Professional Documents
Culture Documents
Review Paper
Potential for Increased Rural Electrification Rate in Sub-Saharan Africa
using SWER Power Distribution Networks
Michael E. Irechukwu and Aviti T. Mushi
ABSTRACT
Rural electrification rate (RER) in Africa is still low to date. Several countries in
Sub-Saharan Africa have tried to address this problem using conventional single-
phase two-wire or three-phase three-wire systems, however at large costs due to the
nature of dispersed rural load centres, low load demand, and low population
density. Another solution of off-grid generation creates associated health problems.
Therefore, this paper undertakes a review of a single wire earth return (SWER)
network as a RER improvement solution. The paper undertakes intensive literature
review to elucidate challenges and solutions to the implementation of SWER
technology. Advantages of SWER technology discussed make it the choice for RER
improvement in Sub-Saharan African countries. After that, a case study is selected in
rural Tanzania, and a preliminary SWER network design is undertaken.
Keywords: Single wire earth return (SWER), power distribution networks, rural
electrification rate (RER).
140
generation of electricity using available aspect of SWER technology in Africa.
fossil fuels to effectuate RER This lack of literature causes lack of
improvement, as a solution. However, comprehensive understanding of the
local generators that produce electricity benefits and/or drawbacks of SWER
thermally have been shown to cause health technology for Africa, especially the rural
problems – diseases of several kinds, in Sri applications. For example, a proposed
Lanka (SLEMA, 2020). This is due to the SWER design in Botswana showed drastic
fumes, emissions, etc. that are produced as cost reduction of about 17.83% the cost of
by-products of the electricity generation 33 kV TPTW (Anderson, 2002).
process. Other places of Africa have Therefore, this paper is an attempt to
proposed RER improvement through solar address this literature and knowledge gap
minigrids such as those found in Kenya, by providing a systemic analysis of
and Uganda (Bahaj et al., 2020). This available literature and document all
improved RER act as a bringer of benefits and drawbacks that have been or
economic improvements to the can be accrued by the African countries by
populations, since technological utilizing SWER technology.
developments happen with reliable power
(Ferguson et al., 2000). 2. CHALLENGES LIMITING
WORLDWIDE APPLICATIONS OF
However, there is a technology that uses SWER
single wire that can effectively supply
scattered rural populations at a supposedly This section presents challenges that
cost-effective method. This technology is plague and as a result limit pervasive
called single wire earth return (SWER) applicability of SWER technologies
distribution system. The technology calls globally and especially Sub-Sahara Africa.
for stringent voltage and current limits These challenges include, but not limited
observance so that the dangers arising to, high benefit-cost-ratio; low load
from touch and step potential are capacity; high reactive losses (Momoh et
alleviated. It was developed and first al., 2019); more than average energy
implemented in New Zealand around 1925 losses of the conventional technologies;
(Mandeno, 1947), then it spread to and voltage regulation.
Australia (Nobbs, 2012). Further, it has
been implemented in Sri Lanka 2.1 High Benefit-Cost-Ratio
(Mahanthege, 2015), Brazil (Luciano et
al., 2012), Namibia (Himmel and Huysen, Rural electrification rate can be measured
2002), South Africa (Kessides et al., using a metric called benefit-cost-ratio
2007), Tunisia (Cecelski et al., 2005), ( ). The ratio should be to
Ghana (Iliceto et al., 1989) and Uganda deliver net value to the utility’s project.
(Bakkabulindi et al., 2012; Bakkabulindi Others denote it as BCR (Karki, 2004),
et al., 2009; Da Silva et al., 2001). while others call it benefit cost analysis
Realizing the potential of SWER, some factor (Parmar, 2016; Sidhu et al., 2018).
researchers suggested it as a feasible The RER in Sub-Saharan Africa has
electrification for a settlement in Rwanda slightly increased from 5% in 2002
(Solange, 2017); Tanzania (Irechukwu, (Davidson and Mwakasonda, 2004) to
2020; Irechukwu and Mushi, 2021; Meijer, 22% in 2017 (IEA, IRENA, UNSD, WB,
1995); a minigrid extension in Uganda WHO, 2019) due to the costly nature of
(Bakkabulindi, 2012); and a future rural distribution system installation faced by
electrification plan for Nigeria (FMPWH, the utilities. On utilities side, this high
2016). These are very few literatures that is undesirable. On the other hand, rich
elucidate the technical and economic countries such as US has achieved wider
141
access to electricity in the scattered rural in rural areas because of low consumption
communities by subsidizing companies or (Karki, 2004; Maunsell Limited, 2006;
utilities which install electricity Rudnick et al., 2014). Despite these
distribution infrastructures (Yuan, 2015), challenges, Cuba has achieved 28.8%
and as such it has provided low-cost for its SWER implementation compared if
technologies for rural electrification, one they used the conventional TPTW
being the SWER. This has been achieved, (Monteagudo, 2014).
