Professional Documents
Culture Documents
We, the staff of Innovare Consulting, express our sincerest appreciation to our Client, the
Department of Planning, Transport and Infrastructure (DPTI) for picking Innovare Consulting to
lead the Design stage for Sir Donald Bradman Drive Intersection.
We personally express our gratitude to Mr Desmond Khoo as a client representative and for his
technical advice. We thank you for providing us with all the required documents and data for this
Design stage.
We would like to express our gratitude to Mr Mark Ellis for his advice and guidance throughout
this Design stage.
1
Executive Summary
Innovare Consulting has undertaken the Design stage to provide non-stop traffic flow at Sir Donald
Bradman Drive intersection. During the feasibility stage our company proposed four options and
now the design stage is mainly focused on the Overpass design for the intersection. The grade
separation at intersection was planned and analyzed in terms of capacity to accommodate present
and future traffic volumes, maintain level of access and increased bus priority and maintain traffic
flow during construction. Geotechnical department analyzed the soil conditions, based on the
reports suitable pile foundation with pile cap is designed and the cross section of pavement for
both the overpass and ramp also made out. Structural components like pier, deck, headstock and
girder was designed based on the ultimate loads using the software Space Gass. Current land utilize
was analyzed and remuneration bundles were approximated to decide the ideal side for road
widening. Drainage system was recommended based on the annual rain fall for overpass and
surface roads. From this Design Stage, Innovare Consulting made a design to achieve a nonstop
motorway at the Sir Donald Bradman Drive intersection by an Overpass. This Overpass is designed
based on site conditions from geotechnical, urban and transportation perspectives. The solution is
arrangement with the 30-Year Plan for Greater Adelaide to give financial, land utilization and
development in infrastructure in Adelaide. We suggest street enlarging on the Eastern arrangement
of South Road, because of distinguished negligible effect on current land utilize and some
notorious structures.
2
Table of Contents
3
5.1 Introduction 71
5.2 Purpose of Environment Management Plan 72
5.3 Existing Environment 72
5.4 Temperature 75
5.5 Rainfall 76
5.6 Environmental Considerations 77
5.7 Noise and Vibration 78
5.8 Air Quality, Emission and Dust Generation 80
5.9 Waste Management and Soil Contamination 82
5.10 Land Disturbances and Erosion 83
5.11 Water quality and Sedimentation 84
5.12 Native Vegetation Removal 85
5.13 Effect of Fauna 87
5.14 Community Management Plan 88
6 Water Engineering 90
6.1 Road Drainage design 91
6.2 Water Sensitive Urban Design 91
6.3 Drainage System Layout 92
6.4 Summary of Design 96
7 References 107
Appendix A1 - Grade and length of the Overpass 108
Appendix A2 - Intersection Summary 110
Appendix B1 – Design of Headstock 115
Appendix B2 – Design of Deck 120
Appendix B3 – Design of Pier using Space Gass 124
Appendix C1 – Pavement Design 131
Appendix C2 – Design of Retaining Wall and Reinforcement 138
Appendix C3 – Design of Pile foundation and pile cap 146
Appendix D Road Drainage Design 156
4
List of Figures
5
4.6 Existing layout of wastewater line 64
4.7 Existing layout of telecommunication cables 65
5.1 The study area 73
5.2 Aerial view 74
5.3 rainfall data of the year 2015 75
6.1 Conceptual diagram of storm water conveyance (Northern side) 94
6.2 Conceptual diagram of storm water conveyance (Southern side) 95
6.3 Cross-section of storm water pipes 104
6
List of Tables
7
1 TRANSPORT ENGINEERING
8
1.1 Overview
This design report section will focus on the transport aspect of the project. Following section will
discuss geometry aspect of the overpass and the surface roads, gradient, length and cross fall. All
geometrical aspects are designed in accordance with DPTI standards.
SIDRA modeling has been done to design traffic signal phases for the new intersection under the
overpass and to analyze intersection performance for detour of vehicle during construction
Final part of the section will about the signage to be adopted along the length of the overpass and
surface road for detour and after construction.
Surface roads
Table 0.1: Surface road components
Surface Road
Components No Width
Footpath - 1.2 m
Lanes 4 3.5 m
Lanes 2 3.3 m
Table 1.1 shows the components adopted for the surface roads. All these widths are adopted based
on DPTI and Austroads Standards for road design. The lane widths of 3.5m and 3.3 m are provided
based on speed of the road.
9
Motorway
Table 0.2: Components of the motorway on overpass
Motorways
Components No Width
Lanes 2 3.3 m
Lanes 4 3.5 m
Median 1 0.8 m
Table 1.2 shows the components of the motorway on the overpass, all these width are adopted
based on DPTI and Austroads Standards for road design. The barrier DPTI SAM 2 is discussed in
the section 1.2.5 of this report
This adopted grade of road decreases the overall length of the overpass which in turn decreases the
overall cost of the overpass.
The road gradient of 5.1 percent is also selected based on freight movement along the motorway.
Modern day trucks are powerful enough to traverse this gradient. This is further based on Austroads
Guide to Road Design Part 3: Geometric Design, table 8.3; which further proves that for a grade
10
between 3 percent and 6 percent, the reduction in speed for heavy vehicles travelling uphill is less.
With the smaller length of the uphill part of the overpass and powerful engine of modern trucks,
the reduction in speed will be easily compensated and recovered. Table 1.2 is the summarized table
of Austroads Guide to Road Design Part 3: Geometric Design, table 8.3 effects of grade on vehicle
type.
Based on the gradient, the length of the overpass is fixed to be 370.1m. This length comprises of
two sloped roads of length 172.55m and flat bridge of 25 m over the intersection. As stated earlier
the length of sloped portion of the overpass is small enough to have effect on freight trucks and the
overall length of 370.1m decreases the cost.
Cross fall
We have adopted 2.5% cross fall for both surface roads as well as the motorway. Water seeping
into bitumen or asphalt is one of the causes that degrade roads surface. Water if allowed to pond
surface can cause formation of potholes which will eventually lead to extensive repair and
maintenance requirement. Water collecting on road surface can cause high speed vehicle to skid,
thus leading to accidents. Austroads Guide to Road Design Part 3: Geometric Design specifies to
adopt a cross fall ranging from 2.5 percent to 3 percent. The adopted cross fall of 2.5% is sure
prevent water from forming ponds and is sufficient to drain the water to drains designed along the
parallel roads and motorway.
Crash Barrier
The crash barrier to be used on the bridge must provide containment of heavy vehicles. After the
construction, the traffic environment is of high volume of mixed heavy vehicles and a posted speed
of 80km/h. With these conditions set; based on Austroads Standardized Bridge Barrier Design the
barrier performance level was selected to be medium with a NCHRP test level of TL-5. Based on
this performance level we choose to provide SAM 2 SA DPTI Barrier. SAM 2 is a single slope
combination barrier with a height of 1400 mm. The use of a predesigned barrier enables
procurement and construction of barrier easy. It also eliminates the need for safety and performance
11
test on the barrier as the design is already approved by the relevant authorities. Figure 1.1 shows
the chosen barrier.
12
Figure 0.2: Seven phases used for new intersection
13
Average Delay
14
Degree of saturation
15
Queue Distance
16
Level of service
Step 3: Begin construction of foundation and pillars in the area allocated between the surface roads.
17
Step 4: Begin construction of bridge
Early construction of surface roads will enable us to keep South Road open. For safety, ease of
construction and to reduce delays, 60 percent of the traffic volume should be diverted. The 40
percent of the traffic can access South Road through one open lane of the surface roads in each
direction. The use of only one lane in each direction provides sufficient clearance from the
construction site hence increased safety and no obstacles for vehicles. With step 2 completed, the
construction of the overpass components can begin.
Conditions stated by the client require us to keep South Road open. The detour we propose enables
us to divert 60 percent of the vehicles along the route in section 1.5.2 of this report and the
remaining 40 percent to use the single lane in each direction of the surface roads, thus keeping
South road open.
Prior warning to the general public to expect delays along South Road.
Provide information and advance notice on the detour routes proposed in section
1.5.2
Temporarily stop right turn movement of vehicles coming from North in South
Road to Sir Donald Bradman Drive
Installation of traffic signal at Sir Donald Bradman Drive and South road
intersection with temporary signal phasing specified in this report.
The temporary traffic signals have been designed to allow fewer delays for all movements towards
the Adelaide Airport
18
The temporary stopping of right turn towards the airport at Sir Donald Bradman Drive and South
Road intersection must be warned. Advice must be given to use the following route to access the
airport.
Analysis of temporary signal design at Sir Donald Bradman Drive and South road intersection
Temporary traffic signals have been designed and analyzed. Care has been taken to minimize delay
as much as possible. The signal phases used, expected delay, expected queue and level of service
are discussed in coming section. Please refer appendix A2 for intersection summary.
19
Signal phasing of temporary signal at Sir Donald Bradman Drive and South road
The following figure 1.8 shows the signal phases designed for the temporary traffic signals.
20
Delay at intersection
Figure 0.9: Delay at intersection of Sir Donald Bradman Drive and South Road
Figure 1.9 shows the expected delay at the intersection. The vehicles towards the airport from the
South and from the East will experience delays less than a minute. Vehicle movement along South
Road will experience less delay if the traffic volume is kept to 40 percent. The movement along
Sir Donald Bradman Drive will experience delay under a minute. All the other movements will
experience delay just above a minute.
Degree of saturation
The degree of saturation indicates ratio of demand to capacity. Figure 1.10 shows the degree of
saturation for the intersection.
21
Figure 0.10: Degree of saturation for the intersection
The analysis clearly indicates that for majority of the movements the degree of saturation is
exceeding 0.6. This implies that the intersection will work very close to capacity level. Since the
traffic signal is only temporary, the expected degree of saturation of 0.9 for the intersection can be
approved.
23
Level of service
Detour
The detour we propose is for at least 60 percent of the total volume of vehicles along South Road.
