MASTER SCHEDULE

PRECAST PLANT MARGOREJO

ID Task Name Duration Start Finish ProgressPredecessors 1st Half


November 2020 December 2020 January 2021
01/11 15/11 29/11 13/12 27/12 10/01
1 1 PEMBANGUNAN PABRIK PRECAST MARGOREJO 190 days Sat 07/11/20 Sun 16/05/21 12%
2 1.1 Milestone 110 days Tue 26/01/21 Sun 16/05/21 0%
3 1.1.1 Galian pondasi batcing plant selesai 0 days Tue 26/01/21 Tue 26/01/21 0% 17
4 1.1.2 Erection silo mulai 0 days Tue 09/02/21 Tue 09/02/21 0% 38SS
5 1.1.3 Batching plant siap produksi 0 days Sat 06/03/21 Sat 06/03/21 0% 49
6 1.1.4 Jalan akses utama selesai 0 days Sun 14/02/21 Sun 14/02/21 0% 63
7 1.1.5 Pekerjaan pemancangan mini pile dimulai 0 days Thu 28/01/21 Thu 28/01/21 0% 79SS
8 1.1.6 Erection kolom shelter baja dimulai 0 days Thu 25/02/21 Thu 25/02/21 0% 103SS
9 1.1.7 Rigid plant selesai 0 days Wed 03/03/21Wed 03/03/21 0% 93
10 1.1.8 Instalasi/erection portal gantry crane line tahap 1 selesai 0 days Sat 03/04/21 Sat 03/04/21 0% 101
11 1.1.9 Instalasi/erection portal gantry crane tahap 2 selesai 0 days Sun 09/05/21 Sun 09/05/21 0% 140
12 1.1.10 Siap produksi 0 days Sun 16/05/21 Sun 16/05/21 0% 11FS+7 days
13 1.2 ZONA 1 (BATCHING PLANT) 119 days Sat 07/11/20 Sat 06/03/21 43%
14 1.2.1 Earth work 85 days Sat 07/11/20 Sun 31/01/21 55%
15 1.2.1.1 Clearing dan stripping 7 days Sat 07/11/20 Fri 13/11/20 100%
16 1.2.1.2 Cut & fill 21 days Wed 16/12/20 Wed 06/01/21 100% 15
17 1.2.1.3 Galian pondasi batcing plant 7 days Wed 20/01/21 Tue 26/01/21 0% 16
18 1.2.1.4 Pondasi kontainer 3 days Tue 08/12/20 Sat 09/01/21 10% 16
19 1.2.1.5 Pekerjaan rigid batching plant 7 days Thu 07/01/21 Wed 13/01/21 0% 16
20 1.2.1.6 Pekerjaan dinding penahan hopper (CCSP sd capping7beam) days Tue 12/01/21 Mon 18/01/21 0% 16
21 1.2.1.7 Pekerjaan stock material split & pasir 12 days Thu 07/01/21 Mon 18/01/21 83% 16
22 1.2.1.8 Pekerjaan pondasi jembatan timbang 7 days Mon 25/01/21 Sun 31/01/21 0% 16
23 1.2.1.9 Pekerjaan pos 2 days Thu 07/01/21 Fri 08/01/21 100% 16
24 1.2.2 Pembesian dan pengecoran 13 days Wed 27/01/21 Mon 08/02/21 0%
25 1.2.2.1 Bekisting, pembesian, dan pengecoran tahap 1 7 days Wed 27/01/21 Tue 02/02/21 0% 17
(sumuran dan pile cap)
26 1.2.2.2 Bekisting, pembesian, dan pengecoran tahap 2 3 days Wed Fri 05/02/21 0% 17;25
(pedestal dan slab atas) 03/02/21
27 1.2.2.3 Setting angkur, base plate dan grouting 3 days Sat 06/02/21 Mon 08/02/21 0% 26
28 1.2.3 Pekerjaan pagar, pos, drainase dan kantor 66 days Tue 01/12/20 Fri 05/02/21 59%
29 1.2.3.1 Pekerjaan pagar 50 days Tue 01/12/20 Wed 20/01/21 80%
30 1.2.3.2 Pekerjaan drainase 3 days Thu 28/01/21 Sat 30/01/21 0% 16
31 1.2.3.3 Pekerjaan pos 2 days Mon 25/01/21 Tue 26/01/21 0% 23
32 1.2.3.4 Erecton container 1 day Sat 30/01/21 Sat 30/01/21 0% 16
33 1.2.3.5 Pekerjaan sanitasi, dan MEP 3 days Sun 31/01/21 Tue 02/02/21 0% 16;32
34 1.2.3.6 Pekerjaan kolam pengolahan air limbah beton 3 days Wed 03/02/21Fri 05/02/21 0% 16;33
35 1.2.3.7 Gedung kantor batching plant 3 days Sun 31/01/21 Tue 02/02/21 0% 16;32
36 1.2.3.8 Gedung laboraturium & test beton 3 days Wed 03/02/21Fri 05/02/21 0% 16;18;35
37 1.2.4 Erection dan instalasi batching plant 9 days Tue 09/02/21 Wed 17/02/21 0%
38 1.2.4.1 Silo 3 days Tue 09/02/21 Thu 11/02/21 0% 27

