Professional Documents
Culture Documents
Ocean Energy - Practical Cases-2019
Ocean Energy - Practical Cases-2019
Background
Narrow mouth of the harbour
• Incidents
• Bussiness losses
• Interior roughness
Initial solution
Detached rubble mound
breakwater
• 440m long
• 16m high
• 370m Access road
Initial solution
New challenge
Restriction
Chosen technology
New restriction:
To build this section with the resources
that had been contracted for the first
design
Functional aim
• Interior roughness
• Navigability to access
• Overtopping waves
Structural aim
• Pressure on caissons
Erection process
To build each chamber piling 16 precasted sections from the “head”
of the breakwater.
To retire the main mantle of 25t blocks and fill the gap and advance
Electro-mechanical equipment
Turbogenerators: 16 x 18’5 kW.
• Wells Turbine:
• Fixed-pitch
• Double rotor
• 5 blades per rotor
• Simetric design, harness both in and
out air flow
• Sweet water injection to clean blades
• 450V asynchronous generators.
• Air cooled
• The rotation speed of the turbine is set
depending on the pressure to get the
maximum energy.
Renewable energy sources Unit 6 Ocean Energy July, 2019 21
Mutriku OWC Plant
Extra cost of
Civil works 4,4 M€
Electromechanical equipment 1,5 M€
Others (permits, tests, …) 0,5 M€
Turbine galery
The turbines are housed in a 96m long
galery, above the air chambers.
8 mufflers to reduce the noise emission.
First mishap
During a storm in December 2011
• No damage at/in the turbine galery
• Control hut flodded:
• To repare damaged doors
• To install aditional outern doors
• To substitute damaged equipment
Possible causes
Large storms.
• Data series 1990-2005
Design wave 7.7m
Implemented solution
Two priorities:
1. Stability of the plant
2. Wave energy harnessing
Implemented solution
Implemented solution
Implemented solution
Brace beam
Implemented solution
Next challenges
• To maximise power output
• Full scale testing of new turbines
• To be a reference on OWC technology
• Touristic use of the plant
• Awareness raising
No problems
Problems Possitive
N/A Negative
TRL 4 - 5
TRL 1 - 3
Centro de Datos
Subestación propia
Videovigilancia
Cables submarinos
Boya Oleaje
Amarre
WEC
2008
Renewable energy sources Unit 6 Ocean Energy July, 2019
BiMEP Project
Existing infrastructures (year 2007)
¿Is there any gap/opportunity?
Basque Country
PORTUGAL
CHANCE
IRELAND EMEC WAVE HUB
TEST AND
SCALED FULL SCALE DEMONSTRATION COMERCIAL
LABORATORY PHASE
PROTOTYPES PROTOTYPES PHASE
Wave Hub
–Cornwall, Gales, UK
–Announced for 2008
–Infrastructure designed to host array
testing
–Sea área 10km far from coats
–4 berths, 5MW each
–4 submarine transformator 11/24
kV, 5MW
Atlas
Infrastructure Archituctural design:
conceptual design
Absorber analisis
Definition of specifications
Location analisis
Technical
specificatios
Estimated budget
Detailed design
MINIMUM Infrastructure
• Offshore
• Grid connected Captador
Amarre
Definircomponents
What qué elementos
havedebe
to incorporate?
tener
• Substation for grid connection
• Transformation stage
• Offshore - onshore
• Submarine cables
• Main connectión unit (connection hub)
• On shore
• Off shore
• Submarine
• On a offshore platform
• Others …
• Mooring area
Device
Berth
Substation
Device
Berth
Substation
Submarine
hub
Floating Hub
Substation
Device Berth
Grid connected
Device Berth
Device Berth
Oil platform
Substation
Device Berth
• Main ports
• Seabed
• Sand - rock
• Slope
• Grid connection
• Existing grid
• Submarine cable route
• Environmental impact
• Other sea users