for these projects, by realizing low
defined as follows (NER, 2001). 2.2 Voltage Regulation and
Transmission Loss Issues
………. (1)
Second challenge that faces applicability
of SWER system is voltage regulation
Benefit-cost-ratio in (1) incorporates the (VR) and transmission losses. This system
following variables: the present value for can efficiently supply loads connected
electricity sales denoted as , the within 25 km from the distribution
amount of electricity in kWh sold in a year transformers (Louie et al., 2015), thus it
denoted as , the value of electricity in can be modelled as a short transmission
kWh denoted as , the discounted value line. Consider Figure 1 showing a model
of investment stream denoted as , the of this short transmission line of length
discounted value of operations and 80 km. The variables are: sending end
maintenance costs each year denoted as voltage denoted by , sending end current
, the present value of losses denoted denoted by , resistance and reactance
as , the long range marginal cost for expressed as and both measured in
distribution denoted as , the kWh /m. Therefore, for line of length forms
losses in a year denoted as . However, line impedance , receiving end
this is easy to plan for but harder to current and voltage denoted by and
implement because other factors challenge respectively.
cheap SWER technology implementation
142
………..….. (3) distribution network losses from 16% in
1926 to 7%, globally (ETSAP, 2014).
143
Table 1: Soil Resistivity (Source: Samra, 1972)
Ground type Organic wet soil Moist soil Dry soil Bedrock Unit
Resistivity ( 10 100 1,000 10,000
Using the KVL, the Carson’s line medium earth resistivity ( ), because this
equations are obtained as equation (5), allows cheap cost of grounding the
which is a modification of equation (2) earthing electrodes and protection of
because of the ground return effect. Where equipment (Iliceto et al., 1989). Therefore,
the potential drops , , , and are it is of utmost importance to prevent dry
all measured with respect to same out soil by fast evaporation near the
reference ( ). electrodes, as this will cause an
uncontrolled increase in resistance and
cause thermal instability, which is checked
…….. (5) by employing Ollendorff formula (Iliceto
et al., 1989).
Further manipulation of equation (5) yields
the potential as the function of line self- ……………………. (8)
impedance, ground correction factors and
the line current, see equation (6). The Where is potential of electrode above
ground correction factor is approximated that of earth; is heat conductivity of the
by ground self and mutual impedances soil; and is the temperature rise of the
as in equation (7). Further electrodes and contiguous soil above the
computations pertaining to equation (7) are ambient. Soil resistivity is affected by ,
outlined by Ciric et al. (2004). moisture, and percentage of salts in the
soil. Practically, for 50 Hz currents, the
... (6) earth path that allows the current to flow is
limited by the skin depth ( ).
……………. (7) Conservatively, the current density should
not exceed 200 A/m2, in the vicinity of the
grounded electrode for more than one
2.4 Ground Resistance
second (Meijer, 1995). The efficient
grounding was experimentally shown to
Design challenge faced in the installation
result to maximum and efficient power
of SWER system is ensuring that the earth
transfer (Neste et al., 2016), albeit that was
resistance ( ) at the isolation and
a wireless system.
distribution transformer is within
acceptable limits (Nebi et al., 2017;
2.5 Limited Power Handling Capability
Solange, 2017). The isolation transformer
is very important because it is often used Power is supposed to flow with minimal
to prevent the SWER ground currents from losses in a SWER network, as was
causing earth current faults on the main previously shown by equation (4). Using
medium voltage (MV) network. There Figure 2 and taking node to enclose point
have been cases of burning of earthing and node to enclose point then the
electrodes and wooden poles due to poor power flow can be computed by Equations
earthing (Catriz et al., 2019; Nobbs, 2012), (9) – (11) observing the power mismatch
and this is expensive as this hardware has criteria equations (12) – (13). The
to be replaced after every burning. To variables are explained as following: -
avoid such dangers and costs, the
and are current injections at node ;
installation site must possess low or
144
and are the scheduled power improve voltage profile, power factor, and
injection at node ; is the admittance of voltage stability of the network.
all shunt elements at node ; is the
admittance of all ground mutual shunt 2.6 Improving Voltage Profile
elements; and are phase voltage
Voltage profile of a SWER line can be
and ground voltage at node ; and
improved using single phase voltage
are current flowing on a section of the regulators. However, these may not
SWER line; is the set of line function so well if a large increase on load
sections connected downstream to node ; demand on SWER line happens with
and and are power mismatches accompanied voltage distortions or VR
at node . (Hosseinzadeh et al., 2011). In this case an
upgrading of a SWER system to handle
..(9) this VR problem is proposed using either
switched reactors, saturable reactors
(Mayer et al., 2006) or DSTATCOMS.
However, this comes at a high cost to the
………. (10) installation (Mirazimiabarghouei, 2017).
The DSTATCOMS works better whenever
they are installed on the customer side to
…... (11) provide the needed voltage support, rather
than upstream in the network. The
.... (12) DSTATCOMS can cause peak value of
line voltage limit at the customer terminal
by injecting active ( ) and reactive ( )
……………..…… (13)
power at constant apparent power ( ). This
action ensures stable operation of the line.