The following route comprises the detour for vehicles moving along North to South and vice-versa
Mile End South - James Congdon Drive - East Terrace - Port Road.
24
N
For vehicles starting from North the vehicles can enter Port road and arrive at Port Road - East
Terrace intersection. This gives them the option to continue South or enter the city by turning left.
For those vehicles that continue along James Congdon Drive, they will get the opportunity towards
25
Henley Beach or the airport by turning right into the Bakewell ramp South. The vehicles that along
James Congdon Drive continue will eventually join South Road at Mile End South.
The detour route chosen have lesser volume and provides access to the city as well as West towards
Henley beach road.
Signalization of Bakewell bridge of Henley Beach road and James Congdon Drive Underpass
The Henley Beach road and James Congdon Drive Underpass provides access on and off access
to James Congdon Drive via the ramps. It is observed that some vehicles use it. Also due to the
detour there are chances for the usage of ramps to increase. Hence due to the high volume of traffic
passing through James Congdon Drive and for the safety of turning vehicles the intersection at the
bridge must be signalized.
Detour analysis
As a part of the detour the following intersections were analyzed to check whether they can
accommodate the new traffic volume or not.
2. Henley Beach road and James Congdon Drive Underpass (Bakewell Bridge)
26
Figure 0.14: Level of service of Sir Donald Bradman Drive and James Congdon Drive Intersection
Figure 1.14 shows the expected level of service at the intersection. The level of service for the
through movement from South to North will be F, while on the other hand the level of service for
the normal movement along the West to East and East to West will be C and E respectively. The
intersection as a whole will reduce to the level of service of E due to the temporary detour
movements.
27
Figure 0.15: Expected delay at Sir Donald Bradman Drive and James Congdon Drive
Intersection
Figure 1.15 shows the expected delays at the intersection. Each approach of the intersection has a
movement that will experience delays about four minutes or under. The main movements West to
East and East to West will experience delay of just above a minute, while North to South and South
to North will experience delay less than two and a half minute. The delays are acceptable due to
sudden influx of heavy traffic along James Congdon Drive and the main movements with the most
traffic volumes will experience lesser delays. The overall delay at the intersection is just above a
minute.
28
Figure 0.16: Degree of saturation at Sir Donald Bradman Drive and James Congdon Drive
Intersection
The figure 1.16 shows the degree of saturation for the intersection. The degree of saturation
exceeds one for three of the movements. The movements along Sir Donald Bradman Drive have
degree of saturation close to one. Due to the temporary nature of the detour this intersection will
be restored to normal once the construction of the overpass is over. Expect the South to North
movements; the other movements that have exceeded degree of saturation of one are minor
movements and have comparatively lower traffic volumes.
29
Figure 0.17: Expected queue length at Sir Donald Bradman Drive and James Congdon Drive
Intersection
Figure 1.17 shows the expected queue length at the intersection. All the movements expect the
North- South movement along Sir Donald Bradman Drive have lower queue distance. The South-
North movement along Sir Donald Bradman Drive will have a queue length 472m. Since only
through movement is allowed along this queue length is acceptable.
With all the results of the intersection within acceptable ranges we can conclude that the Sir Donald
Bradman Drive and James Congdon Drive Intersection can take the extra volume of diverted
traffic.
30
Henley Beach road and James Congdon Drive Underpass (Bakewell Bridge)
The current bridge at the underpass at Henley Beach road and James Congdon Drive is not
signalized, but as reported earlier the re-routing of traffic can increase the number of vehicles
accessing the ramps also, due the increased volume of traffic it is better to signalize the intersection
temporarily. Please refer appendix A2 for intersection summary
The signal phases used for the new signals are shown in figure 1.18
Figure 0.18: The phases for the temporary traffic signals at Bakewell Bridge
Figure 1.18 shows the phases adopted for the temporary traffic signals at Bakwell Bridge. The
phases are adopted to allow safe turning of vehicles into Bakewell ramp south. Using theses phases
the intersection is analyzed and the results are discussed below.
31
Figure 0.19: LOS of traffic signals at Bakewell Bridge
The movements serving the re-routed traffic have good level of service. The level of service for
the vehicles entering the Bakewell ramp south has a level of service of F; this might be due to the
increased importance given to the through movements along the bridge. The intersection will have
an overall level of service of C.
32
Figure 0.20: Expected delays at Bakewell Bridge
The expected delays at the Bakewell Bridge are shown by the figure 1.20. As seen the through
movements along the bridge will experience little or no delay. The right turn movements for
vehicles from North to South will experience delay of four minutes but due to the lesser traffic
volumes it is acceptable. Overall the intersection will face delay of 26.8s.
33
Figure 0.21: Degree of saturation at Bakewell Bridge
Figure 1.21 shows the expected degree of saturation of at the Bakewell Bridge. The right turn from
North exceeds one and the movements in the south are close to one. This is due to the increased
traffic flow due to re-routed vehicles. Due to the temporary nature of the signals, it is acceptable.
34
Figure 0.22: Expected queue lengths at Bakewell Bridge
Figure 1.22 shows the expected queue lengths at Bakewell Bridge. Only the movements from
South of James Congdon Drive will queue length exceeding just 300m while the rest of the
movements have queue lengths well below 100m. The queue length of 300m can be accommodated
in the South Side of James Congdon Drive.
The analysis of the intersection provides acceptable results especially for the re-routed North-South
and South-North traffic movement along James Congdon Drive. The temporary traffic signals
placed can be removed after the construction of the overpass is over.
35
1.6 Signage
Signage provides warning and important information to all the road users. Following signage will
be provided after the construction of the overpass.
Sign Description
36
Warning sign to denote no overtaking on
bridge for safety purpose.
37
2 STRUCTURAL ENGINEERING
38
2.1 Road Traffic Loads
Road traffic load is the load which is resulting from the vehicle passes over the structure either
single or in group. There are several load cases as per Australian code AS 5100.2-2004
Load of an axle is taken as 360 KN and a uniformly distributed component of 6KN/m throughout
the length. This formation is assumed to be at all 6 lanes of bridge for the critical load combination.
M1600 (cl.6.2.3)
=1590KN
=9540KN
39
for the critical case scenario. This maximum bending moment is further used for the design of
reinforcement by the help of empirical formulas.
2.4 Headstock
To minimize costs and improve the efficiency of the design, the headstock will be installed
on the piles by being laid in-situ once the piles have been installed and allowed to cure
adequately. This prevents the need to use cranes, trucks and other heavy lifting equipment
to get the headstock into place. It also allows the design of reinforcement to exact
specifications and reduces the potential for installation problems.
The headstock has been designed to fit between the Super-T and the piers, and thus includes
extended reinforcing from the head of the piers for additional strength. This additional
reinforcing was not incorporated into the actual design and should be extra insurance against
failure of the member. Using ultimate loads obtained from Space GASS, the reinforcement was
designed to meet Australian concrete design standards (AS 3600) as well as the more relevant
bridge code (AS 5100). This was done in conjunction with South Australia’s DPTI structural
design handbook.
Table2.1: Headstock overall design
B 1800 mm
D 1800 mm
Cover 25 mm
f'c 40 MPa
40
fsy 500 MPa
Column height in table is the height of column above ground level. Extra 0.8 meter is provided
below ground level to connect with foundation.
41
3 GEOTECHNICAL ENGINEERING
42
3.1 Introduction
The geotechnical team was involved with the whole construction at the site with their team
members from starting to end. It involves excavation for the retaining walls, bore hole for the pile
foundation, pile cap and design of pile foundation and pavement.
43
14-16 Silty clay VSt 350 M
16-18 clay VSt 500 M
18-20 Silty clay VSt 500 M
Requirements of pavement
The upper surface layer is design for the DESA load.
The sub-base material should be better quality and respond well to DESA load and could
attain heavy load.
The base layer maintains strength with the existing soil.
Top layer or wearing layer must minimize the effect of wheel spray when raining.
Pavement surface should be attractive and mitigate the noise level produced between wheel
and surface.
It should have well skid resistance (0.45) for (80-90km/h) as per austroads.
Material properties
In the design of the pavement, materials are classified as; Subgrade, Granular materials, Cemented
materials, and Asphalt concrete.
44
Subgrade materials are anisotropic elastic, E1/E2=2, Poisson ratio 0.45, Resilient modulus
is calculated by CBR method.
Concrete materials should be Isotropic elastic; Modulus is varying with compaction and
Poisson ratio is approximately 0.2.
Asphalt concrete is considered as elastic and isotropic. In this temperature effects the
modulus and weighted mean annul temperature is needed.
3.5 Excavation
As per the geological conditions excavation is necessary for the pile foundation and retaining wall.
Auger bore hole method is used for the boring of piles and approximately 3m soil is excavated to
place the pile cap. But for the retaining wall, soil is excavated along the length of bridge at both
side. Bulldozers and excavators are used for the soil excavation and trucks are used to remove the
soil from the site.
45
one side. This retaining wall is designed by divided into three parts with top, middle and bottom
parts.
46
back-filling material and this is placed on a slab foundation. This wall is connected to the
foundation and foundation is loaded with the backfill material.
The main objective of pile design is to provide a footing that will safely support the superstructure
over its design life.
The design of pile foundation is based on the geotechnical report of soil, by knowing the soil
properties the type of pile foundation is decided. As Per the department of planning transport and
infrastructure (DPTI) geotechnical properties of soil on bore hole BH7 are discussed above.
Based on the geotechnical report continuous flight auger piles are used for the foundation. CFA
pile is formed in the ground by drilling with a hallow flight auger that is subsequently and
progressively with drawn with the cavity below the auger tip being gradually filled with concrete
or cement grout injected under the pressure. The continuous flight auger piles are built until the
47
depth of 30m and diameter of piles ranging up to 1.2m. According the conditions of soil the length
of pile used is 20m and diameter is 1.2m.
