Professional Documents
Culture Documents
ISO 9001:2015
CMMI Level 3
TABLE OF CONTENTS
1 EXECUTIVE SUMMARY 14
1.1 Purpose of the Study 14
1.2 Scope of Work 14
1.3 Deliverables 15
1.4 Project Description 17
1.5 Traffic Study and Analysis 18
1.6 Engineering Survey and Investigations 20
1.7 Alignment and Engineering 21
1.8 Pavement Design 21
1.9 Design of Traffic Control and other facilities 22
1.10 Bridges and Structures 25
1.11 List of Retained Structures. 29
1.12 Environment and Social Impact Assessment 30
1.13 Land Acquisition and Utility Shifting 30
1.14 Improvement Proposals 30
1.15 Cost Estimates 31
1.16 Financial Analysis 32
1.16.1 Sensitivity Analysis 32
1.16.2 Conclusions 33
2 PROJECT DESCRIPTION 34
2.1 General 34
2.2 Existing Road 34
2.3 Existing Junctions 36
2.4 Existing Bus Shelters & Truck Lay Bye 39
2.5 Land Use Pattern 40
2.6 Existing Structures 41
2.7 Pavement 45
2.8 Historical Traffic Data 45
2.9 Existing Utilities 46
3 METHODOLOGY 47
3.1 Review of Data and Documents 47
3.2 Traffic Surveys 47
3.3 Engineering Surveys and Investigations 48
4 TRAFFIC STUDY AND ANALYSIS 60
4.1 Objective of the Present Study 60
4.2 Traffic Surveys 61
4.3 Classified Traffic Volume Count Survey 61
4.4 Classified Turning Traffic Count Survey 62
4.5 Pedestrian/Cattle Crossings Count Survey 62
4.6 Axle Load Survey 63
4.7 Origin & Destination Survey 63
4.8 Details of Second Time Traffic Survey for Mid Block Locations and Additional
4.9 Details of Second Time Origin-Destination Survey
4.10 PCU Values Adopted
4.11 Traffic Data Analysis
4.12 Classified Turning Traffic Volume Count Survey
4.13 Pedestrian Movement Survey Details
4.14 Analysis of Axle Load Survey Data
4.15 Origin-Destination (O-D) Surveys
4.16 Second Origin-Destination (O-D) Surveys (during Dec-2019)
4.17 Existing Toll System Analysis
4.18 Seasonal Correction Factors
4.19 Comparaison of Survey Data of Feb-2012 and May-2012
4.20 Traffic Forecast
4.21 Capacity Analysis of Road Corridor based on Existing Condition and Future P
4.22 MSA Calculations
4.23 Outcome of Traffic Survey & Analysis
5 ENGINEERING SURVEYS AND INVESTIGATIONS 14
5.1 Topographical Survey
5.2 Geotechnical Investigation Methodology of Field Work
5.3 Subgrade Investigation for Pavements
6 INDICATIVE DESIGN STANDARDS 14
6.1 Traffic Design 1
6.2 Pavement Design Consideration
6.3 Geometric Design Consideration for Highways
6.4 Classification of Roads
6.5 Terrain 15
6.6 Recommended Design Service Volumes
6.7 Design Speed 1
6.8 Cross-Section Elements
6.8.1 Right of Way (ROW)
6.8.2 Camber 1
6.8.3 Carriageway 1
6.8.4 Shoulder 15
6.8.5 Median 15
6.8.6 Sight Distance 1
6.9 Horizontal Curves
6.9.2 Super Elevation 1
6.9.3 Transition Curve 1
6.10 Vertical Alignment
6.10.1 Gradients 1
6.10.2 Vertical Curves
6.10.3 Vertical Clearance at Underpasses
6.10.4 Median Openings
6.11 Relevant Codes 1
6.12 Design of Bridges, Viaduct, Grade Separators and Railway over Bridges
6.13 Design of Box Culverts
7 ALIGNMENT AND ENGINEERING 16
7.1 Geometric Design
7.2 Existing Alignment
7.3 Horizontal Alignment
7.4 Design Standards
7.5 Proposed Design Standards
7.6 Proposed Alignment
7.7 Design Speed 1
7.8 Proposed Widening
7.9 Proposed Realignments
7.9.1 Realignment at T. Begur (km 34.800 to km 36.150)
7.9.2 Realignment after Dobbaspet, near ROB location (km 50.000 to km 51.500)
7.9.3 Realignment from ROB to Hirehalli Railway station (km 55.500 to km 57.800)
7.9.4 Realignment at ROB, After Kyatsandra (km 64.200-65.100)
7.10 Flyover at Kyatsandra Junction
7.11 Service Roads 1
8 PAVEMENT DESIGN 17
8.1 Flexible Pavement Design
8.1.1 Design Life 1
8.1.2 Traffic Loading
8.1.3 CBR of Existing Soil
8.2 Sub Grade Characteristics
8.2.1 New Carriageway and Alignment
8.2.2 Existing Pavements
8.3 Flexible Pavement Design
8.3.1 Flexible Pavement Design as per IRC : 37-2018
8.3.2 Rigid Pavement Design
9 DESIGN OF TRAFFIC CONTROL AND OTHER FACILITIES 1
9.1 Road Furniture 1
9.1.1 Road Signs 1
9.1.2 Road Markings 1
9.1.3 Road Delineators
9.1.4 Reflective Pavement Markers (Studs)
9.1.5 Over Head Sign Boards
9.1.6 Median Barriers 1
9.1.7 Reinforced Cement Concrete Crash Barrier
9.1.8 Kilometre Stones
9.1.9 200m Stones and Road Boundary Stones (RBS)
9.2 Pedestrian Facilities
9.2.1 Footpaths and Street lights
9.3 Lighting Arrangement
9.3.1 Street Lighting 1
9.4 Highway Patrol Unit
9.5 Emergency Medical Services
9.6 Crane Services 1
9.7 Advance Traffic Management System (ATMS)
9.7.1 Data acquisition system
9.8 Variable Message Signs (VMS)
9.9 Central Control Room
9.10 Operation and Maintenance
9.11 Toll Plazas 1
9.11.1 Location of Toll Plaza
9.11.2 Number of Toll Plaza and Toll Lanes
9.11.3 Layout of Toll Plaza
9.11.4 Land for Toll Plaza
9.11.5 Signage System
9.12 Truck Parking 1
9.13 Bus Shelters 1
9.14 Entry and Exit to Main Carriageway
9.14.1 T Begur exit in Nelamangala-Tumkur direction
9.14.2 T Begur Entry in Nelamangala-Tumkur direction
9.14.3 Dabaspet Exit in Nelamangala-Tumkur direction
9.14.4 Dabaspet Entry in Nelamangala-Tumkur direction
9.14.5 Exit to NH-206 in Nelamangala-Tumkur direction
9.14.6 Tumkur Entry (Nelamangala-Tumkur direction)
9.14.7 T Begur Entry in Tumkur- Nelamangala direction
9.14.8 T Begur Exit in Tumkur- Nelamangala direction
9.14.9 Dabaspet Entry in Tumkur-Nelamangala direction
9.14.10 Dabaspet Exit in Tumkur-Nelamangala direction
9.14.11 Tumkur Entry in Tumkur-Nelamangala direction
9.15 Rest Area 1
9.16 Road Intersection
9.16.1 Islands 1
9.16.2 At Grade Intersections
9.17 Median Openings
9.17.1 Width of Median in various stretches
9.18 Landscaping and Tree plantation
9.18.1 Plantation in Medians
9.18.2 Landscape Treatment
9.18.3 Highway Drainage
10 BRIDGES AND STRUCTURES 19
10.1 Improvement Proposals and New Proposals
11 SOCIO ECONOMIC PROFILE 20
11.1 The Area Profile
11.2 Analysis, Mitigation and Suggestions for Alternatives
11.3 Alternatives, Remedial Measures and Mitigation
11.4 Socio – economic benefits of the project.
11.5 Summary and Conclusion
12 ENVIRONMENT AND SOCIAL IMPACT ASSESSMENT 20
12.1 Objectives & Scope of the Project
12.2 Overview of Impacts due to the Project
12.3 Policy, Legal and Administrative Framework 21112.4 Baseline E
16.2 Proposed Alignment
16.3 Pavement Design
16.4 Proposed Structures
16.5 Proposed Facilities
16.6 Preliminary Cost Estimates
16.7 Financial Analysis
16.7.1 Sensitivity Analysis
16.7.2 Conclusions
Table 1.0 (a): Classified Traffic Volume Count Locations considered for Second Time in May-2012 1
LIST OF TABLES
Table 4.16: Present Average Traffic at VC-1 at Km 30.600 near Nelamangala Toll Plaza (Feb-2012 Survey) 7
Table 4.49: Details of the Pedestrian Crossing at Various Locations along NH-4 at various Locations 11
Table 6.6: Minimum recommended Sight Distances 154Table 6.7
Table 15.2: Construction Cost
Table 15.3: Concessionaire’s Cost
Table 15.4: Toll Rates
Table 15.5: Projected Toll Rates for the year 2021
Table 15.6: Base Year Traffic for the Project: Tollable Traffic
Table 15.7: Total Toll Revenue (in Crores)
Table 15.8: Maintenance Cost in Rs Million per Km
Table 15.9: Details of Minimum Viability Criteria
Table 15.10: Summary of Financial Analysis for Concession period of 30 Years
Table 15.11: Results of Sensitivity Analysis
Table 16.1: Proposed new carriageway thickness as per 15 year design period
Table 16.2: Proposed overlay thickness
Table 16.3: Proposed Service road thickness
Table 16.4: Proposed Rigid Pavement Thickness for Toll Plaza
Table 16.6: Cost of the project
Table 16.7: Summary of Financial Analysis for Concession period of 30 Years
Table 16.8: Results of Sensitivity Analysis
NATIONAL HIGHWAYS AUTHORITY OF INDIA
Near JMIT
(Ministry of Road Transport & Highways)
Campus, NH4 (Km 201) Chitradurga – 577 502
OF CONTENTS
ECUTIVE SUMMARY 14
Purpose of the Study 14
Scope of Work 14
Deliverables 15
Project Description 17
Traffic Study and Analysis 18
Engineering Survey and Investigations 20
Alignment and Engineering 21
Pavement Design 21
Design of Traffic Control and other facilities 22
Bridges and Structures 25
List of Retained Structures. 29
Environment and Social Impact Assessment 30
Land Acquisition and Utility Shifting 30
mprovement Proposals 30
Cost Estimates 31
Financial Analysis 32
Sensitivity Analysis 32
Conclusions 33
OJECT DESCRIPTION 34
General 34
Existing Road 34
Existing Junctions 36
Existing Bus Shelters & Truck Lay Bye 39
Land Use Pattern 40
Existing Structures 41
Pavement 45
Historical Traffic Data 45
Existing Utilities 46
THODOLOGY 47
Review of Data and Documents 47
Traffic Surveys 47
Engineering Surveys and Investigations 48
AFFIC STUDY AND ANALYSIS 60
Objective of the Present Study 60
Traffic Surveys 61
Classified Traffic Volume Count Survey 61
Classified Turning Traffic Count Survey 62
Pedestrian/Cattle Crossings Count Survey 62
Axle Load Survey 63
Origin & Destination Survey 63
4.8 Details of Second Time Traffic Survey for Mid Block Locations and Additional Intesection Survey
4.9 Details of Second Time Origin-Destination Survey 64
4.10 PCU Values Adopted 65
4.11 Traffic Data Analysis 65
4.12 Classified Turning Traffic Volume Count Survey 104
4.13 Pedestrian Movement Survey Details 111
4.14 Analysis of Axle Load Survey Data 111
4.15 Origin-Destination (O-D) Surveys 113
4.16 Second Origin-Destination (O-D) Surveys (during Dec-2019) 118
4.17 Existing Toll System Analysis 123
4.18 Seasonal Correction Factors 123
4.19 Comparaison of Survey Data of Feb-2012 and May-2012 125
4.20 Traffic Forecast 126
4.21 Capacity Analysis of Road Corridor based on Existing Condition and Future Projected Traffic131
4.22 MSA Calculations 133
4.23 Outcome of Traffic Survey & Analysis 137
5 ENGINEERING SURVEYS AND INVESTIGATIONS 140
5.1 Topographical Survey 140
5.2 Geotechnical Investigation Methodology of Field Work 141
5.3 Subgrade Investigation for Pavements 143
6 INDICATIVE DESIGN STANDARDS 148
6.1 Traffic Design 148
6.2 Pavement Design Consideration 150
6.3 Geometric Design Consideration for Highways 151
6.4 Classification of Roads 152
6.5 Terrain 152
6.6 Recommended Design Service Volumes 152
6.7 Design Speed 152
6.8 Cross-Section Elements 153
6.8.1 Right of Way (ROW) 153
6.8.2 Camber 153
6.8.3 Carriageway 153
6.8.4 Shoulder 153
6.8.5 Median 153
6.8.6 Sight Distance 154
6.9 Horizontal Curves 154
6.9.2 Super Elevation 155
6.9.3 Transition Curve 155
6.10 Vertical Alignment 156
6.10.1 Gradients 156
6.10.2 Vertical Curves 156
6.10.3 Vertical Clearance at Underpasses 156
6.10.4 Median Openings 156
6.11 Relevant Codes 156
6.12 Design of Bridges, Viaduct, Grade Separators and Railway over Bridges 157
6.13 Design of Box Culverts 159
7 ALIGNMENT AND ENGINEERING 164
7.1 Geometric Design 164
7.2 Existing Alignment 164
7.3 Horizontal Alignment 164
7.4 Design Standards 165
7.5 Proposed Design Standards 166
7.6 Proposed Alignment 166
7.7 Design Speed 167
7.8 Proposed Widening 171
7.9 Proposed Realignments 172
7.9.1 Realignment at T. Begur (km 34.800 to km 36.150) 172
7.9.2 Realignment after Dobbaspet, near ROB location (km 50.000 to km 51.500) 172
7.9.3 Realignment from ROB to Hirehalli Railway station (km 55.500 to km 57.800) 173
7.9.4 Realignment at ROB, After Kyatsandra (km 64.200-65.100) 173
7.10 Flyover at Kyatsandra Junction 173
7.11 Service Roads 173
8 PAVEMENT DESIGN 175
8.1 Flexible Pavement Design 175
8.1.1 Design Life 175
8.1.2 Traffic Loading 175
8.1.3 CBR of Existing Soil 176
8.2 Sub Grade Characteristics 176
8.2.1 New Carriageway and Alignment 176
8.2.2 Existing Pavements 177
8.3 Flexible Pavement Design 177
8.3.1 Flexible Pavement Design as per IRC : 37-2018 177
8.3.2 Rigid Pavement Design 178
9 DESIGN OF TRAFFIC CONTROL AND OTHER FACILITIES 180
9.1 Road Furniture 180
9.1.1 Road Signs 180
9.1.2 Road Markings 180
9.1.3 Road Delineators 181
9.1.4 Reflective Pavement Markers (Studs) 181
9.1.5 Over Head Sign Boards 181
9.1.6 Median Barriers 181
9.1.7 Reinforced Cement Concrete Crash Barrier 181
9.1.8 Kilometre Stones 182
9.1.9 200m Stones and Road Boundary Stones (RBS) 182
9.2 Pedestrian Facilities 182
9.2.1 Footpaths and Street lights 182
9.3 Lighting Arrangement 183
9.3.1 Street Lighting 183
9.4 Highway Patrol Unit 183
9.5 Emergency Medical Services 184
9.6 Crane Services 184
9.7 Advance Traffic Management System (ATMS) 184
9.7.1 Data acquisition system 185
9.8 Variable Message Signs (VMS) 185
9.9 Central Control Room 186
9.10 Operation and Maintenance 186
9.11 Toll Plazas 186
9.11.1 Location of Toll Plaza 187
9.11.2 Number of Toll Plaza and Toll Lanes 187
9.11.3 Layout of Toll Plaza 187
9.11.4 Land for Toll Plaza 187
9.11.5 Signage System 187
9.12 Truck Parking 188
9.13 Bus Shelters 188
9.14 Entry and Exit to Main Carriageway 189
9.14.1 T Begur exit in Nelamangala-Tumkur direction 189
9.14.2 T Begur Entry in Nelamangala-Tumkur direction 190
9.14.3 Dabaspet Exit in Nelamangala-Tumkur direction 190
9.14.4 Dabaspet Entry in Nelamangala-Tumkur direction 190
9.14.5 Exit to NH-206 in Nelamangala-Tumkur direction 190
9.14.6 Tumkur Entry (Nelamangala-Tumkur direction) 190
9.14.7 T Begur Entry in Tumkur- Nelamangala direction 190
9.14.8 T Begur Exit in Tumkur- Nelamangala direction 191
9.14.9 Dabaspet Entry in Tumkur-Nelamangala direction 191
9.14.10 Dabaspet Exit in Tumkur-Nelamangala direction 191
9.14.11 Tumkur Entry in Tumkur-Nelamangala direction 191
9.15 Rest Area 191
9.16 Road Intersection 191
9.16.1 Islands 191
9.16.2 At Grade Intersections 191
9.17 Median Openings 193
9.17.1 Width of Median in various stretches 194
9.18 Landscaping and Tree plantation 194
9.18.1 Plantation in Medians 194
9.18.2 Landscape Treatment 194
9.18.3 Highway Drainage 194
10 BRIDGES AND STRUCTURES 195
10.1 Improvement Proposals and New Proposals 196
11 SOCIO ECONOMIC PROFILE 203
11.1 The Area Profile 203
11.2 Analysis, Mitigation and Suggestions for Alternatives 204
11.3 Alternatives, Remedial Measures and Mitigation 206
11.4 Socio – economic benefits of the project. 207
11.5 Summary and Conclusion 208
12 ENVIRONMENT AND SOCIAL IMPACT ASSESSMENT 209
12.1 Objectives & Scope of the Project 209
12.2 Overview of Impacts due to the Project 210
12.3 Policy, Legal and Administrative Framework 21112.4 Baseline Environment of the Region
16.2 Proposed Alignment 240
16.3 Pavement Design 240
16.4 Proposed Structures 241
16.5 Proposed Facilities 242
16.6 Preliminary Cost Estimates 242
16.7 Financial Analysis 242
16.7.1 Sensitivity Analysis 242
16.7.2 Conclusions 243
Table 1.0 (a): Classified Traffic Volume Count Locations considered for Second Time in May-2012 18Table 1.0 (b): Details of
LIST OF TABLES
Table 4.16: Present Average Traffic at VC-1 at Km 30.600 near Nelamangala Toll Plaza (Feb-2012 Survey) 71Table 4.17: Present Ave
Table 4.49: Details of the Pedestrian Crossing at Various Locations along NH-4 at various Locations 111Table 4.50: Summary of
Table 6.6: Minimum recommended Sight Distances 154Table 6.7: Minimum Radii of Hor
Table 15.2: Construction Cost 234
Table 15.3: Concessionaire’s Cost 234
Table 15.4: Toll Rates 235
Table 15.5: Projected Toll Rates for the year 2021 236
Table 15.6: Base Year Traffic for the Project: Tollable Traffic 236
Table 15.7: Total Toll Revenue (in Crores) 237
Table 15.8: Maintenance Cost in Rs Million per Km 238
Table 15.9: Details of Minimum Viability Criteria 238
Table 15.10: Summary of Financial Analysis for Concession period of 30 Years 239
Table 15.11: Results of Sensitivity Analysis 239
Table 16.1: Proposed new carriageway thickness as per 15 year design period 240
Table 16.2: Proposed overlay thickness 240
Table 16.3: Proposed Service road thickness 241
Table 16.4: Proposed Rigid Pavement Thickness for Toll Plaza 241
Table 16.6: Cost of the project 242
Table 16.7: Summary of Financial Analysis for Concession period of 30 Years 242
Table 16.8: Results of Sensitivity Analysis 242
0
22
30
0
1
2
2
nd Additional Intesection Survey 64
64
65
65
104
111
111
113
118
123
123
125
126
and Future Projected Traffic131
133
137
140
140
141
143
148
148
150
151
152
152
152
152
153
153
153
153
153
153
154
154
155
155
156
156
156
156
156
156
Bridges 157
159
164
164
164
164
165
166
166
167
171
172
172
km 51.500) 172
o km 57.800) 173
173
173
173
175
175
175
175
176
176
176
177
177
177
178
180
180
180
180
181
181
181
181
181
182
182
182
182
183
183
183
184
184
184
185
185
186
186
186
187
187
187
187
187
188
188
189
189
190
190
190
190
190
190
191
191
191
191
191
191
191
191
193
194
194
194
194
194
195
196
203
203
204
206
207
208
209
209
210
112.4 Baseline Environment of the Region 21212.5 Environmental and Social Screening
240
240
241
242
242
242
242
243
012 18Table 1.0 (b): Details of Volume of Traffic for Tollable Vehicle Type 19Table 1.1: Adopted VD
12 Survey) 71Table 4.17: Present Average Traffic at VC-1 at Km 30.600 near Nelamangala Toll Plaza (May-2012 Survey) 72Table 4.18: Prese
ions 111Table 4.50: Summary of Vehicle Damage Factors for Each Vehicle at Km 30.600 near Nelamangala Toll Plaza on NH-4
154Table 6.7: Minimum Radii of Horizontal Curves 155Table 6.8: Radius beyond which Super
234
234
235
236
236
237
238
238
239
239
240
240
241
241
242
242
242
ABBREVATIONS
% Percentage
& And
@ At
% Percentage
& And
< Less than
> Greater than
BB-1 Bus Bye
BOQ Bill of Quantities
DBFOT Design, Build, Finance, Operate and Trans
GAD General Arrangement Drawings
H Horizontal
IRC Indian Road Congress
km Kilometer
kmph Kilometer per hour
LA Land Acquisition
LOS Level Of Service
Ltd. Limited
m Meter
MNB Minor Bridge
NH National Highway
NHAI
P-1
PCU Passenger Car Unit
Pvt. Private
RCC Reinforced cement concrete
ROB Road Over Bridge
RUB Road Under Bridge
SH State Highway
Sl. No. Serial number
TL-1 Truck Lay Bye
TOR Terms of Reference
TP-1 Toll Plaza
V Vertical
v Vent
WA-1 Wayside Amenities
ABBREVATIONS
Percentage
And
At
Percentage
And
Less than
Greater than
Bus Bye
Bill of Quantities
T Design, Build, Finance, Operate and Transfer
General Arrangement Drawings
Horizontal
Indian Road Congress
Kilometer
Kilometer per hour
Land Acquisition
Level Of Service
Limited
Meter
Minor Bridge
National Highway
following:
avoiding land acquisition, except for locations
es, service roads, alignment corrections,
ators etc. are required land acquisition to the
t cross sections
gement Plan, Rehabilitation and
mber 2011.
