You are on page 1of 88

NORTHERN POWER DISTRIBUTION COMPANY

OF TELANGANA LIMITED
Vidyuth Bhavan :: Warangal

COST DATA
FOR THE YEAR
2018-19

. . .
INDEX

Sl.No. Description
I Rates for CENTRALIZED MATERIALS
II ABSTRACT of Schedules of Unit Rates
III Cost Data for CORPORATIONS & MUNICIPALITIES AND AGENCY / TRIBAL AREAS
IV Material Rates for Fabricated Items
Cost data per Km. of 33 kv line (SC) with 100 sq.mm AAA conductor over 11 mts. PSCC poles at
1
80 mts. Span, 75 Kg/sq.mts. wind pressure, working load 365 Kgs.
Cost data per Km. of 33 kv line (DC) with 100 sq.mm AAA conductor over 11 mts. PSCC poles at
2
40 mts. Span, 75 Kg/sq.mts. wind pressure, working load 365 Kgs.
Cost data per Km. of 33 kv line with 100 sq.mm AAA conductor over 9.1 mts. PSCC poles at 80
3
mts. Span, 75 Kg/sq.mts. wind pressure, working load 280 Kgs.
Cost data per Km. of 33 kv line with 100 sq.mm AAA conductor over 9.1 mts. PSCC poles at 65
4
mts. Span, 75 Kg/sq.mts. wind pressure, working load 280 Kgs.
Cost data per Km. of 11 kv line with 55 sq.mm AAA conductor over 9.1 mts. PSCC poles at 60 mts.
5
Span, 75 Kg/sq.mts. wind pressure, working load 280 Kgs.
Cost data per Km. of 11 kv line with 34 sq.mm AAA conductor over 9.1 mts. PSCC poles at 60 mts.
6
Span, 75 Kg/sq.mts. wind pressure, working load 280 Kgs.
Cost data per Km. of 11 kv line with 55 sq.mm AAA conductor over 8 mts. PSCC poles at 60 mts.
7
Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

Cost data per Km. of 11 kv line with 34 sq.mm AAA conductor over 8 mts. PSCC poles at 60 mts.
8
Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

Cost data per Km. of 6.3 kv S-ph line with 34 sq.mm AAA conductor over 8 mts. PSCC poles at 80
9
mts. Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.
Cost data per Km. of LT 3-ph 5 Wire line (Horizontal formation) with 3x55+2x34 sq.mm AAA
10 Conductor over 8 mts. PSCC poles at 65 mts. Span, 75 Kg/sq.mts. wind pressure, working load
140 Kgs.
Cost data per Km. of LT 3-ph 5 Wire line (Horizontal formation) with 3x55+2x34 sq.mm AAA
11 Conductor over 8 mts. PSCC poles at 40 mts. Span, 75 Kg/sq.mts. wind pressure, working load
140 Kgs.

Cost data per Km. of LT 3-ph 5 Wire line (Horizontal formation) with 5x34 sq.mm AAA Conductor
12
over 8 mts. PSCC poles at 40 mts. Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

Cost data per Km. of LT 3-ph 4 Wire line (Horizontal formation) with 3x55+1x34 sq.mm AAA
13 Conductor over 8 mts. PSCC poles at 40 mts. Span, 75 Kg/sq.mts. wind pressure, working load
140 Kgs.

Cost data per Km. of LT 3-ph 4 Wire line (Horizontal formation) with 4x34 sq.mm AAA Conductor
14
over 8 mts. PSCC poles at 50 mts. Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

Cost data per Km. of LT S-ph 3 Wire line (Horizontal formation) with 34 sq.mm AAA Conductor
15
over 8 mts. PSCC poles at 50 mts. Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

Cost data per Km. of LT S-ph 2 Wire line (Horizontal formation) with 2x34 sq.mm AAA Conductor
16
over 8 mts. PSCC poles at 50 mts. Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

Cost data per Km. of LT line with 3x16+25 sq.mm AB Cable over 8 mts. PSCC poles at 65 mts.
17
Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

Cost data per Km. of LT line with 2x16+25 sq.mm AB Cable over 8 mts. PSCC poles at 65 mts.
18
Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.
Cost data for erection of 100 kva - 11 kv/433 V CSP / Amourphous coreDTR (Al) - BIS level -2
19
Transformer on DP Structure
Cost data for erection of 100 kva - 11 kv/433 V CSP / Amourphous core DTR (Al) - BIS level 3
20
Transformer on DP Structure
Cost data for erection of 63 kva - 11 kv/433 V CSP / Amourphous core DTR (Al) - BIS level 3
21
Transformer on DP Structure
Cost data for erection of 25 kva 3-ph 11 kv/433 V CRGO / Amourphous core DTR (Al) - BIS level 2
22
Transformer

. . .
Sl.No. Description
Cost data for erection of 25 kva S-ph 6.3 kv/0-240 V CSP 25 kva S-ph CRGO / Amourphous core
23
DTR (Al) - BIS level 2 Transformer on existing 8 mts. PSCC support

24 Cost data for Release of Poly phase Agricultural service erected on support

Cost data for Release of Domestic and Non-Domestic Service Connection (S-ph) with Electronic
25
meter

. . .
Sl.No. Description

26 Cost data for Domestic and Non-Domestic Service Connection (3-ph) with Electronic meter

Cost data for Poly phase Service connection charges for erection of 1 No. Industrial service (Below
27
20 HP) (Electronic meter)
Cost data for Poly phase Service connection charges for erection of 1 No. Industrial service (20 HP
28
to 50 HP) (LT Trivector meter)
Cost data for Poly phase Service connection charges for erection of 1 No. Industrial service (50 HP
29
to 75 HP) (HT metering)
Cost data for Poly phase Service connection charges for erection of 1 No. HT service (Above 75 HP)
30
(HT metering)

31 Cost data for Street Light Service Connection (S-ph)

32 Cost data for erection of 1 No. LT Electronic Trivector meter on LV side of DTR

33 Cost data for erection of 2 MVAR Capacitor Bank

34 Cost data for erection of 11 kv Bay Extension in existing 33/11 kv SS (with RS Joist)

35 Cost data for erection of 11 kv Bay Extension in existing 33/11 kv SS (with 9.1 mts. PSCC pole)

36 Tower Details

37 Cost data for erection of M+3 Tower as per standards

38 Cost data for erection of M+6 Tower as per standards

39 Cost data for erection of M+9 Tower as per standards

40 Cost data for erection of M+12 Tower as per standards

Cost data for erection of 33/11 kv SS with 2x8 mva Power Transformer and NF = 6 No. 11 kv
41
feeders (with 11 kv 2 MVAR Capacitor Bank)
Cost data for erection of 33/11 kv SS with 2x8 mva Power Transformer and NF = 6 No. 11 kv
42
feeders (without 11 kv 2 MVAR Capacitor Bank)
Cost data for erection of 33/11 kv SS with 2x5 mva Power Transformer and NF = 4 No. 11 kv
43
feeders (with 11 kv 2 MVAR Capacitor Bank)
Cost data for erection of 33/11 kv SS with 2x5 mva Power Transformer and NF = 4 No. 11 kv
44
feeders (without 11 kv 2 MVAR Capacitor Bank)
Cost data for erection of 33/11 kv SS with 1x5 mva Power Transformer and NF = 3 No. 11 kv
45
feeders (with 11 kv 2 MVAR Capacitor Bank)
Cost data for erection of 33/11 kv SS with 1x5 mva Power Transformer and NF = 3 No. 11 kv
46
feeders (without 11 kv 2 MVAR Capacitor Bank)

. . .
I. Cost Data of Centralized Materials
for RE and Distribution works

Price
Ex- Transporta IGST@ %of Amount
Sl.No. Material Code Name of the Material PO number & Date Unit F&I variation SGST@9% CGST@9%
Works tion 18% GST (Rs.)
Amount

SUBHEAD–I: SUPPORT AND FIXTURE, STEEL AND CEMENT


1 MST00032 RS Joists 175x85 mm / 175x75 mm PM-5785, dt.03.12.2018 MT 47000.00 1472.00 4362.48 4362.48 18.00 57196.96
2 MST00029 RS Joists 150x150 mm PM-5785, dt.03.12.2018 MT 47000.00 1472.00 4362.48 4362.48 18.00 57196.96
3 MST00012 MS Channel 100x50 mm PM-5226, dt.12.06.2017 MT 45500.00 1472.00 4227.48 4227.48 18.00 55426.96
4 MST00013 MS Channel 75x40 mm PM-5226, dt.12.06.2017 MT 49000.00 1472.00 4542.48 4542.48 18.00 59556.96
5 MST00003 MS Angle 65x65x6 mm PM-5226, dt.12.06.2017 MT 48000.00 1472.00 4452.48 4452.48 18.00 58376.96
6 MST00002 MS Angle 50x50x6 mm PM-5226, dt.12.06.2017 MT 49000.00 1472.00 4542.48 4542.48 18.00 59556.96
7 MST00015 MS Flat 75x8 mm PM-5226, dt.12.06.2017 MT 47000.00 1472.00 4362.48 4362.48 18.00 57196.96
8 MST00014 MS Flat 50x6mm PM-5226, dt.12.06.2017 MT 47000.00 1472.00 4362.48 4362.48 18.00 57196.96
9 MST00019 MS Rod 20 mm PM-5226, dt.12.06.2017 MT 46000.00 1472.00 4272.48 4272.48 18.00 56016.96
10 MST00018 MS Rod 16 mm PM-5226, dt.12.06.2017 MT 46000.00 1472.00 4272.48 4272.48 18.00 56016.96
TS Transco - D.No.2555/2017,
11 OTH10466 GI S.S. Structures MT 63630.00 1472.00 5859.18 5859.18 18.00 76820.36
dt.12.10.2017
TS Transco - D.No.2555/2017,
12 EMT00023 GI Flat 25x6mm MT 52643.00 1472.00 4870.35 4870.35 18.00 63855.70
dt.12.10.2017
13 WRS00006 GI Stay wire 7/3.15 mm PM-5382, dt.30.10.2017 MT 47776.27 1800.00 4461.86 4461.86 18.00 58500.00
14 WRS00007 GI Stay wire 7/2.5 mm PM-5600, dt.22.06.2018 MT 61500.00 1500.00 5670.00 5670.00 18.00 74340.00
15 WRS00005 GI wire no. 6 (SWG) PM-5654, dt.10.07.2018 MT 54500.00 4000.00 5265.00 5265.00 18.00 69030.00
16 WRS00005 GI wire no. 8 (SWG) PM-5654, dt.10.07.2018 MT 54500.00 4000.00 5265.00 5265.00 18.00 69030.00
17 FBR00065 PSCC Pole (8 mts.) 140 Kg WL PM-5807/2018-19, dt. 30.01.2019 Each 1150.00 184.74 120.13 120.13 18.00 1574.99
18 FBR00066 PSCC Pole (9.1 mts.) 280 Kg WL RPO-5731/2018-19, dt.29.10.2018 Each 2200.00 509.69 243.87 243.87 18.00 3197.43
19 FBR00081 PSCC Pole (11 mts.) 365 Kg WL RPO-5749/2018-19, dt.29.10.2018 Each 4000.00 934.15 444.07 444.07 18.00 5822.30
20 BNT00019 Bolts and Nuts 5/8 x2 1/2" PM-5615, dt.25.06.2018 MT 59400.00 5346.00 5346.00 18.00 70092.00
21 BNT00020 Bolts and Nuts 5/8 x 3" PM-5615, dt.25.06.2018 MT 59400.00 5346.00 5346.00 18.00 70092.00
22 BNT00021 Bolts and Nuts 5/8 x 4" PM-5615, dt.25.06.2018 MT 59400.00 5346.00 5346.00 18.00 70092.00

I . Pg: 1 / 8
Price
Ex- Transporta IGST@ %of Amount
Sl.No. Material Code Name of the Material PO number & Date Unit F&I variation SGST@9% CGST@9%
Works tion 18% GST (Rs.)
Amount

SUBHEAD–II: INSULATOR AND HARDWARE


23 INS30001 33 kv Pin Insulator PM-5344, dt.10.10.2017 Each 169.00 34.00 18.27 18.27 18.00 239.54
24 HWR00003 33 kv GI Pin PM-4469, dt.24.03.2015 Each 140.00 5.50 13.10 13.10 18.00 171.69
25 INS30003 33 kv Post type Insulators PM-5761, dt.01.11.2018 Each 855.76 77.02 77.02 18.00 1009.80
26 HWR00004 33 kv Hard Ware Fittings (B&S) PM-4857, dt.01.04.2016 Each 159.00 14.31 14.31 18.00 187.62
27 INS30007 33 kv Polymer String Insulator (B&S) PM-5405, dt.18.11.2017 Each 221.19 19.91 19.91 18.00 261.00
28 INS30002 33 kv Solid core Insulator RPM 5763, dt.01.11.2018 Each 1547.62 139.29 139.29 18.00 1826.19
29 INS10001 11 kv Pin Insulator PM-5342, dt.10.10.2017 Each 29.50 6.00 3.20 3.20 18.00 41.89
30 HWR00001 11 kv GI Pin PM-5372, dt.26.10.2017 Each 50.64 4.56 4.56 18.00 59.76
31 INS10008 11 kv Post type Insulator RPM-5762, dt.01.11.2018 Each 233.00 20.97 20.97 18.00 274.94
32 INS10004 11 kv String Insulator (B&S) PM-4824, dt.15.03.2016 Each 175.00 25.00 18.00 18.00 18.00 236.00
33 INS10002 11 kv String Insulator (C&T) PM-4518, dt.24.06.2015 Each 178.00 27.00 18.45 18.45 18.00 241.90
34 HWR00002 11 kv String Hardware Fitting (C&T) PM-5328, dt.27.09.2017 Each 63.00 7.17 6.32 6.32 18.00 82.80
35 INS10003 11 kv Polymer String Insulator (C&T) PM-5426, dt.05.12.2017 Each 112.00 10.08 10.08 18.00 132.16
36 INS10007 11 kv Solid core Insulator HG Fuse set RPM-5480, dt.19.02.2018 Each 151.00 13.59 13.59 18.00 178.18
37 INS10006 11 kv Solid core Insulator AB switch Extn&RPM-5764, dt.01.11.2018 Each 223.73 20.14 20.14 18.00 264.00
38 INS00001 LT Pin Insulator PM-5327, dt.27.09.2017 Each 19.00 1.71 1.71 18.00 22.42
39 HWR00015 LT GI Pin PM-5391, dt.08.11.2017 Each 25.00 2.00 2.43 2.43 18.00 31.86
40 INS00002 LT Shackle Insulator PM-5348, dt.13.10.2017 Each 15.00 3.00 1.62 1.62 18.00 21.24
41 HWR00016 LT Shackle Hardware PM-5330, dt.27.09.2017 Each 27.00 1.00 2.52 2.52 18.00 33.04
42 INS00003 LT Guy Insulator PM-5345, dt.13.10.2017 Each 21.36 1.92 1.92 18.00 25.20
43 INS10005 HT Guy Insulator RPM-5757, dt.01.11.2018 Each 39.00 6.00 4.05 4.05 18.00 53.10
44 BNT00037 CI Knob Old Rate (2015-16 Cost data ) Each 11.01 0.99 0.99 18.00 12.99

I . Pg: 2 / 8
Price
Ex- Transporta IGST@ %of Amount
Sl.No. Material Code Name of the Material PO number & Date Unit F&I variation SGST@9% CGST@9%
Works tion 18% GST (Rs.)
Amount

SUBHEAD–III: CONDUCTOR AND CABLE


TS SPDCL Latest Cost Data 2018-19
45 CDR00010 ACSR Panther Conductor (200 sq.mm) Km 124400.00 900.00 11277.00 11277.00 18.00 147854.00
(PM-1508/17, Dt.09.03.2018)

100 sq.mm AAA Conductor or 7/4.26


46 CDR00004 PM-5650, dt.06.07.2018 Km 47879.00 4309.11 4309.11 18.00 56497.22
AAAC
TS SPDCL Latest
55 sq.mm AAA Conductor or 7/3.15
47 CDR00003 Cost Data 2018-19 Km 22850.00 520.00 2103.30 2103.30 18.00 27576.60
AAAC/Rabbit
(Rpt.PM-1402/17, Dt.01.12.2017)
34 sq.mm AAA Conductor or 7/2.50
48 CDR00002 Extn PM-5693, dt.29.09.2018 Km 15232.11 1370.89 1370.89 18.00 17973.89
AAAC/Weasel
SUBHEAD–IV(A): LT PVC SINGLE CORE CABLE
49 CBX00022 6 sq.mm Old Rate (2015-16 Cost data ) 100 mts. 466.67 42.00 42.00 18.00 550.67

50 CBX00023 10 sq.mm Old Rate (2015-16 Cost data ) 100 mts. 740.44 66.64 66.64 18.00 873.72

51 CBX00007 95 sq.mm XLPE PM-5471, dt.20.01.2018 100 mts. 5338.40 53.50 485.27 485.27 18.00 6362.44

52 CBX00008 120 sq.mm XLPE PM-5376, dt.28.10.2017 100 mts. 6449.61 150.00 593.96 593.96 18.00 7787.54

53 CBX00027 150 sq.mm XLPE PM-5366, dt.24.10.2017 100 mts. 8284.61 65.00 751.46 751.46 18.00 9852.54
SUBHEAD–IV(B): LT PVC 3.5 CORE CABLE
TS SPDCL Latest
54 CBX00011 50 sq.mm Cost Data 2018-19 100 mts. 15475.10 174.10 1408.43 1408.43 18.00 18466.06
(PM-1285/17, Dt.04.09.2017)
TS SPDCL Latest
55 CBX00012 70 sq.mm Cost Data 2018-19 100 mts. 15475.1 174.10 1408.43 1408.43 18.00 18466.06
(PM-1285/17, Dt.04.09.2017)
56 CBX00013 95 sq.mm PM-4593, dt.25.08.2015 100 mts. 21112.91 219.40 1919.91 1919.91 18.00 25172.13
57 CBX00014 120 sq.mm PM-5465, dt.23.12.2017 100 mts. 25852.37 452.42 2367.43 2367.43 18.00 31039.65
58 CBX00015 185 sq.mm PM-5466, dt.28.12.2017 100 mts. 37276.72 465.96 3396.84 3396.84 18.00 44536.36
59 CBX00016 300 sq.mm Old Rate (2015-16 Cost data ) 100 mts. 42190.05 3797.10 3797.10 18.00 49784.26

I . Pg: 3 / 8
Price
Ex- Transporta IGST@ %of Amount
Sl.No. Material Code Name of the Material PO number & Date Unit F&I variation SGST@9% CGST@9%
Works tion 18% GST (Rs.)
Amount

SUBHEAD–IV(C): LT CONTROL CABLE


TS SPDCL Latest
60 CBP00002 4x2.5 sq.mm (Cu) Cost Data 2018-19 Km 61001.00 305.00 5517.54 5517.54 18.00 72341.08
(PM-1445/17, Dt.11.01.2018)
61 CBP00006 10x2.5 sq.mm (Cu) PM-5656, dt.19.07.2018 Km 157000.00 3669.49 14460.25 14460.25 18.00 189590.00
SUBHEAD–IV(D): 11 KV & LT AERIAL BUNCHED CABLE
62 CBA10004 11KV 3x35+35 sq.mm Old Rate (2015-16 Cost data ) Km 224420.44 20197.84 20197.84 18.00 264816.12
63 CBA10005 11KV 3x70+70 sq.mm Old Rate (2015-16 Cost data ) Km 291310.22 26217.92 26217.92 18.00 343746.06
64 CBA10006 11KV 3x120+70 sq.mm Old Rate (2015-16 Cost data ) Km 435157.33 39164.16 39164.16 18.00 513485.65
65 CBA00001 1x16+25 sq.mm (LT) Old Rate (2015-16 Cost data ) Km 18682.67 1681.44 1681.44 18.00 22045.55
66 CBA00002 2x16+25 sq.mm (LT) ERPM-5754, dt.30.10.2018 Km 25755.52 606.00 2372.54 2372.54 18.00 31106.59
67 CBA00003 3x16+25 sq.mm (LT) ERPM-5755, dt.30.10.2018 Km 41013.28 3691.20 3691.20 18.00 48395.67
SUBHEAD–IV(E): LT AERIAL BUNCHED CABLE FITTING
68 HWR00018 Suspension Clamp with eye hook Old Rate (2015-16 Cost data ) Each 80.89 7.28 7.28 18.00 95.45
69 HWR00009 Dead-end Clamp with eye hooks Old Rate (2015-16 Cost data ) Each 80.89 7.28 7.28 18.00 95.45
70 HWR00013 LT Connector with Insulator Cover Old Rate (2015-16 Cost data ) Each 72.89 6.56 6.56 18.00 86.01