Length of pile=20m
Diameter of pile=1.2m
Pile design:
All the pile design calculations are based on Australian standard AS2159-2009
Ru*= g * Ru≥ p
48
Design capacity (Rd) = g* Ru
= 0.75 to 0.90
p = percentage of the total piles that are tested and meet the specified acceptance criteria
49
4 URBAN PLANNING DEPARTMENT
50
4.1 Introduction
A key focus of urban planning is to enhance and protect urban component of South Road and Sir
Donald Bradman Intersection and surrounding land area. Urban design particularly concerns with
the affected businesses, public utilities, and land due to the development of expressway and
provides a strategy for revitalization and permanent establishment.
The construction of overpass structure together with the road widening work most optimally causes
the relocation of several buildings along the eastern alignment of South Road. The existing South
Road and Sir Donald Bradman Drive intersection will be also shifted towards eastern side and
results in the requirements of the new layout for running services lines and lighting.
The construction of expressway does not require modification to the western boundary of South
Road, however, urban design of this project equally considers the both side’s socioeconomic
components and parameters. The design is more focused on maintaining unique identification and
visualization of overpass structure and surroundings environment.
4.2 Objectives
In general, urban design objective is to keep the environment better than the existing condition.
Our conceptual direction for urban design specifically reflects the sense of civic pride without
depleting environmental quality.
51
To upgrade the living standard of the community by maintaining the viability of
development.
To improve the aesthetics of the whole project.
52
Further consideration of the remaining two buildings shows that these building would be
the significance of potential state heritage property and could be benefit for present as well
as future generations to promote the necessity of conservation.
Fig 4.2: heritage property to be demolished and preserved (Source: Google earth)
53
Table 4.1: List of the Commercial Buildings
S.No Description Importance Remarks
Start from James Congdon Drive
1 Adelaide Marble Specialist Low
William Street
2 The Carplace Low
3 Laguna Loans Low
4 The Frame Connection Low
5 Gerace Restoration Low
6 Automotive Distributor Low
7 Harvey Norman High
54
17 ALLSTAFF training center Low
18 South Australian Fine Wine Low
19 Ballara Street
20 LIN Andrews Real Estate Low
King Street
21 MK2 Recruitment Low
22 Chem Central Medium Medium
23 Phillis Real Estate Low
24 ASI Solution Low
Cuming Street
55
Category C building would be paid AUD 450,000.00
Overall compensation cost for this particular project is calculate below on the table 1.4.2
Table 4.2: Compensation Cost Calculation
400,000.00
11 ANZ office furniture B
450,000.00
13 BOC (Gas and gear) A
56
16 Huntinton Honda C 380,000.00
400,000.00
22 Chem Central B
One of the key concerns the urban team focuses on is how to develop an effective land
utilization strategy for the unused land after the development of the expressway
57
Fig 4.3 Land utilization strategy towards north
58
There exists approximately 1743.71 sq. meter of unused land north of Rosslyn Street and south of
Sir Donald Bradman drive and approximately 7974.94.sq. meter of unused land between Rosslyn
Street and William Street. Since these land packages lie adjacent to the intersection and has high
commercial value, a practical solution of recouping the Government investment by reselling
packages of these unused lands back to the public by holding a land auction where in the highest
bidder get to acquire the land, is the proposed strategy. With this strategy, the aim is to develop
small business which can run and operate with the existing patch of land that can also cater the
needs of the local community around it. Prioritizing on who the land is sold to should be adopted
so that the businesses that have been affected with this development are being given an option to
redevelop their businesses with the smaller land packages. Although in the 7974.sq.m of land
between Rosslyn Street and William Street, a sedimentation basin of 100 sq. meters is proposed
along with the road development, the rest of the land can be utilized.
With the 8575.9 sq. meter of land that exists between William Street and James Congdon drive,
the land utilization strategy is to develop a park which can be named as Sir Donald Bradman Park.
The idea behind the park here is because this land lies near several residential structures and local
communities. With the motorway being developed a few meters away from these residential
establishments, the vehicular noise, emissions and particulate matter can be a major concern to the
adjacent local population, hence the primary motive in developing a park is to plant tall specialized
trees in rows along the boundary of the park which acts as natural pollution controllers by adhering
dust and particulate matter on to them. It has been proven that when planting these trees in rows,
there has been a reduction in traffic noise levels by 5 or more decibels. Also by developing a green
space with wide varieties of tall and shady trees and lush flora, it can result in an improvement in
the communities’ response towards this project and at the same act as natural pollution control
measure from the vehicular emissions and dust. Further the local council could be requested for
day to day functioning and maintenance of the park after its development. There can be some
provisions for small snack shacks and ice cream shops thereby contributing to the revenge of the
city council and at the same time attracting communities to the park.
Northbound of the intersection, between the Daringa street and the Sir Donald Bradman drive,
there exists the local heritage site. The local heritage site consists of four different buildings and
the urban team having understood its cultural significance has opted for two of the heritage
59
buildings to remain unaffected with road development. Although the remaining two should be
demolished, the little package of land of area 1149.61 sq. meter left after acquisition will be
landscaped thereby providing the remaining heritage site a better aesthetics.
North bound of Daringa Street, most of the unused land lie bordering residential properties and
thereby shall not be utilized for commercial establishments. The proposed noise walls run along
the boundary of the land thereby preventing excessive noise impact to the local communities.
Further the water team has proposed for a sedimentation basin of 100 sq. between Cuming Street
and King Street. And the rest land shall be landscaped. Further the strategy is to replant the
uprooted trees during land acquisition in this section to reduce the air quality and emission impacts.
These trees when planted along row adjacent to the noise wall can act as natural particulate matter
and dust filters thereby reducing community impacts. Further on this is mentioned at the natural
vegetation removal section of the environment management plan.
60
Fig 4.4 land utilization strategy towards south
61
4.5 Services Management
a) Existing Services
The following services are currently locating underneath of South Road.
Water supply lines
Wastewater lines
Optus Cables
Telstra cable
Low voltage electricity lines
The following utilities lines are not detected on the proposed road section
Gas line
Storm water line
Recycle water line
There are two water supply main lines situating under the center of South Road and one
distribution line is locating underneath of the Local Streets. Distribution lines will not be
disturbed but main lines would be necessarily relocated. Household connections are
provided through distribution lines only where different controlling valves are placed to
control the supply. 300 mm and 250 mm diameter cast iron concrete lined pipes has used
in main lines and 100 mm and 150 mm diameter of same material pipes are being used for
distribution lines.
62
Fig 4.5 : Existing layout of SA water line (Source: UNISA, CIVE 4008 Example
documents)
A single wastewater line is running through the center of South Road and Local Street
where 500 mm and 150 mm diameter pipes are being used for main and distribution lines
respectively. Houses are connecting to the distribution lines only and regulating by
respective controlling valves.
63
Fig 4.6 : Existing layout of wastewater line (Source: UNISA, CIVE 4008 Example
documents)
ETSA and other telecommunication cables are running on the common service trenches
under the footpath of South Road and Local Streets. Houses are connected partially from
South Road and Local Street.
64
Fig 4.7 : Existing layout of telecommunication cables (Source: UNISA, CIVE 4008
Example documents)
b) Permanent establishment
As the current intersection, will be shifted and entire width of South Road will be increased,
there will be a huge impact of construction to the all underground services lines. All the
service lines which are lying under Local Street will not be disturbed and same line will be
running after the construction.
i) Water supply and Wastewater line
Water supply and wastewater lines which are currently situating the motorway of South
would be shifted under the new cycle lane. Wastewater line will be running right side cycle
lane and two water supply main line will be locating under the both side cycle lane. These
lines should be connected to the existing distribution lines. The plan views of layouts of
theses line are attached in the Appendix.
Design Constraints:
The minimum cover to the supply lines should be 600 mm.
65
The minimum horizontal separation between waste water line and water
main lines should be 1500 mm.
There should be maintenance shaft (manhole) with in the interval of 400 m.
Water supply lines should be located above wastewater lines during
crossing and the minimum clearance between two lines should be
maintained.
Controlling valves should be provided as necessary and new connection
point should be provided for future extensions.
Pipes should be placed with an appropriate grade to flow the water without
obstruction.
Size and material of the pipes should be according to the SA water
standards.
The final design for the layout of all services is taken considering the both sides public
conveniences. Although the road extension would be along the eastern alignment,
66
amenities of community will be considered equally for both sides. Appropriate arrangement
should be placed during the relocation of services as the interruption of utilities disturbs the
public daily life activities.
4.6 Lighting
Road lighting is an important part of urban development. The main aim of road lighting is
to provide healthy, clear visibility of road to the road users, to reduce the accidents and
crime rate. Lighting is not only essential to road users like vehicle riders, cyclists and for
pedestrians but also gives beauty to that area.
67
at night times not in the day times. By using movable light stands or poles they can take-
off at day times, by take offing it will not obstacle to work.
68
Lighting for pedestrian, beside the pedestrian lane the lighting poles are kept. For the
pedestrian lighting we are going to lamp pole lighting poles.
Color: The choice of color for the overpass can cause it to relate with the surrounding
environment or contrast with it. Grey color can make the underpass standout from the
surrounding landscape without being too flashy and is a widely common choice in
Australia.
Art and bridges: Art works relatable to the history and culture of the area in the overpass
can make it seem more of a sculptural artefact to the surrounding area. Artistic impressions
of the cricketing legend Sir Donald Bradman on either side of the piers can turn the elegant
bridge to a memorable one by portraying the Australian cricketing history.
Noise wall: By providing the proposed acrylic polycarbonate noise wall along the overpass,
the scenic landscapes around it is showcased from a significant height to the motorist,
further to its noise insulating properties. Moreover, it improves the overall aesthetics of the
bridge making it an iconic structure in South Australia.
Advertising: This can be one of the strategies adopted to recoup the government
investments by providing advertising boards along the beam of the bridge without
disrupting the overall visual effect of the bridge. These can be used by the government or
city council or can be auctioned out to the private companies thereby generating a fair share
of income from the structure.