12.
1 March 2012.
ubmitted on 30 March 2012.
mitted on 10 April 2012
13
d report incorporating the changes suggested
tly discussed and finalized during the
ore.
0 Nov 2013.
eport (Addendum-1), comments were
U-CTA/ 6-Laning/ Secon/ 2014-15/06/370
251 dated 16 Jul 2014 regarding further
ures.
submitted on 30 Jan 2019.
ew Delhi on 13 Feb 2019 and following points
Count Existing No of
No. Chainage Location Days
(km)
VC-1 30.60 After Nelamangala Toll Plaza 7
VC-4 61.00 Before Toll Plaza near Manchakalkuppe 7
VC-7 74.00 Before End Point i.e. at the end of Tumkur NH-4 Bypass 7
Tollable vehicles are Four Wheeler (Both White Board & Yellow Board), L
Buses
and Goods Vehicles (2-Axle, 3-Axle & MAV). Details of the Volume of Traf
Vehicle
Type are presented in Table 1.0 (b) below.
Table 1.0 (b): Details of Volume of Traffic for Tollable Vehicle Type
of 10.5 m on either side from km 61.200 to km
s
ns
3326
732
768
815
143
977
724
3539
4007
1404
3
vey at two major junctions has been carried out.
e the findings based on the peak hour traffic
Sl. Pavement
No Type of Construction Composition (mm)
BC DBM Total
1 Overlay 50 110 160
Service Road Pavement Thickness
The expected traffic on the service road is negligible, to provide better acc
road traffic and the built up areas, the service road is designed for 10 msa
2019 and CBR of 8% are adopted and the following pavement thickness
below.
Table 1.4: Pavement Thickness for Service Road
Sl. Pavement
No Type of Construction Composition (mm)
BC DBM Total
1 Overlay 50 110 160
1.9 Design of Traffic Control and other facilities
Traffic control devices comprise of Intersections, Interchanges, Roundabouts, Channe
Islands. Intersections are of two types - At Grade Intersection and Grade Separated In
intersections of the following types have been designed wherever required as per IRC
Minor T – Intersection
Major T- Intersection
Staggered Intersection
4 – Legged Major Intersection
4-Legged minor intersection
The list of Major and Minor Intersections are given in Table 1.6 and Table 1.7 below.
Table 1.6: List of Major Intersections
Cross Road
To Shivaganga (L)
To Dabaspete (R)
To Nijagal (R)
To Siddaganga Matt
(R) To Kyatasandra (L)
To Arakere (R) To
Tumakuru (L)
Toll Plaza
A single Toll plaza has been proposed as per the decision taken in the me
RO on 10 & 11 Jan 2019. The existingToll Plaza at km 30.010 (At the star
Highway) is to be dismantled and at km 61.478 (After Manchakalkuppe
constructed as per the traffic consideration along the project road. Twel
been proposed in each direction (total 28 lanes) at the proposed toll plaza
all other buildings and structures to be accommodated at the Toll plaza loc
Bus Shelters and Truck Parking
Bus shelters and Truck parking are proposed at the following locations as
1.9
Table 1.8: Proposed Locations of Bus shelters along Project Highway
oject Highway
roject Highway
Reconstruction
Reconstruction
Reconstruction
rs
Right
SR
11.75
11.75
-
Below
Existing
Flyover
-
11.75
11.75
11.75
11.75
11.75
11.75
11.75
11.75
11.75
11.75
itation as the bridge comes under existing
Remarks, if any
Sl. Design Proposed Type Proposed Span Arrangement Total Width of Structure
No. Chainage (km) of Structure (No. X Hor. (No. X Hor. (m)
(m) X Ver (m)
1 33.350 VOP 2 X 22.7 X 5.5 1 X 12
2 35.765 VOP 2 X 22.7X 5.5 1 X 12
3 37.300 VOP 2 X 22.7X 5.5 1 X 12
4 48.100 VOP 2 X 22.7X 5.5 2 X 15.1
5 59.445 VOP 2 X 22.7X 5.5 1 X 12
Vehicular Under Pass/Light Vehicular Under Pass
Sl. Design Proposed Type Proposed Span Total Width of
No. Chainage (km) of Structure Arrangement (No. X Hor. Structure (No. X Hor.
(m) X Ver (m)
(m))
1 30.600 VUP 1 x 15 x5.5 2 X 16
2 32.100 VUP 1 x 15 x 5.5 2 X 16
3 39.200 LVUP 1 x 12 x 4.5 2 X 16
4 40.755 LVUP 1 x 12 x 4.5 2 X 16
5 43.055 VUP 1 x 20 x 5.5 2 X 16
6 43.400 LVUP 1 x 12 x 4.5 2 X 16
7 45.750 LVUP 1 x 12 x 4.5 2 X 16
8 55.160 VUP 1 x 15 x 5.5 2 X 16
9 57.600 LVUP 1 x 12 x 4.5 2 X 16
10 60.760 LVUP 1 x 12 x 4.5 2 X 16
11 64.535 VUP 1 X 25 X 5.5 1 X 12.5
12 64.825 VUP 1 X 25 X 5.5 1 X 12.5
13 73.800 LVUP 2 x 12 x 4.5 2 X 13.5
Table 1.13: List of Road Over Bridges
New ROB/ 3-lane New ROB is Proposed Right Side of the Existing ROBs.
Sl. Design Proposed span Total width of the
No. Chainage Type of Structure arrangement (No. structure
(km) X Span, m) (No. X Horizontal, m)
1 50.285 Composite Bow String Girder 2 x 72 2 x 12.5
2 55.940 Composite Bow String Girder 2 x 72 2 x 12.5
3 64.650 Composite Bow String Girder 2 x 72 2 x 12.5
Table 1.14: Proposal for Box Culverts and Pipe Culverts.
Design Span /
S. No. Chainage Opening (m) Proposal Remarks, if any
(Km)
1 29.495 1x2x2 Reconstruction Box
2 29.778 1x3x2 Reconstruction Box
3 30.18 1x2x2 Reconstruction Box
4 30.549 1x6x2 Reconstruction Box VUP Approach
5 31.496 1x3x2 Reconstruction Box VUP Approach
6 32.309 1x2x2 Reconstruction Box VUP Approach
7 32.4 1x4m New Construction Box
8 34.378 1 x 1.5 m Widening Box
9 34.955 1x2m Reconstruction Box Existing dia < 0.9 m
10 35.086 1x2m Reconstruction Box Approach
11 35.15 1x3m Reconstruction Box Approach
12 36.56 1x2x2.5 New Construction Box
13 38.137 1x4m Reconstruction Box VOP approach end
14 39.206 1x3x2 Reconstruction Box LVUP Approach
15 41.878 1x2x2 Reconstruction Box
16 43.201 1x2x2 Reconstruction Box LVUP Approach
17 43.341 1x2 Reconstruction Box LVUP Approach
18 44.254 2 x1.0m dia Widening Pipe
19 45.74 1x6x2 Reconstruction Box LVUP Approach
20 46.74 1x4m Reconstruction Box Flyover Approach
21 47.511 1x2x2 Reconstruction Box
22 47.62 1x2x2.5 New Construction Box
23 49.711 3 x 1 dia Retained Pipe
24 49.771 2 x 1 dia Retained Pipe
25 50.121 3 x 1.2 dia Retained Pipe
26 51.248 1x4m Widening Box
27 51.682 1x6x2 Reconstruction Box Existing dia < 0.9 m
28 51.862 1x4x2 Reconstruction Box
29 52.33 1x3m Reconstruction Box Flyover Approach
30 52.728 1x6x2 Reconstruction Box Flyover Approach
31 52.763 1x2x2 Reconstruction Box Existing dia < 0.9 m
32 53.506 1 x 1.5 m Widening Box
33 53.892 1 x 1.1 m Widening Box
34 54.397 1x5 Reconstruction Box
35 54.432 2x3m Reconstruction Box Choked, distressd
36 54.862 1 x 1.8 m Reconstruction Box VUP approach
37 55.022 1 x 2.0 m Reconstruction Box VUP approach
38 55.215 1 x 3.0 m Reconstruction Box VUP approach
39 55.573 1x2x2 Reconstruction Box
40 56.47 1x6x2 Reconstruction Box
41 56.78 1x3x2 Reconstruction Box
42 57.261 1 x 3.0 m Reconstruction Box LVUP approach
43 57.32 1x6x2 Reconstruction Box LVUP approach
44 57.8 1x2x2 Reconstruction Box LVUP approach
45 57.98 1x3x2 Reconstruction Box LVUP approach
46 58.46 1x4x2 Reconstruction Box
47 58.48 1x2x2 Reconstruction Box Existing dia < 0.9 m
50 59.87 1x3m Reconstruction Box VOP approach
51 59.93 1x3m Reconstruction Box VOP approach
52 60.35 1x2x2 Reconstruction Box VUP approach
53 60.882 1x2x2 Reconstruction Box VUP approach
54 61.385 1 x 1 m dia Retained Pipe
55 62.032 1 x1.2m dia, Widening Pipe
56 62.279 1 x 6.5 m Widening Box
57 62.482 1 x 1.2m dia Widening Pipe Retained VUP approach
58 62.753 1 x 1.2m dia Widening Pipe Retained VUP approach
59 63.167 3 x1.2m dia Widening Pipe
60 64.099 1x6x2 Reconstruction Box Flyover approach
61 65.031 2 x 0.9m dia Widening Pipe
62 68.09 1 x 1m dia Widening Pipe
63 68.121 1 x 1m dia Widening Pipe
64 68.997 3 x 1.2m dia Widening Pipe
65 69.07 1 x 1m dia Widening Pipe
66 70.373 1 x 1m dia Widening Pipe
67 70.389 1 x 1m Widening Pipe
dia, 54.0m
68 70.811 1 x 0.9m dia Widening Pipe
69 71.464 2 x 0.9m dia Widening Pipe
70 71.519 1 x 0.9m dia Widening Pipe
71 72.584 3 x 1m dia Widening Pipe
72 73.536 1x2x2 Reconstruction Box LVUP approach
73 73.658 1 x 3.6 Reconstruction Box LVUP approach
lar Over Pass
.
Table 1.15: List of Proposed Flyovers
Sl. Chainage (km) Length Span Arrangement Remark/Town
No. (m) (No. X Span, m) Name
From To
1 46.980 47.020 20 2 x 20 x 5.5 -
2 52.660 52.700 20 2 x 20 x 5.5 -
3 63.545 63.975 430 13 x 30 + 1 x 40 -
1.11 List of Retained Structures.
Table 1.16: List of Flyovers/GradeSeparators Retained.
Remarks
VUP
Pedestrian Subway
Pedestrian Subway
Pedestrian Subway
VUP
Pedestrian Subway
VUP
Pedestrian Subway
Non Vehicular Underpass
VUP
11 65.062 RCC Solid Slab 1 x 23.80 2 x 12.5
12 67.157 RCC Solid Slab 1 x 13.50 2 x 13.5
13 68.271 RCC Solid Slab 1 x 21.00 2 x 12.5
14 70.137 RCC Solid Slab 1 x 13.60 2 x 13.50
15 71.711 RCC Solid Slab 1 x 22.80 2 x 13.5
1.12 Environment and Social Impact Assessment
The project road under consideration requires land acquisition at locations of realignm
locations of facilities and at few widening portions. However the proposed widening inv
demolition of buildings which include petty shops. Due to the proposed alignment few r
mainly small temples, need to be relocated. Further the project road under consideratio
through any reserve forest area. Hence the project area under consideration is n
adverse social impacts.
Concerned by the seriousness of continuing pollution, the Ministry of Environme
issued an Environment Impact Assessment (EIA) Notification on 14th September, 2006
amendments on 1st December 2009 under which highway projects like new national h
expansion of National Highways greater than 30 km involving additional right of way gr
involving land acquisition and passing through more than one State fall under the purv
Clearance process through submission of an EIA Report.
1.13 Land Acquisition and Utility Shifting
The existing road has been aligned in 43 villages in the Districts of Bangalore Rural an
The present road is proposed to be widened to six lane with service road for the entire
60m of ROW should be available for the development of 6 lane highway. Land acquisi
has been proposed in order to facilitate fast construction. Total of
58.49 ha of land is to be acquired at 43 villages for proposed improvements such as pr
realignments, Proposed Toll Plazas, Widening locations. It is proposed to shift the utilit
space for utility location or other location close to the proposed ROW in consultation w
concerned authorities. All other utilities which are within the existing ROW but not affec
proposed improvements need not be shifted.
1.14 Improvement Proposals
The various improvement proposals suggested are as follows:
Widening of existing 4 lane road with the following:
Six lane of 10.5 m wide carriageway with 3.5 m paved shoulders, 1.5m RCC Drain bet
carriage way and service Road, 7.0 m service road with 1.5m paved shoulders and sp
logitudnal drain on either side.
Service road on both sides of main carriageway except in forest Section on Right
Existing 6 lane road configuration after km 61.478 (Toll Plaza 2) is retainted as it is
proposal to new service road along Tumkur Bypass stretch where it is absent and new
utility are provided throughout the bypass utilising the existing drains as utility duct.
Improvements to Horizontal Alignment and Longitudinal Profile
2 PROJECT DESCRIPTION
2.1 General
The existing ROW along the project road is found to be not uniform a
IRC Recommendations. However, for improvement of junctions, reloc
widening etc, design has been as per functional requirement. Additio
has been proposed to achieve minimum 60m ROW.
The alignment passes through Major villages and towns like Tonachi
Dodderi, Kuluvanahalli, Dobbaspet, Hirehalli, Kyatsandra etc. It c
Administrative Jurisdiction of Bangalore Rural and Tumkur District.