Task Project Summary Manual Task Start-only Deadline Manual Progress


Project: Det Split Inactive Task Duration-only Finish-only Critical
Date: Mon Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress

Note : This Schedule base on Milestone of Final Design Drawing of Precast Element Document has been received by Supplier
MASTER SCHEDULE
PRECAST PLANT MARGOREJO

ID Task Name Duration Start Finish ProgressPredecessors 1st Half


November 2020 December 2020 January 2021
01/11 15/11 29/11 13/12 27/12 10/01
39 1.2.4.2 Pan mixer 2 days Fri 12/02/21 Sat 13/02/21 0% 38
40 1.2.4.3 Cabin 2 days Sun 14/02/21 Mon 15/02/21 0% 39
41 1.2.4.4 Hopper 2 days Tue 16/02/21 Wed 17/02/21 0% 40
42 1.2.5 Mekanikal elektrikal dan plumbing 17 days Thu 18/02/21 Sat 06/03/21 0%
43 1.2.5.1 Pekerjaan penyambungan daya PLN 3 days Thu 18/02/21 Sat 20/02/21 0% 41
44 1.2.5.2 Pekerjaan instalasi listrik batching plant 7 days Sun 21/02/21 Sat 27/02/21 0% 43
45 1.2.5.3 Instalasi Jaringan Air Bersih 7 days Sun 21/02/21 Sat 27/02/21 0%
46 1.2.5.3.1 Test geolistrik 2 days Sun 21/02/21 Mon 22/02/21 0% 17;43
47 1.2.5.3.2 Pengeboran sumur dalam (air bersih 3 liter/detik)2 days Tue 23/02/21 Wed 24/02/21 0% 46
48 1.2.5.3.3 Instalasi jaringan air bersih 3 days Thu 25/02/21 Sat 27/02/21 0% 47
49 1.2.5.4 Commisioning 7 days Sun 28/02/21 Sat 06/03/21 0% 44;48
50 1.3 ZONA 2 (JALUR AKSES) 73 days Tue 08/12/20 Fri 19/02/21 17%
51 1.3.1 Earth work 61 days Tue 08/12/20 Sun 07/02/21 25%
52 1.3.1.1 Clearing dan stripping 7 days Tue 08/12/20 Mon 14/12/20 100%
53 1.3.1.2 Cut & fill 21 days Fri 08/01/21 Thu 28/01/21 11% 52
54 1.3.1.3 Galian pondasi & pekerjaan pasangan batu 7 days Fri 29/01/21 Thu 04/02/21 0% 53
55 1.3.1.4 Galian pondasi drainase (box culvert) 7 days Mon 11/01/21 Sun 17/01/21 100% 53
56 1.3.1.5 Timbunan base & replace tanah dasar 4 days Fri 29/01/21 Mon 01/02/21 0% 53
57 1.3.1.6 Pekerjaan pemancangan sheet pile (CCSP) 10 days Fri 29/01/21 Sun 07/02/21 0% 53
58 1.3.1.7 Pekerjaan pagar pintu gerbang 7 days Fri 29/01/21 Thu 04/02/21 0% 52;53