69
5 ENVIRONMENT MANAGEMENT PLAN
70
5.1 INTRODUCTION
The Environmental Management plan sketches how the development of the proposed overpass at
Sir Donald Bradman Intersection might influence and disturb the surrounding natural environment
and on how those environmental implications can be averted, mitigated, and managed so that the
project is an environmentally sustainable one.
Our environment management plans include both measures and guidelines to minimize, control
and avert environmental impacts during and post construction. These mitigation measures should
be adopted by the contractor during the construction stage to minimize the ecological impact to the
surrounding environment. Further environment management plan also includes design strategies
and consideration to be adopted post development of the overpass to minimize the noise and air
quality impacts to the surrounding environment.
71
5.2 PURPOSE OF THE ENVIRONMENT MANAGEMENT PLAN
The purpose of environment plan is to develop a strategy and framework so that environmental
impacts associated with the project is minimised and mitigated to the maximum possible extent.
The objectives of the environment management plan are
To develop a design strategy to minimise all possible environmental impacts post project
development
To provide suggestions to minimize environmental impacts during construction
Identify and mitigate the community impacts.
72
Fig 5.1: The study area
73
Fig 5.2: Aerial view
74
5.4 TEMPERATURE
Adelaide experiences temperature as high as 45 degrees Celsius during the summer months of
December and January while temperature can go as low as 1 degree Celsius during the winter
months of June to August.
Fig 5.3 The graph contains rainfall data of the year 2015
75
5.5 RAINFALL
Adelaide experience moderate rainfall throughout the year with its higher monthly average
accounting for 80mm during the months of June and July and dropping as low as an average of
7mm in the summer months of January and February.
These data on temperature and rainfall is highly essential to schedule the projects commencement
as environmental impacts is highly affected by existing weather conditions.
76
5.6 ENVIRONMENTAL CONSIDERATION
This sections explains in detail the environmental impacts and mitigation measures during and post
development of the proposed overpass at Sir Donald Bradman intersection. These measure and
mitigation strategies have been designed to minimise the environmental impacts to the surrounding
natural environment and communities. The various environmental aspects and potential impacts
identified with the project were:
Additionally, a community management plan is also developed to generate a plan so as to keep the
community notified about potential impacts and to minimise the impact of the project on the
adjacent communities.
77
5.7 NOISE AND VIBRATIONS
One of the primary environmental concern associated with the development of this project is the
generation of road traffic noise. Different kinds of unwanted sounds like the noise from the engine,
exhaust, aerodynamic effects, road/tyre interactions are produced from running vehicles and this
creates concerns and problems for the communities that lives adjacent to motorway and its arterial
roads.
Hence, there arises an essential need to minimize and mitigate the noise impact from the motorway
on the adjacent communities and the surrounding environment.
An acrylic polycarbonate material noise wall that is optical distortion free for the motorist and
also at the same time, showcasing the scenic landscapes of Adelaide to the motorist will be
constructed along the overpass. The design criteria for this noise wall shall be such that acrylic
polycarbonate sheets of height 2 meters are placed between aluminium support railings of height
2.5 meters spaced at an interval of 1 meter. (See appendix for more info)
Additional to the sound insulating properties, these noise wall does not cast a shadow upon the
motorway and the surrounding environment thereby enhancing the safety of the motorway users
by transmitting light. These noise walls with its attributes such as UV and chemical resistance,
anti-graffiti, low maintenance, good durability, recyclable and excellent optical properties, also
comply well with the Australian standards.
78
Along the surface roads, the aim is to develop a combination of bund (earth mound) and acrylic
polycarbonate noise walls so that the noise impact is absolutely minimised to the adjacent local
communities. The design is to place the 2-meter-high acrylic polycarbonate noise wall over a bund
of height 1meter and width 0.5 meter. This design strategy is adopted so that the traffic noise from
the surface roads can be completely minimised by both the bund and the polycarbonate while at
the same time please aesthetically to the local communities living adjacent by planting fresh patch
of green grass over the earth bund. Also by using the transparent acrylic polycarbonate material
over the bund, light can be transmitted and thereby not casting a shadow upon the residential
buildings despite the overall structure having a total height of 3 meters combined as opposed to the
brick noise wall.
Further to this a noise management plan is to be developed so as to mitigate the noise and vibration
during the construction so that the bordering communities are not severely disturbed. This should
include standard construction hours that is followed every day and various noise mitigation
measure adopted for the machinery involved in construction so that minimum noise is generated.
Further community notification is essential while carrying out highly noise generating jobs like
building demolition and vegetation uprooting and additional noise barriers are to be placed around
the activity. These measures can significantly reduce the generated during and after the project.
5.7.2 VIBARTION
Activities like pile driving and bore excavation during project development may lead to vibrations
in and around its adjacency creating problems for bordering residential and commercial properties.
Further movement of heavy duty trucks and freights can also because vibrations post project
development. Further a study has revealed that buildings beyond 50 meters from the sources is not
highly affected. However, since several buildings lie within 50 meters, mitigation measures need
to be implemented so as the community is less affected.
The proposed noise wall can to an extent limit the vibration. However, this is not sufficient. Some
of the suggestion to reduce vibration are using by mufflers to heavy load vehicles and machinery,
enclosing highly noisy equipment’s and providing noise attenuation screens around them. Further
those activities creating excessive vibration should be restricted to certain time of the day to cause
lesser nuisance. These measures can minimise the vibrations around the area.
79
5.8 AIR QUALITY, EMISSIONS AND DUST GENERATION
With the commencement of the project development, air quality is an issue of major concern in the
locality. Various construction activities like clearing of land, demolition of buildings, running of
diesel engines and burning will immensely contribute to the air pollution and dust generation at Sir
Donald Bradman intersection and its neighbouring areas. Additionally, post construction phase,
with surface roads being closer to the communities residing nearby, vehicular emission and dust
can also create a negative influence to the residences and commercial establishments. Hence the
need to monitor and mitigate the air quality and emissions in the area during and post construction
is of high significance. Some of the objectives identified were as follows
Mitigation measures and plans to control the impact of emissions from vehicles and
machinery in the adjacent areas.
Minimise dust generation during and post construction
Aim to minimise the impact on local communities with the onset of the project
80
aesthetics of the regions by providing the area a greener look. Further the proposed park south
bound of William Street can additionally improve the overall air quality in the locality.
However, more dust suppression strategies must be implemented during the construction phase
when particulate and dust generation is significantly high. Using water trucks to spray and sprinkle
water during construction can prevent excessive dust generation. Additionally, cover must be used
while working with tiny particulate matter like cement, sand and while transporting them. Further
all kinds of burning must be prevented in the construction site as it may cause trouble for the
adjacent communities. Contractors must be advised of using good exhausts for all the machinery
and vehicles to minimise emissions as much as possible.
Assessing weather condition is also essential while carrying out jobs. Undertaking works that can
generate dust like land excavation, painting, vegetation uprooting etc. during windy weather can
lead to the particles being air borne and transmitted to the adjacent residential areas.
Further a complaint register must be set up at the site for communities to lodge complaints and
problems due to the construction activities. By effectively responding to these problems, the
community feedback to the project also improves.
81
5.9 WASTE MANAGEMENT AND SOIL CONTAMINATION
Although waste management and soil contamination falls under the responsibility of the
contractors and their sub-contractors, the Innovare environmental team has come up with some
suggestions and mitigation measures for waste management and soil contamination to make the
project a more environmentally sustainable one.
During the construction operations, a lot of waste is generated at the site that must be recycled,
conserved or disposed properly. Some of the waste generated during construction are excavated
soil and stones, removed vegetation, concrete materials, metal scraps and waste, chemicals, waste
from demolished buildings, excavation waste and minimum amount of food & water bottle waste.
These wastes generated if used productively can be used as a supplement for diverse activities
effectively thereby minimizing the waste storage problems. Also, extensive waste recycling need
to be implemented to make waste management more effective. Further with use of various
chemicals during construction, there is also a risk of soil contamination by increased acidic or
alkalinity level. Hence a regular monitoring system is essential to mitigate soil contamination and
waste management.
Care should be taken to minimize waste generation, waste recycling, and water waste and soil
conditions. There is a need to keep the waste bins at site, to put the waste in it and they should be
regularly dropped off. Further some of the waste generated like excavated soil and plastic can
reutilized for the project. Several studies have been carried out on using plastic in the bitumen mix
for road construction thereby increasing the durability of the roads. This strategy can be adopted
for the project if possible making the project a more environmentally sustainable one. Also the
excavated earth can be utilized to refill the area where trees are uprooted. By doing so the need to
transport the excavated soil is eliminated. Fire should not be produced in site and if any fire is
produced, contractor of the work need to control the fire and he is responsible for it. The
Contractors should keep the necessary equipment to control the fire and leakages. More care should
be taken for soil contamination. If soil at certain areas is severely contaminated soil reclamation is
suggested. By implementing these strategies, soil contamination can be prevented to large extent.
82
5.10 LAND DISTURBANCES AND EROSION
Massive projects like the proposed overpass development at Sir Donald Bradman intersection of
the south road involve huge large disturbances due to earth excavation and vegetation removal.
Activities like these make the soil prone to extensive erosion and soil displaced by erosion may get
to be airborne and become dust causing reduced visibility or be conveyed by water into larger
waterways causing contamination. Hence when it comes to considering erosion, it’s better to focus
on the preventive strategies rather than treatment later. Some of the measures that can be adopted
to prevent erosion are refilling the land removed after vegetation uprooting as soon as possible and
keeping other land clearances to bare minimum. By doing so erosion of the vegetation removed
land is prevented since the land left after plants uprooted is highly prone to erosion. Further, since
this part of the south road does not contain steep slopes, the erosion is likely to be of lesser impact.
Additionally, commencing the construction activities during summer when intense rainstorms are
absent can further prevent the erosion. By adhering to these preventive measures before and during
construction, land destabilization and soil erosion can be minimized to great extent.
