Professional Documents
Culture Documents
Technical Guide - Headworks Design - JICA
Technical Guide - Headworks Design - JICA
May, 2014
Herewith this massage, I emphasize that from Now on, OIDA to make efforts
to utilize all outputs of the project for all irrigation activities as a minimum
standard, especially for the enhancement of irrigation technical capacity.
I believe that all OIDA irrigation experts work very hard with their respective
disciplines using CBID outputs to improve the life standard of all people. In
addition, I encourage that all other Ethiopian regions to benefit from the
outputs.
i
(2) Loading Test ..................................................................... 26
2.3.4 Investigation on Riverbed Deposit ........................................ 26
2.3.5 Groundwater Investigation .................................................. 26
2.4 Assessment & Planning for Construction Works .......................... 27
2.4.1 Meteorology, Surface Water, Groundwater
and Riverbed Conditions ................... 27
2.4.2 Construction Equipment and Materials ............................... 28
2.4.3 Transportation of Equipment and Materials ......................... 28
2.4.4 Power Source for Construction ............................................ 28
2.4.5 Availability of Enough Labor for Construction ...................... 29
2.5 Topographical Survey .................................................................. 29
2.5.1 Topographic Survey ............................................................. 29
2.5.2 Longitudinal and Cross-Section Survey ............................... 30
2.5.3 Surveys for Other Temporary Works and Compensations..... 30
2.5.4 Collection of Topographic and Other Related Maps .............. 31
2.6 Data for Temporary Works .......................................................... 31
2.6.1 Annual Maximum Daily Rainfall and
Annual Maximum Hourly Rainfall ................ 31
2.6.2 Annual Daily Rainfall .......................................................... 32
2.6.3 Environmental Impact Assessment .................................... 32
ii
3.1.2 Position of Headworks ......................................................... 46
(1) Points of selecting Headworks position ............................. 46
(2) Process of selecting Headworks position ........................... 47
3.1.3 Method, Location and Type of Water Intake ......................... 48
(1) Method of water intake ..................................................... 48
(2) Location of intake ............................................................. 49
(3) Type of weir and direction of weir axis .............................. 50
3.1.4 Design Dimensions .............................................................. 54
(1) Design water intake level .................................................. 54
(2) Elevation of crest height of weir ........................................ 55
(3) Ensuring creep length ...................................................... 56
(4) Study of possible effect on the river control of upstream ... 61
3.2 Detail Design ............................................................................. 65
3.2.1 Movable Weir ....................................................................... 65
(1) Sill elevation of movable weir ............................................ 65
(2) Spillway by movable weir .................................................. 66
(3) Scouring sluice ................................................................. 68
(4) Pier .................................................................................. 81
3.2.2 Fixed Weir ........................................................................... 91
(1) Section shape ................................................................... 91
(2) Type of fixed weir .............................................................. 92
(3) External forces ................................................................. 92
(4) Determination of section (Stability analysis)...................... 97
(5) Correction of trapezoidal section ....................................... 98
(6) Apron ............................................................................... 100
3.2.3 Riprap ............................................................................... 101
(1) Basic concept for engineering of riprap work ..................... 101
(2) Conditions required for riprap .......................................... 102
(3) The shape of riprap .......................................................... 102
(4) The length of riprap of upstream side ............................... 103
iii
(5) The length of riprap A of downstream side ........................ 103
(6) Riprap B of downstream side ............................................ 107
(7) Use of Bligh's formula (Reference) ..................................... 107
(8) Structural engineering of riprap........................................ 108
3.2.4 Foundation Work ................................................................ 110
(1) Functions of foundation work ........................................... 110
(2) Types of foundation work ................................................. 110
3.2.5 Upstream and Downstream Cut-off Walls ........................... 119
(1) Upstream cut-off wall ....................................................... 119
(2) Downstream cut-off wall ................................................... 122
3.2.6 Inlet .................................................................................... 123
(1) Function of Inlet ............................................................... 123
(2) Location of inlet ................................................................ 124
(3) Features of Inlet Design .................................................... 124
(4) Flow Discharge at Inlet ..................................................... 126
(5) Water Level Calculation for Inlet ....................................... 128
3.2.7 Gate .................................................................................... 141
(1) Selection of type of gate .................................................... 141
(2) Lifting Height.................................................................... 149
(3) Material ............................................................................ 149
(4) Dimension of gate for Slide gate and Stop-log ................... 150
3.2.8 Related Structures .............................................................. 151
(1) Settling Basin ................................................................... 151
(2) Protection of bank and major bed ..................................... 165
3.2.9 Control Facilities ................................................................. 168
(1) Operation equipment ........................................................ 168
(2) Power receiving and distributing facilities ......................... 168
(3) Operation and maintenance bridge ................................... 168
(4) Other operation facilities .................................................. 170
(5) Operation ......................................................................... 170
iv
4. DATA SHEET, CHECK LIST AND OTHERS ....................................... 175
4.1 Data Sheet .................................................................................. 175
4.2 Check List................................................................................... 178
4.3 Coefficients of Roughness............................................................ 184
v
5.2.5 Elevation of Crest Height and Length of Weir ....................... 203
5.2.6 Possible Effect on the River Control of Upstream.................. 203
(1) Water depth of the river where the place of headworks
before construction as design flood discharge
(Tail water depth) ............................................................. 203
(2) Water depth on the crest as design flood discharge ........... 203
5.3 Detail Design .............................................................................. 206
5.3.1 Fixed Weir ........................................................................... 206
(1) Section shape ................................................................... 206
(2) Determination of section (Stability analysis)...................... 206
(3) Apron ............................................................................... 215
5.3.2 Riprap ................................................................................. 219
(1) Calculation of water depth at the weir toe
as design flood discharge ................................................. 219
(2) Calculation of water depth at the beginning point of
hydraulic jump ................................................................ 221
(3) Comparison with h1a and h1b ............................................ 221
(4) Calculation of supercritical flow length ............................. 221
(5) The length of hydraulic jump ............................................ 221
(6) Necessary Length of riprap A ............................................ 221
(7) Length of riprap B ............................................................ 221
(8) Length of upstream riprap ................................................ 221
5.3.3 Foundation Work ................................................................ 222
5.3.4 Upstream and Downstream Cut-off Walls ............................ 222
5.3.5 Inlet .................................................................................... 222
5.3.6 Gate .................................................................................... 222
5.3.7 Settling Basin ...................................................................... 223
(1) Width and depth of sedimentation ditch ........................... 223
(2) Length of sedimentation ditch .......................................... 224
5.3.8 Protection of Bank and Major Bed ....................................... 224
vi
5.3.9 Scouring Sluice ................................................................... 224
(1) Diameter of riverbed materials .......................................... 225
(2) Design of scouring sluice intake ....................................... 225
(3) Engineering of upstream portion of scouring sluice ........... 225
(4) Cannel width of scouring sluice ........................................ 226
(5) Design of upstream slope of cannel ................................... 227
(6) Design of downstream cannel ........................................... 231
5.4 How to use “Goal seek” ............................................................... 232
vii
Technical Guideline for Design of Headworks
1. GENERAL DESCRIPTION
1.1 Introduction
Irrigation development, irrespective of scale i.e. small, medium or
large, needs detail study and design. The study and design needs to
be conductuted rigorously with minimum standard quality. Unless it
results loss of money, wrong construction that inturn can result
negative environmental impact (water loss, salinity, gully,
conflict,etc.) and in general unsustainable development.
The study and design phase plays decisive role in irrigation
development. To enhance the quality of the study and design of
irrigation projects, it is necessasry to attain minimum quality
standard. For this reasson, it become necessary to prepare standard
terms of refrence, guidelines and manuals.
1.2 Definitions
In this guideline the following words and phrases are defined as
follows:
[Reference]
In the Multilingual Technical Dictionary of Irrigation and Drainage
issued by the International Commission on Irrigation and Drainage
(ICID), headworks is defined as "A collective term for all works
(weirs- or diversion dams, head regulators, upstream and
downstream river training works and their related structures)
required at intakes of main or principal canals to divert and control
river flows and to regulate water supplies into the main canal (s). "
1 . 3 A i m o f t h e Gu i d e l i n e
The aim of this guideline is to show the basic and important way of
design concepts and approaches of headworks for small and medium
1
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1 . 4 S c o p e o f t h e Gu i d e l i n e
This guideline discusses the general procedures to be considered in
the design and construction of small and medium scale irrigation
diversion headworks. In Ethiopian, irrigation schemes are classified
in to three types based on the area. Small scale irrigation scheme is
less than 200ha,medium scale irrigation scheme is 200-3,000 ha
and large scale irrigation scheme is greater than 3000ha (In Oromia
0-2.5 ha micro irrigation, 2.5-200ha small and the rest has the same
classification with country level).
The guideline takes into account all internal and external forces
acting on a weir, how they affect weir and make sure the structure
functions normal throughout its life time the purpose intended to
serve by providing appropriate dimension to all elements.
2
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
3
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Devide wall
Wi n g w a l l (Guide wall)
Scouring River
Canal Settling sluice gate Protection
basin (Gabion)
Inlet/
Intake
Riprap (U/S)
Weir
Wi n g w a l l Apron (U/S)
Inlet /
Scouring Intake
Settling sluice gate
basin
Apron
Devide wall (U/S)
(Guide wall)
Riprap
Wi n g (U/S)
wall Riprap (D/S)
Apron
(D/S)
We i r
4
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Cross section
Wi n g Intake
wall Scouring gate
sluice gate
We i r
Wi n g
wall
Settling
basin Devide wall
(Guide wall)
Apron
(D/S)
5
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Longitudinal section
Apron
Apron
Weir (U/S)
(U/S)
Riprap
Riprap
(U/S)
(U/S)
Cut-off wall
Scouring
sluice gate Apron
Apron Weir (U/S)
(U/S)
Devide Riprap
Riprap Wall (U/S)
(U/S)
Cut-off wall
6
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
7
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
8
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Design of headworks needs input data that have good quality in different
stages of the study. The design of headworks has to identify kinds of data,
availability of data, quality of data in each stage. Headwork design not
only identifies input data but also assesses impacts that have to be tested
like effects of flood, upstream and downstream effects and others issues.
In this section basic design input data and the reasons for the
requirement of these data are briefly explained. This section helps the
engineer to understand what they are designing, what to observe
including impacts and other issues.
The necessary basic primary and secondary data have to be identified and
then to be collected. The collected data have to be examined. Planning is
the primary work in designing i.e. what data to collect, how to collect,
when to collect and where to collect. Data collection and examination has
to be considered not only for design and construction phase but also for
operation and maintenance aspects after construction. This is very
helpful in securing the headworks to function properly, to economize the
project during planning, design, construction and operation stages.
Keeping this in mind, it is important to carry out efficient & effective
planning considering the relationship between the basic design input data
& design, construction and O & M.
When basic design input data is not possible to be accessed with the
same method as explained in guideline, it is necessary to get the
information and data in another method. It is not recommendable to
design without ungrounded information and data.
9
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
10
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
kebele experts.
This data has to be supported by rainfall - run-off analysis (when there is
rainfall data of the area is available). Please refer to “Manual for Runoff
Analysis” in detail.
11
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Table 2.1 Interval of measuring points for water depth and water velocity
Interval of measuring Interval of measuring
Width of water surface
points for water depth Points for water velocity
(B)m
(M)m (N)m
10~15% width of water
Less than 10 N=M
Surface
10~20 1m 2m
20~40 2 4
40~60 3 6
60~80 4 8
80~100 5 10
100~150 6 12
150~200 10 20
More than 200 15 30
12
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
① The float measurement method is used when the current meter method
cannot be used,
② The transversal line is set more than two, and the interval is not less
than 50m basically. But the case of small and medium river, the
interval can be changed to not less than 10m,
③ There is the planning point between the transversal line of upstream
and the transversal line of downstream,
④ The measuring line of velocity of float is set in the direction of the flow
of the river from the transversal line of upstream,
⑤ The relation between width of surface water of river and the number of
measuring line of velocity of float is expressed in Table 2.4,
⑥ The point which the float starts is about 30 m upper from the
transversal line of upstream basically. But the case of small and
medium river, it can be changed for small rivers 5-10m, for medium
rivers 10-20m,
⑦ The mean flow velocity at the planning point is calculated by
multiplying velocity coefficient (Refer to Table 2.3) and average flow
velocity calculated based on the results of measurement in each
measuring line of velocity of float with time record.