Single wire earth return networks can
reach their power and voltage design Other studies (Kashem and Ledwich,
capacity due to unprecedented electrical 2004; Kashem and Ledwich, 2002)
demand brought about by proliferation of proposed installation of distributed
end user loads. When this happens, generators (DG) in the SWER network to
switched capacitors can be employed to aid in improving voltage profiles, reduce
provide voltage support (Shammah et al., the system losses as well as costs
2013). This solution was also deployed by (Hosseinzadeh and Rattray, 2008; Vo et
Ergon Energy (Lowry et al., 2012). Ergon al., 2013). These DGs control system is set
implemented it in the Queensland’s 64,000 to respond very fast to system changes,
km of SWER networks and its efficacy thus performs power factor correction and
was verified experimentally. In addition, correct any VR while at the same time
they alleviate or reduce charging helping to reduce power losses in the
capacitance current associated with SWER system. System reliability is
Ferranti effect on long SWER lines. improved as well. The reliability
Distribution static compensators improvement is due to the SWER design
(DSTATCOM) discussed by being able to carry less reactive and active
Mirazimiabarghouei (2017) and losses in the system compared to the
Mirazimiabarghouei et al. (2016) are conventional technologies (Bank, 2018).
installed to regulate the flow of reactive
power by injecting or absorbing it from the
distribution networks, when the need be, to
145
3. THE DESIGN OF SWER Duplication of the ground points assures
DISTRIBUTION SYSTEM that the system is still safe if either of the
grounds is damaged. In fact, the duplicated
Single wire earth return (SWER) system is ground in SWER leads to zeroing (Bank,
composed of the following components 2012) because the resistance on the ground
(Brooking et al., 1992): (1) isolation between them is much greater than the
transformer with rated voltage 11 kV/ 6.35 resistance of the wire.
kV and power rating 25 – 300 kVA; (2)
distribution primary 6.35 kV and two 3.2 Cost Structure of SWER Network
secondary low voltages of 230 V or 240 V; Comparing with Conventional
(3) aluminium steel clad steel reinforced Technologies
(ACSR) conductor; (4) earthing system
which also is the return path; (5) support The SWER network attracts capital costs
poles – either stainless steel or wooden; at around 55.5% of an equivalent SPTW
and (6) the transformer secondary is network (EU Energy Initiative, 2015). In
protected by a standard high-rupture addition, SWER cost is about 40% of a
capacity (HRC) fuse or low voltage TPTW network costs. One might ask, how
circuit breaker. Figure 3 shows the does the cost saving occur? The answer is
complete SWER distribution system from the massive reduction in the hardware to
the grid to the customer supply side. be used in SWER erection as compared to
those conventional methods.
3.1 Safety Feature of SWER Line Pragmatically, it can be looked at as
follows: TPTW requires seven (07) poles
The SWER line does not use the common per km with spans of 100 to 150 m; while
electrical safety feature – since it lacks a SWER requires spans of about 400 m thus
traditional metallic return to a neutral reducing the poles per km to 2.5 poles
shared by the generator. Instead, the safety (The World Bank, 2006).
is assured from its design of isolation
transformers. These isolate the ground On its entirety, SWER distribution system
from both the generator and user. is a very simple structure to construct
However, still there is possibility of stray because it only requires one live wire and
voltages injuring people and livestock in the earth as return conductor. However,
the vicinity of the line. Therefore, this is easier said than what the actual
grounding is critical to ensure that only 8 construction takes, since lack of technical
A is the limit of ground current flowing know-how limits its applicability in Sub-
(Grad, 2014). These earth grounds are Sahara region.
duplicated to assure increased safety.
146
Figure 3: Configuration of SWER distribution system –isolation transformer rated 11
kV/6.35 kV, distribution transformer rated 6.35 kV/240V, and customer side.
147
households connected annually at a cost of reduction of 40% of the cost per
US$ 384.6 per connection. Table 1 shows connection scenario comparing to before
this 260% connection increment at a SWER, which is thus an improved RER.
Table 1: Costs and connections before and after SWER adoption in Namibia (AEI, 2012;
Himmel and Huysen, 2002)
Table 2: Costs and connections before and after SWER adoption in South Africa (AEI, 2012;
Eskom, 1996; NER, 2001)
148
Table 3: Costs and connections before and after SWER adoption in Tunisia (Cecelski et al.,
2005; World Bank, 2006)
Table 4: Rural electrification levels in SADC Countries in year 2006 (Kapika and Oguah,
2018; Kimambo and Nielsen, 2012; SADC Statistical Yearbook, 2015)
149
This is suggested because of the activities appliances used in typical houses, and
involved – planning for the power flow, those that the villagers wanted to use, but
feeder and substation installation, and did not have at the moment (Figure 4). The
others. Therefore, this section selects a estimated peak load was about 139.7 kW.