83
5.11 WATER QUALITY AND SEDIMENTTION
The unsafe chemicals, oils and acids used in site may have potential to spoil the ground water and
storm water. The affected water can run on the soil, thereby causing soil contamination and soil
erosion. Further with project site containing several underground sewer pipes and waste water
retention lines, there exists a chance of any pipelines getting disturbed and damaged during its
relocation resulting in leakage which can cause soil and underground water to get contaminated. If
the damage on the pipe is higher, it might lead to huge ecological problem like damage to
environment, soil erosion and damage to construction materials. Hence extreme care is needed
while performing soil excavation and services relocation and all the relocation needs to be done
based on services maps provided in the urban section.
Further after a heavy rain, the pooled water needs to pump out. This water very often contains
harmful chemicals and suspended sediments on this. Hence extreme care should be taken while
dewatering the sites as this may cause water pollution. The turbidity and the quantity of this water
need to be analyzed before disposal into water ways. Treatment is needed if the turbidity of the
water is more than 30 NTU and needs to pass over sediment control devices before pumping out.
If the turbidity and quantity of water is low this water can be effectively carried using pipes to
vegetated area adjacent to the intersection where the natural green cover adequately removes the
suspended solids from the water. Care should be taken to prevent water logging also.
Contractor also need to maintain and employ an emergency cleaning team at site to clean if
anything happens and they should be trained to control the extreme situations of oil spills &
chemical response. The project work should not contaminate ground water and soil with chemicals
and paints. There exists a need to check the underground lines regularly and if there is any leakage,
the EPA need to intimated quickly to overcome the danger
84
5.12 Native Vegetation Removal
According to Department of environment water and natural resources, a quarter of all the
indigenous flora and fauna in the state of South Australia has been classified as endangered. Hence
a careful investigation is essential before the commencement of the proposed project so that a bare
minimum damage is inflicted upon the natural environment.
Vegetation in the eastern alinement of the south road is proposed to be removed for the
development of the overpass. This region nearly encompasses 40 to 50 trees and some small shrubs.
According to native vegetation removal act, it is of medium impact (level 2) and they are
represented on the basis of the number of trees impacted in the area. Additionally, among the trees,
most of the trees fall under the species of yellow Bloodwood which are not any kind of indigenous
or endangered species. Most of the trees are on side of the road along the footpath. The strategy is
to uproot the trees as whole without damaging it and relocating it along the boundary of the
acquired land thereby causing minimum environmental impact and at the same time acting as air
pollutant barriers during construction. Further it avoids the growing time it takes for a small tree
to grow into a fully grown big one.
86
5.13 Effect on Fauna
According to department of environment, water and natural resource, there are no protected or
endangered species in the area making the fauna consideration less significant. However, care shall
be taken to avoid environmental impacts on the existing birds and animals. As suggested earlier
artificial bird nest shall be created and fixed if a certain species is known to nest in the existing
Yellow Bloodwood trees. Other than that, no special fauna consideration essential for this project
development.
87
5.14 Community Management Plan
Community management plan is an aspect of extreme significance as the bordering communities
are significantly affected with the onset of the project. Hence an effective community management
plan is crucial to keep the company notified of potential impacts and mitigation measures. An
effective communication between the client and the community is extremely essential to make this
project a successful one.
5.14.1 Communication
Communication is an important aspect when it comes to big developments like the proposed
overpass at Sir Donald Bradman Intersection which creates disruptions in the day to day life of the
adjacent communities and road users. Hence Innovare will design and implement a communication
strategy for effective communication between the community, client and the company. This will
include;
Community News letters: These community news letters will give out information
regarding the proposed projects to the adjacent communities which are directly or indirectly
affected with project development. These will give out information on the benefits of the
project, measures and policies undertaken to reduce and minimize the environmental
impacts.
Community meetings: Meetings between the client and the community can foster a better
a relationship between the community and the client. These meetings should include
members of the city council and client, consultant and community members. By holding
these meeting, the community is better aware of the latest developments
Community notification: These community notifications ensure that the community is
notified during high noise generating works or during redirecting traffic. These
notifications help the adjacent communities better prepared and aware about the
Complaint register: A complaint registers shall be set up to receive community feedbacks
and complaints. Further prompt and effective responses is needed for reasonable
complaints
88
Additional to the communication, there is a need to help the affected businesses in the area
additional to the compensations. As mentioned in the land utilisation strategy in the urban section,
prioritising on who to sell the unused land will be implemented so that the affected business has a
chance to redevelop their business with the remaining land package.
Further, the development of the park in the land between James Congdon drive and William Street
can promote the communities’ positive responses towards the project. The park will serve as a
green space and a place of recreation in the urban neighbourhood.
89
6 WATER ENGINEERING
90
6.1 Road Drainage Design
In South Australia, surface runoff is conveyed away from road infrastructure and urban areas in
storm water drains to existing waterways. The runoff does not receive treatment before discharge.
Hence, the quality of incoming storm water is integral to the preservation of healthy waterways.
The Water Engineering team at Innovare Consulting has undertaken design of the storm water
drainage system for the North-South Corridor Section R4 – Sir Donald Bradman Drive
intersection. Key design parameters are summarized in this report. The design process is
documented in Appendix D.
The expansion of the roads and additional road infrastructure require a new design of the storm
water drainage system in the study area. In this design phase, Innovare Consulting has identified
opportunities for incorporating Water Sensitive Urban Design (WSUD) measures into the South
Road upgrade. This aligns with the City of West Torrens’ aim to become a water sensitive city
(City of West Torrens 2016).
Innovare Consulting has considered the suitability of available WSUD measures based on the
rainfall intensity in the project area, space constraints and preservation of the structural integrity
and durability of the overpass.
In consideration of site constraints, bioretention swales, a popular WSUD measure which provides
the dual function of water quality treatment and flow conveyance, has been removed as a potential
measure.
Innovare Consulting also advises the Client that permeable pavements are unsuitable for the road
infrastructure. Although permeable pavements can provide conveyance and treatment features, the
high traffic volumes on South Road will have detrimental impacts on the infrastructure’s integrity
and durability (Department of Planning and Local Government 2010).
91
Two WSUD measures have been selected and incorporated into the designed drainage network as
part of the Sir Donald Bradman Drive road upgrade project. These are the bio retention systems
and sedimentation basins.
The ponding basin and soil media serve collectively as a litter trap. The exposed surface would
facilitate maintenance, with easy access for regular cleaning to prevent clogging of the system.
Excavation and construction works will remove around 70 street trees currently present on South
Road in the project boundary, as identified by our Urban and Environmental Team. The bio
retention basins will also provide part of the revegetation scheme for this project, through
integration of street trees in the basins.
92
During larger storm events, when the water level in the basin reaches capacity, water will overflow
into the overflow pit to prevent flow buildup along the roadside gutter and increase removal
capacity from the road system.
Treated water from the bio retention basins as well as overflow runoff are delivered by an
underground drainage collection pipe. This pipe then conveys the runoff to a sedimentation basin.
The existing collection drains along Rosebuck St on the northern side and Davenport St on the
southern side will require an upgrade in capacity to accommodate the discharge rate from the
sedimentation basin.
93
Figure 6.1 Conceptual diagram of storm water conveyance (Northern side)
94
Figure 6.2 Conceptual diagram of storm water conveyance (Southern side)
During construction phase, excavation and construction work will require temporary shifting of
storm water services. This can be achieved by replacement of affected sections with a flexible pipe,
while excavation and construction work is carried out.
95
6.4 Summary of Design
This section contains a summary of the key design parameters for the bio retention basins. Detailed
calculations are available in Appendix D.
Table 6.1 lists the specified parameters. The values apply to the surface roads and the overpass.
Parameter Value
Road cross fall 2.5%
Drainage channel Kerb and gutter
Gutter cross fall 2.5%
Gutter longitudinal gradient 1%
Gutter size 300mm x 300mm
A longitudinal gradient of 1% is applied to the gutters to allow for conveyance of surface runoff
along the gutters into the designated bio retention basins along South Road.
96
Innovare Consulting has designed the bio retention basins to adequately accommodate the minor
flood event, represented by the 5-year Average Recurrence Interval (ARI), as outlined in the
Roadworks Storm water Drainage standards. Where applicable, these elements have been checked
to ensure they satisfy DPTI’s traffic ability criteria for major events.
The bio retention basins will receive runoff only from surface roads; overpass runoff will bypass
the system and be conveyed directly to underlying storm water drains. The overpass runoff will
not be treated by the bio retention basins as pumps will be required solely to bring underground
runoff back to the surface for gravitational filtration through the bio retention basins. Innovare
Consulting concludes this is not a feasible option.
Due to the operating mechanism of the bio retention systems, our Water Engineering team has
concluded it is not feasible to direct collected overpass runoff to the bio retention units. To
introduce the overpass runoff to the bio retention units, pumps and additional piping would be
required.
The road system is divided into sections to facilitate the design process. The highest design
flowrate, corresponding to the section with a larger length of area considered, is used to design the
bio retention basin. This provides a uniform construction plan for the bio retention basins while
providing a level of protection against major flood events, particularly for the smaller sections
which are near the intersection.
The bio retention basins will be located at regular intervals along South Road to intercept and treat
surface runoff from each road segment.
Parameter Value
97
Width of bioretention basin 2.2 m
Length of bioretention basin 3m
Surface area of bioretention unit 6.6 m3
Total number of bioretention basins for South Road 23 units
Width of kerb entrance to bioretention basin 0.4 m
Vegetation scour velocity check Passed
Rock beaching at entrance for vegetation integrity Not required
Table 6.3 Distance between bio retention basins along South Road
Plant selection
A street tree will be placed in each bio retention basin. The selected tree species is yellow
bloodwood, which is the preferred species for the City of West Torrens Council. Native plants will
be planted on the floor of the bio retention basin. Tall sedge (Carrex appressa) is recommended,
planted at a density of 8 plants/m2 (Melbourne Water 2005).