I . Pg: 4 / 8
Price
Ex- Transporta IGST@ %of Amount
Sl.No. Material Code Name of the Material PO number & Date Unit F&I variation SGST@9% CGST@9%
Works tion 18% GST (Rs.)
Amount

SUBHEAD–IV(F): 11 KV XLPE POWER CABLE


TS SPDCL Latest Cost Data
71 CBX10002 3x35 sq.mm (XLPE UG Cable) Km 269208.34 24228.75 24228.75 18.00 317665.84
2018-19 (PM-4327, Dt.22.04.2015)
TS SPDCL Latest Cost Data
72 CBX10005 3x95 sq.mm Km 441567.67 39741.09 39741.09 18.00 521049.85
2018-19 (PM-285, Dt.11.02.2015)
TS SPDCL Latest Cost Data
73 CBX10007 3x185 sq.mm Km 592512.00 30930.00 56109.78 56109.78 18.00 735661.56
2018-19 (PM-1144/17, Dt.11.05.2017)
TS SPDCL Latest Cost Data
74 CBX10008 3x300 sq.mm 2018-19 (PM-1127/17, Km 811937.00 41500.00 76809.33 76809.33 18.00 1007055.66
Dt.21.04.2017)
3x35 sq.mm Heat shrinkable cable
75 SCB10017 PM-4049, dt.18.07.2013 Each 584.10 11.68 53.62 53.62 18.00 703.02
jointing Kit
3x95 sq.mm Heat shrinkable cable
76 SCB10012 Old Rate (2015-16 Cost data ) Each 721.78 64.96 64.96 18.00 851.70
jointing Kit
3x185 sq.mm Heat shrinkable cable
77 SCB10010 Old Rate (2015-16 Cost data ) Each 2063.07 185.68 185.68 18.00 2434.42
jointing Kit
SUBHEAD–IV(G): 33 KV XLPE POWER CABLE
TS SPDCL Latest Cost Data
78 CBX30001 3x400 sq.mm Km 1711912.00 121716.94 165026.60 165026.60 18.00 2163682.15
2018-19 (RPT Extn PM-1501/17, )
3x400 sq.mm Raychem and Termination
79 SCB10102 Old Rate (2015-16 Cost data ) Each 31082.67 2797.44 2797.44 18.00 36677.55
Joints Kit
SUBHEAD–V: POWER TRANSFORMER, CAPACITOR AND TRANSFORMER OIL
80 PTR00006 33/11 kv 5 mva Power Transformer RPM-5595/18, dt.20.06.2018 Each 2747715.00 19234.00 355241.38 280997.13 280997.13 18.00 3684184.65
81 PTR00008 33/11 kv 8 mva Power Transformer PM-5313/17, dt.25.09.2017 Each 3837542.00 15000.37 384625.26 381345.09 381345.09 18.00 4999857.80
82 OFO10006 Transformer Oil PM-5204/17, dt.27.05.2017 Litre 54.00 4.83 5.29 5.29 18.00 69.42
11 kv 2 MVAR Capacitor Bank with
83 CPT10009 RPM-5682, dt.15.09.2018 Each 663051.00 59674.59 59674.59 18.00 782400.18
associated equipment
11 kv 1 MVAR Capacitor Bank with
84 CPT10010 PM-5680, dt.15.09.2018 Each 584362.00 52592.58 52592.58 18.00 689547.16
associated equipment
SUBHEAD–VI: DISTRIBUTION TRANSFORMER (CRGO)
25 kva S-ph CRGO / Amourphous core
85 DTC31135 PM-5784/18, dt.13.11.2018 Each 44767.80 550.00 910.93 4160.59 4160.59 18.00 54549.90
DTR (Al) - BIS level 2
25 kva 3-ph CRGO / Amourphous core
86 DTC31131 PM-5566/18, dt.13.06.2018 Each 51549.20 400.00 2000.77 4855.50 4855.50 18.00 63660.96
DTR (Al) - BIS level 2
40 kva 3-ph CRGO / Amourphous core
87 DTC31116 PM-4764, dt.30.01.2016 Each 54916.40 600.00 9693.27 5868.87 5868.87 18.00 76947.41
DTR (Al) - 3 Star (Conventional)
63 kva CSP / Amourphous core DTR
88 DTC31145 PM-5543/18, dt.29.05.2018 Each 82559.33 1000.00 12199.80 8618.32 8618.32 18.00 112995.77
(Al) - BIS level 2
63 kva CSP / Amourphous core DTR
89 DTC31144 PM-5316/17, dt.25.09.2017 Each 84975.00 2313.14 12570.23 8987.25 8987.25 18.00 117832.88
(Al) - BIS level 3
100 kva CSP / Amourphous coreDTR
90 DTC31152 PM-5779/18, dt.08.11.2018 Each 108456.27 1120.00 1949.73 10037.34 10037.34 18.00 131600.68
(Al) - BIS level -2
100 kva CSP / Amourphous core DTR
91 DTC31150 Extn. RPM-5524/18, dt.28.04.2018 Each 103307.00 812.72 10394.74 10306.30 10306.30 18.00 135127.06
(Al) - BIS level 3
160 kva CSP / Amourphous coreDTR
92 DTC31133 Extn PM-5517/18, dt.24.04.2018 Each 170201.51 3643.77 25502.07 17941.26 17941.26 18.00 235229.87
(Al) - BIS level 2
250 kva CRGO /Amourphous core
93 DTC30108 PM-3679, dt. 30.12.2011 Each 267100.00 24039.00 24039.00 18.00 315178.00
DTR
315 kva CRGO / Amorophous core
94 DTC30009 PM-4300, dt.15.11.2014 Each 469530.52 3000.00 42527.75 42527.75 18.00 557586.01
CSP Type Cu Wound Transformers
315 kva CRGO / Amorophous core
95 DTC31137 PM-5318/17, dt.25.09.2017 Each 479650.85 3400.00 62559.67 49104.95 49104.95 18.00 643820.41
(Cu)DTR BIS level 2
500 kva CRGO / Amorophous Core
96 DTC31134 Extn PM-5474/17, dt.27.01.2018 Each 733640.68 2800.00 119726.64 77055.06 77055.06 18.00 1010277.44
(Cu) DTR BIS level 3

I . Pg: 5 / 8
Price
Ex- Transporta IGST@ %of Amount
Sl.No. Material Code Name of the Material PO number & Date Unit F&I variation SGST@9% CGST@9%
Works tion 18% GST (Rs.)
Amount

SUBHEAD–VII: SWITCH CONTROL AND PROTECTIVE GEAR


97 BRK30002 33 kv VCB with CTs & Pannels Extn PM-5159, dt.07.04.2018 Each 325054.47 4000.00 29614.90 29614.90 18.00 388284.27
98 BRK10002 11 kv VCB with CTs & Panels (Feeder) RPM-5527, dt.30.04.2018 Each 200932.20 5000.00 18533.90 18533.90 18.00 243000.00
99 BRK10004 11 kv VCB with CTs & Panels (LV) PM-5519, dt.25.04.2018 Each 202627.17 5000.00 18686.45 18686.45 18.00 245000.06
100 ITR30059 33 kv CTs (400-200-100/1-1A) PM-5340/17, dt.10.10.2017 Each 18432.84 440.30 1698.58 1698.58 18.00 22270.31
101 ITR30034 33 kv CTs (100/1) 0.2 Class PM-5380/17, dt.30.10.2017 Each 12691.50 524.72 1189.46 1189.46 18.00 15595.14
102 ITR30035 33 kv CTs (200/1) 0.2 Class PM-5380/17, dt.30.10.2017 Each 12691.50 524.72 1189.46 1189.46 18.00 15595.14
103 ITR30061 33 kv CTs (50/1) 0.2 Class Old Rate (2015-16 Cost data ) Each 12895.45 1160.59 1160.59 18.00 15216.63
104 ITR30062 33 kv CTs (25/1) 0.2 Class Old Rate (2015-16 Cost data ) Each 12895.45 1160.59 1160.59 18.00 15216.63
105 ITR30058 33 kv CTs (10/1) 0.2 Class Old Rate (2015-16 Cost data ) Each 12895.45 1160.59 1160.59 18.00 15216.63
106 ITR10021 11 kv CTs (400-200-100/5-5A) PM-5341/17, dt.10.10.2017 Each 11900.25 354.00 1102.88 1102.88 18.00 14460.02
107 ITR10020 11 kv CTs (400-200-100/1-1A) PM-5341/17, dt.10.10.2017 Each 11299.55 353.00 1048.73 1048.73 18.00 13750.01
108 ITR30064 11 KV CTs (600-300/1-1A) 0.5 Class PM-5057/16, dt.14.12.2016 Each 11700.00 462.66 1094.64 1094.64 18.00 14351.94
109 ITR30065 11 KV CTs (600-300/5-5A) 0.5 Class PM-5057/16, dt.14.12.2016 Each 11700.00 462.66 1094.64 1094.64 18.00 14351.94
110 ITR30038 33 kv PT (S-ph) PM-5356/17, dt.17.10.2017 Each 16065.00 1458.00 1577.07 1577.07 18.00 20677.14
111 ITR10032 11 kv PT (3-ph) PM-5357/17, dt. 17.10.2017 Each 15668.38 518.06 1456.78 1456.78 18.00 19100.00
33 kv 800 Amps AB Switch (Double
112 ABS30004 PM-5647, dt.03.07.2018 Each 30803.39 2772.31 2772.31 18.00 36348.00
break)
11 kv 800 Amps AB Switch (Double
113 ABS10015 PM-4998, dt.01.09.2016 Each 12948.15 1165.33 1165.33 18.00 15278.82
break)
114 ABS10008 11 kv 400 Amps AB Switch PM-5361, dt.21.10.2017 Each 6300.00 567.00 567.00 18.00 7434.00
115 ABS10009 11 kv 400 Amps AB Switch Double break Rep& Extn PM-5769,dt.01.11.2018 Each 14650.00 1318.50 1318.50 18.00 17287.00
11 kv 200 Amps AB Switch (Tilting)
116 ABS10002 PM-5369, dt.24.10.2017 Each 4950.00 445.50 445.50 18.00 5841.00
(Porcelian type
11 kv 200 Amps AB Switch (Tilting)
117 ABS10017 PM-5636, dt.28.06.2018 Each 5953.70 535.83 535.83 18.00 7025.37
(Polymer Insulators
118 ABS10004 11 kv 200 Amps AB Switch (Horizontal) Extn RPM-5765, dt.01.11.2018 Each 6753.39 607.81 607.81 18.00 7969.00

30 kv 10 KA Metal Oxide Lightning


119 LAS00004 PM-5667, dt.04.08.2018 Each 2793.00 251.37 251.37 18.00 3295.74
Arrester
9 kv 10 KA Metal Oxide Lightning
120 LAS00002 PM-5666, dt.04.08.2018 Each 1400.00 126.00 126.00 18.00 1652.00
Arrester
121 LAS00001 9 kv 5 KA Metal Oxide Lightning Arrester PM-5694, dt.01.10.2018 Each 276.90 7.00 25.55 25.55 18.00 335.00

122 HGF30002 33 kv HG Fuse Set Old Rate (2015-16 Cost data ) Each 6033.78 543.04 543.04 18.00 7119.86
123 HGF10002 11 kv HG Fuse Set with insulators PM-5653, dt.09.07.2018 Each 1593.22 143.39 143.39 18.00 1880.00
124 HGF00004 LT HG Fuse Set with insulators PM-4909, dt.12.05.2016 Each 1068.00 96.12 96.12 18.00 1260.24
24 Volts 40 AH Battery set with Battery
125 BAT00027 Extn RPM-5644, dt. 02.07.2018 Set 21875.00 1968.75 1968.75 18.00 25812.50
charger
24 Volts 40 AH Battery set without
126 BAT00025 Extn PM-5645, dt. 02.07.2018 Set 5100.00 459.00 459.00 18.00 6018.00
Battery charger
127 BAT00056 12 Volts 42 AH maintenance free Battery Old Rate (2015-16 Cost data ) Set 3382.22 304.40 304.40 18.00 3991.02
128 BAT00077 12 Volts 100 AH Battery Old Rate (2015-16 Cost data ) Set 6693.33 602.40 602.40 18.00 7898.13

I . Pg: 6 / 8
Price
Ex- Transporta IGST@ %of Amount
Sl.No. Material Code Name of the Material PO number & Date Unit F&I variation SGST@9% CGST@9%
Works tion 18% GST (Rs.)
Amount

SUBHEAD–VIII: ENERGY METER AND METERING EQUIPMENT


LT S-ph (5-30A) IRDA Electronic Energy
129 MTE10016 RPM-5658, dt.25.07.2018 Each 521.74 19.79 48.74 48.74 18.00 639.01
meter (with PP Box)
LT S-ph (5-30A) IRDA Electronic Energy
130 MTE10017 PM-5687, dt.19.09.2018 Each 452.88 4.55 41.17 41.17 18.00 539.77
meter (without PP Box)
131 MTE30001 LT 3-ph Electronic meter 10-40A RPM-5495, dt.19.03.2018 Each 1525.50 40.50 140.94 140.94 18.00 1847.88
LT 3-ph Class-0.5 Accuracy CT
132 MTO10020 RPM-5540, dt. 23.05.2018 Each 5361.39 150.00 496.03 496.03 18.00 6503.44
operated Electronic meter (125/5A)
LT 3-ph Class-0.5 Accuracy CT
133 MTO10034 operated Electronic meter (250/5A) Old Rate (2015-16 Cost data ) Each 5485.71 493.71 493.71 18.00 6473.14
without Box and CTs
HT Trivector meter (Electronic) (0.5
134 MHT10030 PM-4272, dt.27.10.2014 Each 3915.12 25.00 354.61 354.61 18.00 4649.34
Class)
HT Trivector meter (Electronic) (0.2
135 MHT10032 PM-5286, dt.07.08.2017 Each 5084.00 457.56 457.56 18.00 5999.12
Class)
TS SPDCL Latest
11 kv CTPT set (10/5A) (20/5A) (40/5A)
136 ITR10006 Cost Data 2018-19 Each 32600.00 373.27 2967.59 2967.59 18.00 38908.46
0.2S Class
(PM-843/16, Dt.06.08.2016)
TS SPDCL Latest
137 ITR10009 11 kv CTPT set (60/5A) 0.2S Class Cost Data 2018-19 Each 32600.00 373.27 2967.59 2967.59 18.00 38908.46
(PM-843/16, Dt.06.08.2016)
138 ITR10036 11 kv Metering set (10/5A, 0.5 Class) PM-4142, dt.20.03.2014 Each 29000.00 472.27 2652.50 2652.50 18.00 34777.28
139 ITR10037 11 kv Metering set (20/5A, 0.5 Class) PM-4142, dt.20.03.2014 Each 29000.00 472.27 2652.50 2652.50 18.00 34777.28
140 ITR10040 11 kv Metering set (10/5A, 0.2 Class) PM-5660, dt.26.07.2018 Each 28017.00 2394.00 2736.99 2736.99 18.00 35884.98
141 ITR10041 11 kv Metering set (20/5A, 0.2 Class) PM-5660, dt.26.07.2018 Each 28017.00 2394.00 2736.99 2736.99 18.00 35884.98
142 ITR10042 11 kv Metering set (40/5A, 0.2 Class) PM-5660, dt.26.07.2018 Each 28017.00 2394.00 2736.99 2736.99 18.00 35884.98
143 BXS00031 SMC Box for 3-ph Energy meter Old Rate (2015-16 Cost data ) Each 619.56 55.76 55.76 18.00 731.08
144 BXS00037 GI HT Meter Box Old Rate (2015-16 Cost data ) Each 4000.00 360.00 360.00 18.00 4720.00

I . Pg: 7 / 8
Price
Ex- Transporta IGST@ %of Amount
Sl.No. Material Code Name of the Material PO number & Date Unit F&I variation SGST@9% CGST@9%
Works tion 18% GST (Rs.)
Amount

SUBHEAD–IX: EARTHING MATERIAL


C.I Earth Pipes, 50mm Dia, 2.0 mts long
145 EMT00022 PM-5445, Dt.16-12-2017 Each 1343.23 120.89 120.89 18.00 1585.01
with a weight of 24.5 kg ±5% tolerance
CI Earth pipe 80 mm (2.5 mts. length, 3
146 EMT00006 RPM-5786, dt.04.12.2018 Each 2796.61 251.69 251.69 18.00 3300.00
mm thickness)
147 OTH10106 Fire Extinguisher 5 Kg PM-4783, dt.08.02.2016 Each 3450.00 310.50 310.50 18.00 4071.00
33 kv 'V' x-arm with MS Channel 100x50
148 FBR00030 Each 1206.78 108.61 108.61 18.00 1424.00
mm
33 kv Horizontal x-arm with MS Channel
149 FBR00102 Each 1143.22 102.89 102.89 18.00 1349.00
100x50 mm
150 FBR00028 33 kv Back clamp with MS Flat 75x8 mm 166.10 14.95 14.95 18.00 196.00
33 kv Stay clamp set with MS Flat 75x8
151 FBR00029 251.69 22.65 22.65 18.00 297.00
mm
33 kv MS Stay set without base plate &
152 FBR00033 1381.36 124.32 124.32 18.00 1630.00
concreting
33 kv Bracing set with double x-arm
153 FBR00103 7992.37 719.31 719.31 18.00 9431.00
without stays and concreting
154 FBR00031 33 kv Top fitting with clamp 380.51 34.25 34.25 18.00 449.00
33 kv T-raiser with MS Channel 100x50
155 FBR00094 1960.17 176.42 176.42 18.00 2313.00
mm
11 kv 'V' x-arm with MS Channel 75x40
156 FBR00021 637.29 57.36 57.36 18.00 752.00
mm
11 kv Horizontal x-arm with MS Channel
157 FBR00024 642.37 57.81 57.81 18.00 758.00
75x40 mm
158 FBR00001 11 kv Back clamp with MS Flat 50x6 mm 57.63 5.19 5.19 18.00 68.00
11 kv Stay clamp set with MS Flat 50x6
159 FBR00003 93.22 8.39 8.39 18.00 110.00
mm
11 kv MS Stay set without base plate &
160 FBR00026 1044.92 94.04 94.04 18.00 1233.00
concreting
11 kv Bracing set with double x-arm
161 FBR00104 7072.88 636.56 636.56 18.00 8346.00
without stays and concreting
162 FBR00025 11 kv Top fitting with clamp 227.97 20.52 20.52 18.00 269.00
11 kv T-raiser with MS Channel 75x40
163 FBR00057 1284.75 115.63 115.63 18.00 1516.00
mm
164 FBR00056 11 kv Side arm 1188.14 106.93 106.93 18.00 1402.00
165 FBR00007 LT 3-ph 5 W/L Angle x-arm 50x50x6 mm 478.81 43.09 43.09 18.00 565.00

166 FBR00006 LT 3-ph 4 W/L Angle x-arm 50x50x6 mm 371.19 33.41 33.41 18.00 438.00

167 FBR00107 LT 3-ph 3 W/L Angle x-arm 50x50x6 mm 272.03 24.48 24.48 18.00 321.00

168 FBR00004 LT S-ph 2 W/L Angle x-arm 50x50x6 mm 172.88 15.56 15.56 18.00 204.00
169 FBR00018 LT 3-ph 4 W/LT-raiser 50x50x6 mm 1013.56 91.22 91.22 18.00 1196.00
170 OTH10454 M+3 Tower - 1.946 MT, 16.9 Mts 94321.66 8488.95 8488.95 18.00 111299.56
171 OTH10453 M+6 Tower - 2.379 MT, 19.9 Mts 115329.43 10379.65 10379.65 18.00 136088.73
172 OTH10455 M+9 Tower - 2.813 MT, 22.9 Mts 136351.74 12271.66 12271.66 18.00 160895.05
173 OTH10456 M+12 Tower - 3.246 MT, 25.9 Mts 157340.11 14160.61 14160.61 18.00 185661.33

I . Pg: 8 / 8
Data for RE schemes
II. Abstract of schedule of rates for 2018-19 Cost Data per Km. of 33/11 kv & LT lines

Wind W. No.of
Type of pole Span
Sl.No. Particulars of items Pr. in Load poles/ Size of conductor Amount (Rs)
being used (mts.)
Kg/m2 in Kg Km