The details of existing carriageway, median and shoulder widths are
Detailed road inventory is enclosed as Annexure 2.01 and a complete r
Pavement Condition Survey regarding the existing pavement compos
Annexure 2.02.
Table 2.1: Existing Carriageway Widths & Shoulders
VUP
Non Vehicular Underpass
VUP
Non Vehicular Underpass
VUP
ssment
equires land acquisition at locations of realignments, at the proposed
ng portions. However the proposed widening involves minimal
etty shops. Due to the proposed alignment few religious structures,
ated. Further the project road under consideration does not pass
nce the project area under consideration is not having any serious
way traverse through plain terrain. The entire stretch of the project
uminous surface. The existing alignment is divided carriageway
1.5 m on either side of the road from existing km
arriageway width on either side from km 61.200 to km 74.168. The
tion as well as structural condition is good. A fair assessment
nt and the overlay requirements are evaluated.
gnment is designed by considering all the aspect of safety,
ocial issue. For the proposed alignment, the carriageway of 10.5m,
service road of 7m on either side have been provided for the stretch
ting 6 lane road is maintained with the addition of drainage and
here.
riculture fields on both sides of the road. The land use on either side
rial areas with some open lands near settlements where it is
shops, etc,) Apart from regular settlements/village limits,
ved along the project road.
h Industrial Areas such as Sompura Industrial Area which is located
li Industrial Area, which is located at chainage 59.400 km on a
ong the project road is found to be not uniform and is less than the
ns. However, for improvement of junctions, relocation, realignment
has been as per functional requirement. Additional land acquisition
o achieve minimum 60m ROW.
s through Major villages and towns like Tonachinakuppe, T. Begur,
li, Dobbaspet, Hirehalli, Kyatsandra etc. It comes under the
ction of Bangalore Rural and Tumkur District.
g carriageway, median and shoulder widths are given in Table 2.1.
ry is enclosed as Annexure 2.01 and a complete record of the
Survey regarding the existing pavement composition is attached as
Intersectio n
Chainage
Existing
Road Type
Width (m)
Pavement
(Km)
Side
Remarks
Sl. No.
Type
Type
1 48.900 SH-3 14.75 BT Left Y-Type Existing Flyover, Junction
Improvement at Grade
2 49.200 NH-207 11.40 BT Right 3 legged Existing Flyover, Junction
SH-3 8.40 Improvement at Grade
3 63.690 SH-94 6.18 BT Left 4 legged Fly over proposed
13.10 Right
4 71.420 SH-33 10.50 BT Left 4 legged Existing VUP, Junction
10.50 Right Improvement at Grade
or junctions as in Table 2.2 & Table 2.3
Table 2.3: Existing Minor Junctions
Chainage
Intersecti
Road Type
Pavemen t
Existing
Type of
Proposed
Width (m)
Remarks
Junction
(Km)
Type of
on
Sl. No.
Type
Side
1 29500 VR 8.43 BT RHS Y junction Y junction At grade
intersection
2 30000 VR 5.77 BT proposed
RHS Y junction Y junction At grade
intersection
3 30400 VR 3.00 BT proposed
LHS Y junction Y junction At grade
intersection
4 31000 VR 3.50 BT LHS Y junction Y junction proposed
At grade
intersection
5 31600 VR 3.80 BT proposed
RHS Y junction Y junction At grade
intersection
6 32500 VR 3.90 BT proposed
RHS T Junction T Junction At grade
intersection
7 33920 VR 3.90 BT LHS T Junction T Junction proposed
At grade
intersection
8 35200 VR 3.00 BT LHS T Junction T Junction proposed
Realignment
Proposed
9 35650 MDR 7.00 BT RHS T Junction T Junction At grade
intersection
10 37250 VR 3.00 BT LHS T Junction T Junction proposed
At grade
intersection
11 37900 VR 3.50 Mud proposed
LHS Y junction Y junction At grade
Road intersection
12 38516 VR 3.50 BT proposed
LHS Y junction Y junction At grade
intersection
13 38516 VR 3.50 BT RHS T Junction T Junction proposed
At grade
intersection
14 39400 VR 3.90 Mud proposed
RHS Y junction Y junction At grade
Road intersection
15 40700 VR 3.00 BT proposed
LHS T Junction T Junction At grade
intersection
16 40700 VR 3.30 BT RHS T Junction T Junction proposed
At grade
intersection
17 41350 VR 4.50 BT proposed
LHS T Junction T Junction At grade
intersection
18 42660 VR 5.50 Mud RHS T Junction T Junction proposed
At grade
Road intersection
19 43000 VR 3.90 Mud LHS T Junction T Junction proposed
At grade
Road intersection
20 43000 VR 3.90 BT proposed
RHS T Junction T Junction At grade
intersection
21 43400 VR 4.00 BT RHS T Junction T Junction proposed
At grade
intersection
22 43400 VR 5.00 Mud LHS T Junction T Junction proposed
At grade
Road intersection
proposed
23 44480 VR 5.20 BT RHS T Junction T Junction At grade
intersection
24 44480 VR 4.00 Meta proposed
LHS T Junction T Junction At grade
l intersection
25 45580 VR 4.50 Road
Mud proposed
RHS T Junction T Junction At grade
Road intersection
26 46100 VR 3.50 Mud LHS Y junction Y junction proposed
At grade
Road intersection
27 46200 VR 5.00 BT proposed
LHS T Junction T Junction At grade
intersection
28 46550 VR 5.50 Mud proposed
LHS Y junction Y junction At grade
Road intersection
29 47000 VR 5.00 Mud RHS Y junction Y junction proposed
At grade
Road intersection
30 47685 - 5.5+5.5 BT proposed
RHS T Junction T Junction At grade
intersection
31 48200 VR 2.50 Mud proposed
LHS T Junction T Junction At grade
Road intersection
32 49320 VR 5.50 BT LHS Y junction Y junction proposed
At grade
intersection
33 49950 VR 4.30 BT proposed
LHS T Junction T Junction At grade
intersection
34 51207 VR 4.00 Mud proposed
RHS T Junction T Junction At grade
Road intersection
35 52032 VR 4.00 Mud RHS T Junction T Junction proposed
At grade
Road intersection
36 52670 VR 3.30 Mud proposed
RHS T Junction T Junction At grade
Road intersection
37 54300 VR 7.00 Mud proposed
LHS T Junction T Junction At grade
Road intersection
38 55310 VR 4.50 Mud RHS T Junction T Junction proposed
At grade
Road intersection
39 56500 VR 4.50 BT proposed
RHS Y junction Y junction At grade
intersection
40 56825 VR 4.00 BT RHS T Junction T Junction proposed
At grade
intersection
41 58100 VR 5.50 Mud LHS T Junction T Junction proposed
At grade
Road intersection
42 58230 VR 5.00 Mud proposed
RHS T Junction T Junction At grade
Road intersection
43 59035 - 5.50 BT LHS Y junction Y junction proposed
At grade
intersection
44 59363 VR 6.50 BT LHS T Junction T Junction proposed
At grade
intersection
45 59363 VR 4.00 BT proposed
RHS T Junction T Junction At grade
intersection
46 59875 - 4.60 BT LHS T Junction T Junction proposed
At grade
intersection
47 60400 VR 3.50 BT LHS T Junction T Junction proposed
At grade
intersection
proposed
48 60400 VR 3.50 BT RHS T Junction T Junction At grade
intersection
49 61350 VR 3.50 BT proposed
LHS T Junction T Junction At grade
intersection
proposed
50 62950 VR 5.20 BT RHS T Junction T Junction At grade
intersection
51 63900 - 5.50 BT LHS Y junction Y junction proposed
At grade
intersection
52 65300 VR 3.50 BT RHS Y junction Y junction proposed
At grade
intersection
53 65890 VR 3.30 BT proposed
RHS Y Junction Y Junction At grade
intersection
54 69000 VR 3.00 BT RHS T Junction T Junction proposed
At grade
intersection
55 72400 VR 5.00 BT RHS T Junction T Junction proposed
At grade
intersection
56 72600 VR 5.80 BT proposed
LHS T Junction T Junction At grade
intersection
57 73730 VR 14.50 BT RHS T Junction T Junction proposed
At grade
intersection
proposed
Location
To Nelamangala
At Kulimepalya
(TP 1)
To
Happegowdanapalya
To Bommanahalli
To Ueranangeepura
To Boodihal
To
Chamundeshwari
Nagar
At T. Begur
To Thyamagondlu
To Badayapa Halli
To Thippagondana
Halli
Talakere
To Dodderi
To Dodderi
To Timsandra
To Thyamagondlu
To Mahimapura
To Thyamagondlu
To Kerekathiganur
& Shivaganga
To Hanumanthapura
To Gundenahalli
To Aladahalli
To Thyamagondlu
To Village
To Hosahalli
To Kengal Kempahalli
To Avverahalli &
Gottigere
To K G Srinivasapura
To Bharathipura
To Sompura
Industrial Area
To Village
To Devara Hosahalli
To Village
To
Muddanayakanaha
lliTo Hosanijagal
To Rayanapalya
To Hale Nijagal
To Nandihalli
To Devarahalli
To Chikkahalli
To Kodihalli
To Vrdigere
To Factories
To Singanahalli
Colony
To Urdigere
To Factories
To Village
To Village
To Machanahalli
To Mydala
To Kyatsandra Town
To APMC Yard,
Tumkur City
To Devarayapattana
To Vaddarahalli
To Industrial Area,
Tumkur
*The left and Right direction are given based on the increasing chainage from Nelamangala to Tumkur
2.4 Existing Bus Shelters & Truck Lay Bye
Bus Shelters and Truck Lay Bye exist along the project road in Built-up areas at th
as given in Table 2.4 and 2.5.
Table 2.4: Existing Bus Shelters
m on either side and from 61.478 to 74.168 (At Existing 75 KM Stone) is 3 lane o
th
either side. There is an existing flyover with 3 lane carriage way. Necessary rehab
such as cleaning of expansion joint, cleaning of drainage spout are
proposed for the improvement.
Vehicular Underpass
1 34.230 RCC Solid Slab 1 x 10.00 x 5.10 13.50 13.50
2 44.256 RCC Solid Slab 1 x 10.00 x 5.00 13.60 13.60
3 55.927 RCC Box 1 x 04.00 x 5.00 14.60 14.60
4 64.763 RCC Solid Slab 1 x 25.90 x 5.50 12.80 12.80
5 65.062 RCC Solid Slab 1 x 23.80 x 5.50 12.50 12.50
6 68.271 RCC Solid Slab 1 x 21.00 x 4.50 12.50 12.50
7 71.711 RCC Solid Slab 1 x 22.80 x 5.00 13.50 13.50
Non Vehicular Underpass
8 63.405 RCC Solid Slab 1 x 12.00 x 2.50 12.80 12.80
9 67.157 RCC Solid Slab 1 x 13.50 x 3.00 13.10 13.10
10 70.137 RCC Solid Slab 1 x 13.60 x 3.50 13.50 13.50
Grade Separators
11 62.800 RCC Solid Slab 1 x 22.90 x 5.00 12.70 12.70
12 66.331 PSC Box Girder 1 x 41.60 x 5.30 12.50 12.50
13 73.221 PSC Box Girder 1 x 41.70 x 5.00 13.50 13.50
*The left and right direction are given based on the increasing chainage from Nelamangala t
Table 2.11: List of Pedestrian Subway
Sl. Existing Existing Details
No Chainage Type of Span arrangement (m) Carriageway Width
(km) Super- (m)
structure
Sl. Existing
No Chainage Type of Span arrangement (m)
(km) Super-
structure Left* Right
1 35.320 RCC Box 1 x 4.00 x 3.00 7.50 -
2 39.350 RCC Box 1 x 4.00 x 3.00 7.50 7.50
3 40.710 RCC Box 1 x 4.00 x 3.00 7.50 7.50
4 46.150 RCC Box 1 x 4.00 x 3.00 7.50 7.50
5 57.650 RCC Box 1 x 4.00 x 3.00 7.50 7.50
*The left and right direction are given based on the increasing chainage from Nelamangala t
Table 2.12: List of Box and Slab Culvert
ing chainage from Nelamangala to Tumkur
Traffic
N Volume at TP1, Km 29.50 Traffic Volume at TP2, Km 62.00
H
Vehicle Type May 2006 May 2007 May 2008 May 2006 May 2007 May 2008
-
Two Wheelers 5750
4 6173 5120 3680 5515 4895
Auto Rickshaw 1047 1388 2553 1009 1264 1120
Car/ Van 4240 6628 5924 3161 5358 5542
omposed of bituminous surfacing on top of
ers and Granular Sub base layers for the entire
Monumenting
All high precision, GPS, levelling and traverse control stations has be
pre-cast cement concrete pillars on rock insitu.
Some GPS control and permanent bench marks have also been loca
and proven structures to avoid settlement errors that may occur on n
pillars.
Topographical detail survey within the land width
Topographical strip survey has been based on the primary and tertiar
existing topographical surface terrain features, water bodies, trees, b
buildings, places of burial and worship, road wifdth and structures, ut
telephone lines, foreign pipelines is being surveyed and shown.
Topographical survey has been extended to 40 m on either side of ex
building line, whichever is less. Surveyed area has been extended to
encroachment and where existing alignment requires change. Survey
minimum 100 m on either side for road crossings.
Existing road has several features, both topographical and cultu
surface features has been physically surveyed and shown. Addit
regarding cultural features for building, structures, monuments, place
worship, rail, river, canal and pipeline crossings, tree plantations, pow
cables, etc., has been collected and shown both on the Base Map, as
form, depending availability of space.
Longitudinal levels along road centre line at 25 m interval, at curve po
crossing locations and at all definable points where there is change in
recorded. Cross- section levels at every 50 m interval up to the full s
land have also been recorded for deciding the vertical alignment and
earthwork.
Longitudinal and cross-sections for stream crossings has been e
and downstream, as per IRC Specifications for calculating scouring d
hydraulic details. High Flood Level in the area has been recorded by
enquiries and connecting level lines to visible high flood marks.
Computerization
It is desirable to integrate the survey and investigation data with othe
features. A common data bank with all the topographical survey deta
junctions, land width, ownership details and other inventories is n
retrieval, updating and maintenance of data, as and when required.
Longitudinal and cross-sections for stream crossings has been e
and downstream, as per IRC Specifications for calculating scouring d
hydraulic details. High Flood Level in the area has been recorded by
enquiries and connecting level lines to visible high flood marks.
Computerization
It is desirable to integrate the survey and investigation data with othe
features. A common data bank with all the topographical survey deta
junctions, land width, ownership details and other inventories is n
retrieval, updating and maintenance of data, as and when required.
Therefore computerization has been commenced right from data acq
Station offers complete solution for topographical survey details. The
Total Station can be downloaded to interface with desired software.
has been done with the
help of field book and a Base Map prepared.
and CS
he land width
ight Control
nd breadth of the country with work being
cies. It is therefore desirable that the entire
onnected to the national grid and GTS control.
f planimetric control between GPS stations and
ing rock insitu or permanent structures along the
he land width
sed on the primary and tertiary control points. All
atures, water bodies, trees, built-up areas, huts,
road wifdth and structures, utilities, power and
ng surveyed and shown.
ed to 40 m on either side of existing centre line or
ed area has been extended to include
ment requires change. Survey has been extended
crossings.
oth topographical and cultural. Topographical
surveyed and shown. Additional information
structures, monuments, places of burial and
rossings, tree plantations, power and telephone
own both on the Base Map, as well as in tabular
ion)
ture.
dition information and suggestions to enable
abilitation or replacement of the intended structure.
lyzed and used for assessing the type of
and Structures
ation has been carried out to assess the condition
adation and deterioration of the structures
, exposure of reinforcement, spalling/leaching of
nd deterioration of foot path slabs, handrails,
were noted.
nd the same have been charted out in the format.
as noted and local enquiries were carried out to
tc.
s
ey carried out by experts, the adequacy or
refully studied and necessary data obtained from
esktop studies were carried out to ascertain the
ning
en followed for such studies. The social analysis
rofile of the project influence area and poverty
dustry, agriculture, unemployment, health,
ent, etc. Social impact screening studies included
ssment (SIA).
ent categories of people with different cultural and
e affected due to the project. The purpose of
and maximize benefits for poor and vulnerable
income communities and concentration of tribal
o assure for the right measures to be taken in case
gth
168
feasible proposals, detailed traffic studies need to
his chapter deals with the details of the various
data analysis includes the traffic level,
ly variations, travel characteristics of the vehicles
hicles etc. In case of junctions, the flow of traffic in
les etc will be analysed. All these factors warrants
and analyzed.
socio-economic variables that drive demand for
various improvements
ad intersections
t on the project road
weight of commodities carried by trucks
hicle damage factor of different types of
ock Locations
unt Survey at Junctions
Count Existing No of
No. Chainage Location Days
(km)
VC-1 30.60 After Nelamangala Toll Plaza 7
VC-2 49.50 At NH-207 Junction, Dobbaspet on NH-207 (Mid Block) 1
VC-3 49.50 At SH-3 Junction, Dobbaspet on SH-03 (Mid Block) 1
VC-4 61.00 Before Toll Plaza near Manchakalkuppe 7
VC-5 63.00 Before Tumkur, Bypass Road to Gubbi or Honnavar 1
VC-6 66.00 At Batavadi Junction 1
VC-7 74.00 Before End Point i.e. at the end of Tumkur NH-4 Bypass 7
4.4 Classified Turning Traffic Count Survey
Based on the present traffic movement between Nelamangala to Tumkur Bypass
mentioned above, the road section passes through many important built-up
Dabbaspet, Kyatasandra etc. Presently, there is Flyover at Dobbaspete for the Ju
NH-207 with NH-4. However, before this junction due to establishment of D
Area a road leads to this industrial area at Km 47.600 where considerable movem
been observed. Hence this location has been chosen for intersection volume coun
at Kyatsandra junction where two cross roads are meeting with NH-4 which is loc
main built up area starts for Tumkur City. At this junction one of the cross road le
Kesaramadu and other cross road leads to Holy pilgrim centre i.e. Siddaga
these locations have been considered intersection volume count survey. The su
carried out to assess the volume of traffic movement at the junctions for the
terms of improvement of junction geometrics for better flow of traffic. The survey h
for duration of 12 hours on normal working day from morning to late evening. The
are as furnished in Table 4.2 below.