Measuring line of
velocity of float
Start line
Transversal
Approaching line of
section about 5 ‐ upstream Planning
30m
Transversal
Measurement line of
section downstream
not less than 10‐50m
13
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Fig. 2.3 Float type and stick type for float method
Table 2.2 Selection criteria of float number and submerged depth of flow
Submerged
Water depth Number depth of float
~0.7m ①
0.7m~1.3m ② 0.5m
1.3m~2.6m ③ 1.0m
2.6m~5.2m ④ 2.0m
5.2m~ ⑤ 4.0m
Float Stick type
14
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Table 2.4 Width of river and number of measuring line of velocity of float
100m~
Width of river ~20m 20m~100m 200m~
200m
Number of
measuring line of 5 10 15 20
velocity of float
Q=A·V
1 23 12
V R I
n
15
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
16
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
17
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
EL(m)
EL3
EL2
EL1
(A2) H3
H1 (A1) H2
(A0)
EL0
L0 L1 L2 L(m)
No.0 No.1 No.2 No.3
18
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
19
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
The scale and dimensions of the structure of foot protection, span, etc. of
dikes, bridges and other structures should be investigated to clarify the
influence of flood.
20
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Winch
ウイ ンチ
メタルクラウ
Metal crownン
only at the centerline of the diversion 又はダイヤビツ ト
or Diamond bit
GT-04
weir, but also at the apron Fig. 2.6 Drilling image
21
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
22
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Sand Clay
N value Consistency N value Consistency
0~4 Very loose 0~2 Very soft
4~10 Loose 2~4 soft
10~30 Medium 4~8 Medium
30~50 Dense 8~15 stiff
More than 50 Very dense 15~30 Very stiff
More than 30 Hard
23
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
If the length of the drilling rod is long, this may influence the results of
the standard penetration test. Correction of the measured N-value shall
be made by the following formula:
N’= N (l≦20m)
N’= (1.06 – 0.003l)N (l>20m) ……………………………………(F. 2.3)
24
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
25
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
26
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
27
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
28
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
29
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
During the cross-section surveys, the flood mark of both side of the river
around headworks should be indicated and incorporated for hydraulic
calculations. This can be done based on elderly flood mark and some
safety factor. The extent of this surveying along the river courses at least
has to be 500m to each side of upstream and downstream of the site of
headworks but effects shall be seen to decide the effect of flood.
30
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
31
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
32
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
3. DESIGN OF HEADWORKS
33
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
D = D s ×A p / A r
34
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
W = D × K Qdw
W : The amount of usable water (m 3 /s),
D : Base flow (m 3 /s),
K : Coefficient of released flow for downstream ecology (0.7~0.9),
Q d w : The existing design water intake discharge in the downstream of the
project (downstream demanded water). In case of using actual
measurement data, it should be subtracted from base flow.
35
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
36
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
37
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
H e = H d +H a v
H a v = V a 2 /2g
V a = Q d / L (h+H d )
H e = H d +(Q d ) 2 /[L(h+H d )] 2 /(2g),
Design flood level at weir = H d + Elevation of weir crest
Where H e : Total energy head (m)
H d :Design head (Water depth on the crest) (m)
H a v : Approach velocity head (m)
V a : Approach velocity (m/s)
Q d : Design flood discharge (m 3 /s)
C : 1.7 Discharge coefficient
L : Length of weir (m)
h: weir height (m)
g: 9.8m/s 2 gravity acceleration
38
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
H a v =V a 2 /2g
Qmax He Hd
Sediment
h
Weir
dh Q 2 d 1 n 2V 2
i 0
dx 2 g dx A2 R 4 3
Q: Discharge (m 3 / s)
A: Cross-section area (m 2 )
39
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1) Summary
It is extremely important to predict the future stable riverbed to
decide the height of the water intake sill.
① First, it is necessary to investigate the existing condition
whether there is balanced retrogression or aggrandization,
② Second, it is necessary to assess the variation of the bed that
would occur when other structures are constructed upstream or
downstream or when river improvement is carried out.
Agro‐ecology or characteristic
Rainfall of the source of a river
Collapsed sediment
Discharge amount
Channel erosion Sediment amount
Riverbed formation
downstream
Fig. 3.3 Flow chart of riverbed formation downstream
The flow chart in Fig. 3.3 describes the conditions ② and ③ above.
Usually local characteristics such as those of rainfall distribution
and collapse of sediment amount are extremely indefinite. But the
effect of the occurrence probability of these phenomena is rather
40
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
41
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
42
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
43
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
large-diameter grain
by of tractive sediment volume
location by particle size, Continuous
equation of riverbed and
grain size
Fluctuation of riverbed Basic equation of
assuming that non-uniform flow, equation
constant-diameter of grains of tractive sediment volume
(IV)
predominate in a section of by a particle size and
the river Continuous equation of
riverbed.
44
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Table 3.2
Key points Remarks
① To avoid the curve portion of Flow of river is not
river where curvature radius is uniform, and the thalweg
small, fluctuates from left to right
Selection ② To select the point near swingingly. Due to the
or effect of secondary flows
thalweg (lowest part of valley),
sampling and locational difference of
point ③ To avoid sandy gravel dunes tractive force, significant
and the place where scouring change of particle size in
happens cross section occurs. It is
required to avoid it.
① To avoid collection of cobbles Distribution condition of
the site, which is outside the large-sized cobbles, which
grain size distribution of the greatly affects the grain
riverbed surface, size distribution, is
To record particle size and important data. Sampling
distribution condition of these from two portions, i.e., the
stones. riverbed surface and
② To collect only the riverbed subsurface layer and
analysis is of these two
surface portion after excluding
portions are especially
cobbles. Surface layer thickness
important in case of
is that for the maximum grain
size (90 percent diameter by considering selective
traction and estimation of
weight). Average space is to be
stable riverbed.
1.0 × 1.0m.
The sample taken is to be divided
Sampling by quartering method and
method enough volume of sample to yield
a representative value must be
used, If grain size is small, 35 kg
is the sample.
However, if grain size is larger,
larger sample must be taken
relative to the grain size.
③ To collect sub-layer part of
riverbed. Two sampling points
are required at 1. 0m and 2.0m
deep from surface of riverbed.
Plan dimension of sampling is
1.0m × 1.0m and thickness of
sampling at each point is to be
the nearly same as maximum
grain size.
45
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
46
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
47
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
48
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
49
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1) Stability Factor
(a) Gravity Weir: The weir depends on its weight for countering uplift
pressure due to seepage. The weight of the weir body and/or floor is
higher than the uplift pressure due to head of seepage water
(subsurface flow) under weir. It is used on permeable soil.
(b)Non Gravity Weir: This type of weirs constructed on the piles (cut
offs) and other pressure defusing mechanisms for it's stability
against uplift force from the subsurface flow. It needs careful design
50
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(b) Gabion weir: Gabion boxes filled with rocks. It is economical and
easy in construction where rock is available in required amount at or
nearby site. It is widely used for river training diversion, storage etc.
(c) Masonry weirs: Ti1e weir wall and the solid apron constructed
from masonry wall embedded in cement mortar. It is easy in
construction to provided the material and the skilled (mason)
available at site.
51
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
4) Function factor
(a) Storage: Construction for storage purpose. It is termed as low
dam.
(b) Waste Water: Spilling flood excess of pond capacity and is
constructed to safeguard the main weir.
(c) Pickup: Constructed across the river downstream of storage to
raise the level of water released from the storage and divert it for
utilization.
(d) Diversion: Part of a headworks to raise water level in the river and
divert supplies in to the off taking canal.
52
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(b) Broad Crested: Thick walled over flow weir, constructed mostly
on pervious foundation. (Rectangular, Trapezoidal)
(c) Ogee Crested: The top and bottom downstream part of weir having
a smooth curve is mostly constructed on a rocky foundation.
Special case
According to condition of
foundation and landform,
the most economically
axis should be selected.
53
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
54
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
55
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
① Bligh's method
L ≧ C・ΔH ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・(F. 3.1)
Where L : length of creep length measured along the foundation
face of the weir (which may differ from the actual
56
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
② Lane's method
Lane defined the effect of the horizontal creep length as 1/3 of the
vertical creep length. He has established the weighted creep
length by dividing the total of the vertical and horizontal creep
length by the difference between water heads and defined the
ratio as shown in Table 3.3.
L' ≧ C' ・ ΔH ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・(F.3.2)
Where L' : length of weighted creep Length (m),
L' = Σ v +1/3 Σh
v : creep length of vertical direction (inclination of more than 45
degrees)
h : creep length of horizontal direction (inclination below 45
degrees)
C’ : Coefficient which varies by the type of ground (Table 3.3)
ΔH : maximum difference between water heads (m)
ΔH adopts a value of big one among H 1 and H 2 .
57
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
58
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
59
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
provided in the wall to reduce the uplift pressure.. These wall and
sheet piles are not included in the creep length. Normally, the
upstream apron is not included in the creep length. However, where
the apron has to be included in the creep length caused by trouble in
driving sheet piles, etc., water stops must be inserted in
construction joint. In addition to this, dowel bars or key have to be
made to withstand uneven settlement. Water stops and similar
mechanism are necessary for construction joints or some other
joints in the downstream apron. The difference in head ΔH is usually
adopts a value of big one among H 1 and H 2 , but consideration should
be given to having some safety margin on rivers where retrogression
is anticipated if possible. The abutment foundations of a weir with
banks or embankments will usually be permeable. Therefore, a safe
creep length must be ensured by way of cut-off walls on the extended
line of the weir axis and on the retaining wall or at the foot of the
upstream retaining wall. In this case, it is necessary to study the
percolation path three-dimensionally. Installation of a cut-off wall in
the direction of the weir axis is to ensure a safe creep length along
the route of A - B - C shown in Fig. 3.14. The foot of the cut-off wall
must be at the same level as that of the cut-off wall installed beneath
the weir body with its top being at the same level as the crest height
of the gate.
On the intake side, the intake structure can form a part of the wall.
If the construction of a wall between A - B is not practical due to the
existence of the embankment, etc., then a cut-off wall between A and
A' is required to ensure the required creep length from A' to C. It is
not recommended to make weep holes below the seepage line of the
downstream side retaining wall within the range of the required
creep length. When the upstream side retaining wall is used for the
cut-off wall, it is better not to provide weep holes below retention
level if within the creep length range.
60
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
61
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Q2 1
hi hi 1 hi Z i Z i 1 a 2 1 2 1 4 1/ 3 4 / 13 2 n12 Q 2 xi
2g A
Ai 1 2 Ri Ai 2
Ri 1 Ai 1
i
・・・・・・・・・(F. 3.3)
Where
Q : design flood discharge (m 3 /sec)
A i : flow area at ( i ) section (m 2 )
R i : hydraulic mean depth at ( i ) section (m)
n i : roughness coefficient at ( i ) section
x i : distance between sections (m)
z i : distance from the base line of ( i ) section to riverbed (m)
a : correctional coefficient of the velocity head
g : acceleration of gravity (m/sec 2 }
62
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
p p1 p2 p3 ・・・・・・・・・ pn
Also, the following approximate formula may be used.
1
ne p1n1 p2 n2 ・・・・・ pn nn ・・・・・・・・・・・・・(F. 3.5)
p
E F nn Pn
63
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
64
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
65
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1) Sill elevation
See Section 3.2.1.(1).
2) Width
See paragraph 3.2.7(4).
3) Weir body and apron
In Fig. 3.18, lo should be more than twice the upstream water depth
h 1 at the design flood level in order to have the weir function as a
broad crested weir and to give the roughness effect. Also, the slope
should be taken in parallel with the proposed site slope at the
riverbed.
66
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
The length g , out of the length 0 at upstream side of the pier should
be taken about three times the width of the pier and given an adverse
slope of 30/100, the tip of which is penetrated about d 1 = 1.5m into
the natural riverbed. The thickness of upstream apron t u should be
about 1/2~2/3 of the thickness of downstream apron. The length 1
of the downstream weir body from guide frame of gate to the
downstream apron can be obtained by formula (F. 3.6) and the
thickness t by formula (F. 3.7).
4 ⊿ H - Hf
T≧ ・ ……….(F. 3.7)
3 γ -1
67
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1) Sediment inflow
The first requisite for the intake
site is that the river channel, in Picture 3.2 Scouring sluice
other words the thalweg, should
be stable. Sediment inflow to the canal would take place in the
following cases:
① If the intake site is not correctly sited in relation to meandering
of the river,
② If water intake is required even during floods,
③ If the intake is located too close to the riverbed elevation and the
intake flow velocity is large.
To avoid ① mentioned above, fix scouring sluice just downstream of a
concave bank center as a suitable site for a smooth removal of
sediment. Item ② mentioned above is a multipurpose water intake
68
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
case requiring water intake even during flood such as for water
supply, hydropower, etc. In case of item ③ , when the intake flow
velocity exceeds 40cm/Sec, sediment grain sizes of 0.3mm tend to
move. Hence, it is desirable to dam up water by the intake weir so as
to make the intake flow velocity smaller. It is necessary to study the
relationship with construction cost including provision of a settling
basin.
