You are on page 1of 75

Practical Cases

Wave energy project developments

Renewable energy sources Unit 6 Ocean Energy July, 2019 1


Index

On-shore Case – Mutriku OWC Plant


• Building
• Operation
Off-shore Case –BiMEP Test Site
• Design process
• Operation
• Investments

Renewable energy sources Unit 6 Ocean Energy July, 2019 2


Mutriku OWC Plant

Background
Narrow mouth of the harbour
• Incidents
• Bussiness losses
• Interior roughness

A new breakwater was


proposed to address those
problems

Renewable energy sources Unit 6 Ocean Energy July, 2019 3


Mutriku OWC Plant

Initial solution
Detached rubble mound
breakwater
• 440m long
• 16m high
• 370m Access road

Renewable energy sources Unit 6 Ocean Energy July, 2019 4


Mutriku OWC Plant

Initial solution

Renewable energy sources Unit 6 Ocean Energy July, 2019 5


Mutriku OWC Plant

New challenge

Can the new infrastructure be used to generate power?

Restriction

Respect initial purpose of breakwater

Renewable energy sources Unit 6 Ocean Energy July, 2019 6


Mutriku OWC Plant

Available energy capacity at site


Undefined dephts
• Average energy flow 26 kW/m
• Strong saesonal change: Winter 44 kW/m
Summer 9 kW/m

Off Mutriku, 30 m depht


• Average energy flow 11 kW/m
• Strong saesonal change: Winter 18 kW/m
Summer 4,4 kW/m

Renewable energy sources Unit 6 Ocean Energy July, 2019 7


Mutriku OWC Plant

Chosen technology

Renewable energy sources Unit 6 Ocean Energy July, 2019 8


Mutriku OWC Plant

Alteration required on the design


To ensure that the waves reached the
chambers, we brought the haunch forward to
the foot of the rockfill.

Renewable energy sources Unit 6 Ocean Energy July, 2019 9


Mutriku OWC Plant

Breakwater modified project

Changes for the integration


• 100m long
• To retire the main mantle of 25t blocks
• To construct a vertical seawall
• For housing 16 air columns (chambers)

New restriction:
To build this section with the resources
that had been contracted for the first
design

Renewable energy sources Unit 6 Ocean Energy July, 2019 10


Mutriku OWC Plant

Options to place the OWC plant


Left section Curved section Straight section

Renewable energy sources Unit 6 Ocean Energy July, 2019 11


Mutriku OWC Plant

Laboratory test to know


Energy aim
• Max. energy captured

Functional aim
• Interior roughness
• Navigability to access
• Overtopping waves

Structural aim
• Pressure on caissons

Renewable energy sources Unit 6 Ocean Energy July, 2019 12


Mutriku OWC Plant

First “commercial” wave project all over the world


Multiturbine configuration – also pioneer.

Renewable energy sources Unit 6 Ocean Energy July, 2019 13


Mutriku OWC Plant

Erection process
To build each chamber piling 16 precasted sections from the “head”
of the breakwater.
To retire the main mantle of 25t blocks and fill the gap and advance

Renewable energy sources Unit 6 Ocean Energy July, 2019 14


Mutriku OWC Plant

Renewable energy sources Unit 6 Ocean Energy July, 2019 15


Mutriku OWC Plant

Chamber precastted pieces


• Trapezoidal shaped pieces:
length : 12.25m
sides: 6.10m y 5.80m
edge: 0.80m
beam thickness: 0.40 – 0.50m
• 2 - 3 empty cells, for lightness of the
piece and “monolithicity” of the full
chamber
• Reinforced concrete HA-35
• Weight: 45 t.
• 4 through-pipes for lifting
Renewable energy sources Unit 6 Ocean Energy July, 2019 16
Mutriku OWC Plant

16 chamber precastted pieces


First four pieces of each column:
• For the opening of the chamber
• From level -3.40m to -0.20m

The twelve remaining parts


• For the close chamber parts
• From level -0’20m a 9’60m

Renewable energy sources Unit 6 Ocean Energy July, 2019 17


Mutriku OWC Plant

Chamber precastted pieces


• The parts were prefabricated in
an area on site
• 8 units at a time
• HA-35/P/20/IIIc+Qb with CEM
III/A 32,5 MR cement
• Formwork removed after 3 days
• Manufacture and storage during
the winter