98
Overflow pit
An overflow pit will be located adjacent to each bio retention basin to convey minor floods and
prevent runoff buildups from occurring at the kerb. Calculations have been carried out to check the
minimum pit size requirements. To adequately accommodate minor floods and provide a level of
protection against major flood events, a grated pit with nominal size of 600mm x 600mm should
be used. This grated pit can be purchased as modular pits from Humes.
Maintenance
The soil media provides a physical barrier to coarse sediments and litter, and its exposed surface
provides immediate access for regular cleaning. The exposed surface facilitates regular
maintenance through dry sweeping.
Table 6.4 summarizes the specifications for key design parameters for the underdrainage system
of the bio retention basin.
Table 6.4 Subsurface component specifications for the bio retention basins
Parameter Value
Filtration media Sandy loam
Particle size 0.45 mm
Depth of filtration layer 600 mm
Transition layer media Coarse sand
Particle size 1 mm
Depth of filtration layer 100 mm
Impervious lining Geotextile fabric
99
Depth of impervious lining 100 mm
Drainage layer media Gravel
Particle size Around 5mm
Depth of drainage layer 150mm
Perforated pipe type PVC slotted
Available clear opening (mm2/m) 2100
Number of perforated pipe(s) per bioretention basin 1
Diameter of perforated pipe 100 mm
Slope of perforated pipe 0.5%
Length of perforated pipe per basin 3m
Underlying stormwater pipe Concrete
Diameter of stormwater pipe 375 mm
Impervious liner
The Geotechnical Report provided by the Client has identified the subsurface soil to be composed
of sandy and silty clay. There is possibility of water exfiltration. Hence, an impervious lining is
required to mitigate the risk of water exfiltration from the bioretention system to the surrounding
soil. This lining is to be located at the base of the bioretention unit. The walls of the unit will be
unlined, as gravitational action and difference in hydraulic conductivity will minimise exfiltration.
6.4.5 Overpass
The overpass is designed to accommodate the minor flood (5-year ARI). The overpass design flows
were estimated and the values tabulated in Table 7.5 Selection of appropriate pits and underground
pipeline design are discussed in Section 1.3.5 Pipeline Design.
100
South-side carriageway (eastern side) 0.032
Parameter Value
Sediment removal performance target 90% removal
Target sediment size 125µm
Settling velocity 11m/s
Extended detention depth 0.25 m
Depth of permanent pool 1m
Depth below permanent pool 1m
Minimum sedimentation basin surface area 37.2 m2
Minimum width of sedimentation basin 3.0 m
Minimum length of sedimentation basin 12.2 m
Required cleaning frequency 10 years
Vegetation scour velocity check Exceeded
Rock beaching at entrance for vegetation integrity Required
The sedimentation basin surface area, width and length have been noted as minimum, as this is the
base dimensions for the sedimentation basin to provide 90% removal of 125 µm sediment. The
sedimentation basin can then be incorporated with gradual slopes and aesthetic features.
101
consider. Now the drainage pipe of a variety of materials, quality is uneven in quality, in the choice
of drainage pipe material, according to the influence of the performance of different drainage pipe
and can withstand drainage. So according to the drainage water temperature, water quality, and the
pressure on the section size and construction conditions, to choose the drainage tube material, as
easy as possible, choose to install local materials, easy transportation and drainage materials.
Drainage design of this project is underground drainage, pipe material as shown in the following
table:
𝐷
R = Hydraulic Radius ( )
4
S = pipe slope
102
The hydraulic radius is
Therefore, the appropriate flow in the pipeline can be calculated within the scope of the concrete
with the size.
The flow rate in the pipeline should be at an acceptable level and will not be damaged by the
pipeline. (V<3m/s)
𝐷
R =Hydraulic Radius ( )
4
S = pipe slope
103
Design & Installation: AS/NZS3725:2007
In our design we are recommending pipes should be placed on the outside of the road sidewalk or
below the grass. The minimum overburden thickness should not be less than 0.3m when the pipe
is not affected by the external load.
Pits
The overpass drainage design consists of both side entry pits. Standard modular pit can be used for
this purpose. According to the maximum diameter of the pipe, 900 x 750 x900mm modular pits
are selected for the project.
Pit Installation
The following installation of the storm water pipes and pits will be carried out according to the
following standards:
Manufacture: AS4139:2003
Quality: ISO9001:2008
104
Safety
In the course of transportation, loading and unloading, storage and installation, it is important to
observe the safety requirements and rules and regulations, including wearing appropriate personal
safety protection equipment. The geometry of the storm water pit unit receives its weight, and the
weight will be clearly marked on the drawing of the project. All pits shall be installed and placed
in a prudent manner and in strict accordance with all relevant occupational safety standards.
Delivery
Prior to delivery, in particular for the custom pit, a transport plan, including the delivery order and
the unit load shedding and installation sequence. Shipping plans will help save time and effort, and
reduce congestion at the scene.
Pit installation
Pits are usually installed as follows:
Before delivering the pit into its position, Inspection basis and bedding materials are not subject to
interference.
A small ball or similar tool is used to make the round hole up to the outer diameter of the pipe.
The rain puddles on the position. Lead the hole to the lower pipe. Check if there is enough clearance
below the pipe to allow sealant application.
Pit level should be checked using the spirit level, should also check the downstream and upstream
inversion level.
1. Pipe should be placed in the whole wall penetration. When placing the pipe, cutting, so that the
pipe will be flush with the inner wall of the pit.
2. Using approved non shrink epoxy grouting, the foundation pit wall will be sealed. This
specification shall be approved by the project manager and the site Engineer shall be verified by
105
the project manager. Should be sealed from the outside and inside to ensure adequate waterproof
sealing and quality of the pit wall.
106
7 References
City of West Torrens 2016, Rain Gardens, Government of South Australia, Adelaide.
Department of Planning and Local Government 2010, Water Sensitive Urban Design
Technical Manual for the Greater Adelaide Region, Government of South Australia,
Adelaide.
Melbourne Water 2005, WSUD Engineering Procedures: Stormwater: Stormwater,
CSIRO Publishing, Melbourne.
107
Appendix A1 - Grade and length of the Overpass
Based on Austroads Guide to Road Design Part 3: Geometric Design, Clause 8.5.2 and Clause
8.5.3, Table 8.2 and Table 8.3 we have
8.77𝑚
5% = 𝑅𝑢𝑛
108
Therefore, new run = 175.4 - 2.85 =172.55m
𝑅𝑖𝑠𝑒 8.77𝑚
Therefore, new slope = 𝑅𝑢𝑛 = 172.55𝑚 * 100 = 5.1%
Cross fall
Based Austroads Guide to Road Design Part 3: Geometric Design, Clause 4.2.2, and Table 4.2 we
have
109
Appendix A2 - Intersection Summary
Intersection summary of new traffic signals for Sir Donald Bradman Drive and South Road
110
Intersection summary of temporary traffic signals for Sir Donald Bradman Drive and South Road
111
Sir Donald Bradman Drive and James Congdon Drive Intersection (Bakewell Bridge) Phases
112
Sir Donald Bradman Drive and James Congdon Drive Intersection Summary
113
Henley Beach road and James Congdon Drive Underpass (Bakewell Bridge) Intersection Summary
114
Appendix B1 – Design of Headstock
The calculations used in the Horizontal component, the following moment and shear
values were used, as taken from the SpaceGass analysis.
V* 5245.17 kN
The largest M* value of 16410 kNm was used as the final design value, as this is the
most critical case and covers the smaller negative bending.
𝑀∗ = ∅𝑀𝑢
Therefore
Using
𝑀𝑢 = 𝐴𝑠𝑡𝑓𝑠𝑦𝑧𝑢
115
𝑧𝑢 ≈ 0.85𝑑
Meaning
=20512.5 / (500∗0.85∗753)
= 64096.55 𝑚𝑚2
For crack control, check that the minimum required steel is met, where
= 3∗0.8∗ ((1200∗800∗0.5)/500)
= 2304 𝑚𝑚2
𝐴𝑠𝑡 = 2480𝑚𝑚2
Now
𝐶 = 0.85𝑓𝑐′𝛾𝑘𝑢𝑑𝑏
For which
1240𝑘𝑁
𝑘𝑢
For realistic Mu calculations,
𝑀𝑢 = 𝑇𝑧𝑢
116
Where,
𝑧𝑢 = 𝑑 − 0.5𝛾𝑘𝑢𝑑
= 738 𝑚𝑚
So,
𝑀𝑢 = 1240𝑘𝑁 ∗ 0.738𝑚
Then,
So, use 8 N20 as the reinforcing for the horizontal component of the headstock.
𝑚𝑚
So adequate spacing between reinforcement for aggregate and pile reinforcement.
𝑉∗ = ∅𝑉𝑢
Therefore
Since
𝑉𝑢 = 𝑉𝑢𝑐 + 𝑉𝑢𝑠
117
Where
Therefore 𝛽1 = 1.1
𝛽2 = 1
𝛽3 = 1
𝑏𝑣 = 1200 𝑚𝑚
𝑑𝑜 = 753 𝑚𝑚
So
𝑉𝑢𝑐 𝑘𝑁
And
Therefore
So
𝑉𝑢𝑠𝑚𝑖𝑛
= 1018 𝑘𝑁
118
(Asvfsy. fdo
𝑉𝑢𝑠 = ⁄𝑠) x cot(θv)
where
𝑠 = 250𝑚𝑚
𝑉𝑢𝑚𝑎𝑥 = 7229 𝑘𝑁
So
𝜃𝑣
= 31.08𝑜
𝑉𝑢𝑠𝑠
𝐴𝑠𝑣 = 𝑓 𝑑 𝑐𝑜𝑡(𝜃𝑣)
𝑠𝑦.𝑓 𝑜
= 408 𝑚𝑚2
This means a minimum of 2N12 ligatures for a total Asv = 440 mm2.
119
Appendix B2 – Design of Deck
M1600 - Moving traffic assumes a 25m vehicle as the most critical case.