Table 4.2: Turning Movement Traffic Volume Count Locations
Locations
Remarks
3 Leg Junction
4 Leg Junction
ys are important these days as, the interruptions of
will cause undue damage in terms of loss of life or
ell as animals, since the movement of the pedestrian as
during the day time. Hence based on the initial
ey Locations
O-D Survey Existing Chainage Location Details
Location ID (km) and Location
OD-1 30.600 Near Nelamangala Toll plaza
OD-2 64.180 At Kyatsandra Junction
4.8 Details of Second Time Traffic Survey for Mid Block Locations and Additional Intesec
As per the ToR, the classified traffic volume survey has to be conducted twice dur
First survey report was completed and the traffic survey & analysis report was sub
2012. Subsequently, classified traffic volume count at the the three main locations
out in Sep 2012. In addition, an intersection has also been considered for the purp
count survey. Details of the locations considered for second survey are pre
below.
Table 4.6: Classified Traffic Volume Count Locations considered for Second Time in May- 20
Cycle Rickshaw 3 0 0
VEHICLES
Animal Drawn 1 1 1
Hand cart 0 0 0
Other Non Motorised Vehicles 6 8 6
Total Fast Moving Vehicles 37847 36161 21871
Total Slow Moving Vehicles 30 95 69
Total Vehicles 37877 36256 21940
Total Fast Moving PCU 69355 69954 51159
Total Slow Moving PCU 48 79 60
Total PCU 69403 70033 51219
Table 4.11: 1 Day Average Daily Traffic (ADT) on Other Cross Roads (Fo
on Feb-2012 Survey)
One Day Average Daily Traffic
On NH-207 (Km On SH-03 On Tumkur Bypass On Road to
Category
y Traffic
On Road to
Tumkur City
near Batavadi
(Km 66.000)
12744
4119
566
3808
521
638
210
180
742
224
228
65
3
One Day Average Daily Traffic
On NH-207 (Km On SH-03 On Tumkur Bypass On Road to
Vehicles 49.500) (Km 49.500) towards Gubbi Tumkur City
(Km 63.000) near Batavadi
(Km 66.000)
Category
Hand cart 0 0 0 0
SLOW
Cycle Rickshaw 1 0 0
Animal Drawn 0 1 0
VEHICLES
Hand cart 0 0 0
SLOW MOVING
VEHICLES
Other Non Motorised Vehicles 12 0 0
Total Fast Moving Vehicles 41087 36093 18723
Total Slow Moving Vehicles 31 49 26
Total Vehicles 41117 36142 18749
Total Fast Moving PCU 71545 68086 48255
Total Slow Moving PCU 60 30 13
Total PCU 71605 68116 48268
ed on May-2012 Survey
2 Survey
and ToR, at 3 locations the survey has been
variation of traffic along the corridor. The
s been conducted and the summary of the
ee locations with information such as Motorised
e presented in Table 4.14 below. The data
ge of 7 days for both directions for VC-1, VC-4 &
ree locations has been presented with
Us). Location wise detailed traffic
e 4.01 (a), (b) and (c) respectively.
Average Daily Traffic at VC-1 Location at Km 30.600 near Nelamangala Toll Pla
In Feb-2012, classified traffic volume count survey has been carried o
hours for 7 days. Average of the seven days has been presented bel
traffic for duration of 24 hours for the location is 69403PCUs & 37877
includes 37847 PCUs and 48 PCUs as fast and slow moving vehicles
understood from the above figures that, the intensity of non-motorise
much less which is around
0.1%. Summary of the present day traffic at the location is furnished
Table 4.16: Present Average Traffic at VC-1 at Km 30.600 near Nelamang
2012 Survey)
Vehicle Type/Direction Average for 7 Days
D-1 to D-2 D-2 to D-1 Both Direction
Two Wheeler 3777 3564 7342
Auto Passenger 951 1421 2372
Auto Goods 172 263 435
4-Wheelers - Private (White Board) 4260 4496 8756
4-Wheelers - Taxis (Yellow Board) 796 1498 2294
LCV-4Wheelers 653 1072 1725
LCV-6Wheelers 929 1098 2028
Mini-Bus 339 412 751
FAST MOVING VEHICLES
Cycle Rickshaw 3 0 3
Animal Drawn 1 0 1
VEHICLES
Hand cart 0 0 0
Other Non Motorised Vehicles 3 4 6
Total Fast Moving Vehicles 17816 20030 37847
Total Slow Moving Vehicles 19 12 30
Total Vehicles 17835 20042 37877
Total Fast Moving PCU 32711 36644 69355
Total Slow Moving PCU 29 19 48
Total PCU 32740 36663 69403
Nelamangala to Tumkur (D-1 to D-2) & Tumkur to Nelamangala (D-2
In May-2012, for the same location, Classified traffic volume count su
carried out for duration of 24 hours for 7 days. Average of the seven
presented below. Present average traffic for duration of 24 hours
71,605 PCUs & 41,117 Vehicles. This traffic includes 71,545 PCUs an
and slow moving vehicles
respectively. It is understood from the above figures that, the intensity
vehicles
is very much less which is around 0.1%. Summary of the present day
is given in Table 4.17.
cation at Km 30.600 near Nelamangala Toll Plaza
Cycle Rickshaw 0 0 1
Animal Drawn 0 0 0
VEHICLES
Hand cart 0 0 0
Other Non Motorised Vehicles 11 1 12
Total Fast Moving Vehicles 21449 19637 41087
Total Slow Moving Vehicles 27 4 31
Total Vehicles 21476 19642 41117
Total Fast Moving PCU 36393 35152 71545
Total Slow Moving PCU 53 7 60
Total PCU 36446 35159 71605
Nelamangala to Tumkur (D-1 to D-2) & Tumkur to Nelamangala (D-2
Hourly Variation & Peak Hour Traffic at VC-1 Location at Km 30.600 near Nelam
Seven days average 24 Hour Traffic is analysed for the hourly distrib
study of the hourly distribution of Average Daily Traffic at this loca
peak hour traffic movement is observed during 05.00pm to 06.00pm
3633PCU/Hour for the location as per Feb-2012 survey. Based on th
the peak hour is observed during 06.00pm to 07.00pm hour with traff
The details of traffic intensity during the day and the hourly variation i
are represented graphically in Figure
4.1(a) & (b) for different time.
As per Feb-2012 survey, Peak Hour Traffic Volume for the location is
This traffic includes 3629 PCUs and 4 PCUs as fast and slow moving
respectively. It is understood from the above figures that, the inte
motorised vehicles is very less around 0.15%. The peak hour facto
around 5.23% of the total day traffic.
As per May-2012 survey, Peak Hour Traffic Volume for the location is
This traffic includes 3880 PCUs and 3 PCUs as fast and slow moving
respectively. It is understood from the above figures that, the inte
motorised vehicles is very less around 0.10%. The peak hour facto
around 5.42% of the total day traffic.
The summary of the present average of 7 days peak hour traffic at th
in
Table 4.18 & Table 4.19.
Table 4.18: Present Peak Hour Traffic at VC-1 Location at Km 30.600 near Nela
2012 Survey)
1 at Km 30.600 near Nelamangala Toll Plaza (May-
Govt Bus 48 47 95
Pvt Bus 27 21 48
2-Axle Trucks 91 73 164
3-Axle Trucks 88 92 179
MAV (3 to 6 Axles) 31 25 56
MAV (Above 6 Axles) 0 0 1
Tractor with & Without Trailor 5 3 9
Cycle 1 1 2
SLOW MOVING
Cycle Rickshaw 0 0 0
Animal Drawn 0 0 0
VEHICLES
Hand cart 0 0 0
Other Non Motorised Vehicles 0 1 1
Total Fast Moving Vehicles 1011 1269 2280
Total Slow Moving Vehicles 1 2 3
Total Vehicles 1012 1270 2283
Total Fast Moving PCU 1698 1932 3629
Total Slow Moving PCU 1 3 4
Total PCU 1699 1935 3633
Nelamangala to Tumkur (D-1 to D-2) & Tumkur to Nelamangala (D-2 to D-1)
Nelamangala (D-2 to D-1)
Table 4.19: Present Peak Hour Traffic at VC-1 Location at Km 30.600 near Nela
(May-2012 Survey)
Vehicle Type/Direction Average for 7 Days
D-1 to D-2 D-2 to D-1 Both Direction
Two Wheeler 362 332 693
Auto Passenger 151 85 236
Auto Goods 65 9 74
4-Wheelers - Private (White Board) 252 358 610
4-Wheelers - Taxis (Yellow Board) 66 83 149
LCV-4Wheelers 107 74 181
LCV-6Wheelers 78 58 136
Mini-Bus 27 41 68
FAST MOVING VEHICLES
Govt Bus 43 45 88
Pvt Bus 25 27 52
2-Axle Trucks 95 51 146
3-Axle Trucks 96 82 177
MAV (3 to 6 Axles) 26 20 47
MAV (Above 6 Axles) 0 0 0
Tractor with & Without Trailor 2 2 4
Cycle 1 0 1
SLOW MOVING
Cycle Rickshaw 0 0 0
Animal Drawn 0 0 0
VEHICLES
Hand cart 0 0 0
Other Non Motorised Vehicles 1 0 1
Total Fast Moving Vehicles 1395 1266 2661
Total Slow Moving Vehicles 2 0 2
Total Vehicles 1397 1266 2663
Total Fast Moving PCU 2082 1797 3880
Total Slow Moving PCU 3 0 3
Total PCU 2086 1797 3883
Figure 4.1(a): Average Hourly Variation of Traffic at VC-1 Location at Km
Nelamangala Toll Plaza (Feb-2012 Survey)
Figure 4.1(b): Average Hourly Variation of Traffic at VC-1 Location at Km
Nelamangala Toll Plaza (May-2012 Survey)
Traffic Composition at VC-1 Location at Km 30.600 near Nelamangala Toll Plaza
Traffic composition observed in the survey location is plotted graphic
Figure
4.2 (a) and Table 4.2 (b) for both the time of survey i.e. for Feb-2012 and
Figure 4.2(a): Average Composition of Vehicles at VC-1 Location at Km 3
Toll Plaza (Feb-2012 Survey)
1 Location at Km 30.600 near Nelamangala Toll Plaza
Total Fast Total Slow Total Total Fast Total Slow Total
Date Moving Moving Vehicles Moving Moving PCU
Vehicles Vehicles PCU PCU
Friday 37908 21 37929 76306 26 76332
Saturday 39918 26 39944 74900 47 74947
Sunday 36325 26 36351 64767 47 64814
Monday 37964 27 37991 67177 48 67225
Tuesday 37912 31 37943 67531 38 67569
Wednesday 36050 32 36082 66084 62 66145
Thursday 38849 50 38899 68721 72 68792
Table 4.21: Daily Variation of Present ADT at VC-1 Location at Km
Nelamangala Toll Plaza (May-2012 Survey)
Total Fast Total Slow Total Total Fast Total Slow Total
Date Moving Moving Vehicles Moving Moving PCU
Vehicles Vehicles PCU PCU
Wednesday 40044 17 40061 69393 25 69418
Thursday 44747 42 44789 75921 100 76021
Friday 44761 19 44780 77528 10 77537
Saturday 40018 32 40050 64567 48 64615
Sunday 42206 11 42217 71700 9 71709
Monday 40058 37 40095 74769 36 74805
Tuesday 35773 57 35830 66933 194 67127
A graph indicating the daily variation of traffic at the location is presen
4.3
(b) below.
76332
74947 Daily Variation of Traffic at Km 30.600 After Neelamangala
Toll Plaza on NH-4
68792
67569 80000
70000
67225
60000
66145 50000
64814 40000
37991 30000
20000
37943
10000
36351 0
39944
38899
37929
36082
Figure 4.3(a): Daily Variation of Traffic at VC-1 Location at Km 30.600 near N
(Feb-2012 Survey)
Total Vehicles
Days
Figure 4.3(b): Daily Variation of PCU
Total Traffic at VC-1 Location at Km 30.600 near N
(May-2012 Survey)
Total Vehicles
Days Total PCU
C-1 Location at Km 30.600 near Nelamangala Toll
67127
35830
Total Vehicles
Total PCU
Classified Traffic Volume Details for VC-4 Location at Km 61.000 near Manchak
Table 4.22: Present Average Traffic at VC-4 Location at Km 61.000 near Manch
(Feb-2012 Survey)
Vehicle Type/Direction Average for 7 Days
D-1 to D-2 D-2 to D-1 Both Direction
Two Wheeler 3597 3424 7021
Auto Passenger 773 587 1360
Auto Goods 315 223 538
4-Wheelers - Private (White Board) 4081 4228 8309
4-Wheelers - Taxis (Yellow Board) 1072 776 1848
LCV-4Wheelers 872 849 1721
LCV-6Wheelers 1233 950 2184
Mini-Bus 211 174 385
FAST MOVING VEHICLES
Cycle Rickshaw 0 0 0
VEHICLES
Animal Drawn 1 0 1
Hand cart 0 0 0
Other Non Motorised Vehicles 5 3 8
Total Fast Moving Vehicles 18297 17864 36161
Total Slow Moving Vehicles 86 10 95
Total Vehicles 18382 17874 36256
Total Fast Moving PCU 34445 35508 69954
Total Slow Moving PCU 64 16 79
Total PCU 34509 35524 70033
Nelamangala to Tumkur (D-1 to D-2) & Tumkur to Nelamangala (D-2
In May-2012, for the same location, Classified traffic volume count su
carried out for duration of 24 hours for 7 days. Average of the seven
presented below. Present average traffic for duration of 24 hours for
PCUs & 36142 Vehicles. This traffic includes 68086 PCUs and 30 PCUs
moving vehicles respectively. It is understood from the above figures
non-motorised vehicles is very much less which is around 0.15%. Su
day traffic at the location is presented in
Table 4.23.
Table 4.23: Present Average Traffic at VC-4 Location at Km 61.000 near Manch
(May-2012 Survey)
Location at Km 61.000 near Manchakalkuppe Toll Plaza
Cycle Rickshaw 0 0 0
VEHICLES
Animal Drawn 0 0 1
Hand cart 0 0 0
Other Non Motorised Vehicles 0 0 0
Total Fast Moving Vehicles 18129 17964 36093
Total Slow Moving Vehicles 19 30 49
Total Vehicles 18148 17994 36142
Total Fast Moving PCU 33076 35010 68086
Total Slow Moving PCU 12 19 30
Total PCU 33088 35028 68116
Hourly Variation& Peak Hour Traffic at VC-4 Location at Km 61.000 near Manch
Seven days average 24 Hour Traffic is analysed for the hourly distrib
study of the hourly distribution of Average Daily Traffic at this loca
peak hour traffic movement is observed during 05.00pm to 06.00pm
3411PCU/Hour for the location as per Feb-2012 survey. Based on th
the peak hour is observed during 05.00pm to 06.00pm hour with traff
The details of traffic intensity during the day and the hourly variation i
are represented graphically in Figure
4.4 (a) & 4.4 (b) for different time.
As per Feb-2012, Peak Hour Traffic Volume for the location is 3411P
traffic includes 3407 PCUs and 3 PCUs as fast and slow moving veh
understood from the above figures that, the intensity of non-motorise
which is less than 0.20%. The peak hour factor for the location is aro
total day traffic.