Renewable energy sources Unit 6 Ocean Energy July, 2019 18


Mutriku OWC Plant

Positioning the pieces


• Below 0.00 level: difficulties
• Waves <0.5m
• Diving assisted positioning
• Deviation in positioning: +/- 4cm
• Fast and easy above 0.00m
• Column consolidation and joining
• Filling the front, middle and rear cells
with reinforced concrete
• Vertical joins: submerged concrete,
with PVC 400 tubes filled with
reinforced concrete as permanent
framework.

Renewable energy sources Unit 6 Ocean Energy July, 2019 19


Mutriku OWC Plant
Positioning the pieces

Renewable energy sources Unit 6 Ocean Energy July, 2019 20


Mutriku OWC Plant

Electro-mechanical equipment
Turbogenerators: 16 x 18’5 kW.
• Wells Turbine:
• Fixed-pitch
• Double rotor
• 5 blades per rotor
• Simetric design, harness both in and
out air flow
• Sweet water injection to clean blades
• 450V asynchronous generators.
• Air cooled
• The rotation speed of the turbine is set
depending on the pressure to get the
maximum energy.
Renewable energy sources Unit 6 Ocean Energy July, 2019 21
Mutriku OWC Plant

Minimising the equipment expose to salt


Small hut to house the control and transforming equipment for the
plant, so that the electronic equipment could be kept well away
from the wet saline atmosphere inside the turbine gallery

Renewable energy sources Unit 6 Ocean Energy July, 2019 22


Mutriku OWC Plant

Economic and energy figures


Installed capacity 296kW
Annual output 300.000kWh

Extra cost of
Civil works 4,4 M€
Electromechanical equipment 1,5 M€
Others (permits, tests, …) 0,5 M€

Economic backing from the European


Commission's FP6

Renewable energy sources Unit 6 Ocean Energy July, 2019


Mutriku OWC Plant

Turbine galery
The turbines are housed in a 96m long
galery, above the air chambers.
8 mufflers to reduce the noise emission.

Renewable energy sources Unit 6 Ocean Energy July, 2019 24


Mutriku OWC Plant

Mutriku wave power plant once finished

Renewable energy sources Unit 6 Ocean Energy July, 2019 25


Mutriku OWC Plant

First mishap
During a storm in December 2011
• No damage at/in the turbine galery
• Control hut flodded:
• To repare damaged doors
• To install aditional outern doors
• To substitute damaged equipment

Renewable energy sources Unit 6 Ocean Energy July, 2019 26


Mutriku OWC Plant

First year of operation

Start-up and adjustments to the plant


Energía Energía
Año Mes importada exportada
(kWh) (kWh)
2011 Jun 2.447 3.888 Plant becomes operational
2011 Jul 2.864 5.919
2011 Ago 2.810 3.994
2011 Sep 2.994 20.808
2011 Oct 1.366,00 32.261,50
2011 Nov 599,00 35.105,45 Storm damage.
2011 Dic 652,00 33.846,77
2012 Ene 133,00 0,00 Repairs.
2012 Feb 1.708,00 0,00
2012 Mar 1.579,00 20.272,44
2012 Abr 595,00 33.053,17
2012 May 3.954,00 9.013,60 Plant becomes operational again
21.701,00 198.161,93

Problems arise: lower power generation


and greater consumption levels

Renewable energy sources Unit 6 Ocean Energy July, 2019


Mutriku OWC Plant
First year of operation
Production figures in May fell
dramatically
¿Fairer weather conditions?
Further investigation revealed:
• repeated turbine shutdown
• difficulties in starting it up again
Cause: Breakage of the rubber
components of the damper drive
motor.
Explanatión:
After long time stored (almost 3 year) waiting to be installed, the
condition of the rubber components had deteriorated.
Renewable energy sources Unit 6 Ocean Energy July, 2019 28
Mutriku OWC Plant

Flaw in the breakwater


Structural failures appeared
after winter 2009.
Faults appeared in the air
chambers in the wave plant.
Four chambers were affected

One of them was completely


missing its outer wall.
The turbine gallery, which
runs above the chambers, is
still intact.

