COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS, CULVERTS AND MINOR BRIDGES

RCC BOX CELL BRIDGE OF SIZE : 4 cell x 5.00 M x 5.00 M

Item
Sl No Description of Items Unit Quantity Rate Amount
No.
1 2 4 9 8 9 10
1 11.1 Earthwork in excavation for structures as per drawing
and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and cum 659.35 102.00 Rs.67,253.70
disposal upto a lead of 50 m, dressing of sides and
bottom and backfilling in trenches with excavated
suitable material. I Ordinary soil Upto 3 m depth
2 11.2 Fillling in foundation trenches as per drawing and
cum 45.954 1,411.80 Rs.64,877.86
technical specification Clause 305.3.9 I Sand filling
3 11.4 Providing concrete for plain/reinforced concrete in
open foundations complete as per drawings and
technical specifications Clause 802, 803, 1202 & 1203 cum 21.366 5,389.30 Rs.1,15,147.78
B. With Natural Gravel III P.C.C Grade M 20
Nominal mix 1:2:4 (Hand mixed)
4 11.4 Providing concrete for plain/reinforced concrete in
open foundations complete as per drawings and
cum 31.815 5,648.90 Rs.1,79,719.75
technical specifications Clause 802, 803, 1202 & 1203
B. With Natural Gravel IV R.C.C. M 20
5 11.7 Supplying, fitting and placing HYSD bar reinforcement
in foundation complete as per drawings and technical t 0.853 54,969.90 Rs.46,889.32
specifications Clauses 1000 and 1202
6 12.5 Plain/reinforced cement concrete in substructure
complete as per drawings and technical specification
Clauses 802, 804, 805, 806, 807, 1202 ans 1204 B. cum 237.95 6,417.00 Rs.15,26,925.15
With Natural Gravel IV R.C.C.Grade M 25
I)Height upto 5M
7 12.6 Supplying, fitting and placing TMT(Fe-500D) bar
reinforcement (Fe 415) in substructrue complete as per
t 17.907 55,091.00 Rs.9,86,514.54
drawings and technical specification Clauses 1002,
1005, 1010 & 1202
8 12.9 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return
wall with 100 mm dia AC pipe extending through the
Nos. 64 117.70 Rs.7,532.80
full width of the structures with slope of 1(V):20(H)
towards drawing face complete as per drawing and
technical specification Clauses 614, 709, 1204.3.7
9 12.10 Backfilling behind abutment, wing wall and return wall
complete as per drawings & technical specification cum 107.64 1,280.40 Rs.1,37,822.26
Clause 1204.3.8 I Granular material
10 13.5 Providing and laying cement concrete wearing course
M 30 grade including reinforcement complete as per
cum 10.989 11,952.30 Rs.1,31,343.82
drawing and technical specifications Clauses 800 and
1206.3 B With Natural Gravel
11 13.6 Construction of R.C.C. railing of M 25 grade in cast-in-
situ with 20 mm nominal size aggregate, true to line
and grade, tolerance of vertical railing post not to Runnin
56.4 2,397.00 Rs.1,35,190.80
exceed 1 in 500, centre-to-centre spacing between g m
vertical posts not to exceed 2000 mm as per drawing
and technical specifications Clauses 800, 900 and
12 13.10 Drainage spouts complete as per drawing and technical
Nos. 8 1,640.90 Rs.13,127.20
specifications Clause 1209

1
Box Cul._5x55x0
RCC BOX CELL BRIDGE OF SIZE : 4 cell x 5.00 M x 5.00 M

Item
Sl No Description of Items Unit Quantity Rate Amount
No.
1 2 4 9 8 9 10
13 14.9 Providing and laying curtain walls complete as per
drawing and technical specification Clause 1304 iii cum 55.53 4,955.80 Rs.2,75,195.57
Cement concrete grade M 10
14 14.10 Construction of flexible apron 1 m thick comprising of
loose stone boulders weighing not less then 25 kg cum 250.2 1,831.20 Rs.4,58,166.24
beyond curtain wall
TOTAL = Rs.40,78,453.09