As per May-2012, Peak Hour Traffic Volume for the location is 3341P
traffic includes 2340 PCUs and 1 PCU as fast and slow moving vehic
understood from the above figures that, the intensity of non-motorise
which is than
0.12%. The peak hour factor for the location is around 4.90% of the t
Govt Bus 36 36 72
Pvt Bus 17 16 33
2-Axle Trucks 82 74 156
3-Axle Trucks 101 93 194
MAV (3 to 6 Axles) 29 26 55
MAV (Above 6 Axles) 2 0 2
Tractor with & Without Trailor 4 4 8
Cycle 4 0 4
SLOW MOVING
Cycle Rickshaw 0 0 0
VEHICLES
Animal Drawn 0 0 0
Hand cart 0 0 0
Other Non Motorised Vehicles 0 0 0
Total Fast Moving Vehicles 1145 1020 2165
Total Slow Moving Vehicles 5 0 5
Total Vehicles 1149 1020 2169
Total Fast Moving PCU 1787 1620 3407
Total Slow Moving PCU 3 0 3
Total PCU 1790 1620 3410
Nelamangala to Tumkur (D-1 to D-2) & Tumkur to Nelamangala (D-2
Table 4.25: Present Peak Hour Traffic at VC-4 Location at Km 61.000 near Manc
(May-2012 Survey)
Vehicle Type/Direction Average for 7 Days
D-1 to D-2 D-2 to D-1 Both Direction
Two Wheeler 299 248 547
Auto Passenger 40 39 79
Auto Goods 15 15 30
4-Wheelers - Private (White Board) 274 320 594
4-Wheelers - Taxis (Yellow Board) 54 51 105
LCV-4Wheelers 62 43 105
LCV-6Wheelers 54 43 97
Mini-Bus 9 9 18
T MOVING VEHICLES
Govt Bus 39 38 77
Pvt Bus 13 15 28
FAST MOVING VEHICLES 2-Axle Trucks 87 56 143
3-Axle Trucks 88 102 190
MAV (3 to 6 Axles) 27 32 58
MAV (Above 6 Axles) 0 0 0
Tractor with & Without Trailor 4 10 14
Vehicle Type/Direction Average for 7 Days
Hourly Variation of Traffic at Km 61.000 Near Manchakalkuppe
400 Neelamangala to Tumkur
D-1 to D-2 TolltoPlaza
D-2 D-1 on NH-4
Both Direction
Tumkur to
0
Cycle 1 1 3 Neelamangala Both
SLOW MOVING
350 Direction
Cycle Rickshaw 0 0 0
VEHICLES
0
Animal Drawn 300 0 0 0
0
Hand cart 250 0 0 0
Other Non Motorised0Vehicles 0 0 0
200
Total Fast Moving Vehicles 0 1064 1022 2086
Total Slow Moving Vehicles 150 1 1 3
Total Vehicles 0 1065 1023 2088
100
Total Fast Moving PCU 0 1671 1669 3340
Time in Hour
Total Slow Moving PCU 500 1 1 1
0
Total PCU 1672 1669 3341
Nelamangala to Tumkur (D-1 to D-2) & Tumkur to Nelamangala (D-2
Figure 4.4(a): Average Hourly Variation of Traffic at VC-4 Location at Km 61.00
Toll Plaza (Feb-2012 Survey)
Figure 4.4(b): Average Hourly Variation of Traffic at VC-4 Location at Km 61.00
Toll Plaza (May-2012 Survey)
Hourly Variation of Traffic at Km 61.000 Near Manchakalkuppe
Toll Plaza on NH-4 (MAY-2012)
400 Neelamangala to Tumkur Tumkur to Neelamangala
0
350
0
300
0
250
0
200
0
150
0
100
0
500
0
Time in Hour
Traffic Composition at VC-4 Location at Km 61.000 near Manchakalkuppe Toll
Tumkur to Nelamangala (D-2 to D-1)
Location at Km 61.000 near Manchakalkuppe Toll Plaza
r Manchakalkuppe
Tumkur to
Neelamangala Both
Direction
Near Manchakalkuppe
amangala
6.06%
Auto Goods - 1.22%
4-Wheelers - Private (White Board) - 23.29%
13.00%
4-Wheelers - Taxis (Yellow Board) - 4.80%
4.67%
LCV-4Wheelers - 4.67%
4.80%
LCV-6Wheelers - 6.06%
Mini-Bus - 1.10%
3.65%
Govt Bus - 4.39%
Pvt Bus - 2.77%
0.02%
2-Axle Trucks - 9.63% 3-Axle Trucks - 13.00%
0.44%
MAV (3 to 6 Axles) - 3.65%
0.13%
MAV (Above 6 Axles) - 0.02%
23.29% 0.00%
Tractor with & Without Trailor - 0.44%
Cycle - 0.13%
0.00%
21.80%
Cycle Rickshaw - 0.00%
1.22%
0.00% Animal Drawn - 0.00%
3.02% 0.00%
Hand cart - 0.00%
Other Non Motorised Vehicles - 0.00%
33614
33388
37323 Days Total Vehicles
35442
35299
Figure 4.6(a): Daily Variation of Traffic at VC-4 Location at Km 61.000 near Manchakalkupp
Survey)
- Daily Variation of Traffic at Km 61.000 Near
201 Manchakalkuppe
7- 0 3 6
80000 z H Y
a24) o( M
n
7 70
603 2
1 6770000
4A
Toll 60000
N
50000
Pla 40000
67615
67348 30000
66000 20000
64900 10000
0
39481
37158
36304
35102
34642
34149
36158 Days Total Vehicles
Figure 4.6(b): Daily Variation of Traffic at VC-4 Location at Km 61.000 near Manchakalkupp
Survey)
Classified Traffic Volume Details for VC-7 Location at Km 74.000 near end of T
Average Daily Traffic at VC-7 Location at Km 74.000 near end of Tumkur Bypass
In Feb-2012, Classified traffic volume count survey has been carried
hours
for 7 days. Average of the seven days has been presented below. Pr
for duration of 24 hours for the location is 51219 PCUs & 21940 Vehi
This traffic includes 51159 PCUs and 60 PCUs as fast and slow mov
respectively. It is understood from the above figures that, the intensity
vehicles is very less which is around 0.30%. Summary of the present
location is presented in Table 4.28.
Table 4.28: Present Average Traffic at VC-7 Location at Km 74.000 near
(Feb-2012 Survey)
1.000 near Manchakalkuppe Toll Plaza
for all the days throughout the week due to
However, the variation can be ascertained by
n days and reasons for variations can be
Cycle Rickshaw 0 0 0
VEHICLES
Animal Drawn 0 1 1
Hand cart 0 0 0
Other Non Motorised Vehicles 1 5 6
Total Fast Moving Vehicles 9448 12423 21871
Total Slow Moving Vehicles 22 47 69
Total Vehicles 9471 12470 21940
Total Fast Moving PCU 23259 27899 51159
Total Slow Moving PCU 15 45 60
Total PCU 23275 27944 51219
Nelamangala to Sira (D-1 to D-2) & Sira to Nelamangala (D-2 to D-1)
In May-2012, Classified traffic volume count survey has been carried
hours for 7 days. Average of the seven days has been presented bel
traffic for duration of 24 hours for the location is 48268 PCUs & 18749
includes 48255 PCUs and 18 PCUs as fast and slow moving vehicles
understood from
the above figures that, the intensity of non-motorised vehicles is very
0.15%. Summary of the present day traffic at the location is presente
Table 4.29: Present Average Traffic at VC-7 Location at Km 74.000 near
(May-2012 Survey)
lamangala (D-2 to D-1)
urvey has been carried out for duration of 24
has been presented below. Present average
is 48268 PCUs & 18749 Vehicles. This traffic
nd slow moving vehicles respectively. It is
to Neelamangala
Direction
0.00%
Figure 4.8(a): Average Composition of Vehicles at VC-7 Location at Km 74.000 near end of Tumku
Bypass (Feb-2012 Survey)
Hourly Variation of Traffic at Km 74.000, End of Tumkur Bypass on NH-4
(MAY-2012) Neelamangala to
250 Sira Sira to
0 Neelamangala
200 Both Direction
0
150
0
100
0
500
Time in Hour
Location at Km 74.000 near end of Tumkur Bypass
nd of Tumkur Bypass
location is plotted graphically in Figure 4.8 (a) &
2 and May-2012.
Bypass on NH-4
Neelamangala to
Sira Sira to
Neelamangala
Both Direction
Composition of Vehicles at Km 74.000, End of Tumkur Bypass on NH-4
(MAY-2012)
Two Wheeler - 9.58% Auto Passenger - 1.11%
18.88% 21.37%
Auto Goods - 1.29%
4-Wheelers - Private (White Board) - 17.74% 4-Wheelers - Taxis (Yellow Board) - 3.91% LCV-4Wheelers - 4.10%
3.86%
LCV-6Wheelers - 4.35%
Mini-Bus - 0.76%
7.49%
Govt Bus - 5.21%
5.21%
Pvt Bus - 3.86%
0.01%
2-Axle Trucks - 18.88% 3-Axle Trucks - 21.37%
0.76%
0.21%
MAV (3 to 6 Axles) - 7.49%
9.58% 0.14%
MAV (Above 6 Axles) - 0.01%
1.11%0.00%
Tractor with & Without Trailor - 0.21%
Cycle - 0.14%
1.29% 0.00% Cycle Rickshaw - 0.00%
Figure 4.8(b): Average Composition of Vehicles at VC-7 Location at Km 74.000 near end of Tu
Survey)
Daily Variation of Traffic VC-7 Location at Km 74.000 near end of Tumkur Bypa
Generally the traffic will remain same for all the days throughout the w
reasons beyond the expectations. However, the variation can be
classified traffic
volume count for seven days and reasons for variations can be attrib
In this case also the variation of traffic is observed over the seven da
the seven days traffic are presented in Table 4.32 and Table 4.33 below.
Table 4.32: Daily Variation of Present ADT at VC-7 Location at Km 74.00
Bypass (Feb-2012 Survey)
Total Fast Moving Total Slow Total Total Fast Total Slow Total
Date Vehicles Moving Vehicles Vehicles Moving PCU Moving PCU PCU
Figure 4.9(a): Daily Variation of Traffic at VC-7 Location at Km 74.000 near end of Tumkur
Survey)
51298
Daily Variation of Traffic at Km 74.000, End of Tumkur
50451
Bypass on NH-4 (MAY-2012)
46617 60000 52285
46059 50000 46838
44330
20959
21362 40000
30000
17099 20000
20483 10000 17715
16771 0
16853
Figure 4.9(b): Daily Variation of Traffic at VC-7 Location at Km 74.000 near end of Tumkur
Survey)
Days Total Vehicles
Classified Traffic Volume Details at VC-2 on NH-207 (Junction of NH-4 and NH-
at VC-7 Location at Km 74.000 near end of Tumkur
Govt Bus 32 38 70
Pvt Bus 38 56 94
2-Axle Trucks 267 287 554
3-Axle Trucks 327 283 610
MAV (3 to 6 Axles) 70 66 136
MAV (Above 6 Axles) 4 10 14
Tractor with & Without Trailor 28 22 50
Cycle 20 27 47
SLOW MOVING
Cycle Rickshaw 2 1 3
VEHICLES
Animal Drawn 2 2 4
Hand cart 0 0 0
Other Non Motorised Vehicles 0 0 0
Total Fast Moving Vehicles 3351 3863 7212
Total Slow Moving Vehicles 24 30 54
Total Vehicles 3375 3893 7266
Total Fast Moving PCU 5076 5309 10355
Total Slow Moving PCU 34 37 68
Total PCU 5110 5346 10423
Doddaballapura to Dabbaspete (D-1 to D-2) Dabbaspete to Doddaba
Hourly Variation& Peak Hour Traffic at VC-2 on NH-207 (Junction of NH-4 and N
One day 24 Hour Traffic is analysed for the hourly distribution of traff
hourly distribution of Average Daily Traffic at this location reveals tha
movement is
observed during 04.00pm to 05.00pm hour with traffic of 820PCU/Ho
The details of traffic intensity during the day and the hourly variation i
are represented graphically in Figure 4.10
Peak Hour Traffic Volume for the location is 820PCU per Hour. This t
PCUs and 0 PCUs as fast and slow moving vehicles respectively. It i
above figures that, there is no non-motorised vehicles are seen durin
peak hour factor for the location is around 7.87% of the total day traff
the present day peak hour traffic at the location is presented in Table
Table 4.35: Present Peak Hour Traffic at VC-2 on NH-207 (Junction of NH-4 and
of NH-4 and NH-207 at Km 49.500)
een carried out for duration of 24 hours for 1
4 hours for the location is 10423PCUs & 7266
and 68 PCUs as fast and slow moving vehicles
e figures that, the intensity of non-motorised
Summary of the present day traffic at the
Govt Bus 3 2 5
Pvt Bus 5 3 8
2-Axle Trucks 19 18 37
3-Axle Trucks 21 16 37
MAV (3 to 6 Axles) 10 3 13
MAV (Above 6 Axles) Hourly Variation of Traffic on 1 NH-207 at Junction
1 of NH-4 and NH-207
2 at
90 Km 49.500
Tractor with & Without Trailor
0
5
Doddaballapura to Dabbaspete
0 5
Cycle 80 0 Both Direction0
Dabbaspete to Doddaballapura 0
SLOW MOVING
0
Cycle Rickshaw 0 0 0
VEHICLES
70
Animal Drawn 0 0 0 0
60
Hand cart 0 0 0 0
Other Non Motorised Vehicles
50 0 0 0
0
Total Fast Moving Vehicles 40 292 347 639
Total Slow Moving Vehicles 0 0 0 0
30
Total Vehicles 0 292 347 639
Total Fast Moving PCU 20 436 Time in Hour
384 820
0
Total Slow Moving PCU 10 0 0 0
Total PCU 0 436 384 820
0
Doddaballapura to Dabbaspete (D-1 to D-2) Dabbaspete to Doddaballapura (D-2 to D-
Figure 4.10: Average Hourly Variation of Traffic at VC-2 on NH-207 (Junction of NH-4 and NH-207 at Km
Traffic Composition at VC-2 on NH-207 (Junction of NH-4 and NH-207 at Km 49.500)
The present survey data for the location reveals that, the one day ave
comprises of 14% of Four Wheeler Passenger traffic followed by 42%
traffic, then around 26% of goods vehicles which includes all types su
3-Axle & MAV. Bus & Mini- Bus constitutes around 4% of the total da
Wheelers constitute 12% of the average daily traffic. Remaining pe
accounts for all other remaining categories of vehicles. The traff
observed in the survey location is plotted graphically and
presented in Figure 4.11.
Composition of Vehicles on NH-207 at Junction of NH-4 and NH-207
5.02%
3.37%
0 .964%9.500
1.90% at K m Two Wheeler - 41.99%
7.62%
Auto Goods - 2.45%
4-Wheelers - Private (White Board) - 10.18%
10.18%
4-Wheelers - Taxis (Yellow Board) - 3.96%
2.45% 8.40%
LCV-4Wheelers - 5.02%
LCV-6Wheelers - 3.37%
Mini-Bus - 1.90%
1.87%
Govt Bus - 0.96%
Pvt Bus - 1.29%
0.19%
2-Axle Trucks - 7.62% 3-Axle Trucks - 8.40%
0.69%
MAV (3 to 6 Axles) - 1.87%
0.65%
MAV (Above 6 Axles) - 0.19%
9.34% 0.04%
Tractor with & Without Trailor - 0.69%
Cycle - 0.65%
0.06%
Cycle Rickshaw - 0.04%
41.99%
0.00% Animal Drawn - 0.06% Hand cart - 0.00%
0.00%
Other Non Motorised Vehicles - 0.00%
Figure 4.11: Average Composition of Vehicles at VC-2 on NH-207 (Junction of NH-4 and N
Peak Hour Traffic Volume for the location is 381PCU per Hour. This t
PCUs and 9 PCUs as fast and slow moving vehicles respectively. It i
above figures that, the intensity of non-motorised vehicles is very low
factor for the location is around 8.97% of the total day traffic. The sum
day peak hour traffic at the location is presented in Table 4.37.
Table 4.37: Present Peak Hour Traffic at VC-3 Location on SH-3 (Junction of NH
49.500)
ction of NH-4 and SH-3 at Km 49.500)
n carried out for duration of 24 hours for 1
hours for the location is 4249 PCUs & 4577
82 PCUs as fast and slow moving vehicles
Govt Bus 0 0 0
Pvt Bus 1 3 4
2-Axle Trucks 6 7 13
3-Axle Trucks 3 2 5
Hourly Variation of Traffic on SH-3 at Junction of NH-4 and SH-3 at Km
MAV (3 to 6 Axles) 0 0 0
49.500
MAV (Above 6 Axles) 45 0
Gudemarenahalli(Shivagange) 0
to Dabbaspete 0
0
Tractor with & Without40 Dabbaspete
Trailor to Gudemarenahalli(Shivagange)
3 1 4
Both Direction
Cycle 0 8 7 15
SLOW MOVING
35
Cycle Rickshaw 0 0 0
VEHICLES
0
Animal Drawn 30 0 0 0
0
Hand cart
25
0 0 0
Other Non Motorised Vehicles
0 0 0 0
Total Fast Moving Vehicles 20 237 226 463
0
Total Slow Moving Vehicles 15 8 7 15
Total Vehicles 0 245 233 478
10
Total Fast Moving PCU 0
198 Time in 175
Hour 372
Total Slow Moving PCU 50 5 4 9
Total PCU 0 203 179 381
Gudemarenahalli (Shivagange) to Dabbaspete (D-1 to D-2)
Dobbaspete to Gudemarenahalli (Shivagange)(D-2 to D-1)
Figure 4.12: Average Hourly Variation of Traffic at VC-3 Location on SH-3 (Junction of NH
49.500)
Traffic Composition at VC-3 Location on SH-3 (Junction of NH-4 and SH-3 at K
The present survey data for the location reveals that, the one day ave
comprises of 10% of Four Wheeler Passenger traffic followed by 59%
traffic, then around 10.5% of goods vehicles which includes all types
3-Axle & MAV. Bus & Mini-Bus constitutes around 2% of the total day
Wheelers constitute 15% of the average daily traffic. Remaining perc
accounts for all other remaining categories of vehicles. The traffic com
the survey location is plotted graphically and
presented in Figure 4.13.
Composition of Vehicles on SH-3 at Junction of NH-4 and SH-3
0.74% 7.19% 2.62%
at Km 49.500 Two Wheeler - 58.84%
4.46%
14.33%
Auto Passenger - 14.33%
1.75%
0.48%
0.35% Auto Goods - 0.74%
0.96%
4-Wheelers - Private (White Board) -
2.80%
7.19%
1.31% 4-Wheelers - Taxis (Yellow Board) -
0.31%
2.62%
LCV-4Wheelers - 4.46%
LCV-6Wheelers - 1.75%
Mini-Bus - 0.48%
2.34%
Govt Bus - 0.35%
0.02%
Pvt Bus - 0.96%
0.02%
0.00%
2-Axle Trucks - 2.80%
58.84%
0.02%
3-Axle Trucks - 1.31%
Figure 4.13: Average Composition of Vehicles at VC-3 Location on SH-3 (Junction of NH-4 an
Classified Traffic Volume Details at VC-5 Location on Tumkur Bypass (Towards Gubbi) Junc
63.000
D-1 to D-2)
D-2 to D-1)
n SH-3 (Junction of NH-4 and SH-3 at Km
Govt Bus 1 3 4
Pvt Bus 33 21 54
2-Axle Trucks 197 136 333
3-Axle Trucks 232 150 382
MAV (3 to 6 Axles) 22 23 45
MAV (Above 6 Axles) 1 1 2
Tractor with & Without Trailor 58 49 107
Cycle 28 48 76
SLOW MOVING
Cycle Rickshaw 0 1 1
VEHICLES
Animal Drawn 0 0 0
Hand cart 0 0 0
Other Non Motorised Vehicles 0 0 0
Total Fast Moving Vehicles 3301 2871 6170
Total Slow Moving Vehicles 28 49 77
Total Vehicles 3329 2920 6247
Total Fast Moving PCU 4485 3595 8052
Total Slow Moving PCU 22 35 54
Total PCU 4507 3630 8106
Nelamangala to Tumkur Bypass (Towards Gubbi) (D-1 to D-2) Tumkur Bypass (To
Nelamangala (D-2 to D-1)
Hourly Variation& Peak Hour Traffic at VC-5 Location on Tumkur Bypass (T
with NH-4 at Km 63.000
One day 24 Hour Traffic is analysed for the hourly distribution of traff
hourly distribution of Average Daily Traffic at this location reveals tha
movement is
observed during 05.00pm to 06.00pm hour with traffic of 649PCU/Ho
The details of traffic intensity during the day and the hourly variation i
are represented graphically in Figure 4.14.
been carried out for duration of 24 hours for 1
f 24 hours for the location is 8106PCUs & 6247
and 54 PCUs as fast and slow moving vehicles
Govt Bus 0 0 0
Pvt Bus 4 0 4
2-Axle Trucks 10 8 18
3-Axle Trucks 14 26 40
MAV (3 to 6 Axles) 0 0 0
MAV (Above 6 Axles) 0 0 0
Tractor with & Without Trailor 4 2 6
Cycle 3 2 5
SLOW MOVING
Cycle Rickshaw 0 0 0
VEHICLES
Animal Drawn 0 0 0
Hand cart 0 0 0
Other Non Motorised Vehicles 0 0 0
Total Fast Moving Vehicles 271 243 514
Total Slow Moving Vehicles 3 2 5
Total Vehicles 274 245 519
Total Fast Moving PCU 312 336 646
Total Slow Moving PCU 2 1 3
Total PCU 314 337 649
Nelamangala to Tumkur Bypass (Towards Gubbi) (D-1 to D-2)
Tumkur Bypass (Towards Gubbi) to Nelamangala (D-2 to D-1)
Figure 4.14: Average Hourly Variation of Traffic at VC-5 Location on Tumkur Bypass (T
with NH-4 at Km 63.000
Traffic Composition at VC-5 Location on Tumkur Bypass (Towards Gubbi) Jun
63.000
The present survey data for the location reveals that, the one day ave
comprises of 31% of Four Wheeler Passenger traffic followed by 37%
traffic, then around 20% of goods vehicles which includes all types su
3-Axle & MAV. Bus & Mini- Bus constitutes around 3% of the total da
Wheelers constitute 4.8% of the average daily traffic. Remaining pe
accounts for all other remaining categories of vehicles. The traff
observed in the survey location is plotted graphically and
presented in Figure 4.15.