Renewable energy sources Unit 6 Ocean Energy July, 2019 29


Mutriku OWC Plant

Possible causes
Large storms.
• Data series 1990-2005
Design wave 7.7m

• Data series 1990-2009


Design wave 9.2m

Renewable energy sources Unit 6 Ocean Energy July, 2019 30


Mutriku OWC Plant

Possible causes (2)


Non monolithic design
• First design with no OWC plant
• Modified after tendering and contracting
• Plant design restriction :
• Had to be executed with the contracted
means and methods

Renewable energy sources Unit 6 Ocean Energy July, 2019


Mutriku OWC Plant

Possible causes (3)


Unexpected stress suffered during execution:
• Torsion at lifting and transporting
• Knocking at the positioning
… may have caused small fissures

Renewable energy sources Unit 6 Ocean Energy July, 2019


Mutriku OWC Plant

Implemented solution
Two priorities:
1. Stability of the plant
2. Wave energy harnessing

To build a new haunch attached to


the existing one
• Up to +10m
• 5 metres in width
• Keeping the chamber entrances
• As monolithic as possible

Renewable energy sources Unit 6 Ocean Energy July, 2019


Mutriku OWC Plant

Implemented solution

Gantry pieces positioning.

1. Clearing and dredging


2. Anchoring to the seabed
3. Levelling
4. Gantry piece positioning

Renewable energy sources Unit 6 Ocean Energy July, 2019 34


Mutriku OWC Plant

Implemented solution

Construction of new haunch.

1. Positioning the blocks and anchors


2. Concreting
3. Second block row positioning
4. Frame and anchors positioning

Lay up five rows of block to the


level +8.5m

Renewable energy sources Unit 6 Ocean Energy July, 2019 35


Mutriku OWC Plant

Implemented solution

Brace beam

• Along the whole front.

• From level +8.5m to +10m

• Incorporates wave buffer

Renewable energy sources Unit 6 Ocean Energy July, 2019 36


bootstrap

Mutriku OWC Plant

Implemented solution

Renewable energy sources Unit 6 Ocean Energy July, 2019


Mutriku OWC Plant

First 5 year operation balance


More than 1,000,000kWh
exported to grid
Usually 12 turbine generating
Next target:
reach 300,000kWh/year
Unmanned plant
After 5 year, an overall review
has been needed, and many
components have been
changed

Renewable energy sources Unit 6 Ocean Energy July, 2019


Mutriku OWC Plant

First 5 year operation balance


Maintenance issues
• Generator bearing
• Rotor blades corrosion and damages
• Emergency stop buttons
The part of the power plant that suffers the
most is the civil works

Renewable energy sources Unit 6 Ocean Energy July, 2019


Mutriku OWC Plant

Next challenges
• To maximise power output
• Full scale testing of new turbines
• To be a reference on OWC technology
• Touristic use of the plant
• Awareness raising

No problems
Problems Possitive

N/A Negative

Renewable energy sources Unit 6 Ocean Energy July, 2019


Mutriku OWC Plant

Mutriku as a test site


• Testing of a new turbine within the framework of th OPERA Project (H2020)

This project has received funding from the European


Union’s Horizon 2020 research and innovation
programme under grant agreement No 654444

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Wave energy technology development challenges


• Scientific/Technologic
• Physics of wave movement
• Change from mechanical energy to electricity
• Harsh environment
• Corrosion
• Extreme loads
• Economic
• High investment and O&M costs
• Uncertain pay-back
• Reaching the market in the long term, if so.
• Legal/Administrative
• Inexistent or not suited for purpose legal framework
• Need to demonstrate lack of environmental impact before any real
experience.
• Higher environmental requirement level than other fossil technologies

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Technology development road


• Set stages to reduce risk
• Each stage requires increase the inversment
by one magnitude order
TRL 9
• At each stage some decisions are take and
parameters are fixed, discarding
technological alternatives
TRL 6 - 8

TRL 4 - 5

TRL 1 - 3

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project
Existing infrastructures (year 2007)
EMEC (Orkney, UK)
Marine Institute (Galway, Irlanda)
Conexión a Red

Centro de Datos

Subestación propia

Videovigilancia

Cables submarinos

Boya Oleaje

Amarre

WEC

PILOT Zone (Portugal)


WAVE HUB (Cornwall, UK)

2008
Renewable energy sources Unit 6 Ocean Energy July, 2019
BiMEP Project
Existing infrastructures (year 2007)
¿Is there any gap/opportunity?