Erection of Line
1 33 kv SC line 75 365 11 mts. PSCC 14 80 100 sq.mm AAAC 574720
2 33 kv DC line 75 365 11 mts. PSCC 26 40 100 sq.mm AAAC 1256670
3 33 kv SC line 75 280 9.1 mts. PSCC 14 80 100 sq.mm AAAC 470980
4 33 kv SC line 75 280 9.1 mts. PSCC 17 65 100 sq.mm AAAC 513630
5 11 kv SC line 75 280 9.1 mts. PSCC 18 60 55 sq.mm AAAC 369960
6 11 kv SC line 75 140 9.1 mts. PSCC 18 60 34 sq.mm AAAC 357890
7 11 kv SC line 75 140 8 mts. PSCC 18 60 55 sq.mm AAAC 306600
8 11 kv SC line 75 140 8 mts. PSCC 18 60 34 sq.mm AAAC 272120
9 6.3 kv line 75 140 8 mts. PSCC 13 80 34 sq.mm AAAC 154850
LT 3-ph 5 Wire line 3x55+2x34 sq.mm
10 75 140 8 mts. PSCC 16 65 326510
(Horizontal) AAA
LT 3-ph 5 Wire line 3x55+2x34 sq.mm
11 75 140 8 mts. PSCC 26 40 394480
(Horizontal) AAA
LT 3-ph 5 Wire line
12 75 140 8 mts. PSCC 26 40 5x34 sq.mm AAA 359990
(Horizontal)
LT 3-ph 4 Wire line 3x55+1x34 sq.mm
13 75 140 8 mts. PSCC 26 40 358380
(Horizontal) AAA
LT 3-ph 4 Wire line
14 75 140 8 mts. PSCC 20 50 4x34 sq.mm AAA 285030
(Horizontal)
LT 1-ph 3 Wire line
15 75 140 8 mts. PSCC 20 50 3x34 sq.mm AAA 246000
(Horizontal)
LT 1-ph 2 Wire line
16 75 140 8 mts. PSCC 20 50 2x34 sq.mm AAA 203060
(Horizontal)
17 LT AB Cable 75 140 8 mts. PSCC 16 65 3x16+25 sq.mm 196270
18 LT AB Cable 75 140 8 mts. PSCC 16 65 2x16+25 sq.mm 175570
Erection of Distribution Transformer
19 100 kva - 11 kv/433 V CSP / Amourphous coreDTR (Al) - BIS level -2 Transformer 277840
20 100 kva - 11 kv/433 V CSP / Amourphous core DTR (Al) - BIS level 3 Transformer 281980
21 63 kva - 11 kv/433 V CSP / Amourphous core DTR (Al) - BIS level 3 Transformer 261680
22 25 kva 3-ph 11 kv/433 V CRGO / Amourphous core DTR (Al) - BIS level 2 Transformer 170780
25 kva S-ph 6.3 kv/0-240 V CSP 25 kva S-ph CRGO / Amourphous core DTR (Al) - BIS level 2
23 96250
Transformer on existing 8 mts. PSCC support
Release of Service Connection
24 Poly phase Agricultural service erected on support 6840
25 S-ph Domestic and Non-Domestic with Electronic meter 3060
26 3-ph Domestic and Non-Domestic with Electronic meter 6110
27 Poly phase for erection of 1 No. Industrial service (Below 20 HP) 6370
28 Poly phase for erection of 1 No. Industrial service (20 to 50 HP) 13080
29 Poly phase for erection of 1 No. Industrial service (50 to 75 HP) 145650
30 Poly phase for erection of 1 No. HT service (Above 75 HP) 193810

II . Pg: 1 / 2
Wind W. No.of
Type of pole Span
Sl.No. Particulars of items Pr. in Load poles/ Size of conductor Amount (Rs)
being used (mts.)
Kg/m2 in Kg Km
31 Street Light Service Connection (S-ph) 4750
32 Erection of 1 No. LT Electronic Trivector meter on LV side of DTR 13580
33 Erection of 2 MVAR Capacitor Bank 1141580
34 Erection of 11 kv Bay Extension in existing 33/11 kv SS (with RS Joist) 104050
35 Erection of 11 kv Bay Extension in existing 33/11 kv SS (with 9.1 mts. PSCC pole) 62660
36 Erection of M+3 Tower 236080
37 Erection of M+6 Tower 268740
38 Erection of M+9 Tower 301420
39 Erection of M+12 Tower 334060
Erection of 33/11 kv Sub-station (Rs in lakhs)
40 2x8 mva PTR and NF=6 No. 11 kv feeders (with 11 kv 2 MVAR Capacitor Bank) 248
41 2x8 mva PTR and NF=6 No. 11 kv feeders (without 11 kv 2 MVAR Capacitor Bank) 238
42 2x5 mva PTR and NF=4 No. 11 kv feeders (with 11 kv 2 MVAR Capacitor Bank) 194
43 2x5 mva PTR and NF=4 No. 11 kv feeders (without 11 kv 2 MVAR Capacitor Bank) 182
44 1x5 mva PTR and NF=3 No. 11 kv feeders (with 11 kv 2 MVAR Capacitor Bank) 137
45 1x5 mva PTR and NF=3 No. 11 kv feeders (without 11 kv 2 MVAR Capacitor Bank) 125

II . Pg: 2 / 2
Area allowances for CORPORATIONS & MUNICIPALITIES
AND AGENCY / TRIBAL AREAS
AS ADOPTED FROM
COMMON SCHEDULE OF RATES
AS PER
T.S. REVISED STANDARD DATA
FOR THE YEAR 2018-19

1 A) CORPORATIONS & MUNICIPALITIES:


a) 25% extra over the basic rates on labour component of works is allowed in all Municipal Corporation
Limits of Telangana (up to a belt of 12 Kms. from Municipal Corporation limits).

b) 20% extra over basic rates on labour component of works is allowed in all District Headquarters and
the remaining Municipal limits (up to a belt of 12 Kms from Municipal limits).

B) JAIL COMPOUNDS:
20% extra is allowed over labour rates for the works in the Jail compounds. Only
equivalent number of Man Mazdoor shall be provided in the Jail premises and no women
Mazdoor are allowed inside

C) INDUSTRIAL AREA:
20% over basic rates on labour component of works is allowed for works situated
within 10km belt of Industrial area of Ramagundam and Godavarikhani in Peddapally District,
Manchiryal, Mandamarri,
Bellampalli in Manchiryal District, Sarpaka, Kothagudem, Paloncha and Manguguru in Bhadradri-
Kothagudem district,
Singareni Collieries area limits in Khammam and Bhadradri-Kothagudem Districts, Kamalapur in
Jayashankar-Bhoopalpally District

D) AGENCY / TRIBAL AREAS:


a) 25% extra is allowed for the works located within the interior Agency / Tribal limits, i.e. for the works
located within & upto16 KMs from any all weather route inside Agency / Tribal. Preamble – Common
SoR 2018-19

b) 40% extra is allowed for the works located within the interior Agency / Tribal limits, i.e. for the works
located beyond 16 KMs from any all weather route inside Agency / Tribal.

NOTE:
1. No extra percentage is permissible in respect of Forest produce such as Bamboo, Rellu grass and
for all materials obtained from outside the Agency / Tribal.
2. The extra percentage under Agency / Tribal areas allowance may be allowed on the labour
component and on the labour charges in the rates for conveyance of materials.
3. The extra percentage on cost of materials in Agency / Tribal areas can be allowed on the labour
component only, if they are manufactured in the Agency / Tribal areas itself except Forest produce.

E) GHAT ROADS:
For Ghat Roads and other roads steeper than 1 in 20, the length of the road may be taken as 1.5
times the existing length of the road for the purpose of leads only for conveyance of materials based
on the certificate for the Ghat Road given by the
Superintending Engineer concerned.
Foot Note: Under compelling circumstances, the concerned Chief Engineer can adopt
the equivalent length of road as 2 ½ times of actual length.
Note:
Area allowances:
If more than one area allowance (such as those) for (1) Municipalities (2) Agency / Tribal areas (3) Industrial areas
are applicable for a particular situation, only the maximum out of the allowable percentages is to be allowed.

TSTRANSCO has issued T.O.O No. CE(Transmission)/ Ms.No.7, dt.04.03.2017 for adding 13.615 %
on basic labour rates towards contractor’s overhead and profit including labour importation for turnkey
projects (New substations, Lines, 33 KV features Bay extension works) of more than One Crore and
not applicable to O&M works and other than turnkey works. At present also, TSNPDCL is allowing the
above percentage where contract value is more than Rs.1.00 crore. Hence Contractor’s overhead and
profit including labour importation 13.615% is allowed on basic labour rates for the works more than
one crore value of contract amount. This is to incorporated in all the estimates value more than
ONE Crore.

III . Pg: 1 / 2
Note : The approved Cost Data 2018-19 will be effected from 01.03.2019

III . Pg: 2 / 2
NORTHERN POWER DISTRIBUTION COMPANY OF
TELANGANA LIMITED : WARANGAL
IV. Material Rates for Fabricated items
Amount (Rs.)
Sl.No. Material Rate Units
1 RS Joists 175x85 mm / 175x75 mm 57.20 Kg
2 RS Joists 150x150 mm 57.20 Kg
3 MS Channel 100x50 mm 55.43 Kg
4 MS Channel 75x40 mm 59.56 Kg
5 MS Angle 65x65x6 mm 58.38 Kg
6 MS Angle 50x50x6 mm 59.56 Kg
7 MS Flat 75x8 mm 57.20 Kg
8 MS Flat 50x6mm 57.20 Kg
9 MS Rod 20 mm 56.02 Kg
10 MS Rod 16 mm 56.02 Kg
11 Scrap (Deduction) 25.50 Kg

12 Labour Charges fabrication + cost of red-oxide paint 10.40 LS

IV. Material Rate . Pg: 1 / 1


NORTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED :
WARANGAL
IV. 33 kv
Material
Sl.No. Material Rate Units
Code

1 FBR00030 33 kv 'V' x-arm with MS Channel 100x50 mm

a MS Channel 100x50 mm (1.53 Mt. long)


Length (120+796+320+796+120 mm) 2.152 Mts.
Weight per Metre 9.200 Kgs.
Weight in Kgs. 19.798 Kgs.
Add: wastage 1% 0.198 Kgs.
Add: scrap 4% 0.792 Kgs.
Total weight : 20.788 Kgs.
Steel rate 55.43 Rs.
Cost of MS Channel 1152.23 Rs.
Add: contingencies 3% 34.57 Rs.
Total cost : 1186.80 Rs.
Deduct: scrap 4% 20.19 Rs.
Total : 1166.61 Rs.
b MS Flat 50x6 mm
Length (60 mm x 4 Nos.) 0.240 Mts.
Weight per Metre 2.400 Kgs.
Weight in Kgs. 0.576 Kgs.
Add: wastage 1% 0.006 Kgs.
Add: scrap 4% 0.023 Kgs.
Total weight : 0.605 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 34.59 Rs.
Add: contingencies 3% 1.04 Rs.
Total cost : 35.63 Rs.
Deduct: scrap 4% 0.59 Rs.
Total : 35.04 Rs.
c Labour charges
Total weight of Steel materials 21.393 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 222.49 Rs.
Total (a+b+c) 1424.14 Rs.
Or say : 1424 Rs.

IV. SSR33 . Pg: 1 / 8


2 33 kv Horizontal x-arm with MS Channel 100x50 mm

a MS Channel 100x50 mm
Length 2.100 Mts.
Weight per Metre 9.200 Kgs.
Weight in Kgs. 19.320 Kgs.
Add: wastage 1% 0.193 Kgs.
Add: scrap 4% 0.773 Kgs.
Total weight : 20.286 Kgs.
Steel rate 55.43 Rs.
Cost of MS Channel 1124.39 Rs.
Add: contingencies 3% 33.73 Rs.
Total cost : 1158.12 Rs.
Deduct: scrap 4% 19.71 Rs.
Total : 1138.42 Rs.
b Labour charges
Total weight of Steel materials 20.286 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 210.97 Rs.
Total (a+b) 1349.39 Rs.
Or say : 1349 Rs.

3 FBR00028 33 kv Back clamp with MS Flat 75x8 mm

a MS Flat 75x8 mm
Length (80+120+180+120+80 mm) 0.580 Mts.
Weight per Metre 4.700 Kgs.
Weight in Kgs. 2.726 Kgs.
Add: wastage 1% 0.027 Kgs.
Add: scrap 4% 0.109 Kgs.
Total weight : 2.862 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 163.71 Rs.
Add: contingencies 3% 4.91 Rs.
Total cost : 168.63 Rs.
Deduct: scrap 4% 2.78 Rs.
Total : 165.85 Rs.
b Labour charges
Total weight of Steel materials 2.862 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 29.77 Rs.
Total (a+b) 195.61 Rs.
Or say : 196 Rs.

IV. SSR33 . Pg: 2 / 8


4 FBR00029 33 kv Stay clamp set with MS Flat 75x8 mm

a MS Flat 75x8 mm
Length 2x(80+50+180+50+80 mm) 0.880 Mts.
Weight per Metre 4.700 Kgs.
Weight in Kgs. 4.136 Kgs.
Add: wastage 1% 0.041 Kgs.
Add: scrap 4% 0.165 Kgs.
Total weight : 4.343 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 248.39 Rs.
Add: contingencies 3% 7.45 Rs.
Total cost : 255.85 Rs.
Deduct: scrap 4% 4.22 Rs.
Total : 251.63 Rs.
b Labour charges
Total weight of Steel materials 4.343 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 45.17 Rs.
Total (a+b) 296.79 Rs.
Or say : 297 Rs.

IV. SSR33 . Pg: 3 / 8


5 FBR00095 33 kv MS Stay set without base plate & concreting

a Anchor rod + bow (20 mm dia)


Length
2.974 Mts.
((1760+2x22/7x40)+(2x450+22/7x20/2+22/7x1/4x20x2) mm)
Weight per Metre 2.470 Kgs.
Weight in Kgs. 7.346 Kgs.
Add: wastage 1% 0.073 Kgs.
Add: scrap 4% 0.294 Kgs.
Total weight : 7.714 Kgs.
Steel rate 56.02 Rs.
Cost of MS rod 432.10 Rs.
Add: contingencies 3% 12.96 Rs.
Total cost : 445.07 Rs.
Deduct: scrap 4% 7.49 Rs.
Total : 437.57 Rs.
b Eye bolt
Length ((450-40)+(22/7xD) mm) 0.805 Mts.
Weight per Metre 4.700 Kgs.
Weight in Kgs. 3.784 Kgs.
Add: wastage 1% 0.038 Kgs.
Add: scrap 4% 0.151 Kgs.
Total weight : 3.973 Kgs.
Steel rate 56.02 Rs.
Cost of Eye bolt 222.56 Rs.
Add: contingencies 3% 6.68 Rs.
Total cost : 229.24 Rs.
Deduct: scrap 4% 3.86 Rs.
Total : 225.38 Rs.
c MS Channel 100x50 mm
Length (180 mm) 0.180 Mts.
Weight per Metre 9.200 Kgs.
Weight in Kgs. 1.656 Kgs.
Add: wastage 1% 0.017 Kgs.
Add: scrap 4% 0.066 Kgs.
Total weight : 1.739 Kgs.
Steel rate 55.43 Rs.
Cost of MS Channel 96.38 Rs.
Add: contingencies 3% 2.89 Rs.
Total cost : 99.27 Rs.
Deduct: scrap 4% 1.69 Rs.
Total : 97.58 Rs.
d Square washer @ ` 22/each 22.00 Rs.
e Hexagonal nut 20 mm dia @ ` 18/each 54.00 Rs.
f 33 kv Guy insulator @ ` 27/each 54.00 Rs.
g Stay wire (7/3.15 mm) @ ` 60/Kg. 600.00 Rs.
h Total (a, b, c & d to g): 1490.53 Rs.
i Labour charges
Total weight of Steel materials 13.426 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 139.63 Rs.
Total (h+i) 1630.16 Rs.
Or say : 1630 Rs.

IV. SSR33 . Pg: 4 / 8


6 33 kv Bracing set with double x-arm without stays and concreting

a MS Channel 100x50x6 mm (Top)


Length (3150 mm x 2 Nos.) 6.300 Mts.
Weight per Metre 9.200 Kgs.
Weight in Kgs. 57.960 Kgs.
Add: wastage 1% 0.580 Kgs.
Add: scrap 4% 2.318 Kgs.
Total weight : 60.858 Kgs.
Steel rate 55.43 Rs.
Cost of MS Channel 3373.17 Rs.
Add: contingencies 3% 101.20 Rs.
Total cost : 3474.37 Rs.
Deduct: scrap 4% 59.12 Rs.
Total : 3415.25 Rs.
b Belting Angle 65x65x6 mm
Length (1800 mm x 2 Nos.) 3.600 Mts.
Weight per Metre 5.800 Kgs.
Weight in Kgs. 20.880 Kgs.
Add: wastage 1% 0.209 Kgs.
Add: scrap 4% 0.835 Kgs.
Total weight : 21.924 Kgs.
Steel rate 58.38 Rs.
Cost of MS Angle 1279.86 Rs.
Add: contingencies 3% 38.40 Rs.
Total cost : 1318.25 Rs.
Deduct: scrap 4% 21.30 Rs.
Total : 1296.95 Rs.
c Bracing Angle 50x50x6 mm
Length (2500 mm x 2 Nos.) 5.000 Mts.
Weight per Metre 4.500 Kgs.
Weight in Kgs. 22.500 Kgs.
Add: wastage 1% 0.225 Kgs.
Add: scrap 4% 0.900 Kgs.
Total weight : 23.625 Kgs.
Steel rate 59.56 Rs.
Cost of MS Angle 1407.03 Rs.
Add: contingencies 3% 42.21 Rs.
Total cost : 1449.24 Rs.
Deduct: scrap 4% 22.95 Rs.
Total : 1426.29 Rs.
d MS Flat 75x8 mm
Length (500 mm x 2 Nos. x 2 sets) 2.000 Mts.
Weight per Metre 4.700 Kgs.
Weight in Kgs. 9.400 Kgs.
Add: wastage 1% 0.094 Kgs.
Add: scrap 4% 0.376 Kgs.
Total weight : 9.870 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 564.53 Rs.
Add: contingencies 3% 16.94 Rs.
Total cost : 581.47 Rs.
Deduct: scrap 4% 9.59 Rs.
Total : 571.88 Rs.

IV. SSR33 . Pg: 5 / 8


e Fish Plates 75x8 mm (MS Plate)
Length (280 mm x 6 Nos.) 1.680 Mts.
Weight per Metre 4.700 Kgs.
Weight in Kgs. 7.896 Kgs.
Add: wastage 1% 0.079 Kgs.
Add: scrap 4% 0.316 Kgs.
Total weight : 8.291 Kgs.
Steel rate 57.20 Rs.
Cost of MS Plate 474.21 Rs.
Add: contingencies 3% 14.23 Rs.
Total cost : 488.43 Rs.
Deduct: scrap 4% 8.05 Rs.
Total : 480.38 Rs.
f Back clamps for bracings MS Flat 75x8 mm
Length ((800+600) mm x 2 Nos.) 2.800 Mts.
Weight per Metre 4.700 Kgs.
Weight in Kgs. 13.160 Kgs.
Add: wastage 1% 0.132 Kgs.
Add: scrap 4% 0.526 Kgs.
Total weight : 13.818 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 790.35 Rs.
Add: contingencies 3% 23.71 Rs.
Total cost : 814.06 Rs.
Deduct: scrap 4% 13.42 Rs.
Total : 800.63 Rs.
i Labour charges
Total weight of Steel materials 138.386 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 1439.21 Rs.
Total (a to i) 9430.61 Rs.
Or say : 9431 Rs.

IV. SSR33 . Pg: 6 / 8


7 FBR00031 33 kv Top fitting with clamp

a MS Angle 65x65x6 mm
Length (500 mm) 0.500 Mts.
Weight per Metre 5.800 Kgs.
Weight in Kgs. 2.900 Kgs.
Add: wastage 1% 0.029 Kgs.
Add: scrap 4% 0.116 Kgs.
Total weight : 3.045 Kgs.
Steel rate 58.38 Rs.
Cost of MS Angle 177.76 Rs.
Add: contingencies 3% 5.33 Rs.
Total cost : 183.09 Rs.
Deduct: scrap 4% 2.96 Rs.
Total : 180.13 Rs.
b MS Channel 100x50x6 mm (65 mm)
Length (65 mm) 0.065 Mts.
Weight per Metre 9.200 Kgs.
Weight in Kgs. 0.598 Kgs.
Add: wastage 1% 0.006 Kgs.
Add: scrap 4% 0.024 Kgs.
Total weight : 0.628 Kgs.
Steel rate 55.43 Rs.
Cost of MS Channel 34.80 Rs.
Add: contingencies 3% 1.04 Rs.
Total cost : 35.85 Rs.
Deduct: scrap 4% 0.61 Rs.
Total : 35.24 Rs.
c MS Flat 75x8 mm
Length (580 mm) 0.580 Mts.
Weight per Metre 4.700 Kgs.
Weight in Kgs. 2.726 Kgs.
Add: wastage 1% 0.027 Kgs.
Add: scrap 4% 0.109 Kgs.
Total weight : 2.862 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 163.71 Rs.
Add: contingencies 3% 4.91 Rs.
Total cost : 168.63 Rs.
Deduct: scrap 4% 2.78 Rs.
Total : 165.85 Rs.
d Labour charges
Total weight of Steel materials 6.535 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 67.97 Rs.
Total (a to d) 449.18 Rs.
Or say : 449 Rs.

