Professional Documents
Culture Documents
Project
PROVIDENCE
CHRISTIAN COLLEGE
PRIMARY SCHOOL
STAGE 1
Issue
TENDER
Date
11 JANUARY 2021
Project No.
19.06
SPECIFICATION OF WORKS TO BE PERFORMED AND MATERIAL TO BE USED
for
at
Prepared by:
brad@quartermaine.com.au
CONTRACT PRELIMINARIES
Document No Document Name No of Pages
00200 INFORMATION FOR TENDERERS 1 - 4
00210 GENERAL CONDITIONS OF TENDERING 1 - 2
00230 EXISTING CONDITIONS AT SITE 1 - 1
00300 TENDER FORM 1 - 1
00301 ROCK EXCAVATION SCHEDULE OF RATES & QUANTITIES 1 - 1
00301 TENDER SUM BREAKDOWN 1 - 1
00500 INSTRUMENT OF AGREEMENT 1 - 1
00610 PERFORMANCE BOND 1 - 1
00650 CERTIFICATES OF INSURANCE 1 - 1
00800 SUPPLEMENTARY CONDITIONS OF CONTRACT 1 - 8
00819 OHS & ENVIRONMENTAL REQUIREMENTS 1 - 1
00860 DRAWINGS 1 - 3
00870 SCHEDULES & TABLES 1 - 2
PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL STAGE 1 Page 1 of 2 SECTION 00110 TABLE OF CONTENTS
SECTION 00110 TABLE OF CONTENTS
PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL STAGE 1 Page 2 of 2 SECTION 00110 TABLE OF CONTENTS
00200 INFORMATION FOR TENDERERS
1. The Project
Construction of a new Primary School and associated external works and services.
2. The Contract
Fixed lump sum not subject to rise and fall.
AS 2124 1992 General conditions of contract.
3. Tenders
The proprietor reserves the right to reject the lowest or any tender or an otherwise conforming tender.
Comply with AS 4120 1994 Code of tendering.
4. Tender Documents
Available without fee from the architect.
5. Alternative Proposals
Submit tenders in accordance with the tender documents.
Alternatives may be considered but only where all performance aspects of each item comply with the one
specified and verification of compliance with the relevant Australian Standards must be submitted in writing.
Alternatives will only be considered where a conforming tender is submitted.
7. Schedule
Submit a Preliminary Construction Program indicating commencement and completion dates.
8. Tender Enquiries
All enquiries during the tender period should be directed to:
Brad Quartermaine: Email brad@quartermaine.com.au, Phone: 0417 931 941
The Contractor shall nominate the electrical and hydraulics sub-contractors selected to undertake those
sections of the work within their Tender submission. Failure to nominate the selected Sub-Contractors within
the Tender submission will deem the Tender non-conforming
10. Consultants
For this project, the proprietor has appointed the following Consultants:
The law applicable is that of the State or Territory of: Western Australia
(Clause 1)
Payments under the Contract shall be made at: Perth W.A. - by way of “Electronic Funds Transfer to
(Clause 1) the account nominated by the Contractor/Principal
The time for lodgement of the priced copy of the Bill Not Applicable
of Quantities:
(Clause 4.2)
Contractor shall provide security in the amount of: 5% of the Contract Sum in lieu of retention moneys.
(Clause 5.2)
The percentage to which the entitlement to security 50% (i.e. one of the Banker’s undertakings shall be
and retention moneys is reduced: returned)
(Clause 5.7)
Work which cannot be subcontracted without Work under the Contract that is carried out by
approval: (Clause 9.2) Subcontractors, suppliers or other parties nominated
by the Principal or Superintendent.
Providence Christian College Primary School Stage 1 Page 2 of 25 00200 INFORMATION FOR TENDERERS
The amount or percentage for profit and attendance: 0%
(Clause 11(c))
The assessment for insurance purposes of the costs 5 % of the Contract Sum
of demolition and removal of debris:
(Clause 18(ii))
The time for giving possession of the Site: Within 7 days of the date on which the Building Permit
(Clause 27.1) is issued.
The date for Practical Completion: 44 weeks from the giving of possession of the Site,
(Clause 35.2) inclusive of industry RDO/PDO and public holiday
allowances.
Times for Payment Claims: On the last Working day of the month
(Clause 42.1)
The rate of interest on overdue payments: Supreme Court rates as at the date of Acceptance of
(Clause 42.9) the Tender
The person to nominate an arbitrator: The President for the time being of the Institute of
(Clause 47.3 Arbitrators) & Mediators Australia – Western
Australian Chapter
Providence Christian College Primary School Stage 1 Page 3 of 25 00200 INFORMATION FOR TENDERERS
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 4 of 25 00200 INFORMATION FOR TENDERERS
00210 GENERAL CONDITIONS OF TENDERING
1. Tender Form
Refer Document 00300 "TENDER FORM".
2. Tender Documents
The tender documents include the "The Conditions" or "The Agreement" or "General Conditions of Contract",
tender form, and specification, drawings, schedules and any other documents issued by the architect for the
purpose of tendering (available at point of issue of documents). No explanation or amendment to the tender
documents will be recognised unless in the form of written addendum issued by the architect.
5. Submission of Tender
A. Submit tender only on the form provided, Document 00300 TENDER FORM.
B. Include an address for service of notices for the purpose of this tender and subsequent contact.
C. Sign the tender form, or if the tenderer is a corporation or company, sign the tender with company seal.
D. The tender shall be for the whole of the work described in the tender documents.
E. Do not alter or add to tender documents except as required by these General Conditions of Tendering.
6. Lodgement of Tenders
A. Tender to be placed in a sealed envelope, marked with the name of the project, and lodged in the
tender box at, (or sent by pre-paid post to) the architect’s/proprietor’s office:
by the date and time of closing of tenders. See "C" below.
B. Notwithstanding sub-clause A, faxed, emailed, telegraphic or telexed tenders received by the date and
time for closing of tenders may be admitted for consideration, subject to the concurrent submission of a
written tender. Oral tenders will not be received.
C. Tenders Close 2:30pm on 16th February 2021.
8. Trade Names
Trade or proprietary names, brands, catalogue or reference numbers are specified in the tender documents. A
successful tenderer may offer material or equipment of similar characteristics or type, quality, appearance,
finish, method or construction and performance, after the Letter of Acceptance of tender has been issued,
unless otherwise noted in the specification trade sections.
9. Customs Duties
The tender shall include customs duty and other similar charges applicable to imported materials, plant and
equipment required for work described in the tender documents.
Information pertaining to items B to H are not required to be submitted with the tender. This information will be
requested after the closing of tenders from the tenderer(s) under consideration.
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 6 of 25 00210 GENERAL CONDITIONS OF TENDERING
00230 EXISTING CONDITIONS AT SITE
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 7 of 25 00230 EXISTING CONDITIONS AT SITE
00300 TENDER FORM
Construction Program. Tenderer to submit a Preliminary Construction Program for the works.
working days inclusive of
COMPANY SEAL
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 8 of 25 00300 TENDER FORM
00301 TENDER SUM BREAKDOWN FORM
Total $
GST $
Total Price $
Providence Christian College Primary School Stage 1 Page 9 of 25 00301 TENDER SUM BREAKDOWN FORM
00500 INSTRUMENT OF AGREEMENT
Other documents:
COMPANY SEAL
Signed by the principal
COMPANY SEAL
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 10 of 25 00500 INSTRUMENT OF AGREEMENT
00610 PERFORMANCE BOND
for and on behalf of the principal that the principal desires payment to be made of the whole or any part or parts of the
sum, it is unconditionally agreed that the financial institution will make the payment or payments to the principal forthwith
without reference to the contractor and notwithstanding any notice given by the contractor not to pay same.
Provided always that the financial institution may at any time without being required so to do pay to the principal the sum
of
$ ( )
less any amount or amounts it may previously have paid under this undertaking or such lesser sum as may be required
and specified by the principal and thereupon the liability of the financial institution hereunder will immediately cease.
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 11 of 25 00610 PERFORMANCE BOND
00650 CERTIFICATES OF INSURANCE
Submit each certificate to the principal via the architect before commencement of work.
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 12 of 25 00650 CERTIFICATES OF INSURANCE
00800 SUPPLEMENTARY CONDITIONS OF CONTRACT
Annexure Part B to General Conditions of Contract
The Clauses set out below (the Supplementary Conditions of Contract) have been added to those of AS
2124—1992 and/or have been amended and differ from the corresponding Clauses in AS 2124-1992. If there
is any inconsistency between the General Conditions of Contract and this Annexure Part B, this Annexure Part
B prevails to the extent of any inconsistency.
3. Interpretation of Drawings
Check dimensions on site, certified by a qualified land surveyor, before proceeding with the work of the
contract. Survey needs to be confirmed by a qualified surveyor and checked at specific intervals during the
construction period. Notify architect of omission or conflict in drawings and their relation to specifications.
6. Indemnity of Principal
A. Indemnify, and keep indemnified the principal against claim, demand, action, suit or proceeding that
may be brought or made against the principal by any other person who has entered into a contract with
the principal to execute work associated with the project.
B. Submit evidence of such insurance in respect of loss, damage or expense incurred by that other person
by reason of an act, default or neglect of the builder in the performance of his obligations under the
contract or arising out of or as a consequence of delay by the builder in executing or failing to complete
work under the contract and also from costs and expenses that may be incurred by that other person in
connection with such claim, demand, action, suit or proceeding.
C. Do not proceed with work under the contract until evidence of licencing, indemnities and insurances
required herein, is submitted in writing to the architect.
8. Site Control
A. Existing buildings will remain in occupation throughout the duration of the works. Ensure that the work is
carried out without damage to and with a minimum of nuisance or annoyance to the occupants of the
existing building and adjacent premises. Prevent weather and dust ingress into the existing building for
the duration of the works. Make good any weather damage incurred to the existing building. The
Proprietor’s use of the existing building and adjacent premises as a school must not be negatively
affected in any way. Safe access and egress from occupied premises is to be maintained at all times.
B. Erect approved site safety fence, barriers and hoardings to enclose the works and to protect the
occupants of adjoining occupied premises, and to prevent weather ingress where required. Exact
position of safety fences etc shall be to the approval of the Architect. Use all types and methods of
protection (such as temporary safety fencing and warning signage) that are reasonably practicable and
necessary to protect the public from hazards associated with the work under the Contract. Protection
shall be consistent with the recommendations contained in the WorkSafe WA publication “Construction
Providence Christian College Primary School Stage 1 Page 13 of 25 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT
Work and the Public”. Where a safety fence is used, it shall be not less than 1.8 metres in height, fully
secured for its entire length with visual barrier screens and lateral stays to stabilise the fence against
wind forces.
C. Be responsible for activities on the site including providing access for authorised persons and restricting
access by unauthorised persons. Take necessary precautions to secure the assets of the principal.
D. Be responsible for providing controls to protect workers, working at height, in confined space, in
excavations and trenches, using hazardous substances/chemicals and other tasks and activities
identified by legislation or contained in the builders hazard and risk register, maintained at the project,
that may create a risk to the occupational health and safety of workers and other persons at or near the
workplace.
E. Except as otherwise provided in the contract, delivery of materials for the works, space for storage of
same and for building sheds, office and workshops will be allowed only as directed by the builder. Do
not store waste building materials and flammable liquids in the building.
F. Take proper precautions to keep hazardous chemicals/substances, poisons and other injurious
substances in places secured against access by unauthorised persons, properly labelled and not stored
in food containers or drinking vessels.
G. Confirm that the site is not in an area affected by vermin, noxious pests, e.g. fire ants, termites etc Refer
to relevant authority for guidance.
H. Delivery of materials for the works shall not take place between 7:30am-8:30am and 2:30pm-4pm on
school days.
9. Noise Control
Take adequate measures to control noise on the site and comply with the following requirements.
No operation shall be carried out on the site if it causes the sound emitted (as determined by the sound level at
the site boundary by the Architect) to exceed:
Time of day Sound level in Decibels (A)
Monday to Friday
7.00 am to 7.00pm 80
Saturday and Sunday
7.00 am to 7.00pm 70
Evening
7.00 am to 10.00pm 65
Night
10.00 pm to 7.00 am 55
No appliance shall be used if the noise emitted by the appliance exceeds the following maximum sound levels
measured at any point 7 metres ±200mm from:
The surface of the appliance excepting those items indicated which shall have sound levels measured at the
building site boundary. measurements shall be made in accordance with AS.1217 (methods of measurement of
airborne sound emitted by machines), or where applicable for pneumatic driven appliances, the measurement
procedures set out in the cagi-pneurop test code for the measurement of sound from pneumatic machines
1969 may be used.
- Group (I) 70 decibels (A) max.: Air compressors up to 170 litres/sec capacity.
- Group (ii) 75 decibels (A) max.: Internal combustion or electrically driven equipment up to 14kw N.E.P.
(20hp) (mobile or stationary), construction dumpers up to 1 cu metre capacity, fluid pumps, air
compressors above 170 litres/sec capacity.
- Group (iii) 80 decibels (A) max.: Vibratory compactors, internal concrete vibrators, concrete saws (mobile
and stationary), internal combustion or electrically driven equipment over 14kw N.E.P. (2Ohp) (mobile or
stationary), earth moving equipment up to and including engine capacities of 100kw N.E.P. (lSOhp),
concrete pumps, concrete agitators, portable air or electric tools, public address system (at boundary),
cranes (at boundary).
- Group (iv) 85 decibels (A) max.: Air or electric impulsive tools, scabblers, impact wrenches, explosive
power tools, earth moving equipment of engine capacity between 100kw and 200kw N.E.P. (lSOhp and
300hp), refuse chutes (at boundary).
- Group (V) 90 decibels (A) max.: Sirens - warning (at boundary), pile drivers (at boundary), earth moving
equipment of engine capacity above 200kw N.E.P. (300hp).
For the purpose of this clause:
- Appliance means any apparatus, equipment or machine used for or in connection with the building site and
includes motor vehicles and earth moving machinery.
- Sound level emitted from the building site boundary means the sound level exceeded for 10% of the time
(110), measured in decibels (A) and evaluated over hourly intervals during the period of time specified in
the “time of day and sound level table” above.
- Maximum sound level emitted by an appliance means the sound level in decibels (A) exceeded for 1% of
the measurement period.
- Sound level decibels (A) shall be measured with a sound level meter complying with the specifications set
out in AS.1259 part 1 or AS.1259 part 2, with the microphone oriented in a direction indicating the
maximum sound level.
- means net engine power determined in accordance with Australian design rule no. 28, motor vehicle noise,
dated July 1972.
- Where no means of performing a particular function is available other than by a means which will produce
sound levels in excess of those requirements specified above, the Contractor shall obtain permission from
the Architect to perform such operations on the days and within the hours approved by the Architect.
Providence Christian College Primary School Stage 1 Page 14 of 25 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT
The Architect may require the Contractor to produce a certificate of acoustic performance issued by a
laboratory registered with the N.A.T.A. for any appliance before permitting its use, or continued use, on the
building site.
On occasions for emergency reasons, the Architect may direct that all noise on the site ceases or be reduced.
the Contractor shall direct all its sub-Contractors on site to meet the requirements.
The applicable Department of Education policy requires that all persons working on occupied school premises
be screened for previous convictions for certain types of offences. The Contractor shall screen all employees,
sub-contractors, suppliers and other persons entering the building site for previous criminal convictions by
ensuring that they:
are the holder of a federal police criminal record check that is no more than 2 years old;
or
have completed a “Confidential Declaration” form contained in Appendix B. A person need only complete a
“Confidential Declaration” form once for entry to the school in relation to this contract.
The Contractor shall maintain a register of employees, sub-contractors, suppliers and other persons accessing
the Contractor’s site. On a weekly basis, the Contractor shall provide to the school principal the following
information:
- A list of persons who have entered the site, sorted by:
- Those with a federal police certificate;
- Those who have already provided a “Confidential Declaration” form to the school;
- Those who have completed a “Confidential Declaration” form for the Contractor.
- A copy of all federal police criminal record certificates and “Confidential Declaration” forms provided to the
Contractor.
Once the Contractor ceases to maintain a controlled building site, or where the nature of the work makes a
controlled site impractical, all access to the school/site shall be through the school office.
The Contractor shall cooperate with the school principal to maintain effective control of access to school
premises and site throughout the contract period.
Providence Christian College Primary School Stage 1 Page 15 of 25 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT
13. Compliance with Ordinances, etc.
Comply throughout with the requirements of relevant sections of the National Construction Code (NCC).
Whenever work or type of plant or machinery, etc. is required either by the specification or by the relevant
statutory authority, provide full details of such work, plant, etc. to the relevant statutory authority and make such
applications, etc. as may be required within 2 weeks of receipt of Letter of Acceptance.
In such cases, approval given by the architect to data submitted by the builder will not necessarily imply that
such data meet the requirements of the relevant statutory authority.
18. Water
Provide potable drinking water and adequate signage if relevant to identify same, and maintain a temporary
water supply sufficient for executing the work under the contract. Disconnect and clear away same on
completion and pay costs and charges in connection therewith. Provide tapping of main supply if required.
29. Dimensioning
Do not scale drawings which are clearly diagrammatic and/or marked 'not to scale' or NTS.
Providence Christian College Primary School Stage 1 Page 17 of 25 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT
I. Do not order, manufacture, assemble or supply any item or component needed according to
requirements of Shop Drawings until the architect returns the applicable stamped drawings.
J. The builder is to provide as built drawings and details of all installed in-ground services, including type,
location and depth, referenced against known data or reference points so as to prevent unintended
contractor damage during future excavation works.
39. Warranties
Provide written warranties as set out in the relevant trade specification sections.
42. Asbestos
No asbestos products or asbestos based materials are to be used in any part or parts of this building or its
services and the builder is to ensure that sub-contractors, nominated sub-contractors, suppliers and others are
advised of this restriction.
Instead of granting an extension of time for any such delay the Architect shall issue to the builder a notice
reducing the provisional period by the amount of the extension of time which would otherwise have been
granted, provided that if and when the provisional period is thereby reduced to nil, any further such delay shall
be cause for extensions of time for Practical Completion of the Works, and provided further that if the
provisional period is not thereby reduced to nil by the time the Works shave reached practical completion, the
Date of Practical Completion shall not be altered in consequence thereof.
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 20 of 25 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT
00819 OHS & ENVIRONMENTAL REQUIREMENTS
1. Compliance
Prepare an Occupational Health, Safety and Environmental Management Plan for the works that complies, as a
minimum, with statutory and other legal requirements of the locality the works are to be undertaken in, including
all licensing, permits, fees, charges, etc. relevant to the works they will undertake
Develop a “Hazard and Risk Register” for the construction phase of the project and:
• Include all hazards/risks they have identified as possible, during the conduct of the construction
phase, and
• Rate each hazard/risk level. Where the risk is greater than a first aid injury or minor illness…
• Identify and include specific controls to reduce the risk so the consequence is minor injury or illness
and …
• Re-assess the risk after the introduction of the control so as to ensure the selected control will be
effective in preventing identified injury or illness in the relevant hazard/risk identified and…
• Identify and document how the hazards and risks, as identified, will be monitored and reviewed, and
the frequency of such monitoring and review, during the conduct of the works on the project
Include, where applicable the following hazard categories and associated risks as a minimum in the “Hazard
and Risk Register”:
• Working at height and at same level.
• Working in excavations and trenches.
• Working on or near essential services, including electricity, gas, telecommunications, water, sewer
etc.
• Delivery, storage, decanting, use and disposal of a hazardous chemical/substance.
• Delivery, unloading/loading, servicing, maintenance use and repair of plant.
• Using a confined space.
• Activities generating excessive noise, manual and materials handling risks.
• Asbestos and demolition works.
• Other categories of hazards, as included in the relevant Occupational Health, Safety and
Environmental Act, Regulation, Policy, Code of Practice, Australian Standard etc.
Prepare “Safe Work Method Statements (SWMS)”, or equivalent, so as to control identified hazards and risks
documented in the “Hazard and Risk Register”, in consultation with workers, or providing training to workers, in
the way they will undertake the work, so as to prevent injury or illness during the conduct of the works. Controls
will include the requirements of any Regulation, or where no regulation exists, controls to be equal to or better
than a Code of Practice, Australian Standard, Ministerial Notice, statutory or industry alert, relevant to the
identified hazard and risk,
Provide supervision, training and instruction, as relevant, to all affected workers on the project, so as to ensure
that during the conduct of the works the potential for injury or illness, as identified in the “Hazard and Risk
Register”, and documented in “Safe Work Method Statement” is minimised to an acceptable level.
At the completion of the project, provide a copy of all identified and unresolved hazards and risks that remain to
be controlled by the end user or end user servicing, maintenance or repair personnel, so that they are not put
at risk by the completed project.
2. Submissions
Develop and submit, prior to commencing work on the project, a copy of the contractors:
• Occupational Health Safety and Environmental Management plan, and
• Hazard and Risk Register, and
• Safe Work Method Statement.
Document, and make available as necessary:
• The intended training, supervision, induction and inspection processes and procedures to be
undertaken on the project and …
• The notification of all Incidents occurring at the project, including reporting, investigation, findings and
corrective actions and …
• Any occupational health, safety and environmental visitation, prosecution or consultation, including any
recommendations or finding provided by external parties to the project.
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 21 of 25 00819 OHS & ENVIRONMENTAL REQUIREMENTS
00860 DRAWINGS
ARCHITECTURAL
Number Name Revision No.
A101 Site Demolition Plan 0
A102 Site Plan 0
A103 Piazza Plan 0
A104 Balcony Plan 0
A201 GA Part Ground Floor Plan A Block 0
A202 GA Part Ground Floor Plan B Block 0
A203 GA Part Upper Floor Plan A Block 0
A204 GA Part Upper Floor Plan B Block 0
A211 Setout Plan – Part Ground Floor A Block 0
A212 Setout Plan – Part Ground Floor B Block 0
A213 Setout Plan – Part Upper Floor A Block 0
A214 Setout Plan – Part Ground Floor B Block 0
A241 Verandah Roof Plan 0
A242 Main Roof Plan 0
A301 Elevations – Block A 0
A302 Elevations – Block B 0
A303 Screening Details 0
A401 Sections 0
A402 Sections 0
A403 Sections 0
A411 Sectional Details 0
A412 Sectional Details 0
A413 Sectional Details 0
A441 Stair Details 0
A442 Stair Details 0
A501 Reflected Ceiling Plan – Ground Floor 0
A502 Reflected Ceiling Plan – Upper Floor 0
A601 Room Layouts 0
A602 Room Layouts 0
A603 Room Layouts 0
A604 Room Layouts 0
A605 Room Layouts 0
A606 Room Layouts 0
A607 Room Layouts 0
A608 Room Layout Details 0
A701 Door and Window Schedule 0
A702 Door and Window Schedule 0
A703 Door and Window Schedule 0
CIVIL
Number Name Revision No.
C01 Civil General Notes 0
C20 Bulk Earthworks 0
C30 Site Levels 0
C35 Line Marking 0
C40 Standard Details Road 0
STRUCTURAL
Number Name Revision No.
S 1001 General Notes Sheet 1 0
S 1002 General Notes Sheet 2 0
S 1003 General Notes Sheet 3 0
S 1101 Footing Plan Block A Sheet 1 0
S 1102 Footing Plan Block B Sheet 2 0
S 1110 Footing Details General Sheet 1 0
S 1111 Footing Details General Sheet 2 0
S 1121 Ground Steel Plan Block A Sheet 1 0
S 1122 Ground Steel Plan Block B Sheet 2 0
S 1125 Secondary Steelwork Plans & Details 0
S 1201 First Floor Plan Block A – Sheet 1 0
S 1202 First Floor Plan Block B – Sheet 2 0
S 1210 First Floor Plan Bottom Reinforcement Block A – Sheet 1 0
S 1211 First Floor Plan Bottom Reinforcement Block B – Sheet 2 0
S 1214 First Floor Plan Top Reinforcement Block A – Sheet 1 0
HYDRAULICS
Number Name Revision No.
H 01 Site Plan - Drain, Water & Fire 0
H 02 Part Site Plan / Ground Floor Plan- Drain, Water & Fire 0
H 03 Ground Floor Plan - Drain 0
H 04 First Floor Plan - Drain 0
H 05 Ground Floor Plan - Water 0
H 06 First Floor Plan - Water 0
H 07 Typical Details 0
ELECTRICAL
Number Name Revision No.
DE 000 Cover Page 0
DE 001 Legend 0
DE 002 Luminaire & Direct Connection Schedule 0
DE 003 Details 0
DE 004 Existing Site Plan Forward Works 0
DE 005 Site Plan 0
DE 006 Carpark Lighting Layout 0
DE 007 Ground Floor Power Layout 0
DE 008 Ground Floor Lighting Layout 0
DE 009 First Floor Power Layout 0
DE 010 First Floor Lighting Layout 0
DE 011 Ground Floor Cable Tray Layout 0
DE 012 SMSB & BMSB Single Line Diagram 0
DE 013 DB1 Single Line Diagram 0
DE 014 Communications Schematics 0
MECHANICAL
Number Name Revision No.
M 000 Cover Page 0
M 001 Ground Floor Plan 0
M 002 First Floor Plan 0
M 003 Legend & Details 0
LANDSCAPE
Number Name Revision No.
L 3.101 Levels Works Drawing 0
L 4.101 Hard Works Drawing 0
L 5.101 Soft Works Drawing 0
L 7.101 General Details Drawing 0
FEATURE SURVEY
Number Name Revision No.
F01 (6 Sheets) Feature survey 1.0
END OF DOCUMENT
Provisional Sums
Contingency
Definitions are quotes from (Standards Australia “Glossary of Building Terms”) SAA HB 50.
Providence Christian College Primary School Stage 1 Page 24 of 25 00870 SCHEDULES AND TABLES
B. Slab penetrations for floor mounted GPOs, telephone outlets, etc.
C. Chasing and making good for conduit access for skirting wiring duct, GPOs, switches etc.
D. Supply and installation of access openings where required.
E. Provision of electrical and telephone riser cupboards and floor penetrations.
F. Provision of sign writing to Main Switchroom, Distribution Board and telephone cupboards, etc.
G. Provision of openings for luminaires to sizes required by the electrician.
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 25 of 25 00870 SCHEDULES AND TABLES
SECTION 02210 Civil Works
1 SURVEY SETOUT
2 TESTING
2.1 GENERAL
- It is the contractor’s responsibility to provide all materials for the completion of this project and to
provide verification that all materials comply with the requirements of the contract documents.
- In addition it is the contractors responsibility to undertake all necessary testing of subgrade,
subbase, basecourse and, asphalt to ensure conformance with this specification for compaction,
moisture content, level, dryness, shape, finish etc. The costs for all testing shall be at the
Contractor's expense.
- All compaction testing shall be undertaken by an approved, independent NATA registered testing
laboratory in accordance with A.S. 1289.1.4.1.
Providence Christian College Primary School Stage 1 Page 1 of 14 SECTION 02210 CIVIL WORKS
SECTION 02210 Civil Works
2.2 STANDARDS
The work shall comply with relevant current Australian Standards including but not limited to the
following:
Comply with particular specifications in building regulations and/or local council publications.
Providence Christian College Primary School Stage 1 Page 2 of 14 SECTION 02210 CIVIL WORKS
SECTION 02210 Civil Works
Table 2.3 Material Testing - Compaction Performance Criteria - To Pavements & Structures
Material Material Type Method Minimum Frequency - area per portion (2)
Definition Density
Subgrade Sand PSP - to 95% SMDD >1000m2 1 test per
A.S. 500m2 or
1289.6.3.3 (1) three per
portion
500-1000m2 1 test per
500m2 or
Clay / Clayey NDT - to A.S. 98% MMDD three per
1289.5.2.1 portion
<500m2 2 tests per
500m2 or
three per
portion
Sub-base Limestone NDT - to A.S. 95% MMDD 1 test per 500m2 or three per
1289.5.2.1 portion
Road Base Crushed Rock NDT - to A.S. 98% MMDD 1 test per 500m2 or three per
1289.5.2.1 portion
- Density shall be measured in situ by use of a nuclear moisture/density meter in accordance with
Test Method AS 1289.5.2.1-2003. All measurements shall be made using the direct transmission
Providence Christian College Primary School Stage 1 Page 3 of 14 SECTION 02210 CIVIL WORKS
SECTION 02210 Civil Works
mode. The cost of all testing for direct transmission testing methods shall be borne by the
contractor. Indirect density tests using correlations will not be accepted.
- The nuclear moisture/density meter can be calibrated for the range of density 1.3 t/m³ to 3.05 t/m³.
- If the in situ density is outside the range of densities for which the nuclear moisture/density meter
has been calibrated the "Sand Replacement Method" shall be used.
- For the purpose of conformance judgement of subgrade, and basecourse, the in situ density shall
be expressed as a percentage of the maximum dry density.
- The maximum dry density shall be determined by the appropriate Australian Standard method.
Density - Asphalt
Density shall be calculated on the basis of the results of tests of core samples of asphalt randomly
sampled form the pavement, after laying and compaction, in accordance with AS 2891 “Methods of
Sampling and Testing Asphalt” with MRD Test Methods 731.1 "Stability and Flow of Asphalt”.
Moisture Content
The moisture content shall be determined using the appropriate Australian Standard method.
Remedial Works
- The Contractor shall be responsible for patching holes made during earthworks, subgrade or
pavement testing.
- The test holes shall be backfilled immediately after sampling or testing by the person who made the
holes. Backfilled material shall have similar properties and shall be compacted at or near optimum
moisture content to densities matching the surrounding material.
2.4 CONSTRUCTION TOLERANCES
The surface of all unpaved areas, roadways, subgrade, and embankments constructed or disturbed by
the Contractor shall be graded to a smooth surface. The slope of batters shall not exceed the
specified slope. The finished surfaces of earthworks shall be accurate within the tolerances set out in
the Table below.
All earthworks shall be final graded to the underside of the pavement stage including, but not limited
to:
- evenly graded changes between design levels and existing ground levels;
- smoothly finished surface, no ruts or disturbances;
3 AS-CONSTRUCTED
- Records for all underground works shall show the location of the item referenced from the boundary
or road centre line as applicable with chainage and offset at all changes of direction and 20m
maximum centres on straights.
- "As Constructed" detail shall be at cross sections to coincide with cross sections, chainages and all
offsets on the approved drawings at 20m intervals.
- Final As-Constructed information shall be provided in accordance with the General Requirements
work sections. Additionally, as-constructed locations of all kerbing and centrelines shall be
accurately located by a licensed surveyor. A digital copy of the as-constructed location shall be
provided to the Architect in Autocad dwg and pdf formats for client records.
- Under no circumstance will payment be made for works which have not received the Architects
approval of the "As Constructed" information.
4 ROADWORKS
Providence Christian College Primary School Stage 1 Page 5 of 14 SECTION 02210 CIVIL WORKS
SECTION 02210 Civil Works
75 mm 100
19 mm 50 - 75
- No limestone shall be placed until the subgrade has been approved by the Superintendent.
- The limestone rubble shall be placed so that the subgrade is not disturbed and broken up.
Limestone shall not be spread upon a water logged subgrade. If at any time the subgrade material
becomes mixed with the limestone sub-base, the Contractor at his own cost shall remove the
mixture and reshape with clean limestone.
- The sub-base shall be worked in compacted layers not greater than 250mm nor less than 100mm.
- The limestone shall be compacted by rolling and watering to a firm, even and unyielding surface to
the satisfaction of the Architect.
- Where in the opinion of the Architect, damage to adjoining properties may result, the use of vibrating
rollers will not be permitted.
- The finished surface shall be tested by template to ensure accuracy within tolerance of design levels
per table 2.4
4.4 CRUSHED ROCK BASE COURSE
- The base course material shall be diorite or granite fine crushed rock from an approved source.
The compacted thickness of the base course shall be as shown in the drawings.
- The crushed rock shall comply with the following requirements when sampled and tested in
accordance with AS 1141 and AS 1289.
- Percentage of wear by Los Angeles test not more than 45%.
AS Sieve Size % Passing By Weight
19 mm 100
9.5 mm 70 - 80
4.75 mm 40 - 65
2.36 mm 30 - 50
0.425 mm 12 - 30
0.075 mm 3 - 12
- The ratio of the portion passing 0.075 mm sieve to the portion passing 0.425 mm sieve shall fall
within the range of 40 60%.
- The portion retained on the 0.425 mm sieve shall conform to the following:
. Linear shrinkage not greater than 1%
. Lower liquid limit not greater than 25
. Plasticity index not greater than 5.
. Dry compressive strength not less than 1.75 MPa.
- No rock base shall be placed until the sub base has been approved by the Architect.
- The fine crushed rock shall be maintained at optimum moisture content, within a tolerance of + 2%
(two per cent) until spreading and compaction is completed, additional water being added as
necessary during rolling.
- The road base shall be worked in compacted layers not greater than 250mm nor less than 100mm.
- Materials shall be spread without segregation of large or fine particles. Segregated materials shall
be re mixed by harrowing and blading or, if ordered by the Superintendent, they shall be cast to
waste.
- Fine crushed rock shall not be spread upon a waterlogged sub base. If at any time the sub base
material should become churned up or mixed with the pavement, the contractor shall, without
additional compensation, remove the mixture and re shape with clean material, which shall be
satisfactorily compacted uniformly with the surrounding surface.
Providence Christian College Primary School Stage 1 Page 6 of 14 SECTION 02210 CIVIL WORKS
SECTION 02210 Civil Works
- The finished surface shall be tested by template to ensure accuracy within tolerance of design levels
per table 2.4.
4.5 PRIMING OF PAVEMENT
- No surface shall be primed until the finished base course has been approved by the
Superintendent.
- A short time before the priming is to be commenced, the surface shall be finished by light watering,
planing and rolling with multi wheeled, pneumatic tyred rollers.
- The mulch which forms on the surface shall be removed from the pavement by light grading and
brooming to provide a surface free from loose stones, dirt and foreign matter. At this stage, the
pavement shall be dry, or at most, only slightly damp and the surface pores free from water down to
a depth of 12 mm.
- The pavement shall be primed with a medium curing cut back bitumen containing at least 70% by
volume bitumen. The rate of application shall be not less than 1.20 litres/m2 measured at 15°C. The
spraying temperature shall be between 70°C and 120°C.
- Alternatively, a bitumen emulsion prime containing at least 60% by volume bitumen may be used,
subject to the Architect's approval. The rate of application shall be not less than 1.36 litres/m2
measured at 15°C.
- The method of application shall be in accordance with standard practice adopted by Main Roads
WA.
- The primed spray shall be blinded after spraying.
- For cutback prime, sand or 1.5 mm aggregate shall be applied after penetration of the primer but
while sufficient bitumen is on the surface to allow adhesion.
- For emulsion prime, 5 mm granite aggregate shall be evenly applied at a rate of 100 square metres
coverage per cubic metre. The surface shall be rolled until the aggregate is firmly embedded in the
primer.
- On no account shall the bituminous concrete material be placed on a section of the primed base
course until such section has been inspected and approved by the Architect. A minimum of 72 hours
after application of the primer shall elapse in all cases.
4.6 WEARING COURSE
- The wearing course shall be "bituminous concrete" consisting of coarse aggregate, fine aggregate
and mineral filler uniformly coated and mixed with a bituminous binder.
- The nominal size of the bituminous concrete shall conform to the following requirements.
. 50 Blow Marshall Mix, Class 320 Bitumen
- Aggregate shall be 7mm nominal size unless noted otherwise. Minimum compacted depths as
specified on the Drawings.
- The aggregate for the course shall consist wholly of crushed granite material produced from sound
stone having a Los Angeles Abrasion Test value of not greater than 30 or a mixture of crushed
material and natural sand provided that, if natural sand is included in the mixture, the amount used
shall be so limited that the mixture of aggregate passing the 4.75 mm A.S. Sieve will contain not
less than 50% by weight of crushed particles. The flakiness index of the aggregate shall not exceed
35%.
- Filler, if required, shall consist of Portland Cement, ground limestone or stone dust.
- The paving mixture for the surface coarse shall meet the following requirements by weight when
determined by A.S. sieves. The residual binder, that is the residual asphaltic bitumen, shall be
determined as a percentage by weight of the total mixture.
AS Sieve Size % Passing By Weight
Nominal Size 7 mm
13.2 mm 100
9.50 mm 100
6.70 mm 80-100
4.75 mm 70-90
2.36 mm 49-67
1.18 mm 37-53
Providence Christian College Primary School Stage 1 Page 7 of 14 SECTION 02210 CIVIL WORKS
SECTION 02210 Civil Works
600 um 25-41
300 um 15-27
150 um 8-16
75 um 4-8
Total Mineral Matter 100
- Strict control of temperature shall be maintained to avoid burning of the binder and to also provide
maximum laying qualities in the mix.
- The following limits shall apply:
. Maximum aggregate temperature = 190°C
. Maximum bitumen temperature = 160°C
. Maximum temperature of mix leaving plant = 175°C
. Minimum temperature of mix at spreader = 135 C
4.7 TACK COAT
- A tack coat of rapid breaking cationic bituminous emulsion (CRS / 50 - 60 Grade) shall be applied to
the primed surface at a rate between 0.20 and 0.50 litres per sq. metre.
- The existing surface shall first be swept to the satisfaction of the Architect to a clean, dry surface.
- When ordered, splash guards shall be supplied and used to protect property, traffic and adjoining
work from damage. The Architect shall direct the length of tack coat which may be put out beyond
the point at which the spreading of bituminous concrete is to be undertaken and the period of time
which must elapse before spreading commences on the tack coat. This time shall normally be not
less than 30 minutes nor more than 2 hours.
4.8 PLACING THE MIXTURE
- The mixture shall be laid upon a base which is dry and only when weather conditions are suitable
and atmospheric temperature above ten (10) degrees centigrade.
- The mixture shall be spread to line and camber without tearing, gouging or shearing to produce a
surface free from waves.
- The mixture shall be spread in such a manner as to minimise the number of joints in the pavement.
More than one longitudinal joint will not be permitted if the total width is 7.4 m or less.
- Longitudinal and transverse joints shall be made in a careful manner well bonded and sealed. Joints
between old and new pavements or between successive days work, shall be carefully made to
ensure a thorough and continuous bond between the old and new surfaces.
- Immediately after any course is spread and before roller compaction is started, the surface shall be
checked, any inequalities adjusted, all fat, sandy, segregated hungry or dusty accumulation from the
screed removed by a rake or hoe and replaced with satisfactory material.
4.9 COMPACTION OF MIXTURE
- After spreading, the mixture shall be thoroughly and uniformly compressed as soon after being
spread as it will bear the roller without undue displacement. For the compaction of the mixture, the
Contractor shall provide self propelled and reversible rollers approved by the Architect and
complying with the following requirements:
Providence Christian College Primary School Stage 1 Page 8 of 14 SECTION 02210 CIVIL WORKS
SECTION 02210 Civil Works
. Steel static three wheeled rollers, weighing not less than 10 tonnes nor more than 12 tonnes. The
wheel pressures of the rear wheels shall be not less than 60 kg/cm width.
. Steel static tandem wheeled rollers weighing not less than 10 tonnes nor more than 12 tonnes.
The wheel pressures of the rollers shall be not less than 45 kg/cm width.
. Pneumatic tyred multi wheeled rollers equipped with pneumatic tyres capable of being inflated to
700 kPa. The rollers shall be so constructed that the total weight of the roller can be varied to
produce an operating weight per tyre of up to 200 kg.
. Vibrating rollers each of minimum static mass of six (6) tonnes capable of varying the amplitude
and/or frequency of vibration may be used subject to the approval of the Architect. Vibratory
compaction shall be discontinued in areas where it is considered such vibration could cause
damage to adjacent buildings or structures.
- An approved brush or similar device shall be fitted so that each tyre or roll is kept clean of foreign
material and kept uniformly wet. Tyres shall be free of pit marks.
- The Contractor shall provide a minimum of one steel three wheeled roller and one pneumatic tyred
roller for each asphalt paver in use on the job, but the Architect may require the provision of
additional rolling equipment if, in his opinion, the rollers on the job are not obtaining the required
compaction of the mixture.
- For compacting confined areas, the Contractor shall provide a small roller and/or a mechanical
impact type or vibrating type hand operated compactor of size and mass acceptable to the Architect.
- Undue delays in rolling freshly spread mixture will not be tolerated. Initial compaction of the asphalt
shall be achieved using the self propelled steel wheel roller. Rolling shall start longitudinally at the
sides and proceed toward the centre of the pavement overlapping on successive passes by at least
150 mm. Successive passes of the roller shall be of slightly different lengths. A minimum of three
passes shall be given to the asphalt and these passes shall be completed as soon as practicable
but before the asphalt temperature falls below 110 degrees Celsius. Subsequent to at least three
passes of the static wheel roller, rolling shall be carried out using the pneumatic tyred roller.
- Where the width of the pavement permits, the pavement shall then be subjected to diagonal rolling
in two directions with a tandem roller weighing not less than 10 tonnes, the second diagonal rolling
crossing the lines of the first.
- The speed of the steel wheeled roller shall not exceed 5 km/hour, or 10 km/hour in the case of a
pneumatic tyred roller and shall be at all times slow enough to avoid displacement of the hot
mixture. Any displacement occurring as a result of reversing the direction of the roller, or from any
other cause, shall at once be corrected by the use of rakes and of fresh mixture where required.
Rolling shall proceed continuously until all roller marks are eliminated and no further compression is
possible.
- Along kerbs, channels, headers, manholes and similar structures, and at all places not accessible to
the roller, thorough compaction shall be secured by means of hot tampers and at all contacts of this
character the joints between these structures and the mixture must be effectively sealed.
- After final compaction the course shall conform to the following requirements. It shall:
. be smooth and true to the established crown and grade, and be within a tolerance of + 5 mm of
the design level;
. shall at no point vary more than - 0 mm to + 5 mm from the specified thickness indicated on the
drawings. Any low or defective places shall immediately be remedied by cutting the course at
such spots and replacing it with fresh hot mixture which shall be immediately compacted to
conform with the surrounding area and shall be thoroughly bonded to it. The surface of the
finished course shall be free from depressions exceeding 5 mm as measured with a three metre
straightedge;
. shall have crown or crossfall as directed by the Architect;
. surface slope shall also be such that ponding of water cannot occur at any point.
4.10 PAVEMENT INSPECTION
- The Contractor shall allow for a lightweight water cart to carry out a pond test on the completed
pavement in the presence of the Superintendent.
- The test shall be completed as soon as practicable following completion of the asphalt wearing
course install.
- Any ponding that is identified shall be rectified immediately to avoid accumulation of excess oils.
Ponding is defined as any local depression that holds water any deeper than approximately 2mm.
Providence Christian College Primary School Stage 1 Page 9 of 14 SECTION 02210 CIVIL WORKS
SECTION 02210 Civil Works
5.1 GENERAL
This section of the Specification covers the provision of pavement marking and other surface
delineations.
5.2 STANDARDS
Work carried out and testing performed under this part of the Specification shall comply with the
following standards to the extent that they are relevant.
- AS 1742 Manual of Uniform Traffic Control Devices
- AS 1906 Retroreflective Materials and Devices for Road Traffic Control Purposes
- AS 2009 - 2006 Glass Beads for Road Marking Materials
- AS 4049 Paints and Related Materials - Road Marking Materials
- AS 2890.6 Off-street Disabled Parking
Providence Christian College Primary School Stage 1 Page 10 of 14 SECTION 02210 CIVIL
SECTION 02210 Civil Works
Providence Christian College Primary School Stage 1 Page 12 of 14 SECTION 02210 CIVIL
SECTION 02210 Civil Works
- Sand for bedding or backfilling shall be clean and free from roots, clay or any deleterious matter in
accordance with the requirements of 0222 Earthworks.
Water
- Water for use in concrete and mortar shall be of potable quality free from any impurities harmful to
concrete, mortar or steel.
6.4 RETAINING WALL – WALL CONSTRUCTION
Foundations
- Walls constructed of mass blocks shall be founded on a compacted base of clean sand fill in
accordance with the requirements of 0222 Earthworks.
- Where foundation is bedded in rock the base of the wall shall be prepare by placing mortar and
suitably sized stone to form a level pad. Footings shall be stepped on sloping ground.
Blocks for Walls
- Blocks for walls shall be in accordance with Clause 8.3 (a).
- The size of surface blocks is to retain consistent throughout the job and no rubble to be used.
- All blocks forming the face of all retaining walls are to be laid integrally with the rising of the wall. No
blocks are to be applied as a facing to the retaining wall.
Backfilling Walls
- Backfilling behind the retaining walls is to proceed in accordance with the requirements of section
"Clearing and Earthworks" of this specification.
- In addition to these requirements, the height of any retaining wall must not be raised more 1.0m
above the level of backfill which is to be introduced and compacted in layers progressively as the
wall is constructed, as specified elsewhere.
Pipe Penetration and Ducts
- The Contractor shall install all pipe ducts as nominated on the drawings.
- Pipe materials unless noted otherwise shall generally be PVC pipe ducts, solvent jointed.
Mortar Joints
- Mortar joints (perpendicular and horizontal) shall consist of a mixture of clean sand, lime and
Portland cement as specified below:-
. 1 part cement
. 1 part lime
. 6 parts sand
. All joints shall be fully mortared throughout the entire wall construction.
- Finished joints shall be finished flush with the surface of the wall of where bevelled blocks are
utilised shall be flush with the recessed bevelled edge and shall match in colour the block material
used.
- Other finishes may be selected by the Principal at his discretion and wall finishes shall be approved
by the Architect prior to the commencement of works.
Vertical expansion joints
- Vertical joints shall be provided generally at intervals as indicated on the Drawings, or as nominated
on wall elevations. Otherwise, 20mm wide vertical joints shall be provided at 20 meter centres.
Joints shall be sealed with a flexible, UV resistant mastic on a backing rod. Colour strictly to the
Architect’s selection.
Mortar Mixing
- Where the mortar is used in large quantities, a mixer of approved type shall be used. In hand
mixing, materials shall be thoroughly mixed on a boarded platform. Mortars shall be mixed only for
immediate use and any mortar that has once set or in any way deteriorated shall not be used.
Drainage
- 20 dia PVC-U weep holes shall be provided through the cross section of the wall at centres
nominated on the Drawings, where the wall is founded in rock, capstone or less than 600mm of
sand. A continuous, blue metal aggregate drain wrapped in a non-woven geotextile at the back of
wall connecting to upstream end of weep holes shall be provided at the height nominated on the
Drawings for the full length of the wall.
Providence Christian College Primary School Stage 1 Page 13 of 14 SECTION 02210 CIVIL
SECTION 02210 Civil Works
Providence Christian College Primary School Stage 1 Page 14 of 14 SECTION 02210 CIVIL
SECTION 02220 Earthwork
02220 EARTHWORK
1.1 SCOPE
The work of this section comprises but is not limited to excavation, disposal of surplus excavated
material both on and off the site, supply of compaction and filling material and the preparation
necessary to bring the areas to correct shape and level prior to building construction and as follows:
- Site management
- Site preparation
- Supply and installation of waterproofing membrane
- Termite Treatment
- Temporary site fence
1.2 STANDARDS
Standards
The work shall comply with relevant current Australian Standards including but not limited to the
following:
- AS 1289 Methods of testing soils for engineering purposes.
- AS 2159 2009 Piling - Design and installation. Plus 1 Amdt, 2010.
- AS 3660 Termite management.
. 3660.1 2000 New building work.
. There are 2 other parts, 2000.
- AS 3798 2007 Guidelines on earthworks for commercial and residential developments.
- AS/NZS 4200 Pliable building membranes and underlays.
. 4200.1 1994 Materials. Plus 1 Amdt, 1994.
. 4200.2 1994 Installation requirements.
- AS 4687 2007 Temporary fencing and hoardings.
Comply with particular specifications in building regulations and/or local council publications.
1.3 DEFINITIONS
- Common Material - is defined as any material which can be excavated by any excavation equipment
up to and including a 20 tonne excavator at a rate of 50 bank m3/ hour.
- Excavation in Soft Rock - Soft rock shall be defined as rock that cannot be excavated with a 20
tonne excavator with a G.P bucket at a rate of 50m3 per hour and requires the use of a rock bucket
and/or single tine ripper.
- Excavation in Hard Rock - Hard rock shall be defined as rock that cannot be excavated with a 20
tonne excavator using single tine ripper and rock bucket and therefore requires use of an excavator
with a hydraulic rock breaker.
- Sub-grade: the natural ground below the excavations.
- Filling: a general term for material spread and compacted over the sub-grade to make up finished
levels or levels to the under-side of the base.
- Sub-base: selected filling spread and compacted over the sub-grade to make up levels to the
underside of the base.
- Base: a selected filling layer spread and compacted to form an acceptable working surface directly
under the building.
- Water – Any flow or seepage, either underground or overland from any source including but not
limited to rainfall, precipitation, ground water, perched ground water.
- Comply with particular specifications in Building regulations and/or Local Council publications.
1.4 CERTIFICATION
The builder is to engage and pay for a suitably qualified NATA approved laboratory approved by the
Architect to instruct on and certify the following:
Providence Christian College Primary School Stage 1 Page 1 of 10 SECTION 02220 EARTHWORK
SECTION 02220 Earthwork
Providence Christian College Primary School Stage 1 Page 2 of 10 SECTION 02220 EARTHWORK
SECTION 02220 Earthwork
The CPT probes (CPT1-CPT4) located in the proposed building area indicate the
presence of dense sand in all CPT locations. A localised area of medium dense sand
was encountered in CPT01 and CPT03 at depths of 3.5 to 4.5m below ground level.
Groundwater: Groundwater was encountered in all CPT locations (but CPT02) at depths of
approximately 3.4m (CPT01) to 3.7m (CPT04) below ground level.
1.8 ROCK
The geotechnical report has not identified rock on site. Should rock exists on site and unless specified
to the contrary the Contractor shall include in his Tender Price an amount for excavation in rock.
It will be the Contractor’s responsibility to ensure that the amount tendered allows for excavation in
rock of varying hardness and depth for the entire works. The contractor shall include all but excavation
in Hard Rock in their tender price.
Where rock is encountered below road pavements or building foundations, such material shall be
removed to a depth of 100mm minimum below the design subgrade level and the area filled as
specified.
In addition, the Contractor shall submit to the Superintendent independent of the tendered amount,
rates per cubic metre for excavation in common material and in rock based on the definitions in
section 1.3:
- Common Material.
- Excavation in Soft Rock.
- Excavation in Hard Rock.
The rates shall be used for payment for work which may be required as an extension of the contract
and ordered by the Architect in writing.
The material classification shall be agreed on site at the time of excavation by the Contractor and the
Architect and payment shall be made on quantities determined by field measurement.
Should the Architect and the Contractor fail to agree on the assessment of quantity of rock the
Architect will calculate the quantity and payment will be made accordingly.
1.9 EXPLOSIVES
Do not use explosives in groundworks.
1.10 TOLERANCES
Finish groundworks to reasonably smooth and uniform surfaces conforming to the tolerances per
section 2.4 of 0221 Civil Works:
1.11 SITE MANAGEMENT
General
- Seek approval from the Local Authorities for all works and site access beyond of the site boundaries
prior to commencing work on site. The builder shall ensure that existing roads are protected from
damage. If damage does occur, the builder shall reinstate to a like new state without cost to the
client.
Dust Control
- The builder is advised that this site has a classification. The builder is responsible for maintaining
dust control on the site at all times during the works. Dust control measures must comply with EPA
and City of Gosnells requirements.
- If the Contractor complies with the previously mentioned dust control measures and dust problems
persist then further measures will be adopted (wind fencing, hydromulch, etc). The Contractor shall
at all times however be responsible for implementing the necessary measures to prevent sand or
dust drift and shall be liable for damages as a result of sand or dust drift.
- To avoid dust nuisance to adjacent owners the Architect may direct that no earthworks, including
stripping or replacing of topsoil, shall be carried out when a wind is blowing towards surrounding
properties and in the opinion of the Architect will cause sand drift or dust to reach those properties.
Inspection
Give the Architect at least two working days’ notice that the following are ready for inspection:
- rock encountered in the excavations
- excavation completed to Contract levels
Providence Christian College Primary School Stage 1 Page 3 of 10 SECTION 02220 EARTHWORK
SECTION 02220 Earthwork
Providence Christian College Primary School Stage 1 Page 4 of 10 SECTION 02220 EARTHWORK
SECTION 02220 Earthwork
- 1100 One-Call information confirms critical services exist in Furley Road verge adjacent to the site
including Telstra fibre optic telecommunications and NBN.
- The builder must hand locate all existing services using a qualified service locator to confirm their
actual alignment and depth using non-destructive methods, strictly in accordance with the
requirements of the relevant proprietary service provider. The builder must satisfy themselves of the
actual locations of all services prior to works commencing.
- The builder shall maintain all proprietary service provider’s requirements including but not limited to
minimum cover / clearances to service, particular compaction methodologies over and around
services and any other requirements the provider may have.
- Do not excavate by machine within 1m of existing underground services without prior approval
1.16 SPOIL
- Remove from the site, including debris, tree stumps and the like resulting from site clearance.
Dispose off-site at an approved disposal facility.
- The Contractor shall be solely responsible for the safe and harmless disposal of surplus excavated
material. Do not burn without permission.
1.17 SUPPORTING EXCAVATIONS
- Support sides of excavations as necessary to ensure safe working. The builder is responsible for all
temporary retaining structures required for construction of the footings and other in ground
structures.
- If, in the opinion of the architect any support provided is insufficient, he may order the provision of
additional support fully at the cost of the contractor. No such instruction shall relieve the Contractor
of sole responsibility for the sufficient support of the excavations.
- Remove temporary supports progressively as backfilling proceeds, unless otherwise instructed.
1.18 SITE RESTORATION
Unless otherwise specified, restore the developed and undeveloped ground surfaces of the site to the
condition existing at the commencement of the work under the Contract.
1.19 SUBGRADE PREPARATION
Unless otherwise instructed by the Superintendent, all subgrades shall be proof compacted by rolling
the surface with modern, efficient, heavy duty vibration compaction plant that shall provide uniform
compaction across the subgrade area. The Contractor is responsible for the correct selection of plant
based on the expected ground conditions, however generally, the type of plant required is:
Gravels & sands without surface boulders - Smooth Drum Roller
Clay & Clayey materials - Pad Foot Roller
Subgrade compaction shall proceed in an orderly fashion at constant speed to ensure the whole site
has been given a single pass, without the addition of surface watering. Under no circumstances shall
the initial pass speed be less than that recommended by the plant manufacturer for efficient
compaction. Should any subgrade be shown to be weak or deform under compactive effort, cease
compaction to these zones and these area shall be marked for further inspection. Subsequent passes
shall be carried out except where any non-uniform conditions are encountered.
Non-uniform ground conditions revealed by proof compaction as not improving with compaction shall
be the subject of further investigation. The Contractor shall provide all labour and machinery required
to conduct further investigation. Once it has been confirmed on site that subgrade areas are not
responding to compactive effort or deforming, the contractor shall initially advise the Superintendent in
writing that a discrepancy has been encountered, in accordance with section 1.6 Ground Condition
Discrepancies. Should no notification be provided prior to proceeding with any remediation works, no
claim for extra cost shall exist.
Additional passes may be necessary over non-uniform conditions or where deformations occur.
In accordance with section 1.6 Ground Condition Discrepancies, following notification to the
Superintendent, the Contractor shall in the first instance consult their engaged Geotechnical Engineer
on advise on how to proceed. All remediation shall be to the approval of the Superintendent at all
times prior to beginning remediation works.
Should the material be inconsistent and of variable quality, the Contractor shall consult with their
engaged Geotechnical Engineer to establish an appropriate method of compaction.
Providence Christian College Primary School Stage 1 Page 5 of 10 SECTION 02220 EARTHWORK
SECTION 02220 Earthwork
Following initial passes and provision of a consistent subgrade across the site, the moisture content of
the subgrade shall be controlled to be within 90%-110% of the optimum moisture content for that
material. The material shall be lightly water or dried as required to maintain the moisture content.
The completed subgrade profile shall be in a homogeneous, uniformly bonded condition with no
evidence of layering or disintegration.
1.20 RECORD MEASUREMENT
Should a ground conditions discrepancy be encountered, backfilling or construction over of permanent
structures or fixtures over shall not commence until the following have been confirmed, agreed or
measurement methodology accepted by the Superintendent:
- Depths of excavation relative to the design or an appropriate Datum.
- Actual plan dimensions of excavations.
- Quantities of excavations.
The actual excavations completed shall be site measured and surveyed by a licensed surveyor. The
3d data shall be supplied to the superintendent in native format for review and acceptance.
Survey data shall be provided for each earthworks sequence.
Where rock is measured for payment purposes, do not remove the rock from site until it has been
agreed the material is classified as rock.
1.21 FILLING MATERIAL
Bring filling on to the site unless it can be provided from spoil recovered from site. Filling shall be
sound material, free of organic or perishable material, or material that will form stable fill, but subject
always to Architect’s approval. Filling shall be of the following types:
- Approved Excavated Material: The best of the clean inorganic excavated material, approved by the
Architect.
- Approved Imported General Fill Material: Clean, well graded, compactable granular sand fill, with
less than 5% fines approved by the geotechnical engineer. Fill must be evenly graded to allow for
free draining of stormwater.
Clay soils shall not be used in fill.
1.22 EXCAVATIONS
- Excavate as required or as shown on the Drawings, including but not necessarily limited to the
following:
. Site Surface : Excavate over the site to give correct levels and profiles as the basis for
construction, paving, filling, landscaping and the like. Make allowance for compaction or
settlement.
. Footings : Excavate for footings, pits, wells, shafts and the like, to the required sizes and depths.
. Where footings overlay rock, ensure this rock material is removed to a depth of 600mm below the
underside of footing and replaced with fill material compacted to the standard specified below.
. Services : Excavate for underground services as specified in service trenches.
- No excavation is to be carried out closer to an existing footing than a line extending down from its
bottom edge at 45 degrees.
- Suspend ground works during inclement weather, which would result in unsatisfactory work.
1.23 GRADING
Grade the site as shown and to give falls away from the building, minimum 1:100 unless otherwise
shown.
1.24 BEARING SURFACES
- Provide even plane bearing surfaces for loadbearing elements including footings and the like. Step
as necessary, or as shown on the Drawings, to accommodate level changes. Make the steps to the
appropriate courses if supporting masonry (e.g. brickwork, blockwork).
- If the bearing surface deteriorates after approval because of water or other cause, excavate further
to a sound surface before placing the loadbearing element, without extra charge if the deterioration
has resulted from the Contractor's actions or failure to act.
Providence Christian College Primary School Stage 1 Page 6 of 10 SECTION 02220 EARTHWORK
SECTION 02220 Earthwork
Providence Christian College Primary School Stage 1 Page 7 of 10 SECTION 02220 EARTHWORK
SECTION 02220 Earthwork
- Where thin layers of sand fill are to be compacted (~<150mm), the contractor shall consider
compaction with at least ten passes with heavy smooth-drum roller machinery, rolled in static mode
only.
- The degree and uniformity of compaction shall be tested by use of a standard penetrometer
calibrated for Perth sand.
- For Perth sand and sand of a similar nature the contractor shall best the degree of compaction
using a Perth Sand (16mm diameter tip, 9kg falling weight) penetrometer in accordance with
AS1289 6.3.3.
- For sand of a different nature to Perth sand the Contractor must carry out penetrometer tests in
accordance with AS.1289.6.3.3 using a penetrometer calibrated by a soil testing laboratory. This
calibration will be the accepted criterion for ensuring that the specified density is achieved. The cost
of calibrating the penetrometer shall be borne by the Contractor.
- The Contractor shall arrange for all tests including penetrometer tests to be carried out by an
approved testing laboratory registered with NATA. The Contractor shall allow for all costs.
- The tests shall be carried out in the zone between 0mm and 1500mm below foundation level and
below the base level of any excavations. The frequency of testing shall be
. under pad footings: 1 test per pad
. under strip footings: 1 test per 3m length
. under slabs and paved areas: On 5 x 5 grid
- An acceptable degree of compaction as measured by the penetrometer shall be:
Testing Depth Below Ground Surface at
Required Blows per 300 mm Penetration
Time of Testing (m)
0 – 0.45 8
0.45 – 0.90 10
0.90 – 1.50 14
Providence Christian College Primary School Stage 1 Page 9 of 10 SECTION 02220 EARTHWORK
SECTION 02220 Earthwork
Providence Christian College Primary School Stage 1 Page 10 of 10 SECTION 02220 EARTHWORK
SECTION 02240 Stormwater Drainage
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Provide stormwater drainage, as documented.
2 STORMWATER DRAINAGE
2.1 EXCAVATION
- The Contractor shall excavate pipe trenches to the lines, levels, grades and widths shown or
specified on the Drawings, and in the Specification. Where necessary the trench shall be widened
and/or deepened to facilitate the making of joints, casing pipes with concrete and/or to
accommodate timbering while still maintaining the clearances specified between the timbering and
the pipes.
- The Contractor shall establish prior to commencing excavation whether or not other services exist in
the path of or parallel to excavation. In the event of existence of any such services the contractor
shall take every care not to damage such services. Any damage caused shall be made good at the
entire cost of the Contractor.
- Open cut excavation of trenches will be an acceptable alternative to timbered trenches, provided the
following requirements are complied with:
. The widths of open cutting shall be the absolute minimum practical and necessary for
construction procedures;
. Backfilling over the whole width shall be carried out as provided in this specification;
. The trench width for the first one metre depth (or pipe diameter plus 300mm whichever greater)
shall be confined to the specified widths; and,
. Where indicated on the drawing or ordered by the Architect, the trench shall be timbered to
protect adjacent works or trees. Damage to adjacent works, whether or not the Architect has
given directions in this regard, shall be repaired at the Contractor's expense.
- The maximum width of trench shall be the diameter plus 225 mm clearance on each side, subject to
a minimum width of 850 mm.
- The Contractor shall maintain the works area in a suitable dry condition in order that each and every
part of the works may be constructed to a high standard and for the protection of the works against
damage due to water.
- During the construction of the Works the Contractor shall, at the cost of the Contractor, take every
precaution necessary and provide all plant, materials and labour required for the effective diversion
and removal of surface and sub surface water from the works.
- Trenches in which the bottom is likely to be adversely affected by rain or seepage shall have the last
150 mm of excavation removed as a separate operation immediately prior to the laying of the pipes
or placing of bedding material. Such measures shall be carried out at the Contractor’s expense.
- If pipe trench is excavated deeper than required, the extra depths shall be filled with 1:3:6 cement
concrete or other approved material compacted to a density exceeding the natural surrounding
ground.
- Spoil from excavation shall be kept at least one metre from the edge of excavation.
- The Contractor shall take whatever measures necessary to prevent the spoils of excavation from
being carried away by water or wind from the site.
- Excavation in rock or hard soil will not be carried out be carried out by blasting.
2.2 PIPE BEDDING
- Unless special bedding or pipe supports are shown on the Drawings or specified elsewhere, the
bedding material shall be clean sand.
- One type of bedding support only shall be used along each length of line.
Providence Christian College Primary School Stage 1 Page 1 of 5 SECTION 02240 STORMWATER DRAINAGE
SECTION 02240 Stormwater Drainage
- Clean sand from the excavation may be used. The bed shall be carefully shaped to receive the
pipes with grooves to receive the pipe sockets so that the barrel shall be uniform bearing along its
length.
2.3 BACKFILLING
- Initial backfilling shall be undertaken using selected fill, being defined as sand, gravel or other
approved granular materials free of all stones retained on a 25 mm sieve.
- Initial backfilling at the sides and for 150 mm above the top of the pipe shall be hand tool placed and
compacted ensuring that no joints or pipes are disturbed or damage. Refer to Standard Drawings.
- The joints shall be left fully exposed for inspection during testing.
- No part of the works or any length of pipes or fittings shall be covered up until they have been
inspected and approved by the Architect. The Contractor may still be required to uncover and repair
at the expense of the Contractor, during the period of maintenance, any unsatisfactory work.
- The material excavated from the trench may, subject to the approval of the Architect, be used for
ordinary backfill, provided it is free of rocks and vegetable matter.
- The backfilled material shall be thoroughly rammed and consolidated in 150 mm layers with hand
rammers weighing not less than 9 kg to a height of 600 mm above the top of the pipe, and thereafter
in 250 mm layers with power rammers or in 150 mm layers with hand rammers. The compaction of
the backfill shall be equal or better than the adjacent in situ material, except under roads and where
indicated on the Drawings the compaction shall be equal to or 98% of the modified maximum dry
density.
- Any deficiency found in backfill shall be made good by adding and compacting approved backfill
material at the entire cost of the Contractor.
- After the trench has been filled in, the Contractor shall immediately restore the surfaces, other than
in roads and driveways, to equal or better than their pre existing conditions.
- In roads and driveways, the Contractor shall immediately effect an interim restoration to a safe and
reasonable condition for traffic. The Contractor shall make good any settlement, deterioration etc.,
as they occur.
- The permanent reinstatement of roads shall not be commenced until the Architect is satisfied that
sufficient trench settlement has taken place. The materials used in permanent reinstatement of
roads shall be identical to materials used in adjacent roadwork. The roads shall be restored to pre
existing or improved standards ensuring a good match of restored and existing surfaces.
- The Contractor shall make good at the expense of the Contractor any subsidence or consolidation
that occurs in the backfill and any damage caused by the subsidence before the end of the
maintenance period.
2.4 BASIS OF MEASUREMENT
- For payment purposes, the ground has been classified as common material, soft rock or hard rock.
Definitions of each are covered in the earthworks specification. No rock shall be paid for unless the
amount has been measured and agreed by the Architect. For payment purposes, the trench width
shall be prescribed minimum width applicable to the size of the pipe.
- Measurement of trench depths for the purpose of determining the appropriate scheduled rate for
payment for excavation and refilling shall be made only at manholes, pits and head walls and the
depth of the trench at intermediate points shall be allotted to the several depth groups on the
assumption that the ground surface slopes uniformly between successive points of measurement.
- Work shall include all excavation, bedding, backfilling and compaction testing. Payment will be
made only for completed work, i.e. after the trench has been tested, backfilled and consolidated and
surplus spoil removed.
2.5 DRAINAGE
Materials
- Stormwater pipes shall be reinforced concrete, PVC-U up to 225 diameter manufactured to AS 1254
or polypropylene with SN8 equivalent grade as shown on the Drawings.
- Reinforced concrete pipes shall be socketed, rubber ring jointed, manufactured and tested in
accordance with AS 4058 - 2007 and shall be 1, 2, 4 or 4 class as indicated on the Drawings.
- Polypropylene pipes – to comply with AS/NZS 5065-2005 - Polyethylene and Polypropylene pipes
and fittings for drainage and sewerage applications.
Providence Christian College Primary School Stage 1 Page 2 of 5 SECTION 02240 STORMWATER DRAINAGE
SECTION 02240 Stormwater Drainage
2.7 INSPECTION
- Where the consultant is unable to complete inspection of stormwater drainage pipe trenches, the
builder shall provide photo records of trenches for each line. The photos must include pipe bedding
& backfill,
Photo records shall be named in sequence and to match the documentation.
Providence Christian College Primary School Stage 1 Page 3 of 5 SECTION 02240 STORMWATER DRAINAGE
SECTION 02240 Stormwater Drainage
2.10 CULVERTS
All drainage culvert crossings under roads, crossovers and at culvert entries and outfalls shall have
approved, proprietary headwalls installed to suit the culvert size and type.
2.11 TESTING
- It is the contractor’s responsibility to provide all materials for the completion of this project and to
provide verification that all materials comply with the requirements of this specification. In addition it
is the contractor’s responsibility to undertake all necessary testing of, subgrade and trench backfill
to ensure conformance with this specification for compaction, level, dryness, shape, finish etc.
- The costs for all testing shall be allowed for.
- For the purposes of testing, the works shall be divided into sections referred herein as "portions".
The definition of a "portion" shall be that section between manholes, drainage structures or
terminating end to a maximum length of 100m and to a maximum depth per test of 1.0m.
- All compaction testing for drainage in clean sand shall be undertaken by an approved NATA
registered laboratory unless:
. The Architect specifically permits otherwise or,
. The specialist drainage contractor has an acknowledged Quality Assurance Accreditation
(recognised by the Architect) in which case a maximum of 90% of tests (using a Perth Sand
Penetrometer only) may be undertaken by the contractor/subcontractor so long as a minimum of
10% of tests are undertaken by a NATA registered laboratory and the P.S.P. is calibrated for the
site sand at the commencement of the works.
2.12 AS CONSTRUCTED
- The Contractor is entirely responsible to undertake "As Constructed" survey for all stormwater
drainage installations.
- Records shall include the lengths, alignments, chainage, diameters and invert levels of all pipes
entering access chambers or stormwater entry pits, and the lid levels of the of the access chambers
or stormwater entry pits.
- Preliminary stormwater "As Constructed" information shall be maintained, progressively updated
and available for review by the Superintendent on site. This shall be in the form of a “mark-up” of the
current civil Drawings.
Measurements shall be taken while trenches and pipe are exposed, prior to backfill to record pipe
depth and location of the pipe on site relative buildings, roads, cadastral boundaries or other
relevant site features.
- Where works are completed in stages, the preliminary as-constructed “mark-up” plan with complete
as-constructed information for the stage will be accepted however at the completion of the project,
the final as-constructed Drawing will be required.
- Final As Constructed information shall be provided in accordance with the General Requirements
work sections. Additionally, as-constructed locations of all soakwells, access chambers, gully pits
and the like shall be accurately located by a licensed surveyor. A digital copy of the as-constructed
location shall be provided to the Architect in Autocad dwg and pdf formats for client records.
- Under no circumstance will payment be made for works which have not received the Architects
approval of the "As Constructed" information.
Corrective Maintenance
• For any above ground drainage systems such as swales, compensating basins, open
channels, overland drainage flow paths, check for scouring, erosion, rilling and the like as well
as any new naturally formed drainage paths created by the flows. Replace material and
compact to damaged areas or rock armour, as required.
The design of stormwater drainage systems requires regular, routine maintenance by the owner to
maintain its hydraulic capacity, inlet efficiency and/or design life.
Providence Christian College Primary School Stage 1 Page 5 of 5 SECTION 02240 STORMWATER DRAINAGE
SECTION 02360 TERMITE CONTROL
PART I GENERAL100
101 Scope
The work of this trade section includes but is not limited to the control and/or management of termites on
building sites for both new and existing buildings. Note that this is a design and construct item and the
contractor is to provide all coordination and complete the design for the selected system with provision
of samples and shop drawings as well as the method statement.
Obtain approval from the principal certifying authority prior to commencing work as to the adequacy of
the proposed system and suitability for the intended use.
104 References
Comply with applicable portions of the following Australian Standards which are requirements of the
Building Code of Australia:
AS 3660 Termite management.
3660.1 2014 New building work.
3660.2 2000 In and around existing buildings and structures.
There is 1 other part, 2014.
AS 4349 Inspection of buildings.
4349.3 2010 Timber pest inspections. There are 2 other parts, 2007.
Comply with requirements of statutory and local authorities having jurisdiction.
105 Submissions
Obtain a written statement, from each proposed sub-contractor tendering for the work, that the work to
be performed will comply with the relevant Australian Standard.
106 Warranty
Provide a written warranty from the sub-contractor stating the period of years of protection from termite
damage. Provide also a written statement that the work performed complies 100% with the requirements
of AS 3660.
PART II MATERIALS200
202 Materials
Complete termite management system comprising
1. Bifenthrin impregnated high impact 200 micron single extrusion polymer termite and moisture
barrier to the underside of on ground concrete floor slabs.
2. Bifenthrin impregnated high impact 500 micron embossed polymer damp proof course to the full
perimeter of the ground floor slab.
3. Bifenthrin impregnated collars to all ground floor slab service penetrations.
203 Equipment
Provide equipment needed to effect a treatment which complies with the Australian Standards.
301 Examination
Visit site and inspect conditions, comparing conditions to the drawings before delivery of materials to
site.
Rectify any discrepancy or unsuitability of substrata.
Start of work means total acceptance of conditions.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 02360 TERMITE CONTROL
302 Coordination
Arrange for cooperation of other trades to ensure effective pest control. Take care of materials. Prevent
damage before and during installation.
303 Preparation
Coordinate with and ensure preparatory work by other trades is done prior to commencement of work
and arrange for provision and fixing grounds.
304 Installation
Comply with appropriate Australian Standard.
Take care of and protect surrounding work, including other finishes, equipment and components, during
installation. Provide protective covering where necessary.
306 Protection
Protect finished work.
307 Cleaning
Clean the site where work of this trade is performed.
Remove surplus material.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
Certify the completed system for compliance with statutory regulations and the Council Conditions of
Approval. Hand over to the architect on completion.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 02360 TERMITE CONTROL
SECTION 02769 TACTILE WARNING SURFACES
PART I GENERAL100
101 Scope
Supply and install tactile warning surface material with necessary accessories required for the work.
Refer to architectural documentation and project specific BCA report including access provisions for
scope and extent of work for provision of tactile warning surfaces and stair nosings.
This trade section may include components of design and construct as part of the proposed scope of
work.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1428.4.1 2009 Design for access and mobility – Means to assist the orientation of people
with vision impairment - Tactile ground surface indicators. Plus 2 Amdts,
2010, 2014.
AS 1884 2012 Floor coverings - Resilient sheet and tiles - Laying and maintenance
practices.
AS/NZS 4586 2013 Slip resistance classification of new pedestrian surface material. Plus 1 Amdt,
2005.
AS/NZS 4663 2004 Slip resistance measurement of existing pedestrian surfaces.
HB 197 1999 An introductory guide to the slip resistance of pedestrian surface materials.
105 Submissions
Provide samples and data sheets of materials as well as confirmation of compliance with specific
requirements of the BCA Report.
Where colour contrast is listed on the access report provisions, confirm compliance with technical data
and obtain approval of the Principal Certifying Authority.
If compliance with specific standards are listed confirm all at submissions stage of the project. Obtain
architect's approval for each item before ordering.
107 Warranty
Provide a warranty covering aspects of the installation performed by this trade, against defective
materials and workmanship for a period of 7 years from the date of Practical Completion.
The warranty includes a statement that the whole of the work has been carried out in accordance with
AS 1884 and the instructions of the manufacturers of components in effect at the time of installation.
PART II MATERIALS200
Before ordering materials obtain and provide to the architect written evidence that items to be installed
comply with Australian Standards and are approved by statutory authorities having jurisdiction.
If non-approved materials or components are installed, replacement will be at contractor’s expense.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 02769 TACTILE WARNING SURFACES
201 Acceptable Manufacturers
Nova Products
Provide all materials and components in accordance with the product manufacturers’ specifications and
technical data sheets.
202 Materials
A. Tactile ground surface indicators (TGSI) to concrete slab surfaces: Nova Products PVC TacAlert
Tactile Studs.
Colour: Black.
B. Stair nosings: Nova Products CCRG 10 Tiger 2.0 stair nosing with 10mm riser height. Clear
anodised aluminium retainer extrusion with “Black” insert.
C. Tactile ground surface indicators (TGSI) in paved surfaces: Refer to Landscape specification.
203 Equipment
Supply equipment required for the preparation of floor, and installation of materials as recommended by
the material manufacturer.
301 Examination
Examine the site conditions applicable to each installation and comply with AS 1884.
Start of work means total acceptance of conditions.
302 Preparation
Prepare each area to be surfaced in accordance with AS 1884. Test the dryness of concrete sub-floor
in accordance with AS 1884.
303 Installation
Comply throughout with manufacturer’s current written instruction.
304 Cleaning
Remove excess adhesive and blemishes from the completed surfaces of flooring.
305 Protection
Apply suitable hardboard or plywood to completed floors and maintain in position until final cleaning prior
to Practical Completion.
Remove and replace work which cannot be successfully repaired or cleaned.
306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 02769 TACTILE WARNING SURFACES
SECTION 03100 CONCRETE
0310 CONCRETE
1. GENERAL
1.1 Scope
The work required under this section includes the design, supply, fabrication, erection and stripping of form
work, the scheduling, supply, placing and supporting of reinforcement and the design supply, testing, placing,
finishing and curing of concrete. It also includes the placing of embedded items and the supply and
installation of waterstops and waterproofing.
1.2 Standards
Materials and construction: To AS 3600.
Formwork design and construction to AS3610.
Concrete: To AS 1379.
Reinforcement to AS/NZS 4671.
Concrete structures for retaining liquids: To AS 3735.
1.3 Interpretations
Definitions:
A. Hot weather: Surrounding outdoor shade temperature > 32oC.
B. Contraction joint: An unreinforced joint with a bond-breaking coating separating the concrete joint surfaces.
C. Expansion joint: An unreinforced joint with the joint surfaces separated by a compressible filler.
D. Control joint: A weakened plane contraction joint created by forming a groove, extending at least one quarter
the depth of the section, either by using a grooving tool, by sawing, or by inserting a premoulded strip.
E. Isolation joint: A joint without keying, dowelling, or reinforcement, which imposes no restraint on movement.
1.4 Inspection
A. Witness Points: Give sufficient notice so that inspection may be made of the following:
1. Base prepared for membrane installation.
2. Membrane or film underlay installed on the base.
3. Completed formwork, and reinforcement, cores and embedment’s fixed in place.
4. Shrinkage/Control Joint strengthening plates installed.
4. Commencement of concrete placing.
5. Surfaces or elements to be concealed in the final work before covering.
B. Rejection: Remove rejected concrete from the site.
1.5 Submissions
Builder shall engage a qualified CPE to design all formwork. Formwork must comply to all requirements of
Work Safe WA. Builder to have calculations available for review by the Architect if requested.
A. Tests:
1. Void formers: Submit test certificates to confirm that the formers comply with the following
requirements, under laboratory conditions, when placed on damp sand and loaded with a mass of
wet concrete at least the mass of the beams or slabs they are required to support:
Deflection during placing and compaction of the concrete is less than the span of the beam or slab
divided by 1000.
Additional deflection between initial set and 7 days does not exceed span/400.
2. Collapse and loss of load carrying capacity will occur not more than 48 hours after flooding with
water, creating a void at least 60% of the original depth of the void former.
3. Reinforcement: Certificate of compliance: Submit either the manufacturer's certificate of compliance
with the relevant standard, or an independent testing authority's test certificates demonstrating
compliance.
B. Execution:
1. Builder must have all documentation available for review by the Architect on formwork
documentation and details of proposed form linings, form coatings, release agents and, where
applicable, reuse of formwork.
2. Reshoring: If intended, submit proposals.
3. Surface repair method: Before commencing repairs, submit the proposed method.
4. Changes: Submit proposed changes, if any, in the reinforcement shown on the drawings, including
additional splicing.
5. Mechanical splices: If mechanical bar splices are proposed or required submit details and test
certificates for each size and type of bar to be spliced.
Providence Christian College Primary School Stage 1 Page 1 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
6. Damaged galvanizing: If repair to AS 1650 Appendix F is intended, submit proposals.
B. Dissemination of production information: If concrete is manufactured off site, register the project in
accordance with AS 1379 clause 6.4.3.
1.7 Concrete Tests
A. Concrete Testing Methods
1. Sampling and testing: To AS 1012. Sample the concrete on site.
2. Test authority: NATA Approved Testing Laboratory
B. Test Records
1. Records and reports: To AS 1012
C. Control Tests: Acceptance criteria
1. Average strength of all samples must exceed the required value.
2. Strength of any one sample must be at least 0.85 of the required value.
D Control Test Requirements Schedule: for concrete strength requirements refer to structural drawings.
E Acceptance Testing : All concrete testing shall be carried out in all respects with the provisions of AS1012
and 1379 and AS3600, as currently amended and any relevant N.A.T.A. regulations currently in force.
Before any concreting is commenced, the Architect will ensure that any testing done by the Contractor will
conform with these requirements.
The Contractor shall pay the costs of all tests. The supply of testing equipment and suitable personnel to
carry out the tests will be the responsibility of the Contractor. All test specimens are to be cured and broken
at an approved N.A.T.A. laboratory.
Providence Christian College Primary School Stage 1 Page 2 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
All samples of concrete are to be obtained from a full flow of concrete at the truck discharge chute and shall
be taken after 25% of the load and before 75% of the load has been discharged.
Compression test samples shall be taken in accordance with AS1012 and 1379 and AS3600 at the
frequency set out below:-
Providence Christian College Primary School Stage 1 Page 3 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
2. FORMWORK
2.1 Formwork
A. General
1. General: Design and construct formwork so that the concrete, when cast in the forms, will have the
required dimensions, shape, profile, location and surface finish. Allow for dimensional changes,
deflections and cambers resulting from the application of prestressing forces, applied loads,
temperature changes and concrete shrinkage and creep.
2. Openings: In vertical forms provide form openings or removable panels for inspection and cleaning.
3. Cleaning: Remove free water, dust, debris and stains from the forms and the formed space before
placing concrete.
B. Stripping of Forms : Forms shall not be disturbed until the concrete in contact with them has hardened
sufficiently to withstand such action without damage.
In the absence of any specific direction by the Engineer, the following table shall be used in
determining stripping times for concrete made with Portland cement Type 'A'.
This table is based on construction loads not exceeding 100 kg per square metre.
Bottom Forms of Beams and
Slabs
Average of Daily Vertical less than 3000 to 5000 to over
Minimum Surfaces 3000 5000 7500 7500
Temperatures span span span span
The Builder may use the following alternative to determine stripping times.
Forms shall not be stripped before the concrete supported by them has attained the strength
designated in Table A. The strength of the concrete at stripping shall be taken as the average
strength of 2 cylinders taken from the pour to be stripped.
TABLE ‘A’
% of F’c (28 days value)
Proportion of Design Load on slab at 1/4 1/2 3/4 1.0
stripping
Element Surface Span
Beams and Horizontal 2000 and less 55 60 75 100
Slabs
3000 and less 55 65 80 100
5000 and less 55 70 85 100
6000 and less 80 85 100
7500 and less 90 85 100
above 95 85 100
Removal of bottom forms between bearers or props, prior to the removal of supports may be
permitted by the Engineer, provided the formwork has been designed to allow such removal without
disturbance of the supports.
The Builder shall provide sufficient tomming to ensure that the loading caused by green concrete
floors, (not up to design strength F'c as shown on the drawings) formwork, building equipment and
material is supported by such a number of concrete floors that no floor carries loads exceeding its
capacity based on Table A. The number of floors to remain tommed will depend on the design dead
and live loads of the floors, the pouring cycle and the rate at which the concrete gains its strength.
Neither walls nor any permanent loading shall be erected on any part of the structure while it is still
supported by formwork - unless approved by the Engineer.
Providence Christian College Primary School Stage 1 Page 4 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
Reshoring: Do not reshore.
C. Release Agent : Before placing reinforcement, apply a release agent compatible with the contact surfaces, to
the interior of the formwork, except where the concrete is to receive an applied finish for which there is no
compatible release agent. Clean the reinforcement to remove all traces of release agent.
D. Defective Formwork : Remove rejected concrete, form construction joints, reconstruct the formwork and
recast concrete.
E. Formwork Removal : Remove formwork, other than steel reinforcement decking, including formwork in
concealed locations.
Providence Christian College Primary School Stage 1 Page 5 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
3. MATERIALS
3.1 Polymeric Film Underlay
A. General : Under internal slabs on ground including integral ground beams and footings, provide a vapour
barrier or, in areas prone to rising damp or salt attack, a damp-proofing membrane.
B. Standard : Vapour barriers and damp-proofing membranes: To AS 2870.
C. Base Preparation : According to base type, as follows:
1. Graded stone base: Blind with sufficient sand to create a smooth surface free from hard projections.
Wet the sand just before laying the underlay.
2. Concrete working base: Remove projections above the plane surface, and loose material.
D. Installation : Lay over the base, lap joints at least 200 mm and seal the laps and penetrations with waterproof
adhesive tape. Face the laps away from the direction of concrete pour. Take the underlay up vertical faces as
far as the damp proof course where applicable, and fix at the top by tape sealing. Locate vertical laps only on
vertical or inclined surfaces. Patch or seal punctures or tears before pouring concrete.
3.2 Concrete Materials
Cement shall be locally manufactured normal Portland cement, Type A complying with AS3972. Blended
cement type SA is permissible only in accordance with Clause 4.1 and shall comply with AS3972.
3.3 Concrete
A. Concrete Schedule : Refer to structural drawings for concrete strength & grade.
B. Ready Mixed Supply
1. Method: Use the batch production process. Deliver in agitator trucks.
2. Admixtures: Do not provide admixtures containing significant chlorides.
3. Addition of water: Do not add water at the site.
4. Plastic cracking: Design the concrete mix to minimise plastic settlement and shrinkage cracking.
C. Elapsed Delivery Time : Elapsed time between the wetting of the mix and the discharge of the mix at the site
must not exceed the criteria in the Elapsed delivery timetable.
Elapsed Delivery Time Table
Concrete temperature at time of Maximum elapsed time (hours)
discharge (oC)
< 24 2.00
24 - 27 1.50
27 - 30 1.00
> 30 0.75
Emergencies: Do not mix by hand.
D. Where specified on the drawings provide concrete with Xypex water proofing additive. Concrete mix to be in
accordance with manufactures recommendation for the proposed conditions. Provide certification from the
additive supplier on completion of the concrete works.