59 1.3.1.8 Pekerjaan pos 2 days Tue 02/02/21 Wed 03/02/21 0% 56
60 1.3.2 Pembesian dan pengecoran 14 days Mon 01/02/21 Sun 14/02/21 0%
61 1.3.2.1 Pekerjaan pengecoran capping beam 9 days Mon 01/02/21 Tue 09/02/21 0% 57FS-7 days
62 1.3.2.2 Pengecoran lean concrete 2 days Mon 08/02/21 Tue 09/02/21 0% 56FS+1 day;57
63 1.3.2.3 Bekisting, pembesian, dan pengecoran rigid 5 days Wed 10/02/21 Sun 14/02/21 0% 62
64 1.3.3 Pekerjaan pagar, pos, dan pintu gerbang 22 days Fri 29/01/21 Fri 19/02/21 0%
65 1.3.3.1 Pekerjaan pagar 7 days Fri 29/01/21 Thu 04/02/21 0% 53
66 1.3.3.2 Pekerjaan pintu gerbang 5 days Mon 15/02/21 Fri 19/02/21 0% 63
67 1.3.3.3 Pekerjaan pos 2 days Thu 04/02/21 Fri 05/02/21 0% 59
68 1.4 ZONA 3 (SHELTER/PRODUKSI & STOCKYARD) 156 days Fri 04/12/20 Sun 09/05/21 4%
69 1.4.1 Earth work 78 days Fri 04/12/20 Sat 20/02/21 13%
70 1.4.1.1 Clearing dan stripping 14 days Fri 04/12/20 Thu 17/12/20 100%
71 1.4.1.2 Cut & fill 21 days Thu 07/01/21 Wed 27/01/21 30% 70
72 1.4.1.3 Pekerjaan galian saluran terbuka (utama, & memanjang) 7 days Thu 28/01/21 Wed 03/02/21 0% 71
73 1.4.1.4 Pekerjaan galian saluran cross (utama, & melintang) 7 days Thu 28/01/21 Wed 03/02/21 0% 71
74 1.4.1.5 Pekerjaan galian saluran terbuka (sekunder) 7 days Thu 28/01/21 Wed 03/02/21 0% 71
75 1.4.1.6 Pekerjaan box culvert 7 days Thu 28/01/21 Wed 03/02/21 0% 71
76 1.4.1.7 Pekerjaan repalce dan base tanah dasar 5 days Mon 25/01/21 Fri 29/01/21 0% 71FS-3 days
77 1.4.1.8 Pekerjaan pancang mini pile shelter 14 days Wed 27/01/21 Tue 09/02/21 0% 71FS-1 day
78 1.4.1.9 Pekerjaan galian pondasi lantai & sloof shelter 7 days Wed 10/02/21 Tue 16/02/21 0% 77

Task Project Summary Manual Task Start-only Deadline Manual Progress


Project: Det Split Inactive Task Duration-only Finish-only Critical
Date: Mon Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress

Note : This Schedule base on Milestone of Final Design Drawing of Precast Element Document has been received by Supplier
MASTER SCHEDULE
PRECAST PLANT MARGOREJO