69
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Ve = 20 d e ………..(F. 3.7)
70
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
The height of the guide wall H required to form a channel for the
scouring sluice is made 1.5hc at the point of intake (Fig. 3.20).
71
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1 h
3 n 2 ghc 3
i h c 2 1.5hc 10 / 3 …………(F. 3.11)
1 2h h
m
The second term of the right side of the formula (F. 3.11) represents
the energy gradient I e required for traction of the deposited sediment
within the canal of the scouring sluice. The value I e should be larger
by the energy loss to transport a volume of sediment than the critical
flow I e corresponding to the hc in the formula (F. 3.12). On the other
hand, I e at the fixed floor will be smaller than the energy gradient I tg
for the critical traction against the average grain size. Where, I e from
the Manning's formula of the average flow and I tg from the simplified
formula by Iwagaki can be given in the formulae (F. 3.12) and (F.
3.13) respectively.
Ie = n 2 g / hc 1 / 3 ………………………… (F. 3.12)
Itg = 8.25 × 10 - 2 d m /h m ……………… (F. 3.13)
72
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
h
i 2 2 h x ≒ h 3 2 1 8 F 2 1 ……………(F. 3.15)
2
2
q 1
2
1 2 2
i 2 2 h h 2 e 2 2 n qe 2
10 / 3 …………(F. 3.16)
2 g h h2
h h 2
2
73
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
scouring sluice gate base when the gate is opened to the full width at
the intake water level.
3
v 2 n 2 ghc
y h 1.5hc 10 / 3 ………….(F. 3.17)
2g hm
Where h m = ( hc + h )/2,
qc = V・h (flow per unit width)
h c = ( qc 2 / g ) 1 / 3
i = y/
74
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
hm 1 0 / 3
Bs ≦ Qs / qe ……….(F. 3.18)
Bm ≦ Qm / qc ……….(F. 3.19)
It is desirable to make the width less than 1/2 of its length.
75
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
[Reference 1]
The river discharge at the transportation limit of average grain size;
first the water depth of the average grain size transportation limit
must be obtained by the formula (F. 3.20).
h s c = U * c 2 / g i ………….(F. 3.20)
Where U*c is friction velocity at the limit of the average grain size
transportation, and can be obtained by Iwagaki's simplified formula:
U * c 2 =80.9 dm dm ≧ 0.303cm …………(F. 3.21)
Where dm : average grain size of riverbed (m)
[Reference 2]
Example of calculation of scouring sluice canal for a rapid stream;
(i) Design conditions
River width B = 250m, river slope i = 1/300, average grain size of the
river dm = 0.05m, maximum grain size (grain size of 90% passing by
weight) d 1 = 0.30m, ordinary river discharge Q = 130~170m 3 /sec,
water level of downstream of the weir at the ordinary water level EL
= 34.00m, length of scouring sluice canal at the upstream side of the
weir = 40m (planned), original riverbed elevation at the inlet of
scouring sluice EL = 34.00~34.50m and length of the channel for the
scouring sluice at the downstream side of the weir = 20m (planned).
The flood discharge of the river is 4.0 m 3 /sec.
76
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
77
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Fig. 3.23 Water depth and roughness coefficient for unit width discharge
hc = 20 d l/ g, qe = 20 dl 3 / g 2
By substituting dl=0.30m and g=9.8m/sec 2 for the above formula, hc
= 0.612m, qe = 1.5m 3 /sec/m can be obtained. The height of the
guide wall is H= 1.5 hc = 0.918m. And the correction is made
intaking into account the execution and safety factor, as follows:
78
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Table 3.6 Relationship between Roughness Coefficient and Water Depth (n-h)
h 8.25×10 - 2 d m n 2 gh c 2 / h m 1 0 / 3
hm >
(m) hm n=0.017 n=0.018 n=0.020
0.60 0.633 1/153 1/262 1/229 1/189
0.55 0.608 1/147 1/228 1/204 1/165
0.50 0.583 1/141 1/199 1/177 1/144
0.45 0.558 1/135 1/172 1/153 1/124
0.40 0.533 1/129 1/147 1/131 1/107
0.30 0.508 1/123 1/125 1/112 1/91
0.35 0.483 1/117 1/160 1/95 1/77
In Table 3.6, the water depth at the downstream end of the scouring
sluice channel h becomes h = 0.40m to give a value of grain size
larger than that with maximum grain size in the sediment to be
flushed, taking into account the energy loss due to sediment
transportation and the roughness coefficient n = 0.018.
Consequently, the length of channel 1 is 1 = 40m and the slope of
the channel bed is obtained from the formula below:
1 hc 3 n 2 gh 3
c
i h 1.5h c 10 / 3 0.01562 1 / 64
1 2h 2 h
m
Also, the critical slope becomes
ic = n 2 g / hc 1 / 3 = 1/275
thoroughly satisfying the supercritical flow conditions.
The downstream end of the supercritical flow or the gate base
elevation is as follows;
i × 1 = 40/64 = 0.625m
∴ 34.00-0.625 = 33.375m
(where the inlet base elevation = 34.00m.)
79
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
The condition for the supercritical flow canal with the required
tractive force can be shown as follows.
h2 2
i2 2 h x ≦ 1 8 F2 1 ……….(F. 3.25)
2
Here, the difference in elevation between water level on the gate sill
and that of the downstream.
The water level on the gate sill is
33.375 + 0.40 = 33.775m
∴ x = 34.00 - 33.775 = 0.225m
where the length of downstream channel 2 is made 2 = 20m, and the
channel slope i 2 with the required tractive force can be obtained
from the formula shown below in assuming the water depth at the
end of the channel h 2 ;
2
1 2
n 2 qe 2
1
qe
i 2 2 h h2
10 / 3 ……….(F. 3.26)
2g h2 h 2
2 h h2
2
where qe = 1.7m 3 /sec/m, n = 0.018, F 2 2 = q e 2 / gh 2 3 , h = 0.40m
This H 2 is the value that becomes about the critical water level on
the gate sill when the upstream water level is at the design intake
water level.
80
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(4) Pier
The pier is structure that the gate operation in opening and closing
can be easy,stable mechanically and the obstacles due to the flood
flow can be minimized.
1) Height of pier
The height of pier is determined by the method shown below.
Where, design flood water level = design flood water level at the
upstream side of the weir
Freeboard① = distance between design flood water level and
gate sill, which must be larger than approach
velocity head in flood,
Freeboard② = distance between gate crest and the bottom of
crest plate. When the gate includes such
structures, as spoiler, screen, stopping hook, etc.
and freeboard of hoist. Generally, about 0.50 -
1.00m will suffice.
81
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
River
t p :Thickness
: Length
(a) Thickness
Generally, 1.50~3.00m thickness is sufficient. The thickness is first
estimated prior to designing by the empirical formula (F. 3.28) in
taking the height and span length of the pier as parameters based on
the empirical data and determined after examining the stress, etc.
t p = 0.12( D p + 0.2 B i )±0.25m ……………………… (F. 3.28)
Where t p = thickness of pier (m)
D p = height of pier (m)
B i = span length (m)
It is desirable that the blockage factor of the pier against the flow
(the ratio of the total of the thickness of the pier into the water
surface width at the design flood water level) should be smaller than
10%.
(b) Length
The length of a pier in the direction of the thalweg should provide
sufficient stability for the pier. A trapezoidal section is generally
advantageous for the bottom part of the pier. A rectangular section
can be adopted for a pier if used also as large scale bridge piers for
82
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(c) Others
In determining the thickness and length of the pier, it is necessary
for the engineer to consider the harmony of the whole structure in
regard to height, spacing, bridge, etc.
(b) Arrangement
The arrangement in horizontal section of a pier below the cutwater is
semicircular or a spindle shape toward both the upstream and
downstream sides of the pier so as not to cause a vertical inflow time
of flood. If debris flow is violent in flooding, then the design of the
upstream side must be semicircular. In such a case, it is best to take
measures such as installing an iron plate to protect the pier from
wear or providing vacuum treatment, etc.
83
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
4) Safety analysis
(a) A pier must satisfy the following stability conditions:
① If the gate is opened during flood, then it is stable against
action of wind load from both upstream and downstream,
② If the gate is closed at the low flow, then it is stable of both
upstream and downstream side against seismic forces in the
direction of downstream. In other words, when the hydrostatic
pressure and the dynamic water pressure due to earthquake
are acting on the entire height of the gate on upstream side
and the water pressure at the lowest water level on
downstream side (normally 0),
③ If the dam is empty, then it is stable from both upstream and
downstream against the actions of earthquake in the direction
of upstream,
④ If the dam is empty, then it is stable in the direction of the axis
of the weir against actions of earthquake in the direction of
the axis of the weir,
⑤ If the gate is opened in wet season, then it is stable in the
direction of the axis of the weir against actions of earthquake
in the direction of the axis of the weir,
⑥ Stability against the internal stress of each components of
the pier.
84
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
7
pd ・ w0・ kh H・ h ………..(F. 3.29)
8
Where w o : unit weight of water (t/m 2 )
Kh : design seismic coefficient
85
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
7
Pd 1 ・ w0・ k h・ Bm・ H 2 ………(F. 3.30)
12
Acting point of the resultant force of dynamic water pressure
Y d = (2/5)・H ………(F. 3.31)
b) Type and acting point of external force
(i) Dead weight
W= w ・V
Where w : unit weight (t/m 3 ), refer to Design conditions in
section (b) a) (i) above for concrete
V: volume of the pier (m 3 )
(ii) Weight of hoist W 1 : to be separately calculated.
(iii) Weight of operating bridge W2, : to be separately
calculated,
(iv) Weight of the gate W 3 : to be separately calculated,
(v) Water pressure acting on the gate
1
2
Pg ・ w0 H 2 H 0 ・ B m ………(F. 3.32),
2
(vi) Dynamic water pressure acting on the gate
86
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Fig. 3.27 Water pressure received by gate Fig. 3.28 External force and arm
length
(ix) Wind load
The wind load is assumed to be acting on the net projection
area of body and the value is multiplied by the form factor
of the following:
for vertical projection: area 300 (kg/m 2 )
(xii) Uplift
1
U ( H Ho)・ μ・w o・ A ……………(F. 3.36)
2
Where μ : uplift coefficient
A : bottom area of the pier (m 2 )
However, in the case where the uplift remains at the end of the pier,
p is calculated as a trapezoidal section. The X-X' axis of datum line
87
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
is given to 'the pier section and shows the acting points, of external
force as X and Y, respectively. This distance is called the acting point
distance and obtain Y value for horizontal force and X value for
vertical force.
c) Stability analysis
Moment is calculated from the above external forces and the acting
point distance as well as internal stress and the following items are
examined:
① Safety against overturning
② Safety against sliding
③ Safety against settlement
④ The stress of each member within the allowable stress
First, the resultant force is obtained from the formula below:
( V ・ X )
Xo = …………(F. 3.37)
V
(H ・ Y )
Yo =
H …………(F. 3.38)
∑M=∑(V・X)+∑(H・Y)………….(F. 3.39)
Where
Xo : distance between acting line of resultant force of vertical force and
datum point (m)
Yo : distance between acting line of resultant force of horizontal force
and datum point (m)
ΣV: resultant force of vertical force (t)
ΣH : resultant force of horizontal force (t)
Σ ( V ・ X ) : total of the moments due to vertical force (t・m)
Σ ( H・Y ) : total of the moments due to horizontal force (t・m)
ΣM : total of moments or the moment due to resultant force (t・m)
88
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
M L
e - ……….(F. 3.40)
V 2
L
e ≦ ……….(F. 3.41)
6
Where
e= eccentric distance (m)
L: length of the base (m)
Where
ΣM r : total of the resisting moments against overturning (t・m)
ΣM t : total of the moments against overturning (t・m)
89
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
90
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
91
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1) Dead weight
In the calculation of the dead weight of the weir body concrete to be
used for stability calculation, it is desirable to determine the specific
gravity by measuring the sizes of aggregates. Generally ,
approximate specific gravities are as follows: reinforced concrete:
2.5 (24.5KN/m 3 ), plain concrete: 2.35 (23KN/m 3 ), and cement
mortar: 2.15 (21KN/m 3 ).
92
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
nDf B1 mDf
W1
W2
W3
1 1
W1 woγB1Df W2= woγmD f
2
W3 = woγnD f
2
……..(F. 3.49)
2 2
W2=W1+W 2+W 3
2) Hydrostatic pressure
① In case of non-overflow weir and a weir that has a movable weir on
its crest
The condition of the largest difference in water level between
upstream and downstream should be employed for analysis i.e. the
water level upstream is assumed to reach the weir crest and the
water level downstream is assumed to be as high as base level.