IV. SSR33 . Pg: 7 / 8


8 FBR00094 33 kv T-raiser with MS Channel 100x50 mm

a MS Channel 100x50 mm
Length (2.1+1.5 mts.) 3.600 Mts.
Weight per Metre 9.200 Kgs.
Weight in Kgs. 33.120 Kgs.
Add: wastage 1% 0.331 Kgs.
Add: scrap 4% 1.325 Kgs.
Total weight : 34.776 Kgs.
Steel rate 55.43 Rs.
Cost of MS Channel 1927.53 Rs.
Add: contingencies 3% 57.83 Rs.
Total cost : 1985.35 Rs.
Deduct: scrap 4% 33.78 Rs.
Total : 1951.57 Rs.
b Labour charges
Total weight of Steel materials 34.776 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 361.67 Rs.
Total (a+b) 2313.24 Rs.
Or say : 2313 Rs.

IV. SSR33 . Pg: 8 / 8


NORTHERN POWER DISTRIBUTION COMPANY OF TELANGANA
LIMITED : WARANGAL
IV. 11 kv
Material
Sl.No. Material Rate Units
Code

1 FBR00021 11 kv 'V' x-arm with MS Channel 75x40 mm

a MS Channel 75x40 mm
Length (80+438.40+370+438.40+80 mm) 1.407 Mts.
Weight per Metre 6.800 Kgs.
Weight in Kgs. 9.568 Kgs.
Add: wastage 1% 0.096 Kgs.
Add: scrap 4% 0.383 Kgs.
Total weight : 10.046 Kgs.
Steel rate 59.56 Rs.
Cost of MS Channel 598.31 Rs.
Add: contingencies 3% 17.95 Rs.
Total cost : 616.26 Rs.
Deduct: scrap 4% 9.76 Rs.
Total : 606.50 Rs.
b MS Flat 50x6 mm
Length (60 mm x 4 Nos.) 0.240 Mts.
Weight per Metre 2.400 Kgs.
Weight in Kgs. 0.576 Kgs.
Add: wastage 1% 0.006 Kgs.
Add: scrap 4% 0.023 Kgs.
Total weight : 0.605 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 34.59 Rs.
Add: contingencies 3% 1.04 Rs.
Total cost : 35.63 Rs.
Deduct: scrap 4% 0.59 Rs.
Total : 35.04 Rs.
c Labour charges
Total weight of Steel materials 10.651 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 110.77 Rs.
Total (a+b+c) 752.31 Rs.
Or say : 752 Rs.

IV. SSR11 . Pg: 1 / 8


2 FBR00024 11 kv Horizontal x-arm with MS Channel 75x40 mm

a MS Channel 75x40 mm
Length 1.500 Mts.
Weight per Metre 6.800 Kgs.
Weight in Kgs. 10.200 Kgs.
Add: wastage 1% 0.102 Kgs.
Add: scrap 4% 0.408 Kgs.
Total weight : 10.710 Kgs.
Steel rate 59.56 Rs.
Cost of MS Channel 637.86 Rs.
Add: contingencies 3% 19.14 Rs.
Total cost : 656.99 Rs.
Deduct: scrap 4% 10.40 Rs.
Total : 646.59 Rs.
b Labour charges
Total weight of Steel materials 10.710 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 111.38 Rs.
Total (a+b) 757.97 Rs.
Or say : 758 Rs.

3 11 kv Back clamp with MS Flat 50x6 mm

a MS Flat 50x6 mm
Length (395 mm) 0.395 Mts.
Weight per Metre 2.400 Kgs.
Weight in Kgs. 0.948 Kgs.
Add: wastage 1% 0.009 Kgs.
Add: scrap 4% 0.038 Kgs.
Total weight : 0.995 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 56.93 Rs.
Add: contingencies 3% 1.71 Rs.
Total cost : 58.64 Rs.
Deduct: scrap 4% 0.97 Rs.
Total : 57.67 Rs.
b Labour charges
Total weight of Steel materials 0.995 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 10.35 Rs.
Total (a+b) 68.03 Rs.
Or say : 68 Rs.

IV. SSR11 . Pg: 2 / 8


4 11 kv Stay clamp set with MS Flat 50x6 mm

a MS Flat 50x6 mm
Length 2x(60+35+130+35+60 mm) 0.640 Mts.
Weight per Metre 2.400 Kgs.
Weight in Kgs. 1.536 Kgs.
Add: wastage 1% 0.015 Kgs.
Add: scrap 4% 0.061 Kgs.
Total weight : 1.613 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 92.25 Rs.
Add: contingencies 3% 2.77 Rs.
Total cost : 95.01 Rs.
Deduct: scrap 4% 1.57 Rs.
Total : 93.45 Rs.
b Labour charges
Total weight of Steel materials 1.613 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 16.77 Rs.
Total (a+b) 110.22 Rs.
Or say : 110 Rs.

IV. SSR11 . Pg: 3 / 8


5 FBR00026 11 kv MS Stay set without base plate & concreting

a Anchor rod + bow (16 mm dia)


Length
((1760+2x22/7x40)+(2x450+22/7x20/2+22/7x1/4x20x2) 2.974 Mts.
mm)
Weight per Metre 1.580 Kgs.
Weight in Kgs. 4.699 Kgs.
Add: wastage 1% 0.047 Kgs.
Add: scrap 4% 0.188 Kgs.
Total weight : 4.934 Kgs.
Steel rate 56.02 Rs.
Cost of MS rod 276.41 Rs.
Add: contingencies 3% 8.29 Rs.
Total cost : 284.70 Rs.
Deduct: scrap 4% 4.79 Rs.
Total : 279.91 Rs.
b Eye bolt
Length ((450-40)+(22/7xD) mm) 0.536 Mts.
Weight per Metre 2.470 Kgs.
Weight in Kgs. 1.324 Kgs.
Add: wastage 1% 0.013 Kgs.
Add: scrap 4% 0.053 Kgs.
Total weight : 1.390 Kgs.
Steel rate 56.02 Rs.
Cost of Eye bolt 77.87 Rs.
Add: contingencies 3% 2.34 Rs.
Total cost : 80.21 Rs.
Deduct: scrap 4% 1.35 Rs.
Total : 78.86 Rs.
c MS Channel 75x40 mm
Length (180 mm) 0.180 Mts.
Weight per Metre 6.800 Kgs.
Weight in Kgs. 1.224 Kgs.
Add: wastage 1% 0.012 Kgs.
Add: scrap 4% 0.049 Kgs.
Total weight : 1.285 Kgs.
Steel rate 59.56 Rs.
Cost of MS Channel 76.54 Rs.
Add: contingencies 3% 2.30 Rs.
Total cost : 78.84 Rs.
Deduct: scrap 4% 1.25 Rs.
Total : 77.59 Rs.
d Square washer @ ` 22/each 22.00 Rs.
e Hexagonal nut 20 mm dia @ ` 14/each 42.00 Rs.
f 11 kv Guy insulator @ ` 27/each 54.00 Rs.
g Stay wire (7/3.15 mm) @ ` 60/Kg. 600.00 Rs.
h Total (a, b, c & d to g): 1154.35 Rs.
i Labour charges
Total weight of Steel materials 7.610 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 79.14 Rs.
Total (h+i) 1233.49 Rs.
Or say : 1233 Rs.

IV. SSR11 . Pg: 4 / 8


6 11 kv Bracing set with double x-arm without stays and concreting

a MS Channel 100x50x6 mm (Top)


Length (2500 mm x 2 Nos.) 5.000 Mts.
Weight per Metre 9.200 Kgs.
Weight in Kgs. 46.000 Kgs.
Add: wastage 1% 0.460 Kgs.
Add: scrap 4% 1.840 Kgs.
Total weight : 48.300 Kgs.
Steel rate 55.43 Rs.
Cost of MS Channel 2677.12 Rs.
Add: contingencies 3% 80.31 Rs.
Total cost : 2757.44 Rs.
Deduct: scrap 4% 46.92 Rs.
Total : 2710.52 Rs.
b Belting Angle 65x65x6 mm
Length (1800 mm x 2 Nos.) 3.600 Mts.
Weight per Metre 5.800 Kgs.
Weight in Kgs. 20.880 Kgs.
Add: wastage 1% 0.209 Kgs.
Add: scrap 4% 0.835 Kgs.
Total weight : 21.924 Kgs.
Steel rate 58.38 Rs.
Cost of MS Angle 1279.86 Rs.
Add: contingencies 3% 38.40 Rs.
Total cost : 1318.25 Rs.
Deduct: scrap 4% 21.30 Rs.
Total : 1296.95 Rs.
c Bracing Angle 50x50x6 mm
Length (2500 mm x 2 Nos.) 5.000 Mts.
Weight per Metre 4.500 Kgs.
Weight in Kgs. 22.500 Kgs.
Add: wastage 1% 0.225 Kgs.
Add: scrap 4% 0.900 Kgs.
Total weight : 23.625 Kgs.
Steel rate 59.56 Rs.
Cost of MS Angle 1407.03 Rs.
Add: contingencies 3% 42.21 Rs.
Total cost : 1449.24 Rs.
Deduct: scrap 4% 22.95 Rs.
Total : 1426.29 Rs.
d MS Flat 75x8 mm
Length (400 mm x 2 Nos. x 2 sets) 1.600 Mts.
Weight per Metre 4.700 Kgs.
Weight in Kgs. 7.520 Kgs.
Add: wastage 1% 0.075 Kgs.
Add: scrap 4% 0.301 Kgs.
Total weight : 7.896 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 451.63 Rs.
Add: contingencies 3% 13.55 Rs.
Total cost : 465.18 Rs.
Deduct: scrap 4% 7.67 Rs.
Total : 457.51 Rs.

IV. SSR11 . Pg: 5 / 8


e Fish Plates 75x8 mm (MS Plate)
Length (240 mm x 6 Nos.) 1.440 Mts.
Weight per Metre 4.700 Kgs.
Weight in Kgs. 6.768 Kgs.
Add: wastage 1% 0.068 Kgs.
Add: scrap 4% 0.271 Kgs.
Total weight : 7.106 Kgs.
Steel rate 57.20 Rs.
Cost of MS Plate 406.46 Rs.
Add: contingencies 3% 12.19 Rs.
Total cost : 418.66 Rs.
Deduct: scrap 4% 6.90 Rs.
Total : 411.76 Rs.
f Back clamps for bracings MS Flat 75x8 mm
Length ((750+600) mm x 2 Nos.) 2.700 Mts.
Weight per Metre 4.700 Kgs.
Weight in Kgs. 12.690 Kgs.
Add: wastage 1% 0.127 Kgs.
Add: scrap 4% 0.508 Kgs.
Total weight : 13.325 Kgs.
Steel rate 57.20 Rs.
Cost of MS Flat 762.12 Rs.
Add: contingencies 3% 22.86 Rs.
Total cost : 784.98 Rs.
Deduct: scrap 4% 12.94 Rs.
Total : 772.04 Rs.
i Labour charges
Total weight of Steel materials 122.176 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 1270.63 Rs.
Total (a to i) 8345.70 Rs.
Or say : 8346 Rs.

IV. SSR11 . Pg: 6 / 8


7 FBR00025 11 kv Top fitting with clamp

a MS Angle 50x50x6 mm
Length (300 mm) 0.300 Mts.
Weight per Metre 4.500 Kgs.
Weight in Kgs. 1.350 Kgs.
Add: wastage 1% 0.014 Kgs.
Add: scrap 4% 0.054 Kgs.
Total weight : 1.418 Kgs.
Steel rate 59.56 Rs.
Cost of MS Angle 84.42 Rs.
Add: contingencies 3% 2.53 Rs.
Total cost : 86.95 Rs.
Deduct: scrap 4% 1.38 Rs.
Total : 85.58 Rs.
b MS Channel 75x40x6 mm (65 mm)
Length (65 mm) 0.07 Mts.
Weight per Metre 6.80 Kgs.
Weight in Kgs. 0.442 Kgs.
Add: wastage 1% 0.004 Kgs.
Add: scrap 4% 0.018 Kgs.
Total weight : 0.464 Kgs.
Steel rate 59.56 Rs.
Cost of MS Channel 27.64 Rs.
Add: contingencies 3% 0.83 Rs.
Total cost : 28.47 Rs.
Deduct: scrap 4% 0.45 Rs.
Total : 28.02 Rs.
c Back clamps
2 Nos. 136.00 Rs.
Total : 136.00 Rs.
d Labour charges
Total weight of Steel materials 1.882 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 19.57 Rs.
Total (a to d) 269.17 Rs.
Or say : 269 Rs.

IV. SSR11 . Pg: 7 / 8


8 FBR00057 11 kv T-raiser with MS Channel 75x40 mm

a MS Channel 75x40 mm
Length (1.5+1.5 mts.) 3.000 Mts.
Weight per Metre 6.800 Kgs.
Weight in Kgs. 20.400 Kgs.
Add: wastage 1% 0.204 Kgs.
Add: scrap 4% 0.816 Kgs.
Total weight : 21.420 Kgs.
Steel rate 59.56 Rs.
Cost of MS Channel 1275.71 Rs.
Add: contingencies 3% 38.27 Rs.
Total cost : 1313.98 Rs.
Deduct: scrap 4% 20.81 Rs.
Total : 1293.17 Rs.
b Labour charges
Total weight of Steel materials 21.420 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 222.77 Rs.
Total (a+b) 1515.94 Rs.
Or say : 1516 Rs.

9 FBR00056 11 kv Side arm

a MS Channel 75x40 mm
Length 1.650 Mts.
Weight per Metre 6.800 Kgs.
Weight in Kgs. 11.220 Kgs.
b MS Angle 50x50x6 mm
Length 1.700 Mts.
Weight per Metre 4.500 Kgs.
Weight in Kgs. 7.650 Kgs.
Add: wastage 1% 0.189 Kgs.
Add: scrap 4% 0.755 Kgs.
Total weight : 19.814 Kgs.
Steel rate 59.56 Rs.
Cost of MS Angle 1180.03 Rs.
Add: contingencies 3% 35.40 Rs.
Total cost : 1215.43 Rs.
Deduct: scrap 4% 19.25 Rs.
Total : 1196.19 Rs.
c Labour charges
Total weight of Steel materials 19.814 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 206.06 Rs.
Total (a+b) 1402.25 Rs.
Or say : 1402 Rs.

IV. SSR11 . Pg: 8 / 8


NORTHERN POWER DISTRIBUTION COMPANY OF TELANGANA
LIMITED : WARANGAL
IV. LT
Material
Sl.No. Material Rate Units
Code

1 FBR00007 LT 3-ph 5 W/L Angle x-arm 50x50x6 mm

a MS Angle 50x50x6 mm
Length (30+300+450+300+300+30+(250)) 1.690 Mts.
Weight per Metre 4.500 Kgs.
Weight in Kgs. 7.605 Kgs.
Add: wastage 1% 0.076 Kgs.
Add: scrap 4% 0.304 Kgs.
Total weight : 7.985 Kgs.
Steel rate 59.56 Rs.
Cost of MS Angle 475.58 Rs.
Add: contingencies 3% 14.27 Rs.
Total cost : 489.84 Rs.
Deduct: scrap 4% 7.76 Rs.
Total : 482.09 Rs.
b Labour charges
Total weight of Steel materials 7.985 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 83.05 Rs.
Total (a+b) 565.13 Rs.
Or say : 565 Rs.

2 FBR00006 LT 3-ph 4 W/L Angle x-arm 50x50x6 mm

a MS Angle 50x50x6 mm
Length (30+300+450+300+30+(200)) 1.310 Mts.
Weight per Metre 4.500 Kgs.
Weight in Kgs. 5.895 Kgs.
Add: wastage 1% 0.059 Kgs.
Add: scrap 4% 0.236 Kgs.
Total weight : 6.190 Kgs.
Steel rate 59.56 Rs.
Cost of MS Angle 368.64 Rs.
Add: contingencies 3% 11.06 Rs.
Total cost : 379.70 Rs.
Deduct: scrap 4% 6.01 Rs.
Total : 373.69 Rs.
b Labour charges
Total weight of Steel materials 6.190 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 64.37 Rs.
Total (a+b) 438.06 Rs.
Or say : 438 Rs.

IV. SSRLT . Pg: 1 / 3


3 LT 3-ph 3 W/L Angle x-arm 50x50x6 mm

a MS Angle 50x50x6 mm
Length (30+300+450+30+(150)) 0.960 Mts.
Weight per Metre 4.500 Kgs.
Weight in Kgs. 4.320 Kgs.
Add: wastage 1% 0.043 Kgs.
Add: scrap 4% 0.173 Kgs.
Total weight : 4.536 Kgs.
Steel rate 59.56 Rs.
Cost of MS Angle 270.15 Rs.
Add: contingencies 3% 8.10 Rs.
Total cost : 278.25 Rs.
Deduct: scrap 4% 4.41 Rs.
Total : 273.85 Rs.
b Labour charges
Total weight of Steel materials 4.536 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 47.17 Rs.
Total (a+b) 321.02 Rs.
Or say : 321 Rs.

4 FBR00004 LT S-ph 2 W/L Angle x-arm 50x50x6 mm

a MS Angle 50x50x6 mm
Length (30+450+30+(100)) 0.610 Mts.
Weight per Metre 4.500 Kgs.
Weight in Kgs. 2.745 Kgs.
Add: wastage 1% 0.027 Kgs.
Add: scrap 4% 0.110 Kgs.
Total weight : 2.882 Kgs.
Steel rate 59.56 Rs.
Cost of MS Angle 171.66 Rs.
Add: contingencies 3% 5.15 Rs.
Total cost : 176.81 Rs.
Deduct: scrap 4% 2.80 Rs.
Total : 174.01 Rs.
b Labour charges
Total weight of Steel materials 2.882 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 29.98 Rs.
Total (a+b) 203.98 Rs.
Or say : 204 Rs.

IV. SSRLT . Pg: 2 / 3


5 FBR00018 LT 3-ph 4 W/LT-raiser 50x50x6 mm

a MS Channel 75x40 mm
Length 1.500 Mts.
Weight per Metre 6.800 Kgs.
Weight in Kgs. 10.200 Kgs.
b MS Angle 50x50x6 mm
Length (30+300+450+300+30+(200)) 1.310 Mts.
Weight per Metre 4.500 Kgs.
Weight in Kgs. 5.895 Kgs.
Add: wastage 1% 0.161 Kgs.
Add: scrap 4% 0.644 Kgs.
Total weight : 16.900 Kgs.
Steel rate 59.56 Rs.
Cost of MS Angle 1006.50 Rs.
Add: contingencies 3% 30.19 Rs.
Total cost : 1036.69 Rs.
Deduct: scrap 4% 16.42 Rs.
Total : 1020.28 Rs.
c Labour charges
Total weight of Steel materials 16.900 Kgs.
Rate of fabrication and red oxide paints per Kg. 10.40 Rs.
Total : 175.76 Rs.
Total (a+b) 1196.03 Rs.
Or say : 1196 Rs.

IV. SSRLT . Pg: 3 / 3


REC Construction Standard No.M2/1979 (R-1989)

Cost data per Km. of 33 kv line (SC) with 100 sq.mm AAA conductor over 11 mts. PSCC poles
at 80 mts. Span, 75 Kg/sq.mts. wind pressure, working load 365 Kgs.

(Rs.)
Sl.No. Material Code Particulars Unit Qty. Rate Amount
1 FBR00081 11 M PSCC pole Each 14 5822 81512
2 FBR00030 1.53 M Channel 'V' x-arm Each 12 1424 17088
3 FBR00031 Top fitting with Clamp Each 12 449 5388
4 FBR00028 Back Clamp Each 12 196 2352
MS Stay set with stay clamp and without
5 FBR00095 Each 6 1927 11562
base plate
6 Bracing set with double x-arm Set 1 9431 9431
7 CDR00004 100 sq.mm AAA Conductor Km 3.06 56497 172881
INS30001,
8 33 kv Pin Insulator with Pin Each 39 411 16038
HWR00003

INS30007,
9 Strain Insulators set with fitting (B&S) Set 6 449 2692
HWR00004
Base and Mass concreting of Poles, Stay
10 LS 1 45609 45609
sets
Misc. Items like coil earthing, pipe eathing,
11 LS 1 7787 7787
danger, bolts & nuts, etc
Total Material : 372340
3% Storage & Handling charges on items 1
9568
to 9
3% Contingencies on Materials 11170
Labour : 87636
Transport : 29264
10% Estt. & Genl. charges on Materials 37234
Sub-Total 547213
1% CESS on Sub-Total 5472
18% GST on Labour, Transport and CESS 22027
Total 574712
Or say : 574720

1 33kv SC11 . Pg: 1 / 1


REC Construction Standard No.M2/1979 (R-1989)

Cost data per Km. of 33 kv line (DC) with 100 sq.mm AAA conductor over 11 mts. PSCC poles at 40
mts. Span, 75 Kg/sq.mts. wind pressure, working load 365 Kgs.

