a l
h o l e s , removing o v e r b u r d e n t o s t o c k p i l e and s p r e a d i n g o v e r b u r d e n e v e n l y o v e r t h e
f l o o r and s i d e s o f t h e borrow p i t when b o r r o w i n g i s complete.
8.3.5 E x t r a E x c a v a t i o n i n a l l M a t e r i a l s t o P r o v i d e Working Space around S t r u c t u r e ..... Un t: m2
The a r e a w i l l be computed f r o m t h e p e r i m e t e r o f t h e s t r u c t u r e and t h e average d e p t h
o f e x c a v a t i o n on t h e p e r i m e t e r o f t h e s t r u c t u r e .
The r a t e s h a l l c o v e r t h e c o s t o f t h e o p e r a t i o n s s p e c i f i e d i n 8.3.3(a) i n r e s p e c t o f
t h e e x c a v a t i o n o f an a r e a t h a t i s wide enough f o r w o r k i n g space.
8.3.6 Overhaul ( s e e 5.2.5.2)
g ) e d ...............................................
overhaul ( p r o v i s i o n a l ) Un t: m3
b ) Long o v e r h a u l ( p r o v i s i o n a l ) .................................................. Un t: m3.km
I t e m s ( a ) and ( b ) above a r e a p p l i c a b l e o n l y when t h e a p p r o p r i a t e i n f o r m a t i o n o f
t h a t s e t o u t i n 5.2.5.1(b) was n o t a v a i l a b l e t o t h e C o n t r a c t o r a t t h e t e n d e r i n g
stage.
Volumes w i l l be computed f r o m t h e d e s i g n a t e d dimensions. No a l l o w a n c e w i l l be made
f o r b u l k i n g . Long o v e r h a u l d i s t a n c e s w i l l be measured t o t h e n e a r e s t 0 , l km f r o m
t h e end o f t h e l i m i t e d o v e r h a u l range, i n one d i r e c t i o n o n l y , by t h e s h o r t e s t p r a c -
t i c a b l e r o u t e . M a t e r i a l measured f o r o v e r h a u l u n d e r ( b ) above w i l l a l s o be measured
under ( a ) above.
8.3.7 ........
A d d i t i o n a l L a t e r a l Support between .......... and i f ordered
(provisional) ................................................................... U n i t : Sum
T h i s i t e m may be scheduled as a p r o v i s i o n a l sum t o c o v e r payment f o r
a ) e n s u r i n g t h e s t a b i l i t y o f a p a r t i c u l a r s t r u c t u r e o r any s e r v i c e o r o t h e r p a r t o f
t h e Works t h a t has been s p e c i f i e d i n t h e p r o j e c t s p e c i f i c a t i o n , o r d e s c r i b e d ade-
q u a t e l y elsewhere a t t h e t e n d e r stage, and t h a t may be a t r i s k because o f t h e
p r o x i m i t y o f t h e s l o p e o f a f a c e excavated i n t e r m s o f 5.1.1.2(b);
b ) l a t e r a l s u p p o r t o r d e r e d by t h e Engineer t o ensure t h e s t a b i l i t y o f a f e a t u r e o r
a b n o r m a l i t y t h a t cannot be d e s c r i b e d a d e q u a t e l y a t t h e t e n d e r s t a g e .
Where s u p p o r t i n terms o f ( a ) o r ( b ) above i s o r d e r e d by t h e Engineer, t h e method
may be agreed between t h e Engineer and t h e C o n t r a c t o r , b u t t h e r a t e f o r ( a ) above
s h a l l c o v e r t h e c o s t o f d e s i g n i n g ( i f designed by t h e C o n t r a c t o r ) , p r o v i d i n g ,
i n s t a l l i n g , m a i n t a i n i n g and removing l a t e r a l s u p p o r t t h a t i s p r o v i d e d t o p r e s e r v e
t h e s t a b i l i t y o f t h e s t r u c t u r e , s e r v i c e , o r o t h e r p a r t o f t h e Works, as s p e c i f i e d ,
and payment f o r ( b ) above w i l l be a t a p r i c e t o be agreed upon or, i f agreement
cannot be reached, a t daywork r a t e s .
Where a d d i t i o n a l s u p p o r t i s measured by area, t h e a r e a w i l l be computed by
m u l t i p l y i n g t h e v e r t i c a l d e p t h by t h e l e n g t h o f t h e f a c e o r f a c e s o r d e r e d t o be
suooorted.
8.3.8 E i i k t i n g S e r v i c e s ( s e e 5.1.2.2)
8.3.8.1 L o c a t i o n . Where p a r t i c u l a r items a r e p r o v i d e d i n o t h e r s e c t i o n s o f t h e schedule,
t h e c o s t s o f d e t e c t i o n , exposure, p r o t e c t i o n and a l t e r a t i o n s s h a l l be c o v e r e d by
such p a r t i c u l a r items, Where no such p a r t i c u l a r i t e m s a r e p r o v i d e d and where t h e r e
i s reason t o e x p e c t t h e presence o f s e r v i c e s , t h e f o l l o w i n g items w i l l a p p l y :
a ) Supply ( u n l e s s h i r e d under i t e m ( b ) below) o f s p e c i a l i s t equipment f o r
detection ....................................................................... U n i t : Sum
b r ........................
e o r h i r e o f s p e c i a l i s t equipment f o r d e t e c t i o n U n i t : Hour
(norma 1
working)
o r sum
c ) Excavate by hand i n s o f t m a t e r i a l t o expose .......... service ............... U n i t : m3 o r
daywork
The r a t e s f o r ( b ) and ( c ) above s h a l l c o v e r t h e c o s t o f d e l a y s and d i s r u p t i o n o f
t h e p r o g r e s s o f t h e work caused by t h e s e a r c h f o r t h e p a r t i c u l a r s e r v i c e , i n a d d i -
t i o n t o the c o s t o f searching f o r it.
8.3.8.2 D e a l i n g w i t h s e r v i c e s t h a t a r e a t r i s k because o f t h e c o n s t r u c t i o n o f e a r t h w o r k s
a ) Cables (PS..1 ................................................................ U n i t : No.
The u n i t means one c a b l e or, i f t h e r e a r e more t h a n one, any number o f c a b l e s so
grouped t h a t t h e c r o s s - s e c t i o n c o n t a i n i n g them has a h o r i z o n t a l d i m e n s i o n n o t
e x c e e d i n g 200 mm .
b) Permanent p r o t e c t i o n o f ...... s e r v i c e (PS..) ................................ U n i t : Sum
o r daywork
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.
The rate shall cover the cost of grassing or other covei" as specified in 5.2.4.3.
8.3.12 Road Traffic Signs and Markings .................................................
Separate items will be scheduled for each different size or type of road traffic
Unit: No.
sign. All items except painted lines will be measured by number. Painted lines will
be measured linearly, separate items being scheduled for continuous and for broken
lines. In the case of broken lines, no deduction will be made for unpainted breaks.
The rate shall cover the cost of providing and erecting signs or providing painted
markings in terms of 5.1.6, as applicable.
8.3.73 Daywork. See SABS 1200 A or the project specification, 13s applicable.
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.
El
U
Hard rock: subclause 8.3.2(b)
.-0 E
.-0
4
0
>
0
U
X
W
-U
E
0
Y
I
n
This eStandard is exclusively for use on one standalone PC. To access it from a file server/Intranet constitutes a violation
of SABS copyright rules. Note that only one printout of the standard may be made.