② In case of an overflow weir
In case of the upstream water depth being h 1 and the downstream
water depth being below the weir crest, calculation must be
performed under those conditions in consideration of the design
flood discharge for an overflow weir. But if the downstream water
level is above the weir by h 2 as it is considered that the flow above
the weir becomes a supercritical inflow the range of h 2 ≦ 2/3h 1 in Fig.
3.30, then the hydrostatic pressures on the upstream face, weir
crest and downstream side are assumed to be as the low pressure
occurs at the weir crest because of the bending of water stream line.
It is assumed that the upstream face ab is under a trapezoidal load
(h 1 + V 1 2 /2g) at b and (h 1 + V 1 2 /2g+Df) at α, the weir crest bc is under
a trapezoidal load h 1 at b and 0 at c and the downstream face cd is
under a hydrostatic pressure 0 at c and (h 2 +Df) at d. However, as the
hydrostatic pressure on the weir crest is unstable, it would be safer
to omit this if the width bc is small and the overflow weir is used in
93
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
proportion to h 1 .
Fig. 3.30 H ydrostatic pre ssure of Fig. 3.31 H ydrostatic s ubme rge d we ir
complete overflow
Next, if the weir takes the form of a submerged weir when h 2 >2/3 (h 1
+ V 1 2 /2g), then the condition where h 2 = 2/3 (h 1 + V 1 2 /2g) is
dangerous. The section is determined to satisfy stability under
hydrostatic pressure with the above procedure and to make sure
that the stability can be maintained assuming bc and cd may be
subject to hydrostatic pressure in proportion to the water depth,
when the water level becomes the maximum. Fig. 3.31 shows the
hydrostatic pressure in case of a submerged weir.
4) Seismic force
The seismic force is assumed to be acting horizontally to the center
of gravity of the weir body. The design seismic coefficient applies
correspondingly to the case of Section 3.2.1-(4) pier. As in the case
of the pier, the seismic force is considered only at the time of the
ordinary water level but not at the time of maximum flood.
94
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
The seismic force per unit length F is obtained by the formula (F.
3.50)
1
F KW ( B1 B2 ) D f ………….(F. 3.50)
2
Where F : seismic force per unit length (KN/m)
K : design seismic coefficient (0.15)
W : unit weight of weir body (KN/m 3 )
B 1 : crest width(m)
B 2 : weir bottom width (m)
Df : weir height (m)
1
Pe (W1 wo)CoHe 2 ……….(F. 3.51)
2
6) Uplift
The trapezoidal load of each water depth multiplied by the coefficient
of uplift is considered to act against the bottom at the upstream and
downstream ends. The coefficient of uplift is μ = 0.4 an rock
foundation case or a case using sheet piles reaching an impermeable
stratum, otherwise μ = 1.0.
In calculation, it is convenient to divide the trapezoid into two and
the uplift on the upstream side is made U 1 and that of the
downstream side U 2 .
95
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1
U 1 ・ w0 B2 h1
2
1 ……….(F. 3.52)
U 2 ・ w0 B2 h2
2
The total uplift
96
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Fig. 3.33 Uplift water level Fig. 3.34 The way of taking
water level
e = | ∑ M / ∑V – B 2 / 2 | ≤ B 2 / 6 (Normally),
B 2 / 3 (Earthquake) ……….(F. 3.54 )
Where
ΣV : resultant force of vertical force (KN)
ΣH : resultant force of horizontal force (KN)
e : eccentric distance (m)
To avoid tensile stress in the weir body, the resultant force must
pass within the middle 1/3 of the center of the bottom length as a
limiting stress. Thus the condition against the overturning can be
satisfied.
S L = ∑ M × f / ∑V ≥ 1.5 (Normally),
1.2 (Earthquake) ……….(F. 3.55)
97
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Z B fV
n 0 2 ≧ 4.0 ………(F. 3.56)
H
V 6e
q= 1 < q a …………(F. 3.57)
B2 B2
98
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
2) Downstream face
Although there are various corrected sectional forms for the
downstream face, it is necessary that the overflow water streamline
should not separate from the weir body. For this reason, the
downstream face is shaped as a parabola with x 2 = αhy. The value of
α is made larger than 1.78 and the parabolic line comes in contact
with the downstream face. Therefore, in Fig. 3.35, axes x and y are
taken as shown in the figure and where a point of intersection
between y axis and the slope of downstream is O, and OE = d
The curve formula comes in contact with the downstream face below
the weir crest by d.
x 2 = 4m 2 dy ……………………..(F. 3.59)
The following condition must also be satisfied;
3) Bucket
The bucket is provided to divert the falling water streamline to the
horizontal direction at the toe of the slope of the body of the overflow
weir except for a weir with small flow and constructed on relatively
99
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(6) Apron
1) Downstream apron
To prevent scouring downstream of the weir due to the overflow
water a downstream apron is provided at the downstream face. The
thickness of apron is determined in the same manner as that of the
movable weir.
The length can be obtained from the formula below:
2) Upstream apron
The apron to be provided upstream is to prevent scouring of the
riverbed by vortical flow caused by the overflow water. Therefore, the
thickness may be thinner than the downstream apron. Normally the
thickness is made about 1/2 - 2/3 of that of the downstream apron,
but on a river where vortical flow may occur, the thickness must be
increased. As with the upstream apron of a movable weir, a reverse
slope of about 30% may also be applied for the upstream apron of a
fixed weir. However, when the weir height (D f ) is more than 2 ~ 3m
and deposited silt at the upstream face is foreseen, It is not needed
to provide. The calculation of creep length should not be taken this
100
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
3.2.3 Riprap
Riprap is provided where there is fear that local scouring would be
caused on the riverbed taking into account the condition of the
riverbed and of the flow caused both upstream and downstream, and
of construction that is safe against the flow, and will have an energy
dissipating effect. Riprap is provided continuously on the
downstream apron to prevent the scouring of the riverbed, because it
is apparent that the scouring is caused due to removal of deposited
silt or vortical inflow compensation of the local dissipation of the
water energy.
101
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
3) Wear resistance
As there can be a large movement of sediment at the time of flood,
the riprap must have wear resistance against the flow of sediment.
102
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
103
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Apron
L2 L1
Riprap B Riprap A
L= L 1 + L 2 …………..(F. 3.62)
Where
L 1 :The hypercritical flow section of from dropping
point of stream to start point of hydraulic jump
L 2 :The section of hydraulic jump occurred
⊿Z
104
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
In the case of "h 1 a >h 1 b ",because the perfect hydraulic jump changes
to imperfect jump, turbulent of river bed is decreased.
105
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
h1b 1 2
( 1 8 F2 1) …………..(F. 3.64)
h2 2
Where
h 1b : water depth at the beginning point of hydraulic jump
h 2 water depth of downstream
F 2 : Froude's number of downstream F2 V2 / gh2
V 2 : Velocity of downstream
(obtained by normal flow calculation)
106
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
x : sectional length
a: constant
When h 1 b is substituted for this equation(h = h 1 b ) after first water
depth h 1 a is substituted for this equation(h = h 1 a, x=0) and constant
"a" is obtained, the sectional length x=L 1 is obtained.
L LB a ……..(F. 3.69)
107
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Where
L : length of riprap (m)
L B : total length of protection including length of apron l a
and length of riprap L (m)
H a : height from above water level of downstream side to
weir crest in dry season (m)
q : flow per unit width of design flood discharge (m 3 /sec/m)
f : safety factor, 1.5 in case of movable weir
1.0 in case of fixed weir
C : Bligh's coefficient by type of foundation ground (refer to
Table 3.3)
W 3 . 75 AV 2
/ 2 g ……….(F. 3.71)
Where
W : weight of each block (t)
A : area of collision with flowing water (m 2 )
v : velocity at which flowing water collides with (m/sec)
g : acceleration of gravity (m/sec 2 )
Formerly, the sizes of blocks used in the river works were 2t/blocks
for sluggish stream sloping at less than 1/1000 ; 3t/blocks for
1/1000~1/500 and 4t/blocks for rapid streams more than 1/500.
Unlike a foot protection of river, the size of each block should be
larger than in case of riprap for the headworks.
108
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1) Spread foundations
Although there is no problem when headworks are constructed on
bedrock, footings are required whereby the base of a fixed weir,
abutment and piers are enlarged when the weir is founded directly
on gravel.
110
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
111
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Fig. 3.39
Contact pressure distribution
of rectangular foundation
Fig. 3.40
Graph for calculation of α, α’
112
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Fig. 3.42
Fig. 3.41
Contact pressure distribution
Where eccentric load and
when resultant vertical force
moment work at the
acts on every point of
same time
rectangle bottom
When the vertical load is acting on the outside of the shaded portion
as shown in Fig. 3.42 (b), the compressive stress becomes zero at a
part of the base. The value ߙ in this case can be obtained from Fig.
3.43.
113
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
To obtain the allowable bearing capacity of the ground there are the
following methods:
① Allowable bearing capacity is determined from the ultimate
bearing capacity formula using the results of soil test.
② Allowable bearing capacity is determined directly from the
results of a plate bearing test.
③ Allowable bearing capacity is determined from the
conventionally adopted table of bearing capacity of ground.
qa
1
a・ C・ N c 1 ・ B・ N +γ 2・ D f・ N q …(F. 3. 76)
3
2 1
qa a・ C・ N c 1・ B・ N + γ 2・ D f・ N q ………(F. 3.77)
3 2
114
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
115
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
116
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Where i c = i q = (1 - θ /90) 2
i r = (1 - θ /φ) 2
θ : angle of inclination (degree)
φ: angle of internal friction (degree)
117
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
When the load is eccentric from the center of the footing, there is a
method by which the contact pressure distribution of trapezoidal or
triangular load balanced with the eccentric load is considered as
shown in Fig. 3.42, and designed is such that the maximum contact
pressure σ m a x of the foundation base is within the allowable bearing
capacity (q a ), and another method by which design is performed
assuming that the effective width of the foundation base decreases
by two times the eccentricity. In this guideline, the former method is
used. When the load is inclined or eccentric, design is such that the
maximum contact pressure is within the unit allowable bearing
capacity with inclined load.
118
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
119
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
that it can prevent scouring especially by the floods just after the
completion of construction and as a water-seal during construction.
The walls may be extended from the weir body to abutments of the
headworks to complete the seal if it is necessary. In this case, the
wall should be called a water-cut wall or wing wall to distinguish it
from cut-off wall.
120
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
beds in the same way as sheet piles. When the riverbed contains
large gravel and neither sheet piles nor cast-in-place concrete piles
are applicable, wells or caissons are sunk and used as a cut-off wall
or a dwarf wall .In this case, special attention must be given to
construction of joint portion in order to ensure the water-cut-off
function. Grouting work may follow the above mentioned sealing
works if necessary.
121
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
122
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Downstream cut-off
3.2.6 Inlet
An inlet must be designed to prevent soil, sand and floating material,
which are undesirable in irrigation water, from entering the canals.
Inlets must allow the designed flow-rate and be safe fromexternal
forces. The principle of inlet design is to ensure the consistent
intake of water and prevent inflow of sand. Stability of the river
course, river meandering condition and runoff condition should be
studied to fulfill the principles.
123
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
124
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
The inlet elevation should be 1.0m higher than the base elevation of
the scouring sluice for prevention of sediment, if a diversion weir is
installed. There is a standard that the height from the riverbed to the
inlet elevation should be more than 1/6 of maximum flood depth of
the river, which is based on the consideration of the critical height of
sedimentation on the riverbed by flooding. The inlet elevation should
also be the same level or higher than the guide wall height of the
sediment sluiceway. However, if the width of the sediment sluiceway
is wider than the width of inlet, this does not have to be considered
strictly.
2) Intake Velocity
Generally an intake velocity of 0.6 ~ 1.0m/sec above inlet apron is
standard, which is decided based on the following two conditions'.
First, the approach velocity (velocity of the river flow just upstream
of the inlet) must not exceed 0.4m/sec so that soil particles bigger
than 0.30mm in diameter, which might be harmful for irrigation
water, will not inflow.
3) Width of Inlet
Width of inlet is calculated by the formula (F. 3.85) with inlet apron,
elevation, design intake water level and inflow velocity.
125
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
4) Screen
A trashrack is attached just in front of the
regulation gate with an inclination of about
1:0.3 so that trash is easily evacuated. The top
of the trashrack is made round and workability
of cleaning devices must be considered (see Fig.
3.51). A fish screen that prevents fry from
entering into canals is installed right after the Fig. 3.51 Screen
trashrack if necessary.