(Rs.)
Sl.No. Material Code Particulars Unit Qty. Rate Amount
1 FBR00081 11 M PSCC pole Each 26 5822 151380
2 FBR00030 1.53 M Channel 'V' x-arm Each 72 1424 102528
3 FBR00028 Back Clamp Each 75 196 14671
MS Stay set with stay clamp and without
4 FBR00095 Each 12 1927 23123
base plate
5 Bracing set with double x-arm Set 1 9431 9431
6 CDR00004 100 sq.mm AAA Conductor Km 6.12 56497 345763

INS30001,
7 33 kv Pin Insulator with Pin Each 156 411 64152
HWR00003

INS30007,
8 Strain Insulators set with fitting (B&S) Set 24 449 10767
HWR00004
Base and Mass concreting of Poles, Stay
9 LS 1 108265 108265
sets
Misc. Items like coil earthing, pipe eathing,
10 LS 1 15574 15574
danger, bolts & nuts, etc
Total Material : 845654
3% Storage & Handling charges on items 1
21654
to 9
3% Contingencies on Materials 25370

Labour : 171570

Transport : 53208
10% Estt. & Genl. charges on Materials 84565

Sub-Total 1202021
1% CESS on Sub-Total 12020
18% GST on Labour, Transport and CESS 42624
Total 1256665
Or say : 1256670

2 33kv DC11 . Pg: 1 / 1


REC Construction Standard No.M11/1979 (R-1989)

Cost data per Km. of 33 kv line with 100 sq.mm AAA conductor over 9.1 mts. PSCC poles at 80 mts.
Span, 75 Kg/sq.mts. wind pressure, working load 280 Kgs.

(Rs.)
Sl.No. Mateial Code Particulars Unit Qty. Rate Amount
1 FBR00066 9.1 M PSCC pole Each 14 3197 44764
2 FBR00030 1.53 M Channel 'V' x-arm Each 12 1424 17088
3 FBR00031 Top fitting with Clamp Each 12 449 5388
4 FBR00028 Back Clamp Each 12 196 2352
MS Stay set with stay clamp and without
5 FBR00095 Each 6 1927 11562
base plate
6 Bracing set with double x-arm Set 1 9431 9431
7 CDR00004 100 sq.mm AAA Conductor Km 3.06 56497 172881
INS30001,
8 33 kv Pin Insulator with Pin Each 39 411 16038
HWR00003

INS30007,
9 Strain Insulators set with fitting (B&S) Set 6 449 2692
HWR00004
Base and Mass concreting of Poles, Stay
10 LS 1 31408 31408
sets
Misc. Items like coil earthing, pipe eathing,
11 LS 1 7787 7787
danger, bolts & nuts, etc
Total Material : 321391
3% Storage & Handling charges on items 1
8466
to 9
3% Contingencies on Materials 9642

Labour : 59689

Transport : 19981
10% Estt. & Genl. charges on Materials 32139

Sub-Total 451308
1% CESS on Sub-Total 4513
18% GST on Labour, Transport and CESS 15153
Total 470974
Or say : 470980

3 33kv 9m-80 . Pg: 1 / 1


REC Construction Standard No.M11/1979 (R-1989)

Cost data per Km. of 33 kv line with 100 sq.mm AAA conductor over 9.1 mts. PSCC poles at 65
mts. Span, 75 Kg/sq.mts. wind pressure, working load 280 Kgs.

(Rs.)

Sl.No. Material Code Particulars Unit Qty. Rate Amount

1 FBR00066 9.1 M PSCC pole Each 17 3197 54356

2 FBR00030 1.53 M Channel 'V' x-arm Each 15 1424 21360

3 FBR00031 Top fitting with Clamp Each 15 449 6735

4 FBR00028 Back Clamp Each 15 196 2940


MS Stay set with stay clamp and without
5 FBR00095 Each 6 1927 11562
base plate
6 Bracing set with double x-arm Set 1 9431 9431
7 CDR00004 100 sq.mm AAA Conductor Km 3.06 56497 172881
INS30001,
8 33 kv Pin Insulator with Pin Each 48 411 19739
HWR00003
INS30007,
9 Strain Insulators set with fitting (B&S) Set 6 449 2692
HWR00004
Base and Mass concreting of Poles, Stay
10 LS 1 36382 36382
sets
Misc. Items like coil earthing, pipe eathing,
11 LS 1 7787 7787
danger, bolts & nuts, etc
Total Material : 345866
3% Storage & Handling charges on items 1
9051
to 9
3% Contingencies on Materials 10376

Labour : 68496

Transport : 22983

10% Estt. & Genl. charges on Materials 34587

Sub-Total 491358
1% CESS on Sub-Total 4914
18% GST on Labour, Transport and CESS 17351
Total 513622

Or say : 513630

4 33kv 9m-65 . Pg: 1 / 1


REC Construction Standard No.A34/1993

Cost data per Km. of 11 kv line with 55 sq.mm AAA conductor over 9.1 mts. PSCC poles at 60
mts. Span, 75 Kg/sq.mts. wind pressure, working load 280 Kgs.

(Rs.)
Sl.No. Material Code Particulars Unit Qty. Rate Amount
1 FBR00066 9.1 M PSCC pole Each 18 3197 57554
2 FBR00021 1.07 M Channel 'V' x-arm Each 16 752 12032
3 FBR00025 Top fitting with Clamp Each 16 269 4304
4 FBR00002 Back Clamp Each 16 68 1088
MS Stay set with stay clamp and without
5 FBR00026 Each 6 1343 8058
base plate
6 Bracing set with double x-arm Set 1 8346 8346
7 CDR00003 55 sq.mm AAA Conductor Km 3.06 27577 84384
INS10001,
8 11 kv Pin Insulator with Pin Each 51 101.65 5184
HWR00001
INS10002,
9 11 kv Strain Insulators set with fitting (C&T) Set 6 324.70 1948
HWR00002
Base and Mass concreting of Poles, Stay
10 LS 1 36382 36382
sets
Misc. Items like coil earthing, pipe eathing,
11 LS 1 7787 7787
danger, bolts & nuts, etc
Total Material : 227067
3% Storage & Handling charges on items 1
5487
to 9
3% Contingencies on Materials 6812
Labour : 63941
Transport : 23984
10% Estt. & Genl. charges on Materials 22707
Sub-Total 349998
1% CESS on Sub-Total 3500

18% GST on Labour, Transport and CESS 16456


Total 369954
Or say : 369960

5 11kv 9m-60-280 . Pg: 1 / 1


REC Construction Standard No.A34/1993

Cost data per Km. of 11 kv line with 34 sq.mm AAA conductor over 9.1 mts. PSCC poles at 60
mts. Span, 75 Kg/sq.mts. wind pressure, working load 280 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
1 9.1 M PSCC pole Each 18 3197 57554
2 FBR00021 1.07 M Channel 'V' x-arm Each 16 752 12032
3 FBR00025 Top fitting with Clamp Each 16 269 4304
4 FBR00002 Back Clamp Each 16 68 1088
MS Stay set with stay clamp and without
5 FBR00026 Each 10 1343 13430
base plate
6 Bracing set with double x-arm Set 1 8346 8346
7 CDR00002 34 sq.mm AAA Conductor Km 3.06 17974 55000
INS10001,
8 11 kv Pin Insulator with Pin Each 51 102 5184
HWR00001
INS10002,
9 11 kv Strain Insulators set with fitting (C&T) Set 6 324.70 1948
HWR00002
Base and Mass concreting of Poles, Stay
10 LS 1 44058 44058
sets
Misc. Items like coil earthing, pipe eathing,
11 LS 1 7787 7787
danger, bolts & nuts, etc
Total Material : 210731
3% Storage & Handling charges on items 1
4767
to 9
3% Contingencies on Materials 6322
Labour : 70094
Transport : 23984
10% Estt. & Genl. charges on Materials 21073
Sub-Total 336971
1% CESS on Sub-Total 3370
18% GST on Labour, Transport and CESS 17541
Total 357881
Or say : 357890

6 11kv 9m-60-140 . Pg: 1 / 1


REC Construction Standard No.A34/1993 (A5/1972)

Cost data per Km. of 11 kv line with 55 sq.mm AAA conductor over 8 mts. PSCC poles at 60
mts. Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
1 FBR00065 8 M PSCC pole Each 18 1575 28350
2 FBR00021 1.07 M Channel 'V' x-arm Each 16 752 12032
3 FBR00025 Top fitting with Clamp Each 16 269 4304
4 FBR00002 Back Clamp Each 16 68 1088
MS Stay set with stay clamp and without
5 FBR00026 Each 6 1343 8058
base plate
6 Bracing set with double x-arm Set 1 8346 8346
7 CDR00003 55 sq.mm AAA Conductor Km 3.06 27577 84384
INS10001,
8 11 kv Pin Insulator with Pin Each 51 102 5184
HWR00001
INS10002,
9 11 kv Strain Insulators set with fitting (C&T) Set 6 324.70 1948
HWR00002
Base and Mass concreting of Poles, Stay
10 LS 1 36382 36382
sets
Misc. Items like coil earthing, pipe eathing,
11 LS 1 3065 3065
danger, bolts & nuts, etc
Total Material : 193142
3% Storage & Handling charges on items 1
4611
to 9
3% Contingencies on Materials 5794
Labour : 54214
Transport : 13841
10% Estt. & Genl. charges on Materials 19314
Sub-Total 290916
1% CESS on Sub-Total 2909
18% GST on Labour, Transport and CESS 12774
Total 306599
Or say : 306600

7 11kv 8m-60-55 . Pg: 1 / 1


REC Construction Standard No.A34/1993 (A5/1972)

Cost data per Km. of 11 kv line with 34 sq.mm AAA conductor over 8 mts. PSCC poles at 60 mts.
Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

(Rs.)
Sl.No. Material Code Particulars Unit Qty. Rate Amount
1 FBR00065 8 M PSCC pole Each 18 1575 28350
2 FBR00021 1.07 M Channel 'V' x-arm Each 16 752 12032
3 FBR00025 Top fitting with Clamp Each 16 269 4304
4 FBR00002 Back Clamp Each 16 68 1088
MS Stay set with stay clamp and without
5 FBR00026 Each 6 1343 8058
base plate
6 Bracing set with double x-arm Set 1 8346 8346
7 CDR00002 34 sq.mm AAA Conductor Km 3.06 17974 55000
INS10001,
8 11 kv Pin Insulator with Pin Each 51 101.65 5184
HWR00001
INS10002,
9 11 kv Strain Insulators set with fitting (C&T) Set 6 324.70 1948
HWR00002

10 Base and Mass concreting of Poles, Stay sets LS 1 36382 36382


Misc. Items like coil earthing, pipe eathing,
11 LS 1 3065 3065
danger, bolts & nuts, etc
Total Material : 163757
3% Storage & Handling charges on items 1 to
3729
9
3% Contingencies on Materials 4913
Labour : 54214
Transport : 13841
10% Estt. & Genl. charges on Materials 16376
Sub-Total 256830
1% CESS on Sub-Total 2568
18% GST on Labour, Transport and CESS 12712
Total 272111
Or say : 272120

8 11kv 8m-60-34 . Pg: 1 / 1


REC Construction Standard No.A17/1972

Cost data per Km. of 6.3 kv S-ph line with 34 sq.mm AAA conductor over 8 mts. PSCC poles
at 80 mts. Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
1 FBR00065 8 M PSCC pole Each 13 1575 20475
2 FBR00021 Top fitting with Clamp Each 13 269 3497
MS Stay set with stay clamp and without
3 FBR00025 Each 6 1343 8058
base plate
4 CDR00002 34 sq.mm AAA Conductor Km 1.02 17974 18333
INS10001,
5 11 kv Pin Insulator with Pin Each 10 102 1016
HWR00001
INS10002,
6 11 kv Strain Insulators set with fitting (C&T) Set 6 325 1948
HWR00002
Base and Mass concreting of Poles, Stay
7 LS 1 26435 26435
sets
Misc. Items like coil earthing, pipe eathing,
8 LS 1 3065 3065
danger, bolts & nuts, etc
Total Material : 82828
3% Storage & Handling charges on items 1
1600
to 6
3% Contingencies on Materials 2485
Labour : 37725
Transport : 11379
10% Estt. & Genl. charges on Materials 8283
Sub-Total 144300
1% CESS on Sub-Total 1443
18% GST on Labour, Transport and CESS 9098
Total 154841
Or say : 154850

9 6.3kv 8m-80-140 . Pg: 1 / 1


REC Construction Standard No.B8/1984

Cost data per Km. of LT 3-ph 5 Wire line (Horizontal formation) with 3x55+2x34 sq.mm AAA
Conductor over 8 mts. PSCC poles at 65 mts. Span, 75 Kg/sq.mts. wind pressure, working
load 140 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
1 FBR00065 8 M PSCC pole Each 16 1575 25200
2 FBR00006 LT 3-ph 4 Wire line x-arms Each 18 438 7884
3 FBR00070 LT Top fitting with Clamp Each 18 269 4842
4 FBR00001 Back Clamp Each 18 68 1224
MS Stay set with stay clamp and without
5 FBR00008 Each 6 1343 8058
base plate
6 CDR00003 55 sq.mm AAA Conductor Km 3.06 27577 84384
7 CDR00002 34 sq.mm AAA Conductor Km 2.04 17974 36667
INS00001,
8 LT Pin Insulator with Pin Each 56 54.28 3040
HWR00015
INS00002,
9 LT Shockle insulator with fittings Each 16 54.28 868
HWR00016
10 BNT00037 C.I Knob Each 18 13 234
Base and Mass concreting of Poles, Stay
11 LS 1 36382 36382
sets
Misc. Items like coil earthing, pipe eathing,
12 LS 1 3933 3933
danger, bolts & nuts, etc
Total Material : 212715
3% Storage & Handling charges on items 1
5172
to 10
3% Contingencies on Materials 6381
Labour : 52646
Transport : 12856
10% Estt. & Genl. charges on Materials 21272
Sub-Total 311042
1% CESS on Sub-Total 3110
18% GST on Labour, Transport and CESS 12350
Total 326503
Or say : 326510

10 LT 3ph-5WL-65 . Pg: 1 / 1
REC Construction Standard No.B8/1984

Cost data per Km. of LT 3-ph 5 Wire line (Horizontal formation) with 3x55+2x34 sq.mm AAA
Conductor over 8 mts. PSCC poles at 40 mts. Span, 75 Kg/sq.mts. wind pressure, working
load 140 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
1 FBR00065 8 M PSCC pole Each 26 1575 40950
2 FBR00006 LT 3-ph 4 Wire line x-arms Each 28 438 12264
3 FBR00070 LT Top fitting with Clamp Each 28 269 7532
4 FBR00001 Back Clamp Each 28 68 1904
MS Stay set with stay clamp and without
5 FBR00008 Each 6 1343 8058
base plate
6 CDR00003 55 sq.mm AAA Conductor Km 3.06 27577 84384
7 CDR00002 34 sq.mm AAA Conductor Km 2.04 17974 36667
INS00001,
8 LT Pin Insulator with Pin Each 110 54.28 5971
HWR00015
INS00002,
9 LT Shockle insulator with fittings Each 26 54.28 1411
HWR00016
10 BNT00037 C.I Knob Each 28 13 364
Base and Mass concreting of Poles, Stay
11 LS 1 41355 41355
sets
Misc. Items like coil earthing, pipe eathing,
12 LS 1 3933 3933
danger, bolts & nuts, etc
Total Material : 244792
3% Storage & Handling charges on items 1
5985
to 10
3% Contingencies on Materials 7344
Labour : 73287
Transport : 17782
10% Estt. & Genl. charges on Materials 24479
Sub-Total 373669
1% CESS on Sub-Total 3737
18% GST on Labour, Transport and CESS 17065
Total 394471
Or say : 394480

11 LT 3ph-5WL-40 . Pg: 1 / 1
REC Construction Standard No.B8/1984

Cost data per Km. of LT 3-ph 5 Wire line (Horizontal formation) with 5x34 sq.mm AAA
Conductor over 8 mts. PSCC poles at 40 mts. Span, 75 Kg/sq.mts. wind pressure, working
load 140 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
1 FBR00065 8 M PSCC pole Each 26 1575 40950
2 FBR00006 LT 3-ph 4 Wire line x-arms Each 28 438 12264
3 FBR00070 LT Top fitting with Clamp Each 28 269 7532
4 FBR00001 Back Clamp Each 28 68 1904
MS Stay set with stay clamp and without
5 FBR00008 Each 6 1343 8058
base plate
6 CDR00002 34 sq.mm AAA Conductor Km 5.1 17974 91667
INS00001,
7 LT Pin Insulator with Pin Each 110 54.28 5971
HWR00015
INS00002,
8 LT Shockle insulator with fittings Each 26 54.28 1411
HWR00016

9 BNT00037 C.I Knob Each 28 13 364


Base and Mass concreting of Poles, Stay
10 LS 1 41355 41355
sets
Misc. Items like coil earthing, pipe eathing,
11 LS 1 3933 3933
danger, bolts & nuts, etc
Total Material : 215408
3% Storage & Handling charges on items 1
5104
to 9
3% Contingencies on Materials 6462
Labour : 73287
Transport : 17782
10% Estt. & Genl. charges on Materials 21541
Sub-Total 339583
1% CESS on Sub-Total 3396
18% GST on Labour, Transport and CESS 17004
Total 359983
Or say : 359990

12 LT 3ph-5WL-34 . Pg: 1 / 1
REC Construction Standard No.B8/1984

Cost data per Km. of LT 3-ph 4 Wire line (Horizontal formation) with 3x55+1x34 sq.mm AAA
Conductor over 8 mts. PSCC poles at 40 mts. Span, 75 Kg/sq.mts. wind pressure, working
load 140 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
1 FBR00065 8 M PSCC pole Each 26 1575 40950
2 FBR00006 LT 3-ph 4 Wire line x-arms Each 28 438 12264
3 FBR00001 Back Clamp Each 28 68 1904
MS Stay set with stay clamp and without
4 FBR00008 Each 6 1343 8058
base plate
5 CDR00003 55 sq.mm AAA Conductor Km 3.06 27577 84384
6 CDR00002 34 sq.mm AAA Conductor Km 1.02 17974 18333
INS00001,
7 LT Pin Insulator with Pin Each 78 54.28 4234
HWR00015
INS00002,
8 LT Shockle insulator with fittings Each 28 54.28 1520
HWR00016
9 BNT00037 C.I Knob Each 28 13 364
Base and Mass concreting of Poles, Stay
10 LS 1 41355 41355
sets
Misc. Items like coil earthing, pipe eathing,
11 LS 1 3933 3933
danger, bolts & nuts, etc
Total Material : 217298
3% Storage & Handling charges on items 1
5160
to 9
3% Contingencies on Materials 6519
Labour : 70077
Transport : 17782
10% Estt. & Genl. charges on Materials 21730
Sub-Total 338566
1% CESS on Sub-Total 3386
18% GST on Labour, Transport and CESS 16424
Total 358376
Or say : 358380

13 LT 3ph-4WL-40 . Pg: 1 / 1
REC Construction Standard No.B8/1984

Cost data per Km. of LT 3-ph 4 Wire line (Horizontal formation) with 4x34 sq.mm AAA
Conductor over 8 mts. PSCC poles at 50 mts. Span, 75 Kg/sq.mts. wind pressure, working
load 140 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code

1 FBR00065 8 M PSCC pole Each 20 1575 31500


2 FBR00006 LT 3-ph 4 Wire line x-arms Each 22 438 9636
3 FBR00001 Back Clamp Each 22 68 1496
MS Stay set with stay clamp and without
4 FBR00008 Each 6 1343 8058
base plate
5 CDR00002 34 sq.mm AAA Conductor Km 4.08 17974 73333
INS00001,
6 LT Pin Insulator with Pin Each 66 54.28 3582
HWR00015
INS00002,
7 LT Shockle insulator with fittings Each 22 54.28 1194
HWR00016
8 BNT00037 C.I Knob Each 22 13 286
Base and Mass concreting of Poles, Stay
9 LS 1 36382 36382
sets
Misc. Items like coil earthing, pipe eathing,
10 LS 1 3933 3933
danger, bolts & nuts, etc
Total Material : 169400
3% Storage & Handling charges on items 1
3873
to 8
3% Contingencies on Materials 5082
Labour : 58527
Transport : 14827
10% Estt. & Genl. charges on Materials 16940
Sub-Total 268649
1% CESS on Sub-Total 2686
18% GST on Labour, Transport and CESS 13687
Total 285023
Or say : 285030