4. REINFORCEMENT
4.1 General
A. Steel reinforcement shall comply with the requirements of:-
1. AS/NZS 4671 Steel reinforcing materials.
Where galvanised reinforcing is specified, tie-wire and other similar items shall also be galvanised.
Reinforcement shall be free from scale, loose rust, oil, grease or other deleterious matter that may
Providence Christian College Primary School Stage 1 Page 6 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
impair the bond between the concrete and reinforcement or cause disintegration of the concrete.
All reinforcement shall be cut and bent to the tolerances set out in Clause 19.2 of AS 3600, and fixed
in position to the tolerances set out in Clause 19.5.3.
Reinforcement on site shall be stored clear of the ground and shall be tied free from any form of
surface contamination.
No adjustment to reinforcement other than straight cutting of bars shall be made on site without the
approval of the Engineer.
B. Dowels
1. Standard: To AS/NZS 4671 grade 250R.
2. General: Provide each dowel in one piece, straight, with square cut ends free from burrs. Apply 2
coats of bitumen emulsion to half the length of the dowel at one end. Embed the unpainted half of
the dowels in the concrete placed first.
3. Tolerances:
Location: ± half the diameter of the dowel.
Alignment: 2 mm in 300 mm.
C. Welding
1. General: Give notice before welding reinforcement. Do not weld reinforcement within 75 mm of a
section which has been affected by bending or re-bending.
2. Standard: To AS 1554.3.
Providence Christian College Primary School Stage 1 Page 7 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
concrete supports of the same concrete quality as the concrete element.
B. Supports Over Membranes : Prevent damage to waterproofing membranes or vapour barriers. Place a metal
or plastic plate under each support to prevent puncturing.
C. Support Spacing
1. Bars: £ 60 diameters.
2. Fabric: ³ 750 mm.
B. Horizontal Movement : Use suitable conveyors, clean chutes, troughs or pipes. Do not use water to facilitate
the movement.
C. Vertical Movement : In vertical elements, limit the free fall of concrete to 1500 mm per 100 mm element
thickness, up to a maximum free fall of 3000 mm, using enclosed chutes or access hatches in forms. As far
as practicable keep chutes vertical and full of concrete during placement, with ends immersed in the placed
concrete.
D. Wet Weather Requirements : Concrete shall not be ordered for a pour in wet weather without the approval of
the Architect.
Where approval is given to proceed, the Builder shall undertake responsibility for making good all areas of
mono finish which may be damaged by rain.
Waterproof covers shall be kept close at hand to cover the screeded surface and prevent cement being
washed out of the concrete during showers.
Providence Christian College Primary School Stage 1 Page 8 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
When a pour is in progress and is abandoned due to worsening conditions, it shall be carried to or
subsequently cut back to a joint line to be nominated by the Architect.
Concrete shall not be deposited on ponded areas of formwork, but worked in a face to push the water ahead
of the pour.
Holes will be cut as necessary to allow entrapped water to drain out of the forms.
E. Sequence of Pours : Minimise shrinkage effect by pouring the sections of the work between construction
joints in a sequence such that there will be suitable time delays between adjacent pours.
Minimum Time Delay Schedule
Between (pour locations) Minimum period between
adjacent pours (days)
Adjacent pours abutting vertical construction joints 7 days
in walls
Adjacent pours abutting horizontal construction 7 days
joints in walls or columns
"Pour strips" and adjacent concrete 14 days
F. Compaction
1. General: Remove air bubbles and fully compact the mix.
2. Methods: Use immersion and screed vibrators accompanied by hand methods as appropriate.
3. Vibrators: Do not allow vibrators to come into contact with partially hardened concrete, or
reinforcement embedded in it. Do not use vibrators to move concrete along the forms. Avoid over-
vibration that may cause segregation.
G. Placing Records : Keep on site and make available for inspection a log book recording each placement of
concrete, including the following:
Date.
The portion of work.
Specified grade and source of concrete.
Slump measurements.
Volume placed.
6.3 Cold Weather Placing
A. General : Maintain the temperature of the freshly mixed concrete within the limits shown in the Cold weather
placing table. "Outdoor" air temperature applies to the air temperature at the time of mixing and to the
predicted or likely air temperature at any time during the subsequent 48 hours.
Cold Weather Placing Table
Outdoor air temperature Temperature
of concrete
Minimum Maximum
Less Than 5oC 10oC 32oC
Greater Than 5oC 18oC 32oC
B. Additives : Do not provide calcium chloride, salts, chemicals or other material in the mix to lower the freezing
point of the concrete.
C. High Early Strength Cement : Provide in severe weather conditions to enable the concrete to develop
sufficient strength to permit formwork removal within the specified time. Do not provide as a substitute for the
heating of materials or for adequate protection of placed concrete against low temperatures. Do not provide
high alumina cement.
D. Heating : Heat the concrete materials, other than cement, to the minimum temperature necessary to ensure
that the temperature of the placed concrete is within the limits specified. Maximum temperature of water:
60oC when it is placed in the mixer.
6.4 Hot Weather Placing
A. Mixing : Surrounding outdoor shade temperature > 38oC: Do not mix concrete.
B. Handling : Prevent premature stiffening of the fresh mix and reduce water absorption and evaporation losses.
Mix, transport, place and compact the concrete as rapidly as possible.
Providence Christian College Primary School Stage 1 Page 9 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
C. Placing : Before and during placing maintain the formwork and reinforcement at £ 32oC using protection, cold
water spraying, or other effective means. When placed in the forms, the temperature of the concrete must not
exceed the criteria in the Hot weather placing table.
Hot Weather Placing Table
Concrete element Temperature limit
Normal concrete in footings, beams, columns, 35oC
walls and slabs
Concrete in large mass concrete sections; or 27oC
concrete of strength 40 MPa or greater,
in sections exceeding 600 mm in
thickness
D. Temperature Control Methods : Select one or more of the following methods of maintaining the specified
temperature of the placed concrete:
Use chilled mixing water.
Spray the coarse aggregate using cold water.
Cover the container in which the concrete is transported to the forms.
Cool the concrete using liquid nitrogen injection before placing.
6.5 Curing
A. General
1. Protection: Protect fresh concrete, during the curing period, from premature drying and from
excessively hot or cold temperatures.
2. Curing period: Cure continuously until the total cumulative number of days or fractions of days,
during which the air temperature in contact with the concrete is above 10oC, is at least the following:
Fully enclosed internal surfaces: 3 days.
Other surfaces: 7 days.
B. Curing Componds
1. Standard: To AS 3799 or ASTM-C309.
2. Substrates: Do not use wax-based or chlorinated rubber-based curing compounds on surfaces forming
substrates to concrete toppings and cement-based render.
3. Application: Provide a continuous flexible coating without visible breaks or pinholes, which remains
unbroken at least seven days after application.
C. Hot Weather Curing : Do not use curing compounds. After placement, either
1. immediately cover the concrete using an impervious membrane, or hessian kept wet, until curing
begins; or
2. if the temperature exceeds 35oC or if not protected against drying winds, protect the concrete using a
fog spray application of aliphatic alcohol evaporation retardant.
D. Curing of concrete containing ≥30% fly ash cement replacement:
1. A high quality curing compound (90% min retention to ASTM C309 or AS/NZS 3799) must be applied
as soon as possible after finishing the concrete.
2. After final setting, water curing shall be applied for 14 days. A curing compound only is not suitable.
3. For formed concrete components such as columns and walls, shuttering is to remain in place for a
minimum of 7 days. Where ambient temperature is less than 15°C this is to be 10 days.
4. Take all necessary measures to keep the concrete moist during finishing.
6.6 Protection
A. Loading
1. Notice: Give notice before loading the concrete structure.
2. Protection: Protect the concrete from damage due to load overstresses, heavy shocks and excessive
vibrations, particularly during the curing period. Do not place construction loads on self-supporting
structures which will overstress them.
B. Surface Protection : Protect finished concrete surfaces from damage.
Providence Christian College Primary School Stage 1 Page 10 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
7. JOINTS
7.1 Construction Joints
A. Location : Do not relocate or eliminate construction joints, or make construction joints not shown on the
drawings. This includes emergency construction joints made necessary by unforeseen interruptions to the
concrete pour.
B. Joint Preparation : Roughen and clean the hardened concrete joint surface, remove loose or soft material,
free water, foreign matter and laitance. Dampen the surface just before placing the fresh concrete. Additional
joints in the factory or warehouse slabs on grade are not permitted and any unfished section will need to be
demolished and replaced.
C. Finish at Construction Joints : Butt join the surfaces of adjoining pours. In visually important surfaces make
the joint straight and true, and free from impermissible blemishes relevant to its surface finish class.
7.2 Expansion Joints
A. Jointing Materials
1. Type: Provide jointing materials compatible when used together, and non-staining to concrete in visible
locations.
2. Foamed materials (in compressible fillers): Closed-cell or impregnated types which do not absorb
water.
3. Bond breaking: Provide back-up materials for sealants, including backing rods, which do not adhere to
the sealant. They may be faced with a non-adhering material.
B. Jointing Material Schedule
Location of joint Jointing material
Primer Backing rod Sealant
Vertical Joint 10mm n/a Closed cell Tremco Mono
555 or
approved
equivalent
Fire Rated 10mm n/a Closed cell Sika Firerate or
approved
equivalent
Horizontal Joint 10mm n/a Closed cell Tremco Mono
555 or
approved
equivalent
C. Joint Filling
1. Preparation: Before filling, dry and clean the joint surfaces, and prime.
2. Joint filling: Fill with jointing materials. Finish visible jointing material neatly flush with adjoining
surfaces.
3. Watertightness: Apply the jointing material so that joints subject to ingress of water are made
watertight.
7.3 Waterstops
Provide waterstops as specified on the drawings where required.
Providence Christian College Primary School Stage 1 Page 11 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
9. FINISHES GENERAL
9.1 Tolerances
A. Tolerance Classes : Determine tolerance classes using a straight edge placed anywhere on the surface in
any direction.
B. Tolerances Class Table
Class Measurement Maximum deviation
(mm)
A 3 m straight edge 3
B 3 m straight edge 6
C 600 mm straight edge 6
Providence Christian College Primary School Stage 1 Page 12 of 13 SECTION 03100 CONCRETE
SECTION 03100 CONCRETE
brick until a uniform colour and texture are produced. Do not provide cement grout other than the paste
drawn from the green concrete by the rubbing process.
C. Exposed Aggregate Finish : Remove the forms while the concrete is green. Wet the surface and scrub using
stiff fibre or wire brushes, using water freely, until the surface film of mortar is mechanically removed without
the use of acid etching, and the aggregate uniformly exposed. Rinse the surface with clean water.
D. Bush Hammered Finish : Remove the minimum matrix using bush hammering to expose the coarse
aggregate without recessing the matrix deeper than the aggregate, to give a uniform texture with insignificant
random tool marks.
E. Floated Finishes
1. Sand floated finish: Remove the forms while the concrete is green. Wet the surface and rub using a
wood float. Rub fine sand into the surface until a uniform colour and texture are produced.
2. Grout floated finish: Remove the forms while the concrete is green. Dampen the surface and spread,
using hessian pads or sponge rubber floats, a slurry consisting of one part cement (including an
appropriate percentage of white cement) and one and a half parts sand passing a 1 mm sieve.
Remove surplus until a uniform colour and texture are produced. Cure.
F. Blasted Finishes
1. Abrasive: Blast the cured surface using hard, sharp graded abrasive fine aggregate particles until the
coarse aggregate is in uniform relief.
2. Light abrasive: Blast the cured surface using hard, sharp graded abrasive fine aggregate particles to
provide a uniform matt finish without exposing the coarse aggregate.
10.3 Schedule
Integral Finishes Schedule : Refer to drawings for finishes type and location.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 13 of 13 SECTION 03100 CONCRETE
SECTION 03310 Brick and Block Construction
1 GENERAL
1.1 SCOPE
General
Supply and build all the brick/blockwork shown on the Drawings or needed to complete the works,
including but not limited to the following:
- All labour and materials
- Building in of miscellaneous items provided by others
- Staging and scaffolding
- Flashings and services
- Cleaning
Specifically
- 90mm core filled blockwork as shown on the drawings.
- 140mm core filled blockwork as shown on the drawings.
- 190mm core filled blockwork as shown on the drawings.
- 90mm brickwork as shown on the drawings.
1.2 QUALITY ASSURANCE
Provide manufacturer's certification that bricks and blocks supplied are of the specified type and
strength, and were manufactured in accordance with AS 1225, AS 1653 or AS 2733.
1.3 REFERENCE STANDARDS
Comply with applicable portions of the following Australian Standards:
AS/NZS 1576 Scaffolding
AS 1684 Residential timber-framed construction
AS 2423 Coated Steel Wire Fencing Products for Terrestrial, Aquatic and General Use
AS 3660 Termite Management
AS 3700 Masonry Structures including all The Standards to which it refers (Clause 1.2).
AS/NZS 4671 Steel Reinforcing Materials
1.4 DELIVERY, HANDLING AND STORAGE
Coordination
- Reach agreement with the Architect about site provision for storage of sand, cement and other
materials and for mixing of mortar.
- Deliver, handle and store products in accordance with manufacturer's recommendations and
prevent damage, deterioration or loss.
2 QUALITY
2.1 SUBMISSIONS
Requirement
- Before installation commences, obtain and submit the following data:
- Manufacturer's data: The manufacturer's published product data, including
- Technical specifications;
- Recommendations for installation; and
- Type test or factory test data.
- Product warranties: The manufacturer's written statement certifying that the product complies with
the specification and is suitable for the intended use.
Providence Christian College Primary School Stage 1 Page 1 of 7 SECTION 03100 CONCRETE
SECTION 03310 Brick and Block Construction
2.2 SAMPLES
Requirement
- Submit samples of the following:
- Masonry units: Not less than six units of each type, representing the total range of variation of
colour, texture, surface irregularities (including defective arises), and regularity of shape.
- Sand: A 2 kg sample of sand, where required to be from a particular source or of a particular colour.
2.3 SAMPLE PANELS
Facework
- Prepare in a suitable position, or where directed, a sample panel of facework, double sided with
capping as specified or detailed.
Facework Type
- Face units as specified to be laid in stretcher bond.
- Minimum size (face of panel) 1800 (H) x 1670 (W) and containing all the units specified.
- Allowing for extending panel as necessary to achieve acceptance.
The final accepted sample will form the standard to which all masonry work is to conform.
3 MATERIALS
3.1 BRICKS/BLOCKS
Solid bricks and Blockwork
- Areas where bolt fixings are required
- Cappings and top courses to all other walls
- To perimeter of head and jambs to all doors
- Window sills
Common Brickwork U.C.S.
- Midland Brick 305L x 76H x 90W Maxibricks >12 MPa
- Midland Brick 230L x 76H x 110W Common Bricks >12 MPa
Blockwork U.C.S.
- Boral Besser 390L x 190H x 90W grey smooth faced blocks. >15 MPa
- Boral Besser 390L x 190H x 140W grey smooth faced blocks. >12 MPa
- Boral Besser 390L x 190H x 190W grey smooth faced blocks >12 MPa
Face Brickwork U.C.S.
- Midland Brick 290L x 162H x 90W Opal Blush face bricks >12 MPa
- Midland Brick 290L x 76H x 90W Opal Blush face bricks >12 MPa
(refer to drawings for coursing layout)
3.2 MORTAR AND GROUT MATERIALS AND TYPES
Materials
Comply with AS 3700 as follows:
- Mortar: Restrict the amount of fine aggregate passing a 75 micron test sieve to 5% maximum.
- Grout: Clause 3.5, 10.7
Types
Comply with AS 3700; Clauses 2.23.1, 3.3 and 10.4, 10.7 and Table 10.1, providing materials in the
proportions described below:
- Mortar:
Mix Proportions
Classification Portland Cement Lime Sand
M3 1 1 6
M4 1 0.5 4.5
Providence Christian College Primary School Stage 1 Page 2 of 7 SECTION 03100 CONCRETE
SECTION 03310 Brick and Block Construction
4 EXECUTION
4.5 LAYING
- General: Comply with all applicable provisions of AS 3700. Set out all brickwork and blockwork so
as to reduce cutting to a minimum and, in facework, to avoid irregular or broken bond.
- Make cuts in facework with a masonry saw only. Carefully position openings for other trades to
eliminate cutting.
- Build in accordance with the dimensions, thicknesses and heights shown on drawings, plumb, level
and in the designated position within the tolerances of AS 3700, clause 11.5
- Allow no part to rise more than 1000mm above adjacent unfinished work. Rake back advanced
work, build all blockwork in bond and avoid toothing wherever possible.
- Build in as necessary all reinforcements, arch bars, lintels, frames, straps, bolts, lugs, wall ties,
metalwork, damp-proof courses and flashings, etc.
- Re-lay, in fresh mortar, bricks/blocks accidentally moved after initial laying.
- Keep mortar stains to a minimum and protect horizontal ledges, finished sills and the like from
mortar droppings as work proceeds.
- Before mortar sets hard, remove excess mortar. Scrub brickwork and blockwork within 24 hours of
laying using a bristle brush plus detergent if necessary. Removal of excess mortar with acid is not
permitted.
- Protect new and incomplete brickwork with coverings, temporary bracing or the like - AS 3700,
clause 11.9.
- Form control joints where directed by the Architect and in accordance with AS 3700. Unless noted
otherwise, the maximum unjointed length of wall to be 10m.
4.6 DAMP-PROOF COURSES
Location
General
- Provide damp-proof courses as follows:
. Timber floors: In the first course below the level of the underside of ground floor timbers in
internal walls and inner leaves of cavity walls.
. Cavity walls built off slabs on ground: In the bottom course of the outer leaf, continuous
horizontally across the cavity and up the inner face bedded in mortar, turned 30 mm into the inner
leaf 1 course above.
. Masonry veneer construction: In the bottom course of the outer leaf, continuous horizontally
across the cavity. Fasten to the inner frame 75 mm above floor level.
. Walls adjoining infill floor slabs on membranes: In the course above the underside of the slab in
internal walls and inner leaves of cavity walls. Project 40 mm and dress down over the membrane
turned up against the wall.
Height
- Not less than:
. 150 mm above the adjacent finished ground level.
. 75 mm above the finished paved or concrete area.
. 50 mm above the finished paved or concreted area and protected from the direct effect of the
weather.
Installation
- General: Lay in long lengths. Lap full width at angles and intersections and at least 150 mm at
joints. Step as necessary, but not exceeding 2 courses per step for brickwork and 1 course per step
for blockwork. Sandwich damp-proof courses between mortar.
- Junctions: Preserve continuity of damp-proofing at junctions of damp-proof courses and waterproof
membranes.
- Lap sealing: Seal with a bituminous adhesive and sealing compound.
4.7 SLIP JOINTS
General
Provide slip joints to top of all vertically unreinforced masonry walls supporting concrete slabs and
other concrete elements.
Protection
Keep the slip joints in place and protect from displacement.
Providence Christian College Primary School Stage 1 Page 5 of 7 SECTION 03100 CONCRETE
SECTION 03310 Brick and Block Construction
- Commencement: Do not commence until grout spaces have been cleaned out and the mortar joints
have attained sufficient strength to resist blow-outs.
- Height of lift: Limit the height of individual lifts in any pour to make sure that the grout can be
thoroughly compacted to fill all voids.
- Compaction: Compact by vibration or by rodding.
- Topping up: On the completion of the last lift, top up the grout after 10 min to 30 min, and vibrate or
rod to mix with the previous pour.
4.14 INCIDENTAL WORK
- Chases: Refer to AS 3700, Clause 11.4 and, as far as possible, provide for chases to be made as
the work rises. No horizontal chase will be allowed and no vertical chase may be closer than
600mm to an element providing lateral support. No chase may be more than 20mm deep. Diagonal
chases are not permitted. Perform all miscellaneous incidental blockwork as required throughout
and for other trades. Make good after other trades.
- Build-in flashings progressively with all steelwork, plumbing and electrical items within cavities
separated from external leaf with flashings bent around and taken 100mm beyond.
- Perform all miscellaneous incidental blockwork as required throughout and for other trades. Make
good after other trades.
4.15 COMPLETION
- Complete all contracted work in accordance with contract documents and written variation orders
issued by the Architect.
- On completion clean up all mortar droppings, debris, etc., remove all scaffolding, make good all
putlog holes and blemishes and leave all work in a first class condition.
- Protect all facework surfaces where necessary to avoid damage during other building operations.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 7 of 7 SECTION 03100 CONCRETE
SECTION 03360 CONCRETE FINISHES
PART I GENERAL100
101 Scope
The work of this section includes but is not limited to:
Preparation supply and execution of concrete finishes as shown on Finishes Schedule and in full
accordance with the non-slip requirements for all floor finishes in concrete.
Note that applied floor finishes such as epoxy coatings and concrete sealers are to be provided in full
accordance with the product manufacturer’s specifications and to an approved sample panel for each of
the listed finishes.
Off form concrete surfaces are subject to specific quality control measures and are to be specified with
full colour and tolerance level requirements as applicable to each of the listed types.
Preparation supply and installation of bagged finish.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1379 2007 Specification and supply of concrete. Plus Supplement 1-2008 and 2 Amdts
2009, 2015.
AS 3610.1 2010 Formwork for concrete –Documentation and surface finish.
AS 3700 2011 Masonry structures. There is 1 Supplement 2012, 2 Amdts, 2012, 2015
AS 3799 1998 Liquid membrane-forming curing compounds for concrete.
HB 64 2002 Guide to concrete construction. Chapters 8 and 15.
HB 198 2014 Guide to the specification and testing of slip resistance of pedestrian surfaces
CIA Z39-2008 Render finishes.
106 Submissions
The architect will supply to the contractor a sample of the required material from the range obtained from
the supplier.
The sample will indicate all aspects of the required finish, size of granules, colour, texture, finish etc.
An appropriate supplier's specification may be available from the architect.
107 Warranty
Provide a warranty to the proprietor covering cracking, peeling and fading for a period of years.
PART II MATERIALS200
201 General
Formed concrete finishes: Provide formed concrete finishes with off form concrete surfaces
conforming to control panel installation for tolerance levels and to colour control measures to ensure
compliance with Class 2 finish.
Show all visible components of the finished surface on the control panel and carry out all modifications
to ensure compliance.
Obtain approval from the architect prior to commencing work.
Unformed concrete finishes: Provide non slip self-finished floor surfaces meeting the listed R value for
the non-slip and to finishes listed within the Finishes Schedule.
Coordinate floor finishes with provision of line markings and tactile indicators where required for the
Access provisions of the Building Code of Australia.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 03360 CONCRETE FINISHES
Applied concrete finishes: Provide applied finishes to specific locations scheduled on the Interior and
Exterior Finishes Schedule, all to approved submission of samples.
Ensure non slip finish to floors.
202 Materials
Concrete surface Finish Comments
Floors -sealed concrete Fosroc Nitroflor 150 HP-FC Refer to Interior Finishes
Schedule
External walkway screed Dulux Avista Waterbased Refer to Exterior Finishes
Concrete Sealer Schedule
Exposed concrete columns Class 2 off form finish with Fosroc Refer to Exterior Finishes
Nitocote SN502 penetrating Schedule
sealer
301 Examination
Inspect surfaces to be treated and notify architect of any discrepancy or unsuitability of substrate and
carry out all remedial work to suit.
Comply with manufacturer's recommendations
Start of work means total acceptance of conditions.
302 Preparation
Make good damage in every respect at no additional cost to the proprietor.
Provide and install required scaffolding, hoisting equipment, etc. in accordance with statutory authority
regulations.
Mask dissimilar materials adjacent to surfaces to be treated in order to avoid contact, e.g. metal frames
and cappings.
303 Application
Apply in accordance with manufacturer's recommendations or approved sample regarding mixing of
materials and application methods.
304 Finish
Match approved sample panel
305 Protection
Protect finished surfaces against damage until Practical Completion.
306 Cleaning
At completion of work remove debris, scaffolding, erection materials, etc. and leave surfaces in a
condition entirely satisfactory to the architect.
307 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 03360 CONCRETE FINISHES
SECTION 03410 Structural steelwork
1.1 DEFINITIONS
For the purposes of this specification, the definitions included in AS/NZS 5131 and the following apply:
- Contractor: the party responsible for the relevant scope of work. The contractor shall be designated
by the contractual documentation.
- Hold point: an identified point in a process beyond which the relevant work cannot proceed without
approval.
- Project Drawings: the set of drawings that describe in a diagrammatic fashion the extent and detail
of the Works and the relationship of the Works to the overall construction. The Project Drawings
may include the detail necessary to fabricate and erect the Works, depending on the contractual
relationships established for the project.
- Steelwork: the fabricated structural steel.
- Witness point: An identified point in a construction process at which an activity is observed.
1.2 ABBREVIATIONS
For the purposes of this specification, the following abbreviations apply:
- AESS: Architecturally exposed structural steelwork
- ASI: Australian Steel Institute
- CC: Construction Category (CC1, CC2, CC3, CC4)
- CompMP: Compliance Management Plan
- EPD: Environmental Product Declaration
- ESC: ASI Environmental Sustainability Charter
- ESM: Erection Sequence Methodology
- FC: Fabrication Category (FC1, FC2)
- IL: Importance Level
- ILAC: International Laboratory Accreditation Cooperation
- ITP: Inspection and Test Plan
- MDR: Manufacturer’s Data Report
- NDE: Non-Destructive Examination
- NSSCS: The ASI National Structural Steelwork Compliance Scheme
- PC: Coating quality level
- QP: Quality Plan
- SC: Service Category (SC1, SC2)
- SDoC: Supplier Declaration of Conformity
- SCA: Steelwork Compliance Australia
- UNO: unless noted otherwise
- WPQR: Welding Procedure Qualification Record
- WQR: Welder Qualification Record
- WPR: Welding Procedure Record
- WPS: Welding Procedure Specification
Providence Christian College Primary School Stage 1 Page 1 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
2 GENERAL
2.2 RESPONSIBILITIES
Table B.3 of AS/NZS 5131 details a list of responsibilities to be assigned.
For the responsibilities assigned under the scope of the project contract, if requested, the steelwork
contractor shall provide a list of named personnel and organisations corresponding to the entries in
Table B.3 of AS/NZS 5131 at least 5 working days prior to the respective portion of the works being
undertaken.
All work on this project shall be undertaken by competent personnel. Requirements and examples of
qualifications for competent personnel are contained in AS/NZS 5131.
Comply with: Importance Level 2, Region A1; Terrain Category 2.5
Product substitution
Conform to PRODUCTS, GENERAL, Substitutions in the Preliminaries work section.
2.3 CONFLICTS
If there is a conflict in specified requirements, such conflicts shall be documented, advised to relevant
parties and resolved using a managed process.
Providence Christian College Primary School Stage 1 Page 2 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
3 REFERENCED DOCUMENTS
3.1 STANDARDS
The following Standards and codes applicable to and referenced in this Specification shall be
regarded as describing the minimum standard of materials and workmanship to be provided:
Standard Title
AS 1111 ISO metric hexagonal commercial bolts and screws
AS/NZS 1163 Cold-formed structural steel hollow sections
AS/NZS 1214 Hot-dip galvanized coatings on threaded fasteners (ISO metric coarse thread
series) (ISO 10684:2004, MOD)
AS/NZS 1252.1 High-strength steel bolt assemblies comprising bolts, nuts and washers for
structural engineering – Part 1: Technical requirements
AS/NZS 1252.2 High-strength steel bolt assemblies comprising bolts, nuts and washers for
structural engineering – Part 2: Verification testing
AS 1397 Continuous hot-dip metallic coated steel sheet and strip – Coatings of zinc and
zinc alloyed with aluminium and magnesium
AS/NZS 1554 Structural steel welding (several parts, as applicable)
AS/NZS 1594 Hot-rolled steel flat products
AS 1627.4 Metal finishing – Preparation and pre-treatment of surfaces – Abrasive blast
cleaning of steel
AS 1710 Non-destructive testing – Ultrasonic testing of carbon and low alloy steel plate
and universal sections – Test methods and quality classification
AS 2207 Non-destructive testing – Ultrasonic testing of fusion welded joints in carbon and
low alloy steel
AS/NZS 2312.1 Guide to the protection of structural steel against atmospheric corrosion by the
use of protective coatings – paint coatings
AS/NZS 2312.2 Guide to the protection of structural steel against atmospheric corrosion by the
use of protective coatings – hot-dip galvanizing
AS 1397 Continuous hot-dip metallic coated steel sheet and strip – Coatings of zinc and
zinc alloyed with aluminium and magnesium
AS 3597 Structural and pressure vessel steel – Quenched and tempered plate
AS/NZS 3678 Structural steel – Hot-rolled plates, floorplates and slabs
AS/NZS 3679.1 Structural steel – Part 1: Hot-rolled bars and sections
AS/NZS 3679.2 Structural steel – Part 2: Welded I sections
AS 3750.1 Paints for steel structures Epoxy mastic (two-pack) – For rusted steel
AS 3894.3 Site testing of protective coatings – Determination of dry film thickness
AS 3894.4 Site testing of protective coatings – Assessment of degree of cure
AS 3894.5 Site testing of protective coatings – Determination of surface profile
AS 3894.6 Site testing of protective coatings Determination of residual contaminants
AS 4100 Steel structures
AS/NZS 4600 Cold-formed steel structures
AS/NZS 4680 Hot-dip galvanized (zinc) coatings on fabricated ferrous articles
AS/NZS 5131 Structural steelwork – Fabrication and erection
SA TS 101 Design of post-installed and cast-in fastenings for use in concrete
SA TS 102 Structural steel – Limits on elements added
SA TS 103 Welding to AS/NZS 1554 Parts 1, 5 and 7 – Limits on boron in parent materials
Providence Christian College Primary School Stage 1 Page 3 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Providence Christian College Primary School Stage 1 Page 4 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
4.8 SUBMITTALS
The submittals required are defined in AS/NZS 5131. The timing on specific submittals shall be:
Providence Christian College Primary School Stage 1 Page 5 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Before fabrication is commenced, submit to the Superintendent for examination an electronic PDF set
of the approved shop drawings including marking diagrams and a 3D model of the structural
steelwork. Free software capable of reviewing the model and a hardcopy set of the drawings must be
provided if requested by the Superintendent. Alternatively provide an electronic PDF set of the shop
drawings including marking diagrams as well as a hardcopy set of the drawings.
Examination of the drawings shall not be construed as relieving the Contractor from the responsibility
for ensuring that the work is complete and accurate.
If the drawings are to be submitted in stages, a key or location plan shall be submitted with each
stage.
No fabrication shall commence until shop drawings relating to that part have been reviewed.
Execution details
Subcontractors
If requested, submit names and contact details of any proposed fabricator, detailer, surface
preparation contractor, painter/galvanizer and erector/installer.
Fabrication
Provide documentation to demonstrate NSSCS certified fabricators or subcontractors will be utilised
for the Works.
Approval to use non-NSSCS certified fabricators must be formally requested and approved. In this
case, documentation shall be provided to demonstrate compliance with AS/NZS 5131.
If requested, submit a fabrication program showing the proposed sequence of operations and time
required.
If requested, submit plan for the marking of members to ensure material and component traceability
meets the requirements of AS/NZS 5131.
If requested, submit the completed ‘Supplier declaration of conformity’ (SDoC) for the fabricated
structure or components, as defined in AS/NZS 5131.
Erection documentation
If requested, submit the ‘Erection Sequence Methodology’ (ESM) as defined in AS/NZS 5131 for
review and approval.
If required by the ESM, submit calculations to justify the adequacy of the structure for the intended
erection methodology.
Connections
If requested for bolted connections, submit inspection records for completed installation.
If requested for bolted connections not fully documented, submit proposals for approval.
If requested for bolted connections requiring rectification, submit proposals for approval before
proceeding.
For anchor bolts that do not meet documented location tolerances, submit proposals for rectification
for approval before proceeding.
For temporary connections, if not documented, submit proposals for approval.
If splicing of structural members is proposed, submit details for approval.
Structural steel members shall be in single lengths unless otherwise shown on the shop drawings and
approved by the Superintendent. Splices and joints shall develop the full strength of the members
connected unless otherwise shown on the Structural Drawings.
Where alternative anchors are proposed, submit documentation for approval to substantiate the
anchor capacity to carry the load where mechanical or chemical anchors are required or proposed for
the support or fixing of structural steel.
Steelwork exposed to view
If requested, submit details of proposed member, connection and component marking for steelwork
identified as AESS or otherwise exposed to view.
Rectification works
Proposals for rectification works shall be submitted in writing and approved before being undertaken.
Non-conforming work
Where a section of the Works does not comply with the requirements of the specification and the
Project Drawings (including requirements for inspection and testing), the Contractor shall submit a
non-conformance report detailing the non-conformance and the proposed rectification method for
Providence Christian College Primary School Stage 1 Page 6 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
approval. Where deemed necessary, the non-conformance report may be reviewed and/or inspected
by the relevant consultant(s).
4.9 INSPECTION
Inspection scheduling
Refer Section 4.8 Submittals for inspection notice.
Inspection points
So that inspection may be made, provide notice at the following stages:
- Testing of welding procedures and welder qualification tests.
- Commencement of shop fabrication
- Commencement of surface preparation prior to protective coating
- Completion of protective coating before delivery to site.
- Steelwork on site before erection.
- Commencement of site erection
- Anchor bolts in position before casting in.
- Completion of erection prior to enclosing with cladding or finishes.
No roof or wall cladding nor other finishes shall be installed until the Engineer has inspected the
completed steel framework. The Contractor shall provide reasonable and safe access to all elements
of the work to allow the Engineer to undertake these inspections. The Contractor shall be responsible
for all expenses and allow for the time associated with these requirements.
5.1 GENERAL
Members and components shall be packed, supported, lifted and transported in a manner to prevent
distortion, loss of camber or damage to the steelwork and its protective coating.
Damaged items shall be reported and rectified or replaced. Where rectified, the method of rectification
shall be subject to approval.
Documentation supplied with materials and components shall conform to the requirements of
AS/NZS 5131.
Providence Christian College Primary School Stage 1 Page 7 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
UNO all bolts except holding down and purlin bolts to be Grade 8.8.
Bolt assembly verification
High strength bolt assemblies to AS/NZS 1252.1 shall be verified to AS/NZS 1252.2. Documentation
to meet the requirements of AS/NZS 1252.2 shall be provided.
Bolt finish
All bolts shall be hot dip galvanized to AS/NZS 1214 UNO. Refer Project Drawings for additional
requirements.
Nominal yield strength of steel to be welded Nominal tensile strength of weld metal, fuw
(MPa)
All steel with Grade ≤ 300 MPa 430
All steel with 300 < Grade ≤ 450 MPa 490
Quench & tempered steel to Grade 690 MPa 760
Providence Christian College Primary School Stage 1 Page 8 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
5.12 TESTING
Lamellar tearing
If required, joint details which are susceptible to lamellar tearing (LT) are indicated on the Project
Drawings as “LT susceptible”. The identified plate in joints that have been assessed as ‘LT
susceptible’ shall be ultrasonically tested to AS 1710 Class 1.
Z-plate requirement
Joints that are designated ‘LT susceptible’ (see Section 5.12 Testing - Lamellar tearing) and further
require plate to a nominated Z-value are indicated on the Project Drawings with a designated Z-value.
The plate identified in these joints shall be ordered to the designated Z-value and shall be
ultrasonically tested to AS 1710 Class 1.
Supplementary ultrasonic testing
Supplementary ultrasonic testing to AS 1710 Class 1 is required for all plates 40mm thickness and
over.
6.1 GENERAL
Operations comprising cutting, shaping, holing and assembly into fabricated components shall
conform to the requirements of AS/NZS 5131.
Particular requirements from AS/NZS 5131 are outlined in Section 0
Providence Christian College Primary School Stage 1 Page 9 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Particular requirements, together with a reference to the applicable clause in AS/NZS 5131.
Providence Christian College Primary School Stage 1 Page 10 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
7 WELDING
7.1 GENERAL
Welding shall conform to the requirements of AS/NZS 5131.
Particular requirements from AS/NZS 5131 are outlined in Section 0
Providence Christian College Primary School Stage 1 Page 11 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Weld category, together with a reference to the applicable clause in AS/NZS 5131.
Minimum nominal tensile strength of weld metal to be 430MPa.
All welds to achieve full strength of the connecting element. Where full strength can be obtained by
fillet welds, welding is to be a minimum of 6mm fillet weld continuous all around unless drawn and
detailed otherwise.
All welds shall be SP quality unless noted otherwise.
Fillet welds performed on site are to be GP quality.
All Complete Penetration Butt Welds (CPBW) shall be SP quality.
Providence Christian College Primary School Stage 1 Page 12 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Weld categories for specific details are indicated on the Project Drawings.
Providence Christian College Primary School Stage 1 Page 13 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Clause in
AS/NZS 5131
Acceptance criteria
Alternative acceptance criteria 7.6.1
No additional requirements.
Alternative assessment of nonconformity 7.6.1
No additional requirements.
Fatigue design assumptions 7.6.3
No additional requirements.
8 MECHANICAL FASTENING
8.1 GENERAL
Mechanical fastening shall conform to the requirements of AS/NZS 5131.
Type /TB and /TF bolts are to be tightened using either the part-turn method or load indicating
washers. Where the part-turn method is used, the nut and shank are to be clearly marked to allow
easy visual identification of degree of turn.
Where load indicating washers are proposed, if requested, provide manufacturer installation data to
the engineer prior to installation. Ensure all washers required by the manufacturer are installed in the
correct location relative to the part to be turned prior to tightening.
Particular requirements from AS/NZS 5131 are outlined in Section 8.2 Particular requirements,
together with a reference to the applicable clause in AS/NZS 5131.
9.1 GENERAL
Surface treatment and corrosion protection shall conform to the requirements of AS/NZS 5131.
The Coating Quality Level (PC1, PC2) shall be assessed according to AS/NZS 5131.
Providence Christian College Primary School Stage 1 Page 14 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
All surfaces shall be coated as specified within 4 hours of surface preparation for shop work and 2
hours for field work. In unfavourable locations these times may have to be decreased.
Surface treatment to AS2312-2002 (unless noted otherwise).
Durability – Years to first maintenance: Exposed (visible) 15 years
Concealed 25+ years
Paints referenced below are based on Dulux Protective Coatings. Thicknesses are Minimum Dry Film
Thickness.
Type A Class 2.5 blast clean. 75µm Zincanode 304. (IZS1)
Type B *Class 2.5 blast clean. 75µm Zincanode 402, 200µm Duramax GPE, 75µm Weathermax
HBR (Colour selected by Superintendent) (PUR5)
Type C 2 coats at 200µm Durabild STE over other coating types. Extend to 100mm above
paving, slab or ground level. For Type B, apply after zinc rich primer coat.
Type D Hot Dip Galvanised to 600g/m2 minimum coating mass.
* Ensure compatibility of all coatings.
Surface Atmospheric Parts of Steel Work
Treatment Corrosivity Category
Type A C1 or C2 Internal or External Concealed Steelwork
Type B C1 or C4 Visible Internal Steelwork or Steelwork
Exposed to Weather
Type C C5 Members in contact with the ground or below
finished floor level. (extend 100mm above
surface level).
Type D C4 Members in Cavity of External Brick Walls
including lintels.
Red oxide zinc phosphate shall comply with AS/NZS 3750.20 to a minimum dry film thickness of 50
microns.
Inorganic zinc silicate shall comply with AS/NZS 3750.15 to a minimum dry film thickness of 75
microns.
Paint systems to be all from the same manufacturer.
Particular requirements from AS/NZS 5131 are outlined in Section 9.2 Particular requirements,
together with a reference to the applicable clause in AS/NZS 5131.
Providence Christian College Primary School Stage 1 Page 15 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Clause in
AS/NZS 5131
- Checks for the presence of measurement of and removal of soluble salts or non-
visible contaminants to be in accordance with AS 3894.6.
Damaged coatings 9.2.3.1
After erection and/or site welding make good any damage to shop finish immediately
after cleaning.
Steelwork specified as coated with inorganic zinc silicate shall have damage made
good with 2 coats of a zinc rich epoxy primer such as Dulux Zincanode 202 to a
minimum dry thickness of 100 microns.
Wherever damage occurs to a galvanised surface or edge, prepare surface to ST3,
degrease area, apply two coats of an approved 2 part cold galvanising compound or an
approved zinc rich paint strictly in accordance with manufacturer’s requirement to
provide a total film thickness of 0.1 mm. Finish with an Aluminium paint, blended into
the surrounding area to the Architects satisfaction.
Steelwork specified as painted with red oxide zinc phosphate shall be repaired with a
red oxide zinc phosphate applied to a minimum dry thickness of 50 microns.
For all other Coatings, including duplex Coatings:
- Site Repairs (e.g. after site welding)
. Bristle blast or power tool clean area to be treated. Apply 200µm Dulux Durebild
STE. Where Architectural finish is required, apply suitable primer and final coat to
suit the required treatment.
- Apply finish coats in accordance with Architectural requirements.
Where exposed to view touch up must be consistent with architectural finish. Provide a
coloured top coat to the approval of the Architect.
All touch up paints are to be applied in accordance with the recommendations of the
manufacturer immediately after cleaning.
Providence Christian College Primary School Stage 1 Page 16 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Clause in
AS/NZS 5131
Requirements for hot-dip galvanizing 9.2.3.2
Hot-dip galvanizing shall comply with AS/NZS 4680.
- Where steel is specified as being galvanised, prepare surface to Class 2½ AS
1627.4 and then treat by pickling and neutralising in accordance with the best trade
practice.
- Carry out galvanising to steel members by the Hot Dip process in accordance with
AS/NZS 4791 and 4792 to provide a uniform zinc coating thoroughly adherent and
weighing at least 600 g per square metre for general purposes.
- Galvanise bolts and nuts by the hot dip process in accordance with AS 1214.
Internal threads shall be tapped after galvanising. Surplus zinc shall be removed
from external threads by centrifuging, brushing or similar. External threads shall not
be recut.
- Take care with all members, but in particular with unsymmetrical sections such as
angles and channel members, to avoid distortion. Members may be straightened by
an approved method to achieve the original shape, provided the galvanised coating
is not damaged.
- Where galvanised surfaces are affected by welding, use a zinc/tin lead alloy in a
stick form such as CIG Galvanising Bar or similar, for repair. Apply the stick to the
damaged areas after vigorous cleaning with a wire brush. Apply the stick to the weld
area while it is still hot or, alternatively, pre heat the surface to be treated to 315°C.
Spread the molten alloy with a wire brush or flexible blade.
- Where the galvanised coating is specified as architectural finish, finish to the
member the galvanising is to be architectural grade and quality. Builder is to prepare
samples for the Superintendent to view and approve if acceptable standard. An
approved sample will be used as a measure of the finish and members outside this
will be rejected and require replacement at the builders cost.
- Rough Areas surrounding the welding or cutting should be buffed to a uniform
appearance.
- Sharp edges will normally be heavily coated with zinc but may sometimes need post
galvanizing inspection and dressing.
- At the design stage, ensure that the article to be galvanised will fit inside the
galvanising bath in a single dip and discuss with galvaniser provisions for adequate
filling, venting and draining. Ensure that the design will allow even zinc runoff. This
can have a significant effect on the ability to achieve a smooth finish. As a general
rule, the drainage should be a minimum of 30% of the cross sectional area of the
article.
- Specify steel which, when galvanized, will produce a 'normal' coating in appearance.
Certain steels containing silicon and / or phosphorous can produce coatings which
can be dull or patchy grey in colour, with a rough finish and may be brittle. As a
general rule the following criteria should be used:
. % Si < 0.04 %
. % Si + (2.5 x % P) < 0.09 %
. While dull coating denotes thicker and longer lasting protection, appearance is
adversely affected.
- In extreme cases shot blasting of deformed surfaces may be necessary depending
on the finish required. Examples of a requirement for blasting would be structural
CHS (Circular Hollow Sections) particularly lacquer coated in the warehouse where
part removal has allowed corrosion and texture to affect the steel surface.
- Specify the steel to be galvanized in accordance with Australian Standard
AS/NZS4680 and highlight the need for the coating to be free from runs, dags,
spikes, uneven surfaces and roughness or other defects that could affect
appearance.
- Welding quality should be free from porosity; all weld slag removed and grinding
marks minimized.
Providence Christian College Primary School Stage 1 Page 17 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Clause in
AS/NZS 5131
- Inspection of the finished galvanized work must take place at the galvanizer's yard
prior to dispatch.
- To maintain optimum appearance, it is important that care be taken to ensure the
coating is not dirtied or damaged during transportation, site storage and or erection.
- If the galvanized coating is to be subsequently painted (Duplex Coating) the
galvanizer should be advised of the paint system to be used at the time of order, as
certain operating procedures may need to be taken to ensure the paint coating can
be properly applied.
- Differing time periods will temporarily show brightness variations at the early stages
of exposure but are a transitory effect.
- Care is required with site storage to provide open ventilation which prevents moisture
entrapment with resulting wet storage stain. This is normally a temporary condition
which does not affect the lift of the coating.
- As the galvanizing surface texture can vary and is dependent on steel chemical
composition, consult with the galvanizer on procurement.
For lintels less than 1km from the coast or R4 exposure classification:
Steel lintels shall have a duplex coating consisting of galvanised coating complying with
AS/NZS 4680, with a coating mass of at least 600g/m², and a coating of 50μm min. of
non-inhibitive epoxy primer (two-pack) to AS/NZS 3750.13, plus 200μm min. of high-
build epoxy micaceous iron oxide (two-pack) to AS 3750.1.
For lintels greater than 1km from the coast or R3 exposure classification:
Steel lintels hot-dip galvanised to comply with AS/NZS 4680, with a minimum coating
mass of 600g/m².
All nuts, bolts, washers, pins and other specified brackets and fastenings shall be hot
dip galvanised in accordance with AS/NZS 1214 UNO on Project Drawings.
Any galvanised steelwork receiving a paint coating shall be cleaned, degreased and
abrasive swapblast after galvanising. Alternatively submit details of paint manufactures
requirements for approval. Acid Etching shall not be used as part of the preparation.
Cold-formed sections 2.5mm and thinner shall be formed from steel strip coated in
accordance with AS 1397. Further surface treatment is not required UNO.
Preparation of steel surfaces
Preparation of exterior steelwork 9.3.2
No additional requirements.
Testing for soluble salts 9.3.2
No additional requirements.
Weather resistant steel surfaces 9.3.5
No additional requirements.
Surfaces in contact with concrete 9.3.7
No additional requirements.
Abrasive blasting
Abrasive blast cleaning 9.4.1
No additional requirements.
Alternative surface finishes 9.4.4
No additional requirements.
Sealing of enclosed spaces
Enclosed spaces 9.6.1
No additional requirements.
Sealed spaces 9.6.1
No additional requirements.
Providence Christian College Primary School Stage 1 Page 18 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Clause in
AS/NZS 5131
Fabrication and welding considerations
Rectification of surface defects 9.8.3
The fabricator shall rectify any surface defects not meeting the requirements of
AS/NZS 5131.
Surfaces to be painted 9.8.4
No additional requirements.
Surfaces to be galvanized 9.8.4
No additional requirements.
Treatment of cut edges 9.8.5
No additional requirements.
Welding and repair of pre-coated steel 9.8.6
Welding and repair of pre-coated steel shall be in accordance with the manufacturer’s
written instructions. Refer Section 9.2 Particular requirements - Requirements for
painting and galvanizing - Damaged coatings for additional information.
Application of paint coatings
Monitoring of conditions 9.9.10
Air and surface temperatures, relative humidity and dew point shall be regularly
monitored and recorded.
Testing of film continuity 9.9.16
No additional requirements.
Testing of degree of cure 9.9.17
No additional requirements.
Corrosion protection of fasteners 9.9.18
No additional requirements.
Application of galvanized coatings
Control of distortion 9.10.4
No additional requirements.
Galvanizing process – double dipping 9.10.5
Double dipping of galvanized components is permitted, subject to written approval for
the particular components.
Galvanizing process – test lot 9.10.5
No additional requirements.
End use of galvanized components 9.10.6
No additional requirements.
Adherence of coating 9.10.8
No additional requirements.
Wet storage staining 9.10.10
Wet storage staining shall be removed.
10.1 GENERAL
Architecturally exposed structural steel (AESS) shall conform to the requirements of AS/NZS 5131.
All visible steelwork to be treated as AESS3 unless the AESS category (1,2,3,4 or C) are designated
on the Project Drawings otherwise. Any comments on Project Drawings Specifying “smooth finish” is
deemed as AESS4.
If required, architecturally sensitive connection details are indicated on the Project Drawings.
Particular requirements from AS/NZS 5131 are outlined in Section 10.2 Particular requirements,
together with a reference to the applicable clause in AS/NZS 5131.
Providence Christian College Primary School Stage 1 Page 19 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
11.1 GENERAL
Structural steelwork erection shall conform to the requirements of AS/NZS 5131.
Particular requirements from AS/NZS 5131 are outlined in Section 11.2 Particular requirements,
together with a reference to the applicable clause in AS/NZS 5131.
The steelwork erection contractor shall supply and install all temporary bracing and the like necessary
for the safe erection of the structure.
The contractor shall be responsible for the temporary stability of the structure during construction.
The structure has been designed such that when all members are in place, all bolts are tightened and
all walls are in place, the system will be stable. However, there will necessarily occur intermittent
stages of partial completion when the structure may not be stable under all conditions. The Contractor
shall take adequate precautions to ensure stability and safety during these intermittent stages.
Such extra items supplied by the Contractor to expedite the erection shall remain the Contractor’s
property. All costs associated with these extra items shall be at the Contractor’s expense.
Providence Christian College Primary School Stage 1 Page 20 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
12 GEOMETRICAL TOLERANCES
12.1 GENERAL
Fabrication and erection tolerances shall conform to the requirements of AS/NZS 5131.
Particular requirements from AS/NZS 5131 are outlined in Section 12.3 Particular requirements,
together with a reference to the applicable clause in AS/NZS 5131.
Fabricate and erect beams with natural camber up.
Allow for and correct as necessary for all distortion and out of alignment caused by welding,
galvanising or other processes.
Providence Christian College Primary School Stage 1 Page 21 of 22 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
13.1 GENERAL
Inspection, testing and correction shall conform to the requirements of AS/NZS 5131.
A quality plan shall be prepared covering each stage of the fabrication of the structure.
Particular requirements from AS/NZS 5131 are outlined in Section 13.3 Particular requirements,
together with a reference to the applicable clause in AS/NZS 5131.
Providence Christian College Primary School Stage 1 Page 22 of 23 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Clause in
AS/NZS 5131
Inspection of welding
Inspection and test plan (ITP) 13.6.1.2
An ITP shall be prepared covering the inspection against the items specified in
Section 13.6.1.2 of AS/NZS 5131.
Scope of inspection after welding 13.6.2.2
The extent and type of NDE corresponding to the designated Construction Category or
Categories shall be as per Table 13.6.2.2(A) of AS/NZS 5131.
Assessment of weld defects 13.6.2.5
No additional requirements.
Welds on enclosed spaces 13.6.4
No additional requirements.
Inspection of mechanical fastening
Inspection and test plan (ITP) 13.7.1
An ITP shall be prepared covering the inspection against the items specified in
Section 13.7.1 of AS/NZS 5131.
Non-conforming mechanical fasteners 13.7.4
If the documentation supplied does not meet the requirements of AS/NZS 5131, the
mechanical fasteners shall be treated as non-conforming until such time as it can be
reliably established that the mechanical fasteners meet the requirements of
AS/NZS 5131.
Testing of mechanical fasteners 13.7.5
If testing of mechanical fasteners is undertaken to establish conformity, the type and
extent of testing shall be consistent with that specified in AS/NZS 5131 and shall be
sufficient to establish a proper statistical basis. Single or limited test results shall not be
acceptable.
Inspection of fully tensioned high strength bolted connections
Sampling plan 13.7.8
No additional requirements.
Inspection of mechanical and chemical anchors
Proof testing 13.7.11
No additional requirements.
Inspection of surface treatment
Inspection and test plan (ITP) 13.8.1
For Coating Quality Level PC2, an ITP shall be prepared covering the inspection
against the items specified in Section 13.8.1 of AS/NZS 5131.
Inspection of paint coatings
Inspection and test plan (ITP) 13.9.1
For Coating Quality Level PC2, an ITP shall be prepared covering the inspection
against the items specified in Section 13.9.1 of AS/NZS 5131.
Inspection of galvanized coatings
Inspection requirements 13.10.1
Inspection shall be undertaken according to the requirements of AS/NZS 4680.
Additional or special inspection requirements 13.10.1
No additional requirements.
Inspection of erection
Inspection and test plan (ITP) 13.11.1
An ITP shall be prepared covering the inspection against the items specified in
Section 13.11.1 of AS/NZS 5131.
Additional or special inspection requirements 13.11.1
No additional requirements.
Providence Christian College Primary School Stage 1 Page 23 of 24 SECTION 03410 STRUCTURAL STEEL
SECTION 03410 Structural steelwork
Clause in
AS/NZS 5131
Location and frequency of measurements 13.11.7
No additional requirements.
Inspection of secondary structural elements
Inspection of installation 13.12.2
An ITP shall be prepared covering the inspection of purlins and girts against the items
specified in Section 13.12.2 of AS/NZS 5131.
14.1 GENERAL
Site modifications and repair shall conform to the requirements of Section 14 of AS/NZS 5131.
15 SAFETY
The Contractor shall ensure that all aspects of the Works are carried out in accordance with the
relevant Worksafe Regulations.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 24 of 24 SECTION 03410 STRUCTURAL STEEL
SECTION 03530 CONCRETE SCREEDS
PART I GENERAL100
1. Scope
Supply and install a complete installation of granolithic surface screeds and topping mixes to the extent
and thickness as indicated on drawings or scheduled including but not limited to:
Applied granolithic screeds.
Matching coves, risers, kerbs, margins, pit covers, etc.
Float screeding, curing and protection.
Polished concrete topping mix.
Ensure that all toppings are meeting the required non slip R rating and provide supporting tests for this
item if required by the Principal Certifying Authority.
2 Related Work
Coordinate and cooperate with the following trades:
Concrete Concrete pavements
Sanitary sewerage Floor finishes
Wall finishes Waterproofing and tanking
3 Quality Assurance
A. Provide data indicating that the tradesmen engaged for this project have a minimum of 5 years of
experience in such work as required by this specification.
Supply names of contacts, with telephone numbers, who can verify performance quality.
B. Prepare for the architect’s approval a square meter of granolithic screed, including coves, risers,
kerbs where applicable. When approved proceed with remaining work.
4 References
Comply with applicable portions of the following Australian Standards:
AS 1379 2007 Specification and supply of concrete. Plus Supplement 1-2008 and 2 Amdts
2009, 2015.
AS/NZS 3661.2 1994 Slip resistance of pedestrian surfaces – Guide to the reduction of slip
hazards.
AS 3700 2011 Masonry structures. There is 1 Supplement 2012, 2 Amdts 2012, 2015
AS 3740 2010 Waterproofing of domestic wet areas. 1 Amdt, 2012.
AS 3799 1998 Liquid membrane-forming curing compounds for concrete.
AS 3972 2010 General purpose and blended cements.
Where relevant, comply with construction standards and notes published by the Cement Concrete and
Aggregates Association of Australia , www.concrete.net.au
Read this component of the specification in conjunction with BCA report for the required R values for the
non-slip.
5 Submissions
Where applicable, provide evidence of payment of relevant fees.
PART II MATERIALS
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 03530 CONCRETE SCREEDS
202 Joint Sealing Materials
A. Non-structural external weather-proofing sealants: low modulus neutral curing silicone rubber
compounds.
B. Joint primer/sealer: provide type of joint primer/sealer recommended by sealant manufacturer for
joint surfaces to be primed or sealed.
C. Bond breaker tape: polyethylene tape or other plastic as recommended by sealant manufacturer
to be applied to contact surfaces where bond to substrate or joint filler is to be avoided for proper
performance of sealant. Provide self-adhesive tape where applicable.
D. Sealant backer rod: compressible rod stock of polyethylene foam, polyethylene jacketed
polyurethane foam, butyl foam, neoprene foam or other flexible, permanent durable non-
absorptive material as recommended by sealant manufacturer for compatibility with sealant.
E. Sealant for floor joints: 2-part, self-levelling polyurethane based, chemically cured.
204 Mixes
A. Mix screeds with minimum water to produce screed material that is workable and will consolidate
uniformly. The proportion will depend on the sand in use and is found by practical trial. Minimise
random variations once the proportions are established. Carefully control water quantity.
B. Granolithic finish mix: 1:2:1 cement: stone: sand.
C. Protective screed mix: 20 MPa concrete with maximum aggregate size of 6mm.
D. Batching by shovelful is not allowed. Batch by weight only.
Add pigment as instructed by manufacturer to a sample colour approved by the architect.
E. Waterproofing: add mixture. Refer section 07130 WATERPROOFING AND TANKING, System
Type D.
301 Examination
Visit site and inspect conditions to drawings before delivery of materials to site. Notify contractor of any
discrepancy or unsuitability or substrate.
Start of work means total acceptance of conditions.
302 Records
Obtain essential services information (Dial Before You Dig).
303 Preparation
Before commencing work, ensure that the concrete is clear and free of mortar, honeycombing, surface
cavities, oil, tying wires or other surface deficiencies and is suitable to receive the membrane.
Sweep up all debris.
Roughen surface of existing surface to ensure adequate key for granolithic.
305 Screeds
A. Dense screeds: thickness of not less than 25mm, except 20mm at outlets. Reinforce with light
galvanised steel mesh. Refer clause 201 G.
B. Protective screeds: 50mm thick parallel to substrate.
Reinforce with light galvanised steel mesh. Provide control joints as specified in clause 305D.
Dust on and trowel in bluestone fines.
C. Setdowns: for screeds to receive other finishes, consult with other sub-contractors for those
finishes to determine the setdown required.
D. Walls and upstands: finish at junction with walls and upstands with galvanised wire mesh and
50mm radius cove.
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 03530 CONCRETE SCREEDS
C. Scoring: provide scored pattern of 600 x 600 with trowel to regular depth.
D. Control joints: provide control joints 10mm wide to receive floor joint sealant. Joints to be
maximum 3 metres apart. Provide joint 600mm inside and parallel to parapets or walls.
307 Tolerances
A. Tolerances to grades established on drawings: + 5mm, -5mm
B. Local variation from a flat surface: not to exceed +3mm -3mm under a 3 metre straightedge, with
6mm "feet" on each end so variations can be measured from the surface to the straightedge.
308 Curing
General: protect from premature drying and excessively hot or cold temperatures. Where required,
provide damp curing.
309 Protection
Lay hardboard over completed work for minimum of 5 days.
310 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
Clean up leaving the surfaces in first class condition to the satisfaction of the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 03530 CONCRETE SCREEDS
SECTION 05080 METAL FINISHES - SHOP-APPLIED
PART I GENERAL100
101 Scope
Supply all labour and material, services and equipment necessary for the preparation, application and
finishing of metal surfaces as indicated on drawings, schedules and as specified herein, to internal and
external metal surfaces as follows:
Refer Schedule of Finishes.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1231 2000 Aluminium and aluminium alloys - Anodic oxidation coatings.
AS 1627 Metal finishing - Preparation and pre-treatment of surfaces.
1627.6 2003 Chemical conversion treatment of metals.
There are 6 other parts, 1997 – 2005.
AS 2832 Cathodic protection of metals. There are 5 parts, 2003 – 2015.
AS 3715 2002 Metal finishing - Thermoset powder coating for architectural applications of
aluminium and aluminium alloys.
105 Submissions
Submit the following materials:
A. Product literature on all proposed finishing systems.
B. Colour samples for all approved finishing materials. Provide samples identified with:
1. Manufacturer's colour code and colour name.
2. Match to schedule colour code and name.
C. Samples not less than 100 x 100mm and of the same gloss level as the scheduled colour.
107 Warranty
Provide a written warranty stating the preparation of surfaces, materials and material application under
this contract will show no deterioration and remain in good condition for a period of 10 years from date of
Practical Completion.
PART II MATERIALS200
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 05080 METAL FINISHES - SHOP-APPLIED
Minimum coating thickness of 50 microns subjected to random testing after installation. Remove
and replace non-conforming material.
C. Fluoroset FP (Dulux Product).
203 Schedule
Refer to Finishes Schedule.
301 Examination
Inspect all surfaces and determine that they are in proper condition to receive the work to be performed
under this section.
The starting of work under this section means acceptance of such surfaces as being satisfactory and
any defects in work resulting from accepting poor surfaces are to be corrected at no cost to the
proprietor.
302 Preparation
A. General: prepared to a standard not less than that described in AS 1627.
B. Clean base metal surfaces of all mill scale, rust, grease, oil, dirt or other foreign matter then
properly wash with spirit or other approved cleaning agents.
After cleaning, etch, pickle or prepare as recommended by manufacturer of the finish applied.
303 Protection
Protect finished metal surfaces as necessary during handling, transport and erection to prevent
mechanical imperfections such as scratches, scrapes, dents, spots, stains and streaks.
Do not use adhesive protective coating. Protect by other means with the approval of the architect.
304 Application
Execute all work in this section in strict compliance with the manufacturer's recommendations and with
the provisions of the Australian Standards which are incorporated by reference as part of this
specification and apply to the work in this section to same extent as if written herein. In the event of
conflict between manufacturer's recommendations and the provisions of the Australian Standards,
manufacturer's recommendations govern.
305 Cleaning
At completion of work, keep and maintain finished surfaces clean and free from dust, dirt and other
foreign matter.
306 Completion
Complete all contracted work in accordance with contract documents and written variation orders issued
by the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 05080 METAL FINISHES - SHOP-APPLIED
SECTION 05400 COLD FORMED METAL FRAMING
PART I GENERAL
101 Scope
Provide load bearing and non-loadbearing cold formed metal framing to locations shown on the
drawings and to meet the structural engineer’s design.
Provide all components to approved submission of samples and shop drawings.
Design, engineer, supply and install a complete cold formed metal framing, including but not limited to:
Load bearing wall framing
Non-loadbearing wall framing
Loadbearing roof framing
Other
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1170 Structural design actions.
1170.1 2002 Permanent, imposed and other actions. Plus 2
Amdts,2005 – 2009.
1170.2 2011 Wind actions.
1170.3 2003 Snow and ice actions. Plus 1 Amdt, 2007.
1170.4 2007 Earthquake actions in Australia. Amdt 1 2015
There is 1 other part, several Supplements and Amdts, 2002 – 2011.
AS/NZS 1554 Structural steel welding.
1554.1 2014 Welding of steel structures, 1 Amdt 2015.
1554.2 2003 Stud welding (steel studs to steel) Plus 1 Amdt, 2003.
1554.3 2014 Welding of reinforcing steel.
1554.4 2014 Welding of high strength quenched and tempered
steels.
1554.5 2014 Welding of steel structures subject to high levels of
fatigue loading.
1554.6 2012 Welding stainless steels for structural purposes.
1554.7 2014 Welding of sheet steel structures.
AS 3623 1993 Domestic metal framing.
Comply with relevant authority's requirement for fire.
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 05400 COLD FORMED METAL FRAMING
6. Junctions and trim to adjoining surfaces.
7. Fittings and accessories.
D. Engineer's calculations on wind loading, live and dead loads.
PART II MATERIALS200
201 General
Provide all work in accordance with approved shop drawings and samples as well as technical data
information from approved manufacturers and certified by the structural engineer for adequacy.
The following manufacturers of frames are acceptable:
202 Materials
Wall, floor and roof framing components manufactured from corrosion resistant steel materials.
Match components detailed on drawings or an alternative approved in writing by the architect.
205 Fabrication
Form junctions so that no fixings, such as pins, screws, pressure indentations and the like are visible on
exposed faces. Show on shop drawings fixings which will be exposed. Cut edges, drill holes, rivet joints
and clean flat sheets, neat, free from burrs and indentations. Remove sharp edges without excessive
deformation. Fit mitred joints accurately to a fine hairline.
Pre-assemble and match mark before delivery.
301 Examination
Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are
satisfactory for installation.
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 05400 COLD FORMED METAL FRAMING
Perform rectification required before delivery of materials.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the requirements of the Act, Regulation, Code of Practice and
relevant Australian Standards.
Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.
304 Installation
Wall frames: vertical. Permitted maximum tolerance is 3mm in 3000mm.
Floor frames: horizontal. Permitted maximum tolerance is 3mm in 3000mm.
Except where otherwise directed.
Secure in place in accordance with manufacturer’s instructions.
305 Cleaning
Debris: remove rubbish and debris resulting from the fabrication and erection operations, each day.
306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 05400 COLD FORMED METAL FRAMING
SECTION 05500 METALWORK
PART I GENERAL100
101 Scope
Provide items listed on the drawings and where scheduled.
Supply, engineer and install required general and architectural metalwork items including but not limited
to:
Floor finish trims
Sundry metalwork items
Furniture Steel
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1554 Structural steel welding. There are 7 parts, 2003– 2014.
AS 1627 Metal finishing - Preparation and pre-treatment of surfaces.
1627.6 2003 Chemical conversion treatment of metals.
There are 6 other parts, 1997 – 2005.
AS/NZS 1734 1997 Aluminium and aluminium alloys - Flat sheet, coiled sheet and plate.
AS/NZS 1866 1997 Aluminium and aluminium alloys - Extruded rod, bar, solid and hollow shapes.
AS 4100 1998 Steel structures. Plus 1 Supplement 1999, 1 Amdt 2012.
AS/NZS 4673 2001 Cold-formed stainless steel structures.
AS/NZS 4680 2006 Hot-dip galvanised (zinc) coatings on fabricated ferrous articles.
Comply with requirements of statutory and local authorities.
106 Samples
Sample welds: if requested, provide samples of weld types, including samples of railings joined at right
angles and at typical acute angles, welded and ground smooth, for approval. If not acceptable, provide
additional samples until approved. Approved samples establish quality of similar work of this section.
Check on delivery: request architect to check materials on delivery to site for quality, and materials not
meeting the requirements of this specification or equal to approved samples will be rejected.
Return rejected materials to the fabricator at the fabricator's expense.
Finish: provide samples of specified finishes when requested.
Before ordering materials obtain and provide to the architect written evidence that items to be installed
comply with Australian Standards and are approved by statutory authorities having jurisdiction.
If non-approved materials or components are installed, replacement will be at contractor’s expense.
Providence Christian College Primary School Stage 1 Page 1 of 4 SECTION 05500 METALWORK
Confirm with technical data and samples at the submission stage of the specification and obtain an
approval prior to commencing work.
Metalwork Components Schedule
Providence Christian College Primary School Stage 1 Page 2 of 4 SECTION 05500 METALWORK
203 Finish
Materials exposed to weather may be either:
Mild steel - hot dipped galvanised after fabrication or chromate pre-treated followed by polyester powder
coating.
Finish internal steel after fabrication with zinc-rich organic primer, or with inorganic zinc silicate paint.
Comply with relevant codes of practice or manufacturers' recommendations.
206 Miscellaneous
Fasteners: provide required bolts, screws, inserts, fasteners, templates and other accessories required
for a complete installation.
Coordinate with other trades as to the proper fastening systems suitable for the substrates to which the
item is to be secured. Refer to architect if in doubt.
Fasten galvanised items with galvanised fasteners.
301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure
conditions are satisfactory for installation. Arrange for rectification required.
Start of work means total acceptance of relevant conditions.
302 Preparation
Field measurements: do not delay job progress. Allow for adjustments and fitting of the work in the field
where taking of measurements might cause delay.
Coordination with work of others: furnish to each relevant trade foreman anchorages and setting
drawings, diagrams, templates and instructions for installation of items having integral anchors which
are to be embedded in concrete or masonry construction. Coordinate delivery of such items to the
project site.
Providence Christian College Primary School Stage 1 Page 3 of 4 SECTION 05500 METALWORK
303 Inspection and Reinstatement
Check fabrications as they are unloaded at the project site for evidence of physical damage.
Treat damaged fabrications as follows:
A. Damage through galvanising: perform immediate inorganic zinc silicate paint or cold-galvanising
repair. Do not install until reinstated.
B. Architectural metalwork: returned to shop for repair or replacement.
Verify anchors, bolts and other required anchorage items for proper size and accurate location prior to
erection.
304 Installation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or relevant Australian
Standards,
Anchorage: except for anchorages furnished herein but placed by other trades, set and secure
necessary anchorages, including concrete and masonry inserts, bolts, wood screws and other
connectors as needed. Perform cutting, drilling and fitting as needed, locating anchorages and holes to
ensure proper positioning of completed work.
Fit: during installation and assembly, form tight joints with exposed connections accurately fitted, and
reveals uniform. Finish work accurately, plumb, level, square and true in reference to adjacent
construction. Make tolerances conform to Australian Standards.
Finish: do not cut or abrade shop finishes which cannot be completely restored in the field.
The use of gas-cutting torch in the field for correcting fabrication errors will not be permitted under
conditions. Fabrications may be cut shorter with power hacksaws on site.
Isolate dissimilar metals likely to be subject to moisture with inert materials, not visible on completion of
installation.
306 Protection
Cover work: immediately following installation, wrap or cover architectural metalwork to avoid wear and
tear of finish during subsequent construction.
307 Cleaning
Clean materials installed to the satisfaction of the architect.
Remove temporary protective coatings.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 4 of 4 SECTION 05500 METALWORK
SECTION 05520 HANDRAILS AND BALUSTRADES
PART I GENERAL100
101 Scope
Design, fabricate, supply and install exterior and interior handrail, and rails (which form a
balustrade ) including but not limited to:
Metal pipe handrails and railings.
Associated material e.g. Aluminium balusters.
Solid metal handrails and railings.
Note that components of this trade package may contain aspects of design and construct. Complete the
design indicating full compliance with statutory and structural performance levels and submit for
approval.
Certify on completion for compliance.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1554 Structural steel welding. There are 7 parts, 2003 – 2014
AS 1627 Metal finishing - Preparation and pretreatment of surfaces.
1627.6 2003 Chemical conversion treatment of metals.
There are 6 other parts, 1997 - 2005
AS 4100 1998 Steel structures. Plus 1 Supplement, 1999, 1 Amdt 2012.
AS/NZS 4673 2001 Cold-formed stainless steel structures.
Comply with requirements of statutory and local authorities.
PART II MATERIALS200
Before ordering materials obtain and provide to the architect written evidence that items to be installed
comply with Australian Standards and are approved by statutory authorities having jurisdiction.
If non-approved materials or components are installed, replacement will be at contractor’s expense.
202 Materials
Hot dip galvanised mild steel balustrade posts, rails, handrails and cleats.
Bluechip powdercoat finish 50mm x 50mm aluminium UWB5050 balusters with endcaps fixed to steel
rails. Refer to detail drawings.
203 Finish
Hot dip galvanised.
204 Fabrication
Before delivery to site, pre assemble where possible all items to ensure proper fit and dimension of each
item. Disassemble and pack carefully for shipping to the site. On delivery and unloading, inspect for
damage and arrange immediate replacement if necessary.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 05520 HANDRAILS AND BALUSTRADES
PART III EXECUTION300
301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure
conditions are satisfactory for installation. Arrange for rectification required.
Start of work means total acceptance of relevant conditions.
302 Preparation
A. Field measurements: do not delay job progress. Allow for adjustments and fitting of the work in
the field where taking of measurements might cause delay.
B. Coordination with work of others: furnish to each relevant trade foreman anchorages and setting
drawings, diagrams, templates and instructions for installation of items having integral anchors
which are to be embedded in concrete or masonry construction. Coordinate delivery of such
items to the project site.
304 Installation
A. Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian
Standards, as relevant.
B. Anchorage: except for anchorages furnished herein but placed by other trades, set and secure
necessary anchorages, including concrete and masonry inserts, bolts, wood screws and other
connectors as needed. Perform cutting, drilling and fitting as needed, locating anchorages and
holes to ensure proper positioning of completed work.
C. Fit: during installation and assembly, form tight joints with exposed connections accurately fitted,
and reveals uniform. Finish work accurately, plumb, level, square and true in reference to
adjacent construction. Make tolerances conform to Australian Standards.
D. Finish: do not cut or abrade shop finishes which cannot be completely restored in the field.
The use of gas-cutting torch in the field for correcting fabrication errors will not be permitted
under conditions. Fabrications may be cut shorter with power hacksaws on site.
Isolate dissimilar metals likely to be subject to moisture with inert materials, not visible on
completion of installation.
306 Protection
Cover work: immediately following installation, wrap or cover architectural metalwork to avoid wear and
tear of finish during subsequent construction.
307 Cleaning
Clean materials installed to the satisfaction of the architect.
Remove temporary protective coatings.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 05520 HANDRAILS AND BALUSTRADES
SECTION 06100 CARPENTRY
PART I GENERAL
101 Scope
Scope of work of this trade section is the structural and non-structural carpentry components with timber
being of the type and species suitable for the intended use.
Note that use of treated timber is essential under specific project conditions such as use of termite
resistant structural timber, check and evaluate prior to commencing work.
Coordinate work fully with the structural engineer for structural components of the works.
Provide materials and labour, equipment and services and perform operations necessary to complete
the carpentry as indicated and specified. Include nailers, blocking, furring, grounds, hardware, framing,
shoring, bracing, scaffolding and barriers required by the drawings and construction.
103 Quality Assurance Prototype: at a location selected by the architect on site, construct a full size
prototype of:
Include in each prototype elements required by this specification, and finish in every respect. When
approved by the architect, such samples remain part of the work and become the standard for the
remaining work.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1428.1 Design for access and mobility – General requirements for access - New
building work.
AS 1684 Residential timber-framed construction. There are many parts and
Supplements, 1999 - 2010.
1684.2 2010 Non-cyclonic areas. Numerous supplements, 2 Amdts
2012 and 2013.
1684.3 2010 Cyclonic areas. Numerous supplements, Amdt 2012.
1684.4 2010 Simplified - Non-cyclonic areas. Special reprint with
Amdt 1 2012 included.
AS 1720 Timber structures.
1720.1 2010 Design methods. Plus 3 Amdts, 2010 - 2015.
1720.2 2006 Timber properties. Plus 1 Amdt, 2006.
1720.4 2006 Fire-resistance for structural adequacy of timber
members.
1720.5 2015 Nailplated timber roof trusses.
AS/NZS 1859 Reconstituted wood-based panels - Specifications
1859.1 2004 Particleboard. Plus 2 Amdts, 2006 - 2011.
1859.2 2004 Dry processed fibreboard. Plus 2 Amdts, 2006.
1859.3 2005 Decorative overlaid wood panels. Plus 1 Amdt, 2009.
There is 1 other part, 2004.
AS 1860.2 2006 Particleboard flooring – Installation. Plus 1 Amdt, 2010.
AS/NZS 2904 1995 Damp-proof courses and flashings. 2 Amdts, 1998, 2013
AS 3959 2009 Construction of buildings in bushfire-prone areas. Plus 3 Amdts, 2009 - 2011.
AS 4055 2012 Wind loads for housing. 1 Amdt 2015
AS 4226 2008 Guidelines for safe housing design.
AS/NZS 4364 2010 Timber – Bond performance of structural adhesives.
AS 4786.2 2005 Timber flooring - Sanding and finishing.
HB 44 1993 Guide to AS 1684 1992, The National Timber Framing Code.
Further advice and changes in specifications of timber are needed frequently. For latest information visit
www.timber.net.au
For timber decks visit the Outdoor Timber section of Resources at www.timber.net.au.
105 Submissions
Where timber is used in external locations ensure that correct timber species are used and confirm at
the submissions stage of the works.
Submit the following prior to ordering materials:
Product literature on hardware items proposed.
Technical data on melamine laminates proposed for use.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 06100 CARPENTRY
Technical data and samples of substrate materials (particleboard etc.). Thickness of materials at typical
locations and functions.
301 Examination
Visit site and inspect conditions, comparing conditions to drawings before delivery of materials to site.
Start of work means total acceptance of conditions.
304 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 06100 CARPENTRY
SECTION 06165 FIBRE CEMENT PRODUCTS
PART I GENERAL
101 Scope
Supply and install fibre cement products and associated equipment and fixings including but not limited
to:
External cladding.
Soffit Linings and bulkheads.
A tradesman with wide experience and knowledgeable in this class of work is to undertake the work to
be performed.
104 References
Comply with applicable portions of the following Australian Standards:
AS 2329 1999 Mastic adhesives for fixing wallboards.
AS/NZS 2908 Cellulose-cement products.
2908.1 2000 Corrugated sheets.
2908.2 2000 Flat sheet.
AS 3740 2010 Waterproofing of domestic wet areas. 1 Amdt, 2012
Relevant Technical Bulletins and published instructions produced by manufacturers.
Telephone Customer Services of state office for technical assistance.
Comply with requirements of relevant statutory authorities.
106 Warranty
Provide warranty covering the work against defective materials and workmanship for a period years
from the date of Practical Completion. Include a statement that the whole of the work has been carried
out in accordance with relevant Australian Standards and codes and manufacturer's instructions in effect
at the time of installation.
202 Materials
A. James Hardie 6mm Versilux soffit lining and bulkheads with expressed joints.
B. Black PVC extrusion expressed jointer for 6mm Versilux sheet.
C. James Hardie Exotec Façade System comprising compressed fibre cement 9mm thick sheet
together with all accessories.
203 Equipment
Supply equipment required for the erection and installation of the specified materials as recommended
by the manufacturer.
301 Examination
Visit site and inspect conditions, comparing conditions to the drawings before delivery of materials to
site. Rectify any discrepancy or unsuitability of substrate.
Start of work means total acceptance of conditions.
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 06165 FIBRE CEMENT PRODUCTS
302 Preparation
Coordinate with and ensure preparatory work by other trades is done, prior to commencement of work
and arrange for fixing grounds required for satisfactory execution of the work of this trade, including
penetrations through cement sheet for services.
303 Installation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Comply with the manufacturer's installation instructions. Anchor and fasten materials and components to
comply with ratings and performance requirements, and to comply with governing local regulations.
Comply with appropriate Australian Standard.
Take care of and protect surrounding work, including other finishes, equipment and components, during
installation. Provide protective covering where necessary.
306 Protection
Protect finished work. Make good damage in every respect at no additional cost to the proprietor.
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 06165 FIBRE CEMENT PRODUCTS
307 Cleaning
Clean exposed surfaces including trim, edge moldings, and comply with manufacturer's instructions for
cleaning and touch-up of minor finish damage.
Remove spatterings, droppings and surplus material.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 06165 FIBRE CEMENT PRODUCTS
SECTION 06400 JOINERY
PART I GENERAL
101 Scope
The work of this trade section covers the supply and installation of caseworm joinery items. It includes,
but is not limited to:
Trim, architraves, skirtings, pelmets etc.
Include in each prototype elements required by this specification, finished in every respect. When
approved by the architect, each prototype remains part of the work and becomes the standard for the
remaining work.
104 References
Comply with applicable portions of the Australian Standards listed in SECTION 06100 CARPENTRY,
plus those following, current edition:
AS/NZS 1859 Reconstituted wood-based panels - Specifications
1859.1 2004 Particleboard. Plus 2 Amdts, 2006 - 2011.
1859.2 2004 Dry processed fibreboard. Plus 2 Amdts, 2006.
1859.3 2005 Decorative overlaid wood panels. Plus 1 Amdt 2009.
There is 1 other part, 2004.
AS 2754.2 1991 Adhesives for timber and timber products - Polymer emulsion adhesives.
AS 2796 Timber - Hardwood- Sawn and milled products. There are 3 parts, 1999-
2006.
AS 4785 2002 Timber - Softwood- Sawn and milled products.
4785.1 2002 Product specification.
4785.2 2002 Grade description.
4785.3 2002 Timber for furniture components.
AS 4786.2 2005 Timber flooring - Sanding and finishing.
105 Submissions
Submit the following prior to fabrication:
Product literature on proposed hardware items.
Technical data on melamine laminates proposed for use.
Technical data and samples of substrate materials (particleboard etc.).
Thickness of materials at typical locations.
201 General
Provide all casework joinery items on site fully coordinated with services, check for site
dimensions and constructed from approved high moisture resistant materials.
Provide to an approved sample component if required by the architect.
202 Materials
Medium Density Fibre board. Refer Finishes Schedule and detail drawings.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 06400 JOINERY
PART III EXECUTION300203, G
301 Examination
Visit the site and inspect conditions. Check dimensions and compare aspects with the drawings and
specification. Resolve differences before ordering materials or starting work.
Start of work means total acceptance of conditions.
304 Hardware
Install joinery hardware as scheduled, listed and required in full compliance with the manufacturer's
recommendations.
Adjust as needed to centre doors in openings.
306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 06400 JOINERY
SECTION 07130 WATERPROOFING AND TANKING
PART I GENERAL100
101 Scope
This trade section identifies requirements for the supply and installation of 4 different types and areas of
waterproofing. It covers preparatory and protective work and associated materials including but not
limited to:
A. System Type A, Wet Area membrane as in bathrooms, showers, laundries, garbage rooms and
similar areas.
B. System Type B, Lift overrun pit
C. System Type C, Balcony substrate.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1884 2012 Floor coverings – Resilient sheet and tiles – Laying and maintenance
practices.
AS 3600 2009 Concrete structures. Plus 2 Amdts, 2010, 2013, 1 Supplement 2014.
AS 3740 2010 Waterproofing of domestic wet areas. 1 Amdt, 2012
AS 3799 1998 Liquid membrane-forming curing compounds for concrete.
AS 4654 Waterproofing and membranes for external above-ground use
4654.1 2012 Materials
4654.2 2012 Design and installation
AS/NZS 4858 2004 Wet area membranes.
107 Warranty
Requirement
Prior to completion of the waterproofing systems installation, provide each warranty, in the appropriate
form;
executed by the sub-contractor and the warrantor (or warrantors in the case of joint warranties); and for
the required warranty period.
Warranty Conditions
Sub-contractor's obligations: the provision of a warranty does not relieve the sub-contractor of any of his
contractual obligations.
Guarantee of performance: where the warrantor is a subsidiary of another organisation, provide that
organisation's guarantee of performance of the warranty.
Adjustment of warranty period: where any part of the work is required to be repaired or made good
under a warranty, the warranty period does not terminate until that part has been satisfactorily repaired
Providence Christian College Primary School Stage 1 Page 1 of 5 SECTION 07130 WATERPROOFING AND TANKING
or made good; and in respect of that part, recommences from the date of completion of the repair or
making good.
Product warranties
Provide separate product warranties for each of the waterproofing systems.
System warranty
Provide separate warranties for each of the waterproofing systems, signed jointly by the manufacturer
and the installer, stating that the products applied comply with this specification, are suitable for the
conditions to which they will be subjected and were correctly installed in accordance with the
manufacturer’s published recommendations and details, the contract documents and provide a complete
waterproof membrane.
Warrant each of the waterproofing systems against any defects that affect their performance or
appearance Defects include failure of any element of the waterproofing system, whether or not the
failure causes the system not to achieve the design criteria or specified performance.
The warranty must cover the repair and/or replacement of all other building elements, finishes etc. to
which damage occurs as a consequence of a defect in, or repair work carried out, to the waterproofing
system.
Warranty Period
As noted beside each of the waterproofing systems described in this specification.
Before ordering materials obtain and provide to the architect written evidence that items to be installed
comply with Australian Standards and are approved by statutory authorities having jurisdiction.
If non-approved materials or components are installed, replacement will be at contractor’s expense.
Providence Christian College Primary School Stage 1 Page 2 of 5 SECTION 07130 WATERPROOFING AND TANKING
Membrane curing: allow 72 hours for the membrane to cure prior to carrying out water tests or applying
finishes, toppings etc.
Warranty
Provide a warranty for materials and application of the membrane for a period of 20 years from the
date of Practical Completion, to be in a form approved by the principal.
Alternatives
Type: any proposed alternative to the system specified below is to be a proprietary liquid applied or
sheet membrane system which:
has a current Australian Building Product and Systems Certification Scheme certificate (Australian
Building Codes Board); or
has a current technical opinion issued by the Australian Building Systems Appraisal Council (CSIRO)
stating that the system is suitable for use as a waterproofing system for use in wet areas, shower recess
bases and associated floors and wall/floor junctions which are to be tiled.
Providence Christian College Primary School Stage 1 Page 3 of 5 SECTION 07130 WATERPROOFING AND TANKING
Ensure all surfaces are sound, dry and free from excessive movement, oil,
dust, grease, wax, curing compounds, release agents, paint and any other
loose contaminants. Remove any protrusions from the surface that may
pierce the membrane.
Cracks larger than 2 mm or structural shrinkage cracks must be firstly
cleaned and any loose material removed then filled with Nitoseal MS400 or
covered with Nitoband Tape in conjunction with Nitoproof 410 System.
Refer to technical data sheet.
Priming Nitoprime 120 is to be compatible with the water-based membrane, and
provide high bonding and penetrating properties to porous substrates such
as concrete and masonry. A Nitobond SBR slurry primer must be used to
water-tank and immersed substrates.
Waterproofing Membrane: Apply Nitoproof 410. wall to wall and floor to wall junctions, internal and
external corners are to incorporate Emerband Tape to accommodate any
movement at these junctions in conjunction with the Nitoproof 410 as per
technical data sheet.