5) Inlet Basin
An inlet basin is a transitional structure between an inlet and a head
race for putting the inflow uniform. A guide wall is usually provided
to avoid nonuniformity of flow. During floods, sedimentation usually
occurs in this section. The inlet basin must be as short as possible
and covered.
126
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Q m( B n k h 1 )h 2 2 g ( h 1 h 2 ) ………….(F. 3.86)
2 v2
if h2 h1 1 then the discharge is calculated by the
3 2g
h0
Q m B h 0 2 g h 1 ………..(F. 3 .87)
2
where Q : inflow discharge(m 3 /sec)
m : coefficient, 0.62-0.66 (0.65 is used for design and an
adjustment should be made by measurement after the
completion of construction)
h 0 : gate opening (m)
127
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
V2 2 V1 2 V
2
V 2 V 2
⊿he he f e 2 2 1 …………. (F. 3 .88)
2g 2g
2 g 2 g 2 g
128
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Head loss coefficient (f e ) is due to plan feature of inlet (see Fig. 3.53)
2) Head loss and change of water level due to elevation gap of base
line
V2 2 V12 V
2 2
V V1
2
⊿hc hc fc 2 2
………(F. 3.89)
2g 2g 2g 2g
129
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Head loss and difference in water level due to drop in elevation are
calculated by the formulae (F. 3.90 and F. 3.91).
V2 2 V12
⊿h t h t ………..(F. 3.90)
2 g 2 g
ht ⊿Z
f Fr 2 , ………..(F. 3.91)
h2 h2
130
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Q2 1 1
⊿h p ………..(F. 3.92)
2 g c 2b2 2 ( H ⊿h p ) 2 b12 H12
131
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
V 2 V 2 V
2 V 2 V 2
⊿hr hr 2 1 f r 1 2 1 …………(F. 3.93)
2g 2g 2 g 2 g 2 g
4/3 2
t V1
hr sin …………(F. 3.94)
b 2g
Where
Δh r : difference in water level (m)
h r : head loss (m)
f r : head loss coefficient
β : coefficient for sectional shape of screen bar (see
Fig. 3.60)
θ : inclination of screen (degree),
t : bar screen thickness (m)
b : bar interval (m)
V 1 : upstream average velocity (m/sec)
V 2 : downstream average velocity (m/sec)
g : acceleration of gravity (m/sec 2 )
132
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Formula (F. 3.93) treats only a case without trash obstructing the
screen and an adjustment calculation for actual conditions is
necessary (see Fig. 3.61).
Formula (F. 3.95) is used to calculate head loss by trash*.
4/3
t a
f r 6 . 69 sin exp 0 . 074γw ………. (F. 3.95)
b H
Other notations are same as those in formulae (F. 3.93) and (F. 3.94).
Fig. 3.62 is the calculation condition. Trash sticking height ratio
a/H is usually assumed to be 0.1 as a standard. Since this ratio may
affect the intake discharge and the choice of weir crest elevation,
the ratio has to be decided after considering river conditions.
133
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Fig. 3.61
Change of water level by trash
Fig. 3.62
Latticed type screen
2 gn 2 L V 2
h f 1/ 3
R R 2 g ……..(F. 3.96)
where h f : frictional head loss (m)
n : roughness coefficient (0.014 ~ 0.015 for concrete lining
canal )
V : average velocity (m/sec)
L : canal length(m)
R : hydraulic mean depth(m)
6) Head loss and change of water level due to abrupt increase in flow
area
V 2 V 2 V 2 V 2
⊿hse hse 2 1 he h f 2 1 ……….(F. 3.97)
2g 2g 2g 2g
2
V
he f e 2 ……….(F. 3.98)
2g
134
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
n 2 V1 V2
2 2
hf ……….(F. 3.99)
2 R14 / 3 R2 4 / 3
The head loss coefficient f e is due to width ratio b1/b2 (see Fig. 3.64).
the depth at flow area changing point becomes a critical depth and
there occurs a control section. The area above each line in Fig. 3.65
135
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
where
136
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
V 2 V 2 V 2 V 2
⊿hsc hsc 2 1 hc h f 2 1 ………….(F. 3.101)
2g 2g 2g 2g
2
V2
hc f c ………….(F. 3.102)
2g
n 2 V12 V2
2
hf ………….(F. 3.103)
2 R14 / 3 R2 4 / 3
where
Δh s c : water level difference due to abrupt shrinkage of
flow area (m)
h s c : head loss due to shrinkage (m)
137
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Fig. 3.67
Abrupt shrinkage flow
Fig. 3.68
Energy loss at abrupt
shrinkage
138
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
I 3 b
1 ………..(F. 3.105)
I0 4 R
where
I 0 : bed slope
I : surface slope
b : flow width (m)
R : radius of curvature (m)
139
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
where
Δh b : water level difference (m)
L : radius of curvature (m)
Loss calculation
⊿ he=he+V 2 2 ÷(2×g)-V 1 2 ÷(2×g)
he=fe×V 2 2 ÷(2×g)
⊿ he: Change of water level due to inflow
he: Head loss due to inflow
fe: inflow head loss coefficient=0.5
V 1 : Just in front of intake flow in Velocity=0m/s
V 2 : flow in Velocity Q÷A 2
g: gravity acceleration
h 1 :water depth of intake
B:wide of intake
Q:amount of intake
A 2 :Area of after intake=B×(h 1 -⊿ he)
Calculation Example
B=3.5m, h 1 =0.6m, Q=1.5m 3 /s
At first ⊿ he is assume 0.046m
h 1 - ⊿ he=0.6m-0.05m=0.554m
A 1 =3.5m×0.6m=2.1m 2
A 2 =3.5m×0.554m=1.939m 2
V 2 =Q÷A2=1.5m3/s÷1.939m2=0.77m/s
he=fe×V 2 2 ÷(2×g)=0.5×(0.77m/s) 2 ÷(2×9.8m/s 2 )=0.0153m
140
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
This calculation needs trial and error. For easy calculation the
width of inlet, the ”goal seek” function of excel is useful.
3.2.7 Gate
The gate structure must be watertight to ensure stable water intake
and firm enough against several external forces like flowing water.
Steady and smooth operational workability is also required for its
function.
A gate is one of the most important facilities to control both water
utilization and floods. The following conditions are to be fulfilled for
the purpose of water use and flood control. Conditions required from
the view point of Water use are;
① to keep a constant required water level and to control intake
level and discharge and
② to have water tightness.
On the other hand, conditions required from the view point of flood
control are;
① capability of being operated quickly and smoothly so as to
release water safely and
② to remain workable without accumulation of material carried
by water.
Structural stability and endurability are also required.
141
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
plastic). This section covers a steel gate. When using materials other
than steel for gate, the characteristic features of the material for
gate should be studied carefully.
1) Type of gate
(a) Vertical lift gate ; Fixed wheel type gate
Slide gate
Double leaf gate
Stop-log
(b) Hinged type gate; Radial gate
Sector gate
Mitre gate
Flap gate
Swing gate
(c) Other type
2) Definition of Gate
The gate structure consists of a gate leaf, guide frame, pivot and
hoisting equipment. The gate leaf is the part which receives the
hydraulic load and conveys it to pivot. The guide frame is the
embedded part in concrete and adjacent to the sealing part of the
leaf to prevent water leakage. The pivot is part of a hinged type gate
which transmit the external force (load) to the concrete. 'The guide
frame covers this function for a vertical lift type gate. The hoist is the
equipment which operates a gate leaf.
142
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
A double leaf gate has a complex mechanism for sealing, guide frame
and operation and H/L ratio have to be smaller than the other types.
Stability of these mechanism should be checked carefully. A spoiler
143
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(that separates vein of water and supplies air behind the leaf) or
other reasonable treatment is required to minimize vibration.
Double leaf gates are divided into three types due to structural
differences.
a) Double leaf gate ; Two shell type or girder type gates are
combined. Track rail and a hoist are installed to operate each
leaf.
b) Hook shape type gate ; Hook type gate leaf is installed for upper
leaf and combined with lower wheel gate. Bottom wheel of upper
leaf transmits load by rolling on the skin plate (sheet metal) of
the lower leaf. A hoist is usually used.
c) Shell type with flap ; This is a combination type of a flap gate for
the upper gate and a shell type gate for the lower gate. Since the
sealing mechanism and hoisting mechanism are comparatively
simple, this type has been adapted as regulating gate for the
diversion weir. The hoist part consists of both upper and lower
operative winches and has a mechanism that makes it possible
for the two hoists to work together. Further, the leaf height of
the upper part flap gate should be less than one third of the total
height of the gate.
144
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(d) Stop-log :
Stop-log is a kind of gate that is used for small gate and discrete
operation when main gate is under repair. Horizontally divided
leaves are placed on top of each stair. A portable winch also used for
storage of the stop logs is also desirable. A floating type and a shield
type leaf are also used during temporally gate repair.
Fig. 3.74 Slide type gate Fig. 3.75 Gate types for repairing
145
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
146
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
147
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
148
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(3) Material
Materials must be selected to be suitable for the specific purpose of
each gate type.
149
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Upstream water
height of gate
150
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
151
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1) Selection of site
A settling basin should be installed adjacent to the intake and a
head of the canal. When it is to be constructed downstream it should
be as near to the intake as possible if connective installation to
intake is impossible. The slower the inflow velocity, the more
effectively sand is settled. To have larger flow area, the headrace
should be as wide as the intake width. Transition angles should also
be as small as possible so as to regulate the flow. The inflow
direction should be the same as the center line of the settling basin.
When the headrace has to be curved, uneven flow must be avoided.
When a settling basin is installed separately from the intake,
velocity control in the headrace is important to ensure that sand
does not settle in the headrace bed and to avoid a large velocity
which would accelerate sand inflow. Enough drop in head is required
for natural clearing of sand which settles in the settling basin.
152
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
4) Transition part
Uneven or inverse flow is to be avoided in the transition part. When
the subcritical flow area of the headrace increases sharply at the
transition part, separation of the stream line and uneven or reverse
153
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
flow occurs and the effective area of settling basin and effectiveness
of settling decreases. A wider headrace and smaller angle of
transition are preferred. separation of stream line starts to occur
when the angle is more than 10 degrees. Transition parts which have
a larger angle should have appropriate regulation treatment. There
are several ways to regulate flow such as use of a guide wall,
regulating grating and multi-hole board. The following methods are
most effective.
(b) When the intake water level tends to change, and a constant
water level is difficult to maintain, a regulating pipe (see Fig. 3.83)
which has constant flow area through the pipe is recommended.
The bed of this pipe should have level or reverse gradient subject to
site conditions. This method is applicable when the transition part
crosses a road. This can be used as a spillway by installing a trough
at the beginning of the pipe or as a cleaning channel of suspended
materials. When separating the sedimentation ditch, separate pipes
should be provided and regulation gates are preferred at the
154
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Q
B ………(F. 3.107)
hu
Iwagaki's formula
0.0065m≦ d ≦ 0.0565cm, U*c 2 =τ c /p=8.41d 11 /32 (cm 2 /sec 2 )
155
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
156
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
h Q
LK uK
vg Bvg ………(F. 3.110)
157
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
L 1 2 3 ……….(F. 3.111)
158
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
L 20 Q ……….(F. 3.112)
where L : length of sedimentation ditch (m)
Q : design discharge in the ditch (m 3 /sec)
159
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
When there is enough drop head for a flushing pipe, steeper gradient
should be applied for the end section (5 ~ 10m) of the channel and
the water level at the entrance of the sand flushing pipe should be
lower than design flushing water level in the ditch (see Fig. 3.87).
Fig. 3.87 Tr ansition f ro m e nd of di tch to san d flush pipe , with e noug h drop he a d
160
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
And the cross sectional area and gradient of the pipe should be large
enough to flush sediment out of the pipe. Circular and rectangular
shapes are both applicable for the pipe. The shock wave caused by
the transition part at the end of the sedimentation ditch and a
proper balance between flushing discharge of sediment and width of
the ditch and between the discharge and cross section of rectangular
shape pipe make supercritical flushing in settling basins possible for
any flushing head.
A multi-lane sedimentation ditch in a basin and a
reverse-gradient-transition part to the basin make simultaneous
operation of usual operation and sediment flushing possible. The
velocity caused by drop for flushing is 1.2 to 1.5 times faster than
usual operation and the effects of the reverse gradient is remarkable.
Design flushing discharge of sediment is equal to the discharge of
each ditch. The relationship between the width of the sedimentation
ditch and of the rectangular-shaped flushing pipe is calculated by
the formula (F. 3.113).
161
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
b
2 1 2 / B 2
B 2
2
8 Fr1 ………..(F. 3.113)
2 1 1
B 1 2 / B 2
When h 2 <h c 2 between the critical depth (h c 2 ) and the depth of shock
wave (h 2 ) against the width of flushing pipe (b), the shock wave
enters the flushing pipe, maintaining supercritical flow conditions
and formula (F. 3.114) comes into effect.