14 LT 3ph-4WL-50 . Pg: 1 / 1
REC Construction Standard No.B11/1984

Cost data per Km. of LT S-ph 3 Wire line (Horizontal formation) with 34 sq.mm AAA
Conductor over 8 mts. PSCC poles at 50 mts. Span, 75 Kg/sq.mts. wind pressure, working
load 140 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
1 FBR00065 8 M PSCC pole Each 20 1575 31500
2 FBR00005 LT S-ph 3 Wire line x-arms Each 22 321 7062
3 FBR00001 Back Clamp Each 22 68 1496
MS Stay set with stay clamp and without
4 FBR00008 Each 6 1343 8058
base plate
5 CDR00002 34 sq.mm AAA Conductor Km 3.06 17974 55000

INS00001,
6 LT Pin Insulator with Pin Each 40 54.28 2171
HWR00015
INS00002,
7 LT Shockle insulator with fittings Each 8 54.28 434
HWR00016
8 BNT00037 C.I Knob Each 22 13 286
Base and Mass concreting of Poles, Stay
9 LS 1 32544 32544
sets
Misc. Items like coil earthing, pipe eathing,
10 LS 1 3933 3933
danger, bolts & nuts, etc
Total Material : 142484
3% Storage & Handling charges on items 1
3180
to 8
3% Contingencies on Materials 4275
Labour : 52189
Transport : 14827
10% Estt. & Genl. charges on Materials 14248
Sub-Total 231203
1% CESS on Sub-Total 2312
18% GST on Labour, Transport and CESS 12479
Total 245994
Or say : 246000

15 LT Sph-3WL . Pg: 1 / 1
REC Construction Standard No.B11/1984

Cost data per Km. of LT S-ph 2 Wire line (Horizontal formation) with 2x34 sq.mm AAA
Conductor over 8 mts. PSCC poles at 50 mts. Span, 75 Kg/sq.mts. wind pressure, working
load 140 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
1 FBR00065 8 M PSCC pole Each 20 1575 31500
2 FBR00004 LT S-ph 2 Wire line x-arms Each 22 204 4488
3 FBR00001 Back Clamp Each 22 68 1496
MS Stay set with stay clamp and without
4 FBR00008 Each 4 1343 5372
base plate
5 CDR00002 34 sq.mm AAA Conductor Km 2.04 17974 36667

INS00001,
6 LT Pin Insulator with Pin Each 22 54.28 1194
HWR00015

INS00002,
7 LT Shockle insulator with fittings Each 12 54.28 651
HWR00016

8 BNT00037 C.I Knob Each 22 13 286


Base and Mass concreting of Poles, Stay
9 LS 1 22597 22597
sets
Misc. Items like coil earthing, pipe eathing,
10 LS 1 3933 3933
danger, bolts & nuts, etc
Total Material : 108183
3% Storage & Handling charges on items 1
2450
to 8
3% Contingencies on Materials 3245
Labour : 49685
Transport : 14827
10% Estt. & Genl. charges on Materials 10818
Sub-Total 189209
1% CESS on Sub-Total 1892
18% GST on Labour, Transport and CESS 11953
Total 203054
Or say : 203060

16 LT Sph-2WL . Pg: 1 / 1
REC Construction Standard No.B32/1984

Cost data per Km. of LT line with 3x16+25 sq.mm AB Cable over 8 mts. PSCC poles at 65 mts.
Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

(Rs.)

Sl.No. Material Code Particulars Unit Qty. Rate Amount

1 FBR00065 8 M PSCC pole Each 16 1575 25200


2 FBR00004 LT S-ph 2 Wire line x-arms Each 17 204 3468
3 FBR00001 Back Clamp Each 17 68 1156
MS Stay set with stay clamp and without
4 FBR00008 Each 4 1343 5372
base plate
5 CBA00003 AB Cable 3x16+25 sq.mm Km 1.02 48396 49364
6 HWR00018 Suspension Clamp with eye hook Each 14 95 1336
7 HWR00013 Insulated Connectors with cover Each 4 86 344
8 HWR00009 Dead-end Clamp with eye hooks Each 4 95 382

9 Base and Mass concreting of Poles, Stay sets LS 1 22597 22597


Misc. Items like coil earthing, pipe eathing,
10 LS 1 3933 3933
danger, bolts & nuts, etc
Total Material : 113151
3% Storage & Handling charges on items 1 to
2599
8
3% Contingencies on Materials 3395
Labour : 41069
Transport : 12856
10% Estt. & Genl. charges on Materials 11315
Sub-Total 184384
1% CESS on Sub-Total 1844
18% GST on Labour, Transport and CESS 10038
Total 196267
Or say : 196270

17 LT ABC-3 . Pg: 1 / 1
REC Construction Standard No.B32/1984

Cost data per Km. of LT line with 2x16+25 sq.mm AB Cable over 8 mts. PSCC poles at 65 mts.
Span, 75 Kg/sq.mts. wind pressure, working load 140 Kgs.

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
1 FBR00065 8 M PSCC pole Each 16 1575 25200
2 FBR00004 LT S-ph 2 Wire line x-arms Each 17 204 3468
3 FBR00001 Back Clamp Each 17 68 1156
MS Stay set with stay clamp and without
4 FBR00008 Each 4 1343 5372
base plate
5 CBA00002 AB Cable 2x16+25 sq.mm Km 1.02 31107 31729
6 HWR00018 Suspension Clamp with eye hook Each 14 95 1336
7 HWR00013 Insulated Connectors with cover Each 4 86 344
8 HWR00009 Dead-end Clamp with eye hooks Each 4 95 382
Base and Mass concreting of Poles, Stay
9 LS 1 22597 22597
sets
Misc. Items like coil earthing, pipe eathing,
10 LS 1 3933 3933
danger, bolts & nuts, etc
Total Material : 95516
3% Storage & Handling charges on items 1
2070
to 8
3% Contingencies on Materials 2865
Labour : 41069
Transport : 12856
10% Estt. & Genl. charges on Materials 9552
Sub-Total 163928
1% CESS on Sub-Total 1639
18% GST on Labour, Transport and CESS 10002
Total 175569
Or say : 175570

18 LT ABC-2 . Pg: 1 / 1
REC Construction Standard No.F3 & F4/1993

Cost data for erection of 100 kva - 11 kv/433 V CSP / Amourphous coreDTR (Al) - BIS level -2
Transformer on DP Structure

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
100 kva CSP / Amourphous coreDTR (Al) -
1 Each 1 131601 131601
BIS level -2
2 ABS10002 Erection of 11 kv AB Switch (200A) Each 1 7025 7025
3 DP structure Each 1 18594 18594
4 HGF10002 Erection of 11 kv HG Fuse set Each 1 1880 1880
5 HGF00004 Erection of LT HG Fuse set Each 2 1260 2520
Metering arrangement with CTs including
6 Each 2 9415 18830
cable connections and cleat arrangement
Installation of HT Lightening Arresters
7 Each 1 1005 1005
(3 Nos.)
8 EMT00022 C.I Earth Pipes 50mm Dia Each 5 1585 7925
9 Construction plinth of 4x4x8 ft. LS 1 10035 10035
10 Misc LS 1 1573 1573
Total Material : 200989
3% Storage & Handling charges on items 1
5681
to 8
3% Contingencies on Materials 6030
Labour : 33871
Transport : 1612
10% Estt. & Genl. charges on Materials 20099
Sub-Total 268282
1% CESS on Sub-Total 2683
18% GST on Labour, Transport and CESS 6870
Total 277834
Or say : 277840

19 DTR100-BIS L2 . Pg: 1 / 1
REC Construction Standard No.F3 & F4/1993

Cost data for erection of 100 kva - 11 kv/433 V CSP / Amourphous core DTR (Al) - BIS level 3
Transformer on DP Structure

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
100 kva CSP / Amourphous core DTR (Al) -
1 Each 1 135127 135127
BIS level 3
2 ABS10002 Erection of 11 kv AB Switch (200A) Each 1 7025 7025
3 DP structure Each 1 18594 18594
4 HGF10002 Erection of 11 kv HG Fuse set Each 1 1880 1880
5 HGF00004 Erection of LT HG Fuse set Each 2 1260 2520
Metering arrangement with CTs including
6 Each 2 9415 18830
cable connections and cleat arrangement
Installation of HT Lightening Arresters
7 Each 1 1005 1005
(3 Nos.)
8 EMT00022 C.I Earth Pipes 50mm Dia Each 5 1585 7925
9 Construction plinth of 4x4x8 ft. LS 1 10035 10035
10 Misc LS 1 1573 1573
Total Material : 204515
3% Storage & Handling charges on items 1
5787
to 8
3% Contingencies on Materials 6135
Labour : 33871
Transport : 1612
10% Estt. & Genl. charges on Materials 20451
Sub-Total 272372
1% CESS on Sub-Total 2724
18% GST on Labour, Transport and CESS 6877
Total 281973
Or say : 281980

20 DTR100-BIS L3 . Pg: 1 / 1
REC Construction Standard No.F3 & F4/1993

Cost data for erection of 63 kva - 11 kv/433 V CSP / Amourphous core DTR (Al) - BIS level 3
Transformer on DP Structure

(Rs.)

Sl.No. Material Code Particulars Unit Qty. Rate Amount

63 kva CSP / Amourphous core DTR (Al) -


1 Each 1 117833 117833
BIS level 3
2 ABS10002 Erection of 11 kv AB Switch (200A) Each 1 7025 7025
3 DP structure Each 1 18594 18594
4 HGF10002 Erection of 11 kv HG Fuse set Each 1 1880 1880
5 HGF00004 Erection of LT HG Fuse set Each 2 1260 2520
Metering arrangement with CTs including
6 Each 2 9415 18830
cable connections and cleat arrangement
Installation of HT Lightening Arresters
7 Each 1 1005 1005
(3 Nos.)
8 EMT00022 C.I Earth Pipes 50mm Dia Each 5 1585 7925
9 Construction plinth of 4x4x8 ft. LS 1 10035 10035
10 Misc LS 1 1573 1573
Total Material : 187221
3% Storage & Handling charges on items 1
5268
to 8
3% Contingencies on Materials 5617
Labour : 33871
Transport : 1612
10% Estt. & Genl. charges on Materials 18722
Sub-Total 252311
1% CESS on Sub-Total 2523
18% GST on Labour, Transport and CESS 6841
Total 261675
Or say : 261680

21 DTR63-BIS L3 . Pg: 1 / 1
REC Construction Standard No.F3 & F4/1981

Cost data for erection of 25 kva 3-ph 11 kv/433 V CRGO / Amourphous core DTR (Al) - BIS level 2
Transformer

(Rs.)

Sl.No. Material Code Particulars Unit Qty. Rate Amount

25 kva 3-ph CRGO / Amourphous core DTR


1 Each 1 63661 63661
(Al) - BIS level 2
2 ABS10002 Erection of 11 kv AB switch (200A) Each 1 7025 7025
3 HGF10002 Erection of 11 kv HG Fuse set Each 1 1880 1880
4 Construction plinth of 4x4x8 ft. LS 1 10035 10035

5 HGF00004 Erection of LT HG Fuse set Each 1 1260 1260

6 CDR00002 55 sq.mm AAA Conductor Mts. 20 27.58 552

7 LT 3 1/2 core 50 sq.mm PVC cable Mts. 14 184.66 2585

3-ph Electronic meter with 50/5A CTs housed


8 Each 1 1848 1848
in SMC box
9 FBR00066 9.1 mts. PSCC pole Each 1 3197 3197
10 FBR00026 MS stay set with clamp Each 1 1343 1343
11 LAS00003 11 kv Lightining Arresters Each 3 335 1005
12 FBR00023 11 kv Tapping x-arm (Horizontal) Each 1 758 758
13 FBR00002 Back clamp Each 1 68 68

INS10002,
14 11 kv strain insulator with metal parts Each 3 325 974
HWR00002

15 EMT00006 C.I Earth Pipes 50mm Dia earthing Each 5 3300 16500
16 Concreting of pole & stay set LS 1 6461 6461
17 Misc. items (Bolts & Nuts, Washers etc.) LS 1 701 701
Total Material : 119854
3% Storage & Handling charges on items 1 to
3381
15
3% Contingencies on Materials 3596
Labour : 23826
Transport : 1612
10% Estt. & Genl. charges on Materials 11985
Sub-Total 164253
1% CESS on Sub-Total 1643
18% GST on Labour, Transport and CESS 4874
Total 170770
Or say : 170780

22 DTR25 - BIS L2 . Pg: 1 / 1


REC Construction Standard No.F3 & F4/1981

Cost data for erection of 25 kva S-ph 6.3 kv/0-240 V CSP 25 kva S-ph CRGO / Amourphous
core DTR (Al) - BIS level 2 Transformer on existing 8 mts. PSCC support

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
25 kva S-ph CRGO / Amourphous core
1 DTC10004 Each 1 54550 54550
DTR (Al) - BIS level 2
2 ABS10002 Erection of 11 kv AB switch (200A) Each 1 7025 7025

3 HGF10002 Erection of 11 kv HG Fuse set Each 1 1880 1880

4 FBR00035 Mounting arrangements for Transformer Set 1 3117 3117


5 EMT00006 C.I Earth Pipes 50mm Dia Each 2 3836 7672

LT Distribution Box (S-ph) with XLPE 70


6 Each 1 1730 1730
sq.mm cable and 100 A fuse unit completely

7 Misc. items (Bolts & Nuts, Washers etc.) LS 1 996 996


Total Material : 76971
3% Storage & Handling charges on items 1
2279
to 4
3% Contingencies on Materials 2309
Labour : 4247
Transport : 729
10% Estt. & Genl. charges on Materials 7697
Sub-Total 94233
1% CESS on Sub-Total 942
18% GST on Labour, Transport and CESS 1065
Total 96240
Or say : 96250

23 DTR15 CSP . Pg: 1 / 1


REC Construction Standard No.H6 & H8/1981

Cost data for Release of Poly phase Agricultural service erected on support

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
3-ph High Quality Electronic meter (10-40A)
1 MTE30001 Each 1 1848 1848
without PP Box
2 3-ph 40A MCB Each 1 715 715
3 PVC Cable 6 sq.mm Single core Each 90 5.51 496
4 Installation of 2 KVAR Capacitor Each 1 866 866
5 Moulded Distribution Box Each 1 731 731
6 Misc. items (Bolts & Nuts, Washers etc.) LS 1 172 172
Total Material : 4827
3% Storage & Handling charges on items 1
140
to 5
3% Contingencies on Materials 145
Labour : 787
Transport : 200
10% Estt. & Genl. charges on Materials 483
Sub-Total 6581
1% CESS on Sub-Total 66
18% GST on Labour, Transport and CESS 189
Total 6836
Or say : 6840

24 SC-Agl . Pg: 1 / 1
REC Construction Standard No.H1 to H3/1981

Cost data for Release of Domestic and Non-Domestic Service Connection (S-ph) with Electronic meter

(Rs.)
Chargeable to Chargeable to
Material Item Rate
Sl.No. Particulars TSNPDCL Consumer Amount
Code
Unit Rate Qty. Rate Qty. Rate
MTE10015, S-ph Electronic meter (5-30 A) housed in a
1 Each 639 1 639 639
MTE10016 PP Box
2 S-ph MCB 16A Each 200.2 1 200 200

3 PVC Cable Single core 2.5 sq.mm Mts. 6 60 360 360

4 GI Wire No.6 Kg 69.03 1 69 69

5 PVC Pipe 25 mm Mts. 54.6 2 109 109

6 PVC Bends 25 mm Each 11.7 2 23 23

7 Misc. items (Bolts & Nuts, Washers etc.) LS 171.6 1 172 172

Total Material : 839 733 1572


3% Storage & Handling charges on items 1
25 17 42
to 6
3% Contingencies on Materials 25 22 47

Labour : 237 572 809

Transport : 86 129 215

10% Estt. & Genl. charges on Materials 84 73 157

Sub-Total 1296 1546 2842


1% CESS on Sub-Total 13 15 28

18% GST on Labour, Transport and CESS 60 129 189

Total 3060
Or say : 3060

25 SC-Dom-Sph . Pg: 1 / 1
REC Construction Standard No.H1 to H3/1981

Cost data for Domestic and Non-Domestic Service Connection (3-ph) with Electronic meter

(Rs.)
Chargeable to Chargeable to
Item Rate
Sl.No. Material Code Particulars DISCOM Consumer Amount
Unit Rate Qty. Rate Qty. Rate

1 MTE30001 LT 3-ph Electronic meter 10-40A Each 1848 1 1848 1848

2 3-ph MCB 40A Each 715 1 715 715

3 PVC Cable Single core 6 sq.mm Mts. 5.51 120 661 661

4 GI Wire No.8 Kg 69 1 69 69

5 PVC Pipe 40 mm Mts. 71.5 2 143 143

6 PVC Bends 40 mm Each 26 2 52 52

7 Misc. items (Bolts & Nuts, Washers etc.) LS 171.6 1 172 172

Total Material : 2563 1096 3659


3% Storage & Handling charges on items 1
77 28 105
to 6
3% Contingencies on Materials 77 33 110
Labour : 501 715 1216
Transport : 129 179 308
10% Estt. & Genl. charges on Materials 256 110 366
Sub-Total 3602 2161 5763
1% CESS on Sub-Total 36 22 58
18% GST on Labour, Transport and CESS 120 165 285
Total 6106
Or say : 6110

26 SC-Dom-3ph . Pg: 1 / 1
REC Construction Standard No.H5/1981

Cost data for Poly phase Service connection charges for erection of 1 No. Industrial service (Below 20 HP)
(Electronic meter)

(Rs.)
Chargeable to Chargeable to
Item Rate
Sl.No. Material Code Particulars DISCOM Consumer Amount
Unit Rate Qty. Rate Qty. Rate

1 MTE30001 LT 3-ph Electronic meter 10-40A Each 1848 1 1848 1848

2 3-ph MCB 40A Each 715 1 715 715

3 PVC Cable Single core 10 sq.mm Mts. 8.74 80 699 699

4 GI Wire No.8 Kg 69.03 1 69 69

5 PVC Pipe 40 mm Mts. 71.5 2 143 143

6 PVC Bends 40 mm Each 26 2 52 52


Misc. items (Bolts & Nuts, Washers, Link
7 LS 357.5 1 358 358
clips, Wooden box etc.)
Total Material : 2563 1321 3883
3% Storage & Handling charges on items 1
77 29 106
to 6
3% Contingencies on Materials 77 40 117

Labour : 501 715 1216

Transport : 129 179 308

10% Estt. & Genl. charges on Materials 256 132 388

Sub-Total 3602 2415 6018

1% CESS on Sub-Total 36 24 60

18% GST on Labour, Transport and CESS 120 165 285

Total 6363
Or say : 6370

27 SC-Ind-20 . Pg: 1 / 1
REC Construction Standard No.H5/1981

Cost data for Poly phase Service connection charges for erection of 1 No. Industrial service (20 HP to 50 HP) (LT
Trivector meter)

(Rs.)
Chargeable to Chargeable to
Item Rate
Sl.No. Material Code Particulars DISCOM Consumer Amount
Unit Rate Qty. Rate Qty. Rate
LT 3-ph Class-0.5 Accuracy CT operated
1 MTO10020 Each 6503 1 6503 6503
Electronic meter (125/5A)
2 3-ph MCB 63A Each 1573 1 1573 1573

3 PVC Cable Single core 10 sq.mm Mts. 8.74 80 699 699

4 WRS00005 GI Wire No.8 Kg 69.03 1 69 69

5 PVC Pipe 40 mm Mts. 72 2 143 143

6 PVC Bends 40 mm Each 26 2 52 52


Misc. items (Bolts & Nuts, Washers, Link
7 LS 358 1 358 358
clips, Wooden box etc.)
Total Material : 8076 1321 9397
3% Storage & Handling charges on items 1 to
242 29 271
6
3% Contingencies on Materials 242 40 282

Labour : 644 729 1373

Transport : 157 194 351

10% Estt. & Genl. charges on Materials 808 132 940

Sub-Total 10169 2444 12614

1% CESS on Sub-Total 102 24 126

18% GST on Labour, Transport and CESS 162 171 333

Total 13073
Or say : 13080

28 SC-Ind-50 . Pg: 1 / 1
REC Construction Standard No.H5/1981

Cost data for Poly phase Service connection charges for erection of 1 No. Industrial service (50 HP to
75 HP) (HT metering)

(Rs.)
Sl.No. Material Code Particulars Unit Qty. Rate Amount

1 DP structure with 9.1 mts. PSCC poles Each 1 19599 19599

2 ABS10002 11 kv 200 Amps Tilting type AB switch Each 1 7025 7025


3 HGF10002 11 kv HG Fuse set Each 2 1880 3760
4 CBX10002 3x35 sq.mm 11 kv XLPE cable Mts. 30 317.67 9530
3x35 sq.mm Heat shrinkable cable jointing
5 SCB10017 Each 1 703 703
Kit
6 EMT00022 CI pipe Nos. 3 1585 4755

7 11 kv CT PT 10-20/5 Each 1 38908 38908

8 HT Trivector meter 0.2 class Each 1 5999 5999


Misc. items (Bolts & Nuts, Washers, Link
9 LS 1 787 787
clips, Wooden box etc.)
Total Material : 91066
3% Storage & Handling charges on items 1
2708
to 9
3% Contingencies on Materials 2732

Labour : 29254

Transport : 3289
10% Estt. & Genl. charges on Materials 9107

Sub-Total 138157
1% CESS on Sub-Total 1382
18% GST on Labour, Transport and CESS 6106
Total 145645
Or say : 145650

29 SC-Ind-75 . Pg: 1 / 1
REC Construction Standard No.H5/1981

Cost data for Poly phase Service connection charges for erection of 1 No. HT service (Above 75 HP)
(HT metering)

(Rs.)