Apply Nitoband 410 as three (3) coats with a minimum total coverage of 2.0
litres/m2
Warranty: Provide a warranty for materials and application of the membrane for a
period of 20 years from the date of Practical Completion, to be in a form
acceptable to the principal.
301 Examination
A. Inspect conditions before delivery of materials and start of work on site to ensure that everything
is satisfactory. Arrange with builder for needed rectification.
Start of work means total acceptance of conditions.
B. Waterproofing Table
302 Substrates
Substrates for membranes
Apply membranes to dry, smooth, firm, continuous surfaces, clean and free from loose or foreign matter.
Provide coving or fillets on internal corners. Round or arris external corners and edges.
Dryness tests for substrates: to AS 1884.
Acceptance of substrate: certify that the building structure, including the building tolerance, provision of
reference lines and marks, is satisfactory for receiving the application of the waterproofing system.
Approval of installer: if the installation of the waterproofing system is not by the manufacturer, and a
manufacturer’s warranty is conditional on approval of the installer, then obtain the manufacturer’s
approval of the installer.
Make a photographic record of prepared substrates.
Providence Christian College Primary School Stage 1 Page 4 of 5 SECTION 07130 WATERPROOFING AND TANKING
Type
Provide protection board made from 6mm thick fibre cement or 3mm thick, hollow polypropylene, co-
polymer sheet or proprietary protection board equal Tremco Pty Limited.
Installation
Protect waterproofing membranes upon completion of each area of the application and maintain that
protection until such time as the installation is approved and covered up by other finishes.
Following completion of the waterproof membrane to planter boxes install protection board to the
membrane on vertical faces.
Restrain the board by trapping the top edge under the bottom edge of the K shaped pressure flashing
used to terminate the top of the membrane.
Retaining Walls and Footings
Refer to 02315 SITE PREPARATION - EXCAVATION for membrane protection to retaining walls and
footings built against existing site fill or rock.
305 Cleaning
During the application, promptly remove foreign material from the work area without damaging the
waterproofing system.
Manufacturers’ Inspections
Arrange for and pay the cost of inspections by the waterproofing systems manufacturer at each of the
above stages and at regular frequent intervals during the application of the waterproofing systems.
Maintain a logbook on the site and record the time and date of each inspection, work complete and
underway, at the time of each inspection, and comments by the manufacturer’s representative.
Have the manufacturer’s representative sign the logbook at the completion of each inspection and
record the observations made.
309 Cleaning
Thoroughly clean work on completion, including affected adjacent surfaces.
310 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 5 of 5 SECTION 07130 WATERPROOFING AND TANKING
SECTION 07200 INSULATION (THERMAL AND ACOUSTIC)
PART I GENERAL
101 Scope
The scope of work includes, but is not limited to, the supply and installation of thermal insulation.
It also includes the supply and installation of acoustic insulation.
104 References
Comply with the applicable portions of these Australian Standards:
AS 1366 Rigid cellular plastic sheets for thermal insulation. There are 4 parts, 1989-
1992, and 2 Amdts, 1992 - 1993.
AS/NZS 2107 2000 Acoustics - Recommended design sound levels and reverberation times for
building interiors.
AS 3671 1989 Acoustics - Road traffic noise intrusion - Building siting and construction.
AS 3999 2015 Thermal insulation of dwellings - Bulk insulation - Installation requirements.
AS/NZS 4200 Pliable building membranes and underlays.
4200.1 1994 Materials. Plus 1 Amdt, 1994.
4200.2 1994 Installation requirements.
AS/NZS 4859.1 2002 Materials for the thermal insulation of buildings - General criteria and
technical provisions. Plus 1 Amdt, 2006.
Comply with the requirements of the Building Code of Australia.
105 Submission
Provide to the architect before ordering, samples, literature and technical data of each specified
material.
Confirm compliance with an approved national energy rating system etc. as applicable to the works.
A. Roof: Bradford Anticon FBS-1 Glasswool blanket of thickness 80mm, that is thermally rated to
AS/NZS4859.1, faced with Reflective Foil Laminate (RFL) facing (foil facing downwards), to be
laid over safety wire mesh and held firmly against all sheet metal roofing. R-Value 1.8 minimum.
B. External soffits and stud framed walls between soffit and suspended slab: Bradford Glasswool
Building blanket 80mm thick, R-value R1.8 minimum.
C. Exterior Masonry walls: Bradford Fibertex 650 Rockwool board, 75mm thick R-value R2.1
minimum. Note; Insulation board to be fitted against internal leaf.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 07200 INSULATION (THERMAL AND ACOUSTIC)
D. Metal clad and CFC clad external walls: Bradford Gold High Performance 90mm thick batts, R-
value R2.5 minimum.
E. Suspended ceilings: Bradford Gold batts, R-value R2.5 minimum.
F. Concrete slab soffit insulation: Bradford Gold High Performance 75mm thick batts, R2.0
minimum.
G. Sarking to Metal clad and Fibre Cement clad external walls: Bradford Enviroseal ProctorWrap
Commercial Wall vapour permeable membrane.
H. Thermal breaks to metal clad external walls: James Hardie HardieBreak minimum R-value R0.2
thermal break strips to all external wall studs or girts between cladding and stud / girt.
Comply with manufacturer’s recommendations and the relevant Australian Standards.
203 Materials–Acoustic
A. Internal framed walls: Bradford Acoustigard 14 wall batts, 90mm thick to match stud thickness.
B. Suspended ceilings and soffit fixed ceilings: Bradford Gold batts, R-value R2.5 minimum.
C. Acoustic lagging: Install Pyrotek 4525 Soundlag acoustic lagging to internal rain water pipes, soil
and waste pipes above and within internal spaces.
D. Acoustic wall panels (Music Classroom, Meeting Room); Autex 50mm Quietspace with Vertiface
fabric covering including edge wrapping. Refer Interior Finishes Schedule.
301 Examination
Visit the site and inspect conditions, comparing conditions to drawings before delivery of materials to
site. Start of work means total acceptance of conditions.
302 Preparation
Prepare surfaces and/or framing material and ensure that no obstructions will prevent rapid and effective
installation.
305 Cleaning
Remove surplus material on completion and arrange for inspection(s) by manufacturer’s representative.
306 Completion
Complete contracted work in accordance with the contract document and written variation orders issued
by the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 07200 INSULATION (THERMAL AND ACOUSTIC)
SECTION 07600 METAL ROOFING, SIDING AND ROOF PLUMBING
PART I GENERAL100
101 Scope
Supply and install a complete roofing and siding (external cladding) installation as shown on the
drawings including but not limited to the following:
A. Metal deck of zincalume steel, aluminium, copper etc., including accessories, fastening clips,
apron flashings, gutters, parapet linings, copings, sumps, overflow pipes, downpipes. Refer to
External Finishes Schedule project specific document and to the product manufacturer’s
specification for adequacy of each proposed installation.
B. Roof insulation and wire mesh.
C. Roof penetrations and sealing thereof.
D. Metal cladding.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1170 Structural design actions.
There are 5 parts, several Supplements and Amdts, 2002 – 2011.
AS 1273 1991 Unplasticised PVC (UPVC) downpipe and fittings for rainwater.
AS/NZS 1562 Design and installation of sheet roof and wall cladding.
1562.1 1992 Metal. Plus 3 Amdts, 1993 - 2012.
1562.3 2006 Plastic. There is 1 other part, 1999.
AS/NZS 2179 Specifications for rainwater goods, accessories and fasteners.
2179.1 1994 Metal shape or sheet rainwater goods, and metal
accessories and fasteners.
AS 3566 2002 Self-drilling screws for the building and construction industries. There are 2
parts.
AS 3999 2015 Thermal insulation of dwellings - Bulk insulation - Installation requirements.
AS/NZS 4256 Plastic roof and wall cladding materials. There are 5 parts,
2006.
AS/NZS 4389 1996 Safety mesh.
HB 39 2015 Installation code for metal roof and wall cladding.
HB 114 1998 Guidelines for the design of eaves and box gutters.
105 Submissions
Submit prior to ordering materials:
A. Samples and product data of specified products.
B. Calculation of sizes for gutters and downpipes.
C. To roofer - supply layout showing exact roof framing member positions.
107 Warranty
Provide to the proprietor a warranty on the whole of the roof and roof plumbing including penetrations for
pipes, flues, upstands etc. performed for mechanical equipment sub-contractor which states that work
will remain waterproof and weather-tight for the period of 15 years from the date of Practical Completion.
204 Fabrication
Form and fabricate components in accordance with AS/NZS 1562 and AS/NZS 2179.1, and other
relevant Standards.
Self-drilling screws are to conform to Class 3 as described in AS 3566.
Providence Christian College Primary School Stage 1 Page 2 of 4 SECTION 07600 METAL ROOFING, SIDING AND ROOF
PLUMBING
205 Dissimilar Metals
In moist environments, prevent totally contact between dissimilar metals (any metals).
This instruction takes priority over any drawing, detail or instruction and will prevent cathodic reaction
between the metals.
Refer this instruction to the structural engineer.
301 Examination
Inspect site conditions before installation. Ensure framing is entirely satisfactory.
Ensure that delivery and installation will not be impeded by on-site conditions at time of delivery.
Start of work means total acceptance of conditions.
303 Preparation
Prepare framing and surfaces for installation.
304 Installation
Install work in accordance with manufacturer's instructions and Australian Standards. Refer clause 104.
305 Flashing
Lap flashing at least 150mm at junctions, and over flashings neatly dressed and finished. Where
necessary to follow a roof slope, step flashings in even overlapping widths. Finish top corners to a line
parallel to the roof slope.
Fabricated flashings in materials which are compatible with, and same finish as, gutter and roofing
materials. Complete work and leave an entirely watertight installation.
306 Penetrations
Form penetration flashings neatly with material matching roofing material. Form flanged tubular collars
0.70mm sheet zinc not less than 150mm high and 12mm wider than penetrating item, or use EPDM
collars.
Where the width of a penetration is wider than a roofing trough or extends across several troughs, form
a back gutter, using sheet material similar to the roofing material, well lapped under the roofing, double
riveted and sealed with silicone sealant. Close and seal ends of cut ribs. Form back gutters not less than
100mm wide with falls towards the sides of the penetration collars.
Form over-flashings of penetration collars neatly in material matching the roofing material but not less
than 0.5mm thick, securely clipped and sealed to the penetrating items and dressed well down over the
collars to finish at a straight line level with the tops of the ribs.
Do not use lead or copper for over-flashings.
307 Downpipes
Install in accordance with AS/NZS 2179.1 for metal.
Install in accordance with AS 1273 for PVC. Comply also with manufacturer's instructions.
Secure to building at recommended centres, minimum 1800mm with galvanised steel straps.
308 Cleaning
To prevent contamination and corrosion, keep clean metal roofing and rainwater goods at times during
the progress of the works.
At the end of work each day, and immediately before each occurrence of rain, sweep the metal surfaces
thoroughly to remove metal filing, swarf, off-cuts, dust, and other materials which could cause corrosion
or blockages. Prevent waste materials from entering downpipes, rainwater heads, or drains.
Remove unsecured nails, rivets, screws, bolts and similar fixing devices, guttering, etc., at the end of
work each day and at the completion of roofing installation.
309 Testing
On completion, test the entire installation in the presence of and to the satisfaction of the architect.
Providence Christian College Primary School Stage 1 Page 3 of 4 SECTION 07600 METAL ROOFING, SIDING AND ROOF
PLUMBING
310 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 4 of 4 SECTION 07600 METAL ROOFING, SIDING AND ROOF
PLUMBING
SECTION 07725 FALL ARREST EQUIPMENT
PART I GENERAL100
101 Scope
Supply and install fall arrest equipment including but not limited to:
Anchor points, static line, fixed access ladders, eaves ladder brackets and associated safety signs.
Allow a Provisional Sum of $10,000.00 plus GST for the supply and installation of fall arrest equipment.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1657 2013 Fixed platforms, walkways, stairways and ladders – Design, construction and
installation.
AS/NZS 1891.1 2007 Industrial fall arrest systems and devices – Harnesses and ancillary
equipment.
There are 3 other parts, 1997 - 2009, 1 Supplement 2001, 2 Amdts 2007 –
2008.
AS/NZS 4801 2001 Occupational health and safety management systems - Specification with
guidance for use.
AS 6001 1999 Working platforms for housing construction
Comply with State requirements and codes of practice in relation to work on roofs.
Comply with the requirements of relevant statutory authorities having jurisdiction on this product.
Product manual produced by manufacturers of components.
106 Samples
A. Sample welds: if requested, provide samples of weld types, including samples of railings joined
at right angles and at typical acute angles, welded and ground smooth, for approval. If not
acceptable, provide additional samples until approved. When approved, samples will establish
quality of similar work of this section.
B. Check on delivery: request architect to check materials on delivery to site for quality, and he will
reject materials not meeting the requirements of this specification or equal to approved samples.
Return rejected materials to the fabricator at the fabricator's expense.
C. Finish: provide samples of specified finishes when requested.
107 Warranty
Provide a warranty to the proprietor covering the whole of the work for a period of 5 years after Practical
Completion. Warranty to cover roof penetrations.
PART II MATERIALS200
201 Manufacturers
Acceptable manufacturers include:
Safemaster Safety Products
202 Materials
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 07725 FALL ARREST EQUIPMENT
Item Description Manufacturer/Supplier
Static lines Anchor Strops Safemaster or equal approved
203 Fabrication
Visit site and accurately measure openings etc. before fabrication.
Before delivery to site, pre-assemble where possible all items to ensure proper fit and dimension of each
item. Disassemble and pack carefully for shipping to the site. On delivery and unloading, inspect for
damage and arrange immediate replacement if necessary.
204 Miscellaneous
Fasteners: provide required bolts, screws, inserts, fasteners, templates and other accessories required
for a complete installation.
Coordinate with other trades as to the proper fastening systems suitable for the substrates to which the
item is to be secured. Refer to architect if in doubt. Fasten galvanised items with galvanised fasteners.
301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure
conditions are satisfactory for installation. Arrange for rectification required.
Start of work means total acceptance of relevant conditions.
302 Preparation
Check roof framing and other items to which safety equipment is to be fixed.
Ensure that structures local to the installed items are secure.
A senior technical representative of the material supplier is required to be present to check each part of
the installation.
303 Installation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Secure each item in accordance with Australian Standards.
Arrange with the builder and roofer for penetrations if required through roof materials.
Ensure that penetrations are completely watertight after installation and on completion of the work.
305 Testing
Arrange for tests of each item of equipment. Replace items which fail the test.
307 Cleaning
Remove surplus materials and leave the area clean on completion.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 07725 FALL ARREST EQUIPMENT
SECTION 07810 FIREPROOFING
PART I GENERAL100
101 Scope
Design, fabricate and install materials with required components, fixings, fabrication techniques,
coatings and finishes including but not limited to fire protection of structural steel columns.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1530 Methods for fire tests on building materials, compounds and structures.
There are 7 parts, 2 Amdt, 1992 – 2007.
AS 1603 Automatic fire detection and alarm systems. There are 12 parts 1996 – 2011
and 4 Amdts, 1996 – 2001.
AS 1670 Fire detection, warning, control and intercom systems - System design,
installation and commissioning. There are 4 parts, 1997 – 2015,.
AS 1682 Fire Dampers.
1682.1 1990 Specification.
1682.2 1990 Installation.
AS 2118.4 Automatic fire sprinkler systems - Residential
AS 3784.1 1990 Coatings for fire protection of building elements – Guide to selection and
installation of sprayed mineral coatings.
AS 3959 2009 Construction of buildings in bushfire-prone areas. Plus 3 Amdts 2009-2011
AS 4072.1 2005 Components for the protection of openings in fire-resistant separating
elements – Service penetrations and control joints. Plus 1 Amdt, 2006.
AS 5414 2012 Bushfire water spray systems
Bushfire Set 2009
HB 37.4 1994 Handbook of Australian fire Standards – Building materials, products and
construction.
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 07810 FIREPROOFING
5. Provision for expansion (thermal).
6. Junctions and trim to adjoining surfaces.
7. Fittings and accessories.
D. Sealants: submit manufacturer's product specifications, handling, installation/curing instructions,
and performance tested data sheets for each elastomeric product required. Submit certificate of
test reports for elastomeric sealants on aged performance, including hardness, stain resistance,
adhesion, cohesion or tensile strength, elongation, low-temperature flexibility, compression set,
modulus of elasticity, water absorption and resistance (ageing, weight loss, deterioration),
exposure to heat, ozone and ultraviolet light.
108 Warranty
Provide to the architect a written warranty stating that components of the complete installation will
remain intact and in a satisfactory condition for years from the date of Practical Completion.
PART II MATERIALS200
Before ordering materials obtain and provide to the architect written evidence that items to be installed
comply with Australian Standards and are approved by statutory authorities having jurisdiction.
If non-approved materials or components are installed, replacement will be at contractor’s expense.
204 Fabrication
A. Provide and fabricate frame and support structures.
B. Check site dimensions before fabrication of components. Tolerances are not to exceed +3mm, -
3mm.
C. Schedule fabrication in accordance with builder's construction program.
D. Mark each item for easy identification.
301 Examination
Examine conditions at the site before delivery of materials and prior to the commencement of
installation. Arrange with builder for correction of non-optimum conditions.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 07810 FIREPROOFING
Protect by appropriate means adjoining surfaces of the building which may be damaged during the
installation.
303 Installation
Install/apply 30mm Promatect 250 fireproofing materials to structural steel columns in locations as
detailed on the documents to achieve an FRL of 120/-/-. Secure in final position.
Comply with supplier's/manufacturer's installation recommendations.
Apply plasterboard skim coat finish to any exposed face prior to the application of paint finish.
304 Sealants
At junctions with other materials, insert into opening a backing rod, wedged firmly in place. Apply over
the backing rod an approved fireproofing sealant, to colour selected by the architect.
Comply with supplier's/manufacturer's installation recommendations.
306 Repairs
Repair damaged surfaces which may have been damaged during installation.
Make good the surfaces and reinstate material integrity, all in strict accordance with manufacturer’s
instructions.
307 Protection
Protect the installation until completion of the project. Prevent damage to completed work by necessary
means.
308 Cleaning
On completion, clean up debris, remove support structures, scaffolding and the like. Leave work and
surfaces in entirely clean and uniform condition.
309 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 07810 FIREPROOFING
SECTION 08200 DOORS, DOOR FRAMES AND HATCHES
PART I GENERAL100
101 Scope
Supply and install doors and timber [or steel] door frames including but not limited to:
A. EXTERNAL DOORS
Timber doors in metal frames (jambs).
Solid core doors.
B. INTERNAL DOORS
Flush panel doors - solid core.
Metal frames (jambs).
Acoustic doors.
Glazed doors.
Include in each prototype elements required by this specification, finished in every respect. When
approved by the architect, each prototype remains part of the work and becomes the standard for the
remaining work.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1288 2006 Glass in buildings - Selection and installation.
Plus 1 Supplement, 2006, and 2 Amdt, 2008 - 2011.
AS 1428.1 Design for access and mobility. General requirements – New building work ..
AS/NZS 1859 Reconstituted wood-based panels - Specifications
1859.1 2004 Particleboard. Plus 2 Amdt, 2006 - 2011.
1859.2 2004 Dry processed fibreboard. Plus 2 Amdts, 2006.
1859.3 2005 Decorative overlaid wood panels. Plus 1 Amdt, 2009.
1859.4 2004 Wet-processed fibreboard.
AS/NZS 2272 2006 Plywood – Marine.
AS 2688 1984 (Obsolescent) Timber doors.
AS 2689 1984 (Obsolescent) Timber doorsets.
AS 4145 Locksets and hardware for doors and windows. There are 5 parts, 2001 –
2011 plus 2 Amdts, 2009, 2015.
AS 5007 2007 Powered doors for pedestrian access and egress.
AS 5039 2008 Security screen doors and security window grilles.
105 Submissions
Submit the following for inspection by the architect before installation:
Product literature on proposed hardware items.
Samples of items as requested by architect.
107 Warranty
Provide to the proprietor a warranty covering faulty materials, and installation, warping of materials and
other faults which may occur within 5 years of Practical Completion.
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 08200 DOORS, DOOR FRAMES AND HATCHES
PART II MATERIALS200
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 08200 DOORS, DOOR FRAMES AND HATCHES
204 Hatches
For ceiling hatches ensure that the ceiling performance levels are matched by the hatch construction
and performance levels.
301 Examination
Inspect site conditions. Ensure conditions are satisfactory for installation.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Prepare openings in walls or other structures before installation. Install fixing grounds and inserts as
required to secure frames.
307 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 08200 DOORS, DOOR FRAMES AND HATCHES
SECTION 08330 ROLLER SHUTTER DOORS
PART I GENERAL100
101 Scope
Supply, engineer and install roller shutter door(s) including but not limited to:
Drum support.
Door guides.
Electric motors and controls.
Locking devices.
Wind locks.
Weatherstrips.
Tapered bottom rail.
Powder coating.
104 References
Comply with applicable portion of the following Australian Standards:
AS 1905.2 2005 Components for the protection of openings in fire-resistant walls – Fire-
resistant roller shutters.
Comply with requirements of statutory and local authorities.
106 Samples
A. Sample welds: if requested, provide samples of weld types, including samples of railings joined
at right angles and at typical acute angles, welded and ground smooth, for approval. If not
acceptable, provide additional samples until approved. When approved, samples will establish
quality of similar work of this trade section.
B. Check on delivery: request architect to check materials on delivery to site for quality, and
materials not meeting the requirements of this specification or equal to approved samples will be
rejected.
Return rejected materials to the fabricator at the fabricator's expense.
C. Finish: provide samples of specified finishes when requested.
107 Warranty
Provide to the proprietor a warranty, counter-signed by the installer, on the whole of the installation,
which states that work will remain intact, waterproof and fully operational for the period of not less than 5
years after date of Practical Completion.
PART II MATERIALS200
Before ordering materials obtain and provide to the architect written evidence that items to be installed
comply with Australian Standards and are approved by statutory authorities having jurisdiction.
If non-approved materials or components are installed, replacement will be at contractor’s expense.
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 08330 ROLLER SHUTTER DOORS
201 Acceptable Manufacturers
Mirage Doors B&D Commercial Roller Doors Arco Architectural Systems
202 Materials
A. Roller Shutter: Mirage S75 Steel Roller Shutter
Curtain: 75 x 1.0mm roll formed galvanised steel interlocking slats,
Drum: mild steel or galvanised tube with the outside diameter and thickness appropriate to the size
and application of the steel roller shutter.
Channel guides: 75MM X 37MM roll formed steel
Brackets: fabricate from prime painted mild steel, with the steel gauge to suit the shutter sizes.
Bottom rail: steel box section to accept a weatherseal.
Operation: 1.5 h.p. Electric motor / gearbox c/- push button operation via a reversing contactor,
including emergency chain operation in the event of power failure. Provide key switch in external
weatherproof enclosure.
Finish: Dulux Duralloy powdercoat.
Colour: Refer Exterior Finishes Schedule.
301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure
conditions are satisfactory for installation. Arrange for rectification required.
Start of work means total acceptance of relevant conditions.
302 Preparation
A. Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian
Standards, as relevant.
B. Field measurements: do not delay job progress. Allow for adjustments and fitting of the work in
the field where taking of measurements might cause delay.
C. Coordination with work of others: furnish to each relevant trade foreman anchorages and setting
drawings, diagrams, templates and instructions for installation of items having integral anchors
which are to be embedded in concrete or masonry construction. Coordinate delivery of such
items to the project site.
304 Installation
A. Anchorage: except for anchorages furnished herein but placed by other trades, set and secure
necessary anchorages, including concrete and masonry inserts, bolts, wood screws and other
connectors as needed. Perform cutting, drilling and fitting as needed, locating anchorages and
holes to ensure proper positioning of completed work.
B. Fit: during installation and assembly, form tight joints with exposed connections accurately fitted,
and reveals uniform. Finish work accurately, plumb, level, square and true in reference to
adjacent construction.
C. Finish: do not cut or abrade shop finishes which cannot be completely restored in the field.
The use of gas-cutting torch in the field for correcting fabrication errors will not be permitted.
Fabrications may be cut shorter with power hacksaws on site.
Isolate dissimilar metals likely to be subject to moisture with inert materials, not visible on
completion of installation.
D. Comply with manufacturers' installation instructions throughout.
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 08330 ROLLER SHUTTER DOORS
305 Field Quality Control
Where considered necessary by the architect, arrange for supervision of the installation by a senior staff
member of the manufacturer.
306 Protection
Protect the completed installation from damage by appropriate means until completion of the project.
307 Cleaning
Clean materials installed to the satisfaction of the architect.
Apply necessary lubrication.
Remove temporary protective coating.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 08330 ROLLER SHUTTER DOORS
SECTION 08520 METAL WINDOWS AND GLAZING
PART I GENERAL
101 Scope
Design, engineer, supply and install a complete glazed system of windows, doors and screens, including
but not limited to:
Material type
Finish type
Openings
Glass types
Glazing methods
Insect screens
Ensure compliance with BCA requirements regarding the protection of openable windows.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1170 Structural design actions.
1170.0 2002 General principles. Plus 5 Amdts, 2003 – 2011.
1170.1 2002 Permanent, imposed and other actions. Plus 2 Amdts,
2005 – 2009.
1170.2 2011 Wind actions.
1170.3 2003 Snow and ice actions. Plus 1 Amdt, 2007.
1170.4 2007 Earthquake actions in Australia. 1 Amdt 2015
There are several Supplements and Amdts, 2002 – 2011.
AS 1231 2000 Aluminium and aluminium alloys – Anodic oxidation coatings.
AS 1288 2006 Glass in buildings - Selection and installation.
Plus 1 Supplement, 2006 and 2 Amdts, 2008 - 2011.
AS 2047 2014 Windows and external glazed doors in buildings - Selection and installation.
AS 3715 2002 Metal finishing - Thermoset powder coating for
architectural applications of aluminium and aluminium alloys.
AS 4145.2 2008 Locksets and hardware for doors and windows – Mechanical locksets for
doors and windows in buildings. Plus 2 Amdts, 2009, 2015.
HB 125 2007 The glass and glazing handbook.
Comply with relevant authority's requirement for fire-rated installation.
Providence Christian College Primary School Stage 1 Page 1 of 5 SECTION 08520 METAL WINDOWS AND GLAZING
B. Statement that the proposed system meet(s) the regulatory requirements, thermal, aesthetic and
waterproofing criteria and wind loading, construction, glazing and warranty requirements
specified; noting in detail exceptions.
C. Shop drawings: refer DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT,
clause 27. Provide shop drawings showing the following information where appropriate to the
items:
Layout (sectional plan and elevation of complete assembly).
Full size section of members.
Methods of assembly, type and location of exposed screws.
Methods of glazing.
Methods of installation, including fixings, anchorage, caulking, flashings.
Provision for expansion (thermal).
Junctions and trim to adjoining surfaces.
Fittings and accessories.
D. Engineer's calculations on wind loading.
E. Sealants: submit manufacturer's product specifications, handling, installation/curing instructions,
and performance tested data sheets for each elastomeric product required. Submit certificate test
reports for elastomeric sealants on aged performance as specified, including hardness, stain
resistance, adhesion, cohesion or tensile strength, elongation, low-temperature flexibility,
compression set, modulus of elasticity, water absorption, and resistance (ageing, weight loss,
deterioration) and exposure to heat, ozone and ultraviolet light.
107 Warranty
Provide to the proprietor a warranty, counter-signed by the installer, on the whole of the installation,
which states that work will remain intact, waterproof and fully operational for the period of not less than
years after date of Practical Completion.
PART II MATERIALS
202 Materials
A. Window frames: Alspec McArthur 101x44 centre pocket framing as scheduled on the drawings
with sub-head and sub-sill extruded aluminium components manufactured from aluminium alloy
6063, temper T5 or T6.
B. Doors: Alspec Swan 45mm commercial door series as scheduled on the drawings extruded
aluminium components manufactured from aluminium alloy 6063, temper T5 or T6.
C. Glass: refer clause 206.
D. Sliding windows: Alspec View-Max Commercial sliding window extruded aluminium components
manufactured from aluminium alloy 6063, temper T5 or T6.
E. Folding doors and frames: Alspec Hawkesbury 101x44 commercial multi-fold door manufactured
from aluminium alloy 6063, temper T5 or T6, with flat sill and integral Stormtech stainless steel
grate.
F. Awning windows: Alspec 50mm commercial awning window extruded aluminium components
with lockable chainwinder with security screen adaptor.
G. Vertical sliding windows: Alspec Provista sashless double hung window.
H. Security Insect Screens: Alspec Invisiguard steel security mesh screens manufactured from
grade 316 stainless steel as scheduled on the drawings. Note all screens to first floor windows to
comply with AS5203-2016 for fall prevention.
Providence Christian College Primary School Stage 1 Page 2 of 5 SECTION 08520 METAL WINDOWS AND GLAZING
2. Structural members of glazed units of such strength that when tested at the specified
design wind values they do not deflect by an amount greater than span/240 and do not
cause permanent deflection.
3. Fix members so that the above loading is generated in the members without stress
causing failure or movement becoming evident at any joint.
K. Movement: permit free and noiseless movement of the components due to thermal effects,
structural effect, wind pressure, effect of dead loads, without strain to glass, without buckling of
components and without excessive stress to members or assemblies.
L. Contact with other materials: coat metal surfaces in contact with mortar, concrete, plaster,
masonry, wet-application of fire-proofing and absorbent materials with an anti-galvanic, moisture
barrier material. Isolate, with inert material, dissimilar metals for the prevention of electrolytic
action and corrosion.
M. Distortion: design the glazed assembly to minimise visual distortion of reflected images.
205 Finish
Ensure that in corrosive environment the proposed finish meets the product manufacturer’s warranty.
The warranty may be subject to ongoing maintenance procedures, confirm these at shop drawings
stage.
Refer to Finishes Schedule for type and coating thickness.
Polyester powder coat:
Polyester powdercoated, to colour approved by the architect and by the manufacturer of the powder
material, to metal of windows, doors and shop fronts.
Perform pre-treatment and application of powder coating by applicators approved by the architect and
by the manufacturer of the powder material.
Minimum coating thickness of 50 microns subjected to random testing after installation. Non-conforming
material will be removed and made good by the builder.
Comply with requirements of AS 3715.
206 Glass
Metal of windows, doors and shop fronts anodised to selected colour. Refer to approved national energy
rating system or Section J for glass selection.
A. Glass materials for external use: Viridian Comfort Plus Clear glazing, minimum 6.38mm thick.
B. Glass material for internal use: Clear laminated glass minimum 6.38mm thick.
C. Calculations: calculate glass sizes and thicknesses in accordance with Standards, and fixing
devices and connections to structure in accordance with engineer's computations where
applicable.
Providence Christian College Primary School Stage 1 Page 3 of 5 SECTION 08520 METAL WINDOWS AND GLAZING
E. Bond breaker tape: polyethylene tape or other plastic as recommended by sealant manufacturer
to be applied to sealant-contact surfaces where bond to substrate or joint filler is to be avoided
for proper performance of sealant. Provide self-adhesive tape where applicable.
F. Sealant backer rod: compressible rod stock of polyethylene foam, polyethylene jacketed
polyurethane foam, butyl rubber foam, neoprene foam or other flexible permanent, durable non-
absorbent material as recommended by sealant manufacturer for compatibility with sealant.
G. Glazing tape: polyisobutylene tape of type, thickness and width as recommended by glass
manufacturer and architect.
H. Exposed screws: countersunk type, anodised aluminium or non-magnetic stainless steel evenly
and neatly located in an approved manner. Exposed fasteners: finished to match aluminium.
208 Fabrication
Comply with AS 2047.
Framing system: fabricate from extrusions to profiles shown on approved shop drawings.
Form junctions so that no fixings, such as pins, screws, pressure indentations and the like are visible on
exposed faces. Show on shop drawings fixings which will be exposed. Cut edges, drill holes, rivet joints
and clean flat sheets, neat, free from burrs and indentations. Remove sharp edges without excessive
deformation. Fit mitred joints accurately to a fine hairline.
Pre-assemble and match mark before delivery.
301 Examination
Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are
satisfactory for installation.
Perform rectification required before delivery of materials.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.
305 Glazing
Secure glass in accordance with glass manufacturer's recommendations and AS 1288. Allow for thermal
expansion of glass, the metal framing and spandrels.
Providence Christian College Primary School Stage 1 Page 4 of 5 SECTION 08520 METAL WINDOWS AND GLAZING
307 Installation of Sealants
A. Install bond breaker tape where required by manufacturer's recommendations to ensure that
elastomeric sealants will perform properly.
B. Employ only proven installation techniques, which will ensure that sealants are deposited in
uniform continuous ribbons without gaps or air pockets, with complete "wetting" of joint bond
surfaces equally on opposite sides. Except as otherwise indicated, fill sealant rabbet to a slightly
concave surface slightly below adjoining surfaces.
C. Install sealant to depths as recommended by sealant manufacturer.
D. Cure sealants and caulking compounds in compliance with manufacturer's instructions and
recommendations, to obtain high early bond strength internal cohesive strength and surface
durability.
Advise architect of procedures required for cure and protection of joint sealers during
construction period, so that they will be without deterioration or damage (other than normal wear
and weathering) at time of Practical Completion.
E. Remove excess caulking compound and sealant and leave surfaces neat, smooth and clean,
without smears on surrounding work. Tool joints where recommended by manufacturer or where
required. Remove cartons and debris from site as the work progresses.
309 Protection
A. Framing system: protect metal surfaces as necessary during erection. Finish surfaces free from
mechanical imperfections such as scratches, scrapes, dents, spots, stains and streaks.
B. Glass: protect glass from breakage immediately upon installation and until Practical Completion.
Remove and replace glass and metal panels which are broken, cracked, abraded, chipped or
damaged in other ways, before, during or after installation, at no additional cost to proprietor.
C. Be responsible for breakage and damage to installation until Practical Completion.
310 Cleaning
A. Remove labels, excess glazing compounds, stains, spots and other foreign matter from glass,
frames, hardware and other finished surfaces immediately upon installation of glazing for each
light.
B. Debris: remove rubbish and debris resulting from glazing operations, each day.
311 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 5 of 5 SECTION 08520 METAL WINDOWS AND GLAZING
SECTION 08710 DOOR HARDWARE
PART I GENERAL100
101 Scope
Supply and install door hardware including but not limited to:
Wall mounted grilles for ventilation and other purposes.
Hinges.
Pivots.
Latches.
Locks.
Door holders.
Push plates.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1428 Design for access and mobility. There are 5 parts. 1992 – 2010.
AS 1909 1984 (Obsolescent) Installation of timber doorsets.
AS 2688 1984 (Obsolescent) Timber doors.
AS 2689 1984 (Obsolescent) Timber doorsets.
AS 4145 Locksets.
4145.2 2008 Mechanical locksets for doors in buildings.
There are 4 other parts, 2001 - 2011 plus 2 Amdts 2009, 2015.
AS 4178 1994 Electromagnetic door holders.
Comply with requirements of statutory and local authorities.
106 Warranty
Provide to the proprietor a warranty covering faulty materials and installation for 5 years from date of
Practical Completion.
PART II MATERIALS200
Before ordering materials obtain and provide to the architect written evidence that items to be installed
comply with Australian Standards and are approved by statutory authorities having jurisdiction.
If non-approved materials or components are installed, replacement will be at contractor’s expense.
201 Manufacturers
203 Miscellaneous
Fasteners: provide required bolts, screws, inserts, fasteners, templates and other accessories required
for a complete installation.
Coordinate with other trades as to the proper fastening systems suitable for the substrates to which the
item is to be secured. Refer to architect if in doubt.
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 08710 DOOR HARDWARE
PART III EXECUTION
301 Examination
Examine the materials to which door hardware is to be fixed.
Ensure conditions are satisfactory for installation.
Start of work means total acceptance of conditions.
302 Preparation
Remove hardware from surfaces to be painted. Replace when paint is dry.
303 Installation
Comply throughout with the written instructions of manufacturer.
304 Keys
Supply duplicate labelled keys for each lock. Provide plastic tags for each key.
Arrange with architect for location of a key cupboard.
Fit cupboard with hooks for each key with room names or numbers.
Install cupboard where instructed.
305 Testing
Check each key in relevant lock for satisfactory operation. Replace defective keys or locks.
Clean the materials installed.
Remove construction locks.
306 Coordination
Before finalising hardware order, review with security sub-contractor work related to reed switches,
electric locks/strikes etc. Generally such items will be supplied by the security contractors and fitted to
doors and frame by the builder.
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 08710 DOOR HARDWARE
308 Door Hardware Provisional Sum
Allow a Provisional Sum (PS) of $ 90,000.00 plus GST for the supply of door hardware by a nominated
supplier.
END OF DOCUMENT
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 08710 DOOR HARDWARE
SECTION 08800 GLASS AND GLAZING
PART I GENERAL100
101 Scope
Supply and install a complete system of glass, glazing and sealants including but not limited to:
Glass, clear float
spandrel
Glass, laminated
Glass, tinted, heat reflecting, mirrored
Glazing bars
Glazing beads, strips
Sealants and related materials
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1170 Structural design actions.
1170.0 2002 General principles. Plus 5 Amdts, 2003 – 2011.
1170.1 2002 Permanent, imposed and other actions. Plus 2 Amdts,
2005 – 2009.
1170.2 2011 Wind actions.
There are 2 other parts, several Supplements and Amdts, 2002 – 2011.
AS 1288 2006 Glass in buildings - Selection and installation.
Plus 1 Supplement, 2006 and 2 Amdts, 2008 - 2011.
AS/NZS 2208 1996 Safety glazing materials in buildings. Plus 1 Amdt, 1999.
AS/NZS 2343 1997 Bullet-resistant panels and elements.
AS 4145.2 2008 Locksets and hardware for doors and windows – Mechanical locksets for
doors and windows in buildings. Plus 2 Amdts, 2009, 2015.
AS 4666 2012 Insulating glass units
HB 125 2007 The glass and glazing handbook.
Comply with relevant authority's requirement for fire-rated installation.
Providence Christian College Primary School Stage 1 Page 1 of 4 SECTION 08800 GLASS AND GLAZING
Types, model numbers and names of products, and indication whether products are "off the
shelf" or custom fabricated. Include specific information on finishes - thicknesses,
patented process name, process description and test data.
Detailed information on products manufactured specifically for this project. Detailed system
description including standard details and manufacturer's literature; and large-scale details of
specially fabricated products.
B. Statement that the proposed system(s) meet(s) the regulatory requirements, thermal, aesthetic
and waterproofing criteria and wind loading, construction, glazing and warranty requirements
specified; noting in detail exceptions.
C. Shop drawings: pursuant to DOCUMENT 00800, clause 27 and the provisions of this document,
provide the shop drawings showing the following information where appropriate to the items:
1. Layout (sectional plan and elevation of complete assembly).
2. Full size section of members.
3. Methods of assembly.
4. Methods of glazing.
5. Methods of installation, including fixings, anchorage, caulking, flashings.
6. Provision for expansion (thermal).
7. Junctions and trim to adjoining surfaces.
8. Fittings and accessories.
D. Engineer's calculations on wind loading.
E. Sealants: submit manufacturer's product specifications, handling, installation/curing instructions,
and performance tested data sheets for each elastomeric product required. Submit certificate
test reports for elastomeric sealants on aged performance as specified, including hardness, stain
resistance, adhesion, cohesion or tensile strength, elongation, low-temperature flexibility,
compression set, modulus of elasticity, water absorption, and resistance (ageing, weight loss,
deterioration) and heat and exposure to ozone and ultraviolet light.
107 Warranty
In addition to the warranty requirements of the General Conditions of Contract, provide the following:
A. Warranty: provide glass manufacturer's written warranty, agreeing to, within specified warranty
period, furnish freight paid to project site, replacement units for glass units which have defective
hermetic seals (excluding that due to glass breakage), defined to include intrusion of moisture or
dirt, internal condensation at temperatures above -2°C, deterioration of internal glass coatings,
and other visual evidence of seal failure or performance failure; provided manufacturer's
instructions for handling, installation, protection and maintenance have been adhered to during
warranty period.
B. Warranty period is 10 years after date of installation and not less than10 years after date of
Practical Completion.
PART II MATERIALS200
Providence Christian College Primary School Stage 1 Page 2 of 4 SECTION 08800 GLASS AND GLAZING
Part 1, Section 4, Human Impact Safety Requirements, AS/NZS 2208.
Part 1, Section 3, Non-Vertical Situations.
Part 2, Glazing techniques. Choose the method directly from the eight sections of this part of the
Standard.
301 Examination
Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are
satisfactory for installation.
Arrange for rectification required before delivery of materials.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.
Providence Christian College Primary School Stage 1 Page 3 of 4 SECTION 08800 GLASS AND GLAZING
303 Preparation for Sealants
Joint preparation sealants: clean joint surfaces immediately before installation of sealant or caulking
compound. Remove dirt, insecure coatings, moisture and other substances which could interfere with
bond of sealant or caulking compound. Etch concrete and masonry joint surfaces as recommended by
sealant manufacturer. Roughen vitreous and glazed joint surfaces if recommended by sealant
manufacturer and comply with his instructions.
Prime or seal joint surfaces where indicated, and where recommended by sealant manufacturer. Do not
allow primer/sealer to spill or migrate on to adjoining surfaces.
304 Glazing
Secure glass in accordance with glass manufacturer's recommendations and AS 1288. Allow for thermal
expansion of glass, the metal framing and spandrels.
307 Protection
A. Framing system: protect metal surfaces as necessary during erection.
B. Finish surfaces free from mechanical imperfections such as scratches, scrapes, dents, spots,
stains and streaks.
C. Glass: protect glass from breakage immediately upon installation until Practical Completion.
Remove and replace glass and metal panels which are broken, cracked, abraded, chipped or
damaged in other ways, before, during or after installation, at no additional cost to the Proprietor.
D. Be responsible for breakage and damage to installation until Practical Completion.
308 Cleaning
A. Remove labels, excess glazing compounds, stains, spots and other foreign matter from glass,
frames, hardware and other finished surfaces immediately upon completion of each panel of
glazing.
B. Debris: remove rubbish and debris resulting from glazing operations, each day.
309 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 4 of 4 SECTION 08800 GLASS AND GLAZING
SECTION 08850 MIRRORS
PART I GENERAL
101 Scope
Supply and install mirrors including but not limited to:
Glass mirrors - laminated safety glass
104 References
Comply with applicable portions of the following Australian Standards:
AS 1288 2006 Glass in buildings - Selection and installation.
Plus 1 Supplement, 2006 and 2 Amdts, 2008 - 2011.
AS/NZS 2208 1996 Safety glazing materials in buildings. Plus 1 Amdt, 1999.
105 Submissions
If not specified in Part II Materials, the following submissions are required before ordering materials:
PART II MATERIALS
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 08850 MIRRORS
B. Or an alternative mirror faced bi-fold door system provided complete with components
recommended by its manufacturer.
301 Examination
Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are
satisfactory for installation. Perform rectification required before delivery of materials.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.
Clean glass surfaces immediately before applying silicone sealants to the edges of mirrors. Remove dirt,
insecure coatings, moisture and other substances that could interfere with the bond of the sealant.
Thoroughly clean down the backings to remove dust, dirt and other substances that:
- could interfere with the bond of the adhesive
- could interfere with the bond of the double sided tape
Sand down gloss surfaces of backings to provide porous type finish.
Seal new plasterboard or hard plaster backings with 1 coat of pigmented sealer.
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 08850 MIRRORS
308 Proprietary Brand Systems
A. Proprietary brand glass mirror faced sliding door systems installed in accordance with
manufacturer's printed instructions.
B. Proprietary brand glass mirror faced bi-fold door system installed in accordance with the
manufacturer's printed instructions.
C. Install in the exposed grid, suspended metal ceiling grid in accordance with the manufacturer's
printed instructions. Provide 3mm minimum clearance between the panels and the vertical
flanges of the ceiling grid rails.
309 Protection
A. Aluminium components: protect metal surfaces as necessary during erection and until Practical
Completion. Finish surfaces free from mechanical imperfections such as scratches, scrapes,
dents, spots, stains and streaks.
B. Mirrors: protect mirrors from breakage immediately upon installation until Practical Completion.
Remove and replace mirrors and metal parts that are broken, cracked, abraded or damaged in
other ways before, after or during installation up to the date of Practical Completion at no
additional cost to the proprietor.
310 Cleaning
A. Remove labels, excess silicone, stains, spots and other foreign matter from mirrors, frames,
hardware and other finished surfaces immediately upon completion of the installation of each
mirror. Use cleaning systems recommended by the manufacturer of the mirror type.
B. Debris: remove rubbish and debris resulting from glazing operations each day.
311 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 08850 MIRRORS
SECTION 09200 HARD PLASTER OVER RENDER BASE
PART I GENERAL
101 Scope
The work of this trade section includes but is not limited to the supply and installation of new (render
base and hardwall plaster) work on masonry surfaces as follows:
Glass face cement render to walls
104 References
Comply with applicable portions of the following Australian Standards; current edition:
AS 3700 2011 Masonry structures. There is 1 Supplement 2012, Amdt 2015
AS 3972 2010 General purpose and blended cements.
HB 161 2005 Guide to plastering
106 Warranty
On completion of the work, provide a warranty to the proprietor stating that the work is secure against
defects including delamination from substrate, “blowing", "grinning" and "crazing" for the period of
years from the date of Practical Completion.
PART II MATERIALS
Providence Christian College Primary School Stage 1 Page 1 of 4 SECTION 09200 HARD PLASTER OVER RENDER BASE
Soluble salts content (W/W%) 0.15 max.
NOTE: When instructed by the architect, arrange for laboratory tests to be carried out on sand
samples at no cost to proprietor.
C. Lime (if required): Hydrated lime.
D. Water: Clean, drinkable.
204 Mixes
A. Render base (float coat):
Render over masonry and concrete substrates: sand: 6 parts by volume.
lime: 1 part by volume.
cement: 1 part by volume.
Use minimum water content to achieve workability and adhesion.
Measure parts in mixes by dry volume in gauge boxes. Keep gauge boxes clean and free from
hardened materials.
Do not use any other additives without written permission of the architect.
B. Plaster finish (set coat):
Thistle Multi Finish applied strictly in accordance with the manufacturer’s written instruction
Do not use any other additives without written permission of the architect.
C. Render base (glass face cement render); sand: 6 parts by volume.
cement: 1 part by volume
Use minimum water content to achieve workability and adhesion.
Measure parts in mixes by dry volume in gauge boxes. Keep gauge boxes clean and free from
hardened materials.
Do not use any other additives without written permission of the architect.
D. Finish coat (glass face cement render); sand: 1 parts by volume.
cement: 1 part by volume
Use minimum water content to achieve workability and adhesion.
Measure parts in mixes by dry volume in gauge boxes. Keep gauge boxes clean and free from
hardened materials.
Do not use any other additives without written permission of the architect.
E. Variations in mix
Obtain the architect’s prior permission to vary mixes where necessary to match new work with
existing adjacent work.
301 Examination
Acceptance: notify the architect of discrepancy or unsuitability of substrate.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Remove foreign material, dust, dirt, oil, nails and other material which could reduce bonding of render
base to the masonry substrate.
Providence Christian College Primary School Stage 1 Page 2 of 4 SECTION 09200 HARD PLASTER OVER RENDER BASE
Apply top coats on each plane in a single operation without joints or breaks.
Dampen render base 3 hours after application.
Do not allow finishes to dry out within 48 hours.
Continue render base behind the full extent of unlined fittings.
Finish curved surfaces to a true radius.
At construction joints between different substrate sections or materials, install:
Galvanised stopping beads fixed to substrates each side of joint.
V-joint in render/plaster at construction joints.
Wall finish control joint as detailed.
311 V-Joints
Unless otherwise detailed, form V-joints where plaster finish abuts insitu concrete, face brickwork,
blockwork, plasterboard or timber surfaces.
313 Cleaning
Clean up and remove from site excess materials and debris resulting from operations. Clean and restore
to original condition adjacent materials affected by the work.
Providence Christian College Primary School Stage 1 Page 3 of 4 SECTION 09200 HARD PLASTER OVER RENDER BASE
314 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 4 of 4 SECTION 09200 HARD PLASTER OVER RENDER BASE
SECTION 09210 CEMENT RENDER
PART I GENERAL
101 Scope
The work of this trade section includes but is not limited to the supply and installation of cement render
work
Provide render to locations shown on the drawings and with reference to the Finishes Schedule included
in this documentation.
Where proprietary type render is used provide to the product manufacturer’s specifications.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1672.1 1997 Limes and limestones – Limes for building.
AS 3700 2011 Masonry structures. There is 1 Supplement 2012, Amdt 2015
AS 3972 2010 General purpose and blended cements.
CIA Z39 2008 Render finishes.
Render is a data sheet published by Cement Concrete & Aggregates Australia. Visit
www.concrete.net.au
106 Warranty
On completion of the work, provide a warranty through the builder to the proprietor stating that the work
is secure against defects including delamination from substrate, "blowing", "grinning", and "crazing" for
the period of 7years from the date of Practical Completion.
PART II MATERIALS
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 09210 CEMENT RENDER
D. No additives may be used without architect’s written approval.
202 Accessories
Supplied by Rondo Building Services Pty. Ltd.
Rondo EXTREME UV stabilised PVC render beads to all exterior corners.
203 Mixes
Render over masonry and concrete substrates: not greater than 6 parts sand, 1 part lime, 1 part cement,
by volume. Machine mix materials.
301 Examination
Acceptance: notify architect of discrepancy or unsuitability of substrate.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Remove foreign material, dust, dirt, oil, nails and other material which could reduce bonding of render to
the surface.
310 V-Joints
Form V-Joints in render where steel door frames are flush with render, also where insitu concrete beams
abut brickwork or blockwork and where concrete or masonry walls abut plasterboard or timber substrate.
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 09210 CEMENT RENDER
311 Cleaning
Clean up and remove from site excess materials and debris resulting from operations. Clean and restore
to original condition adjacent materials affected by the work.
312 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 09210 CEMENT RENDER
SECTION 09250 PLASTERBOARD
PART I GENERAL100
101 Scope
Supply and install a complete installation of plasterboard including but not limited to:
Plasterboard
Lining of concrete and masonry walls
Lining of steel stud walls
Lining with water-resistant plasterboard
Ceilings, drop walls, bulkheads
Cornices.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 2589 2007 Gypsum linings - Application and finishing.
HB 161 2005 Guide to plastering
106 Warranty
Provide warranty covering the work against defective materials and workmanship for a period of 5
years from the date of Practical Completion. The warranty includes a statement that the whole of the
work has been carried out in accordance with relevant Australian Standards and Codes and
manufacturer's instructions in effect at the time of installation.
PART II MATERIALS
202 Materials
Supply materials in accordance with material supplier's recommendations for each application. Refer to
the drawings for locations and extent of boards.
13mm thick impact resistant plasterboard, minimum mass 10.5kg/m2.
13mm thick plasterboard.
13mm moisture resistant plasterboard.
13mm perforated plasterboard.
301 Examination
Acceptance: visit site and inspect conditions, comparing conditions to drawings before delivery of
materials to site. Rectify any discrepancy or unsuitability of substrate.
Start of work means total acceptance of conditions.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 09250 PLASTERBOARD
302 Preparation
A. Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian
Standards, as relevant.
B. Coordinate with and ensure preparatory work by other trades is done prior to commencement of
work; failure to do so will involve removal of plasterboard and immediate rectification.
C. Arrange for provision of additional stud, nogging, trimmed openings, boxed studs, fixing grounds,
etc., required for satisfactory execution of the work of this trade including penetrations through
plasterboard for services. Cooperate in installation of frames, duct openings, etc.
D. Space enclosure: do not install materials until space is enclosed and weatherproof, and until wet-
work in space is completed and nominally dry.
307 Protection
Protect finished work. Make good damage in every respect at no additional cost to the proprietor, and
without delay to job progress.
308 Cleaning
A. Adjust and clean: clean exposed surfaces including trim, edge moldings, and comply with
manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and
replace work which cannot be successfully cleaned and repaired to permanently eliminate
damage.
B. Remove spatterings and droppings resulting from work. Remove daily surplus materials and
rubbish from the work area.
C. Leave floors broom clean at completion.
309 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 09250 PLASTERBOARD
SECTION 09260 DRY WALL PARTITIONS
PART I GENERAL
101 Scope
Supply and install drywall partitions including but not limited to:
Steelwork
Stud wall framing
Plasterboard
Pre-surfaced panels of plasterboard etc.
Other:
Include in each prototype all elements required by this specification, and finish in every respect.
When approved by the architect, such samples will be the control standard and remain part of the work.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1428 Design for access and mobility. There are 5 parts. 1992 – 2010.
AS 1684 Residential timber-framed construction. There are many parts and
Supplements, 1999 – 2010 and Amdts 2012, 2013.
AS/NZS 2589 2007 Gypsum linings - Application and finishing.
2589.1 1997 (Available Superseded) Gypsum plasterboard.
2589.2 1997 (Available Superseded) Fibre reinforced gypsum
plaster.
AS 3623 1993 Domestic metal framing.
AS/NZS 4600 2005 Cold-formed steel structures. Plus 1 Amdt, 2010.
106 Warranty
Provide warranty covering the work against defective materials and workmanship for a period of 5 years
from the date of Practical Completion. Include a statement that the whole of the work has been carried
out in accordance with relevant Australian Standards and codes and manufacturer's instructions in effect
at the time of installation.
PART II MATERIALS
202 Materials
Supply materials in accordance with material supplier's recommendations for each application. Refer to
the drawings for locations and extent of boards and framing sizes.
A. 13mm thick impact resistant plasterboard, minimum mass 10.5kg/m2.
B. 13mm thick plasterboard.
C. 13mm moisture resistant plasterboard.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 09260 DRY WALL PARTITIONS
D. 92mm lipped steel studs as nominated on the drawings, base metal thickness to suit maximum
wall height in accordance with manufacturers recommendations.
E. Acoustic and thermal insulation; refer to Insulation Thermal and Acoustic specification.
301 Examination
Visit site and inspect conditions, comparing conditions to drawings before delivery of materials to site.
Rectify discrepancy or unsuitability of substrate.
Start of work means total acceptance of conditions.
Space Enclosure: do not install materials until space is enclosed and weatherproof, and until wet-work in
space is completed and nominally dry.
302 Preparation
F. Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian
Standards, as relevant.
G. Coordinate with and ensure preparatory work by other trades is done prior to commencement of
work; failure to do so will involve removal of dry wall partition and immediate rectification.
H. Arrange for provision of additional stud, nogging, trimmed openings, boxed studs, fixing grounds,
etc., required for satisfactory execution of the work of this trade including penetrations through
plasterboard for services. Cooperate in installation of frames, duct openings, etc.
305 Protection
Protect finish work. Damage made good in every respect at no additional cost to the proprietor, and
without delay to job progress.
307 Cleaning
A. Adjust and Clean: clean exposed surfaces including trim, edge moldings, and comply with
manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and
replace work which cannot be successfully cleaned and repaired to permanently eliminate
damage.
B. Remove spatterings and droppings from work. Remove daily surplus materials and rubbish from
the work area.
C. Leave floors broom clean at completion.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 09260 DRY WALL PARTITIONS
SECTION 09300 CERAMIC TILE
PART I GENERAL100
101 Scope
Supply and install ceramic tile work including but not limited to:
Preparation of surfaces before tiling or bedding.
Bedding screeds where required.
Wall tile.
Floor tile.
Cleaning of finished tiled surfaces.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1428.1 Design for access and mobility. General requirements – New building work.
There are 5 parts. 1992 – 2010.
AS/NZS 3661.2 1994 Slip resistance of pedestrian surfaces – Guide to the reduction of slip
hazards.
AS 3740 2010 Waterproofing of domestic wet areas. 1 Amdt, 2012
AS 3958 Ceramic tiles.
3958.1 2007 Guide to the installation of ceramic tiles.
3958.2 1992 Guide to the selection of a ceramic tiling system.
AS 3972 2010 General purpose and blended cements.
AS 4663 2013 Slip resistance measurement of existing pedestrian surfaces.
Contact www.ardexaustralia.com for technical advice regarding waterproofing matters and technique.
105 Submissions
Copies of minutes of pre-installation conference.
Submissions required prior to installation: product specifications for:
adhesives, primers, prepared grouts, moisture resisting admixtures.
107 Warranty
Provide a warranty covering defects in materials and installation for a period of 5 years from the date of
Practical Completion.
PART II MATERIALS200
Providence Christian College Primary School Stage 1 Page 1 of 4 SECTION 09300 CERAMIC TILE
Item Type Required
Fineness modulus 1.6 to 2.5%
Water demand ratio by weight 0.65% maximum
Aggregate Passing 4.75m sieve 80%
Passing 6.00mm sieve 90%
Passing 8.00mm sieve 100%
Water Clean, drinking quality
Mesh Galvanised steel, welded wire fabric: minimum 2.5mm
diameter wires at 100mm centres each way.
204 Tile
Supply: specified tiles are available from the following suppliers:
Refer Interior Finishes Schedule.
206 Grout
Prepared grout: inorganic Portland cement integrated, ready-to-use, dry-curing grout. Colours to
architect’s selection.
Supply waterproof grout for wet area tiling.
301 Examination
Visit site and inspect conditions, comparing conditions to drawings, before delivery of materials to site.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Rectify any discrepancy or unsuitability of substrate.
Start of work means total acceptance of conditions.
Providence Christian College Primary School Stage 1 Page 2 of 4 SECTION 09300 CERAMIC TILE
B. Expansion Joints
Set out panels of tiling so that tiles may expand or contract to and from corners of tiled walls and
floors. Allow for expansion in each corner of 5mm minimum. Fill expansion joints with silicone
rubber.
C. Control Joints
1. Provide control joint
At junctions of dissimilar wall construction.
2. In walls, no more than 2.5 apart.
3. At junctions of wall and floor in multi-storey buildings.
D. Form junctions of different materials (e.g. tiles to carpet) so that they occur under the centre line
of doors.
Providence Christian College Primary School Stage 1 Page 3 of 4 SECTION 09300 CERAMIC TILE
is pressed or tapped firmly into position, the correct thickness is achieved and the
tile is solidly bedded over its entire surface.
3. Apply dry tiles immediately into the adhesive, before it skins.
4. Press the first tile firmly into position and then remove it to check that complete contact is
being made with the adhesive. Make occasional similar checks throughout the tiling work.
The whole of the back of the tile is to be in good contact with the adhesive. Do not allow
voids to occur beneath tiles.
5. Remove surplus adhesive remaining on the face of the tile or in the tile joints, after fixing,
before it skins.
6. Form joints straight and constant in width. Under no circumstances fix tiles with tight
joints.
7. Allow tiles to set for a minimum 24 hours before grouting and protect from weather, water
penetration, etc. during this period.
8. Expansion joints: refer clause 303 B, complying with AS 3958.1. See clause below.
C. Cement based adhesive method for extruded, quarry or terracotta floor tiles:
Secure to a prepared concrete surface with cement based adhesive 10mm thick with a 10mm
notched trowel. Comply with manufacturer’s current instructions
308 Grouting
A. Except as otherwise required, do not commence grouting for at least 24 hours after placing of
tile. Follow specific instructions of materials manufacturer.
B. Grout mix:
1. Floors: Prepared grout, acid resistive.
2. Walls: Epoxy-based mortar grout, mildew resistant.
3. Colours: as selected by the architect.
C. Grouting and curing:
1. Apply the grouting mix to as large an area as can be worked before hardening
commences. Apply with a squeegee working back and forth over the area until the joints
are completely filled. Remove surplus grout from the tiles with the aid of a damp, not wet,
cloth and the joints then tooled. After the grouting has dried, final polish using a clean, dry
cloth.
2. Remove surplus grout from the floor surface; on no account use sawdust for this purpose,
as there is a danger that sawdust entering moist joint surfaces may break down their
strength, and cause them to become porous.
3. In dry weather, grout joints after maintaining damp condition for 3 days by sponging down,
fog-spraying or other methods. Allow floors to set 48 hours before permitting ordinary foot
traffic.
309 Protection
Prevent walking on or contact with floor or wall tiles for a minimum of 7 days. During that period, cover
floor tiles.
310 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 4 of 4 SECTION 09300 CERAMIC TILE
SECTION 09500 SUSPENDED CEILING
PART I GENERAL100
101 Scope
Supply and install a complete system of suspended ceilings including but not limited to:
Plasterboard ceilings.
Acoustic tile ceilings.
Bulkheads.
Ceiling access panels.
Insulating material.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 2785 2000 Suspended ceilings - Design and installation.
AS 2946 1991 Suspended ceilings, recessed luminaires and air diffusers - Interface
requirements for physical compatibility.
AS/NZS 4600 2005 Cold-formed steel structures. Plus 1 Amdt, 2010.
105 Samples
A. Acoustical ceiling tile: provide samples of tile, as selected by architect to be supplied; not less
than 2 units of each.
B. Provide one sample of each of the following elements:
1. Rounded cornice
2. Cornice internal angle
3. Cornice external angle
C. Suspension systems: provide sample of each component of suspension and acoustic suspension
system, including both standard shapes and accessories.
107 Warranty
Provide warranty covering the work against defective materials and workmanship for a period of 10
years from the date of Practical Completion.
Include a statement that the whole of the work has been carried out in accordance with relevant
Australian Standards and manufacturer's instructions in effect at the time of installation.
PART II MATERIALS200
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 09500 SUSPENDED CEILING
202 Materials
A. Suspension system: Carrier rails shall be 45 x 38 x 0.8mm thick, roll formed steel sections
spread at 1200 centres. Fix carrier rails to 38 x 38 x 0.8mm thick galvanised coated steel angle
hanger at 1200mm centres. Note; spring or friction type suspension clips are not approved
for use.
B. Mineral fibre acoustic tiles, Armstrong Ultima + (factory applied finish, fine textured surface),
1200x600x19mm, in Armstrong Blue Tongue Aluminium 24mm Flat Face Tee exposed T-grid
proprietary suspension system and shadowline wall angle or a similar product / system
equivalent in function, quality, etc. to the approval of the architect. NRC 0.70. CAC 41dB.
C. Perforated plasterboard; CSR Gyptone 12mm square hole perforated with black scrim backing
fabric.
D. Moisture resistant plasterboard, 13mm; to all wet area ceilings and bulkheads.
E. Plasterboard: 13mm
F. Ceiling access panels in flush ceilings: Gyptone 510 x 510 access panels and frame.
G. Cornice: Rondo P50 shadowline wall angle or as specified on ceiling plans and detail drawings.
H. Casing beads, stop-ends, etc.: Rondo trims as required or a similar product equivalent in
function, quality, etc to the approval of the architect.
I. Perforated corrugated soffit lining: Coruline metal strip panels manufactured by Architectural
Ceiling Systems installed strictly in accordance with the manufacturers recommendations.
Carrier rails to be ACS P/No 4 mat black finished universal carrier rails spaced 900mm apart
commencing and finishing at a maximum of 150mm from the ends of the panels. Hangers shall
be ACS P/No 63 25x25 angle compression hangers as supplied by the manufacturer and shall
be fixed with a 12mm wafer head screw to purlins and ACS P/No 4 carriers at a maximum of
1800mm centres.
Conceal fix perforated Coruline metal ceiling face panels, 160mm wide, by means of screws or
rivets as recommended by the manufacturer through the fixing flange on one side of face panel.
Continue to install face panels applying edge pressure on each panel appropriate to achieve a
firm fixing. No rivets or other fixings shall be visible on the main body of the ceiling.
Perforated Coruline panels should be fixed in full lengths, where possible or joined end to end
with the face of a colour matched aluminium T-section trim or H mould covering the meeting of
each panel run. Ensure that the line of each panel flows through to the next bay of panels.
Face panels shall be Colorbond Zincalume 0.4mm BMT and shall be corrugated to provide 6 ribs
per panel. All fixings and raw metal edges shall be concealed. Coruline face panels shall be
perforated with 3mm diam. holes at 7mm centres in a diagonal pattern. Perforations shall cover a
width of 120mm of each face panel leaving 40mm unperforated at the side junction of each of the
panels. Wall trims to be extruded aluminium “L” of baked enamel finish to match the colour of the
panels.
Acoustic and thermal insulation, to a thickness of 50 to roof soffits and 75mm to concrete slab
soffit, shall be black faced with non-woven scrim which is to be laid over perforated ceiling panels
between the up-stand legs of the carrier rails.
J. Insulation: refer Thermal and acoustic insulation specification.
203 Accessories
Supply and install necessary accessories as indicated by component manufacturer for satisfactory and
complete installation.
204 Equipment
Supply equipment, forms, scaffolding, ladders, frames, etc. necessary for the satisfactory installation of
specified items.
301 Examination
Acceptance: visit site and inspect conditions, comparing conditions to drawings before delivery of
materials to site. Rectify unsuitable situation.
Start of work means total acceptance of conditions. Comply with referenced Standards and
manufacturer's recommendations regarding environmental conditions.
302 Preparation
Space enclosure: do not install interior acoustical ceilings until space is enclosed, is weatherproof until
wet-work in space is completed and nominally dry until work above ceilings completed, and until ambient
conditions of temperature and humidity will be continuously maintained at values near those indicated
for final occupancy.
Protect wood, metal, glass, flooring and other finished work during progress. Damage is to be made
good in every respect at no additional cost to the proprietor.
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 09500 SUSPENDED CEILING
Prepare areas and surfaces against which installation will be constructed. Ensure work by other trades
is completed before erecting suspension system.
Powder driven fasteners are not approved for use.
303 Installation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Comply throughout with applicable portions of AS/NZS 2785, or AS 2946, and with the data sheets
supplied by material manufacturer.
305 Adjustment
Adjust installation to permit installation of such items as light fittings, mechanical vent registers and the
like.
306 Protection
Protect completed installation from possible damage until issue of Practical Completion certificate.
307 Cleaning
Clean surfaces exposed to view. Replace sections or components which cannot be cleaned. Make good
damaged sections or panels affected by later work of other trades.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 09500 SUSPENDED CEILING
SECTION 09650 RESILIENT FLOORING
PART I GENERAL
101 Scope
Supply and install resilient floor surfacing material with necessary accessories and related equipment
required for the work including but not limited to:
Vinyl sheet
Moisture barrier
104 References
Comply with applicable portions of the following Australian Standards:
AS 1884 2012 Floor coverings - Resilient sheet and tiles - Laying and maintenance
practices.
AS/NZS 3661.2 1994 Slip resistance of pedestrian surfaces – Guide to the reduction of slip
hazards.
AS 4586 2013 Slip resistance classification of new pedestrian surface materials.
Comply also with instructions of manufacturers of materials to be installed.
105 Submissions
Provide samples and data sheets of materials.
Obtain architect's approval for each item before ordering.
107 Warranty
Provide a warranty covering aspects of the installation performed by this trade, against defective
materials and workmanship for a period of 5 years from the date of Practical Completion. The warranty
includes a statement that the whole of the work has been carried out in accordance with AS 1884 and
the instructions of the manufacturers of components in effect at the time of installation.
PART II MATERIALS
201 Materials
Vinyl sheet: refer to Interior Finishes Schedule.
Adhesive: refer AS 1884.
Moisture barrier: Emer Proof Aqua Barrier by Parchem.
Movement joint cover strip: Armstrong X-pand Strip or similar.
202 Equipment
Supply equipment required for the preparation of floor, and installation of vinyl materials as
recommended by the material manufacturer.
301 Examination
Examine the site conditions applicable to each installation and comply with AS 1884.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Start of work means total acceptance of conditions.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 09650 RESILIENT FLOORING
302 Preparation
Prepare each area to be surfaced in accordance with AS 1884. Test the dryness of concrete sub-floor in
accordance with AS 1884.
303 Installation
A. Moisture content: Test the moisture content of the concrete to AS 1884 Appendix A Submit
moisture content test results to the architect and obtain approval prior to application of the
membrane. If the values required in clause A3.1.2 or A3.1.3 are not obtained apply Emer Proof
Aqua Barrier membrane barrier or a similar product equivalent in function, quality, etc. to the
approval of the architect. Application shall be strictly in accordance with the manufacturer’s
instructions. Compatibility with the floor vinyl adhesive to be confirmed prior to application.
If the required moisture content values are obtained the moisture barrier membrane will
be deducted from the contract as a variation.
B. Adhesives: comply with AS 1884, and manufacturer's instructions.
C. Install material in accordance with AS 1884, including conditioning of both the materials and the
sub-floor.
1. Weld joints of vinyl sheet.
D. Skirting, to manufacturer's instructions.
E. Form junctions of different materials (e.g. tiles to carpet) so that they occur under the centre line
of doors.
F. Movement joints: Install movement joint cover strips over floor slab movement joints. Refer to
structural drawings for locations and extent.
304 Cleaning
Remove excess adhesive and blemishes from the completed surfaces of flooring and skirtings.
305 Protection
Apply suitable hardboard or plywood to completed floors and maintain in position until final cleaning prior
to Practical Completion.
Remove and replace work which cannot be successfully repaired or cleaned.
306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 09650 RESILIENT FLOORING
SECTION 09685 MODULAR CARPET (TILE)
PART I GENERAL
101 Scope
Supply labour, materials and equipment required for supply, delivery, storage, installation and testing for
the complete Modular Carpet installation.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1385 2007 Textile floor coverings - Metric units and commercial tolerances for
measurement.
AS/NZS 2270 2006 Plywood and blockboard for interior use. Plus 1 Amdt, 2007.
AS/NZS 2455 Textile floor covering - Installation practice
2455.1 2007 General. Plus 1 Amdt, 2009.
This standard provides full instructions of pre-installation requirements and
installation methods.
2455.2 2007 Carpet tiles.
Maintain a copy of AS/NZS 2455.1 2007 General, at the project site until completion.
105 Submissions
Submit the following data and obtain approval from the architect before ordering materials:
A. List of recent projects with contact names and telephone numbers.
B. Full size sample module of each carpet type.
C. Confirmation of acceptance and compliance with the requirements of the builder in relation to the
time schedule for supply and laying.
D. Schedule of laying rates per square metre.
These rates include supply and installation of adhesive (if required) and accessories, cutting
(where required) and allowances for profit, overheads and administration costs.
E. Properties: provide test certificates from recognised authorities with the tender to confirm that the
modular carpet complies with the properties set down in clause 204.
F. Certification by the manufacturer that the materials comply with this specification.
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 09685 MODULAR CARPET (TILE)
108 Modular Carpet Installation Contractor's Warranty
Provide a written warranty stating that materials supplied and installed under this contract will remain in
good condition, secure against faulty workmanship and/or defective materials for a period of 7 years
from the date of Practical Completion.
PART II MATERIALS
202 Accessories
Plain clear anodised aluminium (silver)
203 Carpet
Refer Interior Finishes Schedule
Tolerances: AS 1385
Adhesive: Interface TacTiles adhesive connector squares.
204 Properties
208 Identification
Mark modular carpet tiles on the back to identify the manufacturer and the type of modular carpet.
301 Examination
Visit the site and inspect conditions comparing conditions to drawings before delivery of materials to the
site. Notify the architect of discrepancy or unsuitability of the substrate.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Start of work means total acceptance of conditions.
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 09685 MODULAR CARPET (TILE)
302 Preparation
A. Comply with referenced standards and manufacturer's recommendations regarding
environmental and other on-site conditions.
B. Repair by approved means imperfections of the floor surface which might impair the finished
carpeted surfaces.
C. Broom clean or vacuum clean surfaces upon which carpet is to be laid.
D. On completion of cleaning, obtain architect's approval of surface and follow such standard as he
may determine for preparation throughout the project.
308 Partitions
Partitions will be erected prior to the laying of the modular carpet.
310 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 09685 MODULAR CARPET (TILE)
SECTION 09720 WALLCOVERING (PAPER, FABRIC ETC)
PART I GENERAL100
101 Scope
Supply labour and materials, services and equipment necessary for the preparation, application and
finishing of wall covering as indicated on drawings, schedules and as specified herein, to internal
surfaces of building.
Refer to Schedule of Finishes.
104 References
In the absence of Australian Standards, comply with applicable written recommendations of the
manufacturer.
105 Submissions
Submit the following materials:
Product literature on proposed systems.
Samples of approved materials which are to be identified with the manufacturer's colour code batch
number and colour name or match to scheduled colour code and name.
Samples are not to be less than 2 metres long and are to be of the same colour, pattern and type as
scheduled.
107 Warranty
Provide a written warranty stating that preparation of surfaces, materials and material application
installed under this contract will show no deterioration and remain in good condition for a period of
years from the date of completion.
PART II MATERIALS200
201 Materials
Provide all materials necessary for preparation of surfaces and for application of wall coverings.
A. WALL COVERING:
1. Manufacturer: Ecoustic
a. Type: Velour Panel
b. Size: 15mm thick
c. Pattern: N/A
d. Colour: Refer Interior Finishes Schedule
B. ADHESIVES:
1. Follow wall covering manufacturers recommendation for adhesion to plasterboard/ glass
face cement render surfaces.
C. TRIMS:
1. Manufacturer: Refer to Interior Finishes Schedule
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 09720 WALLCOVERING (PAPER, FABRIC ETC)
PART III EXECUTION300
301 Examination
Inspect all surfaces and determine that they are in proper condition to receive the work to be performed
under this section.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
The starting of work under this section means acceptance of such surfaces as being satisfactory.
Correct defects in work resulting from accepting poor surfaces at no cost to the Proprietor.
302 Preparation
Prepare all surfaces as required so that they are in a proper condition to receive the work.
Comply with manufacturer's instructions. Remove dust, dirt, grease and other extraneous matter
affecting the finished work.
Remove lighting fixtures, switches, power outlets and similar items in place prior to installation and
reposition upon completion of each space.
303 Protection
Provide suitable protection in all areas where wall covering is being done to protect adjacent surfaces
from damage during work.
304 Application
Execute all work of this section in strict compliance with the manufacturer's recommendations.
305 Cleaning
At completion of work in each area, thoroughly clean the area.
Replace wall fittings and fixtures previously removed.
307 Completion
Complete all contracted work in accordance with contract documents and written variation orders issued
by the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 09720 WALLCOVERING (PAPER, FABRIC ETC)
SECTION 09910 PAINTING
PART I GENERAL100
101 Scope
Supply labour and materials, services and equipment necessary for the preparation, application and
finishing of painting and staining as indicated on drawings, schedules and as specified herein, to internal
and external surfaces of building, as follows:
Refer Schedule of Finishes.
Consult with the architect with regard to requirements of other trade sections of the specification which
require painting, and include as part of the work of this trade section the appropriate preparation,
painting, and finish required to complete the installation.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 2311 2009 Guide to the painting of buildings.
(NB: maintain this document at the project site by the contractor as a
controlling general reference).
AS/NZS 2312 . Guide to the protection of structural steel against atmospheric corrosion by
the use of protective coatings. There are 2 parts, 2014.
105 Submissions
Submit the following materials:
A. Product literature on proposed painting systems.
B. Colour samples for approved painting materials. Identify samples with:
1. Manufacturer's colour code and colour name (if any).
2. Match to Schedule colour code and name.
C. Samples are not to be less than 100 x 100mm, and are to be of the same gloss level as the
scheduled colour.
D. Copies of pre-installation conference minutes.
Providence Christian College Primary School Stage 1 Page 1 of 6 SECTION 09910 PAINTING
108 Warranty
Provide a written warranty stating that preparation of surfaces, materials and material application
installed under this contract will show no deterioration and remain in good condition for a period of 7
years from date of Practical Completion.
PART II MATERIALS200
Before ordering materials obtain and provide to the architect written evidence that items to be installed
comply with Australian Standards and are approved by statutory authorities having jurisdiction.
If non-approved materials or components are installed, replacement will be at contractor’s expense.
201 Materials
All internal paints are to be low VOC or environmental paints.
General: where manufacturer makes more than one grade of any material specified, use the highest
grade of each type, whether or not the material is mentioned by trade name in these specifications.
Paints and finishes used for the project may be manufactured by the following manufacturers:
Dulux.
No other products will be approved by architect.
Provide materials necessary for preparation of surfaces, and for application of paint finishes.
202 Schedules
Schedules of Finishes is included in this specification.
Providence Christian College Primary School Stage 1 Page 2 of 6 SECTION 09910 PAINTING
203 Paint Types
The architect will prepare a final Schedule of Colours in sufficient time before commencement of work.
INTERIOR TIMBER as per Dulux Specification: AUSD2295 DULUX Aquanamel Semi Gloss
Proprietary item (primer): Dulux Professional Enviro2 ASU
Proprietary item (finishing coats): DULUX Aquanamel Semi Gloss
Location: Interior painted woodwork throughout the Works unless otherwise specified or scheduled
INTERIOR AND EXTERIOR DOORS as per Dulux Specification: AUSD2295 DULUX Aquanamel Semi
Gloss
Proprietary item (primer): Dulux Professional Enviro2 ASU
Proprietary item (finishing coats): DULUX Aquanamel Semi Gloss
Location: Interior and exterior painted timber doors throughout the Works unless otherwise specified or
scheduled
INTERIOR TIMBER as per Dulux Specification: AUSW4749 INTERGRAIN UltraClear Interior Satin
Proprietary item (finishing coats): INTERGRAIN ULTRACLEAR SATIN
Location: Timber skirtings, architraves and the like mouldings nominated for clear finishing.
MEDIUM DENSITY FIBREBOARD as per Dulux Specification: AUSD2872 DULUX Aquanamel Semi
Gloss
Proprietary item (primer): Dulux Professional Enviro2 ASU
Proprietary item (finishing coats): DULUX Aquanamel Semi Gloss
Location: Skirtings, sills, architraves and the like mouldings manufactured from MDF.
PRETREATMENT OF GALVANISED STEEL & ZINCALUME SURFACES: Solvent clean and apply
waterborne pre-treatment for galvanised iron using an abrasive nylon pad, allow to react, rinse off, allow
to dry then apply one coat of specified galvanised iron primer.
Proprietary item: (pre-treatment): DULUX PREP-GALV
EXTERIOR STEELWORK – HOT DIP GALVANISED STEEL (if nominated for painting), as per Dulux
Specification: AUSI3393
Proprietary item (spot primer, applied as full prime coat): DULUX Durebild® STE - PC237
Proprietary item (intermediate coat): DULUX Durebild® STE MIO - PC565
Proprietary item (top coat): DULUX Weathermax® HBR - PC405
Location: All non-galvanised non-visibly exposed structural steelwork not otherwise specified, including
but not limited to:
• Hot dip galvanised exterior structural steelwork and hot dip galvanised metalwork, if nominated
for painting.
Providence Christian College Primary School Stage 1 Page 3 of 6 SECTION 09910 PAINTING
Intumescent paint fire protective coating, as per specification 05100 Structural Steel
Proprietary item (top coat): DULUX Weatherrmax® HBR - PC405; 2 coats at 50 microns per coat
Location: All structural steel nominated for panting, required to be fire protected.
FIBRE CEMENT (VERSILUX & VILLABOARD) - LOW SHEEN EXTERIOR ACRYLIC as per Dulux
Specification: AUSD3458
Proprietary item (sealer-undercoat): DULUX PROFESSIONAL TOTAL PREP.
Proprietary item (finishing coats): DULUX PROFESSIONAL EXTERIOR LOW SHEEN ACRYLIC.
Location: Exterior fibre cement soffits and eaves.
FIBRE CEMENT (VILLABOARD) - LOW SHEEN ACRYLIC as per Dulux Specification: AUSD2288
Proprietary item (sealer-undercoat): Dulux Professional EnvirO2 ASU
Proprietary item (finishing coats): Dulux Professional EnvirO2 Interior Low Sheen
Location: General areas, interior painted fibre cement sheet as indicated on the drawings and
schedules.
FIBRE CEMENT (VILLABOARD) - LOW SHEEN ACRYLIC as per Dulux Specification: AUSD4177
Proprietary item (sealer-undercoat): Dulux Professional EnvirO2 ASU
Proprietary item (finishing coats): Dulux Wash & Wear 101 Advanced Low Sheen
Location: Classroom walls, interior painted fibre cement sheet as indicated on the drawings and
schedules.
FIBRE CEMENT (VILLABOARD) – SEMI GLOSS ACRYLIC as per Dulux Specification: AUSD3711
Proprietary item (sealer-undercoat): Dulux Professional EnvirO2 ASU
Proprietary item (finishing coats): Dulux Professional EnvirO2 Interior Semi Gloss
Location: Food & Textiles, Materials & Technology area walls, interior painted fibre cement sheet as
indicated on the drawings and schedules.
EXTERIOR EXOTECH FIBRE CEMENT CLADDING SYSTEM WITH SEALED EXPRESSED JOINTS
– MEMBRANE FINISH as per Dulux Specification : AUSI1810
Proprietary item (sealer-undercoat): DULUX ACRA-PRIME 501/1.
Providence Christian College Primary School Stage 1 Page 4 of 6 SECTION 09910 PAINTING
Proprietary item (finishing coats): DULUX ACRA-SHIELD 955
INTERNAL MASONRY SURFACES - LOW SHEEN ACRYLIC as per Dulux Specification: AUSD2300
Proprietary item (sealer-undercoat): Dulux Professional Enviro2 ASU
Proprietary item (finishing coats): Dulux Professional EnvirO2 Interior Low Sheen
Location: Painted face of masonry walls nominated on the ROOM DATA SHEETS.
301 Examination
Inspect surfaces and determine that they are in proper condition to receive the work to be performed
under this trade section. Refer 302 A, below.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
The starting of work under this trade section will be taken to mean acceptance of such surfaces as being
satisfactory and defects in work resulting from accepting poor surfaces are to be corrected at no cost to
the proprietor.
Refer AS/NZS 2311 Appendix C.
302 Preparation
A. General: prepared to a standard not less than that described under AS/NZS 2311, Section 3:
Preparation of Un-Painted Surfaces inclusive, and other clauses of Australian Standards
referenced therein.
This Standard is incorporated by reference as part of this specification and applies to the work
below to the same extent as if written herein.
B. Broom clean floor surfaces before painting. Remove dust, dirt, plaster, grease and other
extraneous matter affecting the finish work.
C. Putty-stop or plug nail holes and cracks on both exterior and interior work, as required. Natural or
stained wood finishes are to have putty coloured to match. Putty wood after prime coat or sealer
coat has been applied.
Providence Christian College Primary School Stage 1 Page 5 of 6 SECTION 09910 PAINTING
D. Clean bare metal surfaces of mill scale, rust, grease, oil, dirt, or other foreign matter, then
properly washed with spirit or other approved cleaning agents. After cleaning, etch, pickle, prime,
or otherwise prepare, as recommended by the paint manufacturer.
E. Remove blisters or other imperfections in previous coats caused by foreign substances or paint
skins from painted surfaces before the subsequent coat is applied.
F. Rub down wood and metal surfaces before finishing and between coats with No. 00 and finer
sandpaper or steel wool, leaving a perfectly clean surface. Sand smooth-finished surfaces before
finishing and between coats as required to smooth out rough areas and to assure a smooth, even
finish. Surfaces to receive paint are to be smooth and free of sandpaper scratches, mill-marks,
and other imperfections.
G. Remove hardware, accessories, plates, lighting fixtures and similar items in place prior to
painting and re-position upon completion of each space, or protect as otherwise directed by the
architect.
H. Thoroughly stir materials in containers before application, unless otherwise directed by the
manufacturer of the paint used, to ensure uniformity of colour and mass. Strain out paint skins or
other materials which would cause lumps or roughness. Thin only as recommended by the
manufacturer.
303 Protection
Furnish and lay suitable drop cloths in areas where painting is being done to protect floors and other
surfaces from damage during the work.
304 Application
A. General: execute work of this trade section in strict compliance with paint manufacturer's
recommendations, and with the provisions of AS/NZS 2311, Section 6: Paint Application,
inclusive. This standard is incorporated by reference as part of this specification and applies to
the work below to the same extent as if written herein. In the event of conflict between
manufacturer's recommendations and the provisions of AS/NZS 2311, manufacturer's
recommendations govern.
B. Maintenance or repainting
Execute work of this trade section in strict compliance with paint manufacturer's
recommendations, and with the provisions of AS/NZS 2311, Section 7: Maintenance of Painted
Surfaces on inclusive and Section 8: Maintenance Painting Systems. This standard is
incorporated by reference as part of this specification and applies to the work below to the same
extent as if written herein. In the event of conflict between manufacturer's recommendations and
the provisions of AS/NZS 2311, manufacturer's recommendations govern.
305 Cleaning
At completion of work in each area, remove paint spots, oil and stain from adjacent surfaces, including
finish hardware.
Replace hardware previously removed.
306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
307 Schedules
Refer to Finishes Schedule for locations.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 6 of 6 SECTION 09910 PAINTING
SECTION 10150 TOILET COMPARTMENTS
PART I GENERAL100
101 Scope
Design, supply and install complete compartments and/or enclosures including but not limited to:
Toilet partitions, doors, panels etc.
Urinal partitions constructed of metal, particleboard, laminated surfaces, stone etc.
104 References
AS 1428 Design for access and mobility. There are 5 parts. 1992 – 2010.
Comply with current written instructions of the manufacturer of the products specified.
105 Submissions
Provide to the architect before ordering components:
Manufacturer’s printed data on the specified products and installation instructions.