model rural location in Tanzania and This data was used to design and size the
design the electrification scheme from the transformer shown by Table 5 followed by
grid, using SWER (Irechukwu, 2020; a SWER line design shown in Table 6 for
Irechukwu and Mushi, 2020; Irechukwu the 20 km length. This design is based on
and Mushi, 2021). This village is called consultations with Rural Energy Authority
Homboza, located in Pwani (Coast) (REA) engineers and the data they
Region of Tanzania at coordinates: - provided. Further, note that instead of
7.32380S and 38.82050E. It has a using single 200 kVA transformer, the
population of about 1,565 people, where design has chosen two transformers rated
the economic activities are small scale 100 kVA each (Table 6). Bakkabulindi et
agriculture. The reason to select this al. (2013) specified ACSR for Uganda
location is to impart benefits of SWER network, similarly this paper
electrification to the community, which chooses the same for Homboza. All these
were shown in another similar location in specifications and other materials are
Tanzania (Ngowi et al., 2019), India displayed in Table 6. The grounding is
(Jamasb et al., 2015), and Zimbabwe proposed using readily available materials
(Davidson and Mwakasonda, 2004). such as animal dung and wood coal to
Further, grid connection feasibility fasten the attainment of results and
depends on community size and the minimizing cost, similar to what Adesina
distance from the closest grid point and Akinbulire (2020) proposed in
(Juanpera et al., 2020; Karhammar, 2006), Nigeria. Earth resistance tests are planned
and for the case study of this paper, the to be carried out annually on all the
community size is sparse populated, about transformers using earth resistance tester
20 km from the grid, and rural location. Da (Agugharam et al., 2020), so that if any
Silva et al. (2001) showed a cost saving of problems are present, they can be arrested
29% for a RE in Uganda, if SWER is used before they can cause damage.
to connect about 200,000 inhabitants of
rural remote areas. It should be noted that 6.2 Possible Future Expansion due to
Uganda and Tanzania are geographical Increased Demand
neighbours, so a solution working in one
can be applied with little adaptation to The 20 km long SWER line designed for
another, case in point the Ntenjeru village the Homboza village can be expanded to
(Bakkabulindi et al., 2009). This is increase its capacity (Wolfs, 2005) or
interesting, because few years back in the convert to TPTW system, if and when the
1990s, Meijer (1995) had already proposed load demand warrants it. These loads can
electrifying Tanzania rural areas using be pump applications which work
SWER technology. Current task here is efficiently on three-phase power. The
cementing that work started those times conversion can be achieved by a converter
back and working out a possible technology developed by an engineer
implementation, starting with load demand named Charles F. Scot in the late 1890s.
estimation. The technology bears his name – Scot
Transformer (Wolfs, 2013). Technical
6.1 Load Demand of Homboza details about how to design the Scot
Transformer are covered in detail by Wolfs
Field data were collected for 24-hour (2013). The second option to choose from
electrical power usage by fittings and for the case of increased load growth is to
150
upgrade the network to medium voltage It further suppresses grid voltage
SWER network using the customer data harmonics and eliminate (or compensate)
(Hosseinzadeh and Mastakov, 2008). This for other disturbances such as voltage sags.
method will provide real time solution to
the actual load growth observed giving To make the SWER network robust,
accurate required capacity upgrades. The reliable, and make it long living it is
third capacity enhancement technique is to possible to monitor it using power line
employ controllable reactors which can communications (PLC). One technology –
increase the capacity to about 85% as was narrow band communication channels was
the case for the North Jericho SWER line suggested and tested by several researchers
(Wolfs, 2005; Wolfs et al., 2007) and (Nkom, 2017; Nkom et al., 2018). Another
Central Queensland line (Hesamzadeh et is pole mounted monitoring units installed
al., 2008). on the SWER feeder (Song et al., 2017).
This monitoring will enable regulation and
The 240–0– 240 V distribution transformer maintenance of this network using
may enable the connection of motors rated dynamic devices (Gay et al., 2009).
480 V at less than 12 kW power demand Further, some algorithms can be used to
(Bakkabulindi, 2012; Monteagudo, 2014). detect and protect SWER network against
These motors would still require the power faults, such as high impedance faults (Kavi
electronic starters to alleviate the big et al., 2016) so that the reliability is
voltage dip during the starting. In preserved. These must go hand in hand by
addition,there is a demonstrated proper estimation of the costs of
technology that uses three-phase-to-single- distribution systems installation, as
phase power quality conditioner, that can historically 60% of total power costs is
be used to supply nonlinear loads, and used up in the installation works
three-phase inductive or capacity loads (Baughman and Bottaro, 1975). The cost
(Da Silva and Negrao, 2018). This allocation must be properly handled so that
technology adopts a dual compensation the SWER connected customers are not
strategy, which works by drawing heavily charged; rather their life must be
sinusoidal current that is in phase with the improved by low-cost technology.
voltage thus producing high power factor.
160
140
Power in kW
120
100
80
60
40
20
0
151
Table 5: Distribution transformer size for electrifying Homboza village
Parameter Value
Peak total load for 171 households 139.707 kW
Power factor 0.91
Peak apparent power 153.524 kVA
Multiplying factor 1.3
Transformer rating 200 kVA
Table 6: Material and equipment to connect SWER from grid to Homboza village
152
Planning Algorithm for Single Wire Cecelski E., Ounalli A., Aisaa M.,
Earth Return Distribution Networks. Dunkerley J. (2005). Rural
2012 IEEE Power and Energy Society Electrification in Tunisia: National
General Meeting, 1–7. DOI: Commitment, Efficient Implementation
10.1109/PESGM.2012.6344816. and Sound Finances. Energy Sector
Bakkabulindi G., Hesamzadeh M.R., Management Assistance Programme
Amelin M. and Da Silva I.P. (2013). (ESM 307/05). Washington, DC.:
Models for Conductor Size Selection in World Bank. Available at
Single Wire Earth Return Distribution https://openknowledge.worldbank.org/h
Networks. IEEE Africon, 1–5. DOI: andle/10986/18065 License: CC BY 3.0
10.1109/AFRCON.2013.6757773. IGO.