PE + ultimate traffic load + ultimate pedestrian traffic loads + ultimate wind load
SPACEGASS Analysis
The deck is designed as a super T girder across the width of the bridge by having the Super T
beam web underneath as supports. The distance between the supports is 2.5M. A variety of
positions for truck wheels are placed as eccentrically as possible to give adverse effects. The
loadings applied here is the same as the loadings used for Super T.
Bending moment
120
Fig 2: shows positive bending moment
Sheer force
Pavement 74kn
L =27m
= ((2700-60)/150)+1
121
= (2640/150) +1
=17+1
Cover = 30mm
d=160-30-12/2= 124mm
𝑓′ c = 40𝑀𝑃𝑎 𝑓 sy = 500𝑀𝑃𝑎
𝐸 c =32.8𝐺𝑃𝑎 𝐸 s =200𝐺𝑃𝑎
Span= 2700mm
Beam=2500*1200
Cover=30mm
Pa= slab+beam
Va= 5Kn/m*m
Slab 124mm
=6.25kn/m
Pa= 5*.124*6.5kn/m=3.87kn/m
=4*3.5*6.5kn/m=12.62kn/m
=9.37+17.03
= 26.40
122
Bending movement
Mu=w(l*l)/8
=26.40*(2.5*2.5)/8
=20.62kn/m
Vu=w/2
=26.40/2
=13.2kn/m
123
Appendix B3 – Design of Pier using Space Gass
Load case 10: self wt+ Super imposed dead load+ live load
Load case 11: 1.2 self wt+ 1.2super imposed dead load+ 1.5live load
Shear force and bending moment for each type of piers by the space gass are
124
Result of Analysis and Design of all the type of Piers by space gass
125
126
127
128
129
130
Appendix C1 – Pavement Design
131
132
133
134
135
136
137
Appendix C2 – Design of Retaining Wall and Reinforcement
138
139
140
141
142
143
144
145
Appendix C3 – Design of Pile foundation and pile cap
146
147
148
149
150
151
152
153
154
155
Appendix D Road Drainage Design
D.1 Design Flows Estimation
This section outlines the calculation steps undertaken to estimate the minor and major design flows.
These design flows are then used in the design of the bioretention basins and sedimentation basins.
The Rational Method design procedure was used. The minor flood event is taken as the 5-year
average recurrence interval (ARI) and the major flood event is taken as the 100-year ARI, as
specified in the DPTI Roadworks Stormwater Design standards DD-300 for road projects.
Assumptions
Critical storm duration, tc of 10 minutes
Peak design flows are calculated using the equation:
𝐶𝐼𝐴
𝑄𝑑𝑒𝑠𝑖𝑔𝑛,𝑦 = (1)
360
y = number of years
𝐶𝑦 = 𝐹𝑦 ×𝐶10 (2)
156
C10 = basic runoff coefficient (-)
The frequency conversion factors for the 5-year ARI and 100-year ARI are obtained from Argue
(1986). The factors are tabulated in Table D.1.
The design runoff coefficient for the 5-year ARI, C5 can be determined as follows:
𝐶5 = 0.855
Table D.1 shows the frequency conversion factor for each ARI and the corresponding design runoff
coefficients.
Table D.1 Frequency conversion factor and design runoff coefficient for minor and major systems
157
Figure D.1 Intensity-Rainfall-Duration graph for Sir Donald Bradman Drive
158
3. Catchment Area
The catchment area, A is calculated as the multiplication of flow travel distance, Lflow with the
length of the road, Lroad:
L = length (m)
For both overpass and surface roads, the flow travel distance, Lflow is the given by the combined
width of the road between the median strip and the kerb:
Overpass
The definition of the flow travel length as the distance from the median strip to the kerb requires
the overpass system to be sectioned into 4 equal sections when determining the runoff flow volume.
Hence, the flow travel distance for each section, as determined using Equation 4, is:
The overpass system is also longitudinally divided into 2 equal sections, with each side of the
overpass comprising half of the span and one ramp. Hence, the road length can be calculated as
follows:
1
𝐿𝑜𝑣𝑒𝑟𝑝𝑎𝑠𝑠 = 𝐿 + 𝐿𝑟𝑎𝑚𝑝 (5)
2 𝑠𝑝𝑎𝑛
159
1
𝐿𝑜𝑣𝑒𝑟𝑝𝑎𝑠𝑠 = × 25 + 172.55 = 185.05 𝑚
2
The catchment area for each section of the overpass is calculated using Equation 3:
Surface road
In design, the surface roads are considered up to 500m from the intersection. As the width of the
surface roads varies along South Road due to the presence of the overpass, the catchment area
varies. Additionally, one right-turn short lane of 40m, accompanied by one left-turn short lane of
100m is located on the Western-side carriageway at the intersection on the north side. Likewise,
on the southern side of the intersection, there are two short lanes of the same configuration located
on the Eastern-side carriageway.
To calculate catchment area, the surface road is divided into sections, as shown in Table D.3. Each
section considers the region from the centre median strip to the kerb on the road verge.
Section S1 can be described as the section of the surface road from 500m from the intersection to
the point at which the overpass begins. This gives the length of the surface road in section 1 as
327.45m.
160
For carriageways with no short lanes, Section S2 is the section from the overpass start point to the
intersection.
For carriageways with short lanes, Section S2 is the section from the overpass start point to the
left-turn start point, and Section S3 is from the left-turn start point to the right-turn start point.
Section S4 starts from the right-turn start point to the intersection.
The flow travel distance from the median strip to the kerb is determined using Equation 3 and
shown in Table D.4.
The catchment area is determined using Equation 2 and tabulated in Table D.5.
161
4. Peak Design Flows
The peak design flows are then estimated by substituting calculated values into Equation 1. The
calculation is shown using values for surface road section S1 and finding the design flow for the
5-year ARI as an example:
0.855 ×60×0.269
𝑄5 = = 0.038 𝑚3 /𝑠
360
The peak design flows for the surface road catchment region are calculated and tabulated in Table
D.6.
Table D.6 Minor and major design flows for surface road system
S3 0.010 - 0.029 -
S4 0.009 - 0.025 -
The peak design flows for the overpass catchment region are as follows:
𝑄5,𝑜𝑣𝑒𝑟𝑝𝑎𝑠𝑠 = 0.032 𝑚3 /𝑠
𝑄100,𝑜𝑣𝑒𝑟𝑝𝑎𝑠𝑠 = 0.093 𝑚3 /𝑠
162
2. Required Bioretention Size for Treatment
The bioretention basins for treating surface road runoff are sized based on their efficiencies in
meeting the water quality removal targets specified in the DPTI Roadworks Stormwater Design
standards.
For a nominated extended detention depth of 200mm, the required bioretention system surface area
for achieving specified performance targets is determined using the pollutant removal-treatment
size graphs available in WSUD engineering procedures (Melbourne Water 2005). Although these
performance correlations are for Melbourne, they have been used due to unavailability of these
correlations for Adelaide. The graphs are included as Figures D.2, D.3 and D.4.
163
Figure D.3 Performance for total phosphorous removal
164
The required surface areas to achieve each performance objectives are summarized in Table D.8.
The required surface area for the bioretention basin is taken to be 1.68% of the impervious
catchment, as this is the largest size requirement for achieving one of the performance objectives.
This will also satisfy the other performance objectives.
The impervious catchment in the project site consists of the surface roads and bicycle lanes. Hence,
the impervious width is equivalent to the flow travel distance determined in Section D.1. The
impervious catchment area is obtained by multiplying the catchment areas calculated in Section
D.1 with a fraction of impervious area of 0.9 for urban catchments:
For example:
0.269
𝐴𝑖𝑚𝑝𝑒𝑟𝑣𝑖𝑜𝑢𝑠,𝑆1 = × 0.9
1000
𝐴𝑖𝑚𝑝𝑒𝑟𝑣𝑖𝑜𝑢𝑠,𝑆1 = 2417 𝑚2
165
The total treatment area is determined using the following equation:
𝐴𝑡𝑟𝑒𝑎𝑡𝑚𝑒𝑛𝑡 = 40.6 𝑚2
The total treatment area requirement for each section is tabulated in Table D.9 below.
A road strip of 2.5m has been allocated in the Transportation team’s road design for the
bioretention basins. To provide provision for the external features of the bioretention basin, a width
of 2.2m is adopted. The length is selected as 3m. This yields a proposed bioretention basin surface
area of 6.6m per unit.
The number of bioretention units required for each section is then calculated by dividing the total
area requirement by the surface area of one unit. The results are tabulated in Table D.10.
166
S4 1 -
The bioretention basins will be located at regular intervals along South Road. The interval between
bioretention basins can be determined as follows:
For section S1, which will have 7 bioretention units, the distance between each bioretention unit
is:
327.45 − (3 ×7)
𝐿𝑖𝑛𝑡𝑒𝑟𝑣𝑎𝑙 = = 43.8 𝑚
7
167
3. Bioretention basin inlet design
The runoff from the surface roads are conveyed by a kerb-and-gutter system to the entrance of the
bioretention basins. For a 2-laned 60km/h road, the Austroads Guide to Road Design requires flow
widths to be less than 1.5m for minor events and at least 3.0m trafficable road for major events.
Hence, the inlet flow conditions need to be checked. An appropriate kerb opening is also necessary
to facilitate flow into the bioretention basins.
The components of the bioretention basin have been designed based on the design flowrates for
the largest section, Section S1. As bioretention basins are designed primarily in terms of
accommodating the minor flood event (5-year ARI), this approach can provide a degree of
protection against major flood events (100-year ARI).
𝑄 = 𝑣𝐴 (8)
𝑅 0.667 𝑆 0.5
𝑣= (9)
𝑛
168
Hence, the equation becomes:
𝐴 1.667 0.5
( ) 𝑆
𝑄= 𝑃 (10)
𝑛
The concrete gutter will have a crossfall of 2.5%, which is the same crossfall for the surface roads.