107 Warranty
Provide to the architect a written warranty stating that all components of the complete installation will
remain intact and in a satisfactory condition for 5 years from the date of Practical Completion.
PART II MATERIALS200
Before ordering materials obtain and provide to the architect written evidence that items to be installed
comply with Australian Standards and are approved by statutory authorities having jurisdiction.
If non-approved materials or components are installed, replacement will be at contractor’s expense.
202 Materials
A. Toilet Partitions
Fixed panels: 13mm compact laminate.
Front panels: 13mm compact laminate
Doors: 13mm compact laminate
Supports at floor: 304 stainless steel pinned directly to floor (Regent System).
Anodised Aluminium Proprietary Liberty floor bracket (Kindy System).
Supports at wall: Extruded anodised aluminium U section.
Headrail: Extruded anodised aluminium round headrail (Regent System).
Indicator bolts, hinges turn snibs: Aqualoo concealed series.
Coat hangers: Coat hook with bumper.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 10150 TOILET COMPARTMENTS
B. Tolerances: design frames to accommodate building tolerances, and when completed, within the
following tolerances:
1. Deviation from plumb, level or dimensioned angle within 3mm per 3.5m of length of
member, or 6mm in total run in line.
2. Deviation from theoretical position on plan or elevation, including deviation from plumb,
level or dimensioned angle not to exceed 9mm total at location.
3. Change in deviation not to exceed 3mm for 3.5m run in direction.
301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure
conditions are satisfactory for installation. Arrange for rectification required.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Start of work means total acceptance of relevant conditions.
302 Preparation
A. Field measurements: do not delay job progress. Allow for adjustments and fitting of the work in
the field where taking of measurements might cause delay.
B. Coordination with work of others: furnish to each relevant trade foreman anchorages and setting
drawings, diagrams, templates and instructions for installation of items having integral anchors
which are to be embedded in concrete or masonry construction. Coordinate delivery of such
items to the project site.
304 Installation
A. Anchorage: except for anchorages furnished herein but placed by other trades, set and secure
necessary anchorages, including concrete and masonry inserts, bolts, wood screws and other
connectors as needed. Perform cutting, drilling and fitting as needed, locating anchorages and
holes to ensure proper positioning of completed work.
B. Fit: during installation and assembly, form tight joints with exposed connections accurately fitted,
and reveals uniform. Finish work accurately, plumb, level, square and true in reference to
adjacent construction.
C. Comply fully with manufacturer’s current written instructions.
306 Protection
Cover work: immediately following installation, wrap or cover the installations to avoid wear and tear of
finish during subsequent construction.
307 Cleaning
Clean materials installed to the satisfaction of the architect.
Remove temporary protective coatings.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 10150 TOILET COMPARTMENTS
SECTION 10240 GRILLES AND SCREENS
PART I GENERAL
101 Scope
Design, fabricate, supply and install grilles and screens including but not limited to:
Wall mounted grilles for ventilation and other purposes
External grilles.
Internal grilles.
Ceiling grilles.
Freestanding screens.
Hinged screens.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1428 Design for access and mobility. There are 5 parts, 1992 – 2010.
AS/NZS 1554 Structural steel welding. There are 7 parts, 2003 – 2014.
AS 1627 Metal finishing - Preparation and pre-treatment of surfaces.
1627.6 2003 Chemical conversion treatment of metals.
There are 6 other parts, 1997 – 2005.
AS 4100 1998 Steel structures Plus 1 Supplement, 1999, 1 Amdt 2012.
AS/NZS 4680 2006 Hot-dip galvanized (zinc) coatings on fabricated ferrous articles.
AS 5039 2008 Security screen doors and security window grilles.
AS 5040 2003 Installation of security screen doors and window grilles. Plus 1 Amdt, 2007.
Comply with requirements of statutory and local authorities.
106 Samples
A. Sample welds: if requested, provide samples of weld types, including samples of railings joined
at right angles and at typical acute angles, welded and ground smooth, for approval. If not
acceptable, provide additional samples until approved. When approved, samples are to establish
quality of similar work of this trade section.
B. Check on delivery: request architect to check materials on delivery to site for quality, and he will
reject materials not meeting the requirements of this specification or equal to approved samples.
Rejected materials are to be returned to the fabricator at the fabricator's expense.
C. Finish: provide samples of specified finishes when requested.
Providence Christian College Primary School Stage 1 Page 1 of 3 SECTION 10240 GRILLES AND SCREENS
PART II MATERIALS
201 Manufacturers
Invisiguard
202 Materials
205 Miscellaneous
Fasteners: provide required bolts, screws, inserts, fasteners, templates and other accessories required
for a complete installation.
Coordinate with other trades as to the proper fastening systems suitable for the substrates to which the
item is to be secured. Refer to architect if in doubt.
Fasten galvanised items with galvanised fasteners.
301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure
conditions are satisfactory for installation. Arrange for rectification required.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Start of work means total acceptance of relevant conditions.
302 Preparation
A. Field measurements: do not delay job progress. Allow for adjustments and fitting of the work in
the field where taking of measurements might cause delay.
B. Coordination with work of others: furnish to each relevant trade foreman anchorages and setting
drawings, diagrams, templates and instructions for installation of items having integral anchors
Providence Christian College Primary School Stage 1 Page 2 of 3 SECTION 10240 GRILLES AND SCREENS
which are to be embedded in concrete or masonry construction. Coordinate delivery of such
items to the project site.
304 Installation
A. Anchorage: except for anchorages furnished herein but placed by other trades, set and secure
necessary anchorages, including concrete and masonry inserts, bolts, wood screws and other
connectors as needed. Perform cutting, drilling and fitting as needed, locating anchorages and
holes to ensure proper positioning of completed work.
B. Fit: during installation and assembly, form tight joints with exposed connections accurately fitted,
and reveals uniform. Finish work accurately, plumb, level, square and true in reference to
adjacent construction. Make tolerances conform to Australian Standards.
C. Finish: do not cut or abrade shop finishes which cannot be completely restored in the field.
The use of gas-cutting torch in the field for correcting fabrication errors will not be permitted
under conditions. Fabrications may be cut shorter with power hacksaws on site.
Isolate dissimilar metals likely to be subject to moisture with inert materials, not visible on
completion of installation.
306 Protection
Cover work: immediately following installation, wrap or cover architectural metalwork to avoid wear and
tear of finish during subsequent construction.
307 Cleaning
Clean materials installed to the satisfaction of the architect.
Remove temporary protective coatings.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 3 of 3 SECTION 10240 GRILLES AND SCREENS
SECTION 10400 IDENTIFICATION SIGNS
PART I GENERAL
101 Scope
Design, supply and install required items including but not limited to:
Exterior/interior signs
Plaques
Door signs
Signs for the disabled.
104 References
Comply with the applicable portions of the following Australian Standards:
AS 1319 1994 Safety signs for the occupational environment.
HB 123 1999 Guidelines for the selection, location and installation of visual warning
devices in buildings.
106 Submissions
Submit to the architect for approval, the following before ordering materials:
A. Samples of specified materials, conforming to type and finish required.
B. Fully detailed drawings showing overall dimensions and component sizes with proposed methods
of fixing and/or securing position.
C. Check data on sign for data accuracy - spelling, phone number, etc. before manufacture.
D. Copies of minutes of pre-installation conference.
108 Warranty
Provide to the proprietor a warranty co-signed by the manufacturer and installer stating that items in this
specification will remain in full operational condition for a period of years from the date of Practical
Completion.
109 Maintenance
Provide a written undertaking to the proprietor that parts of the installation will be available for additional
supply from time to time to suit the proprietor's needs for a period of 10 years from the date of Practical
Completion.
PART II MATERIALS
203 Finishes
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 10400 IDENTIFICATION SIGNS
204 Signs for The Disabled
205 Fabrication
Fabricate components in accordance with manufacturer's instructions and approved drawings.
Form junctions so that fixings are concealed.
Cut edges, drill holes free from burrs and indentations. Fit joints to a fine hairline.
Pre-assemble where possible or practical and mark each item for intended location before delivery.
301 Examination
Visit site and inspect conditions, comparing conditions to drawings before delivery of materials to site.
Rectify discrepancy or unsuitability of substrate.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Start of work means total acceptance of conditions.
Space enclosure: do not install materials until space is enclosed and weatherproof, and until wet-work in
space is completed and nominally dry.
302 Preparation
Prepare areas and surfaces before installation, so that best conditions exist.
Where necessary, ensure that lighting cable is in place and concealed ready for connection to light
fittings within the illuminated items.
303 Installation
Comply with manufacturer's written instructions. Provide appropriate anchoring devices, concrete pads
for external signs.
Take care of and protect adjacent surfaces and materials. Provide protective cover to adjacent finishes
where necessary.
304 Protection
Protect finished work.
Replace or make good work found damaged at time of Practical Completion.
305 Cleaning
A. Adjust and clean: clean exposed surfaces including trim, edge moldings, and comply with
manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and
replace work which cannot be successfully cleaned and repaired to permanently eliminate
evidence of damage.
B. Remove spatterings and droppings from work. Remove daily surplus materials and rubbish from
the work area.
C. Leave floors broom clean at completion.
306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 10400 IDENTIFICATION SIGNS
SECTION 10520 FIRE EXTINGUISHERS
PART I GENERAL100
101 Scope
Supply and install extinguishers where indicated in accordance with the statutory authority having
jurisdiction.
104 References
Comply with applicable portion of the following Australian Standards:
AS 1603 Automatic fire detection and alarm systems.
There are 12 parts 1996 – 2011 and 4 Amdts, 1998 – 2001.
AS 1670 Fire detection, warning, control and intercom systems - System design,
installation and commissioning. There are 5 parts, 1997 – 2015..
AS/NZS 1841 2007 Portable fire extinguishers. There are 8 parts, one for each type.
AS 2444 2001 Portable fire extinguishers and fire blankets – Selection and location.
AS/NZS 4353 1995 Portable fire extinguishers - Aerosol type.
Comply with requirements of statutory authority having jurisdiction.
105 Submissions
Copies of minutes of pre-installation conference.
PART II MATERIALS200
201 Manufacturers
Manufacturers of materials approved in writing by the statutory authority may supply equipment.
202 Materials
Allow a Provisional Sum (PS) of $7,500.00 plus GST for the supply of fire extinguishers from a
nominated supplier.
301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure
conditions are satisfactory for installation. Arrange for rectification if required.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Start of work means total acceptance of relevant conditions.
303 Installation
Anchorage: except for anchorages furnished herein but placed by other trades, set and secure
necessary anchorages, including concrete and masonry inserts, bolts, wood screws and other
connectors as needed. Perform cutting, drilling and fitting as needed, locating anchorages and holes to
ensure proper positioning of completed work.
304 Cleaning
Clean materials installed to the satisfaction of the architect.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 10520 FIRE EXTINGUISHERS
Remove temporary protective coatings.
305 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by
the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 10520 FIRE EXTINGUISHERS
SECTION 12300 MANUFACTURED CASEWORK - SHOP BUILT
PART I GENERAL
101 Scope
The work of this trade section covers the supply and installation of manufactured casework items.
It includes but is not limited to:
Kitchen cabinets and cupboards
Shelving
Laboratory cabinets and cupboards
Work benches
Storage cupboards
104 References
Comply with applicable portions of the Australian Standards:
AS/NZS 1859 Reconstituted wood-based panels – Specifications.
1859.1 2004 Particleboard. Plus 2 Amdts, 2006 - 2011.
There are 3 other parts, 2004 – 2005, 3 Amdts, 2006 - 2009.
AS 2754.2 1991 Adhesives for timber and timber products - Polymer emulsion adhesives.
AS/NZS 2924 High pressure decorative laminates – Sheets made from thermosetting
resins.
There are 2 parts, 1998.
AS/NZS 4386 Domestic kitchen assemblies.
4386.1 1996 Kitchen units.
4386.2 1996 Installation.
AS 4786.2 2005 Timber flooring - Sanding and finishing.
105 Submissions
Submit the following prior to fabrication:
Product literature on proposed hardware items including components.
Technical data on melamine laminates proposed for use.
Technical data and samples of substrate materials.
Thickness of materials at typical locations.
PART II MATERIALS
201 Materials
Use low formaldehyde emission particleboards and MDF boards - E0 type. Use low VOC emission
adhesives.
A. Carcass units (Ends and vertical divisions):
1. (DRY AREA) Material : Pre-finished particle board
Finish : White melamine finish internally all exposed external
surfaces to be finished with 0.8mm thick plastic
Providence Christian College Primary School Stage 1 Page 1 of 5 SECTION 12300 MANUFACTURED CASEWORK - SHOP
BUILT
laminate.
Thickness : 18mm
2. (WET AREA) Material : HMR Pre-finished particle board
Finish : White melamine finish internally all exposed external
surfaces to be finished with 0.8mm thick plastic
laminate.
Thickness: 18mm
B. Floors of carcass
1. (DRY AREA) Material : Pre-finished Particleboard.
Finish : White melamine finish internally all exposed external
surfaces to be finished with 0.8mm thick plastic
laminate.
Thickness : 18mm
2. (WET AREA) Material : HMR Pre-finished particle board
Finish : White melamine finish internally all exposed external
surfaces to be finished with 0.8mm thick plastic
laminate.
Thickness : 18mm
D. Doors of cabinets :
1. (DRY AREA) Material : Medium Density Fibreboard
Finish : Pre-finished coloured melamine board.
Thickness : 18mm
2. (WET AREA) Material : HMR Medium Density Fibreboard
Finish : Pre-finished coloured melamine board.
Thickness : 18mm
Providence Christian College Primary School Stage 1 Page 2 of 5 SECTION 12300 MANUFACTURED CASEWORK - SHOP
BUILT
Thickness : 12mm
K. Whiteboard: Vitreous Porcelain Enamel on 0.43mm Thick Mild Steel Sheet. No alternative
finish will be accepted. Test sampling may be performed on whiteboards
installed in the works of this contract.
Facings shall be fixed to gypsumboard core. Provide 0.43mm zincannealed
steel sheet as backing. Provide extruded white power coated aluminium chalk
rail at bottom and white powder coated aluminium edging to remaining edges,
complete with concealed fixing strip.
L. Pin-up boards: 3mm thick Hardboard glued to nom 12mm thick pinnable fabric composite.
22 x 22 x 1.6 aluminium channel to all edges (mitre corners). Refer details.
Selected fabric; refer Finishes Schedule
Frame Finish: Clear Natural Anodised.
203 Hardware
A. Door handles : 200mm long / 20mm thick / 35mm deep “D” handles by Hafele, anodised
aluminium (silver coloured) as scheduled in Finishes Schedule.
B. Drawer handles : 200mm long / 20mm thick / 35mm deep “D” handles by Hafele, anodised
aluminium (silver coloured) as scheduled in Finishes Schedule.
C. Drawer runners : Heavy duty Blum soft close nylon roller powdercoated steel runners, full
extension
D. Adjustable shelf brackets : Ferrule and socket brass shelf supports @ 75mm ctrs.
E. Pin-up fixing to wall: M4.5 x 58mm long flat head masonry anchors @ M2x 600 Centres.
F. Hinges: Slide on type Hafele, Blum or Hettich automatic soft close hinges with steel and nickel
plate finish, heavy duty.115° for doors with restricted opening (against walls etc.) and 180° for all
other doors.
Minimum number of hinges per door: 2, for up to 900mm high door
3, for up to 1500mm high door
Providence Christian College Primary School Stage 1 Page 3 of 5 SECTION 12300 MANUFACTURED CASEWORK - SHOP
BUILT
4, for up to 2000mm high door
Refer manufacturer’s instructions for details and installation requirements.
G. Catches: Magnetic type, unless hinges are of the pressure sprung closer type where catch is not
required.
H. Locks: Lockwood 600 series.
204 Fabrication
Construct by screwing and gluing or other approved method. A dry stapled assembly will not be
approved.
Fabricate bench tops as indicated in a manner recommended by the material's manufacturer. Fabricate
units without joints unless counter length exceeds maximum available length of materials.
Seal joints between counter and splash back with matching colour silicone. Wherever possible, pre-cut
openings to receive hardware, appliances, plumbing fixtures, electrical work and similar items.
Locate openings accurately using templates or roughing-in diagrams for proper size and shape. Smooth
edges of cut-outs and, where located in bench tops and similar exposures, seal edges of cut-outs with a
water resistant coating.
Back prime all concealed solid timber surfaces prior to installation.
Install fasteners, hinges etc. in accordance with manufacturer’s instructions. When in doubt about
suitability, consult with manufacturer of the items specified or selected.
301 Examination
Visit the site and inspect conditions. Check dimensions and compare all aspects with the drawings and
specification. Resolve differences before ordering materials or starting work.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Start of work means total acceptance of all conditions.
303 Installation
Use concealed shims as required to install the work plumb, level, straight and distortion free within the
following tolerances:
- 1mm in 800mm for plumb and level (including bench tops),
- 0.5mm maximum offsets in flush adjoining surfaces,
- 2mm maximum offsets in revealed adjoining surfaces.
Scribe and cut to fit adjoining work; refinish cut surfaces or repair damaged finishes at cuts.
Secure joinery with anchors of blocking built-in or directly attached to substrates. Secure to grounds,
stripping and blocking with countersunk, concealed fasteners and blind nailing as required to complete
the installation.
Except where pre-finished matching fastener heads are required, use fine finishing nails, countersunk
and filled flush. Use a matching filler where a transparent finish is required.
Install casework without distortion so that doors will fit openings properly and be accurately aligned.
304 Hardware
Install all door and joinery hardware as scheduled, listed and required in full compliance with the
manufacturer's recommendations.
Adjust as needed to centre doors in openings.
Providence Christian College Primary School Stage 1 Page 4 of 5 SECTION 12300 MANUFACTURED CASEWORK - SHOP
BUILT
C. Lubricate and clean hardware making any final adjustments needed for proper operation.
D. Remove all handling marks from visible joinery surfaces.
E. Protection: do everything needed to ensure that all work is without damage or deterioration at
completion.
306 Completion
Complete all contracted work in accordance with contract documents and written variation orders issued
by the architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 5 of 5 SECTION 12300 MANUFACTURED CASEWORK - SHOP
BUILT
SECTION 12480 FLOOR MATS AND FRAMES
PART I GENERAL
101 Scope
The work of this trade section covers the supply and installation of floor mats and/or recessed mats and
frames.
104 References
(Not used).
105 Submissions
Provide samples and data sheets of all materials.
Obtain architect's approval for each item before ordering.
107 Warranty
Provide a warranty covering all aspects of the installation performed by this trade, against defective
materials and workmanship for a period of 7 years from the date of completion.
Include a statement that the whole of the work has been carried out in accordance with the relevant
Australian Standards and the instructions of the manufacturers of components in effect at the time of
installation.
PART II MATERIALS
201 Materials
Refer Interior Finishes Schedule.
202 Fabrication
Comply with the relevant Standards.
Contractor to check all dimensions on site.
Contractor to provide prototype for architect's approval prior to manufacture.
Contractor to present sample to architect for final selection.
301 Examination
Examine the site conditions applicable to each installation. Arrange for correction if required.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
Start of work means total acceptance of conditions.
302 Installation
Refer to drawings for location of floor mats.
Providence Christian College Primary School Stage 1 Page 1 of 2 SECTION 12480 FLOOR MATS AND FRAMES
Frame (if required by the manufacturer) to be provided with anchors and cast-in place or to be fixed in
the mat recess with masonry anchors.
303 Preparation
Comply with referenced Standards and manufacturer's recommendations. Do not install material until
space is enclosed and weatherproof and until wet work in space is completed and dry.
305 Completion
Complete all contracted work in accordance with contract documents and written variation orders issued
by the architect.
Work will be deemed complete after being inspected and approved by architect.
END OF SECTION
Providence Christian College Primary School Stage 1 Page 2 of 2 SECTION 12480 FLOOR MATS AND FRAMES
Technical Specification
for
Plan E No. 2006701
TENDER
DECEMBER 2020
2. TECHNICAL SPECIFICATION 6
2.1 TREE REMOVAL & PRUNING 6
2.2 BULK EARTHWORKS 6
2.3 SITE WORKS 6
2.4 SOIL CONDITIONER – ‘C-WISE HORTICUTURE’ 8
2.5 IMPORTED SOIL - SCREENED TOPSOIL 9
2.6 SITE SOIL CONDITIONER – TREE WELLS 9
2.7 IMPORTED SAND – TURF GRASS AREAS 10
2.8 WALL TYPE C 11
2.9 UNIT PAVEMENT 13
2.10 STEELWORK 17
2.11 CONCRETE WORK – STRUCTURAL 19
2.12 CONCRETE SEAT WALLS TYPE D 21
2.13 IN-SITU CONCRETE PAVEMENT 22
2.14 IN SITU CONCRETE MOWING KERB 25
2.15 SEALER / ANTI-GRAFFITI COATING 26
2.16 SITE FURNITURE 26
2.17 STEEL HAND RAIL 26
2.18 COMPOSITE DECKING 28
2.19 SYNTHETIC TURF 28
2.20 TREE, SHRUB AND PLANT (GREEN STOCK) SUPPLY AND PLANTING 29
2.21 MULCH – BOUTIQUE 33
2.22 TURF GRASSING AND ESTABLISHMENT 33
2.23 IRRIGATION – DESIGN AND CONSTRUCT 36
2.24 PRACTICAL COMPLETION 40
2.25 CONSOLIDATION 41
2.26 CONSOLIDATION COMPLETION - PRINCIPAL HAND OVER 43
2.27 FINAL COMPLETION 43
2006701 Providence Christian College – Primary School Preliminary Technical Specification (Stage 1)
2
Where any facility, structure or service is damaged, displaced or otherwise interfered with, the Contractor is to
give notice immediately to the Service Authority and the Superintendents Representative and afford all facilities
to assist in early inspection and repair of the service. All costs associated with the necessary repair, and any
other cost incurred through the damaged, displacement or otherwise interference with any service will be borne
by the Contractor.
The Superintendent’s representative reserves the right to have any poles, cables, ducts, etc. re-sited or diverted
where he considers it inadvisable to allow them to remain in their present position. The Principal will pay for
such re-siting or diversion but the Contractor must give every facility to enable them to carry out the alterations.
Negligence by the Contractor in managing and supervising the protection of services shall be sufficient cause
for the Superintendent to direct the Contractor to remove relevant persons from the site or from any activity
connected with the works, in accordance with Clause 26 of the General Conditions of Contract.
The Contractor shall have no claim for any extra payment due to interference with, or delay in, the carrying out
of the Contract caused by any alteration to a facility, structure or services.
2006701 Providence Christian College – Primary School Preliminary Technical Specification (Stage 1)
3
2006701 Providence Christian College – Primary School Preliminary Technical Specification (Stage 1)
4
1.10 INSPECTIONS
1.10.1 General
Complete all inspections as per the inspection schedule in the presence of the Project Landscape
Architect / Superintendent.
1.10.2 Notice
Give three (3) days’ calendar notice to the Superintendent so that inspection may be made of all items noted in
Schedule of Inspections. Following each inspection, await direction prior to proceeding with works.
1.10.3 Inspection Schedule
Undertake all inspection in accordance with the following schedule:
2006701 Providence Christian College – Primary School Preliminary Technical Specification (Stage 1)
5
TURF GRASSING
Following completion of ground preparation works
At installation of turf grassing
At time of each maintenance task including fertilizing
PAVING TREATMENTS
Following initial set-out
Following initial installation of the paving (for each type)
At completion of each section of each paving type
STEEL FABRICATED ITEMS
At completion of fabrication and finishing of all items, fittings
and fixings and prior to assembly and delivery to site
At completion of installation
TIMBER FABRICATED ITEMS
At completion of fabrication and finishing of all items, fittings
and fixings and prior to assembly and delivery to site
At completion of installation
BESPOKE FURNITURE
At completion of fabrication and finishing of all items, fittings
and fixings and prior to assembly and delivery to site
At completion of installation
PROPRIETARY FURNITURE
Following set-out of major furniture items
Following preparation works prior to installation
Following completion of works
PRACTICAL COMPLETION
Pre-Practical Completion Inspection.
Practical Completion Inspection.
Follow-up Inspections (as required).
CONSOLIDATION PERIOD
Monthly Maintenance Inspection - Month 1
Monthly Maintenance Inspection - Month 2
Consolidation Completion Inspection
FINAL COMPLETION
Pre-Final Completion Inspection.
Final Completion Inspection.
2006701 Providence Christian College – Primary School Preliminary Technical Specification (Stage 1)
6
2. TECHNICAL SPECIFICATION
2.1 TREE REMOVAL & PRUNING
2.1.1 General
Allow in the lump sum tender price for tree removal and pruning / remedial works as indicated on the
landscape drawings. All pruning and remedial works are to be carried out to the direction of the arborist report
& Superintendent on site.
Tree removal and pruning shall be undertaken by a qualified Arborist, to the approval of the Superintendent.
Tree removal and pruning shall be undertaken by a minimum Certificate level 3 qualified Arborist, and in
accordance with AS4373-2007. All works shall be undertaken to the highest safety standard in accordance
with all statutory requirements and bylaws.
All removed trees, pruning and debris shall be loaded, hauled and disposed of off-site in an approved tip in
compliance with statutory requirements.
Any damage to the existing security fences, surrounding surfaces and structures caused by tree removal or
pruning will be rectified at the cost of the contractor.
Remove all resultant spoil, including all vegetative material, from site. Where it is necessary to reinstate levels,
backfill with approved clean, weed-free sand.
Where the use of a non-residual herbicide is approved to eradicate grass and/or weeds, it shall be applied
strictly in accordance with the manufacturers written directions.
Spraying shall only be carried out on windless days and the Superintendent shall be informed when this
operation is to be undertaken.
Do not use Glyphosate near any waterways nor use any other herbicides near waterways unless such use is
specifically approved by the Waters and Rivers Commission and the Relevant Local Authority.
The use of a herbicide will only be approved whilst there is active translocation occurring in the grass and/or
weeds. This can be generally be judged by the presence of visible new growth, however approval shall be solely
at the discretion of the Superintendent.
Where the application of herbicide is proposed between the months of April to October the application rate
shall be increased by 30% to allow for the lower rate of plant translocation during these months.
The ratio for application shall be chosen to suit the hardiest weed species present.
Herbicide shall not be applied within six (6) hours of rain, nor shall the treated area be watered within six (6)
hours of application. Re-apply herbicide, if the treated area is affected by rain or watering within six (6) hours
of the initial application.
Following the application of the herbicide, the treated weeds shall be left undisturbed for a minimum of
fourteen (14) days.
Following the fourteen (14) day "ingestion" period, the treated area shall be cultivated to a depth of 150mm, to
expose all roots, stolons, rhizomes etc, to the atmosphere. The affected area shall be left in this condition for
an additional two (2) days, prior to undertaking any further work.
If, in the opinion of the Superintendent, the use of a herbicide may constitute a threat to any existing habitat or
vegetation, eradicate weeds by manual means only.
2.3.5 Cut and Fill
2.3.5.1 General
Undertake all excavation, cut and fill or fill operations as may be required for the construction of the works
under the contract, including but not limited to excavation and back filling to all retaining walls and excavation
for the importation of prepared soils and the like under the contract. No variation shall be issued for any
earthworks, cut or fill operations, removal of excess material off site or importation of clean fill as may be
required to complete the works under the contract.
2.3.6 Imported Clean Fill
Filling material shall be a clean granular material, sand as defined in AS1289.3.6.1 and shall have the
following properties:
i) Have non plastic fines;
ii) Be clean and free of all silty, organic or any other deleterious inclusions and certified as Die Back
(Phytophthora sp.) free;
iii) Be cohesionless with a minimum permeability of 5m/day when compacted at 95% Modified Maximum
Dry Density in accordance with AS1289.5.2.1; and
iv) Have a particle size distribution in compliance with the limits shown below.
Sieve Size % Passing
4.75mm 100
2.36mm 100
1.18mm 100
600um 84
300um 31
150um 4
75um 1.8
Pan 0
The contractor shall provide results from NATA registered testing authority which demonstrates compliance
with the above criteria prior to undertaking fill operations.
Independent testing certifying compliance shall be provided to the Superintendent within three days of request.
2.3.6.1 Fill Installation
Place and compact filling in uniform layers of thickness. Layers shall extend for the full width of fill area. The
maximum layer thickness generally shall be 150mm compacted. However, greater thicknesses will be
permitted subject to the ability of compaction equipment to achieve specified densities. No layer shall be less
than 100mm thick compacted. Each layer shall be compacted to not less than Eight (8) blows per 300mm with
a Perth sand penetrometer as determined by AS1289.5.2.1-2003.
2.3.6.2 Excess Material
All excess excavated material shall be loaded, hauled and disposed of off site in an approved tip in compliance
with statutory requirements.
2.3.7 Fine Grading
Undertake all minor levelling and grading to achieve final design levels to all areas under the works. Supply all
the machinery and equipment necessary to complete the works in an efficient manner.
Fine grading shall including all excavation or fill as required for the provision of hard landscape works and
prepared soils and mulch to achieve final design levels.
All final grading shall be carried out in accordance with finished contours and levels indicated on drawings, and
to ensure water drains to sumps.
Finish all levels to neatly tie in and match up with existing work in adjoining areas to the satisfaction of the
Superintendent. This shall include all works associated with roads and pavements carried out previously, to
the areas covered by this contract.
Remove from the site all excess excavated material and deleterious material encountered during final grading
and dispose of in the correct manner off site at an approved rubbish tip.
2.4.4 Samples
Prior to delivery of prepared soil, submit a 0.01 m3 sample of the prepared soil to the Superintendent for
approval. Allow for three (3) samples of the mix to be laboratory tested for pH, salt and major trace elements.
A laboratory certificate may be required to accompany the initial sample at the instruction of the
Superintendent. The Superintendent may select a further two (2) samples for analysis during the course of the
Works.
All approvals shall be confirmed in writing. Subsequent conditioner used on the project shall conform to this
sample. In the event that these tests prove unacceptable, the defective conditioner will be removed and
replaced. If further testing is required, the cost of testing shall be borne by the Contractor.
The contractor shall provide results from NATA registered testing authority which demonstrates compliance
with the above criteria prior to undertaking fill operations.
Independent testing certifying compliance shall be provided to the Superintendent within three days of request.
2.7.3 Placement
Place sand to a depth of 100mm over the full extent of areas to be grassed.
Prior to placement, ensure all base material is clean, free draining and free of all builders rubble, rubbish,
deleterious material and contamination. All area contaminated by the builder shall be removed and replace
with clean fill sand to the approval of the Superintendent.
After placement and smudging boarding sand shall finish 10mm below adjacent kerbing and paving.
Finished Walls As-constructed profiles (with tolerances 1 per 20m length of wall
and locations)
2.8.6 Mortar
All cement mortars to be to AS3972, AS3972, and AS3972 Type GP.
Mortar Mix to be 6 part sand: 1 part cement: 1 part lime unless otherwise specified.
For masonry more than three (3) courses below ground and in retaining walls use mortar mixes 3 part sand: 1
part cement: 0.25 part lime.
All sands shall be tested and certified as salt free, either independently or by the sand supplier. The contractor
shall supply a complying copy of the certification to the Superintendent's Representative for approval prior to
ordering materials. The contractor shall ensure all sands used in the works shall be from the same source and
provenance as the tested and certified source.
All cost associated with testing and certification shall be borne by the contractor.
Colour of all mortar to be CCS Marigold to match natural earth block.
2.8.7 Sub-Grade Preparation
2.8.7.1 Moisture Content
Prior to compaction, bring the sub-grade under all walls to within 2% of the optimum moisture content
determined to AS1289.5.1.1 (standard) or AS1289.5.2.1 (modified) as applicable to the material.
2.8.7.2 Compaction
The sub grade under all walls shall be fully compacted with a mechanical vibrator to not less than Eight (8)
blows per 300mm with a Perth sand penetrometer as determined by AS1289.5.2.1 AS1289.5.2.1
AS1289.5.2.1 to a depth of 750mm.
2.8.8 Stone Work Workmanship
All stone works shall comply to AS3700.
Clean stonework progressively as the work proceeds, removing mortar and other droppings as they occur.
Clean face work to remove mortar smears, stains, discoloration, and the like. Stained or damaged surfaces or
edging units shall be replaced not repaired, unless otherwise directed by the Superintendent.
Set out stonework so as to maintain the specified rod and bond with bed joints and vertical joints of uniform
width, and with the minimum muting of units.
Bonding Pattern shall be stretcher bond, unless otherwise shown on the Drawings.
Work with a jointing tool produce face work joints: to a dense, smooth surface to a flush profile, or as detailed.
2.8.9 Waterproofing to Retaining Walls
2.8.9.1 Coating
Location behind all retaining walls to within 100mm of finished ground level or as detailed.
Coating is to be liquid applied single component asphalt latex emulsion which cures by evaporation to form an
elastomeric waterproofing membrane.
Waterproofing agent is to be 'ELASTOSEAL' by CROMMELIN CHEMICALS (WA).
2.8.9.2 Application
Apply the emulsion in two coats at the rate of 1m2 / litre / coat. Allow first coat to cure before application of
the second coat. Apply each coat at right angles to each other in accordance with the manufacturer’s
recommendations.
2.8.10 Wall Backfilling
Compacted structural fill to walls shall achieve a minimum density ratio of 95% of MMDD. Backfilling to be
completed progressively in maximum layers of 500mm once the section of wall has achieved an age of 7 days
since last block laid. Contractor shall take care when backfilling to prevent damage to wall.
Shaped units shall be fitted to match with the paving and to conform to applicable details. Cut or shaped units
shall not be less than one third of the original unit size.
Marks shall not be made on face surfaces. In face work, all units shall be carefully mixed to ensure an even
overall blend of colour, tone, texture and figure.
All prepared units shall be packed for delivery in a manner which will protect them from damage and staining.
Particular care shall be taken during loading, unloading and stacking to prevent damage and defacement.
Under no circumstances shall unloading by tipping and/or dropping be permitted.
Units shall be stacked clear of the ground on pallets or other suitable supporting materials or structures which
will insulate them from rising damp, and the stocks covered by suitable waterproof covers to prevent wetting.
2.9.9.2 Workmanship
All work shall be carried out in the best recognized trade practice by approved firms specializing in the
particular work and employing skilled experienced tradesmen.
Pre-cast paving units shall be carefully unloaded at site and stacked in an approved manner until set in
position.
Provide all accessories and perform all operations necessary for the proper execution of first class paving
including selecting, culling, bedding, setting, sawing, fixings, pointing, grouting, caulking, and the like.
Build in all necessary fixings as required. Provide all other fittings, as detailed. Co-ordinate with other trades
as required.
Inspect all areas to ensure that the surfaces are suitable to receive them.
Undertake all the necessary minor filling and/or minor grinding off of the adjacent surfaces i.e. kerbs, pram
crossings etc. that it deems necessary prior to setting the paving.
2.9.9.3 Samples
Submit representative samples of the paving units for approval prior to proceeding. Upon approval, allow to
construct for further approval, a sample incorporating each type of paving to a minimum of 40m 2. This work
shall be reviewed by the Superintendent, to ensure compliance with the Specification and Drawings.
Once approved, ensure that all materials and workmanship comply with the approved samples. The approved
samples may be incorporated into the finished work if appropriate.
2.9.9.4 Paving
Blocks shall be laid to grades and lines as shown on the drawings.
2.9.9.5 Sub-Grade
2.9.9.5.1 Preparation
Prior to compaction, bring the sub-grade to within 2% of the optimum moisture content determined to
AS1289.5.1.1 or AS1289.5.2.1 as applicable to the material.
2.9.9.5.2 Compaction
The pavement sub grade shall be fully compacted with a mechanical vibrator to not less than Eight (8) blows
per 300mm with a Perth sand penetrometer as determined by AS1289.5.2.1 to a depth of 450mm.
2.9.9.5.3 Finished Sub-Grade Level Tolerances
Maximum deviation from the design level: + 10mm, - 0mm.
Maximum deviation from a 3 m straightedge laid anywhere on each plane surface: 20mm.
2.9.9.5.4 Compaction Equipment:
Use approved rollers, appropriate to the materials and compaction requirements. Use approved plate
compactors on areas inaccessible to rollers. To maintain moisture content, use water spraying equipment
capable of distributing water uniformly in controlled quantities without washing fines from the sub-grade or
base material.
2.9.9.6 Bedding Sand
Bedding sand shall be well graded sand passing a 4.75mm sieve and suited to concrete manufacture. The
bedding sand shall be free of deleterious soluble salts or other contaminants likely to cause efflorescence.
Bricklayers sand and single sized dune sands are not considered to be suitable.
The maximum depth of bedding sand shall be 30mm (+ - 5mm) after compaction of the paving. This shall be
achieved by field trials. The bedding sand is to be spread loose in a uniform layer, screeded loose to a
nominated level just ahead of the laying of the paving units. The Contractor is to ensure that only light
compaction of the bedding sand occurs with a small plate compactor prior to placing of paving units. Only
sufficient area is prepared as will be paved in that day.
Set into expansion joints a backing of 15mm dia. closed cell cream polyethylene strip. Set strip back sufficient
distance so that sealing compound will finish flush with paving.
Seal expansion joints with a polysulphide or polyurethane based sealing compound. Depth of sealing
compound shall not exceed the width of the joint. Colour of sealing compound shall blend with colour of
pavement. Where polysulphide sealing compounds are used, coat surfaces of pavement in contact with
sealing compound with a sealer recommended by the sealing compound manufacturer.
2.9.11 Mortar Haunch
All unrestrained pavement edges and all pavement edges abutting service pits are to have a continuous mortar
haunch to the full extent of all unrestrained edges and service pit edges.
Mortar shall be:
all part sand mortars to AS3972 Type GP, 4 part sand: 1 part cement;
cement to be blended cement with fly ash content approximately 25%;
sand must be clean, washed, medium to fine;
gauge boxes for proportioning of the cement and sand must be used;
a reasonably large powerful mixer capable of thorough mixing must be used; and
contain cement aids "Caltite Water proofer" at the rate of one part water proofer to 5 parts water.
Mortar haunch to be as detailed on the drawing and, as a minimum be 100mm deep below underside of unit
pavement, 200mm wide located central to unrestrained edge of pavement and finishing a minimum of two
thirds up the face of the unsupported edge.
2.9.12 Protection
Protect paving from staining and damage. Use sheeting or other screening as necessary. Do not use
hardwood in contact with units.
Clean off all droppings as they occur. Stained or damaged units shall be replaced, not repaired, unless
otherwise permitted by the Superintendent.
Protect adjoining surfaces during paving work. Finished surfaces in the vicinity of work being carried out shall
be protected from staining and impact and all necessary precautions are to be taken to ensure that protection
is provided and maintained.
Protect all paving as follows:
exclude all foot traffic for 3 days;
exclude all heavier traffic for 7 days;
exclude all vehicles for 21 days minimum; and
provide barriers and planking to accommodate traffic.
2.9.13 Sealer / Anti-Graffiti Coating
Upon completion of construction, supply and apply sealer / anti-graffiti coating to all above ground surfaces.
Sealer / anti-graffiti coating shall be equal or equivalent to Crommelins, to the approval of the Superintendent,
suitable for the substrate and site conditions, as recommended by the manufacturer.
All sealants to meet "non-skid" slip resistance to Pendulum P4 rating or higher as per AS 4586 Slip Resistant
classification of New Pedestrian Surface Materials.
Install strictly in accordance with the manufacturer’s instructions suitable for the substrate.
2.9.14 Completion
On completion and following approval by the Superintendent of the work, all work shall be cleaned by means
(approved by the Superintendent in writing) to give a uniform surface free from all foreign residues.
Clean away and remove from the site all rubbish and unwanted materials and leave the area of the work clean
and tidy.
2.9.15 Testing
The Superintendent reserves the right to take samples of any materials at any time for test or analysis.
Should the results indicate that the requirements of this Specification have not been complied with, action will
be taken under the Contract regarding replacement, re-performance or compensation.
The costs of all failing tests or analysis will in all circumstances be paid by the Contractor.
2.10 STEELWORK
2.10.1 Standards
The following standards shall apply to this Section:
AS1074 Steel tubes and tubulars for ordinary service
AS1214-0983 Hot-dip galvanized coatings on threaded fasteners
AS1397 Steel sheet and strip - Hot-dipped zinc-coated or aluminium/zinc-coated
AS 1428 Design for access and mobility
AS1450 Steel tubes for mechanical purposes
AS 1538 Cold-formed steel structures code
AS 1554 Structural steel welding Part 1 - Welding of steel structures
AS1627.5 Metal finishing - Preparation and pre-treatment of surfaces
AS/NZS4680 Hot-dipped galvanized coatings on ferrous articles
AS 1725 Galvanised rail-less chain wire security fences and gates
AS 2105 Inorganic zinc silicate paint
AS2423-2002 Galvanised wire fencing products
AS 3715 Metal finishing - Thermoset powder coatings for architectural applications
AS 4100 Steel structures.
2.10.5 Workmanship
2.10.5.1 Prefabrication
Fabricate and pre-assemble items in the workshop wherever practicable.
2.10.5.2 Surfaces and Edges
Keep clean, neat and free from all imperfections including burs and indentations.
Remove all imperfections including all bumps and indentations, including all identification markings.
Remove all sharp edges without excessive radiusing.
2.10.5.3 Joints
Fit joints to an accuracy appropriate to the class of work. Finish visible joints made by welding, brazing or
soldering by grinding, buffing or the like methods appropriate to the class of work before painting, galvanizing,
or the like further treatment.
Self-finished metals: Free of surface colour variations, after jointing.
2.10.5.4 Tube Bends
Form bends in tube without unduly deforming the true cross section.
2.10.5.5 Colours
Match colours of sheets, extrusions and heads of fastenings in colour finished work.
2.10.5.6 Metal Separation
Separate incompatible metals by concealed interlayer’s of suitable materials and thicknesses.
2.10.5.7 Thermal Movement
Make provision, sufficient to prevent harmful effects, for thermal movement in joints and fastenings.
2.10.5.8 Steel Welding
To AS/NZS1554 Finished welds shall be free of surface and internal cracks, slag inclusion, and porosity.
2.10.6 Structural Steel
2.10.6.1 Fabrication and Erection
Steel structures to AS4100.
Cold formed steel structures to AS/NZS4600.
2.10.6.2 Beam Camber
If beam members have a natural camber within the straightness tolerance, fabricate and erect them with the
camber up.
2.10.7 Fastenings
2.10.7.1 General
Provide fastenings, including bolts, anchors, screws, rivets, welds, and the like:
sufficient to ensure the rigidity of the assembly;
of types appropriate to the work;
in materials of mechanical strength and corrosion resistance at least equal to that of the lowest resistant
metal joined;
capable of transmitting the loads and stresses imposed; and
installed so as to prevent galvanic corrosion.
2.10.8 Protection
2.10.8.1 Generally
Protect metalwork during the work under the Contract as necessary to prevent damage or defacement.
2.10.9 Galvanized Coatings
2.10.9.1 General
Provide hot dipped galvanized coating to all steelwork including all fittings and fixings.
All galvanised coatings shall be of an Architectural Finish standard.
Finish shall be free from runs, dags, spikes, uneven surfaces and roughness or other defects that could affect
appearance.
All HDG steel shall be inspected by the Superintendent’s Representative, or Clerk of Works, at the galvaniser’s
premises and be approved for use prior to dispatch.
2.10.9.2 Fabrication
Complete welding, cutting, drilling and other fabrication before coating.
2.10.9.3 Surface Preparation
(General ferrous articles): Pickle to AS1627.5
2.10.9.4 Coatings
Unless otherwise specified, zinc coatings shall be by the hot dip method as follows:
Ferrous articles generally: To AS/NZS4680
Ferrous wire: To AS/NZS4680, Section 4, Type A, unless otherwise specified.
Steel sheet: To AS1397, coating class as specified for the particular item.
Threaded fasteners: To AS1214.
2.10.9.5 Damaged Coatings
Repair damaged coating areas by power tool cleaning to AS1627.2 and apply organic single component zinc
coating of minimum 92% (weight) zinc in the dry layer cold galvanizing to provide protection equal to the
original coating.
2.10.10 Dulux Weathermax HBR (High Build Polyurethane)
2.10.10.1 General
Refer Dulux PC 405. Prepare all surfaces and Install strictly in accordance with the manufacturer’s instructions.
2.10.10.2 Fabrication
Complete welding, cutting, drilling and other fabrication before coating.
2.10.10.3 Coatings
Galvanized Steel
Clean, degrease and abrade surface
1st Coat Duremax GPE ZP 125 um DFT
2nd Cost Weathermax HBR 100 um DFT.
2.10.10.4 Damaged Coatings
Repair damaged coating areas by power tool cleaning to AS1627.2 and applying original coating system to
original specification.
2.10.11 Below Ground Steel
All steel works below finished ground level shall be coated with two (2) coats of asphaltic paint, to be approved
by the Superintendent’s Representative. Asphaltic coating shall be applied to the manufacturer’s
recommendations for site specific materials, conditions and use.
2.11.4 Inspection
Give sufficient notice so that an inspection may be made of the following:
Completed form work
Reinforcement fixed in place
Placing of concrete.
2.11.5 Testing
Concrete supplied for the Works shall be subject to production assessment and testing to AS1379, Paragraph
B3.
Testing Authority: Testing and assessment of concrete and concrete materials shall be carried out by an
authority registered with the National Association of Testing Authorities Australia (NATA).
Production Assessment Records: To AS1379. Register the project in accordance with AS1379. Maintain
records and reports of test results required by AS1012. Make the records available on request. Rejection shall
be to AS3600 Clause 19.1.7. Remove rejected concrete from the site.
2.11.6 Materials
2.11.6.1 Concrete Materials
To AS3600 Section 19.
Ready Mix supply to AS1379. Deliver in agitating trucks.
Supply concrete to comply with the following performance criteria:
Class of Concrete: Normal Portland Cement (Type GP).
Cement: To AS3972 AS3972 AS3972 Type GP,
Strength Grade, Slump, Maximum Aggregate Size:
Slabs on Ground: 32MPa, 80mm, 20mm.
Footings: 25MPa, 80mm, 20mm.
Blinding: 15MPa, 80mm, 20mm
Cavity Fill: 25MPa, 200mm, 14mm.
2.11.6.2 Form Work
To AS3600 Clause 19.6.
Design and construct form work so that concrete, when cast in the forms, will have the dimensions, shape,
location and surface finish required by the Contract.
Dimension tolerances to AS3600 Clause 19.5.
Form work removal to AS3600 Clause 19.6.
2.11.6.3 Reinforcing
To AS3600 Clause 19.2.
Supply and fix reinforcement, including the necessary tie wires, support chairs, spacers and the like.
Reinforcement shall be readily identifiable as to grade and origin.
Submit for approval details of proposed bending and splicing not shown on the Drawings.
2.11.7 Workmanship
2.11.7.1 Sub Grade
Compact sub-grade to the full extent of all footings and slabs on ground to a minimum of 8 blows per 300mm
as measured with a Perth Sand Penetrometer to a minimum depth of 750mm.
2.11.7.2 Placing and Compaction
To AS3600 clause 19.1.3.
Use placing methods which minimise plastic settlement and shrinkage cracking.
Movement may be by means of suitable clean chutes, troughs or pipes. Do not use water to facilitate the
movement.
Place concrete in layers such that each succeeding layer is blended into the preceding one by the compaction
process. Concrete exposed to rain before it has set, including during mixing, transport or placing, shall be liable
to rejection.
Use immersion and screed vibrators accompanied by hand methods as appropriate to remove air bubbles and
compact the mix. Ensure concrete is fully compacted and entrapped air removed, but avoid over vibration that
may cause segregation. Do not allow vibrators to come into contact with partially hardened concrete, or
reinforcement embedded in it. Do not use vibrators to move concrete along the forms.
2.11.7.3 Curing
To AS3600 clause 19.1.5.
Protect fresh concrete from premature drying and excessively hot or cold temperatures. Maintain the concrete
at a reasonably constant temperature with minimum moisture loss for the curing period.
Commence curing immediately after finishing, and cure continuously for not less than seven (7) days.
Submit for approval the proposed method of curing, which may include the following:
Ponding or continuous sprinkling with water (moist curing)
An impermeable membrane
An absorptive cover kept continuously wet.
2.11.7.4 Finish
All off form finished surfaces including, but not limited to walls, tables, benches, benching, seats, step treads
and pavement surfaces shall be free draining and free of ponding. All step treads and pavement surfaces shall
comply with AS/NZS 4586 Classifications in Selecting Pedestrian Surface Materials.
All off form concrete work shall be finished to a monolithically smooth “Class 2 Finish” and 10mm chamfer to
all exposed edges.
All steel shall be pre-drilled for fixings and welded prior to hot dip galvanising.
All steel work shall comply with the ‘Steel’ clause of this specification.
Concrete work: refer Structural Engineers specification.
2.12.5 Waterproofing to CONCRETE Retaining Walls
2.12.5.1 Coating
Location behind all retaining walls to within 100mm of finished ground level or as detailed.
Coating is to be liquid applied single component asphalt latex emulsion which cures by evaporation to form an
elastomeric waterproofing membrane.
Waterproofing agent is to be Enviro HP1200.
2.12.5.2 Application
Apply the emulsion strictly in accordance with the manufacturers recommendation.
2.12.6 Sealing
Following installation all concrete surfaces shall be sealed with "DRY TREAT Stain-proof" penetrating sealer,
applied with two (2) coats to the approval of the Superintendent.
2.12.7 Protection
Protect stone work and concrete from staining and damage. Use sheeting or other screening as necessary. Do
not use hardwood in contact with units.
Clean off all droppings as they occur. Stained or damaged units shall be replaced, not repaired, unless
otherwise permitted by the Superintendent. Contractor shall be fully liable for all costs associated with
replacement.
The replacement of units will not be grounds for extension of construction time.
Protect adjoining surfaces during paving work. Finished surfaces in the vicinity of work being carried out shall
be protected from staining and impact and all necessary precautions are to be taken to ensure that protection
is provided and maintained.
2.13.4 Concrete
Concrete mixes shall be as follows:
Pavement Type 1:
Cement: Grey, Portland Cement Type ‘GP’ or approved equivalent,
Oxide: Nil,
Aggregate: Grey granite, nominal maximum size 14mm,
Maximum slump: 80mm,
Thickness: 100mm
Finish Steel float and Broom finish to full extent (no tooled edges or joints),
Compressive Strength: 25 M.Pa. Minimum at twenty eight (28) days.
Pavement Type 3:
Type: Exposed Aggregate Concrete
Colour: Holcim Geostone “GREVILLEA”;
Maximum slump: 80mm;
Thickness: 100mm
Finish: Water-washed exposed aggregate (no tooled edges or joints); and
Compressive Strength: 32 M.Pa. Minimum at twenty eight (28) days.
Pavement Type 4:
Type: Exposed Aggregate Concrete
Colour: Holcim Geostone “JACKWOOD”;
Maximum slump: 80mm;
Thickness: 100mm
Finish: Water-washed exposed aggregate (no tooled edges or joints); and
Compressive Strength: 32 M.Pa. Minimum at twenty eight (28) days.
The Contractor shall guarantee that all concrete shall be of like composition, i.e. utilising the same batch of
sand and using the same proportional mix of materials.
All colour variations caused by variances in the composition of materials used, the lack of cleanliness of the
site or truck, or failure to adequately protect concrete will be replaced by the Contractor, at the Contractor’s
expense.
2.13.5 Form Work
Form work shall be of steel or suitable dressed seasoned timber planks, free of warps, bends or kinks.
Forms shall be staked with no less than 3 stakes and not more than 1.5m apart to prevent unspecified warps
and bends. Forms shall be in one piece for the concrete pavement thickness specified.
2.13.6 Placement
2.13.6.1 Placement – Pedestrian Pavement
Lay concrete 100mm thick minimum between control joints and screened off to falls and finish with a steel
hand trowel.
2.13.6.2 Placement – Trafficable Pavement
Lay concrete 150mm thick minimum between control joints and screened off to falls and finish with a steel
hand trowel.
2.13.7 Expansion and Control Joints
2.13.7.1 Expansion Joints
Provided 15mm All In One Lock Joint expansion joints in paving as indicated on the drawings and, as a
minimum evenly spaced at intervals not exceeding 6000mm apart in any one direction in pavements or in
lineal sections of paths.
All In One Lock Joints rubber top to match surrounding pavement materials.
Provided 15mm wide expansion joints with a backing of 15mm dia. closed cell polyethylene strip (colour to
match surrounding pavements) in paving at all fixed edges including kerbs, adjoining pavement edges and
walls, to the edges of all furniture and fittings, services lids and other pavement inserts and where two linear
paths join or deviate in alignment. Set strip back sufficient distance so that sealing compound will finish flush
with paving.
2.13.7.2 Contraction Joints
Provided 30mm deep cut contraction joints minimum as indicated on the drawings located as per the drawings,
at a minimum evenly spaced at intervals not exceeding 2000mm apart in any one direction.
2.13.8 Finishing
2.13.8.1 General
All pavement surfaces shall comply with AS/NZS 4586 Classifications in Selecting Pedestrian Surface
Materials.
2.13.8.2 Broom Finished Concrete
After placing and compaction, concrete shall be finished monolithically to a smooth, even surface by means of
steel floats or other suitable equipment. On completion of steel floating and before initial set, the surfaces of
concrete pavements shall be brushed to a “non-skid” slip resistant texture to Pendulum P4 rating or higher as
per AS 4586 Slip Resistant Classification of New Pedestrian Surface Materials. This shall be achieved by
drawing a moistened nylon broom lightly across the surface in a continuous direction.
2.13.8.3 Edges and Joints
Pavement finish shall be to full extent with pencil round tooled edges. There shall be no “picture window”
treatment to edges or joints.
2.13.9 Curing
To AS 3600 clause 19.1.5.
Protect fresh concrete from premature drying and excessively hot or cold temperatures. Maintain the concrete
at a reasonably constant temperature with minimum moisture loss for the curing period.
Commence curing immediately after finishing, and cure continuously for not less than seven (7) days.
Submit for approval the proposed method of curing, which may include the following:
Ponding or continuous sprinkling with water (moist curing)
An impermeable membrane
An absorptive cover kept continuously wet.
2.13.10 Protection
Protect paving from staining and damage. Use sheeting or other screening as necessary. Do not use
hardwood in contact with pavements.
Clean off all droppings as they occur. Stained or damaged pavements shall be replaced, not repaired, unless
otherwise permitted by the Superintendent.
Protect adjoining surfaces during paving work. Finished surfaces in the vicinity of work being carried out shall
be protected from staining and impact and all necessary precautions are to be taken to ensure that protection
is provided and maintained.
Protect all paving as follows:
exclude all foot traffic for 3 days;
exclude all vehicles and heavy traffic for 21 days minimum; and
provide barriers and planking to accommodate traffic.
2.13.11 Tolerances
Works shall be undertaken to the following tolerances:
Maximum deviation from design level: + 5mm, - 5mm
Grade across pavement shall be 2% + or -0.5% or as indicated on the drawings.
Pavement surface shall be true to line and not deviate more than 5mm under a 3m straight edge.
Surface irregularities, including abutting to service authority manholes, etc. shall not exceed 2mm.
Thickness: = or –5mm. A random testing programme will be used to check the thickness, and if any
point is outside the tolerance, further testing shall be undertaken within that 5m section and the adjoining
5m sections on either side. Three or more additional thickness tests will be taken on each of the
sections. If any of these show a reading that is outside the required tolerance, that section of the
pavement shall be removed and replaced with new work to this specification.
The pavement shall be constructed to the nominated width + or - 20mm.
Any sections of the pavement not meeting the requirements of this specification shall be removed from the site
and replaced.
2.13.12 Sample Panel
Construct a three (3) square metre sample panel for approval of the Superintendent prior to commencing
works. All works shall comply with the finish of the approved sample panel.
The panel may be incorporated into the Works. Panel location is to be determined on site by the
Superintendent.
2.13.13 Sealer / Anti-Graffiti Coating
Upon completion of construction, supply and apply sealer / anti-graffiti coating to all above ground surfaces.
Sealer / anti-graffiti coating shall be equal or equivalent to Crommelins, to the approval of the Superintendent,
suitable for the substrate and site conditions, as recommended by the manufacturer.
Install strictly in accordance with the manufacturer’s instructions suitable for the substrate.
All sealants to meet "non-skid" slip resistant texture to Pendulum P4 rating or higher as per AS 4586 Slip
Resistant classification of New Pedestrian Surface Materials.
Hand constructed mowing kerbs must be done using good quality framework capable of producing uniform,
well finished kerbs in either straight and even lengths or smooth, even curves.
Top surface of all kerbing must finish flush with surrounding surfaces and/or ground level.
Finish all kerbing monolithically to a smooth, even surface by means of a steel trowel or other surface
equipment.
Provide surface protection to kerbing as necessary to prevent cracking of the concrete due to temperature
changes during curing periods. Make good to all poorly constructed and/or damaged lengths of kerb.
2.14.7 On Completion
Remove all excess concrete from site and backfill with soil flush with top of kerb.
2.17.3 Fixing
Use M6 stud type chemical anchors and stainless-steel acorn nuts fixing to limestone wall and M12 Loxin
masonry anchors with flush head fixing into concrete footing, as detailed.
2.17.4 Fastening
Provide fastenings, including bolts, anchors, screws, rivets, welds, and the like:
Sufficient to ensure the rigidity of the assembly;
Of types appropriate to the work;
In materials of mechanical strength and corrosion resistance at least equal to that of the lowest resistant
metal joined;
Capable of transmitting the loads and stresses imposed; and
Installed so as to prevent galvanic corrosion.
2.17.5 Galvanized Coating
Complete welding, cutting, drilling and other fabrication before coating.
Pickle prepared surface to AS1627.5 Part 5. Unless otherwise specified, zinc coatings shall be by the hot dip
method as follows:
Ferrous articles generally: To AS/NZS4680.
Ferrous wire: To AS/NZS4680, Section 4, Type A, unless otherwise specified.
Steel sheet: To AS1397, coating class as specified for the particular item.
Threaded fasteners: To AS1214-0983.
2.17.5.1 Galvanized Coating
Complete welding, cutting, drilling and other fabrication before coating.
Pickle prepared surface to AS1627.5 Part 5. Unless otherwise specified, zinc coatings shall be by the hot dip
method as follows:
Ferrous articles generally: To AS/NZS4680.
Ferrous wire: To AS/NZS4680, Section 4, Type A, unless otherwise specified.
Steel sheet: To AS1397, coating class as specified for the particular item.
Threaded fasteners: To AS1214-0983.
2.17.5.2 Powder Coating
Complete galvanize coating before powder coating.
All steel frames, horizontals and uprights to be powder coated using Dulux Alphatec Plus. Colour to be advised.
All powder coating application to comply with AS3715
2.17.6 Steel Grab Rail
2.17.6.1 General
Supply and install steel grab rail to all kerb ramps to the locations as indicated on the drawings. Grab rails to
comply with Main Roads WA specification and approval.
2.17.6.2 Steel
Steel grab rail to be constructed using 50mm diameter (nominal) x 3.2mm wall thickness tube. Fabricate as
shown on the Drawings and to comply with AS1428 Part 1. Exposed welds are to be ground off smooth.
2.17.6.3 Fixing
Set grab rail 400mm minimum into 200 x 200 x 400mm deep N20 concrete footings, minimum 50mm cover
as detailed.
2.17.6.4 Galvanized Coating
All steelwork are to be galvanized.
Complete welding, cutting, drilling and other fabrication before coating.
Pickle prepared surface to AS1627.5 Part 5. Unless otherwise specified, zinc coatings shall be by the hot dip
method as follows:
Ferrous articles generally: To AS/NZS4680.
2.17.6.5 Finish
2.17.6.6 Reflective Tape and Powder Coat Finish
Reflective tape and powder coat finish to be installed as detailed on the drawings, to AS1743, colours and
locations as detailed.
All powder coating application to comply with AS3715
2.20 TREE, SHRUB AND PLANT (GREEN STOCK) SUPPLY AND PLANTING
2.20.1 Green Stock Supply
All green stock supplied by the Contractor shall be supplied by suppliers approved by the Superintendent, to the
species, sizes and quality as specified in Specification and Plant Schedules.
2.20.2 Green Stock Supply and Report
2.20.2.1 Supply Report
Within two (2) weeks of acceptance of tender, furnish to the Superintendent a PRELIMINARY GREEN STOCK
SUPPLY REPORT covering all green stock under the works, including Principal supplied stock and stock from
specified suppliers, detailing the following:
Container and Green Stock Size for each species;
Number of each species;
Nursery Supplier for each Species;
Contact Details for each Nursery Supplier;
Holding Location and Details for each Species; and
Green Stock not currently available as specified.
Within four (4) weeks of acceptance of tender, furnish to the Superintendent a FINAL GREEN STOCK SUPPLY
REPORT, including all species substitutions for unavailable green stock as determined by the Superintendent.
The report shall detail the following:
All Green Stock and Stock Substitution Species under the Works,
Container and Green Stock Size for each species,
Number of each Species,
Nursery Supplier for each Species,
Contact Details for each Nursery Supplier,
Holding Location and Details for each Species,
2.20.2.2 Green Stock Supply Guarantee and Penalties
Failure to provide to the Superintendent, in writing, a Preliminary Green Stock Supply Report and a Final Green
Stock Supply report comprising all green stock species and sizes within the contract within the times specified
within this contract will incur a penalty on the Contractor of One Thousand Dollars ($1,000) per week per report
for every week, or part week for which the reports are not submitted, excluding Principal supplied stock and
stock from specified suppliers. The penalty shall be deducted from the value of the Contract.
The Final Plant Supply Report shall constitute a written guarantee by the Contractor that each species listed in
the report will be in good condition and available for use in the works, excluding Principal supplied stock and
stock from specified suppliers.
A penalty on the Contractor of Two Thousand Dollars ($2,000) shall apply for each species listed in the Final
Green Stock Supply Report approved by the Superintendent that is subsequently found by the Superintendent
to not be in good condition or not available for use in the works, excluding Principal supplied stock and stock
from specified suppliers. The penalty shall be deducted from the value of the Contract.
The full cost of the supply and planting of all replacement species for plants that are subsequently found by the
Superintendent to not be in good condition or not available for use in the works shall be borne by the
Contractor, excluding Principal supplied stock and stock from specified suppliers. The Superintendent shall
determine the species and stock to be used for substitution in the works.
2.20.2.3 Green Stock Quality
All green stock shall:
be true to species, subspecies and variety;
be vigorous and healthy;
be of good form consistent with species and variety;
be well established in the plant container specified including having a large and healthy root system that
occupies the full extent of the container while showing no evidence of restriction or having been restricted
or damaged at any time during production;
not be soft or produced using forced growing techniques;
be hardened off;
be fully self supporting without staking or guying;
be free from disease, insect pests and other pathogens and;
be free from damage from staking, tying or any other horticultural techniques used throughout
production.
The Superintendent will reject any green stock which does not meet the required quality.
2.20.2.4 Green Stock Labelling
Label at least one specimen of each species or variety with a durable, readable tag.
Mulch shall not be placed within 100mm of all plant stems for less than 13 litre pot sized stock, and shall not
be placed within 200mm of all plant stems for 13 litre pot size and greater.
2.20.3.14 Staking and Tying
Protect each tree of pot size 200, 100, 45 and 15 Litre with Three (3) 50 x 50 x 2500mm pointed hardwood
stakes.
All Stakes shall be painted Blackusing two coats of Dulux Timber colour Low Sheen Acrylic. Painting of stakes is
to be carried out no less than 48 hours prior to installation to ensure that paint on all stakes is dry prior to
installation
Stakes shall be set out in an equal triangulated configuration, each 600mm from the trunk and at the extent of
much bed in turf grass areas. Do not pierce root ball.
All stakes shall be set 700mm into the ground and individually cut to length to extend 100mm only above
finished tree tie fixing location.
All ties shall be 50mm wide Natural Hessian to the approval of the Superintendent.
Ties are to be located at no more than 2/3 of the tree height from ground and sufficient to provide additional
support during adverse prevailing wind conditions only.
All ties shall be placed in a loose figure of eight around stake and stem to provide adequate protection from
damage without compromising natural plant growth, stabled to skakes.
2.20.3.15 Watering
At time of planting provide by hand watering a minimum of 10 litres of water to each plant. Repeat watering to
each plant with 10 litres of water on each alternate day up to Practical Completion.
Watering of plants by sole reliance on the irrigation system will not be accepted until the irrigation system is
practically complete or, unless approved in writing by the Superintendent.
2.20.4 Tree Planting
2.20.4.1 Planting
Remove tree bag or container carefully to prevent root damage. Edges of the root ball to be ‘ruffled’ to remove
any root circling / girdling that may be occurring.
Backfill with improved soil media to occur in 100-150mm ‘lifts’ with firming of the back-fill occurring around the
root ball of the tree after every lift.
Watering shall occur at the same time as the planting and firming.
Construction a ‘bund’ at the edge of the compost / mulch zone to aid in water retention where landscape
surrounds allow.
After planting conditioned site soil shall finish 120mm below adjacent kerbing, paving and turf areas.
2.20.4.2 Compost
Directly after plating apply 15mm compost to the full extent of the root ball and conditioned soil mix and gently
cultivate into the top 100mm to provide a homogeneous mix.
Compost shall be:
C-Wise ‘Horticulture’.
Soil conditioner shall comply with AS4454Composts, Soil Conditioners and Mulches.
2.20.4.3 Humate
At time of compost application apply a Humate to the full extent of the rootball and conditioned soil mix.
Humate shall be
Eco-Growth’s Humus 400.
Apply at the rate of 50g / square metre.
2.20.5 Clean Up
On completion of planting ensure that all plants are in first class, presentable condition by removing dead,
damaged and unhealthy branches and trimming where necessary to result in balanced growth typical of their
normal form. After inspection by the Superintendent and on Practical Completion, remove labels from plants.
All surfaces prepared for grassing to finish flush with adjoining kerbs to roads, parking and paved areas, and
with foot pavements, terraces, verandas, mowing strips, manholes, pit and the like.
Where plumbing connector traps and rainwater relief overflows occur, finish ground level 75mm below overflow
level.
All grading works shall be undertaken by hand work or by machine as is appropriate to the work however all
grading and earthworks within a distance of 600mm radius of sprinklers or other fixed reticulation apparatus
shall be hand worked to prevent damage to equipment.
Finish shall be smooth rolled, consolidated and smudge boarded to obtain a perfectly even, well consolidated
surface.
No irregularities, depressions, hollows or abrupt changes in grades or falls will be accepted.
The cost of such minor preparation work shall be included in the unit rate per square metre tender price and no
extras will be allowed for such preparation.
Before commencing work, inspect the site with the Superintendent to determine that grading can be achieved
without providing additional filling sand from off-site sources.
If the Superintendent determines that additional filling sand is required, submit a written quotation which will
be the subject of a variation to the contract as per the unit rate schedules.
2.22.2.2 Fertilizing
Prior to turf laying supply and spread to the full extent of area to be turfed pelletised organic fertilizer equal or
equivalent to “Dynamic Lifter” at the rate of 100 grams per square meter to the approval of the
Superintendent.
2.22.2.3 Watering
Supply all equipment necessary to adequately water the site during the Construction period.
Before commencing planting, ensure adequate watering services and equipment are available and properly
functioning.
Areas to be planted shall first be watered to a depth of 100mm and the planting shall be carried out
immediately after watering.
Throughout the contract up to Practical Completion, watering shall be properly undertaken, either by hand or
irrigation system to keep the planted area moist to a depth of 100mm at not more than two (2) day intervals
excepting Saturdays, Sundays and Public Holidays unless otherwise directed by the Superintendent.
Any faults or defects to the watering service and equipment during the construction period shall be immediately
reported to the Superintendent.
2.22.2.4 Turf Laying
Lay the turf along the land contours with staggered, close butted joints, and so that the finished turf surface is
flush with adjacent finished surfaces of paving and the like. As soon as practicable after laying, roll the turf
with a roller weighting not more than 90 kg/m of width or plate compactor. On slopes too steep for rolling,
lightly tamp with turf into place.
2.22.2.5 Making Good
Lift failed turf and relay with new turf. Turf of poor quality will be rejected.
2.22.2.6 Top Dressing
Undertake top dressing as required to produce a true and even surface to the full extent of turf areas free of
humps, hollows and depressions. Should top dressing be required, undertake when the turf is established,
mow closely, remove cuttings and lightly top dress to a depth of 10mm with approved quality top dressing
sand. Rub the dressing well into the joins and correct any unevenness in the turf surface.
2.22.3 Turf Establishment
2.22.3.1 General
All turf grassing shall be fully established prior to granting of Practical Completion of turf grassing.
Undertake all establishment requirements including watering, fertilizing and mowing as specified to all newly
grassed areas for the duration of the mowing and fertilizing programme specified and until such time as the
turf grass is fully established.
For turf laid between the months of November to May inclusive a minimum of 6 weeks shall be allowed for full
establishment. For turf laid between the months of June to October inclusive a minimum of 12 weeks shall be
allowed for full establishment.
Commencement of turf grassing consolidation will be subject to the successful establishment of turf grassing
as solely determined by the Superintendent.
2.22.3.2 Watering
Throughout the turf establishment period, ensure watering shall be properly undertaken, either by hand or
irrigation system to keep the planted area moist to a depth of 100mm at not more than two (2) day intervals
excepting Saturdays, Sundays and Public Holidays unless otherwise directed by the Superintendent.
Any faults or defects to the watering service and equipment shall be immediately reported to the
Superintendent.
2.22.3.3 Fertilizing (1st stage)
One week after laying turf, apply to the whole area a fertilizer mixed in the proportion of:
Two parts AGRAN 34, one part Superphosphate No. 1 and,
One part of MURIATE of Potash or such other lawn starter fertilizer as may be approved.
Evenly spread fertilizer at the rate of 50 grams/square metre and immediately thoroughly water in.
Fertilizing and watering shall be inspected by the Superintendent during each operation.
Give the Superintendent two (2) working days notice before the commencing of fertilizing and watering.
2.22.3.4 Fertilizing (programme)
(2nd, 3rd, 4th, 5th and 6th Applications)
Apply a total of FIVE fertilizer applications to grassed areas after initial fertilizing.
Each application shall be at a maximum of four (4) and a minimum of three (3) weeks after initial fertilizing.
Each application is to be at the following rate:
50 grams/sq. metre of baileys ‘Brilliance’ NPK with trace elements granulated fertilizer immediately
thoroughly watered in.
Give the Superintendent two (2) working days notice before the commencement of each fertilizing and watering
for site inspection.
2.22.3.5 Sample of Fertilizers
Submit to the Superintendent on request, sample of fertilizers used in the works.
The samples may be subjected to analysis. Fertilizer not in accordance with the Specification may be rejected.
Areas found to be not in accordance with the Specification shall be given an additional application of fertilizer
in accordance with the Specification at their own expense.
2.22.3.6 Mowing
All newly grassed areas are to receive six mowing’s using a reel mower or an approved equivalent. When grass
growth has reached 75mm a first light cut shall be made carefully avoiding damage to new turf. Cutting shall
not remove more than 50% of growth and cuttings shall be caught and removed from the site.
Each additional cut (five in total) shall be made when turf has again reached 75mm. Repair all failed turf after
mowing. Cuttings shall not remove more than 50% of growth and all cuttings shall be caught and removed from
the site.
2.22.3.7 Weed, Insect and Fungus Control
The control and eradication of all weed growth, insect and fungus infestations shall be the total responsibility of
the Contractor. During the establishment period all areas shall be managed to ensure minimal weed growth
either by spraying or manual removal at all times until Practical Completion. Where required, spray with
insecticide, herbicide or fungicide in accordance with the manufacturer’s recommendations, to all Health
Department and other statutory requirements. Submit proposal for approval prior to starting this work.
2.22.3.8 Rolling and Surface Finish
After the completion of second mowing the newly grassed areas shall be rolled with a heavy roller and finished
to produce true and even grades and falls free of all wheel marks and ruts, waves, depressions and other
irregularities. Maximum weight of roller is to be 500 kilograms.
2.22.3.9 Programme Inspections
Give the Superintendent not less than two (2) working days notice before completing each stage so that he may
inspect the work.
Payment will only be made upon a satisfactory grass growth pattern being in evidence with sward in a healthy
and vigorous condition at the initial inspection and continuing similar healthy growth being evident. Make
repairs to each stage as are necessary to maintain full cover to the area.
The Contractor shall be fully responsible for all remedial works, including patching, to ensure a 100% full cover
of grass is maintained at all times.
2.22.4 Practical Completion
Practical Completion and commencement of Consolidation will be granted by the Superintendent, upon sole
determination by the Superintendent that the turf establishment programme is fully complete and that the turf
grassing is fully established.
2.23.10 Examination
Inspect site and compare conditions to those provided in specification and drawings. Notify Superintendent of
any discrepancy for direction.
Commencement of works signifies full acceptance on behalf of the contractor of all existing site conditions.
2.23.11 Preparation
Co-ordinate with other trades responsible for any site preparation or works as required prior to making final
preparation before installation of materials.
2.23.12 Trenches and Excavations
Prior to excavation of trenches, obtain approval of pipe runs. Minor adjustment in the system's layout will be
permitted to clear existing underground obstructions. Repair costs to services damaged are the responsibility
of the Contractor performing this work.
Excavate mainline trenches to a depth so as to allow a minimum of 400mm cover from the top of the pipe to
the ground surface. Excavate trenches for lateral spray lines to a depth so as to allow a minimum of 300mm
cover from the top of the pipe to the ground surface. Excavate trenches to sufficient width to permit proper
handling and installation of the pipe and fittings.
Obtain approval prior to back filling trenches. Pipes are to be firmly and evenly supported with clean backfill
material free of rubble, stones and rocks. Where rock and stone is incurred during the excavation works, back
fill material over the pipe to be clean, white packing sand free of organic matter. Place sand layer 75mm
depth from the top of the pipe.
Place trench backfill material in at least two equal layers. Each layer to be wheel-rolled with a backhoe or
other approved compaction equipment and crown completed backfill 30mm higher than the surrounding
surface to allow further consolidation.
Where solid rock is encountered in trench excavation, request an inspection of the open trench prior to further
trench excavation in that area. Rock are to be measured in the solid jointly by representatives of the Contractor
and the Superintendent within the confines of the excavation and within the limits shown on the drawings or
specified prior to back filling. No allowance will be made for over break.
The Contractor is responsible for the erection of all necessary barriers and safety signs to make trench work
safe from public pedestrian entry. Under no circumstances are trenches to remain either open or partially
open over night.
2.23.13 Installing Pipes
Install sprinkler lines or mains with a minimum cover as specified above. Interior of pipes are to be kept free
from dirt and debris. Open ends of pipe to be closed by approved means during the laying process.
Use red priming fluid and blue dyed solvent cement to joints. Ensure that excess solvent is carefully wiped free
of joints and keep joints dry for 24 hours minimum to allow solvent cement to dry. Turn on valves to each
station to flush lines out with water before fitting spray heads.
Ensure that no pipe lengths will carry water at greater than 1.5 metres/second velocity.
2.23.14 Under Road Boring, Sleeve Pipes and Thrust Boring
Utilize under road or pavement boring techniques to facilitate road crossings which may be required for the
placement of irrigation mainlines and control cabling under such infrastructure. All road crossings shall be
accomplished utilizing an appropriately sized PVC sleeve for the placement of mainlines and/or control
cables. Where control cables are to be installed within the same PVC sleeve as irrigation mainlines, install the
cables within an appropriate size PVC low density electrical conduit.
PVC along entire width of pavement. Install top of PVC sleeve pipe 400mm below existing pavement level.
2.23.15 Valves
Inform Superintendent of any proposed change made in supply and installation of Master Valve. Allow for
connection of pipe work tees and junction elbows from the existing pipe work out of the valve.
2.23.16 Sprinkler Risers
Install sprinklers on screwed 15mm schedule 80 PVC articulated risers. Set spray heads level with topsoil or at
a level determined by the Superintendent.
Securely brace the riser against vibration where the sprinkler head is in operation.
Flush out mains, laterals and risers with water before fitting sprinkler heads to risers.
Prior to Date of Practical Completion the Contractor shall supply to the Superintendent one A1 paper (or original
drawing) size and one digital (CD) copy of the as constructed drawings clearly showing all works as executed
and covered by the contract, including all warranties and manuals.
The supply of approved as executed drawings, warranties and manuals forms part of the works and shall be a
condition precedent to the Superintendents acceptance of Practical Completion.
Practical Completion of Turf Grassing will be granted by the Superintendent upon completion of the turf
grassing establishment programme and when the turf grass is fully established as solely determined by the
Superintendent.
2.25 CONSOLIDATION
2.25.1 General
Consolidation shall mean the continuing care and consolidation of the works by accepted horticultural and
landscape maintenance practices, as well as rectifying any defects that become apparent in the works.
The consolidation period for Hard Landscape and Planting works shall commence from the Date of Practical
Completion and be for a period of Three (3) calendar months.
The consolidation period for Turf Grassing shall commence from the Date of Practical Completion of Turf
Grassing (at completion of turf establishment programme to the sole discretion of the Superintendent) and be
for a period of Three (3) calendar months.
Works to be consolidated include all the works under the contract including, but not limited to:
Inspection and Reporting;
Hard Landscape Works Consolidation;
Soft Landscape Works Consolidation;
Irrigation System Operation (where irrigation is within the landscape contract);
Rubbish Removal; and
Rectification of Defects, Vandalism and Theft.
2.25.2 Consolidation Commencement
Works shall only be placed in consolidation when a certificate of practical completion has been issued for the
full or separable portion of the works as stated in the contract.
2.25.3 Inspection and Reporting
2.25.3.1 Weekly Inspection
The Contractor shall inspect the full works at a minimum on a weekly basis and immediately report to the
Superintendent any activities and conditions that in any way adversely affect the works including all damage
and theft.
2.25.3.2 Weekly Consolidation Reporting
Throughout the consolidation period the Contractor shall prepare and submit to the Superintendent on a
weekly basis a consolidation report covering the following:
Date and time of weekly inspections;
Condition of pavements and hard landscape elements;
Condition of garden structures, furniture and fixtures (including lighting where lighting is within the
landscape contract);
Exercise Elements and Surfaces Maintenance;
Condition of irrigation;
Condition of garden beds and turf grassing;
Progress of establishment of green stock and turf grassing;
Damage or disruption by others throughout the works, including sand drift from adjacent sites;
Activities that have been completed throughout the month,
Activities planned for the month ahead, and
Upcoming capital outlays required to consolidate the works.
Payment of claims for consolidation shall be dependent upon the submission and approval by the
Superintendent of compliant consolidation reports.
2.25.4 Hard Landscape Works Consolidation
2.25.4.1 General
Maintain all hard landscape works in a clean, neat and tidy condition for the full extent of the consolidation
period. All defects shall be rectified at the Contractor’s expense within one (1) week of detection.
Notify the Superintendent of any hard works or street furniture that have been stolen or damaged and await
instructions from the Superintendent prior to repair or replacement..
2.25.5 Soft Landscape Works
2.25.5.1 General
The consolidation programme shall include, but not be limited to the following items where and as required:
Turf Grassing Maintenance; and
Mass Planting Area Maintenance.
2.25.5.2 Turf Grass Maintenance
Maintain turf grassing in a healthy, vigorous condition, free of weeds and pest and mown as required to
maintain optimal health and suit seasonal requirements.
Undertake all testing and control as required to identify and control all pests and disease including Pythium
root rot.
2.25.5.3 Weed Control
Maintain site and fence lines free of weeds and invasive plants. Eliminate all weed growth to landscaped areas
using approved non-residual herbicide such as “Roundup”. Control weeds growing in watering basins by means
of suitable selective herbicide such as ‘Roundup’.
2.25.5.4 Vermin, Pest and Disease Control
The Contractor shall maintain all plants free from pests, disease and attack and damage by vermin by
approved methods at the Contractors expense.
Undertake all testing and control as required to identify and control all pests, disease and vermin including
Phytophthora root rot.
Where chemicals are required preference will be given to biological control and low toxicity systemic products.
Mechanical applicators will be precisely calibrated and care taken when applying to minimize over spray.
Chemicals used in plant maintenance shall be applied in accordance with all Health Department Regulations
and relevant approved Safety Data Sheets for each chemical.
2.25.5.5 Re-Planting
Replace weekly all dead and dying plants, including plants damaged by vermin at the Contractor’s expense.
On a weekly basis notify the Superintendent of the quantity and type of plants that have been stolen or
damaged through vandalism and await instructions from the Superintendent prior to replacement.
2.25.5.6 Pruning
Prune all dead wood or foliage from plants as required each week.
2.25.6 Watering - Irrigated
Provide sufficient irrigation to maintain all plants in a healthy growing condition in accordance with the
Irrigation Operation and Maintenance section of this specification for the duration of the Consolidation period.
2.25.7 Irrigation System Operation
Operate and maintain the irrigation system for the extent of the consolidation period to ensure the effective
watering off all irrigated areas under the contract under prevailing site conditions. The Contractor shall be
responsible for all cost associated with maintaining the irrigation during the consolidation period.
Any plant material that has died or is set back due to the failure of the irrigation system shall be immediately
replaced to original specification be the Contractor. All costs associated with replacement of dead or set back
plant material shall be borne by the Contractor.
During the consolidation period of the Contract the Contractor shall immediately repair, at the Contractors
expense, any irrigation component failure or malfunction including the repair of any erosion of soil due to
sprinkler failure or malfunction.
During the consolidation period of the Contract, the Contractor shall immediately inform the Superintendent of
any theft or wilful damage by others and await instruction. All cost associated with repairs due to vandalism
and theft shall be borne by the Principal and be subject to an approved variation to the contract.
The contractor will make immediately make safe and undertake repairs as necessary to the irrigation system
when a failure of the system will jeopardize public safety or the establishment of the landscape works and,
immediately notify the Superintendent of the actions taken.
After establishment of the landscaped areas, adjust the heights of all sprinkler heads, valve boxes, cable pits
etc as and when instructed by the Superintendent.
2.25.8 Rubbish Removal
Maintain the site free of rubbish, rocks, branches etc for the full extent of the consolidation period.
Rubbish, including the emptying of refuse bins from the entire site shall be undertaken as required to maintain
the site in good condition. As a minimum, rubbish removal shall be undertaken once per week on Friday or
Saturday mornings. All rubbish shall be disposed of off site in an approved refuse tip at the contractor’s
expense.
2.25.9 Rectification of Damage, Vandalism and Theft
Take all reasonable steps practicable to minimize the threat and occurrence of damage, vandalism and theft to
the landscape generally. This shall include but not be limited to removal of unused equipment after hours,
maintaining lighting, not leaving tools or piles of pruned or mowed vegetative material on site over weekends
and immediately reporting suspicious activities to the Superintendent and, if deemed necessary the police.
During the consolidation period damage to the works due to vandalism and theft shall be repaired by the
Contractor.
All cost for rectification of damage, vandalism and theft of the works, except those due to an act or omission on
the part of the Contractor, shall be borne by the Principal and subject to an approved variation to the Contract.
No rectification shall be completed without the written approval of the Superintendent. All rectification shall be
completed by the Contractor within seven days of approval to proceed.
Any damage, vandalism or theft that renders the works unsafe shall be immediately made safe by the
Contractor by barricading off or other appropriate means and immediately notified to the Superintendent.
Any damage, vandalism or theft to the landscape shall be reinstated as shown on the plans and as outlined in
the contract documents.
07.1 INTRODUCTION
07.1.1 GENERAL
This section of the specification forms part of the contract documents. It is to be read in conjunction with
the preliminaries section of the specification for full meaning. Both the contractor and subcontractor are
deemed to be fully informed of the contents and requirements of (in the case of the contractor) this
specification section and associated drawings and (in the case of the subcontractor) the relevant sections
of all other specification trade sections, including the preliminaries and all other relevant drawings.
The Mechanical subcontractor is referred to the Preliminaries section of the Specification for the particular
requirements which relate to work arising from and related to the works specified in this section.
07.1.2 TENDER SCHEDULES
The tender schedules supplied within the Preliminaries of the specification relates to this part of the works
only and are to be provide by the contractor as part of the bid documents
The tender schedules relating to the Mechanical works are to be signed and clearly identified as submitted
by the subcontractor and countersigned by the Contractor when submitted.
The tender schedules are to be supplied by the Mechanical Subcontractor and then incorporated by the
contractor as part of its tender and must be complete in all respects to validate the tender. An invalid
tender is subject to rejection.
All particulars requested in the tender form are required and alternatives, if any, are to be offered with the
bid. Tenderers shall submit tender forms in duplicate with their tender submission. The detailing
requirements and comments on information to be supplied and alternatives are set out in the following
sections relating to particulars of the specialist section of the work.
The following Subcontractors are selected for tendering this project to undertake the completion of the
works described in the specification and associated drawings.
The contractor may submit in writing for formal approval from the superintendent and consultant for the use
of an alternative Subcontractor for this section of the work, if it is deemed a benefit to the project quality
and value for money outcome.
The following drawings shall and must be referenced as part of the works described in this Specification.
- Inspected building and services documents and to have visited the site and informed themselves of
site and local conditions offering the contractor works and to have satisfied themselves as to the true
nature and extent of the works.