Bank M. (2018). Electrical Energy Ciric R.M., Ochoa L.F. and Padilha A.
Transmission by Several Wires and (2004). Power Flow in Distribution
Reactive Power Problems. Engineering, Networks with Earth Return. Electrical
10: 329–335. Power and Energy Systems, 26: 373–
.http://www.scirp.org/journal/eng, ISSN 380. doi: 10.1016/j.ijepes.2003.11.006.
Online: 1947-394X, ISSN Print: 1947- Da Silva I.P., Mugisha P., Simonis P.,
3931. Turyahikayo G.R. (2001). The Use of
Bank M. (2012). Single Wire Electrical Single Wire Earth Return (SWER) as a
System. Engineering, 4: 713–722, Potential Solution to Reduce the Cost of
http://dx.doi.org/10.4236/eng.2012.411 Rural Electrification in Uganda.
092. Domestic Use of Energy Conference,
Baughman M.L. and Bottar, D.J. (1975). 78–79.
Electric Power Transmission and Da Silva S.A.O. and Negrao F.A. (2018).
Distribution Systems: Costs and Their Single-Phase to Three-Phase Unified
Allocation. IEEE Transactions on Power Quality Conditioner Applied in
Power Apparatus and Systems, PAS- Single Wire Earth Return Electric
95(3): 782–790. DOI: 10.1109/T- Power Distribution Grids. IEEE
PAS.1976.32161 Transactions on Power Electronics,
Brooking T.R., Van Rensburg J. and 33(5): 3950–3960. DOI:
Fourie R.J. (1992). The Improved 10.1109/TPEL.2017.2723573.
Utilisation of Existing Rural Networks Davidson O. and Mwakasonda S.A.
with the Use of Intermediate Voltage (2004). Electricity Access for the Poor:
and Single Wire Earth Return Systems. A Study of South Africa and
3rd AFRICON Conference, 228–234. Zimbabwe. Energy for Sustainable
DOI:10.1109/AFRCON.1992.624461 Development, 8(4): 26–44.
Carson J.R. (1926). Wave Propagation in DOI: 10.1016/S0973-0826(08)60511-6
Overhead Wires with Ground Return. Eberhard A., Gratwick K., Morella E. and
Bell System Technical Journal, 5: 539– Antmann P. (2016).Independent Power
554. Projects in Sub-Saharan Africa–Lessons
Catriz R., Ahfock T. and Worden J. from Five Key Countries. Directions in
(2019). An Investigation into Wooden Development. Washington, DC: World
Pole Fire Inception Threshold in a Bank. doi:10.1596/978-1-4648-0800-5.
Single Wire Earth Return System under Energy Technology Systems Analysis
Drought Conditions. 29th Australasian Programme (ETSAP). (2014).
Universities Power Engineering Electricity Transmission and
Conference (AUPEC), 1–6. Distribution. IEA ETSAP–Technology
DOI:10.1109/AUPEC48547.2019.2119 Brief E12, 1–16.
14. Eskom (1996). Annual Report. Sandton:
Eskom.
153
EU Energy Initiative. (2015). Low-Cost Hesamzadeh M.R., Hosseinzadeh N. and
Grid Electrification Technologies: A Wolfs P.J. (2008). Design and Study of
Handbook for Electrification a Switch Reactor for Central
Practitioners. Eschborn: EU Energy Queensland SWER System. 43rd
Initiative. International Universities Power
Federal Ministry of Power, Works and Engineering Conference, 1–5. DOI:
Housing (FMPWH) (2016). Rural 10.1109/UPEC.2008.4651481.
Electrification Strategy and Himmel R. and Huysen R. (2002).
Implementation Plan (RESIP). Federal Northern Electricity Distribution
Ministry of Power, Works and Service in Northern Namibia: A Case
Housing–Nigeria. Study in the Private Provision of Rural
Ferguson R., Wilkinson W. and Hill R. Infrastructure. California: EMCON
(2000). Electricity Use and Economic Consulting Group.
Development. Energy Policy, 28(13): Hosseinzadeh N. And Mastakov S. (2008).
923–934. DOI: 10.1016/S0301- Load Modeling for Medium Voltage
4215(00)00081-1 SWER Distribution Networks. 2008
Gay D., Thompson A., Amanulla M.T.O. Australian Universities Power
and Wolfs P. (2009). Monitoring of Engineering Conference (AUPEC’08),
Single Wire Earth Return Systems 1–5.
using Power Line Communication. Hosseinzadeh N., Mayer J.E. and Wolfs
2009 Australasian Universities Power P.J. (2011). Rural Single Wire Earth
Engineering Conference, 1–5. Return Distribution Networks–
Golumbeanu R. and Barnes D. (2013). Associated Problems and Cost-
Connection Charges and Electricity Effective Solutions. Electrical Power
Access in Sub-Saharan Africa. Policy and Energy Systems, 159–170. doi:
Research Working Paper No. 6511. 10.1016/j.ijepes.2010.08.009.