0.06%
0.86%
Auto Passenger - 2.71%
5.33%
Auto Goods - 2.10%
26.04%
4-Wheelers - Private (White Board) -
6.11%
26.04%
4-Wheelers - Taxis (Yellow Board) - 5.33%
0.72%
LCV-4Wheelers - 5.14%
0.03%
LCV-6Wheelers - 3.63%
1.71%
Mini-Bus - 2.26%
1.22% Govt Bus - 0.06%
2.10% 0.02%
Pvt Bus - 0.86%
0.00%
36.72% 0.00%
2-Axle Trucks - 5.33%
2.71% 0.00%
3-Axle Trucks - 6.11%
Figure 4.15: Average Composition of Vehicles at VC-5 Location on Tumkur Bypass (To
with NH-4 at Km 63.000
Average Daily Traffic at VC-6 Location on Road to Tumkur City near Batavadi (
Km 66.000)
649PCU per Hour. This traffic includes 646
vehicles respectively. It is understood from
motorised vehicles is very low. The peak hour
e total day traffic. The summary of the present
ented in Table 4.39.
Location on Tumkur Bypass (Towards Gubbi)
Cycle Rickshaw 0 1 1
Animal Drawn 1 2 3
VEHICLES
Hand cart 0 0 0
Other Non Motorised Vehicles 2 0 2
Total Fast Moving Vehicles 14364 9861 24213
Total Slow Moving Vehicles 263 238 501
Total Vehicles 14627 10099 24714
Total Fast Moving PCU 14489 7116 21583
Total Slow Moving PCU 157 146 298
Total PCU 14646 7262 21881
Nelamangala to Tumkur City (D-1 to D-2) Tumkur City to Nelamanga
Hourly Variation& Peak Hour Traffic at VC-6 Location on Road to Tumkur City
with NH-4 at Km 66.000)
One day 24 Hour Traffic is analysed for the hourly distribution of traff
hourly
distribution of Average Daily Traffic at this location reveals that the pe
movement is observed during 06.00pm to 07.00pm hour with traffic o
the location.
The details of traffic intensity during the day and the hourly variation i
are represented graphically in Figure 4.16.
Peak Hour Traffic Volume for the location is 1744PCU per Hour. This
PCUs and 33 PCUs as fast and slow moving vehicles respectively. It
the above figures that, the intensity of non-motorised vehicles is very
factor for the location is around 7.97% of the total day traffic. The sum
day peak hour traffic at the location is presented in Table 4.41.
Table 4.41: Present Peak Hour Traffic at VC-6 Location on Road to Tum
(Junction with NH-4 at Km 66.000)
een carried out for duration of 24 hours for 1
4 hours for the location is 24714PCUs &
PCUs and 298 PCUs as fast and slow moving
Govt Bus 44 1 45
Pvt Bus 11 0 11
2-Axle Trucks 7 3 10
Hourly Variation of Traffic on Road to Tumkur City near Batavadi
3-Axle Trucks 5 0 5
200 Junction with NH-4 at Km 66.000
MAV (3 to 6 Axles) 0 Neelamangala to Tumkur
0 City 0 0
Tumkur City to Neelamangala Both Direction
MAV (Above 6 Axles) 180 0 0 0
0
Tractor with & Without 160
Trailor 4 2 6
Cycle 0 44 18 62
SLOW MOVING
140
Cycle Rickshaw 0 0 0
VEHICLES
0
Animal Drawn 120 0 0 0
Hand cart 0 0 0 0
100
Other Non Motorised Vehicles
0 0 0 0
Total Fast Moving Vehicles 800 1263 910 2173
600
Total Slow Moving Vehicles 44 18 62
400
Total Vehicles 200 1307 Time928
in Hour 2235
Total Fast Moving PCU 0 1094 619 1711
Total Slow Moving PCU 24 9 33
Total PCU 1118 628 1744
Nelamangala to Tumkur City (D-1 to D-2) Tumkur City to Nelamangala (D-2 to D-1)
Figure 4.16: Average Hourly Variation of Traffic at VC-6 Location on Road to Tumkur C
(Junction with NH-4 at Km 66.000)
Traffic Composition at VC-6 Location on Road to Tumkur City near Batavadi (J
Km 66.000)
The present survey data for the location reveals that, the one day ave
comprises of 17% of Four Wheeler Passenger traffic followed by 52%
traffic, then around 5% of goods vehicles which includes all types suc
Axle & MAV. Bus & Mini- Bus constitutes around 4.5% of the tota
Wheelers constitute 19% of the average daily traffic. Remaining pe
accounts for all other remaining categories of vehicles. The traffic com
the survey location is plotted graphically and
presented in Figure 4.17.
Composition of Vehicles on Road to Tumkur City near Batavadi Junction
15.41%
with NH-4 at Km 66.000 Two Wheeler - 51.57%
Auto Passenger - 16.67%
2.29% 2.11% 2.58%
Auto Goods - 2.29%
16.67% 0.85%
4-Wheelers - Private (White Board) - 15.41%
0.73%
4-Wheelers - Taxis (Yellow Board) - 2.11%
3.00%
LCV-4Wheelers - 2.58%
0.91%
LCV-6Wheelers - 0.85%
0.92%
Mini-Bus - 0.73%
0.26%
Govt Bus - 3.00%
0.01%
Pvt Bus - 0.91%
0.00%
2-Axle Trucks - 0.92%
0.67%
3-Axle Trucks - 0.26%
MAV (3 to 6 Axles) - 0.01%
2.00% MAV (Above 6 Axles) - 0.00%
0.00%
Tractor with & Without Trailor - 0.67% Cycle - 2.00%
0.01%
Cycle Rickshaw - 0.00%
0.00% Animal Drawn - 0.01%
51.57%
Hand cart - 0.00%
0.01%
Other Non Motorised Vehicles - 0.01%
Figure 4.17: Average Composition of Vehicles at VC-6 Location on Road to Tumkur Cit
(Junction with NH-4 at Km 66.000)
4.12 Classified Turning Traffic Volume Count Survey
ar Batavadi
Total Fast Total Slow Total Total Fast Total Slow Total Directional
Direction Moving Moving Vehicles Moving Moving PCU Distribution
Vehicles Vehicles PCU PCU
D-1 to D-2 1017 14 1031 1618 7 1625 4.9%
D-1 to D-3 9361 7 9368 15435 7 15442 44.6%
Total Traffic from D-1 10378 21 10399 17053 14 17067 49.5%
D-2 to D-1 557 6 563 948 3 951 2.7%
D-2 to D-3 498 0 498 622 0 622 2.4%
Total Traffic from D-2 1055 6 1061 1569 3 1572 5.0%
D-3 to D-1 8753 10 8763 14703 5 14708 41.7%
D-3 to D-2 794 4 798 860 2 862 3.8%
Total Traffic from D-3 9547 14 9561 15563 7 15570 45.5%
Total from All 20980 41 21021 34184 24 34208 100.0%
Directions
s identified where the turning of traffic
e, the classified turning traffic volume
n of 12 hours to ascertain the peak hour
the 12 hour and peak hour traffic details
detailed traffic count information is
Directional
Distribution
4.9%
44.6%
49.5%
2.7%
2.4%
5.0%
41.7%
3.8%
45.5%
100.0%
D-1: Nelamangala, D-2: Dobbaspete Industrial Area Road, D-3: Tum
Table 4.44: Peak Hour Direction-wise Traffic Details at Km 47.600 (NH 4
Industrial Area Road Junction) IC-1
Directional
Distribution
5.1%
45.3%
50.4%
2.8%
2.8%
5.6%
40.7%
3.2%
43.9%
100.0%
Industrial Area Road, D-3: Tumkur
00 (NH 4 & Dobbaspete Industrial Area Road Junction) in
Total Fast Total Slow Total Total Fast Total Total Directional
Moving Moving Vehicles Moving Slow PCU Distribution
Direction
Vehicles Vehicles PCU Moving
PCU
D-1 to D-2 12 1 13 8 1 8 0.5%
D-1 to D-3 1106 2 1108 1621 9 1630 43.0%
D-1 to D-4 40 2 42 43 1 44 1.6%
Total Traffic from D-1 1158 5 1163 1671 10 1681 45.2%
D-2 to D-1 9 1 10 13 1 14 0.4%
D-2 to D-3 20 0 20 15 0 15 0.8%
D-2 to D-4 56 1 57 49 1 50 2.2%
Total Traffic from D-2 85 2 87 77 1 78 3.4%
D-3 to D-1 1107 1 1108 1597 1 1598 43.0%
D-3 to D-2 26 0 26 22 0 22 1.0%
D-3 to D-4 37 1 38 36 1 36 1.5%
Total Traffic from D-3 1170 2 1172 1654 1 1655 45.5%
D-4 to D-1 26 0 26 32 0 32 1.0%
D-4 to D-2 77 4 81 61 17 78 3.1%
D-4 to D-3 45 0 45 50 0 50 1.7%
Total Traffic from D-4 148 4 152 142 17 159 5.9%
Total from All Directions 2561 13 2574 3544 29 3573 100.0%
D-1: Nelamangala, D-2: Kesaramadu, D-3: Tumkur, D-4: Siddaganga
Figure 4.19(a): Peak Hour Traffic Flow at Kyatsandra Junction at Km 64.180 in PCUs
Classified Turning Traffic Volume at Km 35.200 (T Begur Industrial Area Juncti
Industrial Area Roads) -IC-3
Classified traffic volume count was carried out at the junction of NH-4
Industrial Area Roads for duration of 12 hours where the directional c
independent as the roads traverses on the circumference of the villag
side. Hence in conducting the junction survey, the cross road traf
the traffic moving from Tumkur to Bangalore direction. Hence, th
Bangalore-Tumkur direction has not been considered. The traffic m
hour duration at the junction is 12036 vehicles & 18978 PCUs and peak h
at the junctions is 1131 Vehicles & 1791 PCUs. Details of
the traffic survey at the junction are presented in Table 4.47 to 4.48 belo
hour traffic flow diagram is presented in Figure 4.19(b) below.
atsandra Junction at Km 64.180
Total Fast Total Slow Total Total Fast Total Slow Total Directional
Moving Moving Vehicles Moving Moving PCU Distribution
Direction
Vehicles Vehicles PCU PCU
Table 4.49 presents the PV value, which is a measure of intensity of vehicular and
2
(Reference: IRC 103:2012 “Guidelines for Pedestrian Facilities”) for all the su
all the locations, the PV value is greater than the value of 10 . Hence, keeping the
2 8
Zone Car Car Mini Bus Bus LCV (4 LCV (6 2 Axle 3 Axle
No. (white (Yellow Bus (Govt) (Pvt) wheelers) wheelers) Truck Truck
board) board)
1 10.5% 10.4% 0.0% 0.8% 1.8% 4.4% 4.5% 3.6% 3.4%
2 0.1% 0.1% 0.0% 0.4% 0.0% 0.0% 0.9% 1.6% 3.0%
3 1.0% 1.6% 2.2% 0.0% 0.0% 1.1% 2.5% 3.6% 4.2%
4 0.4% 0.4% 2.2% 0.0% 0.0% 2.2% 4.7% 5.8% 5.2%
5 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.9% 0.6% 0.9%
6 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.6% 1.1% 0.9%
7 1.4% 1.7% 0.0% 0.2% 0.0% 1.1% 0.6% 0.7% 1.1%
8 0.1% 0.0% 0.0% 0.0% 0.0% 4.4% 2.6% 3.0% 3.3%
9 0.0% 0.0% 0.0% 0.0% 0.0% 1.1% 0.8% 0.8% 0.7%
10 31.8% 30.4% 37.0% 47.4% 47.0% 33.3% 31.1% 27.6% 26.6%
11 0.0% 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
12 0.0% 0.3% 0.0% 0.0% 0.0% 1.1% 0.2% 0.3% 0.2%
13 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.1%
14 0.5% 0.1% 0.0% 0.3% 0.0% 0.0% 1.3% 0.6% 0.6%
15 0.1% 0.2% 0.0% 0.8% 1.0% 1.1% 0.6% 0.2% 0.2%
16 4.5% 5.0% 6.5% 0.6% 0.8% 1.1% 0.6% 0.9% 0.6%
17 1.1% 0.8% 0.0% 0.2% 0.0% 2.2% 1.1% 0.7% 0.7%
18 1.7% 1.1% 0.0% 0.2% 0.3% 15.6% 1.7% 0.3% 0.3%
19 8.5% 7.8% 15.2% 8.8% 7.6% 10.0% 9.4% 7.2% 6.2%
20 2.5% 2.5% 6.5% 1.0% 0.8% 1.1% 0.8% 0.7% 0.8%
21 1.3% 0.9% 2.2% 1.0% 0.5% 0.0% 0.8% 0.3% 0.6%
22 10.6% 8.4% 2.2% 9.9% 18.5% 3.3% 4.7% 5.9% 5.7%
23 4.0% 3.9% 6.5% 11.2% 6.6% 3.3% 3.0% 2.4% 2.9%
24 5.5% 7.8% 6.5% 6.6% 5.6% 3.3% 3.8% 3.6% 3.6%
25 1.9% 1.6% 6.5% 4.6% 4.8% 2.2% 0.6% 2.1% 1.9%
26 1.9% 2.4% 4.3% 0.3% 0.5% 0.0% 0.4% 0.6% 0.9%
27 7.2% 8.7% 2.2% 3.0% 1.5% 1.1% 4.0% 3.6% 4.6%
28 0.9% 1.3% 0.0% 0.1% 0.0% 0.0% 0.9% 1.1% 0.8%
29 0.0% 0.1% 0.0% 0.5% 0.0% 0.0% 0.2% 0.5% 0.6%
30 0.0% 0.0% 0.0% 1.0% 0.5% 0.0% 0.0% 0.0% 0.0%
31 0.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.9% 0.7% 0.6%
32 1.7% 2.3% 0.0% 1.0% 1.3% 4.4% 9.2% 11.8% 9.9%
33 0.3% 0.2% 0.0% 0.1% 1.0% 1.1% 1.1% 1.8% 1.6%
34 0.1% 0.0% 0.0% 0.0% 0.0% 0.0% 2.1% 2.6% 3.0%
35 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.2% 0.1% 0.0%
36 0.0% 0.0% 0.0% 0.0% 0.0% 1.1% 3.2% 3.4% 4.4%
Total 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Km 32.000 near Nelamangala Toll Plaza (OD-1)
Multi
Axle
Truck
3.5%
3.0%
1.7%
12.2%
0.0%
1.7%
0.9%
2.2%
1.3%
21.7%
1.3%
1.3%
0.0%
0.0%
0.0%
0.4%
0.9%
0.0%
2.2%
0.9%
1.3%
3.5%
2.6%
1.3%
2.6%
0.9%
2.2%
0.0%
0.0%
0.4%
0.4%
12.2%
3.0%
8.7%
0.4%
5.2%
100.0%
Table 4.59: Influence Factors for Various Types of Vehicles at Km 62.000 near Tumkur Tol
Zone Car Car Mini Bus Bus LCV (4 LCV (6 2 Axle 3 Axle
No. (white (Yellow Bus (Govt) (Pvt) wheelers) wheelers) Truck Truck
board) board)
1 1.9% 1.6% 12.5% 0.8% 0.0% 2.9% 1.9% 1.9% 1.9%
2 0.5% 0.3% 0.0% 0.1% 0.4% 0.7% 1.1% 1.7% 2.9%
3 0.1% 0.2% 0.0% 0.1% 0.0% 1.5% 3.0% 3.8% 6.9%
4 2.0% 1.3% 2.5% 0.5% 0.4% 5.9% 5.0% 5.6% 10.2%
5 0.1% 0.1% 2.5% 0.0% 0.0% 0.0% 0.0% 0.1% 0.4%
6 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.2% 0.3% 0.1%
7 0.0% 0.0% 0.0% 0.0% 0.0% 0.7% 3.0% 1.2% 0.8%
8 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.7% 0.7% 0.4%
9 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.3% 0.0%
10 36.3% 37.1% 25.0% 44.1% 48.3% 33.8% 31.8% 29.7% 24.5%
11 1.7% 1.0% 0.0% 0.7% 0.4% 0.7% 0.0% 0.3% 0.1%
12 1.1% 1.8% 0.0% 0.8% 0.0% 2.2% 0.6% 0.8% 0.4%
13 0.9% 0.7% 2.5% 0.3% 0.0% 0.7% 0.4% 0.0% 0.1%
14 0.1% 0.1% 0.0% 0.2% 0.0% 0.7% 0.2% 0.2% 0.2%
15 0.3% 0.1% 0.0% 0.2% 0.0% 0.0% 0.2% 0.0% 0.0%
16 2.8% 3.0% 5.0% 1.1% 0.0% 0.0% 0.7% 0.8% 0.6%
17 1.3% 1.6% 0.0% 1.0% 0.4% 0.0% 0.0% 0.4% 0.0%
18 1.0% 1.2% 0.0% 0.8% 0.0% 0.7% 1.3% 2.2% 0.6%
19 12.1% 7.8% 20.0% 9.6% 7.5% 10.3% 12.6% 11.2% 6.6%
20 2.8% 2.3% 0.0% 1.3% 1.7% 1.5% 3.0% 1.4% 1.1%
21 0.9% 2.8% 0.0% 0.6% 1.3% 2.2% 0.4% 0.1% 0.3%
22 8.5% 10.4% 12.5% 11.9% 15.8% 5.1% 2.4% 3.3% 2.8%
23 7.4% 8.6% 5.0% 9.8% 1.7% 2.2% 1.9% 2.1% 1.9%
24 5.2% 4.0% 5.0% 4.7% 0.4% 0.7% 0.6% 1.3% 1.8%
25 5.1% 4.3% 0.0% 4.2% 12.9% 1.5% 1.3% 2.4% 2.1%
26 0.6% 1.1% 0.0% 0.9% 0.0% 0.7% 0.9% 0.6% 1.5%
27 2.9% 2.7% 2.5% 3.6% 2.9% 2.2% 5.4% 5.0% 3.5%
28 0.5% 0.3% 5.0% 0.0% 0.0% 0.0% 0.0% 0.2% 0.9%
29 0.4% 0.3% 0.0% 0.7% 2.1% 2.2% 1.7% 1.8% 1.5%
30 0.0% 0.0% 0.0% 0.1% 0.0% 0.0% 0.4% 0.2% 0.1%
31 0.0% 0.1% 0.0% 0.0% 0.8% 0.0% 0.0% 0.2% 0.2%
32 3.2% 5.1% 0.0% 1.2% 2.1% 18.4% 14.9% 15.6% 21.1%
33 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 2.6% 1.9% 1.3%
34 0.2% 0.0% 0.0% 0.9% 0.8% 1.5% 0.9% 1.5% 2.8%
35 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.6% 0.6% 0.0%
36 0.0% 0.0% 0.0% 0.0% 0.0% 0.7% 0.6% 0.6% 0.4%
Total 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Present section is main route connecting the Bangalore and Mumbai
Chennai. Most of the traffic observed specially goods traffic seems to
Also it is observed that, many industrial areas have been set up betw
and Tumkur which is making
a provision for passenger trips from the surrounding areas i.e. from B
So in order to assess the percentage of traffic crossing the both toll p
percentage of traffic crossing one toll plaza based on the present O-D
been analysed.