- Checked access to the site and ascertained local information required in preparation of the tender with
particular reference to access and systems to enable the execution of the works.
- Assessed the work, materials, plant and similar items necessary to carry out the true intent of the
specification and of the difficulties and hazards that will affect the execution of the works.
The submission of a tender shall be deemed to carry with it agreement to all the items referred to in the
specification and/or indicated on the drawings or inferred therefrom have been included to enable the
completion of the contract, works.
No consideration will be granted for misunderstanding or faulty assessment of the works to be done or of
the materials to be furnished or for lack of knowledge of the nature and conditions of the site.
As part of the Builders monthly Progress Claim submission, the mechanical progress claim break up sheet
must be included in this specification, Refer Section 07.27 of this section for the required format.
Progress claims will not be processed without this sheet being provided by the MSSC
Concrete bases and plinths for the mechanical equipment will be supplied and installed by the Builder at
no cost to the MSSC.
Galvanised steel edge surrounds and steel reinforcement as necessary shall be supplied and positioned
as part of this sub-Contract.
General
Provide detailed builders works shop drawings including, but not limited to; openings, building
penetrations, access panel requirements (particularly ceiling access panels) all as required to complete the
mechanical services installation.
The Builder shall provide all openings throughout the building in accordance with dimensional details
provided by the MSSC. Penetrations through structural beams shall not be permitted without written
approval from the Structural Engineer.
If openings, fixings, chases and similar items of work are wrongly located or omitted due to incorrect or lack
of information supplied to the Builder, the cost of any remedial works shall be paid for by the MSSC.
Penetrations
Penetrations through structural beams, walls or floors will be provided by the Builder.
Materials used for sealing penetrations shall be suitable for the purpose and shall comply with the
requirements of the relevant statutory Authority.
Holes in Roofs
The Builder shall provide roof openings with purlins trimming to all sides of the penetration to support the
roof material and the flashings and complete with under & over flashings, including kerbs as necessary, to
prevent the ingress of water and to accommodate the installation of plant and equipment.
The Builder shall provide under & over-flashings to each penetration to ensure a fully waterproof
installation. Suitable reinforcement to accommodate plant and equipment shall be provided.
The Builder shall provide all HGD roof platforms and associated screening, trimmed openings with
trimming to all sides of the penetration to support the plant and equipment.
Under supports shall be provided in the locations to the builders work drawings provided by the MSSC.
The Builder shall provide all access panels, door and ceiling penetrations and be responsible for co-
ordination of the doors and ceiling installation and commissioning of the Services located above the ceiling.
Progressive removal and replacement of ceiling during the commissioning period for access to equipment
will be carried out by the builder. Should subsequent access to the ceiling space be required due to
deficiencies attributable to the MSSC's installation, the MSSC shall pay all costs associated with removal
and replacement of ceilings.
All outside air grilles associated with the mechanical services systems shall be supplied and installed by
the MSSC. This is to include ember mesh with frame and to be removable for cleaning,
The MSSC shall supply all louvered door grilles to the Builder who will arrange for cutting and preparation
of holes in doors for the installation of grilles.
07.2.7 PLUMBING
The Builder shall provide waste points for disposing of waste water necessary for the operation of the
mechanical plant.
All final water connections to equipment and drains from equipment to the points of collection shall be
provided as part of these Contract works. All drains shall be arranged so that they can be rodded through
for cleaning.
Plumbing work carried out as part of these Contract works shall be undertaken by suitably qualified and
experienced Tradesmen, in accordance with the requirements of the relevant Authority.
07.2.8 ELECTRICAL
The Builder shall arrange with the Electrical services sub-contractor to supply, install and terminate
sub-main cables to all of the mechanical services switchboards.
The electrical services sub-contractor will make provision in each of the distribution boards including circuit
breakers for the power. Termination to the isolators, provided by the MSSC, shall be by the MSSC.
The electrical contractor shall provide power and wire terminations for all of the exhaust fans. Switching
shall be by the MSSC.
The electrical contractor shall take possession of the power meters from the MSSC and install them into
their boards.
Signals from the buildings security system for automatic shutdown of the plant in secure mode will be
provided by the security services subcontractor to terminal strips provided by the MSSC the Mechanical
Services switchboards.
The mechanical services systems shall be installed shut down when the building is secure and the systems
shall be able to operate during occupation.
The Builder will provide sufficient power for testing and commissioning the mechanical services works in
accordance with the agreed construction programme.
i) Provision of co-ordinated & detailed mechanical services & associated builders works shop
drawings.
ii) The supply and installation of the (VRV/VRF) heat recovery and inverter air conditioning systems.
This shall include stainless steel drip trays under condensing with drains, power isolators, wiring,
ductwork, discharge duct and protective mesh power coated to match roof, security shutdown,
flexible and rigid ductwork, air diffusion and grilles, pipe work, valves, controls and all ancillary
equipment necessary to satisfy the requirements of this specification. Power for the fan coil units
shall be derived from the MSSB.
iii) The supply and installation of the general ventilation systems. This shall include power isolators,
wiring, ductwork, ceiling grilles, door and wall grilles, flexible and rigid ductwork, controls and
switching and all ancillary equipment necessary to satisfy the requirements of this specification
The single phase fans must have speed controllers provided to enable the adjustment of volumes
to those specified. The speed controllers must be mounted in the ceiling space adjacent to the
fans.
Ceiling exhaust fan motors must be rated for continuous operation and bearings shall be of the ball
or roller type, sealed for life bearings. The fan shall have an inlet guard/face cover and a line of
sight/dust cover over (behind).
iv) The supply and installation of a full integrated Building Management System including but not
limited to BMS boards and Panels, with 13” inch touch screen within each MSSB, interconnecting
wiring, interface cards, wiring, sensors, controllers, awning window wiring and (Window) power
supplies, control and switching louvre switch panels, indication lights, interconnecting control wiring
and all ancillary items to satisfy the requirements of the specification, including termination,
sensors with tuning and testing.
v) Supply and installation of the building power meters, and associated interfacing with the BMS.
vii) Mounting of all of the wall controllers and sensors in their final locations.
viii) The manufacture, supply and installation of the two mechanical services switchboards shall be
located as shown on the drawings and shall contain run lights, fault lights, manual and automatic
switching, relevant contactors and relays.
Power will be provided to the boards by the electrical contractor, the final termination to the board
is by the MSSC.
The MSSB’s shall be fed from a single power supply and the board shall segregated the feed
between the air conditioning systems, ventilation systems, BMS and louvre relays and control.
The power supplies and controls for all of the equipment under this scope shall also be derived
from this board., including but not limited too;
- Building Management system.
- Condensing units and fan coil units.
- Fan coil units and outside air fans,
- Ventilation Fans,
- Extraction fans,
The boards shall include a terminal strip to pick up signals for the fire panel and the security
system, which will shut down the systems when activated.
ix) All testing and commissioning necessary for the completion and handover of the project.
x) Continuous quarterly tuning and logging of the system necessary for the completion and handover
of the project, including the testing of the system at the 12 month period for certification and for the
completed.
i) All roof mounted plant and equipment, including fans, cowls, conduits, ect, shall be finished to match
the roof colour.
ii) Supply and installation of relief air grilles, ducts and door grilles.
iii) All exposed ductwork, pipework and conduits are to be painted and concealed in a colour bond duct.
The duct colour is to match the mounting surface.
iv) Commissioning and testing of the systems installed during these works.
v) Three (3) sets of the Installation and Operations Manuals, including As Built drawings.
ix) Twelve (12) months warranty on workmanship for all new items.
x) The Contractor shall ensure all filters and equipment are left in a clean condition.
The work not included in the mechanical section but is to be provided by the main contractor/builder and
associated sub-contractors shall include;
Air tight ceiling voids throughout the air conditioned spaces.
Fire barriers.
All the access to enable the installation of the new pipe work, ductwork and air conditioning units,
Unit Structural support trimmers,
Plant area compounds and concrete plinths.
Access panels and hatches.
The access to enable the installation of the new pipework, ductwork and air conditioning units, unit
supports.
Ceiling penetrations for ceiling grilles.
Ceiling access panels
Wall and door penetrations for grilles.
Slab, wall and door penetrations for duct work, pipe work and grilles,
Trimmed roof penetrations and under flashing,
Equipment concrete plinths Metal surround provide by the mechanical contractor,
Condensate drains.
Power supplies associated with the execution of the mechanical contract work component.
The Builder shall provide water supplies and waste points for disposing of waste water necessary for the
operation of the mechanical plant.
All drains from equipment to the points of collection shall be provided as part of these Contract works. All
drains shall be arranged so that they can be rodded through for cleaning.
Plumbing work carried out as part of these Contract works shall be undertaken by suitably qualified and
experienced Tradesmen, in accordance with the requirements of the relevant Authority.
Signals from the fire detection and security system for the overriding control of Mechanical Services plant
in fire mode and security isolation of the building. The control cabling will be reticulated by the fire and
security contractor into a MSSB for use by the Mechanical Contractor in the shutting down of the services.
The mechanical contractor is to provide coordination and penetration drawings for use by the contractor.
The drawing are to be submitted for approval and are to be coordinated with the other trades and services.
07.4.1 GENERAL
The tender documents have been prepared for the guidance of the tenderers.
The MSSC shall guarantee that the performance of the equipment will be as specified. The quality of the
installation shall be in accordance with the Specification and good trade practice.
The MSSC shall advise of any anomalies in the system design, which may prejudice compliance with the
design criteria. Such advice shall be provided in sufficient time to avoid delays, should any changes be
required.
The Sub-Contractor shall prepare piping and ductwork pressure loss calculations to demonstrate selection
of pipework and ductwork does not exceed the specified maximum duties, selections and application.
07.4.2 SERVICES
The design criteria that would be used for the project is as follows:
Outside Air
7.5 l/s per person by the use of air filters which achieve 60% against no. 1 test dust for ducted units and
10l/s for cassette and wall split systems.
Exhaust Systems
AS 1668
07.4.3 STANDARDS
Materials, equipment and workmanship shall comply with the most recent documents published by the
Standards Association of Australia or where S.A.A. documents do not exist, the standards of the British
Standard Institute.
All material, equipment and workmanship shall comply with the requirements of:
- National Construction Code. BCA - 2016
- The Western Power Electricity Act.
- The Health Act.
- The Department of Occupational Health, Safety and Welfare.
- The Western Australian Fire and Rescue Board.
- The Health Department.
Together with all related Australian Standards and Codes including Local Authorities Regulations. All other
applicable Australian Standards and Codes not necessarily nominated above or not referred to by BCA
2015. All Codes and Standards are to be of the latest (current) edition
07.4.6 CHASING
Chasing shall not be permitted in columns and rammed earth walls. Conduits must be cast into location.
All required chases shall be made after checking with the Builder the proposed finish of the surface, to be
chased. Chasing shall be kept to minimum widths and depths but provide sufficient depth so that the
conduit is a minimum of 15mm below the surface after final rendering. All chases shall be completed using
a Carborundum disc saw.
The Builder will rendered walls when installation of conduits and boxes is completed and before plastering
commences in the area.
A limited amount of building-in to wall chases shall be carried out in order to retain conduits and wall boxes
in position.
Pipes greater than 25mm dia. Overall shall not be chased into walls unless directed otherwise in writing.
Pipes chased into walls shall be insulated for thermal reasons and to minimise transmission of vibration
into the structure.
The MSSC shall prepare, and submit for review, before commencing manufacture or installation, drawings
from which the subject works shall be built. No factory or site work, other than manufacture of standard
equipment or controls, shall proceed until such drawings have been reviewed and are deemed to be
satisfactory.
Drawings shall all be on the same size drawing sheets as the design drawings and shall be to a scale of
not less than 1:50.
- Reflected ceiling plans showing all air outlets, sizes, air quantities etc.
- Electrical schematics including proposed switching & thermostat locations and switchboards.
Drawings shall contain reference and required sizes to all Builders work and work required by other trades,
such as plinth dimensions, drain positions, sleeves, penetrations, ceiling access panels, electrical
terminations and the like, to enable the Builder to coordinate these requirements with the trades
concerned.
Submit each of the drawings in AutoCAD 2018 to the BMW CADD Drawings Standards drawing file format,
pdf & 2 hard copies for review and vetting.
Shop drawings are to be co-ordinated with other building & service elements & checked for spatial
requirements of equipment & services indicated diagrammatically in the contract documents.
The Main Contractor shall check and stamp the drawings prior to the submission to the consultants.
An allowance of 10 working days shall be for the consultant’s review of the drawings.
Note: The Main Contractor and Mechanical Services sub-contractor shall complete the “Drawing
Certification Checklist” (Reference Section 07.26), stamp the drawings prior to the submission for
review or approval.
This section deals with the equipment and materials to be supplied for this project.
General Requirements
The Heat Recovery (VRF/ VRV) air conditioning units shall be of a single manufacture. Daikin, Panasonic
or Mitsubishi Electric are the preferred or equivalent can be offered for approval.
General
The unit shall be reverse cycle type. The unit shall be fitted with all safety devices such as H/P, L/P
overload protection, safety condensate tray and return air filter. Separate 25 mm condensate line with ‘P’
trap and all necessary items to enable efficient, safe and serviceable operation. The unit shall be steel
construction finished with powder coat.
The local switching station shall have fault and run indication.
Casing
The casing shall be fabricated from 1.6mm thick galvabond or zincanneal sheet folded to form panels to
accommodate the thickness of the thermal and acoustic insulation. The outside surface of the casings shall
be flush without external framing. Panels shall be adequately braced and effectively sealed at joints with
gaskets.
Access panels shall be provided to allow full and easy access to all internal areas. Access panels shall be
fabricated to that specified above and shall be fitted with weather resistant latches for ease of removal.
Fans and motors shall be selected to provide air flow rates of 10% more than that specified against the
corresponding increased system resistance. Fan discharge velocity at design air flow shall not exceed 9
m/s.
Bearings shall be self aligning ball or roller type fitted with lubricant retaining and dust excluding seals and
shall be selected for an operating life of not less than 100,000 hours. Bearings shall be accommodated in
grease relief housings and shall be lubricated through grease ripples situated in readily accessible
positions.
Coils
Condensate Tray
To comply with AS3666, have a minimum 50mm turn up edges, drain connection is not to be less tan
25mm and have a lip on the leaving edge to prevent carry over.
Insulation
The entire casing shall be acoustically insulated with minimum 25mm thickness fibreglass or nitrile rubber
insulation having a density of not less than 48 kg/m3. The insulation shall be faced with perforated foil
laminate sheet and shall be retained by non piercing fixings.
Access panels and separate joints shall have not less than 25mm edge return of surface material.
Condensers shall have sufficient heat rejection capacity to maintain the saturated refrigerant condensing
temperature not higher than 13K above design ambient dry bulb temperature.
Condensing coils shall be copper tube Aluminium fin type. Sub-cooling circuit is required to give a
minimum of 6.5K sub-cooling. Coils shall be tested to 2800 kPa and guaranteed for 2200 kPa working
pressure.
Condenser fans shall be direct drive, fully balanced fitted with removable safety guards. Fan shafts shall be
corrosion protected. Permanently lubricated bearings shall be provided.
Casings shall be manufactured from galvanised sheet steel. Support legs, framing and structural members
shall be formed from 3mm minimum thick steel and unit panel covers etc from 1.6 mm minimum thick sheet
steel. All casing shall be baked enamel finished. All fixing used in the unit manufacture must be corrosion
resistant.
Fins shall be fabricated from aluminium and be mechanically bonded to the primary surface.
End plates and frames shall be constructed from galvanised steel sheet or aluminium.
Compressor/s shall be of the hermetic type operating on non-toxic and non-inflammable refrigerant.
Compressor/s are to be of the high speed multi-cylinder or helical screw type operating at 48 r/s maximum
speed.
Compressors shall be protected from short circuit by phase failure relays etc.
General
Fans shall be of approved manufacture of the in-duct diaphragm, wall or roof cowl mounting type. Fans
and motors shall be selected to provide air flow rates of 10% more than that specified against the
corresponding increase in system resistance.
Fans shall be selected for a minimum total efficiency of not less than 65%
Construction
Fans shall have cast aluminium or pressed mild steel blades mounted in hubs and complete with brackets.
General
The units shall be totally sealed missed flow or axial flow fans housed in a compact base fitted with a
curved contour.
Fans and motors shall be selected to provide air flow rates of 10% more than that specified against the
corresponding increase in system resistance.
Construction
The units shall be steel casings, stiffened and braced. All rotating parts of the units shall be isolated from
the unit casings by approved resilient mountings.
Fans/Motor Assembly
Fans motor bearings shall be of the ball or roller type, sealed for life or grease packed fitted with lubricant
retaining and dust excluding seals extended to an accessible location, and shall be selected for an
operating life of not less than 100,000 hours.
Fan motors shall be positioned above impellers to allow servicing from above the roof.
Be capable of exhausting the air quantities nominated on the drawing against the resistance of the
installed system.
Fan shall be centrifugal and motors must be rated for continuous operation and bearings shall be of the
ball or roller type, sealed for life bearings. The fan shall have an inlet guard/face cover and a line of
sight/dust cover over.
The fans shall include a shutoff damper that closes when the fan is not operating.
General
• Motors shall be continuously rated squirrel cage metric induction type selected to be non-
overloading at all operating conditions.
• Shall comply with AS 1359 and AS 1360.
• Motors shall be designed to operate on either 415 Volts 3 phase or 240 Volts single phase supply
+ 6% 50 Hz.
• Motors shall be suitable for direct on line starting and shall have minimum Class B insulation and
rated for Class B temperature rise.
• Smoke control motors shall have totally enclosed fan cooled enclosures with Class H insulation, in
accordance with AS 1688 and the requirement of the relevant statutory Authority.
• Class F and Class H insulated motors shall be provided with high temperature leads and terminals
and the bearings packed with high temperature grease and guaranteed for operation at the
specified duty.
• Bearings shall have a minimum service life of 100,000 hours continuous operation.
• Motors up to and including 15kW shall incorporate permanently lubricated ‘sealed life’ bearings.
• Lubrication points and shall be provided for greasing with the motor in operation.
• Motors shall be selected for a minimum efficiency of not less than 90% at design duty point and
70% at 10% load
07.7.1 GENERAL
All air diffusers, air registers, louvres, exhaust air grilles, door relief grilles, supply air grilles and all other
such fittings shall be of SW Hart or Variflow manufacture only.
Provide N.A.T.A., A.D.C. or equal approved certified performance data for all air diffusion equipment to be
installed. Performance data for similar but not identical equipment will not be accepted.
All outlets shall be selected for efficient air distribution and low noise levels and it is the MSSC's
responsibility for selecting and checking neck velocities, horizontal and vertical flow patterns and noise
levels. Outlets with poor distribution and excessive noise levels shall not be used.
All outlets selected for variable volume systems shall be suitable for the system and shall be capable of
providing adequate distribution without causing draughts at high volume or 'dumping' at low volume and
shall only be used if manufacturer's have specifically tested them for variable volume systems.
All slot diffusers, linear grilles and light air saddle diffusers shall have provision for air pattern adjustments
such that air can be deflected in a vertical or horizontal direction.
- Be supplied and installed in quantities, sizes, types and locations shown on the project drawings.
- Be free from distortion, bends, surface defects, irregular joints, exposed fastenings and operating
vibration.
- Where specified to be manufactured from steel shall be finished in enamel or powder coat to the
Architect's choice of colour.
- Where specified to be manufactured from aluminium shall be finished in enamel, powder coat or by
colour anodising as chosen by the Architect.
All air distribution equipment shall be selected and installed to eliminate the formation of condensation.
- Have frame profile dimensioned to suit the ceiling module and type.
- Have metal cores which are easily adjusted to set throw to suit the floor to ceiling height without
disturbing the outer frame.
- Have frame profile dimensioned to suit the ceiling module and type.
- Have metal PCD cores which are easily removed without disturbing the outer frame.
− Louvres and frames to be powder coated to the architects selected colours or provide matching
aluminium jamb, still head flashings as documented and as required.
− Provided fixed black stainless steel woven framed and removeable ember mesh.
− Provide matching aluminium plate behind unused section of louvre (where mechanical
ductwork/piping does not connect) and seal. Builder to provide additional thermal panels.
− Neatly mitre continuous louvres at 90° and provide end concealed fixing clips to support corners
− louvres at 90° and provide end concealed fixing clips to support corners
Note:- Samples of all grilles must be submitted for approval prior to ordering or manufacture.
07.8.2 GENERAL
- Include all traps, separators, double risers, heaters, reservoirs and controls as necessary to provide and
maintain efficient compressor lubrication.
Piping shall be free from defects and have a chemical composition complying with AS1571.
All straight lengths shall be supplied in H temper. All coils shall be 0 temper.
Wall thickness shall be selected in accordance with the recommendations of “Kembla” and “Crane”, “Safe
Working Pressures” for the refrigerant used and a design tensile stress of 65oC for discharge and liquid
service and 45oC for suction lines used in cooling only circuits.
Where refrigeration grade tube is not available, the circuit shall be installed using copper piping in
accordance with AS1432 using fittings with wall thickness equal to the pipe wall.
Where piping to AS1432 is used the pipe and fittings shall be carefully cleaned.
- Be continuously fed with inert gas internally during welding operations and left with welded ends and
"Schaeder" valves. Leave holding charge of inert gas after testing. Ensure tails are of sufficient
length for final connection.
Providence Christian College – Stage 1 18 January 2021
DSA Job No. 6182 Revision 0
0700 MECHANICAL SERVICES
- Be supported by a proprietary system of hangers and clamps located in accordance with the following
table:
0 – 10 1,500
12 – 40 2,000
40 - 3,000
- Be installed in full straight lengths at right angles or parallel to the building structure.
Where pipes of dissimilar diameters are grouped, the smallest line size sets the hanger spacing.
In all situations where changes of direction or elevation occur 45o or 90o bends shall be made using only
mechanical pipe benders or wrought copper fittings.
Have split lengths of UPVC class 6 piping protecting insulation for pipe sizes 10mm diameter and smaller.
Have “Aeroflex”, “Aerofix” hanger blocks for pipe diameters of 10mm or greater.
- Be made by silver soldering using a minimum of heat, rod and non-corrosive flux.
- Be of the spigot and socket type and in continuous runs. The minimum insertion length shall be 10mm.
- May be of the flared type for piping below 6mm nominal diameter. Flared joints may be used up to
20mm nominal diameter.
07.8.6 FITTINGS
Fittings shall be of the wrought copper type for elbows, tees, reducers, sleeves, etc. of wall thickness equal
or greater than the associated pipe.
- Be "Aeroflex" with the thickness complying with the requirements of BCA 2016.
- Be fire rated where penetrating through fire or smoke rated wall to BCA regulations ensuring that a
vapour barrier is maintained.
- Have joints glued with an adhesive recommended by the manufacturer of the insulating material.
- All joints shall be protected and sealed by “Aeroflex Protape” in a workmanlike manner.
- Final connections to units shall have insulation painted with a UV protected paint compatible with the
insulation.
- Be charged into machines cleaned and dehydrated to standards recommended by the manufacturer.
An operating charge of refrigerant shall be proved with each machine and additional refrigerant shall be
provided to maintain the operating charge during the 12 months defects liability period.
Installation
Pipe underlay: Bed piping on a continuous underlay of bedding material, at least 75 mm thick after
compaction. Grade the underlay evenly to the gradient of the piping.
Chases: If necessary, form chases to prevent projections such as sockets and flanges from
bearing on the trench bottom or underlay.
Other services: Separate underground piping from electrical cables and other services by ≥ 300 mm.
Pipe surrounds
General: Place the material in the pipe surround in layers < 200 mm loose thickness and compact
without damaging or displacing the piping.
Protection: Lay continuously concrete tiles > 25 mm thick, or PVC tape at least 3 mm thick, in the
overlay, 50 to 75 mm clear of the piping, for the length of the piping.
Warning tape: During backfilling lay plastic warning tape 300 mm above buried piping, for the full length
of the piping.
07.9 DUCTWORK
07.9.1 GENERAL
Ductwork shall:
- Be manufactured in sizes shown on the drawings. All sizes are clear airway sizes.
- Be delivered to site covered, stored off the ground or slabs and protection provided to internal surfaces.
- Not leak.
All internal perimeter surfaces of ducts as indicated on the project drawings shall be lined with insulation.
Insulation shall:
- Comply with BCA 2016 or 50mm thick as required on the drawings, whichever is greater.
- Have insulation installed proud at each cross joint to provide compression on assembly.
Shall:
- Be perforated "sizalation" except for the evaporative cooler and canopy exhaust systems.
- Be applied to the exposed face and lap 50mm over the edge onto the back surface of the insulation
board.
Shall:
- Be spaced at 300mm maximum centres and so that there are at least two rows of pins per side of duct.
- Be of a length selected to firmly retain insulation without compressing the batt by more than 5mm.
General
Sound attenuators shall be installed into ductwork and masonry risers where shown on the drawings.
The sound insertion figures and pressure loss for the attenuators offered shall be based on figures tested
in a laboratory registered with N.A.T.A. and in accordance with Australian Standard AS1217-1983.
Certified results of this figures may be required.
Construction
The attenuators shall have the outer casings constructed from the following galvanised sheet thickness:
Width/height up to 1100 mm 1.2 mm thick
over 1100 mm 1.6 mm thick
The attenuators shall be fitted with galvanised angle end flanges, as follows:
Width/height up to 600 mm 25x25x3
900 mm 32x32x3
1200 mm 38x38x3
1500 mm 51x51x5
over 1500 mm 51x51x6.5
The casings shall have either Pittsburgh lock seams or welded joints. Welded joints shall be painted to
prevent corrosion.
The splitters shall be securely mounted into the casing on an equal module to suit the case width.
The splitters shall have a matt faced fibreglass sound absorptive fill which is held inside a perforated
galvanised steel skin. The galvanised steel skin shall be securely attached to the splitter or casing to
prevent movement in the air stream.
The splitters shall have Aerofoil shaped inlet and outlet surfaces to minimise pressure drop.
The attenuator shall be externally insulated with 50 mm thick fibreglass and sisal vapour barrier either on
site or at the factory. The insulation shall be secured with steel pins.
Regenerated Noise
The splitter module shall be sized so as to keep channel velocities low and minimise pressure drop.
Channel velocities shall be such as to prevent regenerative noise from exceed NR35.
Installation
The attenuators shall be handled and transported in such a manner as to prevent distortion and damage to
the casing and splitters. Plastic sheet covers shall be installed on the open ends to prevent the ingress of
water and dust during construction.
The attenuators shall be installed through the plant room walls. The holes in the walls shall be sized so as
to allow for the installation of end flanges, through the wall.
The gap around the attenuator shall be packed with semi-rigid fibreglass batt and then with loose
fibreglass held in place with a galvanised sheet steel angle trimmer to prevent noise breakout. The air
conditioning contractor shall install this packing.
The air filters for the project shall be as specified below. All filters must comply with AS 1132.
- Have efficiencies of 80% to no. 4 dust, 70% to no. 2 dust under AS 1132 for the main filter. These filters
shall have a metal frame and replaceable media.
The outside air shall be filtered prior to the entry to the system. The filter shall:
- Have efficiencies of 80% to no. 4 dust, 95% to no. 2 dust under AS 1132 for the main filter to achieve
the outside air rate of 7.5l/s per person. This filter shall be metal frame with disposable media.
- Be fitted with a pre-filter of extended surface with efficiencies of 70% to no. 4 dust. This filter is to be
washable.
07.11 ELECTRICAL
07.11.1 GENERAL
The electrical installation shall be in accordance with the current Regulations and requirements of the local
Supply Authority, and with the relevant SAA Specifications and Codes, in particular AS 2430, AS 3000 and
AS 3003. The installation shall be suitable for the application and provide for satisfactory operation, control,
maintenance and safety of mechanical plant and equipment.
All equipment shall be designed so that interference will not be caused with any electronic transmitting or
receiving equipment in the same locality, including any control equipment associated with any air
conditioning plant and other similar installations.
Separate earthing conductors shall be installed for each outgoing circuit and switchboard gland plate,
originating at the earth bar in the associated switchboard.
All electrical equipment, wiring and fittings shall be of best quality, and, within their respective type, of the
same manufacture throughout the installation.
Steel conduit shall be used in trafficable areas and shall be heavy gauge welded galvanised with screwed
connections complying with AS 2052 of 'GALCON' or approval equal manufacture.
Rigid PVC light duty or heavy duty conduit shall be of the high impact, self extinguishing type, complying
with AS 2053.
Flexible conduits shall be PVC complying with AS 2053 using terminators of approved manufacture, or
heavy duty corrugated PVC conduit and screwed male thread glands complete with conduit locking ring.
The length of flexible conduit shall allow movement of the plant item for normal service adjustment.
Cable troughs for power and control wiring may be used in plant rooms, accessible rising ducts or
accessible ceiling or roof spaces. Cable troughing shall be sized and have derating factors applied in
accordance with AS 3000 and AS 3008, with cables laid in the trough in straight runs avoiding crossovers
wherever possible cables for individual three phase circuits shall be taped together at intervals not
exceeding 5m and control cables shall be taped together with a maximum of 10 cables in any one
grouping.
Rating
All conductors shall be continuous between their terminal points and all cables shall have stranded copper
conductors unless otherwise specified.
Power circuit conductors shall have a minimum effective area equal to 2.5mm2 (7/0.67) and field control
wiring shall have a minimum effective area equal to that of 1.5mm2 (7/0.5). DDC and other electronic
equipment field wiring shall have minimum effective area not less than 0.88mm2 or as recommended by
the controls supplier, whichever is the greater. Earthing conductors shall be not less than 2.5mm2 (7/0.67).
Flexible conductors may be used in switchboards and shall be not less than 1.0mm2 (32/0.20), except that
cabling associated specialised electronic equipment may comprise 0.5mm2 (16/0.20) flexible, terminated
at an intermediate terminal block, mounted adjacent to the devices. Normal switchboard cabling shall then
be extended as required from this terminal block to other items of switchgear in the board.
Control cables operating at extra low voltage shall be selected for minimum 6% voltage drop.
Identification
Cables and conductors shall be colour coded. Red, white and blue shall be used for the three supply
phases, black for neutral circuits, green/yellow for earthing cables and orange, violet or other approved
colour for control circuits. All terminals and each end of each control wire shall be numbered. All numbers
shall be indicated on drawings.
Cable trays and gland plates shall be provided to facilitate sub main connections.
Where cables are installed vertically, an approved method of clamping shall be provided to support the
cable without damage to the insulation, at intervals not exceeding 7.5m.
Field cable joints will not be permitted, except where the length of the cable run exceeds the maximum
manufactured cable length. Cables shall be joined using the manufacturer's recommended procedure and
equipment. Locations of cable joints shall be to approval, and the location of any joints clearly marked on a
drawing.
Minimum bending radius for all cables shall not be less than 6 times the overall cable diameter.
Extra low voltage control cables including DDC cabling, shall be installed strictly in accordance with the
manufacturer's recommendations. Shielded cables shall be earthed at one end only (at the controller not
the sensor). Cables shall be segregated from power cables by a distance of 250mm minimum and
enclosed in separate conduits or as otherwise directed by the manufacturer such that induced stray
voltages are prevented from affecting the operation of the controls under normal and abnormal conditions.
PVC cables for switchboards and for field installation shall be minimum V75 0.6/1 kV single PVC insulated
stranded conductor of CMA, Olex or other Australian manufacture to AS 3147.
PVC insulated and PVC sheathed (PVC/PVC) cables shall be minimum V75 0.6/1 kV stranded conductor
of CMA., Olex or other Australian manufacture to AS 3147 and AS 3191.
Cables shall run straight for at least 300mm immediately prior to entering switchboards and other
equipment.
Multicore cables containing a maximum of three power conductors and one earthing conductor may be of
flat configuration. Cables containing four or more power conductors shall be of circular configuration or
other approved type.
07.11.7 SWITCHBOARDS
General
All new equipment to switchboards shall be strictly in accordance with the relevant Sections of AS 1136
Switchgear and Control Gear Assemblies suitable for 415/240 Volts 50 Hz operation with a minimum
Degree of Protection IP54 Safety Measure 1, with Construction Form 1 unless otherwise specified.
Switchboards shall incorporate all necessary starting arrangements, facilities and accessories.
Clearance between the switchboard and fixed obstructions shall be strictly in accordance with AS3000.
Cable entries shall be readily accessible when the switchboard is in its installed location.
Transformers supplying extra low voltage for control interlocks and other equipment shall be double
wound, and adequately rated for their duty.
The primary and secondary terminals shall be physically separated and clearly marked. HRC fuse
protection shall be provided in the secondary circuit. Where the transformer rating exceeds 300 VA a
separate primary fuse shall be provided. For transformers rated at 300 VA or less, the primary may be
connected to the common control circuit fuse where applicable. Cabling from the secondary winding to the
control circuit fuses shall be rated for full secondary current.
Terminals
All outgoing control circuits shall be connected to tunnel type rail mounted terminals similar to Sprecher
and Schuh VR series or equal approved.
Each switchboard shall be provided with separate earth and neutral bars of adequate cross section and
length to accommodate all earth and neutral cables associated with the circuits controlled from that
switchboard.
Labels
All components shall be labelled with white traffolyte labels machine engraved with black lettering.
Minimum letter size shall be 3mm. Labels shall be fixed with screws mounted on stand off supports, so that
labels are in front of equipment wiring and clearly visible. Labels shall not be fixed to removable cable duct
covers, etc.
All contactors, motor starters, fuses and relays, etc. shall be panel mounted within the cabinet, front
connected and front wired.
Equipment shall be logically grouped in sequence and labelled. Equipment operating at 24 Volts 50 Hz
(contactor coils etc.) shall be mounted on a separate section of the panel, segregated from the 240 Volts
50 Hz equipment by location, with each section shall be appropriately labelled.
Gland plates for cables shall be of 6mm minimum thickness brass drilled to accommodate all incoming and
outgoing cables.
All wiring shall be run and neatly clipped. Special wiring channels, clips and lugs suitable for switchboard
use shall be used in all cases.
Terminal blocks and contactors shall be numbered using proprietary brand machine printed number tags.
Control wiring shall be numbered at each end, using Critchley Type Z slip on cable numbers or similar,
sized to fit firmly over the cable. Stick on numbers or hand written numbers will not be accepted.
All control cables entering or leaving the switchboard shall be brought to numbered terminals.
Switchboards and control panels shall be adequately protected, to avoid damage to paint work and
components. Damaged paint work shall be neatly touched up to match the original finish.
General
Controllers shall be suitable for continuous operation at full load in an ambient temperature of 45oC and a
maximum storage temperature of 60oC.
Enclosures shall be I.P.54 with forced draft ventilation, self contained. Filter fans assemblies are not
acceptable.
An isolating contactor shall be connected on the load side rated for the appropriate duty. Frequency
converter shall be capable of switching on the output without sustaining damage.
Each controller shall be selected on the basis of maximum motor full load "nameplate" Amps and not motor
kW rating.
Output voltage and frequency levels shall remain constant at any given speed setting when supply voltage
varies by not more than + 10%.
Minimum efficiency shall be 96% at the duty point and 85% at 10% of design flow and 30% of design
speed.
The output frequency shall remain constant regardless of load variations or supply frequency variation of +
1.5 Hz. Output frequency shall remain stable throughout the ambient temperature range of 0oC to 45oC.
Each controller shall be protected with suitably rated fuses or circuit breaker on the input side, selected to
provide protection of the controller and associated drive.
The variable frequency power and logic unit shall be solid state, continuously rated with micro processor
based drive logic, transforming input power into frequency and voltage controlled output power, for direct
connection to a standard squirrel cage induction motor, providing positive speed and torque control.
Speed control shall be stepless throughout the speed range under variable load conditions. Frequency
control shall be via pulse width modulation generating a clean sine wave with an operating power factor of
0.96 or better throughout the entire speed range. Power transistor devices shall be used in the output
stage.
Speed controller and motor shall be carefully selected and entirely compatible with each other, to provide
smooth operation over the whole speed range and without objectionable noise. Skip frequency functions
may be used to avoid resonance noise.
The controller shall accept at least two selectable switched inputs to override the speed control signal and
run the controller at a fixed manually adjusted speed.
The following safety protection features shall be provided as a minimum requirement, allowing the
controller to shut down without component damage.
Current limit: To prevent over current tripping due to momentary overload conditions and allow continued
operation (adjustable 110% to 150% of inverter rating).
Over current: When output current exceeds 110% then any speed change shall be halted until the current
drops below 110% when speed change will again be implemented. The controller shall not be damaged by
an output current of up to 150% rating.
Short circuit/instantaneous over current trip: On short circuit or instantaneous over current, the controller
shall shut down.
Earth fault protection: Phase to earth short circuit protection shall shut down the controller on fault.
Under and over voltage trip: Trip when input line voltage drops 15% below rated input voltage or when the
dc bus voltage exceeds 150% of nominal output voltage. On sustained power loss, the controller shall shut
down and upon return of power, the system shall automatically return to normal operation.
Momentary power loss: The controller shall shut down and upon return of power automatically return the
system to normal operation being capable of restarting a rotating motor immediately and regain positive
speed control.
Over temperature trip: The controller shall shut down when operating temperatures exceed safe operating
limits.
Automatic reset and restart: Restart to commence when any under voltage, over voltage or over
temperature condition is restored to normal. The number of restart attempts shall be limited to five restarts.
Automatic reset and restart attempts after an over current condition shall be limited and if a restart does not
occur on the last attempt, the controller shall shut down and require manual reset.
Signal isolation: Current and voltage signals shall be isolated from the logic circuitry via optic isolators.
The frequency output shall be controlled from an input signal derived from DDC or an electronic controller
as appropriate. Interface devices shall be directly compatible and liaised with the supplier.
The controller shall have internal manual adjustment allowing presetting of maximum and minimum speeds
with the limits maintained regardless of the input signal.
The controller shall include an 'auto-off-manual' function and a manual speed adjustment device supplied
by the manufacturer integral with the controller to allow testing and commissioning of the unit. In the
manual mode the automatic speed control signal shall be locked out.
Status Indication
Status indication light emitting diodes or panel display shall be provided for the safety, protection and
operating controls specified, located on the controller. In addition, indication for power on, speed and drive
enabled shall be provided.
Voltage free contacts shall be provided for connection of alarm signals, with contact closure on any fault
condition occurring in the unit.
Each VFD shall be interfaced to the BMS for energy monitoring and programming and have an inbuilt,
BMS addressable, non volatile kWh meter function for input power with a documented accuracy of better
than or equal to 2%.
Motor Overloads
Overloads (and thermistor protection where applicable) for each motor shall be provided within the
controller, to protect the motor and controller at all operating speeds.
Interlock Signals
All external interlock signals as required to operate the controller, shall be connected to terminals on the
controller, with the controller internally wired to suit.
Engineering Back Up
A complete technical engineering service and spare parts facility shall be available locally, with service and
reinstatement of the controller to full working conditions following a failure, guaranteed within 24 hours
The installation of the controller shall be carried out strictly in accordance with the manufacturer's
recommendations. The controller supplier or a trained representative shall attend site to properly set up
and adjust the controller at time of commissioning to ensure optimum performance and ongoing trouble
free operation and clearly document all internal set points for speed, ramp times, etc. following final
adjustment.
DDC INTERFACING
A separate terminal strip shall be provided in each switchboard for connection of DDC interface cabling.
Terminals shall be segregated from other terminals in the same panel.
Contacts for monitoring of status and alarm conditions shall be potential free and incorporate a "wiping"
action to provide a consistently very low contact resistance compatible with the extra low voltage
monitoring supply from the DDC.
Control output from the DDC will be via voltage free contacts. Interface relays shall be mounted within each
switchboard and controlled direct from the DDC at 24 Volts 50 Hz. Relay coil current and relay
characteristics shall be completely compatible with the DDC system.
Interface connections shall be individually connected to terminals (that is, two connections per item). Any
looping required for common connections shall be made at the terminal strip. All DDC point numbers shall
be shown on the wiring diagrams consistent with the DDC numbering system.
07.11.12 METERS
Mechanical Services the building Distribution Board kWh Meter with high level interfaces to the BMS shall
be provided to identify energy usage for the following load components:
General
This Section covers the supply and installation of the automatic controls for all systems, plant and
equipment to be incorporated into the Building Management System.
Controls shall be of approved manufacture and shall be of the same type and manufacture throughout the
project. Hybrid systems are not acceptable.
Proprietary control systems that can be used within this project are:
Innotech
Reliable via (Thorn Electrical)
Unless otherwise approved all controls shall be supplied, installed, tested and commissioned by the
controls manufacturer or supplier. All personnel engaged in this work shall be fully trained and experienced
in this field.
Responsibility shall be accepted for the design, selection of controls equipment, quality of the equipment
and performance of the controls installation. All controls shall be capable of operation within the specified
ranges and tolerances.
The control systems shall be complete in all respects and shall have all items such as, thermostats, relays,
interlocks and the like as necessary for the safe and correct operation of the plant in line with the functional
description.
Unless otherwise specified all adjustable controls such as thermostats, humidistats etc. shall be provided
with lockable covers to prevent tampering.
Where temperatures, set points, time delay periods and other criteria are nominated, the values shall be
treated as indicative only. All such settings shall be adjusted for optimum performance at the time of
commissioning and noted in the operating instructions and commissioning records.
No instruments or control devices shall be located where they will interfere with the operation or removal of
equipment, nor shall conduits or piping be run so as to interfere with the access to any equipment.
Supply and install complete automatic Building Management System for the building which will include the
following mechanical services system operations:
Provision of a Note Book computer to use by the College and service use.
Control, monitoring of the VRV/VRV and split systems through high level interfacing.
• Local switching and time control of exhaust systems, main plant and equipment and all other
ancillary equipment including optimised start/stop for the A/C plant.
• High Level interfacing of the VRV systems controls to the BMS for centralised control and
monitoring.
• High level interfacing and control of the spilt systems through the BMS for centralised control and
monitoring.
• Wiring and control of the exhaust systems including but not limited to the, tea prep, store and
cleaners room exhaust systems
• Provision for monitoring and of the normal external lighting, security and emergency lighting.
• Secure, remote WEB access facilities to ensure the entire system including monitoring, reporting,
trending and control is accessible via internet access using a standard web browser.
The comprehensive commissioning, tuning and testing of the system, system functions and
operation. Logging and tuning shall be quarterly with performance testing with reports and
documentation at practical completion, quarterly and final completion to ensure the Four Star/Green.
Secure, remote access facilities to ensure the entire system including monitoring, reporting, trending
and control is accessible via internet access using a standard web browser.
The comprehensive commissioning, tuning and testing of the system, system functions and
operation. Logging and tuning shall be quarterly with performance testing with reports and
documentation at practical completion, quarterly and final completion to ensure the Four Star/Green
Star is attained.
Operator interface to the system DDC controllers access control interface, emergency lighting system to
enable display of system point and alarm information.
Programming of controllers.
Computer
A Notebook computer (to approval) shall be used as the central computer which is provided to provided in
the lockable cabinet for monitoring, reporting and control on site and data backup purposes.
Software
The central computer (CPU) software shall be tested and commissioned by the Contractor. The software
shall be "user friendly" and incorporate interactive (question and answer) programme techniques to allow
programming and operation by staff who are not trained Computer Operators.
The operator interface software shall incorporate English language descriptors and message and menu
driven displays. All programming (changing set points, adjusting time programmes and such) shall be
performed, on line, without affecting the operation of the system.
OPERATING SYSTEM
The operating system (OS) shall provide control over the operation of the central processing unit and shall
be a product of, and supported by, the CPU manufacturer.
The operating system shall be responsible for scheduling all programmes for execution and shall support a
multi-tasking programme environment which provides for the concurrent execution of multiple real-time
programmes and programme development.
The system shall incorporate a multi-user capability such that multiple operations for multiple input/output
devices shall be able to concurrently issue commands to the running system programme.
A foreground/background structure shall be provided to allow the real-time control and operator interface
programmes to run in the foreground while programme assembly, compiling, debugging and loading
executes in the background.
The OS shall manage a scheme of storage protection which will enable background activities to proceed
without affecting the operating system or real-time programmes. Such protection shall prevent accidental
modification of the OS or real-time programmes resulting from execution of any background activities.
The OS shall include a real-time clock which shall maintain time of day, date and timer information.
When a power failure occurs the CPU shall be shut down in an orderly manner. When power is restored
the CPU shall automatically execute a "bootstrap" routine which shall restart the system.
The CPU shall automatically restart after the occurrence of an event that halts operation. During the restart
procedure the contents of the semi-conductor (RAM) memory shall be stored in a disk file for subsequent
printing and analysing to determine the cause of the failure.
All system transmissions (to either field devices, peripherals or mass memory units) shall be checked for
errors (using an approved error detection and correction technique) and records of such errors shall be
maintained in the system memory.
A failure of any transmission data path shall be audibly annunciated on the system operator's terminals.
SYSTEM ACCESS
Operators shall gain access to the system by "signing on" to a particular operator's terminal. Sign-on shall
be achieved by entry of a unique (to each operator) password and/or identification code.
Each operator shall be assigned a system access level which will enable that operator, once signed on, to
access only those command and programme functions which have an equal or lower access level. A
minimum of three access levels shall be provided.
Only the highest access level shall enable assignment or reading of operator passwords (and/or
identification codes). The system shall support a minimum of twenty separate operators.
The system shall record (in mass memory and optionally on a selected printer) each sign-on activity.
Terminals shall automatically sign-off after a pre-set (adjustable 1 min to 24 hours) time if no keyboard
activity has occurred. In addition, operators shall be able to manually "sign-off" when leaving the terminal.
ALARM PROCESSING
Alarms shall be displayed on the visual display terminal when they occur.
Two levels of alarm shall be provided 'urgent' and 'non urgent' (warning). The type of alarms are described
below:
Urgent Alarms
Equipment failure and hardwire faults
Status mismatch
Communication faults
Sensor or device faults (including open circuits)
Temperatures beyond preset limits
Pressures beyond preset limits
Carbon Dioxide levels beyond preset limits
Refrigerant and water leak detection alarms
Non Urgent Alarms (Warnings)
Temperatures vary from setpoint
Pressures vary from setpoint
Manual over-ride of BMS points
The alarm display shall "flash" and an audible alarm sound until the alarm is acknowledged. Upon
acknowledgment, the display shall steady and the audible alarm be silenced. In the event of multiple
alarms the most recent, highest priority, alarm shall be displayed on the terminal. Once the first alarm is
acknowledged the next alarm shall be displayed (and the audible alarm re-energised) and so on. Alarms
shall "scroll" onto the terminal in this manner until all alarms have been acknowledged.
Alarm messages shall remain active until acknowledged by the operator (ie. they shall not be overwritten
by a return to normal unless they have been acknowledged).
Each change of state (COS) message shall include the time of occurrence of the activity.
Alarms shall be printed on the printer as they occur. (Unless a report printout is in progress in which case
they shall be held and printed upon completion of the report).
In addition, it shall be possible to assign alarm messages which are displayed whenever a system alarm
occurs. Alarm messages shall consist of a minimum of 36 alphanumeric characters.
Each alarm display shall include the point descriptor, alarm message and time of occurrence of alarm.
Each point shall also be assigned an appropriate engineering unit (eg. temperature oC). All engineering
units shall be S.I.
Points as referred to in this clause shall include inputs and outputs, parameters, calculation results and
other hardware or software points.
OPERATOR'S TERMINAL DISPLAYS
Colour graphic visual display units shall include a dedicated change of state area at the top of the screen
(for display of change of state information and alarm action messages) and a header with the current date,
time and operator (if the terminal is "signed-on") displayed.
The balance of the display shall be used for programming, display of system reports and similar functions.
STATUS DISPLAY AND OVERRIDE
A status display programme shall facilitate display of the status of all points in the system.
The display shall include point identification and current status of value, dynamically updated.
The points to be displayed shall be selectable by the operator using individual or group point descriptors.
In manual mode it shall be able to command binary outputs to be On or Off, position analogue outputs to
any value between 0 and 100% and set analogue inputs to any selected value.
The status display shall indicate whether the points in manual or auto mode and shall reflect operator
commands
COLOURGRAPHIC VISUAL DISPLAY UNIT OPERATION
The colourgraphics shall incorporate instantaneous updating of dispersed real-time data and shall provide
an effective means for the operator to relate to the field. Full alphanumeric shall spell out in plain English
any condition, value, or action to be taken. Each graphic shall incorporate up to 40 freely assigned
connected or calculated points, shall be constructed and stored in the CPU mass storage units, ready to be
displayed. All dynamic data points shall be positioned to their respective location on the static portion of
the graphic.
Graphics and all related dynamic data display points shall be keyboard programmable without interfering
with the on-line operation of the system. As with the non-graphic mode of the terminal, an interactive,
conversational mode shall be used to construct graphics data files and to display them.
The programmable colourgraphics shall have dispersed dynamic data providing real-time system
information. These diagrams and variable system data shall be viewed simultaneously on the dedicated
work space section of the terminal screen. A system diagram associated with a point in alarm shall be
indexed from the dedicated alarm section of the screen and displayed by activating a Command Function
via the keyboard or (as a programmable option) automatically on receipt of an alarm. Symbols and point
identifiers on the diagram shall flash in a pre-programmed alarm colour until acknowledged. An
acknowledged alarm shall appear steady and with a colour inversion of its data field. The data field of the
point in alarm shall return to normal when the alarm is corrected in the field. Graphics shall be periodically
updated to keep displayed data current with actual field conditions.
System colourgraphics shall be easily developed, via the keyboard and mouse controller, using a number
of interactive construction programmes and a library of standard symbols representing devices such as
chillers, pump, air handling units, coils, temperature sensors, thermals, contacts, fans, dampers, motors,
relays and similar items. Graphic Construct programmes shall place the desired line drawings or symbols
in the appropriate place on the screen, assign point type, colours and text. Complete diagrams shall be
tested for accuracy and validity. The standard symbols library shall be augmented by user defined
symbols at any time. Editing features for adding, deleting and modifying data, as well as format controls,
shall be provided. Access to the colourgraphics features shall be software controlled so that only
designated operators can display or modify files.
Each point which has been manually forced (ie, not in automatic control) shall be identified with a different
background colour to that associated with alarm (or by approved equivalent means).
Each point which is associated with a failed communications line and/or controller shall be identified on the
graphic via inverse video with a different background colour to either alarms or manual forcing function.
It shall be possible to investigate each control loop by graphic penetration. That is all graphics shall be
constructed in levels as follows.
The system software shall accept up to 6 penetration levels of graphics and it shall be possible to raise and
lower the level of the graphic by moving the cursor, via the mouse, to a selected window and entering a
single character command via the keyboard.
Separate graphics shall be supplied for each sub-system, and control loop within a sub-system. It is not
necessary to provide separate graphic for each VAV box, however, information pertaining to each VAV box
is required to be stored and retrieved via a common logical group.
Logical Groups
It shall be possible to assign system points into logical groups comprising related points. Such grouping
shall be independent of hardware configuration.
The operator shall be able to display system logs (on either the visual display terminal or the printer) on
request. Logs shall, as a minimum, include:
Trend logs: Log of the value of selected points as recorded at predetermined intervals. A minimum of 10
logs each trending 10 points shall be available. (Sample times shall be adjustable in one minute
increments from 1 min. to 24 hrs).
Note: Destination of the log report (eg printer or operator’s terminal) shall be operator selectable.
The DDC central equipment shall provide a facility to issue commands to various points in the system.
On an event basis. Events shall consist of changes of state (eg, controller system alarms including
analogue alarms), fire alarms, power failures, changing of a point value (eg, a calculation result) and
similar items.
Sequential starting or stopping of selected equipment (with time delays between starts)
Historical Logging
It shall be possible to store selected information on the DDC system mass storage unit. This historical data
shall be contained in a file in two ways – as a “wrap around” file and as a “one shot” file.
A wrap around file shall, when full, override the oldest information with the new incoming data. A one shot
file shall store information to the limits of the defined capacity. The system shall audibly annunciate the
fact that a one shot file is almost full and initiate a COS message.
It shall be possible to select the system activity to be stored in the historical files. Options shall include:
Selected (or all) meter and consumption information (trend and data logs)
The system shall historically record all alarms and data for subsequent retrieval.
Hours run information from each plant shall be recorded and automatically printed (in a ‘plant run’ report) at
the end of each week.
Help Function
A help feature shall be provided to guide system operators in the selection or operation of system
functions. It shall be possible for the operator to display help pages via operation of a single help key.
Operator Functions
It shall be possible to alter existing or enter new programmes, display report (on visual display terminals or
printers) display point information, command system points (including controller parameters) and perform
similar functions on-line from the “signed-on” visual display terminal. Examples of functions which shall be
able to be performed by authorised operators include:
Response Times
General
The response times detailed below are the maximum acceptable response times for various
sequences/processes in the DDC System. (Note operators terminal shall mean VDU and/or printer as
appropriate). The times shall be achieved with a fully configures and operational system (as defined
herein) and shall not be affected by addition of spare hardware or software as specified.
Alarm Displays
The time for activation of an alarm (at the source) to registration on the DDC operator’s terminal shall not
exceed five seconds.
The time from activation of a change of status or value of a controller input, to the update of the input in the
data base and registration on the DDC System Operator’s terminal shall not exceed ten seconds.
Graphic Displays
The time from activation of an alarm or change of status or value of an input, to the registration of this new
information on a displayed graphic shall not exceed 20 seconds.
The time for entry of a request for a graphic display until complete output of such display shall not exceed
20 seconds.
System Logs and Reports
The time from execution of a request for a system log or report to commencement of the printout or display
of that report shall not exceed 20 seconds.
The time from execution of a request for display of historical data to commencement of the display shall not
exceed 30 seconds.
The time from occurrence of an event (at the source) to the activation of an associated event programme
shall not exceed 10 seconds.
The time from execution of a manual command (via the system operator’s terminals) to response of the
commanded item shall not exceed 5 seconds.
CONTROL PRIORITIES.
Controllers shall respond to programme control in the following priority (highest priority is listed first):
Source Action
Thus, the programme shall be arranged such that manual override of equipment (dampers, etc.) will not
prevent correct operation of plant during power fail and fire modes. It may be necessary to effect override
control of equipment via a parameter change in the DDC programme, rather than 'forcing' controller
outputs/inputs to ensure this priority operation.
CONTROL PANELS
The DDC equipment, together with associated relays, power supplies and ancillary devices shall be
installed in the Mechanical Services panels.
All control items shall be mounted on a removable panel within the control panel.
ENVIRONMENT
The entire DDC system (inclusive of all power supplies and input/output devices) shall operate
satisfactorily in the ambient conditions normally encountered in non-air conditioned spaces (up to 60oC).
Should ventilation of control panels be required to achieve this then the costs associated with such shall be
included in the tender.
POWER SUPPLY
The controllers shall be powered from the Building Essential Power supply at each mechanical services
switchboard. All transformers, voltage regulators, power conditioning, surge suppressors and similar items
required to ensure safe and correct operation of the system shall be included.
Temperature sensors shall be of the resistance bulb or thermistor type with ranges selected to suit the
particular application. Sensors shall be housed such that access to terminal strips and cabling can only be
achieved by removal of a cover.
Duct sensors shall be of the averaging type with capillary adequately supported to prevent sagging.
Sensors shall be mounted such that effects of radiation from heating elements are minimised.
Insertion sensors shall be mounted to ensure that a rapid response to changing temperature (of the
sensed medium) is achieved.
Calibration of sensors (to compensate for non-linear characteristics, line resistance and similar items) shall
be achieved in the DDC controller's programme (where connected to the DDC or separate system). No
field calibration shall be required.
Temperature sensors shall be such that when used in conjunction with the DDC controller or a separate
controller the accuracy of the displayed value is + 0.1K.
Static pressure sensors shall be of differential pressure type to accurately sense the static pressure and
shall be adjustable to suit the application. The sensor must be capable of withstanding a total pressure
differential pressure of 1000 pa without failure.
Air flow pressure switches shall be used to indicate the status of selected fans as previously specified.
The system will operate completely automatically and independent of any “host” computer or operator
station. All time programs event sequences, DDC etc. occur automatically within the DCU.
The following DDC Control descriptions illustrate the base functionality of the control system. These are
provisional. The MSSC is to prepare a draft full functional description for the system which is to be subject
to DSA review and approval.
Each plant will be started and stopped from the local hard wired controllers once enabled from the BMS. The
enable shall be time and ambient controlled and override
The system will modulate in sequence to maintain a required zone space temperature.
On receipt of a building fire alarm or building security activation, then all units will be stopped.
The operation all systems will be started and stopped from a central hard wired key switch with activation/ run
neon., The switch shall be located within the Staff room, final location will be confirmed onsite
All of the system will modulate in sequence to maintain a required zone space temperatures.
On receipt of a building fire alarm or building security activation, then all units will be stopped.
Holiday Over-Ride
A minimum of fifteen date blocks shall be provided to disable the occupied and holding time clocks during
holidays.
If a particular air handler unit is required to run during a holiday period, then the holiday block displayed on its
graphic can be manually set to “OFF” or “ON”.
On receipt of a call for after hours air conditioning via local push buttons, the associated unit will be started with
full control of heating and cooling. The unit will provide air conditioning for a pre-set time (initially 1 hour) and
then shut down..
The run indicator light on the after hours panel will be illuminated whenever the particular unit is running.
Automatic Restart
Provide a software programme to automatically restart field equipment on a restoration of power following a
power failure.
Each plant will be started and stopped from the local hard wired controllers once enabled from the BMS. The
CRAC unit shall be the primary operation, with the wall split system operating as standby only.
The system will modulate in sequence to maintain a required zone space temperature and humidity.
The toilet exhaust fans will be started under their own time schedule or when any associated fan coil units run.
If a fault occurs on the duty motor fan status, then the duty motor will be stopped, the standby motor started
and an alarm generated. An engraved plate with Run and Fault Lights shall be provided for each system, on
the ceiling adjacent to each toilet block.
If a fault occurs on the standby motor, then an alarm will be generated but the motor will not be stopped. A
faulted motor will require to be reset from the operators terminal.
The exhaust fans will be started from a local switch. The switch panel will include run and fault neons.
IO schedule.
TYPICAL PLANT No: OFF DESCRIPTOR Com. Point Analogue Event Alarm
Inputs Outputs
07.14.1 GENERAL
The mechanical services systems shall be selected and installed for quiet and vibration free operation in
compliance with the Australian Standard 2107 and 1359.51 noise and vibration levels.
Any item of plant or equipment not performing, causing undue noise or vibration levels or exceeds
specified sound power or vibration levels shall be replaced or rectified.
The noise rating levels form the basis of design and are required to be maintained for all conditions of
operation of plant, air distribution, airflow rates and temperature fluctuations.
The levels shall conform to “the Environmental Protection (Noise) Regulation 1987”, and the following:-
NR Levels
Area
(125 to 4000 Hz)
Balancing Criteria
Equipment shall not exceed the vibration levels, defined by the satisfactory levels of AS1359 and AS2625.
07.15.1 GENERAL
All units, fans, cowls, ductwork, supports, pipework, electrical wiring and conduits exposed to view and
within plant rooms must be painted / powdercoated / anodised to Australian Standards colours and
approved by the Architect.
Capable and skilled tradesmen shall carry out painting. Paints shall be applied on correctly prepared
surfaces on exposed equipment, ductwork and supports. Where necessary, finished paintwork shall be
protected during the progress of site works, by suitable dust covers.
07.15.2 MATERIALS
Paints, fillers, temporary surface dressings and all other painting materials shall be the products of an
approved manufacturer and of the best quality in their respective types. Sealers, primers, undercoats and
finishing paints shall be applied in accordance with the manufacturer’s recommendations.
Equipment supplied in a factory finished condition will be acceptable provided that the finish is of high
standard, acceptable in colour and does not require touching up.
Metalwork shall be painted with one coat of zinc chromate or similar approved metalwork primer and two
coats of full gloss enamel.
Galvanised steel surfaces shall be cleaned and given one complete coat of etching primer before applying
the finishing coats as above.
Prior to manufacture of the grilles or completion of the finishes, the MSSC shall request approval and
confirmation of colours and finishes.
07.16 LABELLING
07.16.1 GENERAL
All units, fans, cowls, ductwork, pipework, electrical wiring and conduits must be labelled to Australian
Standards colours and approved by the Consultant.
Unit indentation and number traffolyte labels shall be black on white. 30mm high with 10mm lettering.
07.17.1 GENERAL
The MSSC shall provide all facilities, skilled manpower, materials, instruments and tools to pressure test,
commission, test, balance and prove that the installation is operating correctly and ready to be handed
over.
Commissioning
Comprehensively commission the building services in accordance with CIBSE Commissioning Codes. As
a minimum the commission shall extend to:
Mechanical Services
The CIBSE Commission codes shall be the minimum standard for all non mechanical services.
Provide a complete set of as-built drawings for all mechanical, electrical and hydraulic systems and a
comprehensive Operations and Maintenance (O&M) manual.
Provide a report which confirms that commissioning of each system or feature is in compliance with the
contract documents. The report must also include a documented list of outstanding commissioning issues,
records of all functional/commissioning testing undertaken and list any seasonal testing required in the
future.
Training
Provide comprehensive training to ensure that a building managers or staff have all the information and
understanding needed to operate and maintain the commissioned features and systems. Training issues
covered shall include:
- Design intent (including energy/environmental features);
- Review of controls set-up. Programming, alarms and troubleshooting;
- O&M manuals;
- Building operation (start-up, normal operation, unoccupied operation, seasonal changeover and
shutdown);
- Interactions with other systems;
- Optimising energy efficiency;
- Occupational Health & Safety (OH&S) issues;
- Maintenance requirements and sourcing replacements; and
- Occupant satisfaction feedback.
Provide 12 months building tuning after handover. The tuning shall include monitoring of system
performance (including energy efficiency and consumption) and adjustment of system
parameters/operation to:
- Verify and ensure that systems are performing at their optimum efficiency during all climatic
variations for the occupied building;
- Tune systems to optimise time schedules to be best match occupant needs and system
performance; and
- Aligning the systems operations to the attributes of the built space it serves.
As a minimum:
- Review system operation and performance on a quarterly basis and adjust systems to improve
performance where necessary. The review should include assessment against:
07.17.3 COMMISSIONING
During commissioning the following generalised list of items shall be attended to:
Ensure that all control elements are functioning correctly and are calibrated.
Any defects noted with the existing equipment or control systems during this phase shall not become the
financial responsibility of the MSSC. Any items of defect found shall be noted in with costs of rectification.
Approval shall be received prior to commencing any repairs or upgrading of equipment at the site not
described in the scope of work or shown on the drawing.
The air systems shall be balanced generally in the order of -0 + 10% of the units rated and specified
quantities. Each balancing operation shall have the resulting figures recorded.
The MSSC shall allow for complete parts and labour warranty of the new equipment for a period of twelve
months from the date of practical completion.
Replacement components shall have twelve (12) months warranty from the date of replacement.
Warranty maintenance shall apply to all equipment provided under this contract.
All construction drawings must be correctly brought up to date to reflect all field changes and are a true and
accurate representation of the actual installations. These drawing shall include the following:-
- Complete layout drawings showing the actual sizes and locations of all ducts, pipework, dampers,
supply outlets, return inlets, fresh air intakes, etc.
- Complete plant and/or equipment layout drawings with full identification of each and every item of
equipment.
- Complete control wiring diagrams showing all electrical controls, relays, cut-outs, timing devices,
inter-locks, fuses, over-load, contactors, solenoids, starters, etc. with all items clearly identified as
to type and function, and ‘as installed’ switchboard layout drawings.
- As installed wiring diagrams and switchboard layouts shall be supplied in each switchboard.
Drawings shall be kept up to date with any changes which occur during the Maintenance and
Defects Liability Period and at the end of this period and before final payment is made one (1)
complete set of drawings shall be issued and placed in each switchboard.
Three copies of installation manuals shall be supplied, and Practical Completion will not be granted unil the
final manuals are provided.
The manual shall include ‘As Constructed’ specification and a full description of the installation and
function of the various systems. The manual shall be neatly prepared and bound in a white vinyl hard back
folder with stamped gold lettering on the front in the following format:
INSTALLATION MANUAL
FOR
MECHANICAL SERVICES
‘PROJECT NAME’
Consulting Engineers:
DSA Pty Ltd
In addition, the words ‘Installation Manual’ and the project name shall be gold stamped along the spine of
the folder.
Section 1 – Index
Index all sub-divisions of each section including lists of drawings, equipment, etc. for quick reference.
Divide into sub-sections for each individual air conditioning, mechanical ventilation or mechanical systems
as appropriate and include full details of design, criteria, capacities, return and fresh air flow rates, dry and
wet bulb temperatures, cooling and/or heating duties, etc.
Section 3 – Equipment
Sub-divide as for Section 2 and list all major items of equipment installed complete with manufacturer’s
name, agent’s name, model and/or type No., serial No., size, design ratings and including all relevant data
necessary for re-ordering or replacing the equipment or components of same.
Sub-divide as for Section 2 and include manufacturer’s installation, maintenance and operating instructions
for each items of equipment such as air filters, compressors, controls, cooling towers, fans, motors, etc.
Sub-divide as for Section 2 and provide a complete description and correct sequence of all actions
necessary to start-up, operate and shut-down all plant.
In addition the instructions shall include information on the immediate action to be taken in the event of
fault conditions arising and shall conclude with the following sentence in large lettering:
This section shall be sub-divided as for Section 2 and shall include all performance test results as outlined
in previous clauses.
This section shall be sub-divided as and shall include all As Constructed Layout, Section, Electrical,
pipework and associated drawings.
The drawings shall be provided in hard copy (To Scale), PDF on Disks and DWG to the current BMW
Standards.
The Log Book is to be used to record all service, maintenance and corrective works.
Routine maintenance and servicing shall be carried out for a period of twelve (12) months from date of
practical completion to the end of the maintenance and defects liability period.
Regular maintenance shall be carried out on a quarterly basis and emergency service shall be carried out
on a 24 hour call out basis.
Maintenance procedures shall be as appropriate to ensure the safe and proper operation of all systems
and shall be in accordance with current standard requirements of the Building Act and Regulations.
- Checking filters.
- Checking the operating of all electrical switchgear, including setting and operation of motor
overloads, bi-annually.
- Checking of all motors for temperatures, rise, operating current and leakage, quarterly.
- Cleaning as necessary of drip trays, strainers and other sediment collecting items, which may
become fouled.
- Arranging for a testing authority to carry out tests on refrigerant and oil samples for impurities and
submission of a full report.
- Checking, testing and reporting on a building fire safety control test. This shall include fire detection
and protection systems routine maintenance, fire and smoke dampers.
All maintenance procedures and intervals shall be strictly in accordance with equipment manufacturer's
recommendations, adapted as necessary for the particular installation duty including conditions such as
equipment frequent cycling and dusty environment.
The last maintenance visit prior to the end of the Maintenance and Defects Liability period shall be a major
visit for complete service and shall include the following:
At the conclusion of each maintenance visit a check list of items serviced shall be completed, the service
book shall be signed and check list shall be submitted to a responsible person on site. Within seven (7)
days of the date of the service visit, a report shall be forwarded together with a copy of the check list to the
approving authority.
Retention moneys or bank guarantee will not be released until twelve (12) correctly dated and completed
reports have been received at the appropriate times and approved. Should these twelve (12) inspections
not be completed within the maintenance and defects liability period, then that period, including all
equipment warranties will be extended until the twelve (12) inspections have been completed.
Any refrigerant lost during the maintenance period shall be replaced unless such loss is caused by wilful
damage to the plant by others. The plant shall be fully charged at the end of the maintenance and defects
liability period.
All defects shall be promptly rectified. Retention moneys or bank guarantee will not be released until all
outstanding defects notified during the maintenance and defects liability period have been rectified and
completion of such work subsequently advised in writing to the approving authority.
07.25.1 GENERAL
The following schedules have been prepared as a guide for tendering purposes. They do, however, form a
summary of the preceding Clauses in the Specification and should be read in conjunction with the Project
Drawings.
Air quantities and temperatures may be changed slightly to suit the particular manufacturers equipment
providing full details are submitted with the tender, any changes shall not affect the “Guarantee of
Performance” or conflict with any By-Laws, Statutory Requirements, Public Health Requirements or the
overall design in general.
Pressure drops and fan static pressures have been given as a guide for tendering purposes only. Allow for
all pressure drops through the equipment offered and to suit the ductwork and pipework layouts prepared
as part of the Construction and Workshop Drawings. The schedule shall not be used direct for technical
purposes when order equipment
As following, this form shall be completed and submitted with each and all shop drawings
Checked
Item Reference Document
(Y/N)
Builders access panels checked for compliance with safe access to plant and
( )
equipment for serving and maintenance.
I/we certify the above construction co-ordination between all trades and works is complete in all
respects without exclusions or exceptions.
Signature:
Signature: Signature:
Date:
Date: Date:
Name:
Name: Name:
PROJECT NAME
MECHANICAL SERVICES
Project - 5921
TENDER FORM 1 OF 6
Tender for the supply, delivery, installation, testing and maintenance of the mechanical systems as
specified and detailed in DSA Pty Ltd Specification and Drawings’.
Exhaust Systems
(Excluding. GST) $ $
(Including. GST) $ $
DATE ...................................................................................................................
TENDER FORM 2 OF 6
We advise that our Tender includes work as described below to be carried out in each case by the sub-
contractor or supplier stated.
DUCTWORK $ .............................................................
PIPEWORK $ .............................................................
ELECTRICAL $ .............................................................
PAINTING $ .............................................................
MISCELLANEOUS $ .............................................................
DATE ...................................................................................................................
TENDER FORM 3 OF 6
If awarded the contract, we will sub-let the following section of work to the sub-contractors named,
provided that the sub-contractors meet with the approval of the Architect.
PIPEWORK ...........................................................................................................................................
DUCTWORK .........................................................................................................................................
INSULATION ........................................................................................................................................
ELECTRICAL ........................................................................................................................................
PAINTING .............................................................................................................................................
DATE ...................................................................................................................
TENDER FORM 4 OF 6
All rates below shall include, supply, installation, transport, workshop / as-installed drawings,
commissioning, warranty, site allowances, supervision, project management, overheads and profit.
DATE ...................................................................................................................
TENDER FORM 5 OF 6
All rates below shall include, supply, installation, transport, workshop / as-installed drawings,
commissioning, warranty, site allowances, supervision, project management, overheads and profit.
Return air grille c/w line of sight baffle. 600x600 $ each $ each
DATE ...................................................................................................................
LABOUR RATES
Labour rates applicable for work time on site and in factory and shall include GST, all loadings and
allowances apart from overhead and profit covered by item L below.
Commissioning $ $ $
Drawing Office $ $ $
Maintenance $ $ $
DATE ...................................................................................................................
1 GENERAL
The entire hydraulics hydraulic services work shall comply with all the latest relevant regulations,
Standards and regulatory authority requirements. The cost of any materials or equipment required to
comply with all the latest relevant regulations, Standards and regulatory authority requirements shall
be included in the Tender whether specifically shown or described in the Tender documents or not.
All materials and equipment shall be the best of their respective kinds, complying with the relevant
Standards. All materials and equipment shall be new and delivered to site with the manufacturer’s
labels intact.
The scope of work is described briefly in the following clauses and more fully in the remainder of the
Specification.
In particular the work shall include, but not limited to, the supply, detailed design (where required),
installation, testing, commissioning and maintenance of the following;-
- Inspect the site, ascertain and include for all on site conditions.
- Provide and install all sanitary plumbing including sanitary fixtures and all necessary fittings, traps,
sink basket strainers, waste pipes, acoustic insulation, vent risers, air admittance valves, inspection
openings positioned as required in all discharge pipes and drains.
- Provide and install all property sewerage including drains, clean out points, manhole covers,
overflow relief traps, inspection openings and connection to the existing property sewer at locations
indicated on the drawings.
- Provide and install all building stormwater drainage including allowance for locating and removal of
obsolete stormwater soakwells, sumps and drains. New uPVC rain water pipes, direct connection of
metal rainwater pipes, overflows, outlets, acoustic insulation, sump boxes, relief points, grated
channels, threshold channels and soakwells
- Provide and install potable and non-potable cold water services including connection to the existing
water services, new pipework, valve pits, taps, outlets, hose taps, recessed wall boxes, isolation
valves, backflow valves, valve boxes, branches and connections to fixtures and equipment.
- Provide and install hot water services including water heaters, pipework, thermal insulation,
branches, temperature control valves, isolations valves and connections to fixtures and equipment.
- Provide and install fire services including new fire booster assembly, pipework, connection to the
existing fire service, new isolation valves, valve boxes, fire hydrants, anti-tamper covers to all
hydrants, extended hose length signage, numbering of all fire valves / boxes, fire service block plans
and system testing by a FPA accredited third party contractor.
- Provide and install drainage and water provisions to all mechanical plant and equipment.
- Provide and install approved fire stop products to all penetrations traversing through all suspended
floors and where required fire compartment walls.
- Allow for acoustic treatment of all hydraulic pipework penetrating through acoustic rated walls.
- Submit shop drawings for review and approval for all fabricated stainless-steel fixtures, recessed
hose tap wall cabinets, door threshold drains, stainless steel troughs, chilled water drink units, core
drill details of structural elements and fire booster block plan(s)
- Provide and install signage and/or painting to all above ground pipework, isolation valves, valve pits,
non-potable water outlets, fire booster cabinet, fire hydrants, and hose tap boxes
- Provide and install thermal insulation to all hot water pipework and above ground condensate drains
- Provide and install acoustic insulation to all above ground sanitary and stormwater drains within the
building traversing through all habitable areas.
- Inspection, testing and certification of the complete fire hydrant services installation by a FPA (Fire
Protection Association Australia) accredited and DFES approved third party fire services testing
contractor in accordance with AS1851, AS2419 and DFES operational requirements.
- Allow for all other necessary ancillary items of equipment, scaffolding, penetrations, sleeves, lights,
specialist sub contractors, manufactures, etc. to satisfactorily complete these works to the
satisfaction of the superintendent.
- Provide all relevant test records / sheets, photos, CCTV drain footage etc.. prior to practical
completion to verify that the installation is in accordance with all relevant Australian standards and
the Contract documents
- Provide As Constructed drawings and a separate record of ALL in-ground services prepared and
certified by a Licensed Surveyor prior to practical completion.
To ascertain the scope of work the Specification shall be read in conjunction with ALL drawings. The
Superintendent shall be advised in writing of all discrepancies prior to close of Tenders and all
discrepancy adjustments are deemed to have been incorporated into the Tender.
Design for durability: Develop the design so the systems achieve the documented performance,
reliability, service life, energy efficiency and safety requirements, and are easily maintainable.
Access for maintenance: Develop the design so the systems conform to ACCESS FOR
MAINTENANCE in the General requirements work section.
2.1 PRECEDENCE
General
Work sections and referenced documents:
- The requirements of other work sections of the specification override conflicting requirements of this
work section.
- The requirements of the work sections override conflicting requirements of their referenced
documents.
- The requirements of the referenced documents are minimum requirements.
2.2 CROSS REFERENCES
General
Requirement: Conform to the following work section(s):
- 0171 General requirements.
2.3 INTERPRETATION DEFINITIONS
General: For the purposes of this work section the definitions given in the 0171 General requirements
work section apply.
2.4 STANDARDS
General
Microbial control: To AS/NZS 3666.1, AS/NZS 3666.2 and the recommendations of SAA/SNZ HB 32.
Sanitary plumbing and drainage: To AS/NZS 3500.2.
Water supply: To AS/NZS 3500.1.
Where specified or implied, Australian Standard Specification and British Standard Specification or
Codes shall be the latest revisions.
Materials and Workmanship shall comply with following Australian Standards unless otherwise
specified:
AS 1260 unPlasticised PVC (uPVC) pipes and fittings for sewerage applications
AS 1342 Precast concrete drainage pipes
AS 1345 Identification of the contents of piping, conduits and ducts
AS 1415 unPlasticised PVC (uPVC) pipes and fittings for soil, waste and vent (SWV) applications
AS 1432 Copper tubes for water, gas and sanitation
AS 1464 unPlasticised PVC (uPVC) pipes and fittings for gas reticulation
AS 1477 unPlasticised PVC (uPVC) pipes and fittings for pressure applications
AS 1589 Copper and copper alloy waste fittings
AS 1631 Cast grey and ductile iron non pressure pipes and fittings
AS 2032 Code of practice for installation of uPVC pipe systems
AS 2118.2 Automatic fire sprinkler systems: Wall wetting sprinklers (Drenchers)
AS 2280 Ductile iron pressure pipes and fittings
AS 2419.1 Fire hydrant installations
AS 2758 Aggregates and rock for engineering purposes
AS 2977 unPlasticised PVC (uPVC) pipes for pressure applications - compatible with cast iron pipe
outside diameters.
AS 3500 National plumbing and drainage code - parts 1-4
AS 3517 Capillary fittings of copper and copper alloy for non-pressure sanitary plumbing
applications
Providence Christian College
Primary School – Stage 1 3 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0801 Hydraulic systems
AS 3688 Water supply - copper and copper alloy compression and capillary fittings and threaded
end connectors
AS 3725 Loads on buried concrete pipes AS 3972 Portland and blended cement
AS 256 Plastics Pipe Laying Design Keep an onsite copy of AS3500.
2.5 CONTRACT DOCUMENTS
General
Requirement: Conform to the 0171 General requirements work section.
The Tenderer shall obtain a full set of Tender Documents including Architectural, Structural, Civil,
Mechanical, Electrical and Landscaping Services drawings and specifications. All information
indicated on the Architectural, Structural, Civil, Landscaping, Mechanical and Electrical Services
drawings and specifications that affect this section of the work but not indicated on the hydraulics
services drawings shall be deemed to be incorporated into the Tender.
Plumbing drawings do not show all the Architectural, Electrical, Mechanical and Structural details. Any
information involving accurate measurement on site or buildings shall be taken from the previously
mentioned drawings or at the site.
Should any discrepancies occur they shall be notified to the Superintendent Representative before the
work proceeds.
The hydraulic services drawings indicate the general location and route to be followed by pipe work
and equipment etc, to be installed under this contract. Where the required pipe work is only shown
diagrammatically, the pipe work shall be installed in such a way as to conserve headroom and
interference as little as possible with the free use of the space through which they pass. All pipe work
etc, shall be installed as close as practicable to ceilings, walls, floors, etc, unless otherwise shown or
specified.
The location of pipes, ducts, outlets, etc, may be altered at the direction of the Superintendent without
expense to the Principle provided that the change is made before the installation and does not
necessitate additional materials.
As the work progresses and before installation of fixtures and equipment that may interfere with the
interior treatment of the building, the Head Contractor shall consult with the Superintendent
Representative and obtain detailed drawings and instructions for the exact locations of such
equipment.
No contact variations will be approved for the tenderer not informing themselves of
information on the Architectural Drawings. It is the responsibility of the tenderer to ensure the
contractor has provided a full set of documents and specifications.
The drawings covering this section of work are as follows:
H01 Site Plan – Drain, Water & Fire 1:500
H02 Part Site Plan – Drain, Water & Fire 1:200
H03 Ground Floor Plan - Drain 1:100
H04 First Floor Plan – Drain 1:100
H05 Ground Floor Plan – Water 1:100
H06 First Floor Plan –Water 1:100
H07 Typical Details NTS
2.6 SUBMISSIONS
Maintenance program
General: Submit details of maintenance procedures and program, relating to installed plant and
equipment, 6 weeks before the date for practical completion. Indicate dates of service visits. State
contact telephone numbers of service operators and describe arrangements for emergency calls.
2.7 OPERATION AND MAINTENANCE MANUALS
Requirement: Conform to the 0171 General requirements work section.
Shop drawings
Standard: To AS 1100.101, AS 1100.201, AS 1100.301, AS 1100.401 and AS/NZS 1100.501 as
applicable.
Requirement: Submit detail drawings, showing the following:
Providence Christian College
Primary School – Stage 1 4 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0801 Hydraulic systems
3 PRODUCTS
Equipment: Documented pump heads are based on provisional equipment selections and estimated
pressure drops. Before ordering equipment, calculate the respective system pressure losses based on
the equipment offered and layouts shown on the shop drawings and submit the proposed selections.
Submissions: Submit technical data for all items of plant and equipment. Data: Include at least the
following information in technical submissions:
- Assumptions.
- Calculations.
- Model name, designation and number.
- Capacity of all system elements.
- Country of origin and manufacture.
- Materials used in the construction.
- Size, including required clearances for installation.
- Certification of conformance to the applicable code or standard.
- Technical data schedules corresponding to the equipment schedules in the contract documents. If
there is a discrepancy between the two, substantiate the change.
- Manufacturers’ technical literature.
- Type-test reports.
3.1 INSPECTION NOTICE
Inspection: Give notice so that inspection may be made of the following:
- Excavated surfaces.
- Concealed or underground services.
Providence Christian College
Primary School – Stage 1 5 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0801 Hydraulic systems
4 EXECUTION
- In all other cases, provide proprietary plastic or concrete supports installed with falls that achieve a
raised, impervious and water shedding bearing surface.
- Balustrades: If balustrades or screening are required, obtain the advice of a registered architect.
4.7 GREEN STAR
The Tenderer by submission of his tender acknowledges that he has, and shall be deemed to have,
determined and allowed for all GREENSTAR requirements but not limited to practical demonstration of
equipment, maintenance manuals, providing proof of purchase and installation of Green Star elements
for inclusion in submission.
4.8 PROPRIETARY ITEMS (SPECIFICATION BY EXAMPLE)
Requirement:
The Contractor shall provide and install the proprietary items, materials and goods specified herein.
Substitution:
Where a proprietary item, material, trade name, brand or catalogue number is referred to in the
contract documents, the Head Contractor may propose substituting a similar product equivalent in
form, function and quality, durability, appearance and the like to the approval of the Superintendent,
provided that:
- the Head Contractor has provided all necessary specifications, documentation, test results and the
like comparative information in respect of the proposed substitution to the satisfaction of the
Superintendent, and
- in the opinion of the Superintendent Representative the characteristics of type, quality, finish,
appearance, method of construction, durability and performance of the proposed substitution are not
less than those of the specified item, and
- where the specified product is a Western Australian product, the proposed substitution is also a
Western Australian product, and
- the Superintendent’s written approval of the proposed substitution has been obtained prior to its
implementation.
Such approval shall not be anticipated because of a similar approval having been given in a previous
contract.
UNOBTAINABLE ITEMS: In the event of a specified proprietary item being unobtainable, the
Contractor shall apply promptly to the Superintendent for further directions.
Should any items or materials and/or equipment be found to have been substituted without approval,
same shall be removed and replaced with the correct items as specified at no extra cost to the client.
4.9 APPRECIATION OF REQUIREMENTS
The Tenderer is deemed to have:
- Inspected the project documents (including all Architectural, Structural, Mechanical, Civil, Fire,
Landscape, Hydraulics and Electrical documents) and be cognisant of all conditions affecting the
sub-contract works;
- Inspected the site and existing buildings and ascertained local information required;
- Gathered all relevant regulations and requirements of the authorities having jurisdiction over the
project;
- assessed the work, materials and equipment necessary to carry out the intent of the specification;
- accurately assessed the time frame necessary to complete the work.
No consideration will be granted for misunderstanding the sub-contract works to be undertaken, or for
lack of knowledge of the conditions of the site.
Arrangements to inspect the facility will be coordinated by the Superintendent. Regulations
All plumbing and drainage work shall be carried out in accordance with the PLB and the National
Plumbing Code AS3500, the regulations of the Local Authority and to the satisfaction of the
Superintendent.
A full set of the current legislated AS3500 must be onsite at all times for reference.
All plumbing work shall be carried out by a plumber licensed by the Plumbers Licensing Board
All fire service work shall be carried out in accordance with the Building Code of Australia, the relevant
Australian Standards and to the satisfaction of Departments of Fire and Emergency services and
Rescue Services WA and the Superintendent.
A current legislated A2419 must be onsite at all times for reference.
All gas service shall be carried out in accordance with the ‘Australian Gas Association Installation
Code AG601-2013’ and to the satisfaction of Alinta Gas, Office of Energy and the Superintendent.
All gas service work shall be carried out by a plumber, who is an Approved Alinta Gas Installer.
A current legislated A5601 must be onsite at all times for reference.
Provide and install everything necessary to comply with the by-laws and regulations and relevant
Australian Standards even though not shown on the drawings or specifically mentioned herein.
5 SUPERVISION
A plumbing supervisor, licensed by the Plumbers Licensing Board, with seniority experience in the
type of works to be constructed and is authorised to receive and act upon instruction shall be on site at
all times.
Make all applications, submit plans, pay all fees to all authorities having jurisdiction and obtain all
necessary permits in order to facilitate the uninterrupted installation of this section of the work.
It is the Head Contractor’s responsibility to pay all Water Corporation fees and charges.
Refer to provisional sum in Architectural specification
A receipt indicating the amount paid shall be presented to the Superintendent for the reimbursement.
It is the Sub Contractor’s responsibility to pay all other Plumbing related fees and charges.
7 SETTING OUT
Set out the pipe runs before the pouring of concrete and provide any sleeves, which may be necessary
to avoid cutting holes in finished work.
All sleeves shall be removable type and be removed from the structure prior to the installation of pipe
work.