1 8 Fr1
h1
1 1
2 1 2 / 2
h2
B
…………(F. 3.114)
hc 2 Q2
3
gb 2
Fig. 3.89 shows the relationship between the formulae (F. 3.113) and
(F. 3.114). The ratio b/B is the functions of F r 1 and of l/B. In the
regime where h 2 /h c 2 <1, the values b/B and l/B are read on the
specific line of F r 1 , and b as well as l are determined.
162
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
be larger than the hydraulic jump height (h 3 ). The ceiling of the pipe
should be level. When sedimentation ditch is multi ditch, sediment
is gathered into a collecting pond from each ditch using connecting
pipes and then flushed through a flushing pipe. The connecting
pipes should curve naturally for smooth inflow. Several site
condition may permit right angle curving at a transition portion
which is installed at a side of each ditch.
Fig. 3.89 Relation between Width ratio of sand flush pipe and
sedimentation ditch, ratio of length of curve and
width of sedimentation ditch, ratio of Froude No.
and depth of shock wave
9) Related structures
Regulating gate, flushing gate, spillway, etc. may be installed as
related structures. A regulating gate for a water intake is installed
around intake mouth. When it has to be installed within the
headrace the installation location should be sufficiently apart from
163
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
164
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
165
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
166
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
167
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
168
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
2) Span
The span of the operation bridge is decided after considering river
section, flow direction, features and its economical performance.
3) Location of abutment
(a) An abutment of bridge must not be installed within the flow
section of the river in the following three (3) cases when installed on
the bank of a river (or on the dikes if a sectional shape is designed).
The three cases are ;
① width of the river is more than 50m,
② installing bridge is within the .back water section and
③ installing bridge is within tidal zone of the river (see Fig. 3.92).
169
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(5) Operation
Proper operation are necessary for ordinary and flood cases to
maintain the weir's function to intake and release design discharge.
1) Intake operation
Intake operation must be executed to draw the required discharge,
prevent sand from flowing into the canals and to avoid causing
170
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
171
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
172
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
173
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(c) Revetment
a) Since the scouring sluice is usually installed at the lowest
elevation of a natural riverbed, the flood may be concentrated
there and flood energy may carry its effect further downstream
than expected and a revetment there may be damaged.
Revetment beside the thalweg must be designed with care.
b) The contact line of piers or the fixed weir body with the riprap
may be one of the weak points and must be designed with care.
174
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
175
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
176
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
177
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
178
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
179
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
180
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
181
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
182
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
183
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
184
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
185
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Large canals
1) Regular cross section without 0.025 0.060
large cobble stones or shrubs
2) Irregular and rough cross section 0.035 0.100
186
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
This Chapter shows an example of crucial data and calculation for basic
design of headworks. In case of actual design, designer must follow the
contents of this Chapter.
Example;
Measurement date 26 / 12 / 2012
Area Velocity Discharge
Measurement point Measuring L t Velocity V
Position Q(m3/s)
W(m) D(m) A(m2) line (m) (s) coefficient (m/s)
Left side of - - - No.1 10 12.99 0.85 0.66 0.079
river bank
1 0.2 0.05 0.005 No.2 12.58
2 0.2 0.09 0.014 No.3 13.10
3 0.2 0.12 0.021 No.4 12.81
4 0.2 0.12 0.024 No.5 12.95
5 0.2 0.12 0.024
6 0.2 0.1 0.022
Right side 0.2 0 0.01
of river
bank
187
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Excel format guide 1. Float measurement method
#Please input data into yellow cell.
Measurement date 26 / 12 / 2012
Area Velocity Discharge
Position Measurement point Measuring line L(m) t(s) Velocity V(m/s) Q(m3/s)
W(m) D(m) A(m2) coefficient
Left side of river bank ‐ ‐ ‐ No.1 10 12.99 0.85 0.66 0.079
1 0.2 0.05 0.005 No.2 12.58
2 0.2 0.09 0.014 No.3 13.10
3 0.2 0.12 0.021 No.4 12.81
4 0.2 0.12 0.024 No.5 12.95
5 0.2 0.12 0.024
6 0.2 0.1 0.022
Right side of river bank 0.2 0 0.01
188
Total 1.4 0.12 Ave. 12.89
Technical Guideline for Design of Headworks
According to the river slope survey data, the calculation table can be made.
Example;
↓ ↓ ↓ ↓
Accumulative
Station Distance Elevation Area
No. Height
No. L(m) H(m) A(m2)
H(m)
0 0+000 0 2418.664 0 0
1 0+020 20 2419.42 0.756 7.56
2 0+040 20 2419.608 0.944 17
3 0+060 20 2419.637 0.973 19.17
4 0+080 20 2420.472 1.808 27.81
5 0+100 20 2422.702 4.038 58.46
6 0+120 20 2423.664 5 90.38
7 0+140 20 2423.275 4.611 96.11
8 0+160 20 2422.548 3.884 84.95
9 0+180 20 2423.762 5.098 89.82
10 0+200 20 2423.15 4.486 95.84
11 0+213.07 13.07 2423.681 5.017 62.10
Total 213.07 649.20
189
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Accumulative
Station Distance Elevation Area
No. Height
No. L(m) H(m) A(m2)
H(m)
0 0+000 0 2418.664 0 0
1 0+020 20 2419.42 0.756 7.56
2 0+040 20 2419.608 0.944 17
3 0+060 20 2419.637 0.973 19.17
4 0+080 20 2420.472 1.808 27.81
5 0+100 20 2422.702 4.038 58.46
6 0+120 20 2423.664 5 90.38
7 0+140 20 2423.275 4.611 96.11
8 0+160 20 2422.548 3.884 84.95
9 0+180 20 2423.762 5.098 89.82
10 0+200 20 2423.15 4.486 95.84
11 0+213.07 13.07 2423.681 5.017 62.10
Total 213.07 649.20
190
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(1) In case of getting discharge data in or near river basin of project site
1) Data collection
In or near river discharge data on project site is collected from Ministry of
Water, Irrigation and Energy, etc. It is better to have more than ten years
data. Based on these data, the latest ten years data can be used.
Example;
Take minimum discharge of each year.
Year Minimum Date Remark
discharge (m3/s)
2004 1.50 2 January
2005 1.65 5 December
2006 1.46 23 December
2007 2.02 12 January
2008 1.80 5 January
2009 1.42 25 December ←Reference year
2010 1.55 28 December
2011 1.62 15 December
2012 1.49 20 January
2013 1.52 10 December
Example;
Reference year: 2009
Take small discharge from minimum to 11th value of 2009’s data
Ranking Discharge (m3/s) Date Remark
1 1.42 25 December
2 1.43 24 December
3 1.45 26 December
191
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
4 1.45 23 December
5 1.45 22 December
6 1.50 27 December
7 1.53 21 December
8 1.55 28 December
9 1.55 29 December
10 1.56 30 December
11 1.58 20 December ←355/365 days
discharge
1) Data collection
Refer to 2.1.1(2) and 5.1.1
192
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
The existing design water intake discharge in the downstream of the project
Qdw = 0.01m3/s (This value can be obtained from previous design document
and site investigation.)
W = D × 0.8 – Qdw
= 0.079 × 0.8 – 0.01
= 0.053m3/s
(1) Water level of the field at the highest elevation of the irrigation area
The field level at the highest elevation of the irrigation area + irrigation water
depth on the farmland = EL.2420.5m + 0.05m = EL.2420.55m
(3) The hydraulic loss between the intake and the starting point of the
main canal
There is no structure in this design but this loss assumed 0.1m for safety.
193
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1) Inlet sill
The inlet elevation prefers to be 1.0m higher than scouring sluice sill and
also prefers to be more than 1/6 of maximum flood depth of the river from
the riverbed for prevention of sand. But in case of small head weir, a
minimum inlet elevation is at least 0.5m higher than scouring sluice sill.
If the height from scouring sluice sill to inlet elevation is lower than 1.0m,
settling basin should be considered.
By using the above two formula, it calculates ⊿ he, B and h1 by trial and
error calculation. Refer to Excel format guide 3 for the detail.
194
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Excel format guide 3. Intake size (In the case of diversion weir)
#Please input data into yellow cell
#The input data of green cell is the value assumed yourself. (Goal seek "By changing cell")
#Blue cell is the "set sell" for Goal seek. "to value" = 0
This value is assumption
↓ ↓ ↓Goal seek "By changing cell" ↓Goal seek ("set sell". "to value" = 0)
Inlet width Water depth Head loss Water depth Check assumption of Head loss Intake velocity Approach velocity
(Inflow) (After Inflow) Calculation (After inflow)
Difference between eachᇞhe Result
B(m) h1(m) ᇞhe(m) h2(m) A1(m2) A2(m2) V2(m/s) ᇞhe(m) 0.6≤V2≤1.0(m/s) Va≤0.4
④ ⑤ ⑥ ⑦=⑤‐⑥ ⑧=④×⑤ ⑨=④×⑦ ⑩=①/⑨ ⑪=③×⑩2/2g+⑩2/2g ‐0.01≤⑥‐⑪ ≤ 0.01 ⑫OK or NG ⑬=①/⑨ ⑭OK or NG ⑮=①÷((②+⑤)×④) ⑯OK or NG
0.4 0.2 0.282 ‐0.082 0.08 ‐0.033 ‐1.919 0.282 0.0001 ←Goal seek OK ‐1.92 NG 0.11 OK
0.4 0.25 0.045 0.205 0.10 0.082 0.768 0.045 ‐0.0002 ←Goal seek OK 0.77 OK 0.11 OK Select
0.4 0.3 0.025 0.275 0.12 0.110 0.573 0.025 ‐0.0001 ←Goal seek OK 0.57 NG 0.10 OK
0.45 0.2 0.274 ‐0.074 0.09 ‐0.033 ‐1.891 0.274 0.0004 ←Goal seek OK ‐1.89 NG 0.10 OK
0.45 0.25 0.031 0.219 0.11 0.099 0.639 0.031 ‐0.0003 ←Goal seek OK 0.64 OK 0.09 OK
0.45 0.3 0.019 0.281 0.14 0.126 0.498 0.019 0.0000 ←Goal seek OK 0.50 NG 0.09 OK
0.5 0.2 0.267 ‐0.067 0.10 ‐0.034 ‐1.871 0.268 ‐0.0006 ←Goal seek OK ‐1.87 NG 0.09 OK
0.5 0.25 0.024 0.226 0.13 0.113 0.558 0.024 0.0002 ←Goal seek OK 0.56 NG 0.08 OK
0.5 0.3 0.015 0.285 0.15 0.143 0.442 0.015 0.0000 ←Goal seek OK 0.44 NG 0.08 OK
195
0.5 0.35 0.011 0.339 0.18 0.170 0.372 0.011 0.0004 ←Goal seek OK 0.37 NG 0.08 OK
0.5 0.4 0.008 0.392 0.20 0.196 0.321 0.008 0.0001 ←Goal seek OK 0.32 NG 0.08 OK
0.000 0.00 0.000 #DIV/0! #DIV/0! #DIV/0! ←Goal seek #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
0.000 0.00 0.000 #DIV/0! #DIV/0! #DIV/0! ←Goal seek #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
0.000 0.00 0.000 #DIV/0! #DIV/0! #DIV/0! ←Goal seek #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
0.000 0.00 0.000 #DIV/0! #DIV/0! #DIV/0! ←Goal seek #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
0.000 0.00 0.000 #DIV/0! #DIV/0! #DIV/0! ←Goal seek #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
0.000 0.00 0.000 #DIV/0! #DIV/0! #DIV/0! ←Goal seek #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
0.000 0.00 0.000 #DIV/0! #DIV/0! #DIV/0! ←Goal seek #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
0.000 0.00 0.000 #DIV/0! #DIV/0! #DIV/0! ←Goal seek #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Technical Guideline for Design of Headworks
<Confirmation calculation > Design discharge
Q = m * B * h0 * √ ( 2 * g * ( h1 ‐ h0 / 2 ) ) = 0.101741 m3/s > 0.063 m3/s OK
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
Technical Guideline for Design of Headworks
3) Confirmation calculation
Q = m × B × h0 × √ ( 2 × g × ( h1 - h0 / 2 ) )
Design water intake level = (2) + (3) + (4) = Water level at the starting point of
the main canal + The hydraulic loss between the intake and the starting
point of the main canal + hydraulic loss of entrance = EL.2421.85m + 0.1m
+ 0.045m = EL.2421.995m ≈ EL.2422.0m
So, the difference between inlet sill and base of scouring sluice
= Inlet sill (EL.2421.75m) - Scouring sluice sill (EL.2420.5m)
= 1.25m
Based on this value, the approach velocity can be calculated again using
Excel format guide 3. The result of calculation, Approach velocity is OK.