Sl.No. Material Code Particulars Unit Qty. Rate Amount

1 DP structure with 9.1 mts. PSCC poles Each 2 19599 39198

2 ABS10002 11 kv 200 Amps Tilting type AB switch Each 1 7025 7025


3 HGF10002 11 kv HG Fuse set Each 2 1880 3760
4 CBX10002 3x35 sq.mm 11 kv XLPE cable Mts. 30 317.67 9530

5 SCB10017 3x35 sq.mm Heat shrinkable cable jointing Kit Each 1 703 703

6 EMT00022 CI pipe Nos. 3 1585 4755

ITR10007,
7 11 kv CT PT 10-20/5 Each 1 38908 38908
ITR10037
8 HT Trivector meter 0.2 class Each 1 5999 5999
9 GI HT Meter Box Each 1 4720 4720
Misc. items (Bolts & Nuts, Washers, Link
10 LS 1 787 787
clips, Wooden box etc.)
Total Material : 115385
3% Storage & Handling charges on items 1
3438
to 9
3% Contingencies on Materials 3462

Labour : 45715

Transport : 3289
10% Estt. & Genl. charges on Materials 11539

Sub-Total 182828
1% CESS on Sub-Total 1828
18% GST on Labour, Transport and CESS 9150
Total 193806
Or say : 193810

30 SC-Ind-HT . Pg: 1 / 1
Cost data for Street Light Service Connection (S-ph)

(Rs.)

Sl.No. Material Code Particulars Unit Qty. Rate Amount

MTE10015, LT S-ph (5-30A) IRDA Electronic Energy


1 Each 1 639 639
MTE10016 meter (with PP Box)
2 S-ph MCB 16A Each 1 200 200
3 Light sensitive switch Each 1 644 644
4 PVC Cable 6 sq.mm Single core Mts. 15 5.51 83
5 PVC Pipe 25 mm Each 2 55 109
6 PVC Bends 25 mm Each 2 12 23
7 Moulded Distribution Box Each 1 731 731
8 Misc. items (Bolts & Nuts, Washers etc.) LS 1 237 237
Total Material : 2666
3% Storage & Handling charges on items 1
73
to 7
3% Contingencies on Materials 80

Labour : 1087

Transport : 272
10% Estt. & Genl. charges on Materials 267

Sub-Total 4443
1% CESS on Sub-Total 44
18% GST on Labour, Transport and CESS 253
Total 4740
Or say : 4750

31 SC-Street . Pg: 1 / 1
Cost data for erection of 1 No. LT Electronic Trivector meter on LV side of DTR

(Rs.)

Sl.No. Material Code Particulars Unit Qty. Rate Amount

LT 3-ph Class-0.5 Accuracy CT operated


1 MTO10020 Each 1 6503 6503
Electronic meter (125/5A)
2 CBX00013 3.5 core 95 LT XLPE cable Mts. 10 251.72 2517
Mounting arrangements (MS Angle 50x50x6
3 FBR00090 LS 1 644 644
mm, MS Flat 50x6 mm)
Misc. items (Bolts & Nuts, Washers, Lugs
4 LS 1 315 315
etc.)
Total Material : 9979
3% Storage & Handling charges on items 1
290
to 3
3% Contingencies on Materials 299

Fixing of CT operated meter on LV side of


Distribution transformers with box including 1258
cost of lugs, clamps, GI wire (LABOUR)

Transport : 315
10% Estt. & Genl. charges on Materials 998

Sub-Total 13139
1% CESS on Sub-Total 131
18% GST on Labour, Transport and CESS 307
Total 13577
Or say : 13580

32 SC-DTR-LV . Pg: 1 / 1
Cost data for erection of 2 MVAR Capacitor Bank

(Rs.)

Sl.No. Material Code Particulars Unit Qty. Rate Amount

2 MVAR 11 kv Capacitor Bank along with


1 CPT10009 associated equipment (Capactors, Structure Each 1 782400 782400
and VCB)
24 V 40 AH Battery set including Battery
2 BAT00027 Each 1 25813 25813
charger
3 MST00012 MS Channel 100x50 mm MT 0.24 55427 13302

4 MST00014 MS flat 50x6 mm MT 0.36 57197 20591

5 CDR00010 Panther conductor Km 0.05 147854 7393

6 CBP00002 10 core 2.5 sq.mm PVC Copper control cable Km 0.1 189590 18959

7 CBP00006 4 core 2.5 sq.mm PVC Copper control cable Km 0.11 72341 7958

9 INS10008 11 kv Post type insulators Each 3 275 825

10 EMT00006 Cost of CI pipe Each 2 3300 6600

11 HGF10002 11 kv HG Fuse set with Insulators Each 1 1880 1880

12 LAS00002 11 kv LAs Station type Each 3 1652 4956

13 Miscellaneous items LS 1 787 787

Total Material : 891463


3% Storage & Handling charges on items 1
26720
to 12
3% Contingencies on Materials 26744

Labour : 71385

Transport : 8580

10% Estt. & Genl. charges on Materials 89146

Sub-Total 1114038

1% CESS on Sub-Total 11140

18% GST on Labour, Transport and CESS 16399

Total 1141577

Or say : 1141580

33 Cap . Pg: 1 / 1
Cost data for erection of 11 kv Bay Extension in existing 33/11 kv SS (with RS Joist)

(Rs.)

Sl.No. Material Code Particulars Unit Qty. Rate Amount

150x150 mm H type beam of 8.5 mts. length


1 MST00029 MT 0.598 57197 34227
(2 Nos. RS Joist)
2 MST00012 100x50 mm Channel MT 0.166 55427 9195
3 MST00014 MS flat 75x8 mm MT 0.050 57197 2860
4 ABS10008 AB switch 400 Amps conventional type Each 2 7434 14868
200 sq.mm ACSR Conductor (Panther
5 CDR00010 Km 0.02 147854 2957
conductor)
INS10002,
6 Disc type Insulator with metal parts Each 18 325 5845
HWR00002

7 MS flat 50x6 mm Mts. 20 57.20 1144

Misc. items (Bolts & Nuts, Washers, Pad


8 LS 1 2360 2360
clamps etc.)
Total Material : 73455
3% Storage & Handling charges on items 1
2133
to 7
3% Contingencies on Materials 2204

Labour : 12311

Transport : 2714
10% Estt. & Genl. charges on Materials 7345

Sub-Total 100162
1% CESS on Sub-Total 1002
18% GST on Labour, Transport and CESS 2885
Total 104048
Or say : 104050

34 Bay11-RS . Pg: 1 / 1
Cost data for erection of 11 kv Bay Extension in existing 33/11 kv SS (with 9.1 mts. PSCC pole)

(Rs.)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code

1 FBR00066 9.1 mts. PSCC pole 280 Kg WL Each 2 3197 6395

2 MST00012 100x50 mm Channel MT 0.166 55427 9195


3 MST00015 MS flat 75x8 mm MT 0.050 57197 2860
4 ABS10008 AB switch 400 Amps conventional type Each 1 7434 7434
200 sq.mm ACSR Conductor (Panther
5 CDR00010 Km 0.02 147854 2957
conductor)
INS10002,
6 Disc type Insulator with metal parts Each 18 325 5845
HWR00002
Earthing arrangement (20 mts. length with
7 MST00015 Mts. 20 57.20 1144
75x8 MS flat
Misc. items (Bolts & Nuts, Washers, Pad
8 LS 1 2360 2360
clamps etc.)
Total Material : 38189
3% Storage & Handling charges on items 1
1075
to 7
3% Contingencies on Materials 1146
Labour : 12311
Transport : 2714
10% Estt. & Genl. charges on Materials 3819
Sub-Total 59254
1% CESS on Sub-Total 593
18% GST on Labour, Transport and CESS 2811
Total 62657
Or say : 62660

35 Bay11-PSCC . Pg: 1 / 1
Tower Details

Sl.No. Descriptioin Unit Qty.

1 Weight of M type tower with 2 sections MT 1.375

2 Weight of 1 No. extension of 3 mts. MT 0.394

3 Weight of M+3 tower MT 1.769

4 Weight of M+6 tower MT 2.163

5 Weight of M+9 tower MT 2.557

6 Weight of M+12 tower MT 2.951

7 Weight of each arm MT 0.03

36 Towers . Pg: 1 / 1
Cost data for erection of M+3 Tower as per standards

(Rs.)

Material Material Labour


Sl.No. Particulars Unit Qty.
Code Rate Amount Rate Amount
Supply of M+3 type tower with 2 section
1 OTH10454 MT 1.946 57197 111300
along with stubs
Fabrication of M+3 type tower with 2 section
2 Each 1 10382 10382
with 1 coat of redoxide paint

Excavation of pit including dewatering,


planking, showring and shuttering (where
3 ever necessary) and leveling in all types of CUM 8.96 151 1351
soils such as BC, red earth, hard gravel etc.,
(size 1.6x1.6x3.5 mts. i.e., 8.96 cum

Erection of tower parts completely as per


specifications including erection of insulators
4 with all accessores, jumpering, transport of MT 1.769 12932 22877
meterial and painting of tower with two coats
of alluminium paint and bolts and nuts etc.

Setting of stubs in position for laying of


foundation of towers with 1:3:6 CC mix using
40 mm HBG metal including cost of all
5 concreting materials and cement and curing CUM 9.98 5613 56022
for 14 days (40 mm HBG metal for pyramid
portion and 20 mm HBG metal for chimney
portion) i.e., 9.98 cum

Tack welding bolt and nuts upto 20 feet from


6 Job 1 1195 1195
ground (144 Nos. bolts to be welded)

Pipe earthing of towers with 50 mm dia CI


7 EMT00022, earth pipe, including cost of pipe, bentonite Each 2 1585 3170 1624 3247
powder and running of GI flat etc.

Sub Total : 114470 95074


3% Storage & Handling charges on items 1
3434
to 7
3% Contingencies on Materials 3434

Labour & Transport : 95074

Sub-Total 216412

1% CESS on Sub-Total 2164

18% GST on Labour, Transport and CESS 17503

Total 236079

Or say : 236080

Schedule of Tower
1 100x100x10 (Stubs) Mts. 4.5
2 100x100x10 Mts. 3.4
3 100x100x10 Mts. 3.0
4 80x80x10 Mts. 3.0
5 65x65x6 Mts. 3.0
Total height : Mts. 16.9
Depth of tower below ground level Mts. 3.4
Hight of tower above ground level : Mts. 13.5

37 M+3 . Pg: 1 / 1
Cost data for erection of M+6 Tower as per standards

(Rs.)
Material Labour
Sl.No. Material Code Particulars Unit Qty.
Rate Amount Rate Amount
Supply of M+6 type tower with 2 section
1 OTH10453 MT 2.379 57197 136089
along with stubs
Fabrication of M+6 type tower with 2 section
2 Each 1 10382 10382
with 1 coat of redoxide paint

Excavation of pit including dewatering,


planking, showring and shuttering (where
3 ever necessary) and leveling in all types of CUM 8.96 151 1351
soils such as BC, red earth, hard gravel etc.,
(size 1.6x1.6x3.5 mts. i.e., 8.96 cum

Erection of tower parts completely as per


specifications including erection of insulators
4 with all accessores, jumpering, transport of MT 2.163 12932 27973
meterial and painting of tower with two coats
of alluminium paint and bolts and nuts etc.

Setting of stubs in position for laying of


foundation of towers with 1:3:6 CC mix using
40 mm HBG metal including cost of all
5 concreting materials and cement and curing CUM 9.98 5613 56022
for 14 days (40 mm HBG metal for pyramid
portion and 20 mm HBG metal for chimney
porti

Tack welding bolt and nuts upto 20 feet from


6 Job 1 1195 1195
ground (144 Nos. bolts to be welded)

Pipe earthing of towers with 50 mm dia CI


7 EMT00022, earth pipe, including cost of pipe, bentonite Each 2 1585 3170 1624 3247
powder and running of GI flat etc.

Sub Total : 139259 100170


3% Storage & Handling charges on items 1
4178
to 7
3% Contingencies on Materials 4178

Labour & Transport : 100170

Sub-Total 247784

1% CESS on Sub-Total 2478

18% GST on Labour, Transport and CESS 18477

Total 268738

Or say : 268740

Schedule of Tower
1 100x100x10 (Stubs) Mts. 4.5
2 100x100x10 Mts. 3.4
3 100x100x10 Mts. 3.0
4 100x100x10 Mts. 3.0
5 80x80x10 Mts. 3.0
6 65x65x6 Mts. 3.0
Total height : Mts. 19.9
Depth of tower below ground level Mts. 3.4
Hight of tower above ground level : Mts. 16.5

38 M+6 . Pg: 1 / 1
Cost data for erection of M+9 Tower as per standards

(Rs.)
Material Material Labour
Sl.No. Particulars Unit Qty.
Code Rate Amount Rate Amount
Supply of M+9 type tower with 2 section
1 OTH10455 MT 2.813 57197 160895
along with stubs
Fabrication of M+9 type tower with 2 section
2 Each 1 10382 10382
with 1 coat of redoxide paint

Excavation of pit including dewatering,


planking, showring and shuttering (where
3 ever necessary) and leveling in all types of CUM 8.96 151 1351
soils such as BC, red earth, hard gravel etc.,
(size 1.6x1.6x3.5 mts. i.e., 8.96 cum

Erection of tower parts completely as per


specifications including erection of insulators
4 with all accessores, jumpering, transport of MT 2.557 12932 33068
meterial and painting of tower with two coats
of alluminium paint and bolts and nuts etc.

Setting of stubs in position for laying of


foundation of towers with 1:3:6 CC mix using
40 mm HBG metal including cost of all
5 concreting materials and cement and curing CUM 9.98 5613 56022
for 14 days (40 mm HBG metal for pyramid
portion and 20 mm HBG metal for chimney
portion) i.e., 9.98 cum

Tack welding bolt and nuts upto 20 feet from


6 Job 1 1195 1195
ground (144 Nos. bolts to be welded)

Pipe earthing of towers with 50 mm dia CI


7 EMT00022, earth pipe, including cost of pipe, bentonite Each 2 1585 3170 1624 3247
powder and running of GI flat etc.

Sub Total : 164065 105265


3% Storage & Handling charges on items 1
4922
to 7
3% Contingencies on Materials 4922

Labour & Transport : 105265

Sub-Total 279174

1% CESS on Sub-Total 2792

18% GST on Labour, Transport and CESS 19450

Total 301416

Or say : 301420

Schedule of Tower
1 100x100x10 (Stubs) Mts. 4.5
2 100x100x10 Mts. 3.4
3 100x100x10 Mts. 3.0
4 100x100x10 Mts. 3.0
5 100x100x10 Mts. 3.0
6 80x80x10 Mts. 3.0
7 65x65x6 Mts. 3.0
Total height : Mts. 22.9
Depth of tower below ground level Mts. 3.4
Hight of tower above ground level : Mts. 19.5

39 M+9 . Pg: 1 / 1
Cost data for erection of M+12 Tower as per standards

(Rs.)
Material Material Labour
Sl.No. Particulars Unit Qty.
Code Rate Amount Rate Amount
Supply of M+12 type tower with 2 section
1 OTH10456 MT 3.246 57197 185661
along with stubs
Fabrication of M+12 type tower with 2
2 Each 1 10382 10382
section with 1 coat of redoxide paint

Excavation of pit including dewatering,


planking, showring and shuttering (where
3 ever necessary) and leveling in all types of CUM 8.96 151 1351
soils such as BC, red earth, hard gravel etc.,
(size 1.6x1.6x3.5 mts. i.e., 8.96 cum

Erection of tower parts completely as per


specifications including erection of insulators
4 with all accessores, jumpering, transport of MT 2.951 12932 38164
meterial and painting of tower with two coats
of alluminium paint and bolts and nuts etc.

Setting of stubs in position for laying of


foundation of towers with 1:3:6 CC mix using
40 mm HBG metal including cost of all
5 concreting materials and cement and curing CUM 9.98 5613 56022
for 14 days (40 mm HBG metal for pyramid
portion and 20 mm HBG metal for chimney
portion) i.e., 9.98 cum

Tack welding bolt and nuts upto 20 feet from


6 Job 1 1195 1195
ground (144 Nos. bolts to be welded)

Pipe earthing of towers with 50 mm dia CI


7 EMT00022, earth pipe, including cost of pipe, bentonite Each 2 1585 3170 1624 3247
powder and running of GI flat etc.

Sub Total : 188831 110360


3% Storage & Handling charges on items 1
5665
to 7
3% Contingencies on Materials 5665

Labour & Transport : 110360

Sub-Total 310522

1% CESS on Sub-Total 3105

18% GST on Labour, Transport and CESS 20424

Total 334051

Or say : 334060

Schedule of Tower
1 100x100x10 (Stubs) Mts. 4.5
2 100x100x10 Mts. 3.4
3 100x100x10 Mts. 3.0
4 100x100x10 Mts. 3.0
5 100x100x10 Mts. 3.0
6 100x100x10 Mts. 3.0
7 80x80x10 Mts. 3.0
8 65x65x6 Mts. 3.0
Total height : Mts. 25.9
Depth of tower below ground level Mts. 3.4
Hight of tower above ground level : Mts. 22.5

40 M+12 . Pg: 1 / 1
Cost data for erection of 33/11 kv SS with 2x8 mva Power Transformer and NF = 6
No. 11 kv feeders (with 11 kv 2 MVAR Capacitor Bank)

(Rs. in lakhs)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
As per
1a Lands and Rights LS 1 local 2.000
conditions
1b Plantation of Trees LS 1 0.198 0.198
Control Room and Consumer Service
2 LS 1 6.600 6.600
Centre (including furniture)
3 Station Auxillaries
Peripheral, Security Fencing,
Approach road, Retaing wall around
a) LS 1 9.240 9.240
Switchyard with gravel filling, Gate
and Bore well
b) Yard lighting LS 1 0.792 0.792
c) Fire fighting equipment LS 1 0.876 0.876
d) P&T phone and wireless set LS 1 0.660 0.660
Foundations for structures, PTRs &
4 LS 1 6.600 6.600
breakers
Bus bars, Jumpers, Connectors
5 LS 1 3.300 3.300
clamps etc.
6 Control Cables LS 1 2.640 2.640
7 Structural Steel MT 20 0.572 11.439
8 Transformers
a) PTR00008 33/11 kv 8 mva Power Transformer Each 2 49.999 99.997
11 KV 25 kva 3-ph CRGO /
b) DTC30002 Amourphous core DTR (Al) - BIS level Each 1 0.637 0.637
2
Circiut Breakres (including Trivector
9
meters)
33 kv Group control with CTs and
a) BRK30002 Each 2 3.883 7.766
panel
20 KA 11 kv feeder VCB including
b) BRK10002 Each 6 2.430 14.580
Control panel and CTs (NF=6)
20 KA 11 kv LV VCB including Control
c) BRK10004 Each 2 2.450 4.900
panel and CTs
10 Control Circiut Panels
a) AC Supply Panel Each 1 0.396 0.396
b) Alaram Panel Each 1 0.396 0.396
11 Instrumnet Transformers
a) ITR30038 33 kv PT (Single unit) Each 3 0.207 0.620
b) ITR10032 11 kv PT (3-ph) Each 1 0.191 0.191
12 Lightning Arrestors
a) LAS00004 33 kv 10 KA Each 6 0.033 0.198
b) LAS00002 11 kv Station type 10 KA Each 6 0.017 0.099
c) LAS00001 11 kv Line Type (NF=6) Each 18 0.003 0.060