Grout around all pipes installed through penetrations in concrete or masonry structure and finish off all
grouting with an approved two (2) hour fire resistant material to the satisfaction of the Superintendent.
All pre-fabricated sections must be fixed in position in ample time to avoid delay to other trades.
8 PROTECTION
All pipe work shall be protected against the entry of foreign matter at all times.
Sanitary fixtures shall be protected against damage and any item not considered in first class
condition on completion of the work, shall be removed and replaced at no expense of the Principal
upon receipt of notice from the Superintendent.
Following the date of practical completion and before handing over to the Principle, the contractor
shall provide a practical demonstration in the presence of the Principle, superintendent, of all aspects
of the operation and maintenance, general preventive maintenance and emergency shut down
procedures of the hydraulic services system and equipment.
Final payment is conditional upon satisfactory completion of the above.
Provide and install fire stopping products to all hydraulic services pipes penetrating through all
suspended slabs and where required; fire and/or smoke walls in accordance the National Construction
Code (NCC) clause C3.15 and in accordance with manufacturer’s instructions.
Providence Christian College
Primary School – Stage 1 8 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0801 Hydraulic systems
Refer to Architectural drawings to ascertain exact locations of all fire and smoke walls.
Fire stopping products shall be of an approved manufacture, compatible with the materials being used,
and tested in accordance with AS1530.4 and AS4071.1.
Fire stopping shall be in accordance with the National Construction Code (NCC) clause C3.15
Provide and install Snap H100FWS-RR high top, cast in fire collars to floor waste gully pipework
penetrations in concrete slabs or a similar product equivalent in function, quality to the approval of the
Superintendent.
Provide and install Snap H100S-RR high top, cast in fire collars to all other waste, soil and vent
pipework penetrations in concrete slabs or a similar product equivalent in function, quality to the
approval of the Superintendent.
A stainless-steel identification tag shall be screw fixed adjacent to all fire collars / penetrations which
includes details of the installer and fire stopping product, with a reference number to the fire
penetrations register / schedule in accordance with AS4072.1.
Provide and install H.B Fuller Firesound® fire rated acoustic sealant to gaps of small bore pipework
(15 – 40mm) penetrations and to gaps (0 – 50mm) between pipe and fire collars or a similar product
equivalent in function, quality to the approval of the Superintendent.
The Head Contractor shall provide written certification that all required fire stops have been fitted
and/or applied in accordance with the NCC Clause 3.15 and manufacturer’s instructions and a fire
penetrations register / schedule similar to that detailed in Appendix B of AS4072.1.
A copy of this Certification, specifications of the installed products, and fire collar installation schedule
shall appear in the project handover manual.
Provide and install (two) 2 layers of Soundlag 4525C 5kg/25mm Quadzero Wrap lapped 100mm and
taped with 50mm aluminium tape spirally wound or a similar product equivalent in form, function,
quality, durability and appearance to the approval of the Superintendent.
Generally, insulate all rainwater and sanitary drainage pipes suspended within internal ceiling spaces,
cavities and ducts.
Refer to Acoustic Consultants Report for additional information.
Install acoustic insulation and tape in accordance with the manufacturer’s instructions.
Provide at the completion of the project a Compliance Certificate that all acoustic installation has been
installed as required by the Acoustic Consultant in accordance the manufactures requirements.
All pipework penetrating walls shall be installed so that there is no direct contact between pipes and
the surrounding structure.
Pipework Penetrating Masonry Acoustic Walls
Cut a clean round hole to provide 5 to 20mm clearance with pipes. Pack gap with fibre insulation to a
density of 20 kg/m3 density; (fibre insulation must not be tightly packed). Seal the opening around the
duct on both sides of the wall with a flexible sealant, minimum 15mm thickness.
Clearances greater than 20mm
Where clearances are greater than 20 mm, pack space around the pipe with fibre insulation to a
density of 20 Kg/m3 density. Fix 2 layers of 13mm plasterboard on both sides of the masonry wall to
achieve a clearance of 5 to 20 mm to pipe. Seal the opening around the pipe on both sides of wall
with a flexible sealant, minimum 15mm thickness.
Pipework Penetrating Stud Frame Acoustic Walls
Ensure minimum thickness of plasterboard at penetration is 26mm. Provide additional overlapping
face boards each side if required. Gap between pipe and surrounding plasterboard sheets is to be
maximum of 20mm. Seal the opening around the duct on both sides of the wall with a flexible sealant,
minimum 15mm thickness.
13 CONSTRUCTION
The tenderer shall familiarise himself with the form of construction, as construction is of various forms
ie concrete tilt up, block work, stud walls, pour in situ slabs, pre tensioned slabs steel frame etc and
accommodate them in their tender price.
All pipework positioned adjacent to any building shall be installed in strict accordance with the
Structural Engineer’s requirements and the relevant detailed drawings.
Where necessary, allow for all necessary holing of formwork and/or structural slab to facilitate the
installation of pipework.
Allow for providing all necessary ‘step-downs’, ‘sleeving’, ‘holing’ or ‘casting in’ to concrete foundations
necessary to facilitate the installation of all pipework as shown on relevant drawings to ensure all
pipework is concealed and has a minimum cover as required by the relevant Authorities.
No pipework shall be concealed prior to the completion of all testing by the Superintendent
Representative or his representative and all relevant Authorities.
14 TESTING
All pipe work shall be tested at regular intervals as required during the progress of the work.
Carry out all testing including providing all equipment and expenses, in the presence of the
Superintendent Representatives.
Give three working days’ notice to the Superintendent Representatives or his representative prior to
testing.
Sections of pipe work built into masonry or in inaccessible positions shall be tested and approved
before installation.
The Head Contractor shall provide during construction written Authority evidence stating:
Sections of property sewer, sanitary plumbing and industrial waste systems and stormwater
downpipes have been sited and tested by a DMIRS plumbing Inspector prior to concealment.
Sections of potable and non-potable hot and cold-water systems and fire hydrant services have been
sited by a DMIRS plumbing inspector prior to concealment.
Sections of the rainwater pipe system tested and approved by the Superintendent Representative prior
to concealment.
Sections of the natural gas services installation tested by the installer prior to concealment.
Fire stopping of penetrations approved by the product manufacturer and the DFES, prior to
concealment.
All pipe work shall be tested at regular intervals as required during the progress of the work.
Sections of property sewer tested and approved by the PLB Inspector prior to concealment along with
written Authority evidence.
Ovality test shall be conducted of the installed new property sewer in the presence of the
Superintendent representative and approved by the prior to concealment.
Ovality test
- DN150 plain wall PVC pipes shall be tested for ovality using a 3% deflection gauge.
- The Superintendent representative shall be provided with a letter certifying that all pipelines have
passed an ovality test.
- Straight Sewers lines shall be tested as follows.
- If the ground is dry and no dewatering equipment is required during the excavation of the trenches
the sewers can be tested for ovality 24 hours after the trenches have been backfilled.
- If the ground is wet and the level of the ground water is determined and recorded excavation is
commenced, the sewers can be tested for ovality 24 hours after the trenches have been backfilled
and the ground water has regained its original level.
- IO and IS sewers shall be tested immediately after the sewer has been constructed and the trench
backfilled to the maximum amount possible, consistent with keeping the end of the trench open.
Providence Christian College
Primary School – Stage 1 10 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0801 Hydraulic systems
- Where a section of sewer fails the test, the failed section shall be removed and the sewer replaced
stop. Repair couplings shall be concrete encased with the concrete encasing extending 150 mm
past the ends of the couplings
16 CLEANING UP
On completion of the work, all pipe lines shall be checked, cleaned and flushed out, grated channels
and sumps shall be cleaned out and fixtures cleaned, tapware and chrome plated fittings polished and
the whole of this section of the work left in perfect new condition.
Refer to 2.55 of the Preliminaries and 0171 General requirements section of Natspec.
In addition to the above references include the following specific Hydraulic services requirements.
- Index
- Labelled dividers indicating sections eg. Hot Water, Fire Equipment, As Constructed Drawings,
Warranties, Maintenance Procedures etc
- Name, address and contact numbers of emergency contact persons in event of warranty attendance
during Defects Liability Period
- Dates of Practical Completion and Defects Liability termination
- Schedule resume of maintenance procedures
- Manufacturers pamphlets
- Warranty for each item of equipment installed
- Operating and service instructions for each item of equipment installed
- Schedule resume of names and addresses for all suppliers of equipment
- One complete A3 set of Hydraulic Services As Constructed Drawings in each manual
- As constructed drawings to include clear dimensions to all major hydraulic services on all drawings.
- Site and floor plans.
- Copy of Plumbing Licensing Board ‘Certificate of Completion and Compliance’.
- Copy of Departments of Fire and Emergency services ‘Certificate of Occupancy’
- Copy of Energy safety ‘Notice of Compliance’.
- As Constructed accuracy certification.
- Back flow valve test sheet.
- Thermostatic mixing valve (TMV) test sheets.
- Plumbing Licensing Board compliance sheet.
- Video copies of the CCT property sewer drainage inspection x 3.
- Sub-contractors “Certification of Installation” statement. i.e. installed in accordance with contract
documents and relevant Australian Standards…
- Copies of test results for new gas system.
- Hydrostatic Test sheets for Hot and cold water service.
The hydraulic services operating manual shall have the name, address, phone and facsimile numbers
of the Superintendent Representatives, Hydraulic Services Consultant, Builder and Plumbing Sub-
Contractor in that order on the inside leaf of the cover in letters no less than 20mm high.
Provide sample of Hydraulic Services Maintenance Manual identification lettering prior to manufacture.
Provide with the Maintenance Manual, Two (2) sets of long handle manhole lifting keys to match
covers installed, two (2) anti Vandal tap key for each hose tap installed and a budget keys the booster
cabinet and fire hose reel/hydrant cabinets
Liaise with school superintendent to determine school operating hours and set all plant and equipment
timers to correspond with these operating hours. Submit a schedule of these hours for approval to the
consultant prior to programming timers. Copy the approved document into maintenance manuals.
Note: Final payment is conditional upon receipt of the above-mentioned items.
19 WARRANTY
All materials, equipment and workmanship etc. provided within these works shall be included in the 12
month Defects Liability Period applicable to the Head Contract and effective as from the date of issue
of a Certificate of Practical Completion.
Throughout the warranty period the Warrantor shall make good at no expense to the Principle, any
remedial work which may be required for the rectification of defects whether replacement, repair or
otherwise.
Warranties shall include for site visits, parts and labour necessary for the rectification, adjustment etc.
by the manufacturers service personnel.
- To include for all labour and materials: required to cut and seal redundant services from/in
redundant buildings.
Prepare for the Superintendent Representative approval and a project Specific Quality system
complying with AS 3900, AS3902.2 1994 – Generic guidelines for the application of AS 3901/NZS
9001/ISO 9001, AS 3902/NZS 9002/ISO 9002 and AS 3903/NZS 9002/ISO 9003.
The system shall be kept on site and continuously monitored by the Contractor and Superintendent
Representatives.
Log all non-compliance activities and issues with recommended actions to remedy the situation to
compliance.
Log all hold points for witness testing. Log all testing and inspection results.
Copy all testing and inspection results to the “as constructed” manuals.
Bring to the attention of the Head Contractor and Superintendent Representative all issues of non-
compliance, hold witness points and test results.
22 CERTIFICATION OF INSTALLATION
The Head Contractor shall provide sign-off certification on all services, equipment, plant, fixtures, etc.
installed as part of this contract, so testifying the fact that the Contractor has supplied and installed
and tested and commissioned this Contract in accordance with the Contract Documents, Client
requirements and all other controlling authority’s by-laws, codes and requirements.
22.1 CERTIFICATION CHECK LIST
- Installation Certificate of Compliance
- Copy of Plumbing Licensing Boards ‘Certificate of Completion and Compliance’.
- Copy of Department Fire Emergency Services ‘Site testing results and comments’
- Copies of test results for soil, waste and stack system
- Copy of private certifier Certificate of Compliance for fire service compliance.
- Copies of test results for hot and cold water services site service and each individual units
- Copies of test results for Fire service system
- Copies of test results for all back prevention devices
- Copies of test results for soil, waste and stack system
- Copies of test results for gas system
- Copy of Fire Stopping certification by a FPA registered passive fire engineer
- As Constructed accuracy certification
- As constructed with surveyed invert levels, connection points provided by a licenced surveyor
- Copy of test tag certification for fire hydrants
- Copy of CCTV footage with video operators written report x 2
- Copy of signed Statutory Declaration to confirm the CCTV footage stating that all sewer and
stormwater drains are free of blockages, debris, damage and are flowing freely.
- The Head Contractor shall provide sign-off certification on all services, etc. installed as part of this
contract, so testifying the fact that the Contractor has supplied and installed and tested and
commissioned this Contract in accordance with the Contract Documents, Client requirements and
all other controlling authority’s by-laws, codes and requirements.
Provide and install a sub metered water service for the recording and payment of water usage during
the construction period.
Install a suitable backflow prevention valve immediately downstream of the sub meter.
Reticulate a temporary water service with taps and valves as required.
Providence Christian College
Primary School – Stage 1 13 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0801 Hydraulic systems
Record the sub meter reading on the first day of each month and submit to the Superintendent
24 EXISTING SERVICES
With reference to all available existing service drawings, allow to carry out onsite investigations to
ascertain extent, alignment and depths of all existing services prior to commencing new site works.
Allow to hand excavate all excavations within 1 meter(s) of all known existing services.
The exact location of existing site services, authority services and connection points indicated of the
hydraulic service construction drawings are approximate only. These services have been plotted from
record drawings.
The Head Contractor shall engage a specialised underground service locating contractor to undertake
ground penetrating radar (GPR) scanning of all proposed hydraulic service trenching routes and
excavations and a Licensed Surveyor to survey all investigation findings and provide data in AutoCAD
DWG prior to commencing new works.
Pot hole findings by hand digging to determine type of service, size, depths.
Existing services that remain as part of this contract shall be plotted on ‘As Constructed’ drawings.
Fully seal service penetrations no longer required.
Where existing services are to remain, they shall remain operational at all times.
All obsolete service pipe work, pits, sumps, manholes, valves, etc shall be removed in accordance
with the demolition and construction programme and all excavations backfilled and consolidated.
All temporary services provided shall be removed and cut and sealed upon permanent connections
being made.
The Head Contractor shall engage Tunnel Vision (Unit 1, 15 Baling Street 1800 631 799) or a similar
approved third party CCTV drain inspection specialist contractor to undertake an audit of all new
sewer and stormwater drains, and any existing drains that have been altered and/or connected to at
the following stages of construction.at the following stages of the project;
- Midway of the project – Prior to commencing hard landscaping, carparks and hardcourts
- Practical Completion – Provide video with video operators report 4 weeks prior handover
The Head contractor is to ensure all drains are clear of debris. Debris and obstructions that may be
encountered within the property sewer and stormwater drainage system shall be cleared and the
drains re-video audited by the Head Contractor. The Head Contractor shall provide a final copy of the
video audit to the Superintendent indicating all property sewer and stormwater drains are clear of
debris and obstructions prior to Practical Completion. Final payment will not be made until receipt of
the video audit.
The audit shall contain a drawing highlighting the exact details of the drains audited to correlate with
the video footage submitted for approval in accordance with AS3500.2. Appendix E.
In addition to above, the Plumbing Sub Contractor shall provide a signed Statutory Declaration that
they have viewed all the footage of the property sewer and stormwater drainage system to confirm
they are free of blockages, debris, damage and are flowing freely.
26 BUILDING TUNING
In addition to clause 3.3 MAN-3 Building Tuning the Sub-Contractors shall perform commissioning
building tuning for a continuous 12 month period after handover. This period shall be shown on the
Project time line inclusive of –
The commissioning period shall include but not limited to during the defects liability period a regular
(minimum 2 no - 1 no at 12 months) inspections, maintenance and testing of items such as backflow
prevention valves, water heaters, thermostatic mixing valves, cisterns, filters, line strainers, boiling
water units, water chillers, fire hydrants, fire pumps, domestic water pumps, hot water flow and return
system, flow limiting valves etc
27 BUILDERS WORKS
The Head Contractor shall allow for and arrange the following works;
- Below ground sub services scanning, pot holing and Surveying
- Cutting, removal and reinstatement of existing surfaces for trenching of new services
- Concrete plinth for new fire hydrant booster cabinet
- Excavation and removal of redundant services and accessories.
- Removal of waste and excess soil and rock off site
- Supply of clean free draining sand for backfill of service trenches
- Anti-tamper cage over the existing site meter and backflow valve assembly
- Reinstatement of existing turf and garden beds following installation of new services
- Landscape Irrigation services
- Rock excavation and removal from site as required
- Pipe and stack ‘box outs’ where required by the Superintendent
- Recording of all new installed services by a licensed Surveyor
- CCTV inspections of all new sewer and stormwater drains
- Water proofing of wet areas
- Painting of all exposed hydraulic pipework and accessories
- Signage to hydraulic enclosures, cupboards
- Timber supports for all fixtures installed on stud walls
- Ceiling and wall access panels to hydraulic valves and equipment
- Galvanized steel rain water down pipes and overflows
28 WORKMANSHIP
Generally
Workmanship shall be of a high standard and each section of the work shall be properly and neatly
executed to the best trade practice.
Untidy work, whether exposed to view or concealed, will not be accepted.
Plumbing drawings are provided showing pipe layout and before any layout alteration is made the
Superintendent must be consulted for his approval.
Access
All pipe runs shall be fixed in positions shown with provision for easy access to every section.
Pipe work crossing walk in ducts shall be not more than 300mm above the floor surface or lower than
2100mm, so as to provide free access for persons in duct.
Provide 300mm clearance of pipe work above cisterns for access purposes.
Chrome plating
Unless otherwise directed, install chrome plated piping, accessories, fittings and clips internally where
unavoidable exposed in toilets, food preparation areas, cool rooms, freezer rooms and other similar
areas. Where such pipes pass through walls and floors, provide a suitable chrome plated cover flange
and disconnecting nut.
Escutcheons
Where pipes enter or exit cupboards provide a matching escutcheon neatly fitted to pipe over pipe
penetration.
Dissimilar metals
Where clips, brackets and pipe supports are of dissimilar metal to that of the piping used, completely
insulate the pipe at all fixing points with at least four layers of black polyethylene self-adhesive tape
wrapped around pipe.
Liaison
Allow for and maintain proper liaison with all other trades, particularly the Drainer, Formwork,
Concretor, Reinforcer, Electrical, Mechanical and Bricklaying Sub-Contractors, to ensure that
problems arising from co-ordination or services can be solved before the work is commenced.
Providence Christian College
Primary School – Stage 1 15 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0801 Hydraulic systems
All copper water or fire service piping installed under concrete floors shall be sleeved through
appropriately sized PVC pipe sleeves to facilitate removal and replacement of the copper water pipe.
Remove all residual flux from silver brazed joints by washing with hot water and soap and scrubbing
with steel wire brush.
29.5 CORROSION PROTECTION
“Denso 500” primer paste “Mastic” and “Tape” shall be used to protect all underground copper piping,
nuts and bolts on all fittings, valves, mechanical joints, tapping bands and as directed or a similar
product equivalent in function, quality to the approval of the superintendent.
All copper pipe work chased into masonry walls shall be spirally wrapped with 6mm thick x 65mm wide
foam insulation lapped 20mm.
All steelwork shall be hot dipped galvanised after fabrication.
All fixings shall be stainless steel whether inside or outside.
29.6 UNPLASTICISED POLYVINYL CHLORIDE PIPES (UPVC)
uPVC pipes shall be installed using the longest lengths practicable and shall be fitted with all
necessary matching fittings with solvent welded or rubber ring joints as applicable, expansion joints,
adapters and cast in situ concrete thrust blocks and anchor blocks.
The use of UPVC pipes and fittings are permitted on this project based on the contractor implementing
and adhering to Green Star best-practice guidelines and can present supporting documentation from
the manufacture
29.7 EXCAVATIONS
The Head Contractor shall make himself fully aware of all naturally occurring ground conditions
including the extent of limestone, rock, clay etc likely to be encountered in the excavations and make
all necessary allowances and inclusions in his tender for excavating in the adverse ground and laying
to install all necessary services as found. No extra claims for excavating and laying to install all
necessary services in hard ground, root or any other adverse conditions will be entertained.
The Head Contractor will be responsible for all excavation necessary to facilitate the installation of this
section of the work.
The Head Contractor shall allow for sub surface radar scanning along and below all proposed
excavations and recorded by a Licensed Surveyor. Findings shall be pot holed to identify service type,
size and depth prior to excavations for new services.
Excavations shall be true to line, maintained in a safe condition in accordance with the requirements of
the Scaffolding Act and Worksafe WA and hand dressed to falls as required.
With exception of those clearly indicated on the drawings, no excavation shall encroach within the
angle of repose of any new or existing structural footing, pipe line or pit.
Where it may be necessary to excavate within the angle of repose, approval must be obtained from the
Structural Engineer and the entire operation, including sheet piling and compaction, shall be carried
out under his supervision.
The base of trenches shall be excavated so that the piping will be supported on a solid bed of earth
compacted to ten blows per 300mm on a penetrometer to a depth of 900mm.
Hand excavate and locate all existing services traversed by or in close proximity to the excavations for
this section of the work and hand excavate for a distance of three meters on both sides of all existing
services before commencing machine excavation.
Liaise with the Mechanical and Electrical Contractors and ensure that all sub grade services are
installed in the necessary sequence and in the correct alignments to avoid future damage.
Remove all excess excavated material from site.
No contact variations will be approved for the tenderer not informing themselves of
information contained in the Geotechnical Report. It is the responsibility of the tenderer to
ensure the contractor has provided a full set of documents.
It is the tenderers responsibility to make himself aware of information contained in the site geotechnical
report.
29.8 EXCAVATION IN ROCK
Refer to Civil Specification for definition of excavation in rock.
Providence Christian College
Primary School – Stage 1 17 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0801 Hydraulic systems
29.9 DEWATERING
Refer to Civil Specification for definition of dewatering.
29.10 PIPE BEDDING
Sand Bedding
Where excavations are free from rock or clay, or ground water, sand bedding shall be carried out to an
even and regular grade in sufficiently dewater excavations.
Prior to laying of property sewers in sand bed conditions trench beds shall be tested with a hand
driven penetrometer consisting of a 16mm dia. rod driven by a 9kgm weight falling 600mm to resist 7
blows per 300mm. Should the soil not resist the 7 blows per 300mm, then the Hydraulic Services
Builder shall compact the virgin soil by approved means to give the required compaction.
Metal Bedding
Where excavations encounter rock, clay or water charged ground a 150 mm minimum thick metal bed
shall be laid to an even and regular grade consisting of coarse, diorite, granite or other approved stone
of igneous origin in accordance with AS 1465 - 1974, 100% passing the 13.2 mm BS sieve and 9%
passing the 4.75mm BS sieve.
Pile and Keel
Provide and install 100mm x 100mm jarrah timber piles driven to refusal and topped with galvanised
nailed jarrah timber keel as scheduled herein and in the following circumstances:
In water charged ground (if dewatering is not effective or not approved by the plumbing inspector).
Made up ground where mechanical compaction as previously specified is not obtainable.
The base of trenches shall be excavated so that the piping will be supported on a solid bed of 300mm
clean earth compacted to eight blows per 300mm on a penetrometer to a depth of 900mm above the
top of the pipe.
Pipe work shall not be installed until the bottom of all trenches has been levelled and compacted.
Backfilling shall not commence above half the depth of the service pipe or drain, until the pipe or drain
has been sighted and approved by the Plumbing Licensing Board and the Superintendent.
Selected clean backfill material free of clay, debris, stones, rubbish, etc, shall be provided by the
Contractor above all pipes laid in excavated ground.
If acceptable backfill is not available from excavations, all excavated material shall be removed from
the site and approved earth supplied by the head contractor shall be brought in for use in this event.
All backfilling shall be done in 300mm layers, thoroughly watered and compacted to eight blows per
300mm on a penetrometer. The first 600mm of all backfill over drains shall be hand compacted.
Vibrating rollers or similarly heavy compactors will not be permitted over service lines where there is
less than 600mm soil cover over the barrel of the pipe.
Compaction of soil to this depth shall be carried out only with hand tamper or approved mechanical
type.
Allow for re-testing services in areas where heavy compaction has been undertaken over service pipe
installation.
31 MATERIALS
31.1 GENERALLY
Materials used shall be the best of their respective kinds, manufactured in accordance with the
relevant Australian Standard Specification or in its absence, the relevant British Standard
Specification.
Where required, material shall be tested and Watermarked stamped.
31.2 SUPPLY OF MATERIALS
As soon as practical place all orders and take all necessary measures to ensure the supply on time of
all materials and equipment necessary for this section of the work and verify in writing to the
Superintendent that all materials have been ordered and can be delivered to suit the Construction
Providence Christian College
Primary School – Stage 1 18 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0801 Hydraulic systems
Programme, or point out if the supply of any necessary material or component cannot be arranged to
suit the Construction Programme.
Failure to ensure that all materials and equipment can be delivered to the site to be installed in
accordance with the Construction Programme will render the Head Contractor liable for all extra costs
and work involved in substitutions of a more expensive nature and all freight costs involved in
obtaining the specified materials and components further afield than the normal points of supply.
Late ordering will not be accepted for substitution.
31.3 COPPER PIPES
Copper pipes shall be type 'B' solid drawn tubes manufactured in accordance with AS1432. Copper
fittings for use with copper tubes shall be manufactured in accordance with AS1589.
Provide and install Brady or a similar product equivalent in function, quality to the approval of the
superintendent. Colour coded self-adhesive, coloured and descriptive, stickers with service flow
direction on all soil, waste, vent, rainwater, hot and cold water, gas and fire service pipe work installed
internally at 3m maximum centres, all in accordance with AS1345-1972.
Provide and install Calpico YDET 150mm wide colour coded detectable warning tape over cold water,
fire, gas and property sewer pipe work installed in ground or a similar product equivalent in function,
quality to the approval of the superintendent. Warning tape shall be installed 300mm directly above
pipes with service identification facing up.
Provide and install Brady or a similar product equivalent in function, quality to the approval of the
superintendent.50mm dia. custom brass valve tags secured to valve stem with Brady brass chain.
Engraving shall identify service and rooms/areas of control and shall correspond with As Constructed
drawings.
35 WATERMARK
All pipes, fittings, tapware, fixtures and equipment shall be Watermark approved in accordance with
the Plumbing Licensing Board requirements.
36 MAINTENANCE CONTRACTS
Throughout the Defects Liability Period, the Contractor shall include for regular and comprehensive
maintenance and service inspections by the specialist suppliers of equipment and systems installed in
accordance with the manufacturer’s recommendations and to maintain regulatory compliance.
37 CLEANING UP
On completion of the work clean all pipe work of mortar and other foreign material. Flush and clean
out all debris from wastes, property sewers, rainwater pipes, stormwater drains, grated channels etc.
Inspect and tighten all inspection and cleaning openings. Check all pipe clips and fasteners and
tighten where necessary. All pipelines shall be checked. Taps and valves shall be tested and rectified
if required. Cisterns shall be checked and adjusted if required. Sanitary fixtures and chrome pipe work
shall be uncovered and thoroughly cleaned and the whole of this section of the work shall be left in
perfect new condition.
38 TENDER BREAKDOWN
Tenderers shall submit a breakdown of the total tender price for each section as indicated in the below
table 1.
The contractor shall also allow to provide progress claim breakdown, similar to following table 2 below.
TABLE 1
Tenderers shall submit a breakdown of the total tender for each section as indicated in the below
I / We, the undersigned hereby commit to the following tender for the supply, delivery, installation,
testing and commissioning of the Hydraulic Services Installation associated with this project in
accordance with the design drawings and specification prepared by Hydraulics Design Australia
I / We, unconditionally guarantee the performance of the installation and completion of the works in
accordance with the design drawings and specification prepared by Hydraulics Design Australia
Date:
Plumbing Contractor:
ABN/ACN:
Address:
Signature:
TABLE 2
Total this
Total
External Work sections: % Claim claim
Price
Water Supply $ $ $
Sewer Drainage $ $ $
Fire Services $ $ $
Natural Gas Services $0 $0 $0
Building Stormwater Drainage - Hydraulic $ $ $
Stormwater Drainage – Civil $ $ $
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Provide sanitary fixtures, as documented.
1.2 CROSS REFERENCES GENERAL
Requirement: Conform to the following work section(s):
- 0171 General requirements.
- 0801 Hydraulic systems.
- 0802 Tapware.
1.3 INTERPRETATION ABBREVIATIONS
General: For the purposes of this Sanitary fixtures works section the following abbreviations apply:
- WC: Water closet.
- AWC: Ambulant Water closet
- WB: Wall Basin
- KS: Kitchen Sink
- TR: Trough
- LS: Laboratory Sink
- CS: Cleaners Sink
-
Refer to drawing index for full abbreviation list.
Standards general
Design for access and mobility: AS 1428.1 and AS 1428.2.
Authorised products
Standard: Listed in the Watermark Product Database, unless otherwise required by the Network Utility
Operator.
Labelling
Water efficiency labelling: Provide only products conforming to and labelled to the Water Efficiency
Labelling Scheme (WELS).
1.4 SUBMISSIONS CERTIFICATION
General: Submit evidence that proposed fixtures are listed in the Watermark Product Database.
Samples
General: Submit samples as documented in the Sanitary fixtures samples schedule.
2 PRODUCTS
2.1 PRODUCTS
Laundry troughs and tubs Standard: To AS/NZS 1229. Sealants
General: Use only sealants that do not support microbial growth.
AS/NZS 3666.1 requires that sealants not support microbial growth. Many commonly used silicone
based sealants do not meet this requirement and will support the growth of fungus.
Colour: To match fixture.
2.2 WASH BASINS
Standard: To AS/NZS 1730.
3 EXECUTION
3.1 GENERAL
Storage and handling
Accessories: Use manufacturer's brackets and accessories if these are available and suitable for the
mounting substrate.
Protection: Deliver fixtures to site protected from damage under site conditions by coatings, coverings
and packaging. Remove only sufficient protection to permit installation.
3.2 INSTALLATION GENERAL
Connections: Connect to each fixture supply and waste services. Install plumb and level.
Cutting and fitting: If it is necessary to cut and/or fit substrate to install an item, carry out this before the
surface is finished or painted. Remove items when required for painting and protect until re- installed.
Cap or plug the open ends of pipes. Reinstall when painting and finishing is complete.
Substrate and fixings: Before installation, make sure that the substrate to which the fixtures are to be
installed is adequate for the intended loads and fixings methods. In solid walls, confirm adequacy of
the material at fixing locations.
Provide and fix tested sanitary fixtures to the manufacturer's specifications in positions indicated and
as follows including all necessary brackets, fixings and fittings, brass chrome plated waste outlets,
overflows and such like and connect to services as required in order to complete the work to the
satisfaction of the Superintendent Representatives.
All vitreous china fixtures to be white.
All stainless steel fixtures to be satin finish
Liaise with the Cabinet Worker and provide templates to facilitate correct holing of bench tops for self-
rimming fixtures. Fix all self-rimming fixtures inset into bench tops as required, including waterproof
mastic seals.
All floor mounted pans to be set level and plumb on a white 3:1 sand cement mortar base with
stainless steel counter sunk screws inserted into all fixing points.
All Wall Hung fixtures to be set level and plumb with manufacture approved brackets and fixings. All
exposed flush pipes to be chrome plated copper with chrome plated wall plate over penetration.
All plug and washers to be chrome plated brass. At completions of works ensure all waste outlet plugs
are provided. Obtain receipt of delivery and issue to consultant.
All sinks shall be complete with sound proof backings
Provide and install fixing plates within walls to facilitate the secure anchoring of all fixtures, tapware,
outlets, valves, pipework, rails and appliances. All fixtures and fittings shall be anchored to with stand a
force of 1100 N applied in any position and in any direction without showing any visible sign of
deformation or loosening of the fastenings. All fixtures, tapware, outlets, and valves shall be installed
in a manner that prevents flexing of walls when subject to these forces.
Pipes, fittings, tapware, fixtures and equipment shall be Watermark approved in accordance with the
Plumbing Licensing Board requirements.
Refer to Architectural Room Layout Details and Wall Elevation Detail drawings to ascertain the exact
location of all fixture, tapware, outlets and appliances.
Provide protective covering to all fixtures, fittings and equipment after installation to prevent damage
during construction. Damaged fixtures, fittings and equipment shall be replaced with new at no
expense to the Principal.
Noggings: In framed construction, provide a solid nogging at each fixing point.
3.3 VITREOUS CHINA FIXTURES
General: Undertake preparation, assembly, connections to water supply and sanitary plumbing,
application of slurries and sealants in sequence. Install the fixture without stressing its attachment
points.
3.4 FIXTURES WALL HUNG BASINS
General: Set basins firmly to walls or vanities as detailed. Connect through trap to the drainage
system.
Providence Christian College
Primary School – Stage 1 24 Tender Issue - REV_0_11/01/21
08 Hydraulics 0811 Sanitary fixtures
3.5 VANITIES
General: Install to manufacturer's recommendations and details. Seal top and upstand to wall surface.
Seal cut surfaces to prevent moisture penetration.
3.6 COMPLETION DAMAGE
General: Inspect all work and replace or repair to factory condition damaged or marked fixtures and
components.
3.7 PROTECTIVE COATINGS
General: Immediately before the date for practical completion, remove all protective coatings and
stickers and clean surfaces. Check and clean debris from traps.
4.3 URINALS
(UR) – WALL HUNG
Provide and install Caroma Cube 0.8 wall hung vitreous china box rim urinal complete with urinal
rough-in kit (678803), urinal fit-out kit (678800W), 20mm concealed copper flush pipe and D.167
concealed fixing bracket or a similar product equivalent in function, quality to the approval of the
Superintendent.
Install the sensor control unit at 1500mm above floor within stud wall or on duct wall where shown.
Provide and install a 400x400 satin stainless steel access panel where installed in stud walls.
Install 25mm flexible electrical conduit pipe for the entire length of the sensor cable.
Provide and install 6mm copper charge line from 20mm copper flush pipe to CFWG where shown.
Electrical Contractor to provide a 10 Amp GPO within 1 meter of the sensor control unit.
4.4 BASINS
(WB.1)
Provide and install Corian (3222) glacier white WashPlane (1200Lx475Wx490D) complete with
matching waste kit, wall brackets and 1x Caroma (687290C) Modina 40mm chrome plated bottle trap
or a similar product equivalent in function, quality, etc to the approval of the Superintendent.
Install 2x tapholes in rear upstand
(WB.2)
Provide and install Corian (3224) glacier white WashPlane (2400Lx475Wx490D) complete with
matching waste kits, wall brackets and 2x Caroma (687290C) Modina 40mm chrome plated bottle
traps or a similar product equivalent in function, quality, etc to the approval of the Superintendent.
Install 4x tapholes in rear upstand
(WB.3)
Provide and install Caroma (873915) Luna wall basin (550Lx380Wx158D) complete with one tap hole,
overflow, right hand shelf, chrome plated brass outlet, D.200 basin fixing kit, and 1x Caroma
(687290C) Modina 40mm chrome plated bottle trap or a similar product equivalent in function, quality,
etc to the approval of the Superintendent.
(UWB)
Provide and install Caroma (632110 left bowl / 632210 right bowl) Opal 720 wall basin complete with
one centre tap hole, D.200 basin fixing kit, chrome waste outlet and Caroma (687290C) Modina 40mm
chrome plated bottle trap or a similar product equivalent in function, quality, etc to the approval of the
Superintendent.
Refer to Architectural details to ascertain bowl configurations
4.5 KITCHEN SINKS
(KS.1)
Provide and install Clark (1503.1L / 1503.1R) Advance 930mm long end bowl stainless steel sink
complete with one tap hole, drainer, basket waste outlet, fixing clips, 50mm PVC trap / waste and
mastic seal to bench top or a similar product equivalent in function, quality, etc to the approval of the
Superintendent.
Refer to Architectural details to ascertain bowl / drainer configurations.
(KS.2)
Provide and install Oliveri (NP612) Nu-Petite (1150Lx500Wx160D) 1 & 3/4 end bowl stainless steel
inset sink complete with two tap holes, left hand drainer, basket waste outlet, fixing clips, 50mm PVC
trap / waste and mastic seal to bench top or a similar product equivalent in function, quality, etc to the
approval of the Superintendent.
Note- Install sink mixer to tap hole between sink bowls and the Zip boiling water tap to an additional
tap hole in right hand corner of the 3/4 bowl.
4.6 CLEANER SINKS
(CS)
Provide and install Simcraft (CSL.L.WB) 30L stainless steel cleaners sink (600Lx500Wx250D) with
rear tile lip, hinged grate, wall brackets, 50mm stainless steel waste outlet, 50mm short leg chrome
Providence Christian College
Primary School – Stage 1 26 Tender Issue - REV_0_11/01/21
08 Hydraulics 0811 Sanitary fixtures
plated copper S-trap and waste or a similar product equivalent in form, function, quality, durability and
appearance to the approval of the Superintendent.
Install rim of sink 500mm above floor level, ensure grate when raised clears the taps and outlet.
4.7 PRACTICAL TROUGHS
(PT.1)
Provide and install purpose made Simcraft 304 grade 1.2mm No.4 satin finish stainless steel practical
trough (1800Lx450Wx200Dmm overall), with 1700Lx350Wmm bowl, rear and end tile upstands,
90mm waste outlet (to suit basket strainer), chrome plated copper short leg S-trap and waste, and
stainless steel wall brackets or a similar product equivalent in form, function, quality, durability and
appearance to the approval of the Superintendent.
Provide shop drawings to the Superintendent for review and comment / approval prior to placing order.
Provide and install 3monkeez (Scrap-S-90) 304 grade stainless steel waste arrestor with removable
primary and fixed secondary strainers, short leg 50mm chrome plated P-trap and 50mm chrome
copper waste or a similar product equivalent in function, quality to the approval of the superintendent.
4.8 LAUNDRY TROUGHS
(LT)
Provide and install Clark (1500.1) 45L Flushline stainless steel laundry trough (640Lx480Wx275D)
with one taphole, optional washing machine waste bypass, basket waste outlet, 50mm PVC trap /
waste, fixing clips and mastic seal to bench top or a similar product equivalent in function, quality, etc
to the approval of the Superintendent.
Provide and install 50mm trapped washing machine waste upstand within the cupboard connected to
the bypass hole nearest to washing machine recess.
Extend 65mm washing machine waste direct to the main drain and not to the floor waste gully riser.
5 CONNECT ONLY
Provide all materials and labour to connect the following fixtures and indicated on the drawings
including waste outlets, traps, valves, taps, fittings, chrome plated waste pipe, hot and cold water
connections.
DW Dish Washing Machines
0812 TAPWARE
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Provide tapware, as documented.
1.2 CROSS REFERENCES GENERAL
Requirement: Conform to the following work section(s):
- 0171 General requirements.
- 0801 Hydraulic systems.
- 0811 Sanitary Fixtures.
1.3 STANDARDS
General
Design for access and mobility: AS 1428.1 and AS 1428.2
Authorised products
Standard: Listed in the Watermark Product Database, unless otherwise required by the Network Utility
Operator.
Labelling
Water efficiency labelling: Provide only products conforming to and labelled to the Water Efficiency
Labelling Scheme (WELS).
1.4 SUBMISSIONS
Certification
General: Submit evidence that proposed tapware is listed in the Watermark Product Database.
Samples
General: Submit samples as documented in the Tapware samples schedule.
2 PRODUCTS
2.1 PRODUCTS
Accessories
General: Provide escutcheons and cover plates over visible penetrations. Finish and material to match
adjacent fixtures.
Sealants
General: Use only sealants that do not support microbial growth.
AS/NZS 3666.1 requires that sealants not support microbial growth. Many commonly used silicone based
sealants do not meet this requirement and will support the growth of fungus.
Colour: To match fixture.
2.2 TAP AND VALVE HEADS
Metal heads and handles: Provide brass fittings or a suitable bush to prevent electrolysis and growth.
Plastic heads and handles: Provide compact fittings designed to prevent fracture and exposure of
jagged or rough edges.
Vandal-proof heads: Provide vandal-proof or anti-tampering devices for the designated types.
2.3 WATER EFFICIENCY
Shower heads: To AS 3662 and suitable for the pressures and pressure differences of the supplied
water.
Water efficient tapware: Tested and labelled with their water efficiency rating to AS/NZS 6400.
3 EXECUTION
3.1 INSTALLATION
General
Requirement: Install to manufacturer's recommendations. Use manufacturer's recommended tools and
templates.
Provide and install suitable approved taps, valves and outlets to comply with the following schedule.
Unless otherwise specified all tapware shall be chrome plated
All exposed cocks and outlets shall be chrome plated flanged type.
Flexible hose shall be installed without twisting, tight stress bends or over stretching.
Set taps and outlets true, level and on tile joints where such occur. Ensure assembly and spuds are
securely fastened to prevent any movement within walls.
Tap jumper washers shall be spring loaded ‘Hydroseal’ throughout.
Refer to Architectural Detail and Room Elevation drawings to ascertain exact positions of isolating
valves and outlets.
Wherever necessary all valves for services coming under the jurisdiction of the PLB shall be tested
and stamped with the approval of that Authority.
Provide protective covering to all taps and outlets after installation to prevent damage during
construction. Damaged tapware shall be replaced with new at no expense to the Principal.
All tapware, fittings, outlets, valves and equipment shall be Watermark approved in accordance with
the Plumbing Licensing Board requirements.
Prior to positioning of any pipework in ceiling spaces or wall chases, allow for coordination on site with
all other trades and Superintendent.
Install “Not For Drinking’ signage to each non potable water outlet in accordance with AS1319.
Commission and test each tap with an integral thermostatic mixing valve to manufacture instructions,
set to deliver 45⁰ hot water, provide written test report for each tap within the handover manuals.
All hot and cold water connection points under fixtures have threaded connection, securely anchored
within wall, with chrome plated mini stop, chrome plated wall plate and flexible stainless steel or
chrome plated copper connection to tap, fitting or piece of equipment.
Location
General: Locate to dimensions as documented.
Installation
General: Install level, plumb and true to line in the required location. Make sure moving parts function
freely and without obstruction. Do not modify supplied units.
Seal: Provide resilient seals between fixtures and back nuts.
Fixing: Provide rigid fixing for tapware so that it does not move in normal operation.
Cutting and fitting
General: If it is necessary to cut and/or fit substrate to install an item, carry out before the surface is
finished or painted. Remove items when required for painting and protect until reinstalled. Cap or plug
the open ends of pipes. Reinstall items when painting and finishing is complete.
Providence Christian College
Primary School – Stage 1 29 Tender Issue - REV_0_11/01/21
08 HYDRAULICS 0812 Tapware
Tap positions
General: Locate hot tap to the left of, or above, the cold tap.
3.2 COMPLETION
Adjustment
General: Inspect and adjust tapware for correct and smooth operation. If adjustment does not rectify
incorrect or defective operation, replace units.
Damage
General: Inspect all work and replace or repair to factory condition damaged or marked fixtures and
components.
Foreign matter: Inspect for presence of foreign matter particularly on tap seats. Remove if found.
Replace damaged seats.
Protective coatings
General: On completion of the tapware installation remove all protective coatings and stickers and
clean surfaces. Check and clean debris from traps.
Thermostatic mixing valves
Field testing: To AS 4032.3.
Maintenance: Conform to the 0891 Hydraulic maintenance work section.
4 TAPWARE SCHEDULE
(WB.3)
Provide and install Caroma (96193C6A) Liano Nexus 4.5L/min chrome plated basin mixer or a similar
product equivalent in form, function, quality, durability, and appearance to the approval of the
Superintendent.
Provide and install Arco (103511) mini stops with stainless steel wall plates at high level below each
basin for connection of mixer tap flexible hose connectors.
(UWB)
Provide and install Caroma (90991C5A) Skandic 150mm Care chrome plated basin mixer or a similar
product equivalent in form, function, quality, durability, and appearance to the approval of the
Superintendent.
Remove integral temperature limiting device to ensure correct operation of thermostatic mixing valve.
Provide and install Arco (103511) mini stops with stainless steel wall plates at high level below each
basin for connection of mixer tap flexible hose connectors.
4.5 SHOWERS
(USR)
Provide and install Galvin Engineering (CLEVA035) ClevaCare shower kit complete with slide rail,
shower arm, dual check valve, hose, handpiece and Caroma (90952C) Skandic chrome plated shower
mixer or a similar product equivalent in form, function, quality, durability, and appearance to the
approval of the Superintendent.
Remove integral temperature limiting device to ensure correct operation of thermostatic mixing valve.
Install the slide rail, hose connection point and mixer tap strictly in accordance with AS1428-1 with
particular attention to set out dimensions.
4.6 KITCHEN SINKS
(KS.1 & KS.2)
Provide and install Caroma (96194C5A) Liano Nexus 6L/min chrome plated sink mixer or a similar
product equivalent in form, function, quality, durability and appearance to the approval of the
Superintendent.
Provide and install Arco (103511) mini stops with stainless steel wall plates at high level below each
sink for connection of mixer tap flexible hose connections.
4.7 CLEANER SINKS
(CS)
Provide and install 1x Galvin Engineering (49949 /CD) chrome plated cold and hot water wall set with
ceramic disc spindles, 200x120mm swivel gooseneck outlet and vandal resistant aerator or a similar
product equivalent in form, function, quality, durability, and appearance to the approval of the
Superintendent.
Install wall set at 1300mm above floor level to centre of cleaners sink.
Supply wall set with POTABLE cold and hot water.
Install wall set over cleaners sink with 100mm clearance to raised hinged grate.
Provide and install 1x Galvin Engineering (49965) chrome plated hose tap and 50mm chrome flanged
plated bib tap extension (34819) or a similar product equivalent in form, function, quality, durability,
and appearance to the approval of the Superintendent.
Supply hose tap with non-potable cold water from double check valve (DCV). No vacuum breaker
Install hose tap at 1000mm above floor level and directly below the cold water tap handle above
Ensure cleaner sink hinged grate will not clash with hose tap.
Install non-potable advisory signage “Do Not Drink’ on wall adjacent to non-potable hose tap.
4.8 PRACTICAL TROUGHS
(PT.1)
Provide and install 4x Galvin Engineering (49803) chrome plated 1/2 turn ceramic disc cold water
aerated bib taps with 80mm chrome plated flanged bib extensions or a similar product equivalent in
form, function, quality, durability, and appearance to the approval of the Superintendent.
Providence Christian College
Primary School – Stage 1 31 Tender Issue - REV_0_11/01/21
08 HYDRAULICS 0812 Tapware
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Provide water heaters, as documented.
1.2 CROSS REFERENCES
General
Requirement: Conform to the following work section(s):
- 0171 General requirements.
- 0781 Mechanical electrical.
- 0801 Hydraulic systems.
- 0823 Cold and Heated Water
1.3 STANDARDS
General
Heated water services: To AS/NZS 3500.4. Gas equipment: To AS 3645.
Authorised products
Standard: Listed in the Watermark Product Database, unless otherwise required by the Network Utility
Operator.
Microbial control
Standard: To AS/NZS 3666.1 and AS/NZS 3666.2.
1.4 INTERPRETATION
Abbreviations
General: For the purposes of this work section the following abbreviations apply:
- CFC: Chlorofluorocarbon.
- HCFC: Hydro chlorofluorocarbons.
1.5 SUBMISSIONS
Certification
General: Submit evidence that proposed water heaters are listed in the Watermark Product Database.
Warranties
Requirement: Submit all required warranties:
Warranties extending beyond the end of defects liability period: Make sure that the principal is named
as the warrantee.
2 PRODUCTS
2.1 GENERAL
Insulation
Prohibition: Do not provide insulation materials that use CFC or HCFC as blowing agent during the
manufacturing process.
2.2 ELECTRIC STORAGE WATER HEATERS
Description
General: Provide heaters as documented in the Electric storage water heater schedule. Corrosion
protection: Provide sacrificial anodes in each steel storage vessel as documented in the
3 EXECUTION
3.1 INSTALLATION
General
Standard: Install to AS/NZS 3500.4.
3.2 GAS WATER HEATERS
Standard: Install to AS/NZS 5601.1.
Manifolds
General: If multiple heaters are installed in banks use the manufacturer's standard manifold
arrangement to provide equal flow thorough each heater in the bank.
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Provide filtered water dispenser systems complete with finish, options and accessories,
as documented.
1.2 CROSS REFERENCES
General
Requirement: Conform to the following work section(s):
- 0171 General requirements.
- 0801 Hydraulic systems.
- 0823 Cold and Heater Water.
1.3 STANDARDS
General
Water supply: To AS/NZS 3500.1.
Heated water supply: To AS/NZS 3500.4.
Testing of products for use with potable water: To AS/NZS 4020.
Product authorisation requirements: To AS 3498.
Design for access and mobility: AS 1428.1 and AS 1428.2.
Authorised products
Standard: Provide products listed in the Watermark Product Database, unless otherwise required by
the Network Utility Operator.
Labelling
Tapware: Provide only products conforming to and labelled to WELS.
1.4 INTERPRETATION
Definitions
General: For the purpose of this work section, the following definitions apply:
- Ambient water: Potable water at a temperature provided by the cold water piping system, without
further heating or cooling.
- Boiling water: Potable water at a temperature at or close to 100°C.
- Chilled water: Potable water at a temperature between 6°C and 15°C.
1.5 SUBMISSIONS
Certification
General: Submit evidence that proposed products are listed in the Watermark Product Database.
Warranties
General: Submit evidence of warranties for all proposed tapware which clearly defines the warranty
period and any conditions.
2 EXECUTION
2.1 INSTALLATION
General
Requirement: Install level, plumb and true to line in the required location. Make sure moving parts
function freely and without obstruction. Do not modify supplied units.
Manufacturer's recommendations: Install and use tools and templates as recommended by the
manufacturer.
Providence Christian College
Primary School – Stage 1 35 Tender Issue - REV_0_11/01/21
08 HYDRAULICS 0815 Boiling, chilled and filtered water dispensers
Fixing: Provide rigid fixing for dispenser base so that it does not move in normal operation.
Location
General: Locate to dimensions, as documented.
Sealing
Sealants: Provide sealants that do not support microbial growth.
Colour: To match fixture.
Location: Provide resilient seals between fixtures and back nuts.
Cutting and fitting
General: If it is necessary to cut and/or fit substrate to install an item, carry out before the surface is
finished or painted. Remove items when required for painting and protect until reinstalled. Cap or plug
the open ends of pipes. Reinstall items when painting and finishing is complete.
2.2 COMPLETION
Adjustment
General: Inspect and adjust dispensers for correct and smooth operation. If adjustment does not
rectify incorrect or defective operation, replace units.
Damage
General: Inspect all work and replace or repair, to factory condition, damaged or marked fixtures and
components.
Foreign matter: Inspect for presence of foreign matter. Remove if found. Replace damaged seals.
Protective coatings
General: On completion of the dispenser installation remove all protective coatings and stickers and
clean surfaces. Check and clean debris from traps.
2.3 WARRANTIES
Period
General: Provide manufacturer’s warranty for the periods documented.
2.4 MAINTENANCE
General
Requirement: Conform to the 0891 Hydraulic maintenance work section.
3 SELECTIONS
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Provide stormwater installation, as documented.
1.2 CROSS REFERENCES GENERAL
Requirement: Conform to the following worksection(s):
- 0171 General requirements.
- 0223 Service trenching.
- 0224 Stormwater – Site
- 0821s Siphonic Roof Drainage System
- 0421 Roofing – combined and other Roofing worksections
- 0801 Hydraulic systems.
1.3 STANDARDS STORMWATER DRAINAGE
Standard: To AS/NZS 3500.3.
1.4 INTERPRETATION DEFINITIONS
General: For the purposes of this worksection the following definitions apply:
- Embedment material: Includes bedding, haunch support, side support and overlay material.
- Pipe surround: Includes pipe overlay, pipe side support, side zone and haunch zone.
1.5 SUBMISSIONS TESTS
Pre-completion tests: Submit results from pre-completion leak testing. Certification: Submit certificate
stating that network is leak free upon completion. Warranties
Detention tanks: Submit warranty.
1.6 INSPECTION NOTICE
Inspection: Give notice so that inspection may be made at the following stages:
- Concealed or underground services prior to being covered.
- Upon completion.
2 PRODUCTS
2.1 MATERIALS
Piping
Requirement: As documented in this section.
PVC-U: Provide pipe marked Best Environmental Practice (BEP).
2.2 SURFACE DRAINS – PVC-U CHANNEL DRAINS, GRATING AND SUMPS
General: Provide proprietary PVC-U channel drain complete with friction fit grating sections. Provide
matching sumps.
2.3 SURFACE DRAINS – GRATED TRENCHES
General: Provide precast or cast in situ concrete lined trenches with bitumen coated cast-iron or
galvanized steel gratings.
2.4 SURFACE DRAINS – HALF ROUND PIPE
General: Provide surface drains lined with half round pipe, including bedding and jointing, as
documented in the Surface drains – half round pipe schedule.
Providence Christian College
Primary School – Stage 1 38 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0821 Stormwater - Buildings
2.9 GEOTEXTILES
General
Requirement: Provide polymeric fabric formed from plastic yarn composed of at least 85% by weight
propylene, ethylene amide or vinylidene chloride and containing stabilisers or inhibitors which provide
resistance to deterioration due to ultraviolet light.
2.10 SUBSOIL DRAINAGE
Filter: Conform to AS/NZS 3500.3 clause 2.13.2.
2.11 PREFABRICATED PITS GENERAL
Requirement: Provide precast or prefabricated pits in conformance with AS/NZS 3500.3 clauses
2.12.8 and 7.5.
2.12 METAL ACCESS COVERS AND GRATES
Standard: To AS 3996.
2.13 STORMWATER DETENTION TANKS
General – Forms part of the civil specification Reinforced concrete tanks
Type: Precast. Standard: To AS 3735.
Design and certification: Provided by manufacturer.
3 EXECUTION
3.1 PIPING
General
Laying: Lay lengths separately with the barrel bearing evenly on the prepared bedding. Sockets: Lay
with sockets pointing upstream.
Cleaning: Clean pipe interior of dirt, debris, mortar and other foreign matter.
Protection: Provide temporary caps over the ends of incomplete sections to prevent the entry of foreign
matter.
3.2 TOLERANCES PIPELINE TOLERANCES TABLE
Permissible angular deviation Permissible displacement from
from alignment alignment
Horizontal 1:300 15 mm
Vertical 1:500 5 mm
3.3 STORMWATER DRAINS
Note: These tolerances are conditional on falls to outlets being maintained and no part of a pipeline
Location
having less than the documented gradient.
General: Provide stormwater drains to connect downpipes, surface drains, subsoil drains and drainage
pits to the outlet point or point of connection. Make sure that location of piping will not interfere with
other services and building elements not yet installed or built. Subject to the preceding and
documented layouts, follow the most direct route with the least number of changes in direction.
Downpipe connections: Turn up branch pipelines with bends to meet the downpipe, finishing 100 mm
(nominal) below finished ground or pavement level. Seal joints between downpipes and drains.
Laying
General: Lay in straight lines between changes in direction or grade with sockets pointing up hill. If
other pipes are adjacent, set each pipe true to line and complete each joint before laying the next pipe.
If work is not continuous, cap open ends to prevent entry of foreign matter.
Identification
General: Lay a detectable strip or plastic tape in the trench after pipe laying, testing and initial
backfilling.
Pipe underlay (bedding)
General: Bed piping on a continuous underlay of bedding material, minimum 75 mm, maximum 150
mm thick after compaction. Grade the underlay evenly to the gradient of the pipeline.
Chases: If necessary, form chases to prevent projections such as sockets and flanges from bearing on
the trench bottom or underlay.
Pipe surrounds
General: Place the material in the pipe surround in layers, maximum 200 mm loose thickness, and
compact without damaging or displacing the piping.
Anchor blocks
General: If necessary, to restrain lateral and axial movement of the stormwater pipes, provide
reinforced concrete anchor blocks at junctions and changes of grade or direction conforming to
AS/NZS 3500.3 clause 7.9.
Encasement
General: As documented in this section.
Location: Encase the pipeline in concrete at least 150 mm above and below the pipe, and 150 mm
each side or the width of the trench, whichever is the greater.
Concrete: Grade N15 to AS 1379.
Thermal movement
General: Arrange piping to accommodate thermal expansion. Provide proprietary expansion joints in
copper and plastic pipes where pipe flexibility does not allow movement. Make sure that movement
does not strain branch connections.
Downpipes
Downpipe termination: Stop downpipe 100 mm below the ground level and discharged directly into
stormwater pipes with overflow as documented.
3.4 SUBSOIL DRAINS
General – Forms part of the Civil contract.
3.5 PITS INSTALLATION
General: Prepare foundation, install pit and connect pipes, to manufacturer’s recommendations.
Location: At junctions, changes of gradient and changes of direction of stormwater drains, as
documented.
3.6 METAL ACCESS COVERS AND GRATES
Standard: To AS 3996.
Cover levels: Top of cover or grate, including frame:
- In paved areas: Flush with the paving surface.
- In landscaped areas: 25 mm above finished surface.
- Gratings taking surface water runoff: Locate to receive runoff without ponding.
3.7 STORMWATER DETENTION TANKS
General installation - Forms part of the Civil contract.
Providence Christian College
Primary School – Stage 1 40 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0821 Stormwater - Buildings
3.8 TESTING
Pre-completion tests
General: Before backfilling or concealing, carry out the following tests to AS/NZS 3500.3 Section 9:
- Downpipes within buildings: Air or water pressure test.
- Site stormwater drains and main internal drains: Air or water pressure test.
- Rising mains from pumped discharge: Water pressure test. Leaks: If leaks are found, rectify and re-
test.
4 COMPLETION
Cleaning
General: Clean and flush the whole installation.
5 SELECTIONS
5.1 GENERALLY
All stormwater drains up to and including 225mm shall be DWV grade uPVC with matching fittings and
solvent welded joints. (100mm SN6 grade, 150mm and 225mm diameter SN8 grade).
All stormwater drains larger than 225 shall be Class 2 Reinforced Concrete (RC) with matching fittings
or an approved equivalent where cover in inadequate, or DWV SN10 grade uPVC pipe with matching
fittings with rubber ring joints where applicable.
Drains shall be laid in straight lines to a regular grade and with the barrel of each pipe firmly bedded
on the bottom of the trench.
Each pipe shall be clean of foreign matter and have invert checked before the next pipe is laid.
Allow for all necessary planking and strutting of excavations and protection of adjacent property,
services and footings.
Allow to locate, demolish, remove, and backfill existing soakwells where indicated on drawings.
Carry out CCTV camera inspections of all new installed stormwater drains as previously specified.
5.2 PROPERTY DRAINS
Connect all downpipe sumps, concealed rainwater down pipes, grated channel drains, threshold
channel drains, AC condensate drains, plant room floor wastes; extend and connect stormwater
drains of sizes, at the levels and on the alignments as indicated on the drawings including all
necessary fittings, traps, gullies, etc: to soakwells as shown on the drawings and as required in order
to complete the work to the satisfaction of the Superintendent.
All penetrations into Civil sumps are to be made watertight to the satisfaction of the Civil engineer.
5.3 DOWN PIPE SUMPS (DPS)
Provide and install ACO (77003) Type 33 pit 300mm square x 450mm deep polymer concrete sump
box with ACO (78677) galvanised steel welded bar grate including locking bar and brackets or a
similar product equivalent in form, function, quality, durability and appearance to the approval of the
Superintendent.
Allow to wet saw new sump boxes as required to suit depth and profile of the existing footings to
ensure the top edge of the sump sits flush with paving and 75mm above garden beds.
Form up a concrete footing for the bedding of the sump boxes, cast in a 100mm PVC outlet where the
sump boxes are replacing existing and / or installed over existing footings.
Remove and replace all existing down pipe sump boxes with above item where indicated on drawings.
Provide a sample of the sump box to the Head Contractor prior to construction for the co-ordination of
new footings and preparation of steel shop drawings.
Allow to wet saw new sump boxes as required to suit depth and profile of the existing footings where
relacing any existing sump boxes. Ensure the top edge of the sump sits flush with paving.
Form up a concrete footing for the bedding of the sump boxes, cast in a 100mm PVC outlet where the
sump boxes are replacing existing and / or installed over existing footings.
Providence Christian College
Primary School – Stage 1 41 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0821 Stormwater - Buildings
Ensure the top edge of the sump box / grate sits flush with the finished paving surface level.
Liaise with Head Contractor to ascertain the exact position of all down pipes prior to commencing.
5.4 THRESHOLD CHANNEL DRAINS (TC)
Provide and install Stormtech (65ARTDiS) 316 grade stainless steel threshold channel drains of
required lengths where indicated on drawings with concealed door sill tray (approx. 105Wx30Dmm)
and electropolished premium grade 2mm architectural stainless steel grating a similar product
equivalent in function, quality, etc to the approval of the Superintendent.
Liaise with Head Contractor for exact channel lengths and door track dimensions
Submit detailed shop drawings to the Superintendent for review and approval prior to placing order.
Head Contractor to co-ordinate the slab edge set down, water proofing and door installation
Provide channel drains to the Head Contractor to install in conjunction with the specified door track
and water proofing membrane in accordance with the Architectural detail drawings and manufacturer’s
instructions.
Provide and install 50mm PVC drains from channel outlets, connect to the stormwater drainage
system via a grated relief / overflow point.
5.5 PAVING DRAINS (PD)
Provide and install ACO (77003) type 33 pit 300mm square x 450mm deep polymer concrete sump box
with ACO (78678) galvanised steel heel guard grate and optional lock down bracket or a similar product
equivalent in form, function, quality, durability and appearance to the approval of the Superintendent.
Refer to Landscape Architect drawings, exact location of paving drains to be confirmed onsite with Head
Contractor to suit low points of paving.
Install drain pits with 100mm thick concrete encasement to base and sides.
The finished paving level shall be approximately 3mm above the top of the sump edge. Seal around
paving and edge of sump with a suitable flexible mastic sealant.
Head Contractor to ensure sufficient falls to paving are achievable to drainage grates to facilitate
complete and efficient surface drainage.
5.6 RAIN WATER PIPES (RWP)
Provide and install all above ground DWV grade PVC rain water pipes and overflows of sizes and in
locations indicated on the Architectural and Hydraulic drawings complete with PVC offsets where
required to facilitate connections between gutter outlets and galvanised steel rainwater downpipes.
Refer to Architectural roof plans and detail drawings for PVC rainwater and overflow connections.
Refer to the Architectural section drawings to ascertain exact length of rainwater and overflow pipes.
Refer to Architectural drawings for details on location of PVC overflow pipes and terminals.
All rainwater pipework above ground and within the building shall be wrapped with acoustic insulation
as previously specified.
Head Contractor to provide and install all exposed above ground galvanised steel rainwater pipes.
Liaise with Head Contractor to ensure that all direct connect galvanised steel rainwater pipes are of a
length that will enable a concealed connection to PVC drains below finished ground level.
Connect onto galvanised steel rainwater pipes installed by Head Contractor with Fernco uPVC to CHS
flexible adaptor complete with stainless clamps and watertight mastic seal below paving level.
Wrap below ground galvanised steel rain water pipes and adaptors with Denso Petrolatum tape.
5.7 RELIEF POINTS (RP)
Provide and install relief point comprising of 100mm uPVC riser from main drain topped with Galvin
Engineering (302745X) 150x100BSP 316 grade stainless steel square grate with 100BSP x 100 PVC
coupling (302133) set flush with finished surface level or a similar product equivalent in form, function,
quality, durability and appearance to the approval of the Superintendent.
Install grate assembly and adjacent unit pavers on a 300mm square x 100mm deep concrete footing
with grate set flush with finished paving level.
0822 WASTEWATER
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Provide sanitary plumbing and drainage, as documented.
1.2 CROSS REFERENCES
General
Requirement: Conform to the following worksection(s):
- 0171 General requirements.
- 0223 Service trenching.
- 0801 Hydraulic systems.
- 0811 Sanitary fixtures.
- 0821 Stormwater - Buildings
1.3 STANDARDS
Authorised products
Standard: Listed in the WaterMark Product Database, unless otherwise required by the Network Utility
Operator.
1.4 SANITARY PLUMBING AND SANITARY DRAINAGE
General: To AS/NZS 3500.2.
1.5 SUBMISSIONS
Certification
General: Submit evidence that proposed tapware is listed in the WaterMark Product Database.
1.6 INSPECTION
Notice
Inspection: Give sufficient notice so that inspection may be made at the following:
- Excavated surfaces.
- Concealed or underground services.
2 PRODUCTS
3 EXECUTION
- Follow the most direct route with the least number of changes of direction.
Ducts: If installed in ducts, locate and fix stacks, wastes and pipes independently of other services.
Arrange so they are easily accessible and removable throughout their entire length.
Piping: As documented in this schedule. Discharge from air handling systems
Trays, sumps and plumbing: To AS/NZS 3666.1.
3.2 THERMAL MOVEMENT
General: Arrange piping to accommodate thermal expansion. Provide proprietary expansion joints in
copper and plastic pipes where pipe flexibility does not allow for movement. Make sure that movement
does not strain branch connections.
3.3 VENT PIPES
Staying to roof: If fixings for stays penetrate the roof covering, seal the penetrations and make
watertight.
Terminations: Provide vent cowls of the same material as the vent pipe.
3.4 WET AREA FLOORS
General: Where drainage connections pass through wet area floors, terminate 4 mm below the
substrate surface.
3.5 SANITARY DRAINAGE
Laying
General: Lay in straight lines between changes in direction or grade with sockets pointing up hill. If
other pipes are adjacent, set each pipe true to line and complete each joint before laying the next pipe.
If work is not continuous, cap open ends to prevent entry of foreign matter.
Piping: As documented in this schedule. Pipeline identification
General: Lay detectable plastic warning tape, 300 mm above buried piping, for the full length of the
piping.
3.6 PIPING
Finishes
General: Finish exposed piping, including fittings and supports, as follows:
- In internal locations such as toilet and kitchen areas: Chrome plate copper piping to AS 1192
service condition 2, bright.
- Externally, and steel piping and iron fittings internally: Paint.
- In concealed but accessible spaces (including cupboards and non-habitable enclosed spaces):
Leave copper and plastic unpainted except for identification marking. Prime steel piping and iron
fittings.
Valves: Finish valves to match connected piping.
Supports
General: As documented in this schedule.
3.7 PIPELINE TOLERANCES TABLE
Permissible angular deviation Permissible displacement from
from alignment alignment
Horizontal 1:300 15 mm
Vertical 1:500 5 mm
3.8 TRADE WASTE
General: As documented in the Sanitary plumbing, Sanitary drainage and the following:
- Piping: As documented in the Trade waste schedule.
- Disposal: Provide sumps or interceptors.
4.1 GENERALLY
Soil, waste, Stormwater and vent pipes shall be complete with all bends, junctions, inspection and
cleaning openings carefully selected to ensure that inspection and cleaning openings are correctly
positioned and the correct radius bends and junctions are installed to provide a first class installation.
Pipework up to and including 100mm shall be SN6 DWV grade uPVC
Pipework larger than 100mm shall be SN8 DWV grade uPVC
Floor waste grates, clean out points, traps and standing wastes shall be protected from scratching and
damage throughout.
At completion remove protection and clean and polish all chrome plated sanitary ware and fittings.
4.2 SOIL PIPES
Soil pipes shall be DWV grade uPVC with matching fittings and solvent welded joints.
Connect to fixtures with the necessary adaptors and extend soil pipes to connect to property sewers
all as indicated on the drawings and as required in order to complete the work to the satisfaction of the
Superintendent Representatives.
Provide and install inspection openings to each WC branch and within stacks at each floor level.
Coordinate the installation of access panels where required.
The use of UPVC pipes and fittings are permitted on this project based on the contractor implementing
and adhering to Green Star best-practice guidelines and can present supporting documentation from
the manufacture
4.3 WASTE PIPES (WP)
Waste pipes shall be DWV grade uPVC with matching fittings and solvent welded joints.
Traps and waste pipes installed in exposed positions shall be chrome plated with chrome plated
disconnector nuts and flanges at floor and wall penetrations. Chrome plated flanges shall be installed
flush with floor/wall. Chrome plated nuts shall be installed flush with flanges.
Connect to all fixtures with the necessary double union traps and adaptors and extend waste pipes to
connect to property sewers all as indicated on the drawings.
Install chrome plated bottle traps to all exposed wall basins as previously specified.
4.4 VENT PIPES (VP)
Vent pipes shall be DWV grade uPVC with matching fittings and solvent welded joints.
Provide and install vent pipes and extend up through the building and discharge through roof with
water proof flashing and anti-vermin / fire rated mesh cowls as required in order to complete the work
to the satisfaction of AS3500 and the Superintendent Representatives.
Provide and install DEKS Dektite Premium roof flashings of minimum sizes required to all roof
penetrations in accordance with manufactures instructions or a similar product equivalent in form,
function, quality, durability and appearance to the approval of the Superintendent.
Ensure vent pipe termination locations are in accordance with Code requirements, co-coordinate exact
location of building air intakes with mechanical contractor.
5 PROPERTY SEWERS
5.1 GENERALLY
Property sewer drains shall be Iplex or Vinidex DWV grade uPVC (100mm diameter SN6 grade and
150mm diameter SN8 grade) with matching fittings and solvent welded joints or a similar product
equivalent in form, function, quality, durability and appearance to the approval of the Superintendent.
The use of uPVC pipes and fittings are permitted on this project based on the contractor implementing
and adhering to Green Star best-practice guidelines and can present supporting documentation from
the manufacturer.
Pipes shall be complete with all bends, junctions, inspection and cleaning openings, etc, and shall be
of the appropriate grade to suit the application.
Drains shall be laid in straight lines to a regular grade and with the barrel of each pipe firmly bedded on
the bottom of the trench.
Each pipe shall be clean of foreign matter and have invert checked before the next pipe is laid.
Allow for all necessary planking and strutting of excavations and protection of adjacent property,
services and footings.
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Provide cold water and heated water systems, as documented.
1.2 CROSS REFERENCES GENERAL
Requirement: Conform to the following work section(s):
- 0171 General requirements.
- 0801 Hydraulic systems.
- 0811 Sanitary fixtures.
- 0812 Tapware.
- 0813 Water heaters
1.3 STANDARDS
General
Water supply: To AS/NZS 3500.1. Heated water supply: To AS/NZS 3500.4.
Backflow prevention: To AS/NZS 2845.1 and AS 2845.2. Copper pipe: To AS 1432 and AS 4809.
Microbial control: To AS/NZS 3666.1 and AS/NZS 3666.2 and the recommendations of SAA/SNZ HB
32.
Authorised products
Standard: Listed in the Watermark Product Database, unless otherwise required by the Network Utility
Operator.
Installation of glass wool and rock wool insulation
General: Conform to the ICANZ Industry code of practice for safe use of glass wool and rock wool
insulation.
Marking: Deliver mineral wool products to site in packaging labelled FBS1 BIO-SOLUBLE
INSULATION.
Labelling
Water efficiency labelling: Provide only products conforming to and labelled to the Water Efficiency
Labelling Scheme (WELS).
1.4 INTERPRETATION
Definitions
General: For the purposes of this work section the following definitions apply:
- FBS-1 (fibre-bio-soluble) mineral wool: Insulation composed of bio-soluble glass or rock fibres.
- Heated water: Water that has been intentionally heated. It includes hot water and warm water.
- Material R-Value: The thermal resistance (m2.K/W) of a component calculated in conformance with
AS/NZS 4859.1 clause 2.3.3.8. Material R-Value does not include air space or surface resistances.
1.1 SUBMISSIONS
Certification
Watermark certification: Submit evidence that proposed components are listed in the Watermark
Product Database.
Fire hazard properties
General: Submit evidence of conformance with MATERIALS, Fire hazard properties. Materials
Thermal insulation performance: Submit evidence of conformance to AS/NZS 4859.1.
Samples
General: Submit samples of accessories identified by proprietary item, including the following:
- Valves.
Providence Christian College
Primary School – Stage 1 49 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0823 Cold and heated water
2 PRODUCTS
2.1 COMPONENTS
Pressure control valves
General: Provide reduction valves, pressure limiting valves, or ratio valves, which produce the
necessary reduction in pressure.
Backflow prevention devices
General: As documented in the Testable backflow prevention devices schedule. Standard: To
AS/NZS 2845.1 and AS 2845.2.
Line strainers
Type: Low resistance, Y-form bronze bodied type, with screen of dezincification resistant brass,
corrosion-resistant stainless steel, or monel.
Screen perforations: 0.8 mm maximum.
2.2 MATERIALS
Fire hazard properties
Spread-of-flame index: Maximum 9 where tested to AS/NZS 1530.3.
Smoke-developed index: Maximum 8 if spread-of-flame is over 5, when tested to AS/NZS 1530.3.
Flammability index of facing materials: Maximum 5 when tested to AS 1530.2.
Materials with reflective foil facing: Test to AS/NZS 1530.3 clause A6.
2.3 INSULATION MATERIALS
General
Standard: To AS/NZS 4859.1.
Material R-Value of insulation: ≥ Total R-Value in AS/NZS 3500.4 for the type and location of the pipe.
Polyolefin foam
Type: Closed cell cross-linked polyolefin foam produced using a hydrocarbon blowing agent.
Insulation surface facing: Heat-bonded aluminium foil laminate.
Glass wool and rock wool and polyester
Description: Select from the following:
- Glass wool or rock wool resin-bonded to form tubular sections.
- Polyester in moulded tubular sections.
Elastomeric foam insulation
Type: Chemically blown closed cell nitrile rubber in tubular sections for pipe insulation, in sheets for
insulating pipe fittings, and in sheets or rolls for large pipes, tanks, vessels and heat exchangers.
Provide with smooth natural finish and vapour barrier properties. Physical properties:
- Free of ozone depleting gases in manufacture and composition.
- Moisture absorption: Non-hygroscopic.
- Water vapour permeability: Maximum 0.065 ng/Pa.m.s.
Aluminium foil laminate sheet
Standard: To AS/NZS 4200.1.
Material: Glass fibre reinforced, aluminium foil-paper laminate. Duty classification to AS/NZS 4200.1:
Heavy duty.
Adhesives and sealants
Requirement: Provide adhesives and sealants to manufacturer's recommendations.
Providence Christian College
Primary School – Stage 1 50 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0823 Cold and heated water
3 EXECUTION
3.1 PIPING
Location
Mains connection: Connect the cold water supply system to the Network Utility Operator's main
through a stop valve and meter.
Cold water system: Provide the cold water supply system, installed from the meter to the draw-off
points or connections to other services as documented in this schedule.
Heated water system: Provide the heated water system, installed from the cold water connection
points to the draw-off points or connections to other services as documented in the Piping system
schedule.
Finishes
General: Finish exposed piping, including fittings, cover plates and supports, as follows:
- Chrome plate copper piping to AS 1192 service condition 2, bright in internal locations such as toilet
and kitchen areas:
- Paint external above ground piping, and internal steel piping and iron fittings exposed to view.
- In concealed but accessible spaces (including cupboards and non-habitable enclosed spaces):
Leave copper and plastic unpainted except for identification marking. Prime steel piping and iron
fittings.
- Valves: Finish valves to match connected piping.
Fittings and accessories
General: Provide the fittings necessary for the proper functioning of the water supply system, including
taps, valves, backflow prevention devices, pressure and temperature control devices, strainers,
gauges and automatic controls and alarms.
Provision for dismantling: Arrange piping by the provision of unions or similar so that valves, taps and
other maintainable components can be removed for maintenance without disturbing or cutting
adjacent piping.
Material identification marks
General: Pipes with grade or class identification markings: Install so that the markings are visible for
inspection.
Pipes under pressure embedded in concrete
General: Use only copper pipe and the minimum number of joints. Pressure test and rectify leaks
before the concrete is poured.
Valve spindles
General: If practicable, install valve spindles in a vertical position.
3.2 PIPING INSULATION
General
Requirement: Insulate all non-chrome plated heated water piping, fittings and valves.
Application: Fit insulation tightly to piping surfaces without gaps. Close butt ends of insulation sections.
Minimise number of joints. If the insulation is in half-sections, make only half-circumferential joints at
any one place. Seal longitudinal seams in foil laminate and fix insulation at maximum 500 mm centres
with polypropylene, zinc-coated steel or aluminium straps.
Unions and other items requiring service: Install the insulation so that it is readily removable.
Fittings: Provide insulation with thermal resistance at least equal to that of the adjacent piping
insulation.
Insulation material
General: Provide insulation material as documented.
Construction
Internal dimensions: To give 300 mm clear space all around the fittings in the pit. Concrete: Grade N20
to AS 1379, 100 mm thick, reinforced with F82 fabric.
Pit covers: To AS 3996.
Installation
General: Grade floor to a point on one side and drain to the stormwater drainage system. Carry the pit
walls up to 50 mm above finished ground level. Cast in the pit cover frame flush with the top. Trowel
the top smooth.
3.4 MARKING
Notice plate
General: Provide a notice plate containing condensed emergency instructions, legibly printed or
engraved on durable material resistant to defacement, at least 3 mm thick or mounted on board at
least 3 mm thick, permanently fixed in a convenient position at the control valves.
Marker Tape
Provide detectable marker tape conforming to AS/NZS 2648.1 along the entire length of below ground
water services at 150 mm above the installed pipe.
3.5 VALVE BOXES
General
General: Provide cast-iron valve boxes with removable covers for access to underground gate valves.
Provide cast-iron sluice valve covers for access to sluice valves.
Installation
General: Set beneath each box a shaft formed of PVC-U pipe to give clear access to the valve wheel
or spindle. Set top flush with pavement surface, or 15 mm above unpaved surfaces, and encase in
formed concrete box 150 mm thick, with top surface troweled smooth.
3.6 TESTING
Pre-completion tests
Pressure tests: Before insulation is applied to joints pressure test piping to AS/NZS 3500.1 and
AS/NZS 3500.4 as appropriate.
Leaks: If found, rectify and re-test.
Cross connections: Isolate systems individually and check for cross connections. Backflow prevention:
To AS/NZS 3500.1.
Tapware: Check for leaks.
Completion test
General: Provide a full operational test to verify conformance.
3.7 COMPLETION
Commissioning
Strainers: Remove, clean and replace strainer baskets. Cleaning: To AS/NZS 3500.1 Appendix I.
Disinfection: Disinfect to AS/NZS 3500.1 Appendix J.
Cold water systems: Test and commission to AS/NZS 3500.1 Section 18. Heated water systems: Test
and commission to AS/NZS 3500.4 Section 13.
Testable backflow prevention devices: Test and commission to AS 2845.3 by a licensed plumber with
backflow device accreditation. Tag and certify to the requirements of the Network Utility Operator.
Charging
Completion: On completion of installation, commissioning, testing and disinfection, fill the system with
water, turn on control and isolating valves and the energy supply and leave the water supply system in
full operational condition.
Maintenance manuals
Standard: To AS/NZS 3666.2.
3.8 MAINTENANCE
General
Requirement: Conform to the 0891 Hydraulic maintenance work section.
Providence Christian College
Primary School – Stage 1 53 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0823 Cold and heated water
4 SELECTIONS
4.1 GENERALLY
Provide and install new water service pipework of sizes and on alignments indicated on drawings.
Maintain existing water service in operation until completion and testing on the new water service.
Provide and install temporary pipework as required to maintain the existing system.
Liaise with the Superintendent 4 weeks prior to isolation of the existing water service to discuss the
planned works with a date, time and expected duration of the changeover.
To minimise duration off shut downs, ensure all new pipework, water meters and backflow valves have
been installed and tested, all associated works have been undertaken, excavate to locate and prepare
existing pipework for new connection and make available all required fittings, valves etc..
4.2 PIPING
Cold water services installed in the ground external of buildings shall be Acu-Water SDR11 PN16
PE100 (black with blue stripe) polyethylene manufactured to AS/NZS 4130 with matching
electrofusion fittings manufactured to AS/NZS 4129 or a similar product equivalent in form, function,
quality, durability and appearance to the approval of the Superintendent.
Install polyethylene water service pipes and fittings in accordance with the manufacturer’s guidelines
and specifications.
Polyethylene pipes and fittings shall be installed be skilled operatives, trained and certified by the
supplier / manufacture install polyethylene water service.
Provide copy of Polyethylene welding accreditation certificate to Superintendent prior to insulation.
Cold and hot water service installed above ground and within buildings shall be Kembla Type B
copper tube with Viega Propress copper EPDM rubber seal fittings installed in accordance with
manufactures instructions or a similar product equivalent in form, function, quality, durability and
appearance to the approval of the Superintendent.
All below ground copper pipework be protected by wrapping with Denso petrolatum tape.
ALL non-potable pipework shall be fitted with purple sleeving and labelled to AS3500.
All hot water pipe work shall be installed in a way that ensures damage to pipe work will not occur due
to movement or pipework due to expansion.
All hot water pipes shall have 150mm minimum clearance from cold water pipes throughout.
Where chased into walls pipes shall be protected by wrapping with approved sponge tape.
Cone-tite fittings or cast brass tees and elbows will not be accepted, flare type unions only.
Provide adequate anchorage where pipes terminate in walls, at taps and outlets, etc.
ALL above ground cold and hot water pipework shall be labelled in accordance with AS3500.
4.3 HOT WATER PIPEWORK INSULATION
Provide and Armaflex FRV 25mm wall thickness pipe insulation to all hot water pipework in
accordance with manufactures instructions or a similar product equivalent in form, function, quality,
durability and appearance to the approval of the Superintendent.
Insulation shall be installed over piping before installation and shall not be cut longitudinally.
4.4 ISOLATION VALVES
Above Ground
Provide and install Zetco (1005) series ball valves, of sizes indicated on the drawings, with stainless
steel handles and disconnecting unions comprising tube bush on inlet and flared type boiler union on
outlet or a similar product equivalent in form, function, quality, durability and appearance to the
approval of the Superintendent.
Below Ground
Provide and install Zetco (2505) series below ground ball valves, of sizes indicated on the drawings,
with stem cap and disconnecting unions comprising tube bush on inlet and flared type boiler union on
outlet or a similar product equivalent in form, function, quality, durability and appearance to the
approval of the Superintendent.
All below ground valves, bolts, nuts shall be protected by wrapping with Denso petrolatum tape.
Providence Christian College
Primary School – Stage 1 54 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0823 Cold and heated water
Provide and install Zetco (2502) 900mm underground valve key or a similar product equivalent in form,
function, quality, durability and appearance to the approval of the Superintendent.
Provide a valve key handle to all below ground valves / valve pits.
Key handle to terminate 100mm below valve box cover, cut down each key handle to required length.
4.5 VALVE PITS / BOXES
Provide and install valve boxes to all inground valves comprising of a 225mm PVC riser below a
Galvin Engineering (178049) 250x250 hinged cast iron valve box cover or a similar product equivalent
in form, function, quality, durability and appearance to the approval of the Superintendent.
Install box on a 150mm wide x 150mm deep concrete strip footing with hinged cover set flush with
finished paving level.
Cast iron covers shall label embossed 'WATER' and epoxy coated blue.
4.6 THERMOSTATIC MIXING VALVES (TMV)
Provide and install Galvin Engineering (101.70.00.00) CliniMix Lead Safe thermostatic mixing valve
(TMV) with 15mm inlets, 15/20mm outlet, right angle ball valves, non-return valves and strainers or a
similar product equivalent in form, function, quality, durability and appearance to the approval of the
Superintendent.
Provide and install purpose made stainless steel standoff wall brackets
Install thermostatic mixings valves on the hot water supply to all personal hygiene fixtures / tapware
and all sinks that are accessible to students at locations indicated on the drawings.
The Head Contractor shall provide suitably sized ceiling access panels where required to provide
access for maintenance purposes. Liaise with Builder and establish suitable location for ceiling access
panels prior to installing on thermostatic mixing valves.
Test all hot water outlets for maximum temperature delivery at prior to Practical Completion.
Provide test sheets and written certification that all outlets have been tested to deliver 42°C maximum
temperature hot water.
Test sheets shall nominate Room number and temperature at outlets and shall be included with the
Hydraulics Manual.
4.7 BACKFLOW PREVENTION VALVES (DCV)
Provide and install Wilkins (20-350CAB1R) 20mm double check valve with 2 No ball valves and line y-
strainer in recessed stainless-steel cabinet (500mm wide x 400mm high x 90mm deep) with removable
inspection window panel and 40mm BSP waste outlet or a similar product equivalent in form, function,
quality, durability and appearance to the approval of the Superintendent.
Extend non potable water service and connect to non-potable cold water to hose tap over cleaner sink
as specified in section 0812.
Subject all backflow valves to test procedures as required by AS3500 and the Water Corporation.
Install engraved commissioning / service test tags to all backflow valves with test date and testing
contractors’ details.
Within 5 days of installation submit all required certificates and results to the Water Corporation.
Provide ‘owners’ copy of test certificates in operation and maintenance manuals.
Allow for servicing and retesting of backflow valves 1 month prior to end of defects liability period.
4.8 LINE STRAINERS
Provide and install Zetco (1504) brass y-strainers with 316 grade stainless steel 500 micron mesh
strainer with disconnecting unions comprising tube bush on inlet and flared type boiler union on outlet
or a similar product equivalent in form, function, quality, durability and appearance to the approval of
the Superintendent.