Intake 0.25m
EL. 2421.75m
0.4m
1.25m
EL. 2420.5m
196
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
(1) In case of getting past flood discharge data in or near river basin of
project site
197
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
3) Based on the data of river basin and catchment area of the project, flood
discharge at the place of headworks is calculated.
4) If the river discharge data is less than 50years, design flood discharge (Qd)
is calculated by the value which flood discharge calculated in 3) above
multiplies 1.2 for the safety.
(2) In case of using the maximum flood in the past based on flood mark
or discharge capacity of the river by slope area method
According to the river cross-section survey data, the calculation table and
drawing of cross-section of the river can be made.
Example;
198
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Rating curve
2423.5
2423 2423
2422.5
Elevation(m)
2422.186
2422 2422
2421.5
2421 2421
2420.5
2420 2420
2419.762
2419.5
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
Discharge(m3/s)
According to the rating curve of this river, the river discharge at the flood
mark (EL. 2422.186m) is 88.26m3/s.
In this case, peak flood should be multiplied 1.2 for safety.
199
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Excel format guide 4. Rating curve of the river
#Please input data into yellow cell.
1. Basic data for making cross‐section of the river
Accumulated
X Y Distance Distance Elevation (Z) Depth Auto CAD
Point ID
(East) (North) (m) (Width) (m) (m) (x,y)
(m)
RCX 0+00 546325.93 897337.45 0 0 2423.000 0 0,0
RCX 0+01 546326.099 897337.372 0.19 0.19 2422.944 ‐0.056 186.131673808933,‐56.00000000004
5151.27608979397,‐2695.99999999991
200
RCX 0+07 546330.011 897334.358 0.07 5.15 2420.304 ‐2.696
RCX 0+08 546331.425 897333.131 1.87 7.02 2419.859 ‐3.141 7023.42058204379,‐3141.00000000008
<How to make cross‐section by Auto CAD>
1.Open Auto CAD → 2. Turn off Object Snap and Ortho Mode → 3.Copy the low of "Auto CAD"(or column H) → 3. Input PL to commandline in Auto
CAD and push Enter→ Paste the data which copy from Excel file (the part of "Copy to Auto CAD") to comandline in Auto CAD → Push Escap
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
2423.500
2423.000 2423.000
2422.944 2423.000
2422.628
2422.500 2422.500
2422.186
2422.000
2421.500 2421.483
2421.278
2421.000 2420.934
Elevation(Depth) (m)
2420.729
2420.500
201
2420.304
2420.297
2420.000 2419.974
2419.859 2419.813
2419.762
2419.500
0 2 4 6 8 10 12 14
Distance(Width)(m)
Technical Guideline for Design of Headworks
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
2. Discharge of the river
Slope 0.029
Coefficient of Roughness 0.04
Wetted Note ; Water area and
Elevation Depth Water area Hydraulic radius velocity Discharge Wetted
Perimeter Perimeter calculated by
(m) (m) (m2) (m) (m/s) (m3/s)
(m) Auto CAD
2419.762 0 0 0 0 0 0
2420 0.238 0.46 3.44 0.13 1.11 0.51
2421 1.238 5.99 7.70 0.78 3.60 21.57
2422 2.238 14.71 11.37 1.29 5.05 74.36
2422.186 2.424 16.57 11.84 1.40 5.33 88.26 Flood mark
2423 3.238 25.54 14.71 1.74 6.15 157.07
Rating curve
202
2423.5
2423 2423
2422.5
2422.186
2422 2422
2421.5
2421 2421
Elevation(m)
Technical Guideline for Design of Headworks
2420.5
2420 2420
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
Technical Guideline for Design of Headworks
And the length of weir can be decided from cross-section survey data and
geological data of the bank around weir site.
- Based on the survey data of cross-section on weir site and geological data
of the bank around weir site (up to the hard rock), the length of weir =
12.5m (EL.2422.1m).
(1) Water depth of the river where the place of headworks before
construction as design flood discharge (Tail water depth)
From 5.2.3(2), the depth of the river at design flood discharge (Qmax =
106m3/s) = EL. 2422.4m (Reading from the Rating Curve)
So, Tail water depth = EL. 2422.4m – EL.2420.5m = 1.9m
(2) Water depth on the crest as design flood discharge …… (See 3.1.1(4))
- Total energy head as design flood discharge
He = (Qd / CL)2/3 = (106m3/s / (1.7 × 12.5m))2/3 = 2.92m
- Water depth on the crest
He = Hd + Qd2/ ( ( L ( h + Hd ) )2 × 2g)
∴0 = Hd + Qd2/ ( ( L ( h + Hd ) )2 × 2g) – He
= Hd + 1062 / ( ( 12.5 × ( 1.6 + Hd ) )2 × 2 × 9.8) - 2.92
The value of Hd is calculated by trial and error calculation. Refer to Excel
format guide 5 for calculation of above formula.
The result of calculation, Hd = 2.72m, Hav = He - Hd = 2.92 – 2.72 = 0.20m
203
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1. Design head
#Please input data into yellow cell
#The input data of green cell is the value assumed yourself. (Goal seek "By changing cell")
#Blue cell is the "set sell" for Goal seek. "to value" = 0
204
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Hd value should adopt the biggest one from the result of above calculation.
So Hd = 2.72m
Hav=Va2/2g
Qmax He Hd
h Weir
Sediment
According to the design flood level at weir (EL.2424.82m), river slope (1/35)
and cross-section data, possible effect on the river control of upstream can
be assumed or modeled.
205
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
206
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Excel format guide 6. HW Stability Analysis (Summary)
【Case1 : Hdownstream < Hw】
#Please input data into yellow cell
1.Basic data for calculation
Item Value Reference
3
Unit weight of plane concrete γc= 23 kN/m Reinforced concrete: 24.5KN/m3, Plain concrete: 23KN/m3, Cement mortar: 21KN/m3
3
Unit weight of wet soil γwse= 18 kN/m
3
Unit weight of water W0 = 9.8 kN/m
3
Unit weight of submerged soil γwe= 8.2 kN/m (γwse-w0)
Coefficient of earth pressure C0= 0.45
Uplift coefficient μ= 0.4 Rock foundation case or a case using sheet piles reaching an impermeable stratum: 0.4, Otherwise: 1.0
Seismic horizontal acceleration kh= 0.15
Friction coefficient f= 0.7 0.7‐0.75
2
Allowable stress of the graund qa= 1000 kN/m Bedrock=100t/m2*9.8m/s2=980KN/m2 See 3.2.4
207
B (B1+B2) 3.80 m ΣV/B・(1-6e/B)<qa 26kN/m2 < 1,000kN/m2 OK 14kN/m2 < OK 19kN/m2 < 1,000kN/m2 OK
Hw 1.60 m (Without uplift) ΣV/B・(1+6e/B)<qa 48kN/m2 < 1,000kN/m2 OK 42kN/m2 < 1,000kN/m2 OK 37kN/m2 < 1,000kN/m2 OK
Hd 2.72 m (Without uplift) ΣV/B・(1-6e/B)<qa 33kN/m2 < 1,000kN/m2 OK 14kN/m2 < 1,000kN/m2 OK 19kN/m2 < 1,000kN/m2 OK
Hdownstream 1.90 m
He 2.92 m
He
Hd
B1
Technical Guideline for Design of Headworks
B2
Hdd
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
①Stability analysis (The case of flood)
1.Basic calculation 2.Calculation table
(1 )Area (unit width)
External force Area Vertical DistanceResistance Horizontal Distance Turning
Dead load; W1 3.20m2= 2.00m× 1.60m force moment force moment
W2 1.44m2= 1.80m× 1.60m× 1/2 V(kN) x(m) V*x(kN・m) H(kN) y(m) H*y(kN・m)
Static water P1 4.67m2= 2.92m× 1.60m Dead load W1 73.60 1.00 73.60
pressure; P2 1.28m2= 1.60m× 1.60m× 1/2 W2 33.12 2.60 86.11
P3 2.72m2= 2.72m× 2.00m× 1/2
P4 2.03m2= 1.90m× 2.14m× 1/2
P5 1.81m2= 1.90m× 1.90m× 1/2 water pressure P1 45.77 0.80 36.62
Earth pressure; Pe 1.28m2= 1.60m× 1.60m× 1/2 P2 12.54 0.53 6.65
Uplift; U1 8.21m2= 3.80m× (2.72m+ 1.60m) × 1/2 P3 26.66 0.67 17.86
U2 3.61m2= 3.80m× 1.90m× 1/2 P4 19.89 3.09 61.46
P5 -17.74 0.63 -11.18
(2)Distance
External force Distance
Dead load; W1 1.00m= 2.00m× 1/2 Earth pressure Pe 4.72 0.53 2.50
W2 2.60m= 2.00m+ 1.80m× 1/3 Uplift U1 -32.18 1.27 -40.87
Static water P1 0.80m= 1.60m× 1/2 U2 -14.15 2.53 -35.80
pressure; P2 0.53m= 1.60m× 1/3 Total 106.94 162.36 45.29 34.59
208
P3 0.67m= 2.00m× 1/3
P4 3.09m= 1.66m+ 2.14m× 2/3
P5 0.63m= 1.90m× 1/3
Earth pressure; Pe 0.53m= 1.60m× 1/3
Uplift; U1 1.27m= 3.80m× 1/3 He
U2 2.53m= 3.80m× 2/3 P3↓
Hd
B2 B1
(3)External force by unit width
External force
lf EExternal force by unit width
lf b i id h Hdd
Dead load; W1 73.60kN= 3.20m2× 23.00kN/m2 P1←
W2 33.12kN= 1.44m2× 23.00kN/m2 P4↓
Hw
Technical Guideline for Design of Headworks
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
②Stability analysis (The case of dry)
1.Basic calculation 2.Calculation table
(1 )Area (unit width)
External force Area Vertical Distance Resistance Horizontal Distance Turning
Dead load; W1 3.20m2= 2.00m× 1.60m force moment force moment
W2 1.44m2= 1.80m× 1.60m× 1/2 V(kN) x(m) V*x(kN・m) H(kN) y(m) H*y(kN・m)
Static water P1 Dead load W1 73.60 1.00 73.60
pressure; P2 1.28m2= 1.60m× 1.60m× 1/2 W2 33.12 2.60 86.11
P3
P4
P5 water pressure P1 0.00 0.00 0.00
Earth pressure; Pe 1.28m2= 1.60m× 1.60m× 1/2 P2 12.54 0.53 6.65
Uplift; U1 3.04m2= 3.80m× 1.60m × 1/2 P3 0.00 0.00 0.00
U2 P4 0.00 0.00 0.00
P5 0.00 0.00 0.00
(2)Distance
Distance
Dead load; W1 1.00m= 2.00m× 1/2 Earth pressure Pe 4.72 0.53 2.50
W2 2.60m= 2.00m+ 1.80m× 1/3 Uplift U1 -11.92 1.27 -15.14
Static water P1 U2 0.00 0.00 0.00
pressure; P2 0.53m= 1.60m× 1/3 Seismic load S1
P3 S2
P4
209
P5 Total B1 94.80 144.57 17.26 9.15
B2
Earth pressure; Pe 0.53m= 1.60m× 1/3
Uplift; U1 1.27m= 3.80m× 1/3
U2
Seismic load S1
Hw
S2
↓w2 ↓w1
(3)External force by unit width Pe← P2←
External force External force by unit width
Dead load; W1 73.60kN= 3.20m2× 23.00kN/m2
Technical Guideline for Design of Headworks
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
Seismic load S1
S2
③Stability analysis (the case of earthquick )
1.Basic calculation 2.Calculation table
(1 )Area (unit width)
External force Area Vertical DistanceResistance Horizontal Distance Turning
Dead load; W1 3.20m2= 2.00m× 1.60m force moment force moment
W2 1.44m2= 1.80m× 1.60m× 1/2 V(kN) x(m) V*x(kN・m) H(kN) y(m) H*y(kN・m)
Static water P1 Dead load W1 73.60 1.00 73.60
pressure; P2 1.28m2= 1.60m× 1.60m× 1/2 W2 33.12 2.60 86.11
P3
P4
P5 water pressure P1 0.00 0.00 0.00
Earth pressure; Pe 1.28m2= 1.60m× 1.60m× 1/2 P2 12.54 0.53 6.65
Uplift; U1 3.04m2= 3.80m× 1.60m × 1/2 P3 0.00 0.00 0.00
U2 P4 0.00 0.00 0.00
P5 0.00 0.00 0.00
(2)Distance
External force Distance
Dead load; W1 1.00m= 2.00m× 1/2 Earth pressure Pe 4.72 0.53 2.50
W2 2.60m= 2.00m+ 1.80m× 1/3 Uplift U1 -11.92 1.27 -15.14
Static water P1 U2 0.00 0.00 0.00
pressure; P2 0.53m= 1.60m× 1/3 Seismic load S1 11.04 0.80 8.83
P3 S2 4.97 0.53 2.63
P4
P5 Total 94.80 144.57 33.27 20.61
210
Earth pressure; Pe 0.53m= 1.60m× 1/3
Uplift; U1 1.27m= 3.80m× 1/3
U2
Seismic load S1 0.80m= 1.60m× 1/2
S2 0 53m=
0.53m= 1 60m×
1.60m× 1/3
B2 B1
(3)External force by unit width
External force External force by unit width
Dead load; W1 73.60kN= 3.20m2× 23.00kN/m2
W2 33.12kN= 1.44m2× 23.00kN/m2
←s1
Technical Guideline for Design of Headworks
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
S2 4.97kN= 33.12kN× 0.15
Excel format guide 6. HW Stability Analysis (Summary)
【Case2 : Hdownstream > Hw】
#Please input data into yellow cell