41 SS-2x8-CB . Pg: 1 / 2
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
13 Isolating switches
33 kv 800 Amps AB Switch (Double
a) ABS30004 Each 4 0.363 1.454
break)
b) ABS10015 11 kv 800A AB switch (Double break) Each 4 0.153 0.611
c) ABS10008 11 kv 400A AB switch Each 12 0.074 0.892
d) ABS10004 11 kv 200A AB switch Each 1 0.080 0.080
e) HGF30002 33 kv Horn Gap Fuse set (1xNT) Each 2 0.071 0.142
f) HGF10002 11 kv HG fuse set with insulators Each 1 0.019 0.019
2 MVAR 11 kv Capacitor Bank along
14 CPT10009 Each 1 8.915 8.915
with Associated equipment
24 V 40 AH Battery set including
15 BAT00027 Each 4 0.258 1.033
Battery charger and DC DB
Earthing of Power Transformer VCBs,
16 AB swicthes, Strucutres with 75x8 mm LS 1 5.720 5.720
GI Flat

Total Material : 193.050


11% Labour charges for Erection &
16.987
Commissioning on items 7 to 15
4% Transport charges on items 7 to
6.177
15
3% Contingencies on items 7 to 15 4.633
1% T&P charges on items 7 to 15 1.544
10% Estt. & Genl. charges on
19.305
Materials
1% Cess on (M+L+T) 2.162
GST 18% on Labour portion,
4.559
Transport and CESS
Total : 248.42
Or say : 248

Note: NF = No.of 11 kv feeders. The No.of outgoing feeders at substation limited


to the demand in MVA i.e., if substation demand is 5 MVA, the No.of
feeders should not exceed five

41 SS-2x8-CB . Pg: 2 / 2
Cost data for erection of 33/11 kv SS with 2x8 mva Power Transformer and NF = 6 No.
11 kv feeders (without 11 kv 2 MVAR Capacitor Bank)

(Rs. in lakhs)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
As per
1a Lands and Rights LS 1 local 2.000
conditions
1b Plantation of Trees LS 1 0.198 0.198
Control Room and Consumer Service
2 LS 1 6.600 6.600
Centre (including furniture)
3 Station Auxillaries
Peripheral, Security Fencing, Approach
a) road, Retaing wall around Switchyard LS 1 9.240 9.240
with gravel filling, Gate and Bore well
b) Yard lighting LS 1 0.792 0.792
c) Fire fighting equipment LS 1 0.876 0.876
d) P&T phone and wireless set LS 1 0.660 0.660
Foundations for structures, PTRs &
4 LS 1 6.600 6.600
breakers
Bus bars, Jumpers, Connectors clamps
5 LS 1 3.300 3.300
etc.
6 Control Cables LS 1 2.640 2.640
7 Structural Steel MT 20 0.572 11.439
8 Transformers
a) PTR00008 33/11 kv 8 mva Power Transformer Each 2 49.999 99.997
25 kva 3-ph CRGO / Amourphous core
b) DTC30002 Each 1 0.637 0.637
DTR (Al) - BIS level 2
9 Circiut Breakres (including Trivector meters)
a) BRK30002 33 kv Group control with CTs and panel Each 2 3.883 7.766
20 KA 11 kv feeder VCB including
b) BRK10002 Each 6 2.430 14.580
Control panel and CTs (NF=6)
20 KA 11 kv LV VCB including Control
c) BRK10004 Each 2 2.450 4.900
panel and CTs
10 Control Circiut Panels
a) AC Supply Panel Each 1 0.396 0.396
b) Alaram Panel Each 1 0.396 0.396
11 Instrumnet Transformers
a) 33 kv PT (Single unit) Each 3 0.207 0.620
b) ITR10032 11 kv PT (3-ph) Each 1 0.191 0.191
12 Lightning Arrestors
a) LAS00004 33 kv 10 KA Each 6 0.033 0.198
b) LAS00002 11 kv Station type 10 KA Each 6 0.017 0.099
c) LAS00001 11 kv Line Type (NF=6) Each 18 0.003 0.060

42 SS-2x8 . Pg: 1 / 2
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
13 Isolating switches
a) ABS30004 33 kv 800A AB switch (Double break) Each 4 0.363 1.454
b) ABS10015 11 kv 800A AB switch (Double break) Each 4 0.153 0.611
c) ABS10008 11 kv 400A AB switch Each 12 0.074 0.892
d) ABS10004 11 kv 200A AB switch Each 1 0.080 0.080
e) HGF30002 33 kv Horn Gap Fuse set (1xNT) Each 2 0.071 0.142
f) HGF10002 11 kv HG fuse set Each 1 0.019 0.019
24 V 40 AH Battery set including Battery
14 BAT00027 Each 4 0.258 1.033
charger and DC DB
Data Acquisition Euipement (SIM,
15 LS 1 0.715 0.715
Modem, Cabling etc.)
Earthing of Power Transformer VCBs,
16 AB swicthes, Strucutres with 75x8 mm LS 1 5.720 5.720
GI Flat

Total Material : 184.851


11% Labour charges for Erection &
16.085
Commissioning on items 7 to 15
4% Transport charges on items 7 to 15 5.849

3% Contingencies on items 7 to 15 4.387


1% T&P charges on items 7 to 15 1.462
10% Estt. & Genl. charges on Materials 18.485
1% Cess on (M+L+T) 2.068
GST 18% on Labour portion, Transport
4.320
and CESS
Total : 237.51
Or say : 238

Note: NF = No.of 11 kv feeders. The No.of outgoing feeders at substation limited


to the demand in MVA i.e., if substation demand is 5 MVA, the No.of feeders
should not exceed five

42 SS-2x8 . Pg: 2 / 2
Cost data for erection of 33/11 kv SS with 2x5 mva Power Transformer and NF = 4 No. 11
kv feeders (with 11 kv 2 MVAR Capacitor Bank)

(Rs. in lakhs)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
As per
1a Lands and Rights LS 1 local 2.000
conditions
1b Plantation of Trees LS 1 0.198 0.198
Control Room and Consumer Service
2 LS 1 6.600 6.600
Centre (including furniture)
3 Station Auxillaries
Peripheral, Security Fencing, Approach
a) road, Retaing wall around Switchyard with LS 1 9.240 9.240
gravel filling, Gate and Bore well
b) Yard lighting LS 1 0.792 0.792
c) Fire fighting equipment LS 1 0.876 0.876
d) P&T phone and wireless set LS 1 0.660 0.660
Foundations for structures, PTRs &
4 LS 1 6.600 6.600
breakers
Bus bars, Jumpers, Connectors clamps
5 LS 1 3.300 3.300
etc.
6 Control Cables LS 1 2.640 2.640
7 Structural Steel MT 18 0.572 10.295
8 Transformers
a) PTR00006 33/11 kv 5 mva Power Transformer Each 2 36.842 73.684
b) DTC30002 11kv / 433 V 25 kva 3-ph Stn. Transformer Each 1 0.637 0.637
9 Circiut Breakres (including Trivector meters)
20 KA 11 kv feeder VCB including Control
a) BRK10002 Each 4 2.430 9.720
panel and CTs (NF=4)
20 KA 11 kv LV VCB including Control
b) BRK10004 Each 2 2.450 4.900
panel and CTs
10 Control Circiut Panels
a) AC Supply Panel Each 1 0.396 0.396
b) Alaram Panel Each 1 0.396 0.396
11 Instrumnet Transformers
a) ITR10032 11 kv PT (3-ph) Each 1 0.191 0.191
12 Lightning Arrestors
a) LAS00004 33 kv 10 KA Each 6 0.033 0.198
b) LAS00002 11 kv Station type 10 KA Each 6 0.017 0.099
c) LAS00001 11 kv Line Type (NF=4) Each 12 0.003 0.040

43 SS-2x5-CB . Pg: 1 / 2
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
13 Isolating switches
a) ABS30004 33 kv 800A AB switch (Double break) Each 3 0.363 1.090
b) ABS10015 11 kv 800A AB switch (Double break) Each 3 0.153 0.458
c) ABS10008 11 kv 400A AB switch Each 10 0.074 0.743
d) ABS10004 11 kv 200A AB switch Each 1 0.080 0.080
e) HGF30002 33 kv Horn Gap Fuse set (1xNT) Each 2 0.071 0.142
f) HGF10002 11 kv HG fuse set Each 1 0.019 0.019
2 MVAR 11 kv Capacitor Bank along with
14 CPT10009 Each 1 8.915 8.915
Associated equipment
24 V 40 AH Battery set including Battery
15 BAT00027 Each 4 0.258 1.033
charger and DC DB
Data Acquisition Euipement (SIM, Modem,
16 LS 1 0.715 0.715
Cabling etc.)
Earthing of Power Transformer VCBs, AB
17 LS 1 5.720 5.720
swicthes, Strucutres with 75x8 mm GI Flat

Total Material : 152.377


11% Labour charges for Erection &
12.513
Commissioning on items 7 to 16
4% Transport charges on items 7 to 16 4.550

3% Contingencies on items 7 to 16 3.413


1% T&P charges on items 7 to 16 1.138
10% Estt. & Genl. charges on Materials 15.238
1% Cess on (M+L+T) 1.694
GST 18% on Labour portion, Transport
3.376
and CESS
Total : 194.30
Or say : 194

Note: NF = No.of 11 kv feeders. The No.of outgoing feeders at substation limited to the
demand in MVA i.e., if substation demand is 5 MVA, the No.of feeders should not
exceed five

43 SS-2x5-CB . Pg: 2 / 2
Cost data for erection of 33/11 kv SS with 2x5 mva Power Transformer and NF = 4 No. 11
kv feeders (without 11 kv 2 MVAR Capacitor Bank)

(Rs. in lakhs)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
As per
1a Lands and Rights LS 1 local 2.000
conditions
1b Plantation of Trees LS 1 0.198 0.198
Control Room and Consumer Service
2 LS 1 6.600 6.600
Centre (including furniture)
3 Station Auxillaries
Peripheral, Security Fencing, Approach
a) road, Retaing wall around Switchyard with LS 1 9.240 9.240
gravel filling, Gate and Bore well
b) Yard lighting LS 1 0.792 0.792
c) Fire fighting equipment LS 1 0.876 0.876
d) P&T phone and wireless set LS 1 0.660 0.660
Foundations for structures, PTRs &
4 LS 1 6.600 6.600
breakers
Bus bars, Jumpers, Connectors clamps
5 LS 1 3.300 3.300
etc.
6 Control Cables LS 1 2.640 2.640
7 Structural Steel MT 18 0.572 10.295
8 Transformers
a) PTR00006 33/11 kv 5 mva Power Transformer Each 2 36.842 73.684
11 KV 25 kva 3-ph CRGO / Amourphous
b) DTC30002 Each 1 0.637 0.637
core DTR (Al) - BIS level 2
9 Circiut Breakres (including Trivector meters)
20 KA 11 kv feeder VCB including
a) BRK10002 Each 4 2.430 9.720
Control panel and CTs (NF=4)
20 KA 11 kv LV VCB including Control
b) BRK10004 Each 2 2.450 4.900
panel and CTs
10 Control Circiut Panels
a) AC Supply Panel Each 1 0.396 0.396
b) Alaram Panel Each 1 0.396 0.396
11 Instrumnet Transformers
a) ITR10032 11 kv PT (3-ph) Each 1 0.191 0.191
12 Lightning Arrestors
a) LAS00004 33 kv 10 KA Each 6 0.033 0.198
b) LAS00002 11 kv Station type 10 KA Each 6 0.017 0.099
c) LAS00001 11 kv Line Type (NF=4) Each 12 0.003 0.040

44 SS-2x5 . Pg: 1 / 2
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
13 Isolating switches
a) ABS30004 33 kv 800A AB switch (Double break) Each 3 0.363 1.090
b) ABS10015 11 kv 800A AB switch (Double break) Each 3 0.153 0.458
c) ABS10008 11 kv 400A AB switch Each 10 0.074 0.743
d) ABS10004 11 kv 200A AB switch Each 1 0.080 0.080
e) HGF30002 33 kv Horn Gap Fuse set (1xNT) Each 2 0.071 0.142
f) HGF10002 11 kv HG fuse set Each 1 0.019 0.019
24 V 40 AH Battery set including Battery
14 BAT00027 Each 4 0.258 1.033
charger and DC DB
Data Acquisition Euipement (SIM,
15 LS 1 0.715 0.715
Modem, Cabling etc.)
Earthing of Power Transformer VCBs, AB
16 LS 1 5.720 5.720
swicthes, Strucutres with 75x8 mm GI Flat

Total Material : 143.462


11% Labour charges for Erection &
11.532
Commissioning on items 7 to 15
4% Transport charges on items 7 to 15 4.193

3% Contingencies on items 7 to 15 3.145


1% T&P charges on items 7 to 15 1.048
10% Estt. & Genl. charges on Materials 14.346
1% Cess on (M+L+T) 1.592
GST 18% on Labour portion, Transport
3.117
and CESS
Total : 182.44
Or say : 182

Note: NF = No.of 11 kv feeders. The No.of outgoing feeders at substation limited to


the demand in MVA i.e., if substation demand is 5 MVA, the No.of feeders should
not exceed five

44 SS-2x5 . Pg: 2 / 2
Cost data for erection of 33/11 kv SS with 1x5 mva Power Transformer and NF = 3 No.
11 kv feeders (with 11 kv 2 MVAR Capacitor Bank)

(Rs. in lakhs)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
As per
1a Lands and Rights LS 1 local 2.000
conditions
1b Plantation of Trees LS 1 0.198 0.198
Control Room and Consumer Service
2 LS 1 6.600 6.600
Centre (including furniture)
3 Station Auxillaries
Peripheral, Security Fencing, Approach
a) road, Retaing wall around Switchyard with LS 1 9.240 9.240
gravel filling, Gate and Bore well
b) Yard lighting LS 1 0.792 0.792
c) Fire fighting equipment LS 1 0.876 0.876
d) P&T phone and wireless set LS 1 0.660 0.660
Foundations for structures, PTRs &
4 LS 1 6.600 6.600
breakers
Bus bars, Jumpers, Connectors clamps
5 LS 1 3.300 3.300
etc.
6 Control Cables LS 1 2.640 2.640
7 Structural Steel MT 18 0.572 10.295
8 Transformers
a) PTR00006 33/11 kv 5 mva Power Transformer Each 1 36.842 36.842
11kv 25 kva 3-ph CRGO / Amourphous
b) DTC30002 Each 1 0.637 0.637
core DTR (Al) - BIS level 2
9 Circiut Breakres (including Trivector meters)
20 KA 11 kv feeder VCB including Control
a) BRK10002 Each 3 2.430 7.290
panel and CTs (NF=3)
20 KA 11 kv LV VCB including Control
b) BRK10004 Each 1 2.450 2.450
panel and CTs
10 Control Circiut Panels
a) AC Supply Panel Each 1 0.396 0.396
b) Alaram Panel Each 1 0.396 0.396
11 Instrumnet Transformers
a) ITR10032 11 kv PT (3-ph) Each 1 0.191 0.191
12 Lightning Arrestors
a) LAS00004 33 kv 10 KA Each 6 0.033 0.198
b) LAS00002 11 kv Station type 10 KA Each 3 0.017 0.050
c) LAS00001 11 kv Line Type (NF=3) Each 9 0.003 0.030

45 SS-1x5-CB . Pg: 1 / 2
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
13 Isolating switches
a) ABS30004 33 kv 800A AB switch (Double break) Each 2 0.363 0.727
b) ABS10015 11 kv 800A AB switch (Double break) Each 2 0.153 0.306
c) ABS10008 11 kv 400A AB switch Each 8 0.074 0.595
d) ABS10004 11 kv 200A AB switch Each 1 0.080 0.080
e) HGF30002 33 kv Horn Gap Fuse set (1xNT) Each 1 0.071 0.071
f) HGF10002 11 kv HG fuse set Each 1 0.019 0.019
2 MVAR 11 kv Capacitor Bank along with
14 CPT10009 Each 1 8.915 8.915
Associated equipment
24 V 40 AH Battery set including Battery
15 BAT00027 Each 2 0.258 0.516
charger and DC DB
Data Acquisition Euipement (SIM, Modem,
16 LS 1 0.715 0.715
Cabling etc.)
Earthing of Power Transformer VCBs, AB
17 LS 1 5.720 5.720
swicthes, Strucutres with 75x8 mm GI Flat

Total Material : 109.343


11% Labour charges for Erection &
7.779
Commissioning on items 7 to 16
4% Transport charges on items 7 to 16 2.829

3% Contingencies on items 7 to 16 2.122


1% T&P charges on items 7 to 16 0.707
10% Estt. & Genl. charges on Materials 10.934
1% Cess on (M+L+T) 1.200
GST 18% on Labour portion, Transport
2.125
and CESS
Total : 137.04
Or say : 137

Note: NF = No.of 11 kv feeders. The No.of outgoing feeders at substation limited to


the demand in MVA i.e., if substation demand is 5 MVA, the No.of feeders
should not exceed five

45 SS-1x5-CB . Pg: 2 / 2
Cost data for erection of 33/11 kv SS with 1x5 mva Power Transformer and NF = 3 No.
11 kv feeders (without 11 kv 2 MVAR Capacitor Bank)

(Rs. in lakhs)
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
As per
1a Lands and Rights LS 1 local 2.000
conditions
1b Plantation of Trees LS 1 0.198 0.198
Control Room and Consumer Service
2 LS 1 6.600 6.600
Centre (including furniture)
3 Station Auxillaries
Peripheral, Security Fencing, Approach
a) road, Retaing wall around Switchyard with LS 1 9.240 9.240
gravel filling, Gate and Bore well
b) Yard lighting LS 1 0.792 0.792
c) Fire fighting equipment LS 1 0.876 0.876
d) P&T phone and wireless set LS 1 0.660 0.660
Foundations for structures, PTRs &
4 LS 1 6.600 6.600
breakers
Bus bars, Jumpers, Connectors clamps
5 LS 1 3.300 3.300
etc.
6 Control Cables LS 1 2.640 2.640
7 Structural Steel MT 18 0.572 10.295
8 Transformers
a) PTR00006 33/11 kv 5 mva Power Transformer Each 1 36.842 36.842
11kv 25 kva 3-ph CRGO / Amourphous
b) DTC30002 Each 1 0.637 0.637
core DTR (Al) - BIS level 2
9 Circiut Breakres (including Trivector meters)
20 KA 11 kv feeder VCB including Control
a) BRK10002 Each 3 2.430 7.290
panel and CTs (NF=3)
20 KA 11 kv LV VCB including Control
b) BRK10004 Each 1 2.450 2.450
panel and CTs
10 Control Circiut Panels
a) AC Supply Panel Each 1 0.396 0.396
b) Alaram Panel Each 1 0.396 0.396
11 Instrumnet Transformers
a) ITR10032 11 kv PT (3-ph) Each 1 0.191 0.191
12 Lightning Arrestors
a) LAS00004 33 kv 10 KA Each 6 0.033 0.198
b) LAS00002 11 kv Station type 10 KA Each 3 0.017 0.050
c) LAS00001 11 kv Line Type (NF=3) Each 9 0.003 0.030

46 SS-1x5 . Pg: 1 / 2
Material
Sl.No. Particulars Unit Qty. Rate Amount
Code
13 Isolating switches
a) ABS30004 33 kv 800A AB switch (Double break) Each 2 0.363 0.727
b) ABS10015 11 kv 800A AB switch (Double break) Each 2 0.153 0.306
c) ABS10008 11 kv 400A AB switch Each 8 0.074 0.595
d) ABS10004 11 kv 200A AB switch Each 1 0.080 0.080
e) HGF30002 33 kv Horn Gap Fuse set (1xNT) Each 1 0.071 0.071
f) HGF10002 11 kv HG fuse set Each 1 0.019 0.019
24 V 40 AH Battery set including Battery
14 BAT00027 Each 2 0.258 0.516
charger and DC DB
Data Acquisition Euipement (SIM, Modem,
15 LS 1 0.715 0.715
Cabling etc.)
Earthing of Power Transformer VCBs, AB
16 LS 1 5.720 5.720
swicthes, Strucutres with 75x8 mm GI Flat

Total Material : 100.429


11% Labour charges for Erection &
6.798
Commissioning on items 7 to 15
4% Transport charges on items 7 to 15 2.472

3% Contingencies on items 7 to 15 1.854


1% T&P charges on items 7 to 15 0.618
10% Estt. & Genl. charges on Materials 10.043
1% Cess on (M+L+T) 1.097

GST 18% on Labour portion, Transport


1.866
and CESS

Total : 125.18
Or say : 125

Note: NF = No.of 11 kv feeders. The No.of outgoing feeders at substation limited to


the demand in MVA i.e., if substation demand is 5 MVA, the No.of feeders
should not exceed five

46 SS-1x5 . Pg: 2 / 2

You might also like