4.9 NON RETURN VALVES
Provide and install Zetco Series 1805 bronze check valves with disconnecting unions comprising tube
bush on inlet and flared type boiler union on outlet or a similar product equivalent in form, function,
quality, durability and appearance to the approval of the Superintendent.
0831 HYDRANTS
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Provide fire hydrant installations including water supply, piping, valves, hydrant valves,
booster valve and suction points, as documented.
Design
Standard: To AS 2419.1.
1.2 CROSS REFERENCES
General
Requirement: Conform to the following work section(s):
- 0171 General requirements.
- 0801 Hydraulic systems.
- 0814 Hydraulic pumps.
- 0891 Hydraulic maintenance.
1.3 STANDARDS
General
Standard: To AS 2419.1.
1.4 SUBMISSIONS
Products
Product listing: Submit documentation to verify product listing in the ActivFire Register of Fire
Protection Equipment for the respective item.
Samples
General: Submit samples of accessories not documented as proprietary items, including the following:
- Fire brigade booster valve.
- Fire hydrant valve.
- Vandal resistant canister enclosures.
1.5 INSPECTION
Notice
Inspection: Give notice so that inspection may be made of the following:
- Connection branch to existing site water mains.
- Pipes installed in trenches including all thrust blocks where required.
- Flow testing of the most hydraulically disadvantage hydrant
- Fire brigade booster / operational test
2 PRODUCTS
2.3 VALVES
Isolating valves
Below-ground metal seated isolating valves: To AS/NZS 2638.1. Below-ground resilient seated
isolating valves: To AS/NZS 2638.2. Fire hydrant valves
Standard: To AS 2419.2.
Requirement: Provide fire hydrant valves as follows:
- To the requirements of the local fire brigade.
- Copper alloy construction.
- Matching non-ferrous dust cap and chain. Valve monitors: To AS 4118.1.4.
3 EXECUTION
3.1 INSTALLATION
General
System: To AS 2419.1.
Valves: Locate valves to permit satisfactory operation and maintenance.
3.2 COMMISSIONING GENERAL
System: To AS 2419.1.
Baseline data
Requirement: Provide baseline data to AS 1851.
3.3 MAINTENANCE GENERAL
Requirement: Conform to the 0891 Hydraulic maintenance worksection.
4 SELECTIONS
4.1 GENRALLY
Provide and install fire booster assembly, hydrants, valves and pipework as indicated on drawings.
Liaise with DFES and the Superintendent 2 weeks prior to any isolation of the existing fire service to
discuss the planned works with a date, time and expected duration. Submit an Impairment Notification
to DFES at least 72 hours prior to planned isolation of the fire hydrant system.
To minimise duration off shutdowns, ensure all new pipework has been installed and tested, all
associated works have been undertaken, excavate to locate and prepare existing pipework for new
connection and make available all required fittings, valves etc.
It is important that where buildings are occupied during construction, that the Head Contractor
prepares a management plan to ensure the existing installed fire safety systems remain operational
and accessible for the duration of the construction.
4.2 FIRE HYDRANT BOOSTER (FB)
Provide and install Galvin Engineering (380168) two point fire hydrant booster assembly comprising of
150mm galvanised steel and painted pipework, 150mm table E flanges, gear operated butterfly valves
(chain open), non-return valve, pressure gauge, 2x 65 BIC hydrant valves, 2x booster inlet valves,
valve caps / plugs or a similar product equivalent in form, function, quality, durability and appearance
to the approval of the Superintendent.
Provide and install Galvin Engineering (380212) fire hydrant booster cabinet (2000mmL x 600mmW x
1500mmH) comprising of powder coated zincalume panels, raised support legs, hinged doors, budget
taper lock and signage to AS2419 or a similar product equivalent in form, function, quality, durability
and appearance to the approval of the Superintendent.
Provide and install 150mm galvanised steel risers from below ground polyethylene pipework complete
with table E flanges, fibre gaskets and matching galvanised steel nut/bolts.
Wrap all below ground steel pipework, flanges and bolts with Denso petrolatum tape.
Head Contractor to construct a 150mm thick 2400mmLx1000mmW concrete pad for mounting and
fixing of the fire booster cabinet at 50mm above surrounding finished surface level.
Providence Christian College
Primary School – Stage 1 58 Tender Issue - REV_0_11/01/21
08 HYDRAULIC 0831 Hydrants
Ensure that there is sufficient clearance from face of fire hydrant and booster inlets to face of booster
cabinet and as per AS 2419 and DFES requirements.
Head Contractor to repaint the fire hydrant booster assembly pipework and fittings with R13 “Signal
Red” gloss enamel paint prior to practical completion.
Head Contractor to paint signage in 75mm high lettering in a contrasting colour to the booster cabinet
doors 1) “FIRE HYDRANT BOOSTER” 2) “FH” within a circle of 100mm inside diameter to external
face of door(s)
Provide and install 2 No 150mm x 1800mm steel bollards filled with concrete, adjacent to fire booster
cabinet. Confirm location of bollards with Superintendent prior to installing.
Head Contractor to allow for painting of the bollards and re painting of the fire booster cabinet with
approved primer, undercoat and three coats of R13 “Signal Red” gloss enamel paint.
Provide and install A1 size engraved (black and red embossed) aluminium block plan in accordance
with AS2419 and to the satisfaction of the DFES within the fire booster cabinet. Submit a draft of the
fire service block plan to DFES for approval 6 weeks prior to DFES booster testing. Block plans to be
mechanically screw fixed.
On completion of booster testing provide and install engraved stainless steel black embossed notice of
boost “BOOST PRESSURE xxx kPa” and test pressure “TEST PRESSURE xxx kPa” to inside of
booster cabinet in letters 25mm high in accordance with AS2419 and to the satisfaction of the DFES.
4.3 PIPING
Fire service pipe installed in the ground external of buildings shall be Acu-Fire SDR11 PN16 HD-
PE100 (black with red stripe) manufactured to AS/NZS 4130 with matching electrofusion fittings
manufactured to AS/NZS 4129 or a similar product equivalent in form, function, quality, durability and
appearance to the approval of the Superintendent.
Install polyethylene pipework and fittings in accordance with the manufacturer’s instructions.
Polyethylene pipes and fittings shall be installed be skilled operatives, trained and certified by the
supplier / manufacture install polyethylene water service.
Fire service piping installed in the ground shall maintain 750mm minimum depth to top of pipe.
Fire service pipe of 100mm and larger, installed above ground and within the buildings shall be
ActivFire certified, hot-dip galvanised, medium wall steel pipes in accordance with AS1074, with
matching hot-dip galvanised roll grooved fittings and couplings.
Internal above ground pipework supports shall have an FRL of no less than 60/–/–, while maintaining
a pipe-support temperature of not less than 500°C when tested in accordance with AS 1530.4 to the
satisfaction of the Superintendent.
Galvanised steel pipe installed below ground shall be of 1500mm maximum length.
Connect steel risers to vertical polyethylene pipework 600mm below ground level.
Galvanized steel pipe and fittings shall be Denso wrapped where installed within the ground.
4.4 ISOLATION VALVES
Below ground fire main isolation valves 100mm and larger shall be AVFI (RSGV-AS) clockwise close
resilient sealing sluice valve in accordance with AS2638, with stem cap, table E flange AS2129, fibre
gaskets, galvanized steel bolts, washers and nuts or a similar product equivalent in form, function,
quality, durability and appearance to the approval of the Superintendent.
Sluice valves shall operate anti-clockwise open.
Provide and install spindle extension to terminate stem cap 100-350mm below finished surface level.
All below ground valves, bolts, nuts shall be protected by wrapping with Denso petrolatum tape.
Below ground fire hose reel isolation valves shall be Zetco (1007) series lockable ball valve, of sizes
indicated on the drawings with tube bush on inlet and flared type boiler union on outlet or a similar
product equivalent in form, function, quality, durability and appearance to the approval of the
Superintendent.
All below ground valves shall be protected by wrapping with Denso petrolatum tape.
Install engraved tag with 8mm high uppercase text – “FIRE SERVICE VALVE - CLOSE ONLY TO
SERVICE FIRE HOSE REELS
Provide and install 003 padlock, lock in open position and hand over keys to the Superintendent
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Maintain the hydraulic systems for the documented maintenance period so that the
performance, reliability, service life, energy efficiency and safety of the system is equal to or better
than that at the beginning of the maintenance period, in parallel with and including:
- Periodic and statutory maintenance, cleaning and replacement of consumables.
- Emergency repairs.
Maintenance period: As documented.
1.2 CROSS REFERENCES GENERAL
Requirement: Conform to the following work section(s):
- 0171 General requirements.
1.3 INTERPRETATION DEFINITIONS
General: For the purpose of this work section the following definition applies:
- Consumable: Materials or components intended to be replaced within the service life of the
associated plant or equipment.
- Periodic maintenance: Planned routine maintenance of plant and equipment (proactive), including
fire safety measures and statutory requirements.
- Repairs: Unplanned/corrective maintenance (reactive).
- Replacement: Upgrading of a higher value component on regular cycle, including repainting and
replacement of air conditioning equipment.
1.4 SUBMISSIONS CERTIFICATION
Annual certification: Inspect and submit certification for all items required to be inspected annually
under statutory requirements including, but not limited to, air handling systems required for fire
operation, boilers and pressure vessels.
Records
Maintenance records: Conform to the 0171 General requirements work section.
Periodic maintenance and performance report: At the frequency documented, submit reports
summarising the maintenance performed and the performance of the hydraulic installation in the
preceding period. Set out the report in a form that permits comparison with previous reports. Include
the following as minimum requirements:
- Dates and number of site labour hours for periodic maintenance. Exclude travelling time.
- Dates, number of site labour hours and nature of work for emergency repairs. Exclude travelling
time.
- Dates and number of site labour hours for defects liability rectification if within the defects liability
period. Exclude travelling time.
- List of any motors for which the motor current varied by more than 10% from the current measured
during commissioning.
- For each separately metered item, the water or gas use for each month of the reporting period.
1.5 INSPECTION
Notice
Requirement: Give notice so that an inspection may be held simultaneously with the final programmed
maintenance visit.
2 PRODUCTS
2.1 GENERAL
Product selection
Proprietary items: Select products, as consumables or replacement items, of the same make, model
and type as those being replaced.
Substitutions: Where the existing product is no longer available, provide products with at least the
same performance and construction characteristics.
3 EXECUTION
- Check equipment items and record values for operation, calibration, performance compliance,
temperature and energy consumption.
- Rectify all water leaks regardless of size. Clean and repair any water damage.
- Check condition of insulation and repair as required.
- Provide service tags recording inspections and tests.
Cold and heated water
Maintenance of tanks and piping for potable water: To AS/NZS 3500.1 and AS/NZS 3500.4. Ball float
valves: Check and adjust for no overflow.
Heated water systems:
- Conform to AS/NZS 3500.4 Section 12.
- Inspection and maintenance: To AS/NZS 3666.2.
- Provide service tags recording inspections and tests.
- Leaks: Inspect cold and heated water systems at least annually for the following:
- Leaks, including leaks from cisterns.
- Other defects.
- Safe condition.
- Conformance to the PCA and network utility operator requirements. Leaks and defects: Report if
found and rectify.
Strainers: Inspect and clean at least annually.
Tapware
Requirement: Inspect for leaks and damage. If leaks are found, service O-rings, replace washers and
reseat to rectify.
Backflow prevention devices
General: Maintain to AS 2845.3 and AS/NZS 3500.1. Service tags: Record inspections and tests.
Thermostatic mixing valves
Field testing and maintenance: To AS 4032.3. Service tags: Record inspections and tests.
Fuel gas
Requirement: Maintain fuel gas services so that they are:
- Free from leaks and other defects.
- Efficient and safe.
- In conformance with AS/NZS 5601.1 and network utility operator requirements.
- Maintenance: Perform the following annually:
- Inspect all gas reticulation including fixings, isolating valves, regulators and safety enclosures.
- Pressure test the whole installation for leaks.
- Provide service tags recording inspections and tests.
Sanitary plumbing
Requirement: Maintain as follows:
- At least annually: Inspect for leaks, repair and report.
- At other times: Attend and clear blockages within 24 hours of notification. Submit a report on the
cause of the blockage.
System performance: Conform to the PCA and network utility operator requirements.
Stormwater
Requirement: Regularly clean and inspection as follows:
- Annually at the end of autumn: Inspect guttering and other rainwater goods. Remove leaves and
other potential blockages. Clean leaf screens.
- At other times: Attend and clear blockages within 24 hours of notification.
System performance: Conform to the PCA and network utility operator requirements.
Hydrants
Hydrants: To AS 1851.
4 SELECTIONS
Provision Requirement
Maintenance period Conform to the 0171 General requirements work
section
ELECTRICAL, COMMUNICATIONS
AND SECURITY SPECIFICATION
Revision: 0
Reviewed/Approved: SB / SC
61 Loftus Street
Leederville WA 6007
T: (08) 9328 5500
E: etc@etcpl.com.au
PROVIDENCE CHRISTIAN COLLEGE PAGE i
REVISION REGISTER
TABLE OF CONTENTS
PART A GENERAL CLAUSES ............................................................................ 7
A1 GENERAL ................................................................................................................................ 7
A1.1 Contract Conditions ............................................................................................................. 7
A1.2 Definitions of Terms ............................................................................................................. 7
A1.3 Scope of Work ..................................................................................................................... 7
A1.4 Order of Precedence ........................................................................................................... 8
A1.5 Assignment/Sub-Contracting ............................................................................................... 9
A1.6 Programming of Work .......................................................................................................... 9
A1.7 Quality Control and Quality Assurance ............................................................................... 9
A1.8 Variation Pricing................................................................................................................. 10
A1.9 Supervision and Coordination ........................................................................................... 10
A1.10 Risk Management / OHS ................................................................................................... 11
A1.11 Design and Certification .................................................................................................... 12
A1.12 "As New" Condition on Completion Date........................................................................... 12
A1.13 Alternative Equipment ....................................................................................................... 12
A1.14 Discrepancies and Queries ............................................................................................... 13
A1.15 Labour ................................................................................................................................ 13
A1.16 Regulations ........................................................................................................................ 13
A1.17 Drawings ............................................................................................................................ 14
A1.17.1 Contract Drawings ..................................................................................................... 14
A1.17.2 Shop Drawings .......................................................................................................... 14
A1.17.3 As Constructed Drawings .......................................................................................... 15
A1.17.4 Purchase of CADD Drawings .................................................................................... 16
A1.18 Existing Site Conditions ..................................................................................................... 16
A1.18.1 Demolition .................................................................................................................. 16
A1.18.2 As Constructed .......................................................................................................... 17
A1.19 Existing Equipment ............................................................................................................ 17
A1.20 Samples ............................................................................................................................. 17
A1.21 Electro Magnetic Radiation ................................................................................................ 17
A1.22 Electromagnetic Interference (EMI) and Electromagnetic Compatibility (EMC) ............... 17
A1.23 Chasing and Openings ...................................................................................................... 17
A1.24 Fire/Smoke Sealing ........................................................................................................... 18
A1.25 Fixing of Equipment ........................................................................................................... 18
A1.26 Fabricated Equipment ....................................................................................................... 19
A1.27 Materials Selection and Corrosion..................................................................................... 19
A1.27.1 General ...................................................................................................................... 19
A1.27.2 Corrosion ................................................................................................................... 19
A1.27.3 Exterior Installations .................................................................................................. 19
A1.28 Painting .............................................................................................................................. 19
A1.28.1 General ...................................................................................................................... 19
A1.28.2 Surface Preparation ................................................................................................... 20
A1.29 Phase Balancing ................................................................................................................ 20
A1.30 Testing, Commissioning and Tuition ................................................................................. 21
A1.31 Thermographic Survey ...................................................................................................... 23
A1.32 Operating and Maintenance Handbook ............................................................................. 23
A1.32.1 General ...................................................................................................................... 23
A1.32.2 Hard Copy .................................................................................................................. 24
A1.32.3 Electronic Copy.......................................................................................................... 24
A1.32.4 Sections ..................................................................................................................... 25
PART D APPENDICES....................................................................................... 73
D1 SCHEDULE OF ACCEPTABLE PITS / LIDS ....................................................................... 73
D2 ENCLOSURE LV ELV SEGREGATION REQUIREMENTS SUMMARY ............................. 74
D3 SWITCHBOARD DESIGN ITP .............................................................................................. 75
A1.5 Assignment/Sub-Contracting
Nominate with tenders, proposed companies for which the work described within this section
of the specification, will be assigned or subcontracted.
Do not further assign or sub-contract any part of the works described in this section of the
specification to another party without the express written approval of the Superintendent.
Refer to preliminaries.
• Check and coordinate all works against shop drawings of other trades and notify
Superintendent of any discrepancies between the electrical services drawings and
other trade drawings;
• Check, coordinate, integrate, accept and endorse shop drawings and submit same to
the Superintendent for review as required;
• Brief, coordinate and liaise with the Contractor, all subcontractors, Superintendent and
Authorities to ensure the supply, installation and commissioning and resultant data
provided for Superintendent’s approval is consistent with the requirements of the
Contract;
• Prepare detailed progress reports on testing and commissioning;
• Detailed programming and interfacing of commissioning activities for all services as
detailed in this specification;
• Arranging meetings with interested parties, including Superintendent and Authorities as
appropriate, to deal with commissioning and testing and to chair and minute such
meetings. Minutes are to be issued within three (3) days to all attendees and the
Superintendent;
• Compilation, checking and endorsement of operation and maintenance documents,
warranties, and ‘As Constructed’ drawings;
• Attend meetings, assist Principal’s staff and prepare status reports on defects during
the Defects Liability period, and submit these reports regularly to the Superintendent.
The Electrical Services Supervisor is also responsible for fully briefing and coordinating the
participation of the Principal’s staff during the testing, commissioning, and handover phases
of all services detailed in this specification to the Superintendent’s satisfaction.
The Electrical Services Supervisor’s participation in the Contract shall commence from the
earliest required time and their Site presence, shall, from that time, be sufficient to inspect all
electrical work, and liaise with Superintendent and Authorities and to attend to other duties as
required.
During the latter period of the Contract, and for at least the commissioning period of the
Contract, the Electrical Services Supervisor shall be located full time on Site to manage the
commissioning process.
Pit depths – over 1200mm deep, confined Risks of storm, flood, fire, intrusion, duress,
space work practice. hazard, industrial relations.
Contract management.
The aim of Risk Management and Job Safety Analysis is to integrate hazard identification into
the construction and maintenance process early to eliminate or minimise the risks of injury
throughout the life of the Facility, Building or Structure. It encompasses components of the
process including facilities, hardware, systems, equipment, products, tooling, materials,
controls, layout and configuration.
The Operation and Maintenance handbook specified herein must include copies of all residual
OHS risk information / JSA’s associated with the construction and maintenance of the project,
along with specific instructions in the safe maintenance and monitoring of all services and
products supplied and installed. Refer to Safe Work Australia’s codes of practice.
Authorities, any associated works required by other trades and any other relevant information
requested by the Superintendent. Technical information shall include manufacturer, supplier,
catalogue reference number, product brochure and comparison sheet of technical
performance between specified and alternative offered.
Where alternative luminaires are offered luminaire technical information shall also include
lighting calculations for all associated areas indicating illumination and glare levels in
accordance with AS/NZS 1680. The maintenance factor used for all calculations shall be
clearly identified and calculations supporting each maintenance factor shall be provided. All
lighting calculations must be certified by an independent qualified Engineer.
Alternate tender prices submitted shall include the clause numbers of the specification to
which the alternatives apply.
No substitution will be authorised through failure of the Contractor to place orders in sufficient
time to avoid delays to the Works other than in circumstances where the Contractor can
demonstrate that delay in material supply is or was beyond the Contractor’s control. No claim
shall arise from any refusal of the Superintendent to approve a substitution.
Where specified materials are unobtainable, notify the Superintendent in time to avoid delays
to the Works. Obtain written instructions from the Superintendent before commencing any
work associated therewith.
Generally alternatives will not be considered after the tender closing date.
All alternative proposals offered after closing of tender date must include a benefit to the
Principal in the form of reduction in cost, improvement in quality or improvement in
performance. Proposals shall also include for the Superintendent costs borne in carrying out
a review of the proposed alternatives. These costs shall be charged at commercial rates and
shall include for all time, travel and redesign required ensuring alternatives are suitable for
use. Confirm costs with Superintendent prior to submission of alternative.
A1.15 Labour
All workmanship shall be of a high standard and only carried out by suitably trained and
qualified labour.
Where necessary, employ specialist tradespersons/service providers to carry out work
covered by the specification.
A1.16 Regulations
Materials and workmanship shall comply with all relevant current Australian Standards, Codes
and Regulations and also reference codes and Standards listed in the prefaces to those
standards and codes. All installations must comply with AS/NZS 3000 Wiring Rules.
Where Australian Standards and Codes do not exist the appropriate International Standard or
Codes shall apply. Request an instruction from the Superintendent for amendments to
Standards, Codes or Regulations that come into effect during the works and affect the works
of the contract.
All work shall comply with the Electricity Supply Authority Regulations, National Construction
Code (NCC), Health Department Regulations, Australian Communications and Media
Authority (ACMA), Local Building Authority, Worksafe, Western Australia and DFES WA
requirements and guidelines.
If any discrepancy exists between the requirements of the specification and the requirements
of Standards or authority regulations, the more stringent requirement shall apply. In each
case however, request an instruction from the Superintendent.
A1.17 Drawings
A1.17.1 Contract Drawings
Confirm the location, electrical ratings and connection details of all electrical equipment and
switchboards furnished by all trades, prior to commencement of installation. Immediately
before installation of cabling or conduiting, re-confirm the location of equipment and
connection details. Refer to Clause A1.14 ‘Discrepancies and Queries’.
All drawings are diagrammatic. Check all relevant dimensions on site before proceeding with
the work. Do not scale dimensions from the drawings.
Include in tender price for any accessory or appliance to be relocated up to 1 metre in any
direction by the Superintendent, prior to any associated works being undertaken on site, at no
additional cost adjustment to contract.
A1.17.2 Shop Drawings
Prepare shop drawings as further specified, in digital (CADD) format.
Submit shop drawings electronically (minimum A3 PDF format unless otherwise specified) to
the Superintendent for examination. A single printed hard copy of each drawing (plus
additional copies where nominated by the Contract Preliminaries) shall be provided on
request.
Shop drawings are to be reviewed and certified correct by a senior representative of
the Electrical Services Company with a signature on each drawing prior to being
submitted for examination. Unsigned drawings will be rejected.
Obtain examined drawings from the Superintendent before manufacture or installation
commences for all fabricated equipment as further detailed herein. Submit shop drawings in
a timely manner, allowing a minimum of twenty-one (21) days for examination prior to return,
unless nominated otherwise.
Comments on “examined” shop drawings will apply to general principles of design only.
Examination of the drawings by the Superintendent will in no way relieve the Contractor’s
responsibility for any errors, omissions or necessity of furnishing such workmanship or
materials as may be required for the completion of these works in accordance with the contract
documents.
Provide shop and detailed design drawings for all fabricated equipment and specialty services
including, but not limited to:
• Switchboards
• Car park Lighting Poles
• Security system
• Communications equipment rack / cabinet details, layouts and elevations
• Luminaire suspension and support systems
• Connections and interfaces to mechanical, hydraulic and lift services
Electrical Services contract drawings indicate design intent only and shall not be reproduced
in specialty services shop drawings. Electrical services shop drawings shall instead be
produced based on the actual equipment, devices, settings and component selections
proposed by the contractor.
Where required, request from the Superintendent and issue architectural backgrounds to
specialty services Subcontractors for production of shop drawings. Include all associated
costs in tender price.
Show on drawings single line schematics, control diagrams, floor plans, elevations,
dimensions, equipment details, panel layouts, labeling, operational descriptions,
compliance/certification, as required to fully describe the system/equipment to be supplied,
installed and/or commissioned. Shop drawings shall contain reference to all work required by
all trades.
Specialty services shop drawings shall be upgraded to ‘As Constructed’ status, at the
completion of the project, as defined herein.
A1.17.3 As Constructed Drawings
Prepare comprehensive ‘As Constructed’ drawings, detailing all equipment and services
installed within the scope of work defined within the contract documents. As Constructed
drawings shall show location of all equipment, circuit details, single line diagrams, switchboard
layouts, equipment rack layouts, system schematic diagrams, details of special items of
equipment and requirements as nominated for shop drawings.
As Constructed drawings shall show the exact depth and location (±300mm) of all inground
services excluding final circuit conduits. Such services shall be dimensioned off actual
building lines or surveyors datums.
Drawings shall not make reference to construction notes or information relevant only to the
construction process. All information associated with specialty systems shall not appear on
general electrical services drawings.
As Constructed drawings shall be prepared in CADD format. All CADD drafting shall be to
Australian Standards unless otherwise specified. Confirm exact requirements with the
Superintendent in each case, prior to submission.
All ‘As Constructed’ drawings shall incorporate the supplier’s and/or supplier’s company title
block. A statement shall be provided on each drawing, to read: ‘As Constructed by (company
name and telephone number)’ and signed and dated by a senior representative of the
company. The signatory’s name and position within company shall also be provided in block
capitals. Title block shall clearly incorporate Engineering Technology Consultants as Electrical
Consulting Engineers.
Preliminary ‘As Constructed’ drawings shall be prepared and submitted for the
Superintendent’s review, before completion of commissioning. Preliminary drawings shall be
examined by the Electrical Services Company or Installer and signed to confirm the
preliminary drawings are representative of the equipment and systems installed.
Where a total electrical services drawing or parts of a drawing are superseded by a shop
drawing (as built status drawing) the original drawing shall be amended and clearly notated
as cross referenced to the new as built drawing.
Upon completion of commissioning and in no case less than two (2) weeks prior to practical
completion, submit final approved drawings. Each drawing shall be signed and verified correct
by the Electrical Services Company, or Installer. Unsigned drawings will be rejected without
further review.
Supply one (1) set of CADD disk(s), electronic copy of ‘As Constructed’ drawings in PDF
format and one (1) set of full size drawing prints, for each maintenance manual. In addition
provide one (1) No. set of CADD disk(s) containing an electronic copy of ‘As Constructed’
drawings in CAD and PDF format to Superintendent.
A1.17.4 Purchase of CADD Drawings
Contract drawings may be purchased from Engineering Technology Consultants, in electronic
media format. An administration cost of $6.00, plus GST, per drawing file (subject to a
minimum charge of $28 per issue) will apply. Electronic media drawings will be issued in CD
format. Where Architectural backgrounds are required to form the basis of specialty services
shop drawings, delete all electrical services information from the drawing in order to obtain
the clear Architectural background.
Issue a written order, stating the drawings numbers required, to the appropriate value as noted
above, and prior to electronic drawings being issued by Engineering Technology Consultants.
A1.18.2 As Constructed
Using the marked up electrical and communication service plans CAD draft all existing
services which remain underground following completion of the project works to provide an
‘As Constructed’ record of the existing and modified services remaining.
This shall be setup as a separate CAD layer over the new services to Superintendent’s
approval.
A1.20 Samples
Submit samples and colour range of each type of light fitting, switch and outlet to be used prior
to ordering and delivery to site, for approval. Catalogue pamphlets may be accepted in lieu of
samples as agreed by the Superintendent. Verify requirements with Superintendent in each
case. Where night testing is required for specific luminaires orders are not to be placed until
night testing approval and luminaire approval has been obtained.
Obtain approval for all samples in a timely manner to ensure that the item of equipment can
be supplied and installed without impact on the construction programme.
Chase conduits or otherwise conceal conduits in masonry to be rendered. All chases and
openings shall be in accordance with Australian Standards and suitable for the application of
specified finishes.
Fire and smoke stop openings in fire and smoke rated walls, floors or ceilings to approval with
a material which meets current National Construction Code (NCC), DFES WA and Worksafe
Requirements.
• Where aluminum material is shown or proposed this shall be LM6 marine grade (to
BS1490) or equivalent (e.g. switchboards, CEC).
• Where hot dip galvanized material is shown or proposed, this shall be painted to Cat
5D to AS/NZS 2312 and to approval (e.g. poles).
All exterior fixings including pole, luminaire, socket outlets etc. shall be 316 grade stainless
steel. During manufacture or installation, all exposed threaded and bolted or screwed fixings
shall have a corrosion inhibitor such as graphite or lanolin grease applied.
A1.28 Painting
A1.28.1 General
Remove or otherwise protect flush plates, luminaires and all similar equipment that could be
disfigured during painting. Correctly and permanently re-install or remove protection on all
equipment after completion of painting.
Paint all equipment including cable supports, cable trays and ducts, conduit luminaire
supports, unistrut framework and all fabricated equipment unless otherwise specified or where
concealed from view in ceiling spaces. Equipment located in plant rooms generally do not
require painting unless otherwise stated. Finished surfaces of all paintwork shall be free from
bubbles, runs or any other imperfections. All galvanised surfaces shall be suitably heated and
degassed prior to painting to prevent air pin holes in final paint finish.
All surfaces to be painted shall be free of rust, scale, oil and other foreign matter, and then
painted with one coat of compatible etching primer, zinc primer or similar corrosion resistant
barrier to suit the material being painted and the finishing coats to be applied. This shall be
followed by two coats of approved wet spray polyurethane or powdercoat paint in accordance
with AS 4506, to an approved colour. All external metal work shall be aluminium, hot dip
galvanised or stainless steel. Paint finish to external metalwork shall be finished with two
coats of approved colour Dulux or equal two pack polyurethane epoxy paint in accordance
with AS/NZS 2312 (pur5) Cat 5 unless otherwise specified as powdercoat where it shall be in
accordance with AS 4506 Cat 5.
Carry out all surface preparation, painting and curing in accordance with the paint
manufacturers recommendations and data sheets.
Hot dip galvanise metal surfaces not requiring painting (e.g. where concealed in ceiling
spaces, in plant rooms) or protect against corrosion by application of an approved corrosion
inhibitor suitable for the installed location. Hot dip galvanising shall be to AS/NZS 4680 unless
otherwise specified.
A1.28.2 Surface Preparation
Prior to any painting the surfaces to be painted shall be prepared as follows:
• All sharp edges and points must be rounded and smoothed using a suitable grinder
then sanded.
• Any porosity, holes, flat spots, indentations or the like in the material surface shall be
filled with weld or approved filling compound. The surface is to then be smoothed using
a suitable grinder then sanded.
• Where porosity is detected after paint is applied, the paint is to be removed and the
porosity filled then smoothed as above.
• All weld splatter is to be removed using a scraper, wire brush or sander.
• Ensure close fitting surfaces such as light pole access doors have adequate clearance
gap all round after painting to accommodate the dry film paint thickness (DFT) on both
surfaces.
Insulation Test - For all mains, sub-mains and final sub-circuits. Test
between each live conductor (including neutral) and
earth and individually between conductors of a circuit.
Earth Fault Loop Impedance - Test for compliance in accordance with Clause 8.3.9 of
AS/NZS 3000.
Description By
“We certify that the Emergency Lighting System was installed in compliance with AS 2293,
AS/NZS 3000, the design specification and drawings and all statutory requirements. The
Principals Representatives have been trained in system operation and basic maintenance”.
The certification is to be made on company letterhead stationery and is to include ACN/ABN
and licence numbers.
Practical completion cannot be granted without Completion Certificates and O&M manuals.
• Details of company and personnel carrying out the test, including qualifications of
personnel;
• Project details, site address and date;
• Methodology statement on how the survey was conducted, switchboards surveyed and
conditions at time of survey including external ambient temperature and commentary
on any loads not connected or not likely to be drawing full load at time of survey, or
anything that could influence the outcome of the survey;
• Survey results including time of survey, normal and thermal images, room and/or
enclosure ambient temperature and load (amps) drawn by the switchboard or
equipment at time of survey;
• Analysis of results including identification of any faults, abnormal conditions and
recommendations;
• Details of equipment used to carry out the survey including serial number, calibration
records etc.
The report shall be certified correct and wet signed by a senior representative of the company.
Submit report to the Superintendent for review prior to practical completion. Include a copy of
the report in the Operating and Maintenance Handbook.
Maintenance Handbook complete with all ‘As Constructed’ drawings must be submitted
for approval at least two weeks, before application for practical completion. The final
submission shall include a written certification from the Contractor that the Operation and
Maintenance Manuals and all information therein, including As Constructed drawings, and has
been completed satisfactorily and in accordance with the contract.
A1.32.2 Hard Copy
Bind literature and drawings in hard bound A4 size handbooks in commercial quality 4-ring
binders with white coloured hard covers with each indexed, divided and titled. Features shall
include:
Hard copy shall include:
• Ring size: 50 mm maximum, with compressor bars.
• Cover: Identify each binder with typed or printed title (PROJECT NAME, SERVICES
NAME, VOLUME No.) OPERATION AND MAINTENANCE MANUAL, to the spine and
front. Index: Provide an overall index for each section inside the front cover of each
Volume and sub index at the start if each section.
• Dividers: Durable divider for each section separately identified, with typed description
of system and sub sections for major equipment components. Clearly print index
number and short title on laminated plastic tabs.
• Brief description of each system at start of each section.
• Copies of Risk, Safe Design, Job Safety Analysis sheets for all constructed and
maintainable items and their safe use.
• Copies of all equipment guarantees suitably completed and dated.
• Copies of all literature elsewhere required by the Specification.
• Specific operating and maintenance instructions for all equipment and systems, with
programmed maintenance schedules and safe work practices action sheets (JSA’s).
• Copy of all test results and reports specified.
• Contact list of all companies supplying and/or installing works under this contract.
• Contact list of all maintenance companies, which carry out maintenance of the specified
works.
• List of maintenance requirements for each system.
• Asset register of all major items of equipment and all serviceable items with full technical
details and identification of key characteristics, service dates, etc
• As-constructed information including A3 copies of as-constructed drawings, folded to
A4 size, individually inserted in protective removable covers. Drawings shall include:
- As-constructed Contract drawings
- As-constructed equipment shop drawings;
- As-constructed speciality system drawings.
• One (1) electronic copy as further described below.
A1.32.3 Electronic Copy
Provide an electronic copy of the material contained in the hard copy on a suitable sized USB
flash drive.
The material shall be in PDF format. Drawings shall be provided in both PDF and native
fromats (e.g. DWG, DGN, Revit etc.).
Files shall be logically named and organised in folders that correspond to the sections of the
hard copy.
A1.32.4 Sections
The following additional individual sections shall be provided in the manual as per the following
table.
SECTION DESCRIPTION
Switchboards • Description of site power distribution and isolation points in the event on emergency or
fire
• Schedule of all switchboards – reference / identifier, manufacturer’s name and contact
number
• Schedule of all equipment installed, including technical literature, manufactured part
numbers, manufacturer’s name and contact number
• Copy of all site specific information including, circuit schedules, circuit breaker settings
• Operating and Maintenance requirements including associated operating and
maintenance instructions, test procedures, JSA, PPE requirements, etc
• Copy of As Constructed switchboard shop drawings
• Copy of Switchboard manufacturers ITP and Factory test results
• Copy of all relevant technical data supporting compliance of the works with Contract
requirements
• Additional requirements as nominated herein or required by Statutory Authorities
• Copy of all circuit schedules
• Maintenance requirements RCD test, injection testing, risk analysis, JSA’s, etc
Lighting • Schedule of all light fittings complete with the following:
- Description of fitting (as per legend sheet) including all accessories
- Fitting catalogue number, lamp type, rating, colour temp, beam angle, control gear
or driver type and catalogue number
- Manufacturers or local suppliers name, addresses and contact details
• Luminaire data sheets and control gear details, performance, specifications,
compliances and relevant certifications
• Maintenance requirements for all light fittings: e.g. testing and inspections, cleaning
materials, relamping strategy, maintenance risks / JSA’s, PPE, etc
• For emergency lighting fittings a schedule showing drawing number for luminaire
positions, unique luminaire identifier and type of luminaire
• Additional requirements as nominated herein or required by Statutory Authorities
Fittings and • Schedule of all equipment installed, including technical literature, manufactured part
Accessories numbers, manufacturer’s name and contact number for:
- Cable tray and ladder
- Cable duct
- Conduits
- Pits
• Copy of Certification of cable tray / ladder and support systems to carry installed cable
loads
• Copy of Certification of cable tray / ladder and support systems to comply with fire rating
to AS 3013
• Copy of all relevant technical data supporting compliance of the works with Contract
requirements
• Operating and Maintenance requirements including associated operating and
maintenance instructions, test procedures, JSA, PPE requirements, etc
• Additional requirements as nominated herein or required by Statutory Authorities
Cables • Schedule of all cables installed, including technical literature, manufactured part
numbers, manufacturer’s name and contact number for:
- Electrical cables (LV)
- Electrical cables (ELV)
- Electrical cables fire rated to AS 3013
- Communications cables (CAT 6A)
- Communications fibre optic cabling
• Copy of all relevant technical data and Certification supporting compliance of the works
with Contract requirements
• Additional requirements as nominated herein or required by Statutory Authorities
Communications • Description of system
Structured • Schedule of all equipment installed, including technical literature, manufactured part
Cabling System numbers, manufacturer’s name and contact number
• Copy of all site specific information including settings, custom modifications, etc
• Operating and Maintenance requirements including associated operating and
maintenance instructions, test procedures, JSA, PPE requirements, etc
• Copy of As Constructed shop drawings
• Copy of manufacturers ITP and Factory test results
• Copy of all relevant technical data supporting compliance of the works with Contract
requirements
• Additional requirements as nominated herein or required by Statutory Authorities
If reported defects are not rectified within an acceptable period, or maintenance is not carried
out, the Superintendent shall issue two (2) weeks written notice to complete the work. If works
are not completed within an approved timeframe, suitably qualified companies, selected by
the Superintendent, will be authorised to carry out the work and associated costs will be
deducted from retention monies.
A1.34 Keys
Three (3) sets of keys shall be provided to the Superintendent at Practical Completion for all
lockable devices and enclosures. Where site standard key system exists, all locks shall be
keyed alike to match the master key system. Confirmation required for keying prior to
manufacture.
B1.1 General
Design all equipment to operate on the Supply Authority power supply.
Make all necessary arrangements with the Supply Authority and furnish all necessary
provisions for service.
Where works include new or modifications to existing incoming service, on commencement of
works on site issue the service provider (Western Power unless otherwise specified) with the
“Preliminary Form” and “request For Network Service” forms, and a copy of the site drawing
and building programme. Copy of advice to be forwarded to the Superintendent. Unless
otherwise specified, pay all service provider fees and charges associated with the new or
modified service.
B2 EARTHING - GENERAL
B3 SWITCHBOARDS - GENERAL
B3.1 Manufacturer
Engage a switchboard manufacturer to design, construct, test and commission the
switchboards. The engaged company must be a member of the National Electrical
Switchboard Manufacturers Association (NESMA). The following companies are pre-
approved:
• Arc Switchboards
• C.P.E. Pty Ltd
• Nilsen Electrical Switchboards
• NRP Switchboards
• Plummers Switchboards
• Ray Brookes Pty Ltd
• SJ Electrics
• PGS Industries
• Price Trandos
Any others must be approved by the Superintendent.
B3.2 General
Switchboards shall be complete with all necessary components, comply with AS/NZS 61439
and be designed and constructed in accordance with this specification and contract drawings.
B3.2.1 General Requirements
All switchboards shall have a minimum of 25% spare spaces for additional circuit protection
and control devices. Spare spaces shall include busbars, mountings and individually blanked
openings (e.g. spare poles on MCB chassis’ shall have insert-type pole fillers).
All switchboards shall have metal enclosures and all metalwork shall conform to General
Clause ‘Fabricated Equipment’. Finish switchboards inside and out in accordance with
General Clause ‘Painting’.
Paint all switchboards white internally or in an otherwise approved colour.
Paint all switchboards externally in an approved colour.
Provide anti-graffiti treatment to all external switchboards unless otherwise approved.
Switchboards shall be the front access type with escutcheons unless otherwise shown.
Unless otherwise specified, the top of the switchboards shall be 2000mm above floor level.
Miniature Circuit Breakers (MCBs) are to be mounted on proprietary brand mounting chassis
complete with busbars unless approved otherwise. Split or cut chassis’ will not be accepted
where separate chassis’ have been identified on the drawings.
Cover spare busbar arrangements and tags for future circuit breakers with either heat shrink
sleeving or proprietary insulating shrouds or caps.
Neutral links shall have at least as many terminals as to suit full incoming and outgoing active
cable capacity (including spare spaces). The terminals shall be numbered and connected to
correspond with the fuse or circuit breaker numbers.
Plate all hardware to prevent corrosion.
Unless otherwise specified, key all locks alike to Electricity Supply Authority standard. Refer
to clause “KEYS” herein for key details.
Self-tapping screws shall not be used anywhere in the construction of switchboards.
Unless otherwise specified use a single brand throughout the project for each type of
equipment (e.g. MCBs, contactors, fuses, switches etc). All switchboard protective devices
and components shall be of a manufacturer with locally available spare parts / replacements
and regional technical support.
Observe maximum and minimum mounting heights for equipment and devices (e.g. controls,
safety switches, displays etc.) per AS/NZS 3000 and AS/NZS 61439. Ensure minimum and
maximum mounting height requirements for Electricity Supply Authority meter panels in
accordance with Supply Authority standards are achieved. Confirm that the height
requirements are achieved to standing area finished floor/ground level on site after installation
of the switchboard, accounting for mounting plinth, concrete foundation (if applicable) and
potential level differences due to sloping surfaces (e.g. external paved areas). For external
installations in particular, the installed height of the equipment or device after installation may
differ and the Contractor shall be responsible for ensuring this is checked and accounted for
in switchboard design and/or installation methods.
B3.2.2 Identification
Provide a label fixed to the front elevation of the switchboard to detail manufacturer, fault
rating, form construction, submain cable type and size and source of supply.
All equipment and devices shall be labelled to identify function and service it provides to
approval.
Uniquely identify all sub-circuit protection devices with labels that correspond with the single
line diagram with the use of numbered phase markers (e.g. red markers - 1, 2, 3 etc, blue
markers - 1, 2, 3 etc) or engraved traffolyte fixed to panels or escutcheon plates, secured in
line and centered directly adjacent the related items. Where multiple chassis’ are installed for
a single switchboard, ensure numbered phase markers are sequential and numbers are not
duplicated across chassis.
Where an alternative labeling format is noted on the drawings, engraved traffolyte glued and
screw fixed adjacent to the protective device(s) shall be utilized.
Multi-module devices on chassis shall be identified by a single marker only to ensure accurate
identification and the chassis poles increased as required to achieve the nominated spare
spaces required.
Multiple master meters shall be labelled to approval.
For all switchboards containing RCD units, either integral or within the field wiring, install a
label to the chassis escutcheon plate to read ‘Warning: RCD’s installed on this switchboard
and in the field, do not megger. Refer to circuit schedule’. Label to be green on white.
Clearly label all other devices on switchboards stating their function and unique identification
corresponding with the drawings.
Clearly label all contactors, controls and the like installed behind escutcheon stating their
functions using labels as specified above.
B3.2.3 Legend and Drawing Holder
Provide a circuit schedule holder for each switchboard and secure it inside the switchboard
doors. All circuit details shall be typewritten on a circuit schedule card and placed in the
schedule holder. Circuit details shall include circuit reference, circuit description, rating of
protection device and size of cable for each circuit.
The card shall also show the customer's name for each multiple master meter, where such
metering is fitted.
Provide a separate drawing holder. Holder shall contain switchboard As Built drawings and
shall also contain site plans in accordance with AS/NZS 3000 – Clause 3.11.4.6.
B3.2.4 Bus Bars
Busbars shall be completely insulated with colour coded heat shrunk sleeving, or otherwise
protected by clear polycarbonate barriers to IP2X, in accordance with AS/NZS 61439.
Busbars shall be design and brace for the fault current shown on the drawings or available at
the point of installation applied for one second.
Ensure that busbar systems are re-torqued after transport to ensure busbar fixings have not
loosened off since factory setting.
Bus bars shall be sufficiently sized to ensure space for bolting of all cable lugs, ensuring lugs
achieve full contact on the bar. Lugs overhanging the bar and not achieving full contact will be
rejected.
B3.3 Enclosures
Enclosures generally shall be steel unless exposed to weather where they shall be aluminium
or stainless steel. Where aluminium it shall be marine grade (5000 or 6000 series to BS 1490
or equivalent) with brushed external finish unless otherwise indicated.
Isolate aluminium from dissimilar metals, masonry and concrete. Use aluminium channel for
mounting of aluminium enclosures in lieu of steel. All switchboards exposed to the weather
shall be minimum IP54 rated to AS 60529 and fitted with weatherproof and insect proof
ventilation. All fixings into aluminium shall be 316 stainless steel.
External switchboards shall be constructed with a sun shield and rain hood to the top section
of the board. The shield shall be welded to the panel roof, open at both ends and provide for
sufficient slope to avoid ponding of water. Provide details for comment with shop drawings.
Ground mounted external enclosures shall be fixed to an inground concrete foundation
suitably sized to retain the switchboard. Foundation to extend 150mm above ground level.
Provide a watertight, vermin proof seal between switchboard base and the foundation..
External switchboards shall be provided with an anti-graffiti treatment applied after surface
finishing in accordance with system manufacturers application instructions, relevant clauses
of AS/NZS 2311, and this specification “Painting”. Submit proposed “Anti-Graffiti System” for
approval prior to application.
Select equipment and size enclosures to suit cupboards, ducts or spaces provided. Confirm
exact dimensions of areas available and clear opening dimensions in the case of door frames
with Architect prior to preparation of shop drawings to ensure switchboards can be installed
and removed through final finished clear openings.
Switchboard enclosures shall be complete with suitable gland plates for bottom and/or top
entry as required to suit cable entries. Gland plates design shall minimise circulating eddy
currents.
Switchboard enclosures shall be complete with door(s) unless otherwise specified. Doors shall
be hinged, lockable and secured shut in three locations, top, middle and bottom. Door locking
devices shall be “Lock Focus” stainless steel swing lockable handles with recessed key barrel
or equal approved. During design of all switchboards, particular attention must be paid to the
prevention of inadvertent contact with live parts during inspection of equipment, by use of
insulation or barriers in accordance with AS/NZS 61439.
Doors shall open through 100 and when installed externally be complete with captive stays
to hold open against wind.
Doors shall be earthed by means of 4mm2 copper braid.
Circuit breakers shall be rated for the prospective fault current available at the point of
installation, or the fault current nominated on the drawings, whichever is the greater.
All trip units shall be suitable for continuous full load enclosed operation with such trip rating
nominated on the drawings or as specified herein. Commission all trip units to meet authority
requirements and discrimination co-ordination requirements specified herein.
Transformer isolating switches for Supply Authority Transformers or for transformers of
500KVA rating and greater shall be Withdrawable Air Circuit Breakers (Withdrawable ACB’s).
Moulded Case Circuit Breakers (MCCBs) shall be used for protection of all circuits of 100A
rating or greater and whenever such protective device is utilised for submains protection and
/ or isolation. MCCB’s may only be used as transformer isolating switches for transformers
rated at less than 500KVA and used in combination with line-side transformer isolating links
sized to suit 110% of transformer capacity.
For all adjustable circuit breakers, detail frame size and settings on the submitted shop
drawings. In some instances, electronic trip units must be used to ensure compliance with
earth fault loop impedance. Obtain earth cable sizes prior to final selection of trip units. Final
settings shall be recorded on as built single line diagrams.
Miniature Circuit Breakers (MCBs) shall be utilised for the protection and control of all
subcircuits rated at less than 100 Amps, unless otherwise specified.
B3.4.2 Moulded Case Circuit Breakers (MCCBs)
Moulded Case Circuit Breakers (MCCBs) shall be constructed of a non-conducting low
hydroscopic case that will not fail under the maximum electrical, thermal or mechanical
conditions possible at the point of installation.
MCCBs shall comply with AS/NZS 60947.2.
All MCCBs shall be fitted with adjustable trip units. Electronic trip units shall be installed for all
MCCBs rated at 400A or greater, or where nominated on the drawings or to achieve electrical
performance requirements (e.g. earth fault loop impedance or discrimination) nominated
herein.
All moulded case circuit breakers shall be fitted with positive “flag” identification of open or
closed positions, or shall otherwise be clearly labelled for rapid identification of switch position.
Where used as transformer protection in accordance with this specification, MCCB’s shall be
fitted with fully adjustable short time and long time overcurrent and earth fault trip units as
specified for ACBs.
B3.4.3 Miniature Circuit Breakers (MCBs)
Miniature circuit breakers (MCBs) shall have a minimum fault interrupting capacity of 10kA.
Where back-up protection is provided via the upstream device (i.e. cascading) in accordance
with manufacturer’s requirements, MCBs with a lower fault interrupting capacity may be
utilized to approval.
All MCBs shall have ‘C’ curve tripping characteristics unless otherwise specified. MCBs shall
comply with AS/NZS 60898.1 It is the responsibility of the switchgear manufacturer to certify
acceptability prior to submission of shop drawings.
MCB’s shall be installed on proprietary, fully insulated and colour coded MCB chassis.
MCB’s shall be of a readily and locally available manufacture.
Non Auto MCB’s shall not be used as isolators.
MCB’s shall not be utilised for submain protection unless otherwise approved or specified
herein or on the drawings.
B3.4.4 Residual Current Devices (RCDs)
RCDs shall be with integral overcurrent protection (RCBOs) to AS/NZS 61009 unless
otherwise noted.
The requirements for RCBOs shall be as per section ‘Miniature Circuit Breakers (MCBs)’, with
additional requirements as follows.
RCBOs shall have a rated operating residual current not exceeding 30mA in accordance with
AS/NZS 3000. Devices with 10mA sensitivity shall be used where noted on the drawings or
required by AS/NZS 3000. Tripping shall be ensured for residual sinusoidal alternating
currents (Type AC RCD per AS/NZS 61009.1).
RCBOs shall be of single pole width for single phase circuits, and shall be installed on all light
and power circuits required by AS/NZS 3000.
Multiphase sub-circuits requiring RCD protection shall be RCBOs.
B3.5 Fuses
B3.5.1 H.R.C. Fuse Units
Fuses shall only be used where shown on drawings or where prior written approval is given.
The fuse fittings shall have fully shrouded bases and carriers. H.R.C. fuse cartridges shall be
GEC or approved equal standard T type, Class Q1.
All fuses shall be the HRC gG type unless otherwise shown.
B3.5.2 Spare Fuses
Provide one set of three (3) spare HRC fuse cartridges for each rating and type of fuse
incorporated on each switchboard. Mount these fuse cartridges neatly on racks located in a
section of the switchboard front zone.
B3.6 Escutcheons
Escutcheons shall have turned edges, chrome lift off handles, locating pins and chrome
captive thumb screws with screw slot. Provide locating pins at a rate of one pair for each
450mm length of escutcheon or part thereof.
All operating devices including reset buttons shall protrude through escutcheons.
All fixings for escutcheons shall be complete with internal star metal captive washers.
Paint all escutcheons in approved colour.
All escutcheons shall be designed to prevent inadvertent contact of the escutcheon with live
parts during removal and installation by means of insulation or barriers to AS/NZS 61439.
Escutcheon plates equal to or greater than 900mm high shall be installed with lift off hinges in
addition to chrome captive thumb turn screws and lift off handles.
Starters shall have thermal overload in all three phases and single phasing protection. Size
overloads to suit motor nameplate data and in accordance with manufacturer's
recommendation.
Install contactors and motor starters with adequate clearances from other equipment as
recommended by the specific equipment manufacturers.
B3.11 Wiring
Wiring shall be neatly run, generally contained in slotted PVC cable duct or harnessed in an
approved manner such that any cable can be readily traced.
Use compression type lugs to properly terminate all cables where suitable tunnel terminals
are not provided.
Label active neutral, and earth conductors using numbered and phase coloured printed type
coded ferrule type proprietary brand cable markers at protection device, earth bar and neutral
bar. Neutral labels shall be black with white lettering R1, R2, etc. Tape markers are not
acceptable.
Each active, neutral, and earth cable is to be identified with its corresponding I.P.A. marked
fuse/MCB.
Mark control cables to correspond with terminal numbers on shop drawing control diagrams.
Show all label wording, positions, details, and clearly indicate the fault ratings of all protective
devices and busbar assemblies on shop drawings. Submit detailed control diagrams for all
control circuits, complete with termination and cable schedules.
Shop drawings shall comprise of the following:
• Minimum A3 drawing sheet size;
• Produced using Autocad or equivalent electronic drafting package;
• Manufacturer’s drawing sheet title block identifying the project name, project number,
drawing number;
• Minimum scale of 1:10;
• Include equipment materials list with part numbers;
• Labelling schedule noting size and colour of lettering and background;
• Switchboard general arrangements; front elevations with escutcheons fitted and without
escutcheons, minimum one section both vertically and horizontal;
• Confirm form construction;
• Confirm fault rating;
• Diagrams for all control equipment, (e.g., lighting controls, meters, relays) complete with
terminal strip numbers;
• Schedule of construction details confirming as a minimum material type and sizes used,
colour, handle types, locks and all hardware, etc;
• Simplified single line diagram clearly showing all principle equipment, busbar and
internal wiring, fault rating of equipment and protective devices. The diagram must
identify proposed detailed design and construction and therefore shall not utilise
consultant’s drawings;
• Where protective devices are fitted with adjustable settings, confirm settings on the
drawings;
• Provide Manufacturers pamphlet details of any proprietary equipment used as part of
the switchboard construction, e.g. meters, relays, contactors, time clocks, and push
buttons.
All switchboard designs and shop drawings must be checked and endorsed by the Contractor
for correctness prior to submission to Superintendent. The Superintendent will reject shop
drawings that have not been so endorsed.
B3.14 Discrimination
Prior to submission of tenders and again prior to selection of switchgear supplier, the
switchboard manufacturer must ensure discrimination can be achieved as follows. The
switchboard manufacturer must obtain submain cable details from the design drawings to
ensure discrimination and earth fault loop impedance requirements are met.
Co-ordinate the protection equipment on all main and distribution switchboards such that in
the event of any condition of over-current or short circuit occurring at the load side of terminals
of any submain protective device or final subcircuit equipment isolator/connection device to
the full prospective fault level of the installation;
Devices shall have a maximum load current IL equal to the circuit protection device rating.
Additionally, filters shall reduce the voltage rise time (dv/dt) to a maximum of 100V/us.
B3.17.3 Performance
Performance of a surge protection device shall be based on the testing methods of IEC 61643-
11 and AS/NZS 1768. The device should meet Class I, II or III as per IEC 61643-11.
Devices tested to UL 1449 Ed 3 but not IEC 61643-11 shall be reviewed by the
Superintendent.
B3.17.4 Performance Criteria
Generally, unless otherwise specified on the drawings, SPDs shall meet the following
minimum performance requirements, depending on where on the electrical network the device
is located, as follows:
BMSB DB
Voltage protection level @ 3kA, 8/20us (Up) < 1kV < 750V
Devices with visual indication of health shall protrude through the switchboard escutcheon.
B3.17.8 Approved Manufacturers
The following manufacturers are approved:
• ABB
• Ciprotec
• Dehn
• Eaton
• Erico
• Novaris
• Schneider
Alternative manufacturers may be considered only if certification of product compliance to IEC
61643-11 can be provided and certified by an electrical engineer whom holds registration
(NER) with Engineers Australia or equal internationally recognized registration body. Results
of testing by a NATA accredited laboratory that demonstrates compliance to IEC 61643-11
shall be available on request.
B3.17.9 Warranty
All devices shall be provided with a minimum 5 years warranty.
B4.1 General
B4.1.1 Standards
Generally, refer to AS/NZS 3000 and AS/CA S009 for minimum requirements for underground
electrical and telecommunications installations.
Other standards that shall be adhered to include:
• Utility Provider’s Code of Practice for minimum separations in verges and road reserves;
• AS/NZS 2067 for high voltage installations;
• ACIF C524 and G645 for communications carrier installations;
• AS/NZS 3084 and AS/NZS 14763.2 for telecommunications installations;
• Utility/authority standards where installing utility services or in proximity to utility services.
B4.1.2 Trenching and Excavation
All excavation work shall be carried out in accordance with the requirements of WorkSafe WA
Code of Practice – Excavation and the Principal’s Safety Procedures and Instructions.
Before trenching, make thorough enquiries and take every reasonable precaution to locate
and avoid damage to existing services. Replace all damage to existing services caused by
failure to comply with this specification.
Excavations shall provide the specified minimum cover to avoid damage or loss of support to,
obstacles such as pipes, drains, cables and other utilities and services; and the excavated
area shall be reinstated in accordance with Principal’s requirements.
Keep trench widths to the minimum, sufficient for satisfactory and safe working conditions and
to provide the specified minimum bedding and cover of services so as to avoid damage or
loss of support to, ducts, cables, drains and other utilities and services.
If excavated material cannot be used for filling or backfilling, remove it from the site in
accordance with the environmental specification.
Open trenches and excavations including excavation for cable joints shall be protected against
entry of water from any source.
During trenching and excavation make sure that water is prevented from flowing into the
excavations. Where this is not possible, undertake all works necessary to adequately dewater
the trench or excavations. Installation of cables and equipment, bedding or backfilling and
compaction must not be undertaken where water is present.
Place "DANGER ELECTRIC CABLE UNDER" orange PVC tape or polymer cover strip at 50%
burial depth below ground along all electrical cable routes to AS/NZS 3000. Place “DANGER
COMMUNICATIONS CABLE UNDER” white PVC tape to AS/CA S009 and S008.
Record as built locations of all underground cabling routes. As built copy of electrical cable
routes shall be provided in site main switchboards in accordance with AS/NZS 3000.
B4.1.3 Bedding and Backfilling
Supply imported bedding sand approved for bedding of direct buried cables. Sand shall be,
clean sand free of rocks, clay lumps, tree roots, building rubble, metal, glass, sharp objects,
organic solvents or other deleterious material that is likely to damage cables.
Sand used for bedding of direct buried power cables shall be imported yellow brickie’s sand
and shall surround the cable of minimum 200mm thickness unless otherwise noted.
Imported bedding sand is not required for cables installed in conduits. Conduits shall be laid
on compacted clean fill providing minimum 200mm thickness around the conduit.
Backfilling shall not commence until inspections have been completed and approved by the
Superintendent and Principal.
Backfill shall be equal to the original excavated material / surrounding soil.
Where cables and/or conduits are laid beneath other buried services, ensure that the backfill
beneath such services is adequately compacted to prevent damage to the other buried
services, due to inadequate support.
Where installed under roadway and the like, compacted soil and backfill shall be in not more
than 300mm layers to a compaction equal to that specified for road works.
The surface shall be reinstated to its original condition. Make good to all lawn, paving, gardens
and finished surfaces to original condition.
B4.1.4 Separation of Services
Minimum separation to services in accordance with relevant standards shall be observed at
all times.
Generally, refer to AS/NZS 3000, AS/CA S009 and referenced standards for minimum
separation required for electrical and telecommunications installations.
B4.1.5 Directional Boring
Provide horizontal directional boring, carried out by suitably qualified personnel.
Utilize accurate and proven guidance equipment and procedures to undertake the works.
Make all necessary investigation and examinations of the site conditions to determine the
suitability of the works.
The Contractor undertaking the boring works shall supply a log for the total length of the bore
for inclusion on the “As Constructed” construction records. The Log shall include for each
bore, as a minimum:
• Contractor details
• Location;
• Size and number of conduits installed;
• Depth below finished surface level to the top of the bore at 3m spacing.
Where required, bends shall be pre-fabricated large-sweep bends of suitable bend radius that
exceed the cable minimum bend radius. The bending radius of the cable whilst under tension
(during installation) shall be used and not the set in position bending radius.
B4.2.3 Couplings
PVC conduit fittings shall be coupled with a suitable PVC cement or adhesive that forms a
durable and watertight seal.
B4.2.4 Depth of Cover
Minimum depth of cover for underground power shall be in accordance with AS/NZS 3000
and AS/NZS 2067, generally 500mm for LV and 750mm for HV. Depth of cover may be
reduced in specific situations as defined in AS/NZS 3000, however approval must be sought
in each case.
Minimum depth of cover for communications conduits shall be a minimum of 450mm. Depth
of cover may be reduced in specific situations as defined in AS/CA S009, however approval
must be sought in each case.
Where installing conduits beneath railway, conduit depth of cover shall be increased as
required by the relevant authority.
B4.2.5 Empty Conduits
Provide a 2.5mm2 PVC insulated copper draw wire or suitable nylon rope in each spare or
empty conduit.
B5 CABLING – GENERAL
B5.1 General
Wiring shall be carried out with stranded copper conductor, Class V-75/V-90, PVC insulated
and sheathed, 400/750V grade or with X-90 or X- 110 XLPE insulation and sheath.
Cables with alternate insulation used in accordance with AS/NZS 3000 and AS/NZS 3008,
with higher current rating than the specified cable, may be used in lieu of specified cables.
All cables shall be new and delivered on site in unbroken reels with maker labels attached.
Loop all cables (including mains, submains and final circuits) from point to point without joints
and with terminations only at switchboards, devices, switches or outlets. Cable joints shall not
be permitted unless otherwise indicated on the drawings, or where cable run length exceeds
standard cable drum length. If in-line joints are required, they shall be carried out using
proprietary jointing kits that are fit for purpose and acceptable to the cable manufacturer for
the installation conditions proposed. Where in-line joints are required they shall be utilised in
accessible locations only, joints within conduits will not be accepted.
Obtain Superintendent’s approval for proposed jointing kit, method of jointing and locations of
joints prior to placing cable orders. Locations of joints shall be recorded as-built drawings.
Enclose unsheathed cable in conduit. Underground cabling shall be sheathed circular in
conduit unless otherwise specified.
Install and conceal all wiring, including sheathed cable, within or by the building structure in a
manner that can be easily replaced without damage to the completed building finishes.
All cable entries into ingress protected (IP rated) enclosures shall be glanded. Cable entries
must not compromise the ingress protection rating of the enclosure.
Cables shall not be installed in any area until all construction work which is likely to damage
cable is completed. All cabling installed in stud walls shall be enclosed in conduits where
required by AS/NZS 3000 – Figures 3.3 to 3.7 and where not easily withdrawable for
refurbishment.
Cabling in cavities and stud walls is not permitted unless cables are RCD protected or
enclosed in conduit. Drop vertically down walls from ceiling spaces to accessories. Install
conduit sleaves through “noggings” where required to comply with AS/NZS 3000 – Figure 3.4.
Suspend/secure cabling within ceiling spaces over removable tile ceilings in such a manner
and spaced above ceiling to ensure cables do not interfere with the removal and reinstallation
of tiles, or the maintenance of in ceiling equipment.
Where more than 5 cables are in close proximity, they shall be installed on catenary wire, on
trays or in ducts with segregated sections and removable lids. Securely fix all cables direct to
the structure (not to ceiling hangers, pipes, ducts, etc). All wiring enclosures in walls shall
extend up to easily accessible location in ceiling space, cable tray, catenary wire or other
permanent support structure to produce a neat appearance and suitably protect the cable from
disturbance. Install, group and fix all cables in a tradesman like manner. Notify the
Superintendent, prior to installation of ceilings, that the above ceiling cable installation is ready
for inspection. Carry out any remedial works necessary prior to installation of ceilings.
Cabling passing through a roof shall be water tight sealed to approval. Cable penetrations
through metal roofs shall be made at the top/crest of the profile, and shall not be made in the
trough. A proprietary, tested sealing solution (e.g. Dektite, cable glands) shall be used unless
otherwise approved. In all instances, submit details of proposed solution for approval prior to
installation.
Cables shall be installed so as not to penetrate damp proof courses nor bridge the cavity in
external masonry cavity walls.
Minimum conductor size for a given circuit rating shall ensure protective device disconnection
time within the limits of AS/NZS 3000 Clause 1.5.5 and limit temperature rise to that of the
insulation. Size all cables in accordance with AS/NZS 3000 and AS/NZS 3008. RCBOs,
installed in accordance with this specification, that are used to protected circuits ensure
disconnection times under earth fault are achieved.
Group and install all cabling in straight runs parallel with line of building. Cable sizes specified
have not been derated for grouping of multiple circuits unless otherwise noted. The Contractor
shall be responsible for determining applicable derating factors based on Contractor’s chosen
cable installation methods and the circuit protection device setting. Refer to AS/NZS 3008.1.1
regarding derating factors for cables. Install cables with spacing between circuits to avoid
derating, but where derating is necessary (e.g. due to reduced spacing)increase cable sizes
as specified in AS/NZS 3008.1.1. Where cables are installed in walls filled with thermal
insulation, increase cable size or separately enclose cables in individual conduits to ensure
ventilation around cable. Refer to derating tables of AS/NZS 3008.1.1.
Cable sizes specified for connection to equipment supplied by other trades are based on
design information and are for tender purposes only. Check and re-confirm all electrical
information with equipment suppliers prior to commencement of works, and notify
Superintendent of any discrepancy with the design information. Submit schedules and cost
adjustment for any proposed changes to contract documentation for approval prior to
installation.
Unconditionally guarantee all cables during the maintenance period.
B5.3 Labelling
B5.3.1 General
Provide unique identification labels for all above ground and underground ground cables.
Labels shall be positioned such that they are visible, not obstructed by other cables, and
readable. Where there are multiple cables in a single location, labels shall be orientated the
same such that they are readable from the same direction.
Labels shall be secured in place by nylon cable ties. Minimum text height shall be 10mm, and
shall be of a contrasting colour. Details of label proposed shall be submitted for approval prior
to procurement.
Unless the format is otherwise noted on the drawings, label format and text shall be as follows:
B6 POWER - GENERAL
B6.1 General
Supply and install power outlets, cabling enclosures and cabling to all appliances and
equipment as shown on the drawings. All cabling to equipment, appliances and socket outlets
shall include suitably sized neutral and earth.
Connections are only mentioned in the Specification where additional detail is necessary.
Make final connections to all appliances and equipment. Provide suitable isolating switches
where necessary.
Where equipment is furnished by other trades check wiring details and locations with
equipment suppliers before beginning any installation.
The following subclauses shall be read in conjunction with clause ‘Fittings and Accessories’.
B6.4 Isolators
Install isolators wherever required by the authorities or these documents. Isolators shall have
Fault Make, Load Break contacts at prospective fault level rated at not less than 125% of
circuit cable ratings. Rate motor isolators to Fault Make, Locked Rotor Current Break.
Enclosures shall be dustproof internally and weatherproof externally. Label all switches
appropriately. Isolators must accept a padlock in the on and off position.
Refer also to clause ‘Fittings and Accessories’.
B7 LIGHTING - GENERAL
B7.1 General
Supply and install the complete lighting installation as specified, scheduled and shown on the
Drawings.
All lighting circuits shall be protected by RCDs in accordance with AS/NZS 3000.
All fittings shall be clean and all lamps shall be new at Practical Completion.
All components forming the luminaire shall be compatible to achieve the performance
nominated in manufacturer’s published data.
Luminaire manufacturer certified IP Ratings to AS60529 shall not be compromised or reduced
due to incorrect or poor installation.
Guarantee all luminaires against faulty design workmanship, materials and components for
the defects liability period. The guarantee shall include for labour, transport and materials to
rectify any such faults on site.
The lighting installation shall be complete with luminaires, lamps and all necessary
accessories and all control gear.
Verify the exact location of all luminaires with the Architect before proceeding with any
installation. Coordinate final location of luminaires with other services and structures.
All luminaires shall be securely fixed, supported, and provided with suitable trimmers where
necessary.
Internal wiring shall be securely fixed throughout the luminaire and comprise minimum 105 oC
insulated copper cable selected to suit the operating temperature within the luminaire.
A terminal block with tunnel terminals shall be provided to all luminaires to allow connection
of at least 3 x 2.5mm2 conductors in each.
The IP rating specified for luminaires shall be maintained through installation of fixings,
supports and wiring.
B7.4 Samples
Submit samples as specified under "Samples".
An override switch at the switchboard shall be provided for maintenance and testing purposes.
B7.5.1 Switchboard Mounted
Where required to be mounted to a switchboard, the PE cell shall be a two part device
comprising an external light sensor and a DIN rail mounted relay. The device shall be capable
of a sensitivity adjustment range from 1 to 1000 lux.
Where a sun shield is fitted, the sensor shall be fitted to top of enclosure beneath the shield,
positioned close to the edge of the switchboard. Where a sun shield is not fitted, the sensor
shall be fitted to the South facing side of the switchboard where possible.
The sensor shall be fitted by the switchboard manufacturer, and adequately sealed to maintain
enclosure ingress protection rating.
Relay and sensor combo shall be Schneider IC2000, Finder 11 Series or equal to approval.
B7.5.2 Building Mounted
A building mounted PE cell shall be a combined relay and sensor type, incorporated within an
IP56 rated enclosure and capable of sensitivity adjustment between range of 20 to 500 lux.
The device shall be externally mounted in accordance with manufacturer recommendations,
and mounted in a location not exposed to direct sunlight or where sources of artificial light and
shadowing may affect correct operation.
PE cell shall be Clipsal 56SSR/3, HPM PE170R2 or equal to approval.
B7.7 Dimmers
Where necessary fit dimmers with suppressors and / or filters to prevent noise interference
with audio, video and communication systems in accordance with EMC standards.
Wall mounted local dimmers shall be Clipsal or HPM unless otherwise specified.
Unless otherwise nominated dimmers shall be of type and sized to suit circuit load plus 20%
as recommended by manufacturer.
Dimmers shall be matched to suit the lamp or control gear used.
Refer to clause ‘Fittings and Accessories’ for further requirements.
Offices / - Passive infra-red detection with single channel output. Can be set in
Classrooms absence mode with momentary bell press switch. Delay timer ranging
from 5 seconds to 4 hours. Movement sensitivity shall be adjustable.
With inbuilt passive and active photocell that can be set in units of
Lux. Revolution Building Controls LS3100RF or equal approved.
Toilets - Where shown a single channel output, shall be Revolution Building
Controls LS3100RF or equal approved.
Passive infra-red detection with single channel output and 16M
Corridors -
coverage. Can be both flush or surface mounted with the same unit.
Revolution Building Controls RBC521 or equal approved.
1) 1-3 hour adjustable timer pushbutton test switch which automatically reverts to normal
operation after the required test duration (duration to be preset to approval). A manual
interrupt/reset function shall be provided to the timer function.
2) The test switch facility shall be clearly labelled 'Emergency Lighting Test Switch' and
'Emergency Lighting Test Reset'.
Supply a hard bound emergency lighting maintenance logbook and manual complying with
AS/NZS 2293 for all installations with emergency and exit lighting. The manual shall be
completed and a full inspection and discharge test carried out in accordance with AS/NZS
2293.2 at practical completion.
Following entry of the test results into the manual, submit the original manual to the
Superintendent for examination.
B7.12 Commissioning
Provide all necessary personnel and equipment to commission the complete lighting
installation to the satisfaction of the Superintendent.
Supply all necessary meters, instruments, temporary wiring, electrical supply, scaffolding and
labour to perform all required tests and adjustment of equipment and wiring installed and
connected under this specification.
B8.1 General
Provide fittings and accessories, including socket outlets, switches and the like as shown on
the drawings. This section describes general requirements for fittings and accessories. Refer
to power, lighting and communications clauses elsewhere in this specification for specific
requirements of individual components.
Flush mount all fittings on flush set wall boxes as recommended by the switchgear/accessory
manufacturer. All adjacent flush wall fittings shall be in a ganged wall box under a common
flush plate. Provide fire rated wall boxes in all fire rated walls. Provide acoustically rated wall
boxes in all acoustic walls.
“C” clips for plasterboard type walls may be used in non-fire or acoustic stud plaster walls. All
such mounting clips must be securely retained in place such that clip does not fall into stud
wall cavity upon removal of accessory.
Where 2 or more phases occur behind a common plate, provide adequate barriers or
separation.
Request the Superintendent to select accessory colours from standard ranges not less than
two (2) weeks before a critical date.
Where flush plates, light switch panels and other items of equipment are to be labelled or
engraved, they shall be machine engraved in upper case lettering filled with black pigments
to approval.
Where works are alterations and additions to existing buildings, fittings shall be of type to
match existing unless specifically noted in detailed clauses or drawings.
Unless otherwise specified a single brand of fittings and accessories shall be used throughout
these works.
B8.3 Conduit
Conduit shall be circular rigid PVC generally. Use galvanised steel conduit where exposed to
mechanical damage and UV stabilized conduit where exposed to sunlight.
Enclose tails to fixed connections in PVC sheathed steel flexible conduit where mechanical
protection is required. Where a flexible connection is mechanically protected by alternate
means, PVC heavy gauge sheathed corrugated conduit will be accepted.
Minimum size shall be 20mm.
Conceal all conduits including draw-in boxes from view within or by building into structure.
At all outlets and devices use wall boxes and/or conduit boxes
Completed conduit installations shall enable wiring to be drawn in or out at any time without
damage to cable or the building. Keep conduits and boxes free of moisture and rubble.
All electrical conduits shall be installed by a licensed electrical installer.
B8.3.1 Conduits in Concrete
Attend all concrete pours involving conduits. Repair any damage during pouring. Provide an
approved flexible joint at all concrete expansion joints and in every 12 metres of conduit.
Refer to structural drawings for expansion/construction joints.
Review large concentrations of conduits in suspended slabs with the Superintendent before
proceeding.
Obtain approval from the Superintendent concerning the positioning of any conduit larger than
25mm in a concrete footing, slab or wall.
• Be complete with matching splice plates, tees, bends, transitions, etc as required. All
changes of direction shall be suitable radiused.
Provide sample of cable tray for approval prior to placing orders.
Fixing shall be rigid hot dipped galvanised metal brackets or ‘Unistrut’ channels (and
accessories) as appropriate.
Continuous threaded galvanised rod shall be used for suspended trays. Cable ladder shall
be specified for cable trays above.
Where specified to accommodate fire rated cables, cable supports shall be suitable to achieve
WS rating of the fire rated cable in accordance with AS 3013.
Cable trays, ladders, support systems where penetrating through fire and smoke rated
construction shall be discontinuous or adequately wrapped in accordance with National
Construction Code (NCC) requirements.
The drawings show main cable tray routes only. Prior to and during installation, the Contractor
shall carefully validate cable tray requirements and re-coordinate routes with all other above
ceiling services trades (e.g. mechanical, fire, hydraulics) and check for conflicts and to
determine sequencing of installation. Any conflicts shall be resolved on-site by the Contractor.
The Contractor shall be responsible for any additional cable tray required including any
additional material and labour costs. Request approval from the Superintendent prior to
significant deviations to routes which results in a cable length change of over 10m. Ensure
alignment with wall and slab penetrations.
Cable tray widths nominated on the drawings are correct at time of design however due to
potential for site changes in cable size and routing, Contractor shall be responsible for
ensuring cable pathway spare space of 20% is provided at completion of work. Additional
cable tray/ladder required shall be at no additional cost to the Principal.
Cable ladder/tray should be located so as to be accessible for future installation of cables.
Where trays/ladders are located above non-tiled ceilings, arrange with the builder for
installation of access hatches.
Electrical continuity shall be maintained at joints between sections of metallic cable tray using
earthing straps/cables.
Cable tray/ladder shall only be cut along a line of unperforated material. After cutting, all sharp
edges shall be made smooth and the finish made good as per manufacturers
recommendations.
Multiple short sections of duct cover (less than 300mm) shall not be installed adjacent each
other except at outlet positions.
Any cutting shall be carried out with a machine saw and jig to ensure a straight and square
cut. Use packers if necessary to make duct body straight after installation for easy fitting and
removal of covers. Adjoining sections of duct shall be securely fixed for alignment. Earth
continuity of metal duct shall be maintained throughout its length. Obtain confirmation of outlet
locations on site prior to final installation.
All duct covers shall be secured via approved concealed clipping device or screw fixing to
ensure lids cannot be dislodged.
All electrical cable duct shall be installed above benches unless otherwise indicated on
drawings.
B9.1 General
Supply, install and commission a structured cabling system for telephone (voice) and data
communications as specified herein and as shown on the drawings. The structured cabling
system shall be in compliance with Australian Standards, client and manufacturers
requirements.. The structured cabling system shall be supplied by FibreStore, no other
supplier will be accepted. The works shall include but not be limited to:
Australian Standards
Telecommunications installations –
AS/NZS 3084 telecommunications pathways and spaces
for commercial buildings
Telecommunications installations –
AS/NZS 3085 administrations of communications cabling
systems
B9.1.2 Licence
The work shall be performed by an Installer registered on the Australian Cablers Registration
Services (ACRS) Register. The Installer shall be registered as an Open Cabler and shall also
be endorsed and approved/certified by the manufacturer of the equipment and cabling
installed.
Submit evidence of cabling registration at time of tender.
B9.1.3 Approved Vendors, Cable and Equipment
Materials, products and installation shall comply with the mandatory provisions of ACMA
(Australian Communications and Media Authority) Technical Standards AS/CA S008 and
AS/CA S009 and installed in compliance with ACMA requirements and vendor
recommendation, where applicable if more stringent.
Refer to the ACMA Certified Components List (CCL) for customer equipment and customer
cabling which comply with the relevant mandatory requirements for electrical safety and
network compatibility as detailed in ACMA Technical Standard AS/CA S008, or refer to
manufacturer to verify compliance with AS/CA S008.
Unless otherwise noted, the entire structured cabling system shall be from a single approved
vendor. Submit details of the proposed vendor with tender.
As a minimum, Category 6 U/UTP cable and components shall be utilised for copper based
horizontal and backbone structured cabling subsystems.
• Enclosed type, complete with removable sides and vented and earthed lockable front
and rear door;
• Fitted with exhaust fans;
• Front and rear adjustable depth mounting rails;
• Vertical cable management fixed to both sides of the enclosure, comprising of cable tray
or proprietary management troughs;
• Where accessible from the front only, located to ensure clearance to front face equivalent
to the depth plus 300mm.
• Metallic divider(s) to separate other sections shared with other systems (e.g. CCTV, PA)
• Communications Earth Bar;
• Two sliding shelves for each rack for equipment storage, unless otherwise shown on the
drawings
• Provision for level adjustment
• Power distribution unit, cable termination equipment and cable management as further
described herein.
The rack shall meet the following minimum usable depth, usable height and feature
requirements:
Submit details of the proposed communications equipment racks and layout of equipment to
be mounted in the rack before construction of the racks to ensure suitability of the rack offered.
B9.2.2 Cable Management
Supply and install horizontal and vertical brackets (cable tidies) for cable management of
patching leads.
Horizontal brackets shall be open ring type with minimum dimensions 40mm x 60mm.
Horizontal brackets shall be provided between every 2RU of patch panels.
Vertical brackets shall be open ring type with minimum dimensions 40mm x 125mm, and shall
only be installed in cabinets greater than 600W.
B9.2.3 RJ45 Patch Panels
Supply and install Cat 6A UTP RJ45 keystone patch panels in the communications equipment
rack(s).
Fit each panel with a rear cable support bracket running the full length of the panel and spaced
approximately 100mm behind the panel.
Size patch panels to suit the installation and provide a minimum spare capacity of 30%. Equip
each patch panel, to its full capacity, with Cat 6A UTP type RJ45 modular sockets.
B9.2.4 Distribution frames / Termination modules
Distribution frames populated with termination modules shall be utilised for termination of
incoming service cabling where required.
Size distribution frames to suit the installation and quantity of cable pairs specified and provide
a minimum spare capacity of 30%.
Equip frames with IDC termination modules matched to cable type.
Provide a completed record book for each distribution frame and fit into a record holder
installed within each communications room or cupboard.
Provide approved line protector units (surge arrestors) to the connectors of all cables installed
external to buildings. Critec SLPI0-K4 or equal approved.
B9.2.5 Power Distribution Unit (PDU)
Provide a power distribution unit (PDU) mounted to the internal of the rack.
PDU shall be fitted with six (6) switches socket outlets (SSOs). Fit the power duct with a
minimum 2 meter flex and plug top, and plug into a dedicated 15A SSO provided within the
rear of the communications cupboard or outlets in rooms. Outlets in rooms shall be mounted
in a location to avoid interference with equipment being mounted in rack.
Terminate all the fibre optic cable cores with plug in provision (eg. No onsite termination),
unless otherwise specified within the respective communications equipment racks in fibre
optic break out trays (FOBOTs).
Terminate all fibre cores in all cables with industry standard L.C. connectors that are FOIRL
(Fibre Optic Inter Repeater Link) compliant. Confirm requirement for L.C. connectors or
otherwise with Superintendent prior to placement of orders and installation. Ensure that all
connectors are matched to the cable to which they are connected and fitted using the correct
crimping tool.
Ensure that each cable is installed in one continuous length, that is joints or splices in the
cable are NOT permitted except at the FOBOT where connecting to a pigtail.
Provide cable coils in fibre cables in the following locations:
• Within the rack, a single coil of minimum diameter 600mm;
• Within the first pit entering or exiting a building, rack or equipment, 2m length;
• Within every other pit, a single coil of minimum diameter 600mm;
Indelibly label all underground cables within pits clearly notating where the cable originates,
type of cable and where it terminates.
• Cable containment (e.g. conduits, trays, ducts) fill factor shall not exceed 50%
B9.4.2 Terminations
All copper twised-pair cable terminations shall use the insulation displacement contact (IDC)
method.
Data and voice cable termination to RJ45 socket and UTP cable pair/pin assignment shall be
to T568B of AS/NZS 11801.
B9.4.3 Cat 6A UTP Patch Leads
UTP patch leads shall be RJ45 Cat 6A (male) to RJ45 Cat 6A (male) of adequate length to
connect any two outlets. Supply sufficient patch cables for all terminated outlets and not less
than 10% spare. Patch cables shall be capable of the highest operating transmission rates
specified and comply with Cat 6A specifications. Patch leads shall be minimum multi-strand
flexible copper 24AWG Cat 6A. Patch leads to be colour coded to distinguish between data
and voice as a minimum. Cabling requirements including quantities and lengths of patch leads
to be confirmed with Superintendent prior to placement of order.
B9.4.4 Work Area Cords (Flyleads)
All work area cords (flyleads) at outlets will be provided by others.
B9.4.5 Surge Protection
Supply and install an approved surge protection device to all outdoor copper twisted pair
cabling. Devices shall be fitted at both ends of the cable at the termination frame or panel and
in accordance with AS/CA S009 and AS/NZS 1768.
Surge protection devices shall be the following or equal approved:
• ABB
• Ciprotec
• Dehn
• Eaton
• Erico
• Novaris
• Schneider
Alternative manufacturers may be considered only if certification of product compliance to IEC
61643-21 can be provided and certified by an electrical engineer whom holds registration
(NER) with Engineers Australia or equal internationally recognized registration body. Results
of testing by a NATA accredited laboratory that demonstrates compliance to IEC 61643-21
shall be available on request.
B9.5 Outlets
Outlets shall be RJ45 Cat 6A tooless keystone network jack modules type outlets. Colour to
match electrical GPO's.
The minimum mounting height for data and voice outlets is 500mm above finished floor, unless
otherwise shown, to avoid accidental damage.
Outlets shall be positioned so as not to be obstructed by fixed furniture, fixtures and the like
(i.e. taps, gas valves, heaters).
Review current Architectural detail drawings on site prior to installation of outlets to ensure no
obstruction.
Cabling duct mounted outlets shall have cable termination method of type to ensure
flushplates are installed flush on ducting.
B9.6 Labelling
Communications equipment racks shall be sequentially numbered. Confirm numbering with
Superintendent. Screw fix a clearly visible engraved traffolyte label with the rack desigation
to the front and rear of each rack. Text size shall be minimum 25mm high in contrasting colour,
nominally black on white background.
Identify all sockets on the patch panels with a 4mm high engraved traffolyte label above each
socket. Numbering shall be in the form ‘N-1’, ‘N-2’, ‘N-3’, etc, where ‘N’ indicates the rack
number. Numbering shall be sequential (left to right and top to bottom) from the top left hand
corner of the panels. Where more than one panel is required continue to number the sockets
sequentially, following on from the first panel.
Label outlet flush plates above the RJ45 sockets with engraved traffolyte (black text with white
background) fixed with Araldite to the centre of flush plate. Labels shall not be located on
removable surrounds. Engraving shall correspond to the number on the respective
communications equipment rack outlet patch panel to which they are connected, i.e. ‘N-1’, ‘N-
2’, ‘N-3’, etc, where ‘N’ indicates the rack number. Identification shall also be reflected on the
as built plans and schematics.
All lines/outlets used for security services/monitoring facilities shall be clearly labelled
“Reserved for Security – Do not Alter”.
Indelibly label all underground cables within pits, pole and other access points clearly notating
where the cable originates, type of cable and where it terminates. Refer to “Cables – General”
for additional requirements including labelling.
B9.7 Earthing
B9.7.1 Communications Earth System (CES)
Provide a Communications Earth System (CES) to AS/CA S009 requirements. Provide a
Communications Earth Terminal (CET) within the rack (for single racks), or in an approved
accessible location within each comms room, and bond to the earth bar of the switchboard
supplying the rack/room with 6mm2 green/yellow PVC insulated copper cable.