1.Basic data for calculation
Item Value Reference
Unit weight of plane concrete γc= 23 kN/m3 Reinforced concrete: 24.5KN/m3, Plain concrete: 23KN/m3, Cement mortar: 21KN/m3
3
Unit weight of wet soil γwse= 18 kN/m
3
Unit weight of water W0= 9.8 kN/m
Unit weight of submerged soil γwe= 8.2 kN/m3(γwse-w0)
Coefficient of earth pressure C0= 0.45
Uplift coefficient μ= 0.4 Rock foundation case or a case using sheet piles reaching an impermeable stratum: 0.4, Otherwise: 1.0
Seismic horizontal acceleration kh= 0.15
Friction coefficient f= 0.7 0.7‐0.75
Allowable stress of the graund qa= 1000 kN/m2 Bedrock=1000KN/m2 See 3.2.4
211
Hd 2.72 m (Without uplift) ΣV/B・(1-6e/B)<qa 33kN/m2 < 1,000kN/m2 OK 14kN/m2 < 1,000kN/m2 OK 19kN/m2 < 1,000kN/m2 OK
Hdownstream 1.90 m
He 2.92 m
He
Hd
B2 B1
Technical Guideline for Design of Headworks
Hdownstream
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
【Case2 : Hdownstream > Hw】
①Stability analysis (The case of dynamic)
212
P3 0.67m= 2.00m× 1/3
P4 3.20m= 2.00m+ 1.80m× 2/3
P5 0.53m= 1.60m× 1/3
Earth pressure; Pe 0.53m= 1.60m× 1/3
Uplift; U1 1.27m= 3.80m× 1/3
U2 2.53m= 3.80m× 2/3 He
P1←
Static water P1 45.77kN= 4.67m2× 9.80kN/m2 Hdownstream
pressure; P2 12.54kN= 1.28m2× 9.80kN/m2 Hw
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
【Case2 : Hdownstream > Hw】
②Stability analysis (The case of static)
213
P3 S2
P4
P5 Total 94.80 144.57 17.26 9.15
Earth pressure; Pe 0.53m= 1.60m× 1/3
Uplift; U1 1.27m= 3.80m× 1/3
U2
Seismic load S1
S2 B1
B2
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
Uplift; U1 -11.92kN= 3.04m2× -9.80kN/m2 ×0.4
U2
Seismic load S1
S2
【Case2 : Hdownstream > Hw】
③Stability analysis (the case of earthquick )
214
P3 S2 4.97 0.53 2.63
P4
P5 Total 94.80 144.57 33.27 20.61
Earth pressure; Pe 0.53m= 1.60m× 1/3
Uplift; U1 1.27m= 3.80m× 1/3
U2
Seismic load S1 0.80m= 1.60m× 1/2
S2 0.53m= 1.60m× 1/3 B2 B1
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
Uplift; U1 -11.92kN= 3.04m2× -9.80kN/m2 ×0.4
U2
Seismic load S1 11.04kN= 73.60kN× 0.15
S2 4.97kN= 33.12kN× 0.15
Technical Guideline for Design of Headworks
L1 = 0.6C√D1
= 0.6 × 9 × √1.6 = 6.83m ≈ 13.0m (After calculate creep length, L1 is to
be 13.0m finally)
215
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1.6m 2.0m
1.9m ΔH2 = 1.6m
Point A Point B
3.8m 13.0m
0.35m
2.5m 1.7m
2.15m
0.8m
From the result of (a) and (b), the length of apron and cut-off are OK.
216
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Hf value adopts the smallest one from the result of calculation for safety.
So, Hf = 0.79m
Hf value adopts the smallest one from the result of calculation for safety.
So, Hf = 2.34m
217
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
218
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
⊿Z
(1) Calculation of water depth at the weir toe as design flood discharge
….. (See 3.2.3(5)1)(a))
2 2
Vc V
⊿Z+hc= 1a h1a
2g 2g
Where, Qd = 106m3/s ………. (From 5.2.3)
W = 12.5m ……….…. (From 5.2.5)
⊿Z = h = 1.6m …….. (From 5.2.5)
219
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
220
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
221
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Example;
Based on geological data, this weir foundation selects spread foundation
because there is hard rock (hard brown Ignimbrite rock) at proposed
headworks site excavated around 0.5m to 1.5m from the surface.
This gate will be opened during rainy season, so the upstream water height
of gate assumes height of gate plus half of design flood height for safety.
Hupstream = 1.6m + 2.72m/2 = 1.6 + 1.36 = 2.96m
222
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1) Calculation of κ
2) Calculation of B and H
1/ 2
Q2
B h 2
h
kh 2
Where, h = 0.6m (Assumption value)
Q = 0.063m3/s (From 5.2.1)
α = 1.2
∴ B = ( 0.62 + 1.2 × 0.0632 / (0.0126 × 0.62) )1/2 – 0.6 = 0.59m ≈ 0.6m
223
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
2) Empirical formula
L 20 Q = 20 × √ 0.063 = 5.02m
The result of calculation 1) and 2), the length of sedimentation ditch adopts
8.4m
In the place of headworks, if there is low elevation land than design flood
level (EL. 2424.82m), it is necessary to protect this part from flood.
This part is protected by gabion starting from EL.2423.4m (Stable bank. The
depth of foot protection from O.G.L is 0.5m.) to EL.2424.82 (Design flood
level) + 0.5~0.6m (freeboard) which is equal to EL.2425.4m. For the length
of 10m, bottom width is 1.0m and thickness is 0.5m.
EL.2425.4m
O.G.L EL.2423.9m
Stable bank (hard rock) 0.5m EL.2423.4m
1.0m
224
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
The height of the guide wall H required to form a channel for the scouring
sluice is made 1.5hc at the point of intake.
H=1.5 × hc=1.5 × 1.02 > 1.5m
225
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1=S++1.5Hs
Where S=0.7m, =0.4m, Hs=1.5m
1 = 0.7+0.4+1.5 × 1.5 = 3.35 (m)
The upstream length of scouring sluice is 1 = 3.35m on calculation,
1 = 3.7m is adopted as design length.
The elevation at point EL2 of the inflow of the scouring sluice in principle
should be almost the same as the existing riverbed elevation. The average
river slope is 0.029.
- The friction velocity at the limit of average grain size transportation (UXc)
UXc2 = 80.9dm = 80.9 × 15 (cm/sec)2 = 1213.5 (cm/sec)2
- The water depth at the limit of average grain size transportation (hsc)
hsc = UXc 2/ gi = 1213.5 / ( 980 × 0.029) = 42.7cm = 0.43m
- The discharge per unit width for the limit of average grain size
transportation (qsc)
h = (q2/gFr2)1/3
∴ q = Fr × g1/2 × h3/2
∴ qsc = Fr × g1/2 × hsc3/2 = 1.27 × 9.81/2 × 0.433/2 = 1.12 m3/s/m
226
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
- The river discharge at the limit of average grain size transportation (Qs)
Qs = qsc × B = 1.12 × 12.5 = 14 m3/s
Where, River width B = 12.5m
In case of wider cannel width, required discharge can be increased and the
sand flushing capacity is declined.
When the width is smaller than a half of its length, from the viewpoint of
sand flushing function of the scouring sluice, the direction of the flow can be
controlled more easily. And also the width of scouring sluice is decided
based on the applicable size of skin plate shown in 3.2.7(4). From these
viewpoints, the width of scouring sluice is adopted to 1.0m. (See 5.3.6)
n2 g n 2 ghc 3 8.25 10 2 d m
hc1 / 3 hm10 / 3 hm
In assuming the water depth at the downstream end of the supercritical flow
canal h and then value of the canal, following table can be obtained. Refer to
Excel format guide 8 for the details.
Example;
Test calculation table of water depth
h hm n2・g n2・g・hc3 8.25 10 -2 dm
10/3
(m) h c1 3 < hm < hm
From the above table, the water depth at the downstream end of the
scouring sluice channel h becomes h = 1.0m to give a value of grain size
larger than that with maximum grain size in the sediment to be flushed,
taking into account the energy loss due to sediment transportation and the
roughness coefficient n = 0.018.
227
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
1 h c3 n 2・g・h c 3
i h+ 2 -1.5hc +
2h h m 10 3
= 1/3.7 (1.0 + 1.073 /2 × 1.02 - 1.5 × 1.07) + 0.0182 × 9.8 × 1.073 /1.03510/3
= 0.0055 = 1/182
228
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
<Formula>
n2g/hc1/3 < n2ghc3/hm10/3 < 8.25*10-2dm/hm
n= 0.018
2
g= 9.8 m/s
hc = 1.07 m
hm = (hc+h)/2 m
dm = 0.15 m
229
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
2.Test calculation of upstream slope
1 = 3.7 m
h = 1m
hm = 1.035
= 0.005501175 = 1/182
3.Confirming a calculation
<Formula>
Q = B*h* I 1/2 * (Bh/(B+2h))2/3 / n
n = 0.015
Q = 3.46 m3/s
B = 1m
I = 0.0297
de = 0.5 m
↓ Goal seek ("By changing cell")
h = 1.21 m > 0.5 OK
The result of calculation
3.460 ← Goal seek ("set cell". "to value" = Q value)
230
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
231
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
After select [Goal Seek], it can be selected “Set cell” which is having formula.
Then enter a figure into “To value” which is target value.
Finally it can be selected “By changing cell” which is a cell to change figure
to get target value. This cell’s figure is an assumption value at first.
After those three cells are set on Goal Seek and click on OK, Excel calculates
to find target value by itself and show that value under “By changing cell”.
There is some guidance about “Set cell”, “To value” and “By changing cell” in
Excel format guide on this manual as follows.
232
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
<Example>
In this case above,
“Set cell” is a ⑥ cell (blue color cell) which is having formula about the
calculation of Design head,
“To value” is 0 because the formula about the calculation of Design head
should be close to zero as much as possible,
“By changing cell” is ⑤ cell (green cell). This cell’s figure is an assumption
value at first.
After those three cells are set on Goal Seek and click on OK, the value of “By
changing cell” is shown most proper value (target value) to be close to zero
as the answer of formula about the calculation of Design head automatically.
233
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
References
234
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
List of Authors
Name of Guidelines and Manuals Name Field Affiliation
Ministry of
Water resources
Mr. Nobuhiko Suzuki Agriculture, Forestry
Guideline for Irrigation Master planning
and Fisheries
Plan Study Preparation
on Surface Water Resources
Mr. Roba Muhyedin Irrigation Engineer OIDA Head Office
LANDTEC JAPAN,
Manual for Runoff Analysis Mr. Yasukazu Kobayashi Runoff Analysis
Inc.
(Agronomy and Soil Part) Mr. Abdeta Nate'a Agronomist OIDA Head Office
235
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
236
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
237
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
238
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
239
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
Amhara Agriculture
Mr. Assefa Zeleke Economist
Bureau
Metaferia Consulting
Mr. Getu Getoraw Irrigation Engineer
Engineers
Metaferia Consulting
Mr. Hassen Bahru Sociologist
Engineers
Metaferia Consulting
Ms. Nitsuh Seifu Irrigation Engineer
Engineers
Remarks: Office Name is shown when he/she works for CBID project.
240
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
List of Editors
Name of Guidelines and Manuals Name Field Affiliation
241
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Technical Guideline for Design of Headworks
List of Coordinators
Name Field Affiliation
242
Japan International Cooperation Agency (JICA) & Oromia Irrigation Development Authority (OIDA)
The Project for Capacity Building in Irrigation Development (CBID)
Contact Person