Basque Country

PORTUGAL
CHANCE
IRELAND EMEC WAVE HUB

TEST AND
SCALED FULL SCALE DEMONSTRATION COMERCIAL
LABORATORY PHASE
PROTOTYPES PROTOTYPES PHASE

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

To take in to account to design a test site


Ubicación
Site Elementos
Components
• Energy resource • Substation to connect to the grid
• Distance to coast • Transformation stage
• Distance to main ports • Offshore - onshore
• Seabed • Submarine cable
• Sand - rock
• Slope • Main connection unit
• On shore
• Grid connection possibility on
land • Submarine
• Existing grid • On existing offshore platform
• Submarine cable route to shore • Others…
• Environmental impact • Berth
• Other users of sea
Renewable energy sources Unit 6 Ocean Energy July, 2019
BiMEP Project
Existing infrastructures (year 2007)
EMEC: European Marine Energy Centre
–Orkney Islands, Scotland, UK
–Up and running since 2003
–Infrastructure to host testing on:
•Wave energy absorbers
•Current energy absorbers
–Subestation 11kV
–Grid connected berths
–Integral SCADA
–Fibre optic data transmission to allow
remote access
–Environmental, wave and current data base

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project
Existing infrastructures (year 2007)

Wave Hub
–Cornwall, Gales, UK
–Announced for 2008
–Infrastructure designed to host array
testing
–Sea área 10km far from coats
–4 berths, 5MW each
–4 submarine transformator 11/24
kV, 5MW

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Phases to develop the infrastructure (2007)


Fase 1 Fase 2 Fase 3
Analisis
Other projects:
Wab Hub
EMEC
Portugal State of the art
Oregón (USA) and commun
knowledge
Irlanda report Conceptual design:
Generation and selection of
alternatives
Location selection

Atlas
Infrastructure Archituctural design:
conceptual design
Absorber analisis
Definition of specifications
Location analisis

Technical
specificatios
Estimated budget

Detailed design

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Infrastructure scope definition

MINIMUM Infrastructure
• Offshore
• Grid connected Captador
Amarre

• Berths for full scale WECs


• Individual berths for only one
device
Subestación
• Infrastructure for testing and
demonstration, not commercial
phase

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Infrastructure scope definition


GENERACIÓN
MEDIUM Infrastructure
• Offshore
• Grid connected
• Berths for full scale WECs
• Individual berths for only one
device
ENSAYO
• Berths for arrays
• Infrastructure for testing,
demonstration and commercial Subestación
phase
• ¿Two work areas or only one?

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Infrastructure scope definition


GENERACIÓN
MAXIMUM Infrastructure
• Offshore
• Grid connected
• Berths for full scale WECs
• Individual and array berths Subestación
ENSAYO
• Infrastructure for testing,
demonstration and commercial
phase
• Three-four work areas
• ¼ scale testing ESCALA
• Full scale WEC testing
• Commercial explotation
• Environmental impact studies
FONDEOS
• Mooring …

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Definition of infrastructure architecture

Definircomponents
What qué elementos
havedebe
to incorporate?
tener
• Substation for grid connection
• Transformation stage
• Offshore - onshore
• Submarine cables
• Main connectión unit (connection hub)
• On shore
• Off shore
• Submarine
• On a offshore platform
• Others …
• Mooring area

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Definition of infrastructure architecture


1. Main connection unit on onshore substation

Device
Berth

Substation

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Definition of infrastructure architecture


2. Submarine main connection unit

Device

Berth

Substation

Submarine
hub

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Definition of infrastructure architecture