ID Task Name Duration Start Finish ProgressPredecessors 1st Half


November 2020 December 2020 January 2021
01/11 15/11 29/11 13/12 27/12 10/01
79 1.4.1.10 Pekerjaan pondasi mini/spun pile portal gantry & trolley
23 days Thu 28/01/21 Fri 19/02/21 0% 71
80 1.4.1.11 Pekerjaan timbunan batu pecah stockyard & base jalan 3 days
akses Thu 28/01/21 Sat 30/01/21 0% 71
81 1.4.1.12 Pekerjaan beton sleeper 3 days Sun 31/01/21 Tue 02/02/21 0% 80
82 1.4.1.13 Pekerjaan base jalan desa baru 3 days Thu 28/01/21 Sat 30/01/21 0% 71
83 1.4.1.14 Pekerjaan galian tiang kabel tray gantry 7 days Thu 28/01/21 Wed 03/02/21 0% 71
84 1.4.1.15 Pekerjaan galian pile cap 24 days Thu 28/01/21 Sat 20/02/21 0% 79FS-23 days
85 1.4.2 Pekerjaan struktur (pengecoran) 33 days Sat 30/01/21 Wed 03/03/21 0%
86 1.4.2.1 Pekerjaan rigid jalan desa 7 days Sun 31/01/21 Sat 06/02/21 0% 82
87 1.4.2.2 Pekerjaan pile cap shelter 24 days Sat 30/01/21 Mon 22/02/21 0% 84FS-22 days
88 1.4.2.3 Pekerjaan pile cap portal gantry & trolley 24 days Mon 01/02/21 Wed 24/02/21 0% 84FS-20 days
89 1.4.2.4 Pekerjaan kolom pedestal 24 days Mon 01/02/21 Wed 24/02/21 0% 87SS+2 days
90 1.4.2.5 Pekerjaan sloof shelter 24 days Thu 04/02/21 Sat 27/02/21 0% 78FS-13 days
91 1.4.2.6 Pekerjaan sloof IWF portal gantry & trolley 24 days Thu 04/02/21 Sat 27/02/21 0% 88SS+3 days
92 1.4.2.7 Pekerjaan tiang kabel tray gantry 7 days Thu 04/02/21 Wed 10/02/21 0% 83
93 1.4.2.8 Pekerjaan lantai shelter 26 days Sat 06/02/21 Wed 03/03/21 0% 78FS-11 days
94 1.4.2.9 Rigid jalur akses 7 days Sun 31/01/21 Sat 06/02/21 0% 80
95 1.4.3 Erection dan instalasi 70 days Sun 31/01/21 Sat 10/04/21 0%
96 1.4.3.1 Instalasi panel listrik 7 days Sun 31/01/21 Sat 06/02/21 0% 80
97 1.4.3.2 Instalasi kabel listrik 7 days Sun 31/01/21 Sat 06/02/21 0% 80
98 1.4.3.3 Instalasi/grouting rel & embeded plate portal gantry & 14trolley
days Sun 28/02/21 Sat 13/03/21 0% 91
99 1.4.3.4 Instalasi tiang power portal gantry 7 days Thu 11/02/21 Wed 17/02/21 0% 92
100 1.4.3.5 Instalasi kabel power portal gantry 7 days Wed 10/02/21 Tue 16/02/21 0% 77
101 1.4.3.6 Instalasi/erection portal gantry crane Kap. 80 ton (4 unit)
21 days Sun 14/03/21 Sat 03/04/21 0% 98;100
102 1.4.3.7 Instalasi/erection portal gantry crane Kap. 15 ton (2 unit)
14 days Sun 14/03/21 Sat 27/03/21 0% 98;100
103 1.4.3.8 Erection kolom shelter baja 7 days Thu 25/02/21 Wed 03/03/21 0% 89
104 1.4.3.9 Erection rafter shelter 7 days Thu 04/03/21 Wed 10/03/21 0% 103
105 1.4.3.10 Erection gording shelter 3 days Thu 11/03/21 Sat 13/03/21 0% 104
106 1.4.3.11 Pekerjaan atap shelter 7 days Sun 14/03/21 Sat 20/03/21 0% 105
107 1.4.3.12 Pekerjaan plumbing 7 days Sun 21/03/21 Sat 27/03/21 0% 106
108 1.4.3.13 Instalasi lampu penerangan shelter 7 days Sun 28/03/21 Sat 03/04/21 0% 107
109 1.4.3.14 Instalasi lampu penerangan stock yard 7 days Sun 04/04/21 Sat 10/04/21 0% 108
110 1.4.3.15 Instalasi Jaringan Air Bersih 9 days Sun 31/01/21 Mon 08/02/21 0%
111 1.4.3.15.1 Test geolistrik 3 days Sun 31/01/21 Tue 02/02/21 0% 80
112 1.4.3.15.2 Pengeboran sumur dalam (air bersih 3 liter/detik)3 days Wed 03/02/21Fri 05/02/21 0% 111
113 1.4.3.15.3 Instalasi jaringan air bersih 3 days Sat 06/02/21 Mon 08/02/21 0% 112
114 1.4.4 ZONA 4 (STOCKYARD) 154 days Sun 06/12/20 Sun 09/05/21 6%
115 1.4.4.1 Earth work 84 days Sun 06/12/20 Sun 28/02/21 13%
116 1.4.4.1.1 Clearing dan stripping 14 days Sun 06/12/20 Sat 19/12/20 100%
117 1.4.4.1.2 Cut & fill 21 days Mon 18/01/21 Sun 07/02/21 0% 116
118 1.4.4.1.3 Pekerjaan galian saluran terbuka (utama, & memanjang)
7 days Mon 08/02/21 Sun 14/02/21 0% 117