Washington, DC.: World Bank. Hosseinzadeh N. and Rattray J. (2008).
https://openknowledge.worldbank.org/h Economics of Upgrading SWER
andle/10986/15871 License: CC BY 3.0 Distribution Systems. 2008
IGO. Australasian Universities Power
Gonzalez-Eguino M. (2015). Energy Engineering Conference (AUPEC'08),
Poverty: An Overview. Renewable and 1–7.
Sustainable Energy Reviews, 47: 377– IEA, IRENA, UNSD, WB, WHO. (2019).
385.http://dx.doi.org/10.1016/j.rser.201 Tracking SDG 7. The Energy Progress
5.03.013. Report 2019, Washington DC.
Grad P. (2014). SWER Still Going Strong. Iliceto, F., Cinieri, E., Casely-Hayford, L.
https://www.esdnews.com.au/swer-still- and Dokyi, G. (1989). New concepts on
going-strong/ accessed on 25th July MV distribution from insulated shield
2019. wires of HV lines: Operation results of
Grainger J.J. and Stevenson W.D. (1994). an experimental system and
Power System Analysis. New York: applications in Ghana. IEEE
McGraw Hill. Transactions on Power Delivery, 4(4):
Guinane A., Shafiullah G.M., Oo A.M.T. 2130–2144. DOI: 10.1109/61.35640
and Harvey, B.E. (2012). Voltage Irechukwu M.E. (2020). Feasibility
Fluctuations in PV Penetration on Analysis of Using Single Wire Earth
SWER Networks–A Case Study for Return Medium Voltage Distribution
Regional Australia. 2012 IEEE Power Network for Homboza Village
and Energy Society General Meeting, Electrification. M.Sc. Dissertation.
1–6. DOI: University of Dar es Salaam, Tanzania.
10.1109/PESGM.2012.6344630.
154
Irechukwu M.E. and Mushi A.T. (2020). Kashem M.A. and Ledwich G. (2004).
Feasibility Analysis of Using SWER for Distributed Generation as Voltage
Homboza Village Electrification. 6th Support for Single Wire Earth Return
International Conference in Mechanical Systems. IEEE Transactions on Power
and Industrial Engineering (MIE2020), Delivery, 19(3): 1002–1011. DOI:
1–6. 10.1109/TPWRD.2003.822977.
Irechukwu M.E. and Mushi A.T. (2021). Kashem M.A. and Ledwich G. (2002).
Proposal for Single Wire Earth Return Impact of Distributed Generation on
Distribution System for Homboza Protection of Single Wire Earth Return
Village Electrification. International Lines. Electric Power Systems
Journal of Mechatronics, Electrical and Research, 62(1): 67–80.
Computer Technology (IJMEC), https://doi.org/10.1016/S0378-
11(39): 4837–4842. ISSN: 2305–0543 7796(02)00031-7
(Online), ISSN: 2411–6173 (Print). Kavi M., Mishra Y. and Vilathgamuwa
Jamasb T., Nepal R. and Timilsina G.R. D.M. (2016). Detection and
(2015). A Quarter Century Effort yet to Identification of High Impedance Faults
Come of Age: A Survey of Power in Single Wire Earth Return
Sector Reforms in Developing Distribution Networks. IEEE
Countries. Working Paper. Washington, Australasian Universities Power
D.C., World Bank Group. Engineering Conference–AUPEC2016,
https://openknowledge.worldbank.org/h 1–6. DOI:
andle/10986/22211. 10.1109/AUPEC.2016.7749341.
Juanpera M., Blechinger P., Ferrer-Marti Kersting W.H. (2005). The Modeling and
L., Hoffmann M.M. and Pastor R. Analysis of Parallel Distribution Lines.
(2020). Multicriteria-Based IEEE 2005 Rural Electric Power
Methodology for the Design of Rural Conference, 1–7. DOI:
Electrification Systems. A Case Study 10.1109/REPCON.2005.1436300.
in Nigeria. Renewable and Sustainable Kersting W.H. and Green R.K. (2011).
Energy Reviews, 133: 1–16. The Application of Carson’s Equation
https://doi.org/10.1016/j.rser.2020.1102 to the Steady-State Analysis of
43. Distribution Feeders. 2011 IEEE/PES
Kapika J.M. and Oguah S.K.E. (2018). Power Systems Conference and
Project Information Document (PID). Exposition, 1–6. DOI:
Network Reinforcement and Access 10.1109/PSCE.2011.5772579.
Project (P166170), The World Bank. Kessides I.N., Bogetic Z. and Maurer L.
Karhammar R., Sanghvi A., Fernstrom E., (2007). Current and Forthcoming Issues
Aissa M., Arthur J., Tulloch J., Davies in the South African Electricity Sector.
I., Bergman S. and Mathur S. (2006). World Bank Policy Research Working
Sub-Saharan Africa: Introducing Low- Paper 4197.
cost Methods in Electricity Distribution Khator S.K. and Leung L.C. (1997). Power
Networks. ESMAP Technical Paper Distribution Planning: A Review of
104/06. Models and Issues. IEEE Transactions
Karki N.R. (2004). Reducing the Cost of on Power Systems, 12(3): 1151–1159.