3. Floating main conexión unit

Floating Hub
Substation
Device Berth

Grid connected

Device Berth

Non grid connected

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Definition of infrastructure architecture


4. Main connection unit on offshore infrastructure

Seabed fixed Hub


Substation

Device Berth

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Definition of infrastructure architecture


4. Main connection unit on offshore infrastructure v2.0

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Definition of infrastructure architecture


5. Main connection unit taking advantage of existing infrastructures

Oil platform

Substation

Device Berth

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

To take in to account to design a test site


Location
Location
• Energy resource
• Distance to coast
• Distance to main ports
• Seabed
• Sand - rock
• Slope
• Grid connection possibility on
land
• Existing grid
• Submarine cable route to shore
• Environmental impact
• Other users of sea
Renewable energy sources Unit 6 Ocean Energy July, 2019
BiMEP Project

Possible locations: Close to Bilbao Port


Location
• Energy resource
• Distance to coast
• Main ports
• Seabed
• Sand - rock
• Slope
• Grid connection
• Existing grid
• Submarine cable route
• Environmental impact
• Other sea users

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Possible locations: Donostia-Pasaia Port


Location
• Energy resource
• Distance to coast
• Main ports
• Seabed
• Sand - rock
• Slope
• Grid connection
• Existing grid
• Submarine cable route
• Environmental impact
• Other sea users

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Possible locations: Igeldo-Donostia detail


Location
• Energy resource
3
• Distance to coast 1 2

• Main ports
• Seabed
• Sand - rock
• Slope
• Grid connection
• Existing grid
• Submarine cable route
• Environmental impact
• Other sea users

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Possible locations: Gorliz-Lemoiz-Bakio


Location
• Energy resource
• Distance to coast
• Main ports
• Seabed
• Sand - rock
• Slope
• Grid connection
• Existing grid
• Submarine cable route
• Environmental impact
• Other sea users

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP BiMEP

Possible locations: Gorliz-Lemoiz-Bakio detail


Location
• Energy resource
• Distance to coast
• Main ports
• Seabed
• Sand - rock
• Slope
• Grid connection
• Existing grid
• Submarine cable route
• Environmental impact
• Other sea users

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Final location proposal: Armintza - Lemoiz


Location
• Energy resource
• Distance to coast
• Main ports
• Seabed
• Sand - rock
• Slope
• Grid connection
• Existing grid
• Submarine cable route
• Environmental impact
• Other sea users

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Dealing on final location: Armintza - Lemoiz


Location
• Energy resource
• Distance to coast
• Main ports
• Seabed
• Sand - rock
• Slope
• Grid connection
• Existing grid
• Submarine cable route
• Environmental impact
• Other sea users

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Final location and shape: Armintza - Lemoiz


Location
• Energy resource
• Distance to coast
• Main ports
• Seabed
• Sand - rock
• Slope
• Grid connection
• Existing grid
• Submarine cable route
• Environmental impact
• Other sea users

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Final location and characteristics: Armintza - Lemoiz


Location
• 4 cable, 20 MW, grid connected
• Energy resource • Environmental monitoring
• Distance to coast • Depths from 50 to 90m
• Surveillance and
• Main ports emergency respons 24/7
• Seabed • Fast access
• Sand - rock • Suitable wave climate
• Slope
• Grid connection
• Existing grid
• Submarine cable route
• Environmental impact
• Other sea users

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

BiMEP Project presentation

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

BiMEP Project – Explanation

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Operating at BiMEP – OPERA Project (H2020)

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Investment to build the infraestructura

Power lines 13.2 kV 12 M€


• Submarine cables 3 M€
• Submarine cable installation 4 M€
• Horizontal drilling 2 M€
• Submarine conectors 1 M€
• Others 2 M€
Onshore substation 2’7 M€
Marking of the sea area 0’5 M€
Site engineering services 0’6 M€
Preliminary studies and works 2 M€

Renewable energy sources Unit 6 Ocean Energy July, 2019


BiMEP Project

Biscay Marine Energy Platform www.bimep.com


Dorleta Marina dmarina@bimep.com

Renewable energy sources Unit 6 Ocean Energy July, 2019

You might also like