Task Project Summary Manual Task Start-only Deadline Manual Progress


Project: Det Split Inactive Task Duration-only Finish-only Critical
Date: Mon Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress

Note : This Schedule base on Milestone of Final Design Drawing of Precast Element Document has been received by Supplier
MASTER SCHEDULE
PRECAST PLANT MARGOREJO

ID Task Name Duration Start Finish ProgressPredecessors 1st Half


November 2020 December 2020 January 2021
01/11 15/11 29/11 13/12 27/12 10/01
119 1.4.4.1.4 Pekerjaan galian saluran cross (utama, & melintang)7 days Mon 08/02/21 Sun 14/02/21 0% 117
120 1.4.4.1.5 Pekerjaan galian saluran terbuka (sekunder) 7 days Mon 08/02/21 Sun 14/02/21 0% 117
121 1.4.4.1.6 Pekerjaan box culvert 7 days Mon 08/02/21 Sun 14/02/21 0% 117
122 1.4.4.1.7 Galian pondasi & pekerjaan pasangan batu 7 days Mon 08/02/21 Sun 14/02/21 0% 117
123 1.4.4.1.8 Pekerjaan pondasi mini pile portal gantry & trolley21 days Mon 08/02/21 Sun 28/02/21 0% 117
124 1.4.4.1.9 Pekerjaan timbunan batu pecah stockyard & base3jalan daysaksesMon 08/02/21 Wed 10/02/21 0% 117
125 1.4.4.1.10 Pekerjaan beton sleeper 3 days Thu 11/02/21 Sat 13/02/21 0% 124
126 1.4.4.1.11 Pekerjaan base jalan desa baru 3 days Mon 08/02/21 Wed 10/02/21 0% 117
127 1.4.4.1.12 Pekerjaan galian tiang kabel tray gantry 7 days Mon 08/02/21 Sun 14/02/21 0% 117
128 1.4.4.2 Pekerjaan struktur (pengecoran) 53 days Thu 11/02/21 Sun 04/04/21 0%
129 1.4.4.2.1 Pekerjaan rigid jalan desa 7 days Thu 11/02/21 Wed 17/02/21 0% 126
130 1.4.4.2.2 Pekerjaan pilecap portal gantry & trolley 21 days Mon 01/03/21 Sun 21/03/21 0% 123
131 1.4.4.2.3 Pekerjaan sloof IWF portal gantry & trolley 14 days Mon 22/03/21 Sun 04/04/21 0% 130
132 1.4.4.2.4 Pekerjaan tiang kabel tray gantry 7 days Mon 15/02/21 Sun 21/02/21 0% 127
133 1.4.4.2.5 Rigid jalur akses 7 days Thu 11/02/21 Wed 17/02/21 0% 124
134 1.4.4.3 Erection dan instalasi 88 days Thu 11/02/21 Sun 09/05/21 0%
135 1.4.4.3.1 Instalasi panel listrik 7 days Thu 11/02/21 Wed 17/02/21 0% 124
136 1.4.4.3.2 Instalasi kabel listrik 7 days Thu 11/02/21 Wed 17/02/21 0% 124
137 1.4.4.3.3 Instalasi/grouting rel & embeded plate portal gantry
14 days
& trolley
Mon 05/04/21Sun 18/04/21 0% 131
138 1.4.4.3.4 Instalasi tiang power portal gantry 7 days Mon 22/02/21 Sun 28/02/21 0% 132
139 1.4.4.3.5 Instalasi kabel power portal gantry 7 days Mon 01/03/21 Sun 07/03/21 0% 138
140 1.4.4.3.6 Instalasi/erection portal gantry crane Kap. 80 ton 21