Rural Electrification: A Key to Improve DOI:10.1109/59.630455.
the Quality of Life in Rural Areas in Kimambo C.Z. and Nielsen T.K. (2012).
Developing Countries. 2004 Potential of Small-Scale Hydropower
International Conference on Power for Electricity Generation in Sub-
System Technology–POWERCON, Saharan Africa. ISRN Renewable
447–452. Energy, 2–3.
155
Louie H., O’Grady E., Van Acker V., Mirazimiabarghouei S.J. (2017).
Szablya S., Kumar N.P. and Podmore Distributed Static Compensator
R. (2015). Rural Off-grid Electricity (DSTATCOM) for Voltage Support in
Service in Sub-Saharan Africa. IEEE Single Wire Earth Return (SWER)
Electrification Magazine, 7–15. DOI: Networks. Doctoral Thesis, University
10.1109/MELE.2014.2380111. of Southern Queensland, Australia.
Lowry S.N., Oo A.M.T. and Robinson G. Mirazimiabarghouei S.J., Ahfock A. and
(2012). Deployment of Low Voltage Helwig A. (2016). Single Wire Earth
Switched Capacitors on Single Wire Return (SWER) System Voltage
Earth Return Networks. 22nd Support Using Four Quadrant
Australasian Universities Power DSTATCOM. 2016 IEEE International
Engineering Conference (AUPEC), 1– Conference on Power and Energy
5. (PECon), 228–233. DOI:
Luciano B.A., Inacio R.C. and Silva P.P. 10.1109/PECON.2016.7951564.
(2012). Performance of Single Wire Momoh I.O., Jibril Y., Jimoh B., Abubakar
Earth Return Transformers with A.S., Ajavi O., Abubakar A., Sulaiman
Amorphous Alloy Core in a Rural S.H. and Yusuf S.S. (2019). Effect of
Electric Energy Distribution System. an Optimal Conductor Size Selection
Materials Research, 15(5): 801–804. Scheme for Single Earth Wire Return
DOI: 10.1590/S1516- Power Distribution Networks for Rural
14392012005000045. Electrification. J. Science Technology
Mahanthege S.D. (2015). Technological and Education, 7(3): 286–295. ISSN:
and Cost-Effective Selection Procedure 2277-0011. www.atbuftejoste.com.
for Rural Electrification Systems. M.Sc. Accessed on 17th July 2020.
Dissertation. University of Moratuwa, Monteagudo R.M. (2014). Circuitos de
Sri Lanka. Distribución Monofásicos con Retorno
Mandeno L. (1947). Rural Power Supply por Tierra. Diploma Work,
Especially in Back Country Areas. New Departamento de Electroenergética,
Zealand Institution of Engineers, Facultad de Ingeniería Eléctrica. Santa
33(1947). New Zealand Institute of Clara: Universidad Central Marta
Engineers, Wellington, New Zealand. Abreu de Las Villas.
Maunsell Limited (2006). Review of National Electricity Regulator (NER)
Solomon Islands Electricity Act and (2001). Electricity Supply Statistics for
Rural Electrification Framework – Final South Africa. National Electricity
Report. Prepared for Pacific Islands Regulator of South Africa, Pretoria,
Energy Policy and Strategic Action South Africa.
Planning (PIEPSAP) and Solomon Nebi E., Yuksel H., Sagir D., Yilmaz I.,
Islands Department of Energy. Koc M., Cebeci M.E., Tor O.B. and
Mayer J., Hosseinzadeh N. and Wolfs P. Guven A.N. (2017). Feasibility of
(2006). Reactor Solutions for Voltage Distributing Electric Power through
Control of SWER Systems. in Kalam, Single-Phase Transformers at Rural
A. (ed), Australasian Universities Regions of Turkey based on Rural
Power Engineering Conference AUPEC Characteristic Indices. IEEE Power and
2006. Victoria University, Melbourne, Energy Conference at Illinois (PECI),
Australia. 1–6. DOI:10.1109/PECI.2017.7935728.
Meijer A.C. (1995). Suitability of Single Neste C.W., Hull R., Hawk J.E., Phani A.,
Wire Earth Return (SWER) Systems for Unsworth J. and Thundat T. (2016).
Rural Electrification in Tanzania. Electrical Excitaion of the Local Earth
Master Thesis, Eindhoven University of for Resonant, Wireless Energy
Technology (TUE), The Netherlands.
156
Transfer. Wireless Power Transfer, Future. Gaborone: SADC Statistical
3(2): 117–125. doi:10.1017/wpt.2016.8. Yearbook.
Ngowi J.M., Bangens L. and Ahlgren E.O. Samra B.S. (1972). An Analysis of Single
(2019). Benefits and Challenges to Wire Earth Return (SWER) System for
Productive Use of Off-Grid Rural Rural Electrification. Masters Thesis
Electrification: The Case of Mini- 506, Department of Electrical and
Hydropower in Bulongwa-Tanzania. Computer Engineering, University of
Energy for Sustainable Development, Missouri--Rolla, USA.