From the pre defined zones, it is possible to estimate the Through Tr
but vehicles pass through two toll plaza & Semi-Through Traffic whic
crossing one toll plaza at both the toll plaza has been considered. De
presented in Table 4.60 to Table 4.61 below.
Table 4.60: Details of Through & Local Traffic at Km 30.600 (OD-1 Location)
Km 62.000 near Tumkur Toll Plaza (OD-2)
Multi
Axle
Truck
0.9%
4.3%
6.0%
9.5%
0.4%
0.4%
0.4%
0.4%
0.0%
26.7%
0.0%
0.0%
0.0%
0.0%
0.0%
0.9%
0.0%
0.0%
3.0%
0.0%
0.9%
3.0%
2.2%
1.7%
0.4%
0.4%
3.0%
0.4%
1.7%
0.0%
0.4%
20.3%
4.7%
7.3%
0.0%
0.4%
100.0%
Bangalore and Mumbai and also with
lly goods traffic seems to be through traffic.
s have been set up between Nelamangala
c-2019)
as conducted for both passenger and freight
rmal working day for the above mentioned Km
on of Vehicle Trips Based on Trip Length of Travel at all Locations for Passenger
on of Vehicle Trips Based on Trip Frequency of Travel at all Locations for Goods
Table 4.65: Distribution of Vehicle Trips Based on Type of Commodity Carried
all Locations
Sl. No. Type of Commodity OD-1 at Km OD-2 at Km
30.600 62.000
1 Foodgrains & Pulses 3.1% 1.1%
2 Cash crops 3.2% 0.3%
3 Vegitables & fruits 7.2% 1.6%
4 Processed food items 1.4% 3.9%
5 Packed food items 0.6% 1.1%
6 Fishery, Poultry & Animal feed 3.3% 1.7%
7 Building Material 7.7% 4.7%
8 Industrial Raw Material 3.3% 3.0%
9 Forest(Log,Timber,Plywood) 2.8% 1.5%
10 Consumer Goods 6.1% 7.0%
11 Fertilizers, Chemicals & Pharmaceuticals 4.4% 5.4%
12 Machinary & Automobiles 9.3% 13.6%
13 Petrolium Products 3.8% 3.9%
14 Parcel Goods 9.2% 15.3%
15 Empty 25.0% 28.3%
16 Industrial Output 7.4% 6.7%
17 Liquor & Cool-drinks 1.9% 0.8%
Total 100.0% 100.0%
Origin-Destination Matrices
Based on the above mentioned zones, the data collected during the O
coded respectively according to their zone numbers. With these infor
indicating the origin & destination has been formulated for individual
for both the locations separately.
In order to assess the influence of each zone on its traffic attraction a
trips, the influence factors have been calculated for each vehicle type
results provide a clear indication of the regions, which contribute to th
existing roads in the project influence area. Number of trips origina
destined to any zone represents the influence of that zone on the
the percentage of trips that are being originated or designated to a pa
of trips originating from and destined to any zone divided by twice the
observed trips in percentage terms gives the influence factor (IF) of th
The details of influence factors for all the vehicle types are given in T
4.66 to Table 4.67 below. The details of the O-D matrix for all the loca
in
Annexure 4.04 (a).
Table 4.66: Influence Factors for Various Types of Vehicles at Km
Nelamangala Toll Plaza (OD-1)
Vehicles At Km 30.600 At Km At Km
on NH-4 61.000 on 74.000 on
NH-4 NH-4
Two Wheeler 7342 7021 3196
Auto Passenger 2279 1307 645
Auto Goods 418 517 333
4-Wheelers - Private (White Board) 8414 7985 3829
4-Wheelers - Taxis (Yellow Board) 2205 1776 923
LCV-4Wheelers 1618 1615 854
LCV-6Wheelers 1902 2048 821
Mini-Bus 704 361 98
FAST MOVING VEHICLES
Cycle Rickshaw 3 0 0
VEHICLES
Animal Drawn 1 1 1
Hand cart 0 0 0
Other Non Motorised Vehicles 6 8 6
Total Fast Moving Vehicles 37221 35629 21695
Total Slow Moving Vehicles 30 95 69
Total Vehicles 37252 35725 21764
Total Fast Moving PCU 69117 69852 51402
Total Slow Moving PCU 48 79 60
Total PCU 69165 69931 51463
nducted in the month of February, the seasonal
e same month have been considered in arriving the
verage Daily Traffic. Details of the Annual
ns on NH-4 between Nelamangala to Tumkur
d in Table 4.73 below.
Traffic of Feb-2012
Table 4.74: Details of Annual Average Daily Traffic of May-2012
Annual Average Daily Traffic
Category
Cycle Rickshaw 1 0 0
Animal Drawn 0 1 0
VEHICLES
Hand cart 0 0 0
Other Non Motorised Vehicles 12 0 0
Total Fast Moving Vehicles 39387 34696 18055
Total Slow Moving Vehicles 31 49 26
Total Vehicles 39418 34745 18081
Total Fast Moving PCU 69040 65876 46924
Total Slow Moving PCU 60 30 13
Total PCU 69100 65906 46938
4.19 Comparaison of Survey Data of Feb-2012 and May-2012
Following table gives the comparision of traffic data at three locations.
Table 4.75: Comparision of Average Daily Traffic at three locations as per Feb-2012 and May
At Km At Km At Km At Km At Km
30.600 61.000 74.000 30.600 61.000
on NH-4 on NH-4 on NH-4 on NH-4 on NH-4
Two Wheeler 8871 7880 1796 7342 7021
FAST MOVING VEHICLES
2
hree locations.
ons as per Feb-2012 and May-2012 Survey Data
Cycle Rickshaw 1 0 0 3 0 0
VEHICLES
Animal Drawn 0 1 0 1 1 1
Hand cart 0 0 0 0 0 0
Other Non Motorised Vehicles 12 0 0 6 8 6
Total Fast Moving Vehicles 41087 36093 18723 37847 36161 21871
Total Slow Moving Vehicles 31 49 26 30 95 69
Total Vehicles 41117 36142 18749 37877 36256 21940
Total Fast Moving PCU 71545 68086 48255 69355 69954 51159
Total Slow Moving PCU 60 30 13 48 79 60
Total PCU 71605 68116 48268 69403 70033 51219
4.20 Traffic Forecast
The traffic level & demand assess benefits to the users and the cost
be the derived on the same traffic details, which indicates the basis fo
priorities. As this project calls for investment, prediction of traffic dem
important task and has to be carried out accurately. The accurate e
has direct bearing on design of the facility and the viability of project.
efforts have been made to carefully assess all the parameters that he
traffic demand in future. Following guidelines have been considered f
estimating the future traffic.
Econometric Method of Traffic Projection (as suggested in IRC: 1
Recommendation of Planning Commission for BOT projects.
ate
ed in the Karnataka State for 6 years i.e.
tails are presented in Table 4.76 below.
ownership has increased in higher
a State
Source: Transport Department and Directorate of Statistics & Economics, GOK
Econometric Model for Traffic Projections State Income
In order to estimate the growth of economy of the region or the state,
to Net State Domestic Product (NSDP) for the Karnataka State has b
details of NSDP both at Current price as well as Constant Price have
from the year 2004- 05 to 2010-2011. The base for the NSDP is base
data.
Apart from the total NSDP details, information of about the Per-Capit
Karnataka State has also been presented in Tables 4.77 & 4.78 below. B
available information about the NSDP, economic growth of Karnataka
years in terms of NSDP at current price and constant price is abou
8.44% respectively. Similarly the Per-Capita Income of the state un
and constant price are 14.45% and 7.23% respectively.
Table 4.77: Past Economic Growth of Karnataka State in Terms of NSDP (At Cu
AT CURRENT PRICE
Year NSDP In Growth of NSDP-Per- Growth of NSDP Per-
Rs. Crore NSDP per Capita Income in Capita Income per
Year, % Rs. Year, %
2004-05 148047 26758
2005-06 174080 17.58% 31090 16.19%
2006-07 203690 17.01% 35958 15.66%
2007-08 243019 19.31% 42418 17.97%
2008-09 268118 10.33% 46285 9.12%
2009-10 303638 13.25% 51858 12.04%
2010-11 355019 16.92% 60000 15.70%
Average Growth, % 15.73% 14.45%
Source: Department of Statistics and Economics, Government of Karnataka
of Statistics & Economics, GOK
ns State Income
conomy of the region or the state, the details pertaining
DP) for the Karnataka State has been considered. The
ce as well as Constant Price have been considered
11. The base for the NSDP is based on the 2004-05
Tg = Eg * e
Where Tg is Traffic Growth Rate
Eg is Economic Growth Rate for the Region “e” is the Traffic Demand
Traffic Growth Rates
Traffic growth rates are necessary to estimate the traffic levels expec
using the project road. The traffic growth rate is a product of econom
influence area and elasticity of traffic demand. Traffic growth rates fo
of vehicle types were estimated based on the economic forecasts in t
the corresponding elasticity of
traffic demand.
ct.
s, the elasticity values obtained for each type of vehicle
onomic growth of the region.
-Values
Motor Motor Auto Buses & Goods Other
cycles Cars, Rick Omni- Carriages Vehicles
Vehicle Type Tractors
Jeeps & shaws Buses
Cabs
E-Value as per NSDP &
Vehicle Registration 0.933 1.242 0.765 0.941 1.319 0.891 1.524
Regression
The elasticity values estimated by vehicle type have thereafter
Average Economic Growth of state to arrive at growth rate for each ty
Table 4.58 gives the combined Traffic Growth Rates.
Table 4.80: Estimated Traffic Growth Rates
t 30 Years
Future Traffic Projection by Various Growth Rates
Future Projection of Traffic based on Econometric
Method of Traffic Growth Rates
ne requirement.
tio has been worked out and the requirement
on and with a proposal of 6 lane divided
on level has also been presented Table
Total PCUs
Total PCUs
Total PCUs
V/C Ratio-
V/C Ratio-
V/C Ratio-
V/C Ratio-
Proposed
Proposed
Vehicles
Vehicles
Vehicles
Existing
Existing
Total
Total
Total
2012 37252 69166 1.73 1.15 35725 69932 1.75 1.17 21764 51464
2013 40845 76223 1.91 1.27 39217 77156 1.93 1.29 23938 56869
2014 44794 84015 2.10 1.40 43059 85138 2.13 1.42 26335 62849
2015 49136 92618 2.32 1.54 47288 93961 2.35 1.57 28977 69468
2016 53911 102121 2.55 1.70 51942 103715 2.59 1.73 31891 76794
2017 58899 112093 2.80 1.87 56809 113959 2.85 1.90 34944 84497
2018 64361 123057 3.08 2.05 62144 125231 3.13 2.09 38295 92984
2019 70343 135113 3.38 2.25 67992 137635 3.44 2.29 41975 102334
2020 76896 148373 3.71 2.47 74404 151289 3.78 2.52 46016 112636
2021 84074 162956 4.07 2.72 81434 166316 4.16 2.77 50454 123990
2022 91546 178196 4.45 2.97 88758 182032 4.55 3.03 55085 135875
2023 99698 194885 4.87 3.25 96755 199254 4.98 3.32 60150 148913
2024 108594 213164 5.33 3.55 105489 218130 5.45 3.64 65689 163217
2025 118302 233184 5.83 3.89 115029 238818 5.97 3.98 71749 178911
2026 128899 255116 6.38 4.25 125449 261496 6.54 4.36 78378 196129
2027 139889 277941 6.95 4.63 136265 285114 7.13 4.75 85269 214079
2028 151837 302840 7.57 5.05 148032 310891 7.77 5.18 92776 233690
2029 164827 330002 8.25 5.50 160835 339030 8.48 5.65 100956 255114
2030 178954 359637 8.99 5.99 174768 369747 9.24 6.16 109870 278522
2031 194318 391970 9.80 6.53 189932 403281 10.08 6.72 119584 304099
2032 210194 425489 10.64 7.09 205612 438063 10.95 7.30 129643 330652
2033 227393 461913 11.55 7.70 222612 475881 11.90 7.93 140562 359544
2034 246030 501498 12.54 8.36 241042 517000 12.93 8.62 152415 390983
2035 266224 544519 13.61 9.08 261026 561712 14.04 9.36 165283 425196
2036 288109 591278 14.78 9.85 282698 610335 15.26 10.17 179255 462430
2037 310643 639564 15.99 10.66 305025 660568 16.51 11.01 193667 500927
2038 334973 691841 17.30 11.53 329147 714980 17.87 11.92 209256 542655
2039 361245 748445 18.71 12.47 355209 773920 19.35 12.90 226118 587888
2040 389616 809734 20.24 13.50 383369 837769 20.94 13.96 244359 636921
2041 420257 876101 21.90 14.60 413799 906937 22.67 15.12 264092 690077
4.000, VC-7 End of Tumkur
V/C Ratio-
V/C Ratio-
Proposed
Existing
1.29 0.86
1.42 0.95
1.57 1.05
1.74 1.16
1.92 1.28
2.11 1.41
2.32 1.55
2.56 1.71
2.82 1.88
3.10 2.07
3.40 2.26
3.72 2.48
4.08 2.72
4.47 2.98
4.90 3.27
5.35 3.57
5.84 3.89
6.38 4.25
6.96 4.64
7.60 5.07
8.27 5.51
8.99 5.99
9.77 6.52
10.63 7.09
11.56 7.71
12.52 8.35
13.57 9.04
14.70 9.80
15.92 10.62
17.25 11.50
Table 4.85: Details of Congestion Effect based on 5% as Traffic Growth Rates
At Km 30.600, VC-1 After At Km 61.000, VC-4 Near At Km 74.000, VC-7 End of
Nelamangala Toll Plaza Manchakalkuppe before Toll Plaza Tumkur Bypass
Year
Total PCUs
Total PCUs
Total PCUs
V/C Ratio-
V/C Ratio-
V/C Ratio-
V/C Ratio-
Proposed
Proposed
Vehicles
Vehicles
Vehicles
Existing
Existing
Total
Total
Total
2012 37252 69166 1.73 1.15 35725 69932 1.75 1.17 21764 51464
2013 39114 72624 1.82 1.21 37511 73429 1.84 1.22 22852 54037
2014 41070 76256 1.91 1.27 39386 77100 1.93 1.29 23994 56739
2015 43123 80068 2.00 1.33 41356 80955 2.02 1.35 25194 59575
2016 45280 84071 2.10 1.40 43423 85003 2.13 1.42 26454 62554
2017 47544 88275 2.21 1.47 45595 89253 2.23 1.49 27777 65681
2018 49921 92689 2.32 1.54 47874 93715 2.34 1.56 29165 68966
2019 52417 97323 2.43 1.62 50268 98401 2.46 1.64 30624 72414
2020 55038 102190 2.55 1.70 52781 103321 2.58 1.72 32155 76034
2021 57790 107298 2.68 1.79 55421 108487 2.71 1.81 33763 79837
2022 60679 112664 2.82 1.88 58192 113912 2.85 1.90 35451 83828
2023 63713 118297 2.96 1.97 61101 119607 2.99 1.99 37223 88019
2024 66899 124211 3.11 2.07 64156 125587 3.14 2.09 39084 92420
2025 70244 130422 3.26 2.17 67364 131866 3.30 2.20 41039 97041
2026 73756 136943 3.42 2.28 70732 138460 3.46 2.31 43091 101893
2027 77444 143790 3.59 2.40 74269 145383 3.63 2.42 45245 106987
2028 81316 150980 3.77 2.52 77982 152652 3.82 2.54 47507 112338
2029 85382 158529 3.96 2.64 81881 160285 4.01 2.67 49883 117954
2030 89651 166455 4.16 2.77 85975 168299 4.21 2.80 52377 123852
2031 94133 174777 4.37 2.91 90274 176713 4.42 2.95 54996 130044
2032 98840 183516 4.59 3.06 94788 185549 4.64 3.09 57746 136546
2033 103782 192692 4.82 3.21 99527 194827 4.87 3.25 60633 143374
2034 108971 202327 5.06 3.37 104504 204568 5.11 3.41 63665 150542
2035 114419 212444 5.31 3.54 109729 214796 5.37 3.58 66848 158069
2036 120140 223065 5.58 3.72 115215 225536 5.64 3.76 70190 165972
2037 126147 234219 5.86 3.90 120976 236812 5.92 3.95 73700 174271
2038 132455 245929 6.15 4.10 127025 248653 6.22 4.14 77385 182985
2039 139078 258226 6.46 4.30 133376 261086 6.53 4.35 81254 192134
2040 146031 271137 6.78 4.52 140045 274140 6.85 4.57 85317 201741
2041 153333 284694 7.12 4.74 147047 287847 7.20 4.80 89582 211828
4.22 MSA Calculations
It is absolutely necessary to calculate the number of repetitions of the
going to affect the durability of the pavement. Hence in all the c
pavement is to be constructed or strengthening of the existing pave
out, it is necessary to estimate the no. of repetitions of the wheel load
section which is expressed in terms
of Million Standard Axle Loads (MSA).