(4 days
unit) Mon 19/04/21 Sun 09/05/21 0% 137;139
141 1.4.4.3.7 Pekerjaan plumbing 7 days Thu 11/02/21 Wed 17/02/21 0% 124
142 1.4.4.3.8 Instalasi lampu penerangan stock yard 7 days Thu 18/02/21 Wed 24/02/21 0% 136
143 1.4.5 ZONA 5 (OFFICE) 48 days Mon 08/02/21Sat 27/03/21 0%
144 1.4.5.1 Earth work 20 days Mon 08/02/21Sat 27/02/21 0%
145 1.4.5.1.1 Clearing dan stripping 7 days Mon 08/02/21 Sun 14/02/21 0%
146 1.4.5.1.2 Cut & fill 7 days Mon 15/02/21 Sun 21/02/21 0% 145
147 1.4.5.1.3 Pekerjaan galian saluran terbuka (utama, & memanjang)
3 days Mon 22/02/21 Wed 24/02/21 0% 146
148 1.4.5.1.4 Pekerjaan galian saluran cross (utama, & melintang)3 days Mon 22/02/21 Wed 24/02/21 0% 146
149 1.4.5.1.5 Pekerjaan galian saluran terbuka (sekunder) 3 days Mon 22/02/21 Wed 24/02/21 0% 146
150 1.4.5.1.6 Pekerjaan box culvert 3 days Mon 22/02/21 Wed 24/02/21 0% 146
151 1.4.5.1.7 Galian pondasi & pekerjaan pasangan batu 3 days Thu 25/02/21 Sat 27/02/21 0% 150
152 1.4.5.1.8 Pondasi kontainer 3 days Mon 22/02/21 Wed 24/02/21 0% 146
153 1.4.5.2 Pekerjaan Bangunan Pendukung 31 days Thu 25/02/21 Sat 27/03/21 0%
154 1.4.5.2.1 Erection container office 7 days Thu 25/02/21 Wed 03/03/21 0% 152
155 1.4.5.2.2 Pekerjaan modifikasi knock down office 24 days Thu 04/03/21 Sat 27/03/21 0% 154
156 1.4.5.2.3 Pekerjaan fasilitas gudang pabrik 21 days Thu 25/02/21 Wed 17/03/21 0% 152
157 1.4.5.2.4 Pekerjaan fasilitas work shop pabrik 28 days Thu 25/02/21 Wed 24/03/21 0% 152
158 1.4.5.2.5 Pekerjaan toilet pekerja 7 days Thu 25/02/21 Wed 03/03/21 0% 152

Task Project Summary Manual Task Start-only Deadline Manual Progress


Project: Det Split Inactive Task Duration-only Finish-only Critical
Date: Mon Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress

Note : This Schedule base on Milestone of Final Design Drawing of Precast Element Document has been received by Supplier
MASTER SCHEDULE
PRECAST PLANT MARGOREJO

ID Task Name Duration Start Finish ProgressPredecessors 1st Half


November 2020 December 2020 January 2021
01/11 15/11 29/11 13/12 27/12 10/01
159 1.4.5.2.6 Pekerjaan MEP 14 days Thu 04/03/21 Wed 17/03/21 0% 154

Task Project Summary Manual Task Start-only Deadline Manual Progress


Project: Det Split Inactive Task Duration-only Finish-only Critical
Date: Mon Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress

Note : This Schedule base on Milestone of Final Design Drawing of Precast Element Document has been received by Supplier