Thus, the channel area can be calculated as a right-angled triangle:
1
𝐴𝑐ℎ𝑎𝑛𝑛𝑒𝑙 = × 𝑑 × 𝑊 (11)
2
The flow depth and width along the gutter are calculated using an iterative process, with depth and
width modified until Equation 9 yields a similar value to the design flows Q5 and Q100. Both width
of flow and depth of flow are checked to be contained within the gutter.
𝑄 = 𝐶×𝐿×𝐻1.5 (12𝑎)
𝑄
𝐿= (12𝑏)
𝐶×𝐻1.5
169
0.038
𝐿= = 0.4𝑚
1.7 × 0.141.5
Therefore, the bioretention basin should have a kerb opening width of 0.4m.
𝑄 𝑄
𝑣= = (13)
𝐴 𝑊× 𝑑𝑒
0.038
𝑣5−𝑦𝑒𝑎𝑟 𝐴𝑅𝐼 =
2.2 ×0.2
170
𝑣5−𝑦𝑒𝑎𝑟 𝐴𝑅𝐼 = 0.09 𝑚/𝑠
This value is below the maximum allowable velocity (0.5m/s for five-year ARI). A similar process
is carried out to check the 100-year ARI velocity. A velocity of 0.25m/s was obtained through the
same process, which is below the maximum of 1.0m/s.
Hence, vegetation integrity is ensured for both major and minor flood events.
The underdrainage system provides the outflow pathway to filtered water. The maximum
infiltration rate through the filter media serves as the design flow used to design this system.
Parameter Value
Media Sandy loam
Saturated hydraulic conductivity, ksat (m/s) 5 x 105
Maximum pondage depth above filter media, hmax (m) 0.2
Depth of media, d (m) 0.6
ℎ𝑚𝑎𝑥 + 𝑑
𝑄𝑚𝑎𝑥 = 𝑘 × 𝐴𝑏𝑎𝑠𝑒 × (14)
𝑑
171
Where Qmax = maximum infiltration rate (m3/s)
hmax = maximum pondage depth above filter media = extended detention depth
Assumptions
Assume no blockage of pathways for water filtration through the voids of the filter media
Substituting the values in Table D.12 into Equation 8 gives:
0.2 + 0.6
𝑄𝑚𝑎𝑥 = 180 × 5 × 105 ×
0.6
𝑄𝑚𝑎𝑥 = 0.00044 𝑚3 /𝑠
Assumptions
Assume orifice flow conditions as water flows through perforations
50% of slotted area is blocked, so as to provide redundancy to the design
The equation for flow through a sharp-edged orifice is:
The total head on the perforated pipe is the sum of the following parameters:
Hence:
Table D.13 provides the pipe dimensions, as available in the WSUD Engineering Procedures
(Melbourne Water 2005).
Parameter Value
Total clear opening, Oc (mm2/m) 2100
Slot width, Ws (mm) 1.5
Slot length, Ls (mm) 7.5
Number of rows of slots 6
𝐵×𝑂𝐶
𝑁𝑠𝑙𝑜𝑡𝑠 = (17)
𝑊𝑆 × 𝐿𝑆
173
Where B = blockage factor = 0.5
Thus:
0.5 × 2100
𝑁𝑠𝑙𝑜𝑡𝑠 = = 93.3 𝑠𝑙𝑜𝑡𝑠 𝑝𝑒𝑟 𝑚𝑒𝑡𝑟𝑒 𝑜𝑓 𝑝𝑖𝑝𝑒
1.5×7.5
𝐴𝑜𝑟𝑖𝑓𝑖𝑐𝑒 = 𝑊𝑆 × 𝐿𝑆 (18)
1.5 7.5
𝐴𝑜𝑟𝑖𝑓𝑖𝑐𝑒 = × = 1.13×10−5 𝑚2
1000 1000
For the nominated bioretention basin length of 3m, the flow through perforations is:
𝑄𝑝𝑒𝑟𝑓𝑜𝑟𝑎𝑡𝑖𝑜𝑛𝑠 = 0.00785 𝑚3 /𝑠
The maximum infiltration rate through the filtration layer is 0.00044 m3/s, which is less than the
inlet capacity (i.e. Qperforations). Hence, this pipe diameter is accepted.
0.5 𝜈 0.5
𝑄 = [−2(2𝑔𝐷𝑆𝑓 ) 𝑙𝑜𝑔10 (𝑘⁄3.7𝐷) + 2.51 (2𝑔𝐷𝑆𝑓 ) ] ×𝐴 (19)
𝐷
174
A = area of pipe (m2)
To allow for flow under gravity, pipes should be laid at a minimum slope of 0.5%. An initial slope
of 0.5% is used in determining the flowrate through the pipe. Should the maximum infiltration rate
exceed the discharge rate, the slope will be increased to increase the flowrate exiting the system.
𝑄𝑝𝑖𝑝𝑒 = 0.0054 𝑚3 /𝑠
This exceeds the maximum infiltration rate. Hence, a perforated pipe with a diameter of 100mm
placed at a slope of 0.5% is suitable for the underdrainage system.
Selection of a commercially-available pit is carried out based on the required weir length, which
sets the minimum requirements for the pit perimeter.
As runoff enters the overflow pit with minor debris trapping, the overflow pit is sized based on the
assumption that the outlet is half blocked. The blockage factor is taken as 0.5.
Assumptions
Assume water flows freely into the overflow pit
Outlet is half blocked
Two checks are required for selecting the appropriate overflow pit size:
175
(a) Required weir length
The overflow pit is sized using a rearranged flowrate equation for a broad-crested weir:
3⁄
𝑄5 = 𝐵×𝐶×𝐿 ×𝐻 2 (20𝑎)
𝑄5
𝐿= 3⁄ (20𝑏)
𝐵×𝐶 ×𝐻 2
WSUD Engineering Procedures recommends placing the overflow pit inverts at a minimum of
100mm below the maximum ponding depth. This prevents ponding to reach the maximum depth,
thereby mitigating the risk of back-flooding from the basins onto the roadside gutters. Hence, a
value of 100mm is adopted.
0.0383
𝐿= 3⁄ = 1.42 𝑚
0.5 ×1.7 ×0.1 2
The required weir length, L is 1.42m, which would require a pit of at least 360mm x 360mm.
176
g = gravitational acceleration (m2/s)
𝑄5
𝐴 = (21𝑏)
𝐵×𝐶√2𝑔ℎ
0.38
𝐴 = = 0.091 𝑚2
0.5×0.6 ×√2×9.81×0.1
This area is equivalent to a grated pit of 300mm x 300mm. The required weir length necessitates a
larger pit size.
Hence, the overflow pit is selected based on the required weir length. The smallest pit availale
from Humes is 450 mm x 450 mm.
This selected pit size is checked on its capacity to partially accommodate (50%) the major flood
event. Using the same equations with Q5 replaced with Q100, the following values are obtained:
𝐿 = 2.04 𝑚
𝐴 = 0.13 𝑚2
The required pit size is then 510mm x 510mm. Hence, to provide a level of protection against
major flood events, the commercially-available pit size of 600mm x 600mm is selected.
177
2. Design flow estimation
Assumptions:
Critical storm duration, tc is 10minutes
The design flowrates are calculated by following the same calculation steps in Section D.1. To
design the sedimentation basin, a single flowrate is obtained for the ARI of interest. This flowrate
is calculated as a function of the urban catchment consisting of surface roads and overpass, such
that catchment area is:
𝐶𝐼𝐴
𝑄𝑑𝑒𝑠𝑖𝑔𝑛,𝑦 = (1)
360
where:
The sedimentation basin is designed based on the minor flood event for a 5-year ARI. The design
flowrate is:
𝑄5 = 0.19 𝑚3 /𝑠
Sedimentation basins can have different configurations and width-to-length ratio, depending on
project constraints.
For this project, a 1:4 width-to-length ratio is selected. This would allow the sedimentation basin
to be located within available surplus land from road expansions. The sedimentation basin will
have the following configuration (Figure D.5):
178
For this aspect ratio, the parameter signifying flow hydrodynamic conditions, λ is 0.4. The
corresponding turbulence, n is then:
1
𝑛= (23)
1−λ
1
𝑛= = 1.67
1 − 0.4
−𝑛
1 𝑣𝑠 (𝑑𝑒 + 𝑑𝑝 )
𝑅 = 1 − [1 + × × ] (24)
𝑛 𝑄⁄ (𝑑𝑒 + 𝑑 ∗ )
𝐴
The required sedimentation surface basin area, A can then be estimated by rearranging Equation
24 for A, and using an iterative procedure until values convergence.
Parameter Value
Extended detention depth, de 0.25 m
Depth of permanent pool, dp 1m
Depth below permanent pool, d* 1m
Substituting known values into the equation and iterating until convergence yields the following
required surface area
𝐴 = 37.2 𝑚2
For the aspect ratio that has been specified (λ =0.4), the required width and length of the basin can
then be determined:
𝑊 = 3.0 𝑚
179
𝐿 = 12.2 𝑚
𝑉𝑠𝑡𝑜𝑟𝑎𝑔𝑒,𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 = 18.6 𝑚3
𝑆𝑡 = 𝐶𝑎 × 𝑅 × 𝐿0 × 𝐹𝑟 (25)
R = removal efficiency
𝑆𝑡 = 9.2 𝑚3
The available volume for storage exceeds the required storage volume. Hence, the sedimentation
basin dimensions are accepted.
Applying Equation 25 in a rearranged form and using available storage area gives the cleaning
frequency as: 𝐹𝑟 = 10 𝑦𝑒𝑎𝑟𝑠
180
4. Vegetation scour velocity check
The inlet velocity is checked to determine if scouring will occur, thereby necessitating rock
beaching to be provided. The flowrate equation Q = vA is used, with area given by pipe area. The
incoming velocity for minor flood events was determined to be 0.51 m/s, which did not satisfy the
maximum permissible velocity. Hence, rock beaching is necessary to minimise scouring and
protect vegetation.
181