53: 97–103. https://scholarsmine.mst.edu/masters_th
https://doi.org/10.1016/j.esd.2019.10.00 eses/5062
1. Shammah A.A.E., Azmy A.M., Simonds
Nkom B. (2017). Modelling of P. and El-Ela A.A. (2013). Optimal
Transformer and Medium Voltage Sitting and Sizing of Capacitor Banks
Powerline Channels for Data in Distribution Networks using
Communication on Single Wire Earth Heuristic Algorithms. Journal of
Return Distribution Grids. Doctoral Electrical Systems, 9(1): 1–12.
Thesis, School of Engineering of the Sidhu A.S., Pollit M.G. and Anaya K.L.
Auckland University of Technology, (2018). A Social Cost Benefit Analysis
Australia. of Grid-Scale Electrical Energy Storage
Nkom B., Taylor A.P.R. and Baguley C. Projects: A Case Study. Applied
(2018). Narrowband Modeling of Energy, 212: 881–894.
Single-WireEarth Return Distribution https://doi.org/10.1016/j.apenergy.2017.
Lines. IEEE Transactions on Power 12.085
Delivery, 33(4): 1565–1575. DOI: Solange N.M. (2017). Design of a Single
10.1109/TPWRD.2017.2775189. Wire Earth Return (SWER) Power
Nobbs R.K. (2012). Development of Distribution System and Improvement
Advanced SWER Models for the Ergon of its Voltage Profile Using Capacitors.
Energy Network. Bachelor Dissertation, M.Sc. Dissertation. Pan African
University of Southern Queensland, University, Nairobi, Kenya.
Australia. Song R., Lu S., Sirojan T., Phung B.T. and
Parmar V. (2016). Benefit Cost Analysis Ambikairajah E. (2017). Power Quality
of Solar Power Over On-Grid Monitoring of Single-Wire-Earth-
Electricity for Residential Systems: Is Return Distribution Feeders. 2017
Photovoltaic Technology Really International Conference on High
Effective? Master Thesis, Texas A&M Voltage Engineering and Power
University, Australia. Systems (ICHVEPS), 404–409. DOI:
Rudnick H., Mutale J., Chattopadhyay D. 10.1109/ICHVEPS.2017.8225879.
and Saint R. (2014). Studies in Sri Lanka Energy Managers Association
Empowerment: Approaches to Rural (SLEMA). (2020). Study Report on
Electrification Worldwide. IEEE Power Estimation of External Cost of Thermal
and Energy Magazine, 35–41. DOI: Power Generation. Public Utilities
10.1109/MPE.2014.2317960. Commission of Sri Lanka, Final Draft
SADC (2010). SADC Regional Energy Report.
Access Strategy and Action Plan. Sumaya R.J., Nkom B. and Nair N.-K.C.
SADC Energy Programme, with (2019). Island Power Operation with
Support of European Union Energy Single-Wire Earth Return (SWER),
Initiative (EUEI). Solar PV and Diesel Generation–
SADC Statistical Yearbook (2015). Marinduque, Philippines Case Study.
Southern African Development 2019 29th Australasian Universities
Community: Towards a Common Power Engineering Conference
157
(AUPEC), 1–7. DOI: Wolfs P. (2013). A Scott Transformer
10.1109/AUPEC48547.2019.214527. based Single to Three Phase Power
The Africa Electrification Initiative (AEI) Converter for SWER Applications.
(2012). Institutional Approaches to 2013 Australasian Universities Power
Electrification: The Experience of Rural Engineering Conference (AUPEC), 1–
Energy Agencies/Rural Energy Funds 6. DOI:
in Sub-Saharan Africa. Dakar, Senegal. 10.1109/AUPEC.2013.6725381.
The World Bank (2014). Improving the Wolfs P.J. (2005). Capacity Improvements
Quality of Engineering Education and for Rural Single Wire Earth Return
Training in Africa. The World Bank Systems. 2005 International Power
Report No. 86062. Engineering Conference, 1–8. DOI:
The World Bank. (2006). Sub-Saharan 10.1109/IPEC.2005.206925.
Africa: Introducing Low-Cost Methods Wolfs P.J., Hosseinzadeh N. and Senini
in Electricity Distribution Networks. S.T. (2007). Capacity Enhancement for
Washington D.C.: World Bank. Aging Distribution Systems Using
United Nations Educational, Scientific and Single Wire Earth Return. 2007 IEEE
Cultural Organization (UNESCO) Power Engineering Society General
(2010). Engineering: Issues Challenges Meeting, 1–8. DOI:
and Opportunities for Development. 10.1109/PES.2007.385451.
UNESCO Report, Paris: UNESCO. Yuan G. (2015). Rural Electrification Goes
Vo T.H., Ravishankar J. and Fletcher J.E. Local–Recent Innovations in
(2013). Assessment of Distributed Renewable Generation, Energy
Generation on the Efficiency of Single Efficiency, and Grid Modernization.
Wire Earth Return Systems. Advanced IEEE Electrification Magazine, 16–24.
Materials Research. 622–623: 1887– DOI: 10.1109/MELE.2014.2380193.
1891. doi: Zoomers A. (2014). Context, Challenges,
10.4028/www.scientific.net/AMR.622- and Obstacles in Rural Electrification.
623.1887. IEEE Power and Energy Magazine, 26–
34. DOI: 10.1109/MPE.2014.2315916.
158