The CET shall be separate to the electrical earth bar in accordance with AS/CA S009.
B9.7.2 Telecommunications Reference Conductor (TRC)
Install TRC exclusive to the telecommunications systems in accordance with AS/CA S009.
Install additional earth electrode to obtain the specified maximum earth resistance in
accordance with AS/NZS 3000 and to AS/CA S009, where required.
For the connection of the main earthing conductor and interconnecting bonding, use clamps
to AS1882.
Locate connections within a pit having a removable cover. Size the pit to suit testing,
disconnection and reconnection.
Install the pit cover flush with the surrounding finished ground level and make the connection
to the earthing system not less than 150mm above the level of the ground within the pit.
Where electrodes are to be installed in rock, fill the gap between the rock and electrode with
a bentonite clay or resin compound or as otherwise approved.
Permanently label, using an engraved brass plaque, with the works “Telecommunications
Electrode”.
Install earthing cables from the BD link bar to each FD and from each FD to each LD.
B9.9 Testing
B9.9.1 General
On completion of the installation of the structured cabling system check test of all
telecommunications cabling and outlets and confirm that the equipment has been installed
and connected in accordance with the specification and drawings and that the specified
performance is achieved.
Testing of all cabling shall be carried out using handheld testers Fluke or equal approved,
complete with system compatible test probes/leads, suitable for the tests specified herein.
Test equipment shall be calibrated and current test certificates shall be supplied along with
test results.
Advise the Superintendent in writing, giving at least five (5) working days notice that the work
is ready for testing so that testing may be witnessed.
All cables failing specified testing shall be replaced at no cost to the contract.
Submit one written copy and one electronic copy of test results in the testers native file format.
Include the software to enable review of results from any PC.
B9.9.2 Copper Cabling
All UTP cabling shall be tested to IEC 61935.1 and be compliant to AS/NZS 11801
specification.
Test all UTP cable pairs in accordance with IEC 61935.1 as summarised below:
B10.1 Fabrication
Unless otherwise specified, poles shall be steel hot dipped galvanised and painted. Poles,
bases, footings and holding down bolts shall be designed in accordance with the appropriate
Australian Standard to suit the soil and wind loading conditions of the site and shall be certified
by a practicing Structural Engineer. Submit Structural Engineers certification with shop
drawings.
Poles shall have no manufacturers labeling, numbering identification or the like exposed
externally.
Install cabling inside poles and a minimum of two 32mm large sweep conduit bend shall be
provided through each concrete footing. Verify the top elevation of each pole foundation before
proceeding.
Poles shall be complete with all necessary brackets, spigots and ferrules to suit light fittings
and crossarms, etc. Generally poles shall be base-plate mounted with base plates and holding
down bolts concealed below finished ground level.
All fixing and fasteners on poles shall be unpainted marine grade stainless steel (316 grade).
Isolate dissimilar metals. A suitable insulating barrier and/or shrouds (sleeving) shall be
installed to provide adequate barrier between any dissimilar metals. Request a detailed
installation instruction from the pole manufacturer.
As electrical cables will be installed in the pole, it is essential that all holes and surfaces are
free of burrs and sharp edges.
Generally all holes and penetrations in poles e.g. cable entries shall be drilled.
Where oxyacetylene is used to form a penetration all jagged edges must be ground smooth.
Seamed poles must be ground and then sanded to a smooth finish.
Where pole sections are joined to achieve the required height, joins are to be welded. Poles
must be finished in accordance with General Clauses ‘Surface Preparation’ prior to painting.
Pole colours shall be to Architects selection.
B10.4 Manufacturer
Engage one of the following pole manufacturers to design, construct and supply the poles:
• Ingal EPS
• A D Coote & Co Pty Ltd
• G & S Industries
• Auspole
No other manufacturer will be approved without prior written approval.
B10.5 Finishing
Hot dip galvanise all steel poles to AS/NZS 4680. Where no further finishes are to be applied,
“dress” the galvanised pole to remove galvanising lumps, runs, imperfections etc to give each
pole a consistent neat finish without compromising the protective galvanising coating. Where
painting is specified, poles shall be lightly sanded to remove surface imperfections or lightly
abrasive blast cleaned to AS 1627.4 Class 2. All poles to be painted shall be pretreated in a
suitable primer followed by a two pack polyurethane system as specified elsewhere in this
specification. Final paint colour shall be to approval. Counterbalanced poles shall have their
overlapping surfaces treated in a similar manner. Where any damage occurs to the pole
surface repair damage to approval; clean and paint to above standard.
• Painting of walls, smoke sealed doors and ceiling to electrical and communications
cupboards.
• Cupboards for electrical switchboards.
• Cupboards/Rooms for Communication Racks and Security Equipment.
• Recesses for GPO’s, light switches, light switch panels, etc where larger than a
standard electrical wall box, in rammed earth walls.
• Labelling of services cupboards and rooms.
• Temporary power for construction purposes.
• Temporary lighting for construction purposes.
• Sealing of all penetrations through acoustic rated walls and floors other than 50 mm dia
cable penetrations.
• Fire stopping of penetrations between fire zones or through fire rated walls and floors
other than 50 mm dia cable penetrations.
• Reinstatement of any bitumen, paving and landscape garden areas associated with the
installation of underground conduits and cable pits.
• Structural supports for Projectors, motorised screens, LCD screens, associated with the
Audio Visual services equipment by the Audio Visual Contractor.
• Ceiling access panels to obtain access to cable trays and the like.
• Set out of walls for locating of services.
• Cutting of holes in benches, partitions, furniture, ducts and other timber work to
accommodate electrical services outlets and switches.
• Protection of services once installed ie. switchboards, conduits, cable trays and the like.
• Combined services riser/ducts with smooth sealed internal surfaces.
• Building in of flush/recess mounted panels larger than a double gang box.
• Cutting and trimming of ceilings for recessed luminaires, speakers and the like.
• Filling in and making good of wall chases around conduits, wall boxes and flush
mounted panels.
• Production of detailed combined services external works drawing with surveyed
locations of all inground services.
C2 GENERAL POWER
C4 SECURITY SYSTEM
C4.1 General
Modify and extend the existing security intruder alarm system.
Engage Securex to complete the supply and installation of the security system. No other
companies will be accepted.
The work includes but is not limited to:
C4.11 Installation
The system must be installed and commissioned by security company staff (i.e.
subcontractors must not be used).
C4.12 Cabling
Install the cable in accordance with the general clauses of this specification and as follows:
• Cable to passive infra-red detectors shall generally be multi-conductor PVC sheathed
cable with conductor size 14/0.20 stranded copper.
• A separate cable run is required for each detection point.
• Cable for control and communications signals shall be to the equipment manufacturer's
requirements.
• Identify cables by numbered ferrules or approved labels affixed to each cable end.
Numbering shall be consistent throughout each run.
• No jointing of cables, other than at terminal strips or junction boxes, shall be permitted.
• At junction box terminal trips provide sufficient terminals for individual conductors.
Multiple conductors on a single terminal point is not acceptable. Blue point type
connectors and terminal strips not fixed to the cabinet are not acceptable.
• A cable schedule shall be provided at each cable termination box.
C4.13 Programming/Training
Fully programme the system.
Train users in system operation and programming.
Include in tender price for 2 hours training for group (minimum of 4 representatives).
C4.14 Testing
Prior to commissioning of the system completely test the alarm system. This testing shall
include:
C4.15 Commissioning
Commission the complete intruder alarm system in the presence of the Architect.
Commissioning will not take place until the system has operated free of faults for seven (7)
days following testing of the installation.
Commissioning will consist of:
• Final inspection of the complete installation
• Confirmation all items have been tested
Prior to commissioning supply handbooks as detailed in this specification and completed test
schedule.
C4.17 Samples
Provide samples and data sheets of all proposed Security equipment and devices to
Superintendent for approval prior to ordering.
C4.18 Handbooks
Supply three (3) neatly bound service handbooks for the installation and equipment. These
handbooks shall give complete and detailed information on the installation and shall contain
at least the following information:
• Block diagrams which shall show the interconnection between major pieces of
equipment
• Circuit diagrams, which shall be annotated with voltages present, under no signal
conditions, at salient points in the equipment
• Layout diagrams, which shall indicate the location of major pieces of equipment and the
location of each component within each piece of equipment
• Cabling diagrams, which shall indicate the layout of all cables, including colour codes
and details of the terminations shall be stated
• Operating instructions, which shall clearly set out the operation of each piece of
equipment
The above literature, shall be of a professional standard, both in format and presentation.
The push buttons shall be installed where shown on the drawings with the light and buzzer
indicator installed to the common area shown on the drawings
Provide an alarm system for each accessible toilet as indicated on the drawings.
The system control voltage shall be 24 Volt DC dedicated extra low voltage power supply.
Call points shall be provided with the following:-
• Flush mounted on walls with flushplates finish matching other wall plates.
• Alarm button with mushroom head not less than 25mm diameter, coloured red.
• Latching facilities.
• Reassurance light to illuminate when a call has been placed.
• Splash proof construction.
• Contact to operate a combined indicator light and buzzer above the toilet door or in
locations as shown on drawings.
• Sealing to prevent the egress of water between the flush plate and wall box with a non
hardening anti-fungus silicon sealing compound.
• Have flush plate indelibly marked “Press for assistance”.
• Remote combined indicator light and buzzer shall be provided with the following:
• White translucent dome.
• Red indicator lamp.
• Protrude not less than 50mm.
• Visible through all angles up to 90o from horizontal.
• Buzzer.
Be indelibly marked “UAT ASSISTANCE REQUIRED” as applicable.
PART D APPENDICES
D1 SCHEDULE OF ACCEPTABLE PITS / LIDS
Minimum Acceptable Types
Installation Notes (Notes are in addition to
Service Installation Conditions Pit Lid Load Lid Style
manufacturer’s recommendations)
Telstra • All locations (pits not permitted in Telstra Specification Telstra Telstra To Telstra standards flush with surrounding surfaces.
roadways or driveways). Specification
Power & • Garden Beds (non-trafficable) GFRC/PC/HDPE ‘A’ Class Flat with plugged lifting Install flush with garden/ mulch level
Comms AS3996 eye/s
• Lawns/Mowing Strips GFRC/PC ‘B’ Class Flat with plugged lifting Install 100W x 200D collar (poured concrete haunch)
AS3996 eye/s around pit to support lid edge. Install flush with grass
level.
• Paved External Pathways GFRC/PC ‘B’ Class Galvanised steel recessed. Pit lid recess to suit surrounding paving, flush with
(Pedestrian) AS3996 paving.
• Paved Roadways/Driveways – GFRC/PC/PCRC/SMB ‘C’ Class Gatic or equal concrete Fully surround pit in concrete haunching/bedding with
Residential AS3996 filled ductile iron cells. 200mm edge to lid. Install flush with paving.
• Paved Roadways/Driveways – GFRC/PC/PCRC/SMB ‘E’ Class Gatic or equal recessed Ductile iron recess lid to suit paving used. Fully
Commercial and Industrial AS3996 ductile iron cells. surround pit in concrete haunching/bedding with
200mm edge to lid. Install flush with paving.
• Internal Paved Areas (No Vehicles) GFRC/PC/HDPE ‘A’ Class Galvanised steel recessed. Pit lid recess to suit surrounding paving, flush with
AS3996. paving.
• Concrete/Bitumen External GFRC/PC ‘B’ Class Flat with plugged lifting Install flush with surrounding pathway.
Pathways (Pedestrian) AS3996 eye/s.
• Concrete/Bitumen GRFC/PC/PCRC/SMB ‘C’ Class Gatic or equal concrete Fully surround pit in concrete haunching/bedding with
Roadways/Driveways (Residential) AS3996 filled ductile iron cells. 200mm edge to lid. Install flush with surrounding
roadway/driveway.
• Concrete/Bitumen Roadways & PC/GFRC/PCRC/SMB ‘E’ Class Gatic or equal, concrete fill Fully surround pit in concrete haunching/bedding with
Driveways – Commercial and AS3996 ductile iron cells. 200mm edge to lid. Install flush with
Industrial roadway/driveway.
• Internal Concrete/Bitumen Areas GFRC/PC/HDPE ‘A’ Class Flat with plugged lifting Flush with surrounding areas.
(No Vehicles) AS3996 eye/s.
Abbreviations: • ‘A’ Class > 10kN lid load • GFRC – Glass Fibre Reinforced Concrete Notes:
• ‘B’ Class > 80kN lid load • PC – Polymer Concrete
• ‘C’ Class > 150kN lid load • HDPE – HDPE Plastic 1) PCRC pits shall be proprietary concrete liners
with poured base and proprietary lid system.
• ‘D’ Class > 210kN lid load • PCRC – Precast Reinforced Concrete: Note 1
Submit details for approval
• ‘E’ Class > 400kN lid load • SMB – Site manufactured brick: Note 2
2) SMB pits shall be designed by a Civil Engineer
and constructed to civil engineers details. Submit
shop drawings for approval.
CABLES TERMINATIONS
Summary: Switchboard Segregation
ELV ELV
Selected Requirements LV Power LV Comms ELV Power LV Power LV Comms ELV Power
Comms Comms
LV Power Cables (double insulated) - 50a 50a 0d - 150b,c 150b 0d
LV Comms Cables (e.g. PA, Fire) 50a - 50a 50a 150b,c - 150b 150c
ELV Comms Cables (e.g. CAT6, 48V to Comms Equipment) 50a,d 50a - - 150b,c 150b,c - -
ELV Power Cables (e.g. Isolated from Comms Equipment) 0a,d 50a - - 0c,d 150b,c - -
Note 1: This is only a summary of selected communications segregation requirements applicable to switchboards. All works shall comply with AS/NZS 3000 and AS/CA S009 in their entirety,
including the recommendations contained within those standards. Refer also to AS/CA S009 Table G1. All new switchboards to be designed for communications section to be open while
switchboard is energised.
Note 2: "ELV Comms" on this table refers to the AS/CA S009 categories of SELV, TNV and Limited Current Circuits, which includes CAT6 communications and most DC power supply cabling.
Refer to AS/CA S009 for additional requirements for ELV that does not meet these categories (e.g. self-generated power / solar). "ELV Power" on this table refers to the AS/NZS 3000 definition
of SELV (similar to AS/CA S009 TNV), where the cable is in no way connected to comms equipment.
a = fixed in a way that permanently provides 50mm separation. Alternatively, provide a barrier of durable insulating material, metal, or enclose in conduit.
b = fixed in a way that permanently provides 150mm separation. Alternatively, provide a rigidly fixed barrier of durable insulating material or earthed metal.
c = accidental human contact with LV terminals, single insulated LV cable or uninsulated LV cable prevented to approval.
d = AS/NZS 3000 Clause 3.9.8.3 and 7.5 permit LV and ELV cables to be installed touching, provided the LV cable is double insulated and the ELV cable is insulated to 500VAC for 1 min, and
IPxxB / IP2x is provided at terminals. This is only applicable where AS/CA S009 does not apply to the cable, and ETC interpret AS/CA S0009 to include DC power supply cabling to comms
equipment.
IP RATING NOTED
INSTALLATION ITEMS
SWITCHBOARD SIZE CHECKED AND IS ABLE TO BE
TRANSPORTED AND INSTALLED IN ALLOCATED SPACE
SWITCHBOARD HEIGHT CHECKED AGAINST DOORWAYS
LIFT SERVICES
SPECIFICATION
Revision: 0
Reviewed/Approved: SB/SC
61 Loftus Street
Leederville WA 6007
T: (08) 9328 5500
F: (08) 9328 5522
E: etc@etcpl.com.au
PROVIDENCE CHRISTIAN COLLEGE – LIFT SERVICES PAGE ii
REVISION REGISTER
Clause
Revision Date Revision Details Originator Reviewed Approved
No.
0 12/01/21 Tender TS SB SC
TABLE OF CONTENTS
1 GENERAL ............................................................................................................................... 7
1.1 Introduction ............................................................................................................................ 7
1.2 Application of General Requirements Clauses .................................................................. 7
1.3 Interpretation of Terms ......................................................................................................... 7
1.4 Requirement for Contract ..................................................................................................... 7
1.5 Contract Sum ......................................................................................................................... 7
1.6 Goods and Services Tax ....................................................................................................... 8
1.7 Progress Claims .................................................................................................................... 8
1.8 Construction Program ........................................................................................................... 8
1.9 Site Meetings .......................................................................................................................... 8
1.10 Quality Assurance ................................................................................................................. 8
1.11 Health and Safety ................................................................................................................... 8
1.12 Site Conditions ...................................................................................................................... 9
1.13 Shop Drawings ....................................................................................................................... 9
1.14 Samples ................................................................................................................................ 10
1.15 Fire Service and Protection ................................................................................................ 10
1.16 Review of Work .................................................................................................................... 11
1.17 Testing and Commissioning .............................................................................................. 11
1.18 Tuition ................................................................................................................................... 11
1.19 Final Completion .................................................................................................................. 12
2 OPERATION AND MAINTENANCE MANUAL .................................................................... 12
2.1 General.................................................................................................................................. 12
2.2 Drawings ............................................................................................................................... 13
2.3 Format ................................................................................................................................... 13
2.4 Quantities ............................................................................................................................. 14
3 SCOPE .................................................................................................................................. 14
3.1 Extent of Works ................................................................................................................... 14
3.2 Schedule of Main Features ................................................................................................. 15
3.3 Work by Other Parties ......................................................................................................... 18
3.4 Rules and Regulations ........................................................................................................ 19
3.5 Finishes and Painting.......................................................................................................... 20
3.6 Labels and Notices .............................................................................................................. 21
3.7 Performance Requirements ................................................................................................ 21
3.8 Testing and Commissioning .............................................................................................. 21
LIFT SERVICES
1 GENERAL
1.1 Introduction
Providence Christian College Primary School is located at, Southern River, Western
Australia.
The new building will encompass 2 levels of teaching and accommodation.
The lift services will comprise of one (1) stretcher capacity passenger lift.
Passenger lift car finishes are to good quality as selected by the Architect from the
manufactures standard range of finishes.
Claims for variations to labour rates, material costs, GST, import duties, freight charges,
currency exchange rates, customs’ and primage duties for all work or materials provided or
supplied during the contract period will not be considered for payment.
the safety of all personnel during construction, inspection, testing and subsequent
operation of the systems
4) Advising of all potential hazards not adequately protected to the requirements of the
Health and Safety Legislation, Acts, Regulations and Codes of Practice
5) Providing all temporary or permanent screens, guarding, safety notices, identification
labels and safety clothing, footwear and equipment required for the execution, testing,
commissioning and maintenance of the works.
Even where the above obligations are not imposed on the Contractor by Health and Safety
Legislation, the Contractor will take all steps to ensure that the obligations are complied with
at all times.
In performing its Health and Safety obligations the Contractor will coordinate with other
services to ensure that notwithstanding the activities of other services, its Health and Safety
Obligations are met.
Comply with Statutory Authorities and show sufficient information to verify that the
equipment can be installed, operated, adjusted and maintained in the manner for which the
system was designed.
Show all building details and identify services and plant by the same numbering as used on
the drawings. Metric units of measurement are to be used throughout.
Take all responsibility for, and pay for, all alterations of the works due to any discrepancies,
errors or omissions in the shop drawings or other information supplied under the contract,
whether such prints of drawings or information have been reviewed or not, provided that
such discrepancies, errors or omissions are not due to inaccurate or incomplete information
provided for the works.
Shop drawings shall be reviewed marked where alterations are desired, and returned within
14 working days, unless specified elsewhere, of receipt. Where marked to be resubmitted,
amend the originals as required and cloud the parts of the drawing altered as a
consequence of the last revision and resubmit a plain paper print for review.
1.14 Samples
If requested, submit samples for review. Once accepted, retain as the reference benchmark
for materials, finish, quality and workmanship. Any deviation in the final installed item, from
the submitted samples, may be cause for their rejection. Where an article is too large to
submit as a sample, arrange for the item to be made available for review at a suitable
location.
Submit other samples where clarification is required for additional items not specified as
requiring samples. Once accepted, retain the samples and treat in the same manner as
specified samples.
Samples shall:
1) Be submitted within sufficient time to permit modifications to be made if such are
deemed necessary and allowing not less than seven working days for comment
2) Be submitted with copies of relevant approval certificates and technical data where
associated with essential services and emergency systems
3) Be complete in every detail and labelled to include; name of Contractor, date
submitted, make, model no., purpose of sample and relationship to these documents
4) Be submitted with a complete list of those non-complying features where deviations
from specification in the samples exist. Should such a list not be provided the
Contractor shall be responsible for full compliance with the specification, irrespective
of any review by the Superintendent.
5) Be held on site after review until built into the works as the final unit
6) Documentation submitted with samples shall be returned:
7) Marked acceptable, subject to any comments applicable or
8) Marked resubmit, which shall require the rejected sample to be amended as required
and resubmitted.
A certified fitter shall carry out all welding or cutting activities as required by AS1735 part 1.
1.18 Tuition
Provide an experienced technical person, who has a complete technical knowledge of the
installation, to instruct and demonstrate to the Principal or his nominated representatives,
method of operation and maintenance requirements of all components in the installation. All
operating manuals and as installed drawings shall be available prior to tuition being given.
2.1 General
Provide documentation to allow the Principal to operate and maintain the plant and
equipment, together with all relevant information that would assist in carrying out operation,
maintenance, additions and alterations to the installation.
The Manuals shall be prepared by personnel who are familiar with the system design and
capable of providing a detailed description of the system operation and related items.
The manuals shall be concise and written in English to describe the systems installed and
the method of operation and maintenance procedures.
All text in the manual shall be written in terminology to enable it to be understood by non-
technical personnel.
Documentation shall include:
1) A title section including the project name, address, Principal, Superintendent and
Contractor.
2) As installed layouts, car interiors and appointment drawings
3) Wiring diagrams
4) Listings of all entered programmable parameters and fault codes
5) Operating characteristics of the lift together with descriptions of special features and
functions of key switches
6) Procedure to be followed when accidents involving injury to persons occur
7) Brief technical description of the lift including technical data information supplied with
the tender
8) Provide copies of landing door and frame fire test certificate
9) All test results
10) Approval and compliance certificates and notices issued by Authorities, Agencies,
Suppliers, Installers and Contractors.
11) Manufacturer’s documentation of all equipment
12) Care and maintenance of applied finishes
13) Instructions for operation of the system
14) Maintenance schedule and procedures
15) Recommended frequency of inspection and lubrication of equipment
16) Information relating to the expected operational life of all major system components.
17) Warranty details in excess of the defects liability period
The details to be contained within the documents are specified in the Scope and Quality
Requirements sections of this specification.
Submit a ‘draft’ copy of the Manual, for approval, prior to practical completion.
An interim copy of the sections of the Operating and Maintenance Manual which refers to
essential and emergency services shall be provided prior to practical completion for site use
until the final versions of the manual are supplied.
2.2 Drawings
The drawings shall include the final shop drawings provided during the progress of the works
and as installed drawings for the installation.
All drawings shall be produced in electronic format (CAD) using a standard print font.
Freehand or manually drafted drawings and sketches are not acceptable.
2.3 Format
Hard copy manuals shall:
1) Be sized with A4 pages.
2) Contain typewritten text. Handwritten documents are not acceptable.
3) Be bound in binder/s, which shall be labelled with the project description, service and
volume number on the cover and spine of the binder. Binders shall be hard covered,
multi ring type, which enable easy removal or insertion of pages.
4) Include original copies of printed documents of equipment by manufacturers, note that
if the applicable component is only a minor part of printed manufacturer’s documents,
the relevant pages shall be colour photocopied and inserted in the manual.
5) Include dividers between sections of the manual with printed identification of the
section as cross referenced in the index.
6) Include clear plastic sleeves to contain documents, which are not suitable for binding,
e.g. Certificates. etc.
Electronic format manuals shall:
7) Be sized for A4 paper
8) Be provided in two formats:
a) Adobe Portable Document Format, PDF
b) The original source file
9) Be produced to suit electronic on line documentation
10) Be produced in a form suitable for use with Adobe Acrobat 5.0 software or higher
11) Be produced in one of the following format files not less than a maximum three
versions older than the current release version:
a) Microsoft Office
b) Adobe PageMaker
c) Adobe FrameMaker
12) For pre-formatted documents produced by other software products for inclusion in the
manuals, be provided in one of the following formats:
a) Adobe Portable Document Format, PDF
b) Postscript File, Level II
13) Where manufacturer’s documents are not available in electronic format, be provided
with electronically scanned images of relevant sections of the documents in Adobe
Acrobat PDF format at a resolution not less than 150dpi
14) Be provided on an indexed CD ROM or USB electronic format, labelled with the
following information:
a) Project name
b) Drawing numbers
c) File type/s
d) Date
15) Hard Copy drawings shall:
16) Be provided on the same size print sheet for uniformity of all drawings
17) Be bound in a set with a proprietary binding system which enables easy removal or
insertion of drawings.
18) Be bound in a set with a cover sheet labelled with the project description, service and
volume number of the drawing set.
19) Include an index of all drawings in the set
20) Electronic format drawings shall:
21) Be produced in a suitable file format that can be viewed and opened by the latest two
versions of AutoCAD
22) Be prepared utilising one of the latest two versions of AutoCAD with all details of the
layers system utilised.
23) Be prepared as a black and white postscript plot file or Adobe Acrobat PDF file in the
same standard as for AutoCAD printed versions
24) Be provided on an indexed CD ROM or USB electronic format, labelled with the
following information:
e) project name
f) drawing number/s
g) file type/s
h) date
2.4 Quantities
Provide the following quantities of documents for the Operation and Maintenance Manual:
1) Manuals – Three (3) sets in hard copy format and two sets in CD ROM or USB
electronic format
2) Drawings – Three (3) sets in hard copy format and two sets in CD ROM or USB
electronic format
3 SCOPE
6) Engineering calculations
7) Payment of Plant Registration fees
9) Roping - 2:1
10) Machine location - Overhead located within the top of the lift
shaft
11) Lift well plan size - 2000mm wide x 2400mm deep (clear internal
shaft)
19) Entrance protection acceptable - ‘3D’ Multiple infrared light beam, proximity
types device or electronic scanner
a) Car control button - Two (2) on the lift car side walls
panels
e) Flooring - Vinyl
j) Ventilation - Fan
a) Landing call button - One (1) dual illuminated (White/ Blue) manual
panels push button with call registration at both
floors. Mounted flush with vandal resistant
hidden fixings
b) Machine area - 1 off two hour capacity unit at top of shaft and
1 off in the lift pit area
33) Buffers -
Lift Pits
1) Provide a tanked waterproof lift pit to lift code and contractors requirements. Pit to
extend to solid earth and be designed to withstand dynamic loadings provided by the
Contractor.
2) Building in of buffer support steelwork or inserts, where required.
3) 300mm x 300mm x 300mm dry sump recess to pits complete with non-slip, perforated
grates. Grade pit slab with a minimum fall to the sump. To be located immediately
below the lowest level landing door entrance.
Lift-Wells
1) Construct waterproof, fire rated lift-well with non-brittle material. Lift-well should not
deflect more than 25mm when subjected to a force of 450N applied horizontally on
any square of 50mm side.
2) Lift-well to be constructed square and plumb within 25mm. Front wall shall be
constructed plumb within + or - 6mm on the inside face and + or - 12mm on the lobby
side face.
3) Rough openings at each floor served, as nominated, for lift door frames and recesses
or set downs for door sills.
4) Provide floor datum’s for the installation of door frames and landing tracks.
5) Make good landing rough entrances to the lift door frames and sills following
installation by the Contractor.
6) Build into the lift well structure fixings for guide rail brackets and landing door frame
supports. Brackets to be provided by the Contractor.
7) Provide lifting beam, or lifting eyes, with a two (2.5) tonne capacity in the top of the lift
overrun to lift contractor detail.
8) Provide 200 x 200 ventilation relief at the top of the lift shafts
Electrical and Security Services
1) Provide and connect a suitable three phase and neutral, 50 Hz, 415 volt fire rated
sub-main, from main switchboard to lift machine distribution board inside the lift shaft
adjacent to the top landing entrance. Fault level of the lift switchboard is to be
confirmed with the Electrical Engineer.
2) Apply with the lift contractor and make application for the connection of the phones to
each lift. Pay for all fees for connection of lift phones
Mechanical Services
1) Fire protection services
2) Provision of fire detection and/or suppression equipment to the lift-well as detailed
within the Fire Protection Services specification and in compliance with the
Regulations, including but not limited to:
a) Supply and install fire detection to the top over runs and sprinklers in the lift pits
of each lift shaft.
3) Liaise with the Contractor for all installation and positioning of equipment
3.5.6 Cleaning
Prior to practical completion the entire installation shall be thoroughly cleaned of dust, grime,
oil and grease.
Car interior finishes, car operating panels, handrails, doors and frames shall be cleaned and
polished to remove any dust, stains, etc. Any protective compound as recommended by the
manufacturer shall be applied prior to practical completion.
Replace any equipment found to be defective during such tests and repair or replace any
equipment damaged. In particular, the guide rails are to be redressed after safety gear
tests.
In addition to the mandatory tests, all the equipment including finishes will be inspected and
checked for correct operation of at least the following for each lift:
1) Levelling accuracy
2) Independent service
3) Simplex operation
4) Fireman's service
5) Load weighing operation
6) Sound levels
7) Passenger protection devices
8) Car lighting and emergency lighting
9) Car ventilation
10) Car emergency communication and alarm system
11) Car and landing controls and indicators
12) Auto Rescue Device
13) Pit and well lighting
14) Car roof inspection operation
Allow for repeating all tests prior to expiry of the maintenance period.
3.8.2 Keys
Supply three keys for each key switch. Respective keys shall be attached to a plastic
engraved label for each key switch function, i.e., car lights and car fan, independent service,
etc.
Comply with the requirements of authorities having jurisdiction over any part of the works
including requirements for ladders, stairs, platforms, safety access and scaffolding.
Make all applications and pay all fees required by any such Authority. Prepare and submit
applications including those that are required to be signed by the Owner.
3.14 Standards
Work not covered by the requirements of Regulatory Authorities or this specification shall
comply with the appropriate publication of the Standards Australia.
Wherever a Standard or Code of Practice is referred to in this specification, it will imply the
latest issue and/or revision applicable at the time of tender.
3.20 Drawings
Provide full working drawings for approval, including shaft layouts, builders works lift car
design and car and landing appointments.
Any information involving accurate measurement of the works shall be taken from the
architectural and structural drawings and at the site.
Co-ordinate with all other trades, Architectural and Structural drawings to ensure that
equipment is accessible and suitably located.
The final location of all equipment shall be determined in co-ordination with other services
and architectural details.
Examine carefully, as soon as is practicable prior to the commencement of any works, the
architectural, structural and other trade drawings and be satisfied that the works can be
satisfactorily carried out without changes to the building as shown on the architectural
drawings. Before commencement of any works, report any defect or interference affecting
the works.
13) nylon ties for all power sub mains and feeders except where run in horizontal plane
and weight of sub-mains is directly supported by cable tray or ladder rack
The bearing plates and supports where required, shall be built into the structure.
5 CONTROLLER
5.1 General
Control equipment shall be designed and manufactured for lift usage and shall operate free
of vibration and noise.
Control equipment shall be housed in robust metal cabinets and fitted with closely fitting
doors.
Equipment shall be mounted with adequate ventilation being provided to prevent
overheating or early component failure.
All equipment, contactors and junction strips shall be clearly labelled.
All 240 volt and 415 volt terminals and connections shall be adequately protected from
incidental contact.
All bolts and screws shall be fitted with washers, nuts and locknuts or spring washers.
Under voltage, sustained overload, phase failure or phase reversal protection shall be
provided to prevent damage.
Control circuits shall be adequately protected by fuses or other appropriate means.
Thermal protective devices, where used, shall not be subject to heat rising from rectifiers,
resistors, etc.
Solid state devices shall be conservatively rated for the duty with adequate provision for
short term overload situations.
All card mounted microprocessor and/or integrated circuits shall be fixed in the vertical
position to minimise the accumulation of dust.
Any special tools required for initial set up, retune or adjustment or for the purpose of
diagnosing faults, shall, either be incorporated into the controller or if separate, be supplied
complete with codes and passwords and remain the property of the owner.
6.1 General
Provide a distribution board in the controller unit located on the top landing of each lift.
The controller shall be provided with a fire rating where it penetrates the lift shaft.
The distribution board shall be:
1) complete in every respect, fully wired and factory tested
2) of overall dimensions suitable for spaces allocated
3) designed to facilitate easy access to and removal of component parts
4) constructed and contain equipment as required by the Local Supply Authority
5) The distribution switchboard shall:
6) conform to AS3439.1
7) be provided with a minimum protection rating of IP 51 as defined in AS1939
8) be capable of withstanding the stresses caused by a fault level as specified for a
period of one second
9) be of the following minimum form construction as per AS3439.1:
10) less than 150 amps capacity - Form 1
Distribution switchboard shall:
The switchboard shall contain the following:
11) three phase main circuit breaker for each lift
12) single phase, Earth Leakage Protected, circuit breaker for each car lighting and power
13) single phase, Earth Leakage Protected circuit breaker for lift well lighting in each lift
shaft
14) single phase, Earth Leakage Protected circuit breaker for the General Purpose
Outlet located in each lift pit overrun
15) be provided with emergency lighting test facilities in accordance with AS2293.1 for car
emergency lighting.
Connection of sub mains to the lift control system shall be completed by the electrical
contractor. Allowance should be made for tails and connection.
7.1 General
Provide, and fit as necessary, the following accessories in each lift machine area prior to
practical completion:
1) as installed wiring diagrams suitable protected and wall mounted
2) well access key and door unlocking devices suitably labelled and wall mounted
3) holder fixed to the lift shaft wall adjacent to the top landing for log books and relevant
information
4) duplicate book to record all maintenance, emergency lift calls and breakdowns
8 LIFTWELL EQUIPMENT
8.3 Screens
Supply and install pit counterweight screens and any guarding necessary for the prevention
of travelling cables being damaged by the shaft or lift equipment.
Where the distance between lifts does not meet the requirements of 500mm clearance then
full height screening between lifts is the be provided.
8.4 Counterweight
The counterweight shall be of the structural frame type and designed to balance the total
weight of the finished lift car plus not less than 40% of the rated load. Space shall be left for
the addition of further filling weight to a minimum of 10% of the total calculated weight
required.
Counterweight and associated equipment shall be designed and installed to minimise noise.
Noise from the counterweight or associated equipment shall not be audible from within the
lift car, or on any of the occupiable areas.
Counterweights shall also be fully balanced after correct final weights are established.
The counterweight filler weights shall be painted bright yellow for safety purposes.
8.4.1 Guide Shoes
Each counterweight shall be fitted with roller or slipper guide shoes, adjustable to ensure
sufficient contact with the guide rails.
Adjustment shall be made to ensure the counterweight will hang vertical at the mid-point of
travel, prior to the top set of guide shoes being finally bolted in position.
Two way intermediate switching for the luminaries shall be provided within easy reach in the
lift well at the bottom and top floors served and the lift machine access door.
Guide shoes shall be located at maximum vertical spacing permissible within the specified
overrun dimensions. Care should be taken to ensure guide centres do not coincide with rail
fixing centres or rail joint centres.
• equipment number
6) independent service key switch
7) emergency telephone call button complete with engraved details of building address
8) car light and fan key switch
9) fire service control
10) Car Position Indicators
Car position indicators shall be in the form of electronic LCD screens display types featuring
minimum 50 mm high characters.
Floor designation numerals and letters shall be capitals and shall be reprogrammable.
Position indication shall be in the form of numerals and/or letters corresponding to the floors
served such that they illuminate brightly when arriving at each floor.
Whenever the emergency telephone button in the lift car is pressed, the following shall be
activated:
2. the door open signal to the control system; if the lift is within the door zone the doors
shall re-open if they are operable.
3. after at least three seconds of constant pressure, the hands-free telephone system in
the lift car shall autodial to the nominated location,
Fully programmable two-way hands free auto-dialling telephone system in the lift car,
compatible with the aforementioned wireless gateway shall include:
• Dual LED illuminating ‘AMBER/AMBER’ colour telephone button, to illuminate brighter
to indicate connection to the emergency answering service.
• Loudspeaker volume set to normally produce a sound pressure level 1 m in front of
the speaker of 70 dB(A), adjustable
• Automatic dial out to the lift maintenance contractor’s emergency call centre or other
24 hour manned remote locations,
• Remote lift identification at the lift maintenance contractor’s emergency call centre
• External callers (eg contractor’s emergency call centre) shall be capable of dialling
into the lift car
The passenger protection device shall incorporate a nudging feature, which, after an
adjustable pre-set time, shall cause the doors to close at a reduced speed and sound an
audible buzzer. Such nudging feature to be initiated under any of the following conditions:
1) obstruction of the passenger protection device for an extended period
2) the passenger protection device becoming inoperative for any reason
3) stuck landing button at a floor where the lift is parked
The door open button shall remain operative at all times and upon operation shall reset the
time delay for nudging operation.
Interruption of the passenger protection device shall reduce the door open dwell time to less
than one second once the entrance becomes clear.
10 LANDING EQUIPMENT
Supply and fix mild steel forming strips to the lift well side of all door frames to facilitate
building in by the Builder without entering the lift-well.
Door panels shall be perfectly flat without sharp edges dents or dishing and constructed to
withstand severe service conditions.
Sight guards, where fitted, shall be finished in the same material as the doors and shall be
provided and attached to the leading edges of door panels and shall be equal in height to
the clear opening height.
Landing doors shall be fitted with removable guides to slide silently in the groove of the
landing sills.
Protection of landing door and frame finishes up to the time of practical completion shall be
provided.
Landing door closers shall be based on an air cord connected counterweight system and
shall slide silently in enclosed guide tubes fitted with over travel stops.
Clearances between the landing door vanes and pick up rollers and the opposite car door
member shall be tight fitting during door opening and closing cycles. The fit shall only be
reduced on the coupler mechanism in the final closing sequence. In all cases, the fit shall
not enable slop between the car and landing door sets.
Emergency door unlocking devices shall be provided at all landings.
The units shall be constructed and installed such that no light leakage occurs.
Units shall be suitably sized or treated, e.g., steel plates behind, to comply with local
Building Regulations in relation to maintaining the fire rating of lift-well.
11.4 Operation
On automatic control, the method of operation for the lift shall be as described below.
Each landing call shall be cancelled immediately the car commences to slow down in
answer to the call.
Car call preference shall be provided and shall be maintained at least until commencement
of the door closing sequence.
The lift shall park with its doors closed.
12 SOFTWARE
12.1 General
Supply all equipment and software for the project capable of handling and interpreting
without error, time, day and year dates including leap years, without the necessity of human
intervention, i.e., free of any date related bug or issue.
Ensure that all equipment and components including software, firmware and controls
conforms to the requirements of Australian Standard HB104 or British Standard PD2000.
Where modifications are made to existing systems as part of the works, the Contractor shall
provide certification of the systems compliance with these clauses prior to practical
completion of the works.
Access to control and drive motor parameter settings shall be free, without project or
manufacturer specific passwords, flash card re-initialisation or run timer menu shutdowns.
Where lifts are controlled via a programmable logic controller, then the installing contractor
shall provide the diagnostic tool, the programme and schematic ladder diagram on CD.
These shall be handed over when the lift is commissioned and accepted by the Owner.
13 ELECTRICAL
13.5.2 General
All equipment and/or appliances provided under this specification shall not cause electrical
interference to any other equipment within the building. If the inherent characteristics of the
lift equipment are such that interference is possible, provide efficient devices capable of
suppressing the interference.
13.5.3 Limitation of Disturbances
Solid state direct drive units shall be isolated electrically from the main supply by an isolation
filter transformer to prevent high frequency harmonic feedback. A ripple filter shall be
incorporated to reduce harmonic distortion to the machine.
Limit the overall voltage distortion factor at the lift electrical switchboard to a maximum of
3%.
Precautions shall include compensation for the following:
1) harmonic distortion
2) flicker
3) line notching
Installation with an overall voltage distortion factor exceeding 3% will not be accepted.
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Site
Carpark Bitumen Bitumen - Black - -
Paving - - - - - Refer Landscape Schedules
Walls
Masonry Walls (Brick) Clay Brick Face Brick Midland Brick Opal Blush 290x90x162mm Rolled joints to match existing
Refer to drawings for coursing detail
Masonry Walls (Brick) Clay Brick Face Brick Midland Brick Opal Blush 290x90x76mm Rolled joints to match existing
Refer to drawings for coursing detail
Retaining Walls Clay Brick Face Brick Midland Brick Opal Blush 290x90x162mm Rolled joints to match existing
Steel Sheet Cladding Zincalume Custom Orb Colourbond Bluescope Steel Surfmist Spandek -
Masonry Walls (Brick) Cement Render Sand Finish render with Dulux Acratex To be selected - -
Textured Paint coating
Fibre Cement (Walls) Compressed Fibre Low Sheen acrylic paint Dulux Weathershield Colorbond Surfmist C1 -
Cement sheeting
Fibre Cement (Walls) Compressed Fibre Low Sheen acrylic paint Dulux Weathershield Feature Colour TBS TBS -
Cement sheeting
Steel Structure
Steel Columns Steel Hot dip galvanised - - - -
Steel Beams Steel Hot dip galvanised - - - -
Steel PFC Fascia Beam Steel Gloss Polyurethane Dulux Weathermax HBR Colorbond Basalt C30 Surface Treatment to drawing S1001
Note S23 Type B.
Weathermax HBR top coats to Dulux
specification.
Doors & Windows
Door & Window Frames Aluminium Powdercoat Dulux Duralloy Basalt 260-7473S Satin -
Doors (Swing doors) Aluminium Powdercoat Dulux Duralloy Surfmist 272-1137S Satin -
Doors (Bi Fold doors) Aluminium Powdercoat Dulux Duralloy Basalt 260-7473S Satin -
Doors Timber Semi-Gloss Enamel Paint Dulux Aquanamel Colorbond Surfmist C1 -
Door Frames Steel Semi-Gloss Enamel Paint Dulux Aquanamel Colorbond Basalt C30 -
Page 1 of 3
EXTERIOR FINISHES SCHEDULE
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Doors & Frames (Electrical) Timber / Steel Semi-Gloss Enamel Paint Dulux Aquanamel To match feature wall TBS -
colour TBS
Window Awning Heka Hood Aluminium Powdercoat Dulux Duralloy Basalt 260-7473S Satin -
Security Screens Stainless Steel Powdercoat - Black - -
Security Screen Frames Aluminium Powdercoat Dulux Duralloy Basalt 260-7473S Satin -
Roller Shutter Steel Powdercoat B & D Roller Doors Dulux Surfmist 272-1137S Satin -
Glazing
Vision Glass - Comfort Plus Viridian Clear - Refer Door & Window Schedule
Vision Glass - Comfort Plus Viridian Neutral - Refer Door & Window Schedule
Louvres & Grilles
Wall Grilles Aluminium Powdercoat Dulux Duralloy Surfmist 272-1137S Satin -
Soffit
Soffit Lining Fibre Cement Low Sheen Acrylic Paint Dulux Weathershield Colourbond Surfmist C1 -
Soffit Lining Zinclaume Colourbond Australian Ceiling Surfmist Perforated -
Systems Corruline
Roof
Roof Sheeting Steel Colourbond Bluescope Steel Surfmist Spandek profile -
Capping and Flashings Steel Colourbond Bluescope Steel To match roof - -
Translucent roof sheeting Fibreglass reinforced - Ampleite Opal Wonderglas GC FS Firecheck 2400
polyester
Eaves Gutter Steel Colourbond Bluescope Steel Basalt - -
Rainwater Downpipes Steel Hot dip galvanised - - - -
Miscellaneous
Balustrade framing & Steel Hot dip galvanised - - - -
handrails
Screens UWB5050 Aluminium Powdercoat Bluechip Woodstock UW2311 -
Battens
Balusters UWB5050 Aluminium Powdercoat Bluechip Woodstock UW2311 -
Battens
Page 2 of 3
EXTERIOR FINISHES SCHEDULE
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Bag Racks Compact Laminate Carbide Finish Laminex Sentry Alfresco Compact -
Laminate
Exposed Concrete Structure
Concrete Columns Concrete Class 2 finish - Portland grey cement - Fosroc Niticote SN502 Clear matt
sealer
Concrete Beams Concrete Class 2 finish - Portland grey cement - Fosroc Niticote SN502 Clear matt
sealer
Concrete Soffit Concrete Textured Paint Dulux Acratex Colourbond Surfmist C1 -
Concrete Balcony Floor Concrete Screed Wood float finish to - Portland grey cement - Dulux Avista water based sealer.
P4/R11 slip resistance
END OF SCHEDULE
Page 3 of 3
INTERIOR FINISHES SCHEDULE
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 1 of 3
INTERIOR FINISHES SCHEDULE
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 2 of 3
INTERIOR FINISHES SCHEDULE
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 3 of 3
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 1 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
FA-01
LA-01
A-G04 NW WL-01 CA-01 SK-01/PA-02 CE-01 - - - - - - -
Office PA-01 CE-02
NE WL-02 SK-01/PA-02 PA-04 - - - -
PA-01
SE WL-02 SK-01/PA-02 - - - - -
PA-01
SW - - PC-01 PC-02 - PC-01 PC-01
A-G05 NW WL-02 TF-01 SK-02 CE-02 PA-03 PA-03 - - - - LA-04 Toilet cubicle panels &
Toilets PA-01 PA-04 doors
NE WL-02 SK-02 - - - - - - Washplane Basin SF-01
PA-01
SE WL-02 SK-02 - - - - - -
PA-01
SW WL-02 SK-02 - - - - - -
PA-01
A-G06 NW WL-02 TF-01 SK-02 CE-02 - - - - - - TR-01 to TW-02 edges
UAT 1 PA-01 PA-04
TW-01
NE WL-02 SK-02 PA-03 PA-03 - - - -
PA-01
SE WL-02 SK-02 - - - - - -
PA-01
SW WL-02 SK-02 - - - -
PA-01
TW-01
A-G07 NW WL-02 RF-01 SK-01/PA-02 CE-02 PA-03 PA-02 - - - - -
Store PA-01 PA-04
NE WL-02 SK-01/PA-02 - - - - - - -
PA-01
Page 2 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
SE WL-02 SK-01/PA-02 - - - - - - -
PA-01
SW WL-02 SK-01/PA-02 - - - - - - -
PA-01
A-G08 NW WL-02 RF-01 - CE-02 - - - - - - -
Comms PA-01 PA-04
NE WL-02 - - - - - - - -
PA-01
SE WL-02 - - - - - - - -
PA-01
SW WL-02 - PA-02 PA-02 - - - - -
PA-01
A-G09 NW WL-02 TF-01 SK-02 CE-02 PA-03 PA-03 - - - - LA-04 Toilet cubicle panels &
Toilets PA-01 PA-04 doors
NE WL-02 SK-02 - - - - - - Washplane Basin SF-01
PA-01
SE WL-02 SK-02 - - - - - -
PA-01
SW WL-02 SK-02 - - - - - -
PA-01
A-G10 NW BR-01 CS-01 - CE-02 - - - - - - -
Electrical PA-01 PA-04
NE BR-01 - PA-05 PA-05 - - - - -
PA-01
SE BR-01 - - - - - - - -
PA-01
SW BR-01 - - - - - - - -
PA-01
A-G11 NW WL-02 RF-01 SK-01/PA-02 CE-03 PC-01 PC-02 - PC-01 - - TR-01 to FA-01/LA-01 edges
Kitchen PA-01 MA-01 PA-04
Page 3 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 4 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 5 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 6 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
W WL-01 SK-01/PA-02 - - - - - -
PA-01
B-08 N WL-01 CA-01 SK-01/PA-02 CE-02 - - - - - - 3 No. AP-01panels to N wall
Meeting Room PA-01 PA-04
AP-01
E WL-01 SK-01/PA-02 - - PA-02 PC-01 BL-01 -
PA-01
S WL-01 SK-01/PA-02 - - - - - -
PA-01
W - SK-01/PA-02 PC-01 PC-02 - PC-01 - -
B-09 N WL-02 TF-01 SK-02 CE-02 - - - - - -
WC PA-01 PA-04
E WL-02 SK-02 PA-03 PA-03 - - - -
PA-01
S WL-02 SK-02 - - - - - -
PA-01
TW-02
W WL-02 SK-02 - - - - - -
PA-01
B-10 N WL-02 RF-01 SK-01/PA-02 CE-02 - - - - - Refer
Parent Room PA-01 PA-04 Cabinetry
SF-01 Schedule
E WL-02 SK-01/PA-02 - - - - - -
PA-01
S WL-02 SK-01/PA-02 PC-01 PC-02 - PC-01 - -
PA-01
W WL-02 SK-01/PA-02 PA-03 PA-03 - - - -
PA-01
B-G11 N WL-02 TF-01 SK-02 CE-02 PA-03 PA-03 - - - - Toilet cubicle interior finishes to
Toilets PA-01 PA-04 match.
Page 7 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 8 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 9 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
S WL-02 SK-02 - - - - - -
PA-01
W WL-02 SK-02 - - - - - -
PA-01
B-G19 N WL-01 RF-01 SK-01/PA-02 CE-01 - - - - - - -
Activity Area PA-01 MA-01 CE-02
FA-01 PA-04
LA-01
E - - PC-01 PC-02 - PC-01 - - Bifold Doors – PC-01
S WL-01 SK-01/PA-02 - - - - - Refer -
PA-01 Cabinetry
FA-01 Schedule
W WL-02 SK-01/PA-02 PC-01 PC-02 - PC-01 - - TR-01 to TW-01 edges
PA-01
TW-01
B-G20 N WL-01 RF-01 SK-01/PA-02 CE-01 - - - - - Refer -
Activity Area PA-01 MA-01 CE-02 Cabinetry
FA-01 PA-04 Schedule
E - - PC-01 PC-02 - PC-01 - - Bifold Doors – PC-01
S WL-01 SK-01/PA-02 - - - - - -
PA-01
FA-01
LA-01
W WL-02 SK-01/PA-02 PC-01 PC-02 - PC-01 - - TR-01 to TW-01 edges
PA-01
TW-01
B-G21 N WL-01 RF-01 SK-01/PA-02 CE-01 - - - - - Refer -
Activity Area PA-01 MA-01 CE-02 Cabinetry
FA-01 PA-04 Schedule
E - - PC-01 PC-02 - PC-01 - - Bifold Doors – PC-01
Page 10 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
S WL-01 SK-01/PA-02 - - - - - - -
PA-01
FA-01
LA-01
W WL-02 SK-01/PA-02 PC-01 PC-02 - PC-01 - - TR-01 to TW-01 edges
PA-01
TW-01
A-F01 NE - CA-01 - CE-01 PC-01 PC-01 - - - Refer LA-01 to sliding operable wall
General Learning MA-01 CE-02 Cabinetry
Area PA-04 Schedule
SE WL-01 SK-01/PA-02 PC-01 PC-02 - PC-01 - - -
PA-01
SW WL-01 SK-01/PA-02 - - - - - - TR-01 to FA-01 edges
PA-01
FA-01
NW WL-01 SK-01/PA-02 PC-01 PC-01 - - - - -
PA-01
LA-01
A-F02 NE - CA-01 - CE-01 PC-01 PC-01 - - - Refer LA-01 to sliding operable wall
General Learning MA-01 CE-02 Cabinetry
Area PA-04 Schedule
SE WL-01 SK-01/PA-02 PC-01 PC-02 - PC-01 - - -
PA-01
SW WL-01 SK-01/PA-02 PC-01 PC-01 - - - - LA-01 to sliding operable wall
PA-01
FA-01
NW WL-01 SK-01/PA-02 PC-01 PC-01 - - - - -
PA-01
LA-01
Page 11 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 12 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
PA-01
SW WL-01 SK-01/PA-02 PA-03 PA-02 - - - - -
PA-01
NW WL-01 SK-01/PA-02 - - - - - - -
PA-01
B-F01 N WL-02 TF-01 SK-02 CE-02 - - - - - - LA-04 Toilet cubicle panels &
Male Toilets PA-01 PA-04 doors
E WL-02 SK-02 - - - - - - Washplane Basin SF-01
PA-01
S WL-02 SK-02 - - - - - -
PA-01
W WL-02 SK-02 PC-01 PC-02 - - - -
PA-01
B-F02 N WL-02 TF-01 SK-02 CE-02 - - - - - - -
Staff WC PA-01 PA-04
TW-02
E WL-02 SK-02 - - - - - -
PA-01
S WL-02 SK-02 PA-03 PA-03 - - - -
PA-01
W WL-02 SK-02 - - - - - -
PA-01
B-F03 N WL-02 TF-01 SK-02 CE-02 PA-03 PA-03 - - - - -
UAT PA-01 PA-04
E WL-02 SK-02 - - - - - -
PA-01
TW-02
S WL-02 SK-02 - - - - - -
PA-01
W WL-02 SK-02 - - - - - -
PA-01
Page 13 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
B-F04 N WL-02 TF-01 SK-02 CE-02 - - - - - - LA-04 Toilet cubicle panels &
Female Toilets PA-01 PA-04 doors
E WL-02 SK-02 - - - - - - Washplane Basin SF-01
PA-01
S WL-02 SK-02 - - - - - -
PA-01
W WL-02 SK-02 PC-01 PC-02 - - - -
PA-01
B-F05 N - CA-01 - CE-01 PC-01 PC-01 - - - Refer LA-01 to sliding operable wall
General Learning MA-01 CE-02 Cabinetry
Area PA-04 Schedule
E WL-01 SK-01/PA-02 PC-01 PC-01 - - - - -
PA-01
LA-01
S WL-01 SK-01/PA-02 - - - - - - TR-01 to FA-01 edges
PA-01
FA-01
W WL-01 SK-01/PA-02 PC-01 PC-02 - PC-01 - - -
PA-01
B-F06 N - CA-01 - CE-01 PC-01 PC-01 - - - Refer LA-01 to sliding operable wall
General Learning MA-01 CE-02 Cabinetry
Area PA-04 Schedule
E WL-01 SK-01/PA-02 PC-01 PC-01 - - - - -
PA-01
LA-01
S WL-01 SK-01/PA-02 PC-01 PC-01 - - - - LA-01 to sliding operable wall
PA-01
FA-01
W WL-01 SK-01/PA-02 PC-01 PC-02 - PC-01 - - -
PA-01
Page 14 of 15
INTERIOR FINISHES SCHEDULE ROOM BY ROOM
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL- STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
Page 15 of 15
INTERIOR FINISHES SCHEDULE CABINETRY
PROJECT PROVIDENCE CHRISTIAN COLLEGE PRIMARY SCHOOL-STAGE 1 PROJECT NO. 19.06 DATE OF ISSUE 23 December 2020 REVISION 0
This schedule is to be read in conjunction with the drawings and specifications. Submit control samples of all finishes for approval and keep on site once approved.
ROOM ITEM PLINTH CUPBOARDS BENCH TOP OPEN SHEVLVING EDGES FRAMING NOTES
INTERNALS FACE HANDLES SHELVES SURROUND
A-G01, A-G02, Cupboard LA-02 White LA-03 HD-02 - LA-02 LA-02 ABS - Face matched ABS edging
B-G19, B-G20, Melamine ABS Multiplex Ply ABS edging
B-G21 to LA-03
Activity Area
A-G11, B-G16 Kitchen LA-02 White LA-02 HD-01 SF-01 - - ABS - Face matched ABS edging
Kitchen cupboards Melamine SF-01 splashback
Kitchen - White LA-03 HD-01 - - - ABS - ABS Multiplex Ply ABS edging
Overhead Melamine
Cupboards
Laundry LA-02 White LA-02 HD-01 SF-01 - - ABS - Face matched ABS edging
Cupboard Melamine SF-01 splashback
Laundry - White LA-03 HD-01 - - - ABS - ABS Multiplex Ply ABS edging
Overhead Melamine
Cupboards
B-G01 Wall Shelf - - LA-02 - - - - ABS - Face matched ABS edging
Cleaner
B-G05 Kitchen LA-02 White LA-02 HD-01 SF-01 - - ABS - Face matched ABS edging
Staff Study cupboards Melamine SF-01 splashback
Kitchen - White LA-03 HD-01 - - - ABS - ABS Multiplex Ply ABS edging
Overhead Melamine
Cupboards
B-G10 Cupboards LA-02 White LA-02 HD-01 SF-01 - - ABS - Face matched ABS edging
Parent Room Melamine SF-01 splashback
A-F01, A-F02, A- Cupboard LA-02 White LA-03 HD-01 - - - ABS - ABS Multiplex Ply ABS edging
F03, B-F05, B- Melamine
F06, B-F07
General
Learning Area
END OF SHEDULE
Page 1 of 1
ATC WILLIAMS PTY LTD
Perth
t +61 8 9213 1600
1141 Hay Street,
West Perth, WA, 6005
atcwilliams.com.au
ABN 64 005 931 288
BPA Engineering
460 Roberts Road
SUBIACO WA 6008
Dear Long,
1 INTRODUCTION
This report presents the results of a geotechnical investigation carried out at the Providence
Christian College Primary School in Southern River. The plans provided indicate that a northern
portion of the existing Primary School site located to the northwest of the existing Administration
building will be demolished and replaced with four new double storey Primary Teaching Block
buildings. A new covered Piazza area is proposed to be constructed in the middle. In addition
to this, several car parking areas are also proposed to be constructed to the north and west of
the proposed building area.
Footing design criteria including allowable bearing pressures for pad and strip
footings.
Soil permeability and suitability of site for on-site disposal of stormwater (if granular
soils are encountered).
Terms of reference for this investigation were provided in ATC Williams proposal 120118.01P01
dated 9 June 2020. Authorisation to proceed was received from Long Truong of BPA
Engineering in an e-mail dated 26 June 2020.
The study site is located on the western side of Furley Road in Southern River and has a total
area of approximately 14.5 ha.
The available geological map for the area [3] indicates the site to be underlain by thin Bassendean
sand overlying clayey soils of the Guildford Formation.
The Perth groundwater atlases (1st and 2nd Editions [4],[5]) indicate groundwater levels at the site
to be between 24.5 m AHD and 23 m AHD, respectively.
3 SCOPE OF WORKS
Due to the limited access to the proposed building area, only the Stage 1 investigation was
carried out. The fieldwork was carried out on 9 July 2020 and comprised:
Dial Before You Dig underground service search for the site and engagement of the
underground service locator to clear the proposed CPT and HA borehole locations of
any underground services (undertaken on the 8 July 2020).
Four electric friction cone penetrometer tests (CPTs) (located at the front portion and
rear portion of the site), advanced to depths of between 4.4 m (CPT04) and 7.6 m
(CPT03).
Three hand auger boreholes (HA01-HA03) (located within the proposed building
areas) advanced to depths of 1.9 m (HA1), 1.8 m (HA2), and 0.7 m (HA03) to visually
assess subsurface conditions and obtain samples for laboratory testing.
Excavation of two shallow test pits located in the proposed car parking areas at the
northern portion of the site to obtain samples for the Standard compaction and
soaked CBR testing.
Four Perth Sand Penetrometer (PSP) tests, one adjacent to each borehole and
shallow test pit, to a depth 1.05 m to determine the relative density of the subgrade.
On complete of the excavations, all boreholes and shallow test pits were backfilled and levelled.
4 LABORATORY TESTING
The following laboratory tests were carried out on soil samples recovered from selected
borehole and test pit locations across the site:
The borehole logs (including PSP test results) and photographs in Appendix B.
Topsoil: A thin layer of loose, fine and medium, brown sand with trace silt and grass roots
was encountered in all hand auger boreholes
Fill: A layer of medium dense to dense yellow brown sand material was encountered
in all hand auger locations, below the topsoil to depths of approximately 0.8 m
below ground level (BGL).
Sand: Dense fine and medium, pale grey sand was encountered in all hand auger
locations to depths of up to and beyond 1.9m below the ground level.
The CPT probes (CPT1-CPT4) located in the proposed building area, indicate
the presence of dense sand in all CPT locations. A localised area of medium
dense sand was encountered in CPT01 and CPT03 at depth of 3.5 to 4.5 m below
ground level (BGL).
Groundwater: Groundwater was encountered in all CPT locations (but CPT02) at depths of
approximately 3.4m (CPT01) to 3.7m (CPT04) below ground level (BGL).
Selected soil samples recovered from hand auger boreholes and test pit locations were submitted
for laboratory classification testing.
The results of a Particle Size Distribution test carried out on a sample sand from HA1, located
within the proposed building area, are summarised in TABLE 1.
The results of compaction and soaked CBR testing are summarised in TABLE 2.
A soil sample obtained from HA03 (0.4 – 0.7 m) was assessed for the purpose of soil exposure
classification with respect to concrete durability. The results of pH and SO 4 are summarised in
TABLE 3 on the following page.
After site preparations are carried out in accordance with Section 7.3, the site is considered to
be a Class A site in accordance with AS 2870-2011 [1].
The site sub-soil class is Ce (shallow soil site) in accordance with AS 1170.4-2007 [2],
Prior to bulk earthworks commencing, the existing building on site should be demolished and the
entire site should be stripped of topsoil, trees, tree roots, and any other unsuitable material. The
exposed subgrade should be proof compacted and any excavations to remove trees and tree
roots should be backfilled with clean sand fill and compacted to a dry density ratio of at least 95%
relative to Standard Maximum Dry Density (SMDD) in accordance with AS 3798-2007 [6]
It is recommended that the subgrade compaction is verified using a Perth Sand Penetrometer
(PSP) with a target of at least 7 blows/300 mm in the depth range 150 mm to 450 mm below the
compacted surface.
It is recommended that all site preparation earthworks compaction is verified by PSP testing
prior to footing construction.
Following site preparation and compaction verification testing detailed in Section 7.3, the
subsurface conditions are considered suitable to support standard footings designed in
accordance with AS 2870-2011 [1], including slab on ground footing systems and systems
comprising pad and strip footings.
The assessment is based on the results of CPT03 probe and assumes footing depths of at least
0.60 m. In order to maintain foundation settlements within tolerable limits (approximately 15 mm)
allowable bearing pressures not greater than 150 kPa are recommended for pad footings and for
strip footings.
Figure 3 and Figure 4 provides an indication of predicted pad and strip footing settlements
respectively for various column loads and bearing pressures.
In all instances the base of footing excavations supported on sand should be proof compacted
using a plate compactor prior to footing construction.
Following the site preparation work, the subgrade should comprise compacted sand. Provided
the in-situ material is compacted to at least 98% SMDD, a design subgrade CBR of 14% (light
brown sand) is considered appropriate for pavement design, based on laboratory test results.
Chemical analysis of a sand sample was undertaken to determine the site exposure classification
in accordance with AS 3600 [7]. Based on the test results, non-aggressive conditions are inferred
and an exposure classification of A1 is considered satisfactory for concrete buried within
approximately 0.7 m of the site surface.
Near-surface level soakwells should be suitable for stormwater drainage at the site if placed in
the areas with deeper sand deposits. Based on empirical calculations, a soil infiltration rate of
approximately 4.0 x 10-4 m/s is suggested for the near-surface level sand deposits encountered.
Soakwells should be placed as far as possible from foundations. Exact distances will depend on
the depth of footings and soakwells but generally, a line drawn downward and outward at a slope
of 1H:1V from footing edges should not intersect with a soakwell.
8 CLOSURE
Your attention is drawn to the “Conditions of Investigation and Report” which are presented at
the end of this report.
Yours sincerely,
[2] AS 1170.4 (2007): Structural Design Actions Part 4: Earthquake Actions in Australia.
[3] Geological Survey of Western Australia. 1:100,000 Environmental Geology Series, Perth
Sheet.
[4] Water and Rivers Commission (1997): Perth Groundwater Atlas (1st Edition).
[6] AS 3798 (2007): Guidelines on earthworks for commercial and residential development.
2. This report has been prepared by ATCW for the purposes stated herein and ATCW’s experience,
having regard to assumptions that can reasonably be expected to make in accordance with sound
professional principles. ATCW does not accept responsibility for the consequences of
extrapolation, extension or transference of the findings and recommendations of this report to
different sites, cases, or conditions.
3. This document has been prepared based in part on information which was provided to ATCW by
the client and/or others and which is not under our control. ATCW does not warrant or guarantee
the accuracy of this information. The user of the document is cautioned that fundamental input
assumptions upon which the document is based may change with time. It is the user’s
responsibility to ensure that these assumptions are valid.
4. Unless specifically agreed otherwise in the contract of engagement, ATCW retains Intellectual
Property Rights over the contents of the document. The client is granted a licence to use the report
for the purposes for which it was commissioned.
2. The scope of the work has been planned in the absence of any fore knowledge of the site other
than that stated in the report. Unless otherwise stated we consider that the number of locations
investigated and the depths to which they have been investigated are reasonable bearing in mind
the scale and nature of the project, and the defined purpose for which the investigation was
undertaken.
3. We do not accept any responsibility for any variance between the interpreted and extrapolated
conditions and those that are revealed by any means subsequently. Specific warning is also given
that many factors, either natural or artificial, may render ground conditions different from those
which pertained at the time of the investigation. Should there be revealed during the construction
or at any other time any apparent difference from subsurface conditions described or assessed in
this report, it is strongly recommended that such differences be brought to our attention so that its
significance may be assessed, and appropriate advice given.
0
0m
REV DESCRIPTION
CLIENT ISSUE
40 m
26 26
.72 .93
26 27
27
.09
.42 .02
26
.39
26
26 .88 27
.73 .06
27
119°49'5"
27
.11
.0
26
.43
26 26 27
26 26 .78 .90 .19
112
.25 .67
26
.98
26
DP414958
80 m
.27 26
.48
26 26 26 27 27
.17 .72 .93 .07 .19
26.3
26
26
26
.24
.34
.10
26
.21
26
.16
26
27
109.
89 26.5
.31
.20
26 26
.11 .24 27
.26
26
27
.8
27
26 26 .19 .15
.39
07/07/20
.09
25
.98 26 27
26 .49 26 27 27 .22
26
.58
26
.71
27
.25
RM
26
26
.58
.30
26
.14 26 27
.69 27 .24
.13
26
CPT04
26
.00
.61
27.0
28 27
.24 .20
PC
25
27
.90
.22
26
.90
27
26 27
.23
.69 26
.55 .26
27 27
26
.18T .26
.64
OW
27 27
STP01
.22 .18
26
.64 27 12
.20T
DATE
27
0.9
HA03
FIG
26 OW
26 1 .20
.57 .71 27
26 .23
.43 26 27
26 .80T .06
2
DRAWN
.66T
DESIGN
OW
OW 27
26 .17
.48
26
A
.56
CHECKED
27
26.5
26 26
120 m
.26 27
.30 26 .88 27
26 26 .41T .29
.32
SHT SIZE A4
.44
SCALE 1:1000
26
.39
PR
PC
RM
RM
26 27
SHEET 1 OF 1
.95 .24
27
03/07/20
26 .28
.14
27
26 26 .26
.72 .40
27
.20 27
27 .20
26 .11 27
.00 .21
27
.17
26
.81 27
.07
26
27
.47
.08
25
25 .99
.88 27 26
.15 .92
29
26 26
.24
26
27
.09
OW
HA02
26.5 26
.91
26 26
.64 .8
25 26
.74 .82
26
.61
26
CPT03
26 .68 27
HA01
.31 26 .08T
27.3
.61 OW
26
.74
26
STP02
26
26 OW
.5
.53
26
.22
160 m
27 26
.03T .40 26
25 OW .47
26
.77
.86
26
26 .64 26 26
.42 26 .37 .32
.85
26
.25
26
.40
26.0
26
.19
25.8 26
.06 26 26
.65 .85
26
26 .87 26
27 .92 .20
.02T
26 26
.22 OW .96
25 26
.60 .19
26
.05 26
.62
25
.89
26
.05
26
CPT01
CPT02
.21
26
26 26 .55
.07 .45 26 26
26 .44 .49 26
.30 .19 27
26 .15
.14
26
26 .36
.20 26
26 26 26.1
.17 6
.38
.21 26 26
.22 26 .34
.15
25
.55 26 26
.29 .20 26 26 26
.12 .27 .90
26
26 26 26 .25
.22 .15 .10
26 27
26
.12
.19
.47
26
26 .08
.12 26
.80
26
.49
26
.03
26 26
.23 .05 26 26
.74 .89
26 26 26
.20 .06 .03
26 26
.21 .02
26
.16
25 26 26
26
200 m
.99 .10
.026 .74
26.0
26 1.07
.0 25
2626 1 .98
FU
.00.0
25 4
.96 25
R
.93
26
26 .0 26
.07 26 250 .41
LE
25 .02 .9
8 25
.92
25 26
Y
25 .9256
25 .60
25.8
25
www.atcwilliams.com.au
.75 .27
.98
25
.84
25 26
.87
25 .45
26
26 .79
.04
.01 26
.49
25
.80
26.0
25
FU
.89 26
.06
26 25
R
26.0
.09 .82
R
26
25 .31
O
.75
26 26
LE
.06
-
.09 25 25
AD
.88 25 25
.81
Y
.83.78
25 25 26
25
.73 25.77 25 26
.7 .36
.75
9 25
.82 .00
R
.72
26 26
26 .05 26
D
.06
26 .03 .24
.09 25
.80
25
.95
25
25
.62 25 26
.64
26
.92 25 25
.29
.57
.09 25 .93 25
.93 .94
26 25 26
.08 .95 25 25 .17
26 .55 .96
25 .11 26
.98 .03
LEGEND:
26 26
.09T 25
.04 .92 26
OW .10
25
.76
25 26
25 .97
.97 25 25.9 26 .23
.94 4 .09 26 25 25
.13T .96 .90
OW
25 26
25 .76 .02
.95
25
.93 26
.13 26
25 26 .19
.11
.85
LOCATION
25
.97 26 26
.01
25
.06
25 25
.84
25 .85 .99
.95
26
.08
25
25 .97
25 .87 25
26 .98 25 .99
.08 25 .91
.99
25
26 .97 25 25
.09 .94 .97
25
.98
25 25
- CPT LOCATION
26 .91
PLAN
.08 .98
25
25 .99
25 .98
.99
JOB No. 120118.01 REV No. 0
25
25 25 25 .91
.96 .92 .98
26 25
.00 26
25
.94 26 .06
.0254 2626
26262626
.91 .94 26
0.11.1.1.12
.1.10.126
25 26 .12234
26 .90 .16
26 25
.0252
25 .07
25
.96 26 .93
.01
.88 .88
25
.87
HAND AUGER AND PSP
25 25
.92 .93
25
25 .9
25
25 .94 5
.97
.94
25
25
25 25
.95
.88
25 26
26
26 .0 .93 .97
.91 26
25 25 2626.0.0.0877 25
26
25
0 .11.12
25 .94 .91
.91
BPA ENGINEERING
.89 25 5
26
.0 .80
26 8
.08
26
INFERRED NEW BUILDINGS
26.0
25 .07
STAGE 1 SITE INVESTIGATION
26 .92
.07 25 25
2526 25 .78 .71 25
.99.0 .87 .77 25
8 26 .79
.07
25 25
.84
25 25 .76
FIGURE 1
PROVIDENCE CHRISTIAN COLLEGE
.93 .74
- SHALLOW TEST PIT LOCATION
25
.93 25
25 .76
25
25.8
.88
.72
25 25 25
.95 .79
25 .84
.93
NATURAL
GROUND SURFACE
FILE: G:\SYNERGY\PROJECTS\120\120118 PROVIDENCE CHRISTIAN COLLEGE PS\01 SITE INVESTIGATION\CADD\120118.01 SITE PLAN.DWG
INFERRED TOP OF
NATURAL SAND LAYER
5
Footing Settlement - mm
100
10
150
15
200
20
250
25
300
30 350
35
Notes: The settlements are based on the Schmertmann calculation method using E/qc = 5
Based on the cone resistance data from CPT03
The footing founding depth is 0.5m
The footing aspect ratio is constant for all footings (L/B = 1)
G:\Synergy\Projects\120\120118 Providence Christian College PS\01 Site Investigation\Data and Calcs\[Schmertmann Settlement Calculation CPT03.xlsm]Column Load Plot
5
100
10 150
200
15
250
20
300
25
350
30
Notes: The settlements are based on the Schmertmann calculation method using E/qc = 5
Based on the cone resistance data from CPT03
The footing founding depth is 0.5m
The footing aspect ratio is constant for all footings (L/B = 10)
G:\Synergy\Projects\120\120118 Providence Christian College PS\01 Site Investigation\Data and Calcs\[Schmertmann Settlement Calculation CPT03 Strip.xlsm]Column Load Plot
10
10
15
20
25
30
35
40
45
50
55
60
10
0
1
2
3
4
5
6
7
8
9
0
5
0
1
2
3
4
5
6
7
8
9
0
0
Tip Resistance
Friction Sleeve
1
1
2
2
3
3
Depth (m)
Depth (m)
Depth (m)
4
4
5
5
6
6
7
7
8
8
0
100
200
300
400
500
600
10
10
15
20
25
30
35
40
45
50
55
60
10
0
1
2
3
4
5
6
7
8
9
0
5
0
1
2
3
4
5
6
7
8
9
0
0
1
1
2
2
3
3
Depth (m)
Depth (m)
Depth (m)
4
4
5
5
6
6
Tip Resistance
Friction Sleeve
7
7
8
8
0
100
200
300
400
500
600
10
10
15
20
25
30
35
40
45
50
55
60
10
0
1
2
3
4
5
6
7
8
9
0
5
0
1
2
3
4
5
6
7
8
9
0
0
1
1
2
2
3
3
Depth (m)
Depth (m)
Depth (m)
4
4
5
5
6
6
Tip Resistance
Friction Sleeve
7
7
8
8
0
100
200
300
400
500
600
10
10
15
20
25
30
35
40
45
50
55
60
10
0
1
2
3
4
5
6
7
8
9
0
5
0
1
2
3
4
5
6
7
8
9
0
0
1
1
2
2
3
3
Depth (m)
Depth (m)
Depth (m)
4
4
5
5
6
6
Tip Resistance
Friction Sleeve
7
7
8
8
0
100
200
300
400
500
600
100
200
300
400
500
600
10
15
20
25
30
35
40
45
50
55
60
10
0
5
0
1
2
3
4
5
6
7
8
9
0
0
0
0
1
1
1
2
2
2
3
3
3
Depth (m)
Depth (m)
Depth (m)
4
4
5
5
5
6
6
6
7
7
7
8
8
8
&21(,' (&
&RQH&DSDFLW\
5HVXOWVRI&DOLEUDWLRQ7LSTF 5HVXOWVRI&DOLEUDWLRQ)ULFWLRQ6OHHYHIV
$SSOLHG 0HDQ 0HDQ $FFXUDF\ 5HSHDWDELOLW\ $SSOLFDWLRQ $SSOLHG 0HDQ 0HDQ $FFXUDF\ 5HSHDWDELOLW\ $SSOLFDWLRQ
)RUFH 2EVHUYHG &DOFXODWHG &ODVV )RUFH 2EVHUYHG &DOFXODWHG &ODVV
N1 5HDGLQJ 3UHVVXUH N1 5HDGLQJ 3UHVVXUH
9ROWV 03D 9ROWV N3D
9:
$8; / 9:
$8; /
Nicole London
&DOLEUDWLRQ&KHFNHG $XWKRULVHGBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB
-RE'HWDLOV
ATC Williams 09/07/2020
&OLHQW 'DWHRI-RE
35.79
/RFDWLRQ
Southern River 6OHHYH'LDPHWHU
APPENDIX B – BOREHOLE LOGS AND PHOTOGRAPHS
HAND AUGER NUMBER HA01
SHEET 1 OF 1
CLIENT BPA Engineering JOB NAME Providence Christian College Primary School
JOB NUMBER 120118.01 JOB LOCATION Southern River
Sample condition
Material Description: No. of blows for depth
indicated by bar thickness
Classification
Graphic Log
Soil: type, USCS symbol, strength, plasticity or particle size, colour, secondary
components, moisture condition
Sample
Symbol
Method
Water
Type
RL Depth
(m) (m)
0 4 8 12 16 20
SP TOPSOIL
Loose, fine and medium, brown sand with roots, moist
SP FILL
Medium dense becoming dense, fine and medium, yellow brown sand, moist
SP SAND
Dense, fine and medium pale grey, moist
26.0 0.5
Not encountered
25.5 1.0
25.0 1.5
24.5 2.0
24.0 2.5
23.5 3.0
PHOTO 1 – HA01
CLIENT BPA Engineering JOB NAME Providence Christian College Primary School
JOB NUMBER 120118.01 JOB LOCATION Southern River
Sample condition
Material Description: No. of blows for depth
indicated by bar thickness
Classification
Graphic Log
Soil: type, USCS symbol, strength, plasticity or particle size, colour, secondary
components, moisture condition
Sample
Symbol
Method
Water
Type
RL Depth
(m) (m)
0 4 8 12 16 20
SP TOPSOIL
Loose, fine and medium, light brown sand with roots, moist
27.0
SP FILL
Dense, fine and medium, yellow sand, moist
0.5
26.5
Not encountered
SP SAND
Dense, fine and medium pale grey, moist
1.0
26.0
1.5
25.5
2.0
25.0
2.5
24.5
3.0
PHOTO 3 – HA02
CLIENT BPA Engineering JOB NAME Providence Christian College Primary School
JOB NUMBER 120118.01 JOB LOCATION Southern River
Sample condition
Material Description: No. of blows for depth
indicated by bar thickness
Classification
Graphic Log
Soil: type, USCS symbol, strength, plasticity or particle size, colour, secondary
components, moisture condition
Sample
Symbol
Method
Water
Type
RL Depth
(m) (m)
0 4 8 12 16 20
SP TOPSOIL
Loose, fine and medium, brown sand with roots, moist
SP SAND
Dense, fine and medium pale grey, moist
Not encountered
26.5 0.5
BK 2
26.0 1.0
25.5 1.5
2020 TEST PIT FIELD LOGS REVA.GPJ GINT AUSTRALIA.GDT 18/7/20
25.0 2.0
24.5 2.5
24.0 3.0
PHOTO 5 – HA03
CLIENT BPA Engineering JOB NAME Providence Christian College Primary School
JOB NUMBER 120118.01 JOB LOCATION Southern River
Sample condition
Material Description: No. of blows for depth
indicated by bar thickness
Classification
Graphic Log
Soil: type, USCS symbol, strength, plasticity or particle size, colour, secondary
components, moisture condition
Sample
Symbol
Method
Water
OMC
MDD
Type
RL Depth
(m) (m)
0 4 8 12 16 20
SP TOPSOIL
Loose, fine and medium, brown sand with roots, moist
SP FILL
Not encountered
26.5 0.5
BK 1.72 13.5
26.0 1.0
25.5 1.5
2020 TEST PIT FIELD LOGS REVA.GPJ GINT AUSTRALIA.GDT 18/7/20
25.0 2.0
24.5 2.5
24.0 3.0
PHOTO 7 – STP01
CLIENT BPA Engineering JOB NAME Providence Christian College Primary School
JOB NUMBER 120118.01 JOB LOCATION Southern River
Sample condition
Material Description: No. of blows for depth
indicated by bar thickness
Classification
Graphic Log
Soil: type, USCS symbol, strength, plasticity or particle size, colour, secondary
components, moisture condition
Sample
Symbol
Method
Water
Type
RL Depth
(m) (m)
0 4 8 12 16 20
SP TOPSOIL
Loose, fine and medium, brown sand with roots, moist
SP FILL
Dense, fine and medium, yellow brown sand, moist
Not encountered
27.0 0.5
26.5 1.0
26.0 1.5
2020 TEST PIT FIELD LOGS REVA.GPJ GINT AUSTRALIA.GDT 18/7/20
25.5 2.0
25.0 2.5
24.5 3.0
PHOTO 10 – STP02
75.0
70
37.5
19.0 60
9.5 50
Passing (%)
4.75 100
40
2.36 100
1.18 100 30
0.600 84
20
0.425 46
10
0.300 18
0.150 6 0
0.0 0.1 1.0 10.0 100.0 1000.0
0.075 2 Particle Size (mm)
Comments:
Approved Signatory:
1.750
1.700
1% Air voids
2% Air voids
1.650
3% Air voids
1.600
7.00 8.00 9.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00
Moisture Content (%)
Approved Signatory:
Cody O'Neill Accreditation No. 20599
Name: Cody O'Neill Accredited for compliance
Function: Senior Technician with ISO/IEC 17025 - Testing
1.0
Surcharges Applied (kg) 4.50 Measured Swell (%) 0.0
Dry Density (t/mᶟ) 1.68 Dry Density Ratio (%) 97.5
Moisture Content (%) 16.7 Moisture Ratio (%) 125.0
Approved Signatory:
Accreditation No. 20599
Brooke Elliott
Name: Brooke Elliott Accredited for compliance
Client Details
Client Western Geotechnical & Laboratory Services
Attention Matt Van Herk
Address 235 Bank Street, Welshpool, WA, 6101
Sample Details
Your Reference BPA Engineering/ Providence CC/ S1433
Number of Samples 1 Soil
Date samples received 13/07/2020
Date completed instructions received 13/07/2020
Analysis Details
Please refer to the following pages for results, methodology summary and quality control data.
Samples were analysed as received from the client. Results relate specifically to the samples as received.
Results are reported on a dry weight basis for solids and on an as received basis for other matrices.
Report Details
Date results requested by 17/07/2020
Date of Issue 16/07/2020
NATA Accreditation Number 2901. This document shall not be reproduced except in full.
Accredited for compliance with ISO/IEC 17025 - Testing. Tests not covered by NATA are denoted with *
pH pH Units 6.8
Sulphate % <0.001
Result Definitions
NT Not tested
NA Test not required
INS Insufficient sample for this test
PQL Practical Quantitation Limit
< Less than
> Greater than
RPD Relative Percent Difference
LCS Laboratory Control Sample
NS Not specified
NEPM National Environmental Protection Measure
NR Not Reported
Surrogates are known additions to each sample, blank, matrix spike and LCS in a batch, of compounds which
Surrogate Spike
are similar to the analyte of interest, however are not expected to be found in real samples.
Australian Drinking Water Guidelines recommend that Thermotolerant Coliform, Faecal Enterococci, & E.Coli levels are less than
1cfu/100mL. The recommended maximums are taken from "Australian Drinking Water Guidelines", published by NHMRC & ARMC
2011.
The recommended maximums for analytes in urine are taken from “2018 TLVs and BEIs”, as published by ACGIH (where available).
Limit provided for Nickel is a precautionary guideline as per Position Paper prepared by AIOH Exposure Standards Committee,
2016.
Guideline limits for Rinse Water Quality reported as per analytical requirements and specifications of AS 4187, Amdt 2 2019, Table
7.2
For VOCs in water samples, three vials are required for duplicate or spike analysis.
Duplicates: >10xPQL - RPD acceptance criteria will vary depending on the analytes and the analytical techniques but is typically in
the range 20%-50% – see ELN-P05 QA/QC tables for details; <10xPQL - RPD are higher as the results approach PQL and the
estimated measurement uncertainty will statistically increase.
Matrix Spikes, LCS and Surrogate recoveries: Generally 70-130% for inorganics/metals (not SPOCAS); 60-140% for
organics/SPOCAS (+/-50% surrogates) and 10-140% for labile SVOCs (including labile surrogates), ultra trace organics and
speciated phenols is acceptable.
In circumstances where no duplicate and/or sample spike has been reported at 1 in 10 and/or 1 in 20 samples respectively, the
sample volume submitted was insufficient in order to satisfy laboratory QA/QC protocols.
When samples are received where certain analytes are outside of recommended technical holding times (THTs), the analysis has
proceeded. Where analytes are on the verge of breaching THTs, every effort will be made to analyse within the THT or as soon as
practicable.
Where sampling dates are not provided, Envirolab are not in a position to comment on the validity of the analysis where
recommended technical holding times may have been breached.
Measurement Uncertainty estimates are available for most tests upon request.
Samples for Microbiological analysis (not Amoeba forms) received outside of the 2-8°C temperature range do not meet the ideal
cooling conditions as stated in AS2031-2012.
STRICTLY CONFIDENTIAL
Please read the following carefully, and tick (ü) one of the boxes below:
OR
I certify the accuracy of the above information. I am aware that I may be required to consent to a criminal
record clearance, through the Department of Education’s Screening Unit, if it is considered necessary to
verify the information I have provided.
Name:
Company: (if relevant)
Address:
Telephone:
Email:
School visiting:
Purpose of visit:
Signature: Date:
In 1997, the then Education Department of Western Australia joined other Australian states to
implement the National Strategy in Schools for the Prevention of Paedophilia and Other
Forms of Child Abuse. The Confidential Declaration form is designed to prevent people from
entering schools who may pose a potential risk to children based on previous criminal history. It
does not replace the Working With Children check for employees.
The Confidential Declaration form is for persons who are not Providence Christian College
employees, and are not involved in child-related work, but who do require access to a school (for
example, tradespeople carrying out repairs or entertainers who do not work directly with children).
By completing this form, you will help the College ensure that schools are safe places for our
children.
Confidentiality:
Please be assured that unless statutory obligations require otherwise, the information on the
completed form will not be used without your consent for any purpose other than in relation to your
entry onto the school premises.
The completed form will be treated with the utmost confidentially at all times. Thank you for taking
the time to read this information.