Present scope of work involves widening of the existing 4 lane carriag
divided carriageway configuration.
Apart from widening to 6 lane divided carriageway condition, the exis
be strengthened, which can be done by evaluation of the residual stre
pavement and expected repetitions of loads by which, required Overl
estimated.
So for the present section also in order to estimate the new pavemen
widening sections and Overlay thickness for the existing pavement, t
calculated based on the following considerations.
Initial Traffic in terms of the number of commercial vehicles per da
Lane Distribution Factor of 60% as per IRC-37-2018, for a dual ca
Lane carriageway in each direction
Vehicle Damage Factor
Design Life in Years (includes 3 Year Construction)
5% Annual Growth Rate of Commercial Vehicles has been consid
Traffic Distribution in each direction-Since the directional distributi
the range of 45% to 55%, hence 50% average distribution has been c
The present section between Nelamangala to Tumkur Bypass End P
divided carriageway with paved shoulder. However, based on the pro
improvements, it is decided to provided, 6 lane divided carriageway a
above parameters, the expected MSA along the corridor is estimated
lane configurations with estimated Vehicle
Damage Factors and presented in Table below.
Growth Rates
At Km 74.000, VC-7 End of
Tumkur Bypass
V/C Ratio-
V/C Ratio-
Proposed
Existing
1.29 0.86
1.35 0.90
1.42 0.95
1.49 0.99
1.56 1.04
1.64 1.09
1.72 1.15
1.81 1.21
1.90 1.27
2.00 1.33
2.10 1.40
2.20 1.47
2.31 1.54
2.43 1.62
2.55 1.70
2.67 1.78
2.81 1.87
2.95 1.97
3.10 2.06
3.25 2.17
3.41 2.28
3.58 2.39
3.76 2.51
3.95 2.63
4.15 2.77
4.36 2.90
4.57 3.05
4.80 3.20
5.04 3.36
5.30 3.53
ber of repetitions of the loads which is
nt. Hence in all the cases when new
ing of the existing pavement is to be carried
itions of the wheel loads on the road
struction)
hicles has been considered as per ToR
he directional distribution of vehicles is in
distribution has been considered in design
Tumkur Bypass End Point is having 4 lane
wever, based on the proposed
e divided carriageway and considering the
he corridor is estimated according to the
w.
Following are the details considered in calculation of MSA for various
the Parameters and the MSA calculations based on the present
sections are presented in Table 4.86 to Table 4.87 below.
Table 4.86: Design Details for Calculation of MSA
MAV (Above 6
2-Axle Trucks
3-Axle Trucks
MAV (4 to 6
Wheelers
Wheelers
Axles)
LCV-4
LCV-6
Govt Bus
Details
Pvt Bus
Axles)
Lane Distribution Factor D= 60% 60% 60% 60% 60% 60% 60% 60%
Vehicle Damage Factor F= 0.602 0.602 1.083 1.083 4.512 6.730 6.697 9.227
Traffic Distribution Td = 50% 50% 50% 50% 50% 50% 50% 50%
Table 4.87: Design MSA based on Traffic Volume at Km 30.600
MSA CALCULATIONS Total
LCV-4 LCV-6 Govt Pvt 2-Axle 3-Axle MAV MAV MSA
Year
Wheelers Wheelers Bus Bus Trucks Trucks (3 to 6 (Above 6
Axles) Axles)
2012 0.11 0.13 0.20 0.13 1.81 3.18 0.99 0.07 6.61
2013 0.22 0.26 0.41 0.27 3.71 6.51 2.02 0.15 13.56
2014 0.34 0.40 0.63 0.42 5.70 10.01 3.11 0.23 20.85
2015 0.46 0.54 0.87 0.58 7.80 13.69 4.25 0.32 28.50
2016 0.59 0.69 1.11 0.74 10.00 17.55 5.45 0.41 36.54
2017 0.73 0.85 1.37 0.91 12.31 21.61 6.71 0.50 44.98
2018 0.87 1.02 1.64 1.09 14.73 25.86 8.03 0.60 53.84
on of MSA for various sections. Details of
sed on the present traffic at various
below.
m 30.600
MSA CALCULATIONS Total
LCV-4 LCV-6 Govt Pvt 2-Axle 3-Axle MAV MAV MSA
Year
Wheelers Wheelers Bus Bus Trucks Trucks (3 to 6 (Above 6
Axles) Axles)
2019 1.02 1.20 1.92 1.28 17.28 30.33 9.42 0.70 63.15
2020 1.18 1.38 2.22 1.48 19.95 35.03 10.88 0.81 72.92
2021 1.34 1.58 2.53 1.69 22.76 39.95 12.41 0.93 83.18
2022 1.51 1.78 2.86 1.91 25.70 45.13 14.02 1.05 93.95
2023 1.70 1.99 3.20 2.13 28.80 50.56 15.70 1.17 105.26
2024 1.89 2.22 3.56 2.38 32.05 56.27 17.47 1.30 117.14
2025 2.09 2.46 3.94 2.63 35.46 62.26 19.33 1.44 129.61
2026 2.30 2.70 4.34 2.89 39.04 68.55 21.29 1.59 142.70
2027 2.52 2.97 4.76 3.17 42.80 75.15 23.34 1.74 156.45
2028 2.76 3.24 5.20 3.47 46.75 82.08 25.49 1.90 170.88
2029 3.00 3.53 5.66 3.77 50.90 89.36 27.75 2.07 186.04
2030 3.26 3.83 6.14 4.10 55.25 97.01 30.13 2.25 201.95
2031 3.53 4.14 6.65 4.43 59.82 105.04 32.62 2.43 218.67
2032 3.81 4.48 7.18 4.79 64.62 113.46 35.24 2.63 236.21
2033 4.11 4.83 7.74 5.16 69.66 122.31 37.99 2.83 254.63
2034 4.42 5.19 8.33 5.56 74.95 131.61 40.87 3.05 273.98
2035 4.75 5.58 8.95 5.97 80.51 141.36 43.90 3.28 294.29
2036 5.09 5.98 9.60 6.40 86.35 151.61 47.08 3.51 315.62
2037 5.45 6.41 10.28 6.85 92.47 162.36 50.42 3.76 338.01
2038 5.83 6.85 10.99 7.33 98.90 173.66 53.93 4.02 361.53
2039 6.23 7.32 11.74 7.83 105.66 185.52 57.61 4.30 386.22
2040 6.65 7.81 12.53 8.36 112.75 197.97 61.48 4.59 412.14
2041 7.08 8.33 13.36 8.91 120.20 211.05 65.54 4.89 439.36
Table 4.88: Design MSA based on Traffic at Km 61.000
MSA CALCULATIONS Total
LCV-4 LCV-6 Govt Pvt 2-Axle 3-Axle MAV (3 MAV MSA
Year
Wheelers Wheelers Bus Bus Trucks Trucks to 6 Axles) (Above 6
Axles)
2012 0.11 0.13 0.19 0.13 1.91 3.62 1.03 0.03 7.15
2013 0.22 0.28 0.39 0.26 3.91 7.43 2.12 0.06 14.66
2014 0.34 0.43 0.59 0.40 6.01 11.43 3.26 0.09 22.54
2015 0.46 0.58 0.81 0.55 8.21 15.62 4.46 0.12 30.81
2016 0.59 0.75 1.04 0.70 10.53 20.03 5.72 0.15 39.50
2017 0.72 0.92 1.28 0.87 12.96 24.65 7.04 0.19 48.63
2018 0.87 1.10 1.53 1.04 15.51 29.51 8.42 0.23 58.21
2019 1.02 1.29 1.80 1.22 18.19 34.61 9.88 0.27 68.27
2020 1.17 1.49 2.08 1.40 21.01 39.97 11.41 0.31 78.83
2021 1.34 1.70 2.37 1.60 23.96 45.59 13.01 0.35 89.92
2022 1.51 1.92 2.68 1.81 27.07 51.49 14.70 0.40 101.57
2023 1.69 2.15 3.00 2.03 30.32 57.69 16.47 0.44 113.80
2024 1.88 2.39 3.34 2.25 33.75 64.20 18.33 0.49 126.64
2025 2.09 2.65 3.69 2.49 37.34 71.04 20.28 0.55 140.12
2026 2.30 2.91 4.07 2.75 41.11 78.21 22.33 0.60 154.27
2027 2.52 3.19 4.46 3.01 45.07 85.75 24.48 0.66 169.13
2028 2.75 3.49 4.87 3.29 49.23 93.66 26.74 0.72 184.74
2029 2.99 3.80 5.30 3.58 53.60 101.97 29.11 0.78 201.13
2030 3.25 4.12 5.75 3.89 58.18 110.69 31.60 0.85 218.33
2031 3.52 4.46 6.23 4.21 62.99 119.85 34.21 0.92 236.40
2032 3.80 4.82 6.73 4.55 68.05 129.47 36.96 1.00 255.37
2033 4.10 5.20 7.26 4.90 73.36 139.56 39.84 1.07 275.29
2034 4.41 5.59 7.81 5.27 78.93 150.17 42.87 1.15 296.20
2035 4.74 6.01 8.39 5.66 84.78 161.30 46.05 1.24 318.16
2036 5.08 6.44 8.99 6.08 90.93 172.99 49.38 1.33 341.22
2037 5.44 6.90 9.63 6.51 97.38 185.26 52.89 1.42 365.43
2038 5.82 7.38 10.30 6.96 104.15 198.15 56.57 1.52 390.85
2039 6.21 7.88 11.00 7.43 111.26 211.68 60.43 1.63 417.54
2040 6.63 8.41 11.74 7.93 118.73 225.89 64.49 1.74 445.56
2041 7.07 8.97 12.52 8.46 126.57 240.81 68.75 1.85 474.99
Total
MSA
7.15
14.66
22.54
30.81
39.50
48.63
58.21
68.27
78.83
89.92
101.57
113.80
126.64
140.12
154.27
169.13
184.74
201.13
218.33
236.40
255.37
275.29
296.20
318.16
341.22
365.43
390.85
417.54
445.56
474.99
Table 4.89: Design MSA based on Traffic at Km 74.000
MSA CALCULATIONS
Year LCV-4 LCV-6 Govt Pvt 2-Axle 3-Axle MAV (3 MAV
Wheelers Wheelers Bus Bus Trucks Trucks to 6 Axles) (Above 6
Axles)
2012 0.06 0.05 0.12 0.09 1.79 3.24 0.77 0.05
2013 0.12 0.11 0.25 0.18 3.67 6.65 1.58 0.10
2014 0.18 0.17 0.38 0.27 5.65 10.22 2.43 0.16
2015 0.24 0.23 0.52 0.37 7.73 13.98 3.33 0.22
2016 0.31 0.30 0.67 0.48 9.91 17.92 4.27 0.28
2017 0.38 0.37 0.82 0.59 12.19 22.06 5.25 0.34
2018 0.46 0.44 0.99 0.70 14.60 26.40 6.28 0.41
2019 0.54 0.52 1.16 0.82 17.12 30.97 7.37 0.48
2020 0.62 0.60 1.34 0.95 19.77 35.76 8.51 0.55
2021 0.71 0.68 1.52 1.08 22.55 40.79 9.71 0.63
2022 0.80 0.77 1.72 1.23 25.47 46.07 10.97 0.71
2023 0.90 0.86 1.93 1.37 28.53 51.62 12.29 0.80
2024 1.00 0.96 2.15 1.53 31.75 57.44 13.67 0.89
2025 1.10 1.06 2.37 1.69 35.13 63.55 15.13 0.98
2026 1.21 1.17 2.61 1.86 38.68 69.97 16.66 1.08
2027 1.33 1.28 2.87 2.04 42.41 76.72 18.26 1.19
2028 1.45 1.40 3.13 2.23 46.32 83.79 19.95 1.30
2029 1.58 1.52 3.41 2.43 50.43 91.23 21.72 1.41
2030 1.72 1.65 3.70 2.63 54.75 99.03 23.57 1.53
2031 1.86 1.79 4.01 2.85 59.28 107.22 25.52 1.66
2032 2.01 1.93 4.33 3.08 64.03 115.83 27.57 1.79
2033 2.17 2.08 4.66 3.32 69.03 124.86 29.72 1.93
2034 2.33 2.24 5.02 3.57 74.27 134.35 31.98 2.08
2035 2.51 2.41 5.39 3.84 79.78 144.31 34.35 2.23
2036 2.69 2.58 5.78 4.12 85.56 154.77 36.84 2.39
2037 2.88 2.77 6.19 4.41 91.63 165.75 39.46 2.56
2038 3.08 2.96 6.62 4.71 98.00 177.28 42.20 2.74
2039 3.29 3.16 7.08 5.04 104.70 189.39 45.08 2.93
2040 3.51 3.37 7.55 5.37 111.72 202.10 48.11 3.13
2041 3.74 3.60 8.05 5.73 119.10 215.44 51.29 3.33
m 74.000
TOTAL
MSA
6.18
12.66
19.47
26.62
34.12
42.00
50.28
58.97
68.09
77.67
87.73
98.29
109.38
121.03
133.25
146.09
159.57
173.73
188.59
204.19
220.58
237.78
255.85
274.81
294.73
315.64
337.60
360.65
384.86
410.28
Table 4.90: Summary of the Design MSA at all Locations for different Durations
Year/ VC-1 at Km VC-4 at Km VC-7 at Km Remarks
Locations 30.600 62.000 74.000
2012 6.61 7.15 6.18 Present MSA
2015 20.85 22.54 19.47 MSA by Opening to Traffic Construction
2019 63.15 68.27 58.97 MSA for 5 Years after Opening to Traffic
2024 117.14 126.64 109.38 MSA for 10 Years after Opening to Traffic
2029 186.04 201.13 173.73 MSA for 15 Years after Opening to Traffic
2034 273.98 296.20 255.85 MSA for 20 Years after Opening to Traffic
4.23 Outcome of Traffic Survey & Analysis
Detailed traffic surveys have been conducted along the project road as w
roads which are joining with NH-4 between Nelamangala and Tumkur Bypas
on the initial reconnaissance survey supported by subsequent detailed site v
consultation with NHAI, it was decided to conduct classified traffic volume co
three locations along the corridor for duration of 7 days 24 hours continuousl
locations are spaced in such way that, the distance between each count loca
of 20 to 30 km.
In addition to these, to know the volume of traffic influencing NH-4 project ro
major roads such as NH-207, SH-03, Tumkur Bypass to Gubbi and Tumkur
volume counts have been carried out with one day classified traffic volume c
locations.
Based on the traffic surveys, the 7 days ADT at the three VC locations are as
From the above data it can be concluded that, the traffic at VC-1 i.e.
slightly increased from Feb-2012 survey to May-2012 survey. Where
Km 61.000 &
VC-7 at Km 74.000, the traffic volume has reduced when compared w
to May-2012 survey.
Similarly, the one day ADT in May 2012 at the four locations which ar
as under:
VC-2 on NH-207 (at Km 49.500 of NH-4) ADT is 10,423PCU per d
VC-3 on SH-03 (at Km 49.500 of NH-4) ADT is 4,249PCU per day
VC-5 on Tumkur Bypass to Gubbi (at Km 63.000 of NH-4) ADT is
VC-6 on Tumkur City Road from NH-4 at Batawadi (at Km 66.000
21,881 PCU per day
Based on these traffic, the road stretch between Nelamangala and Tu
Point warrants for 6 laning immediately and even warrants 8 laning b
and Start of Tumkur Bypass by LOS B criteria. It has been observed
Nelamangala will slightly get reduced near Dabbaspete and at Da
merging and diverging has been observed from both NH-207 tow
Doddaballapura and SH-03 towards Gudemarenahalli. Similarly, a
after the existing Toll Plaza just before the Tumkur City, a road which
Tumkur City in the western side connecting to NH-206 towards
has also merging and diverging of traffic.
Thereafter, at Batavadi junction, a considerable volume of traffic is le
the NH-4 from the Tumkur City. Hence, comparing with all the three l
count, at Km 30.600 and Km 61.000, the traffic volume is 69,403PCU
per day where as at Km 74.000 the volume is 51,219PCU per day ha
20,000PCU per day which is
attributed to the traffic plying between Bangalore and Tumkur and vic
or different Durations
U per day
U per day
U per day
CU per day
U per day
U per day
Table 4.91 below. When this value is more than 10 , grade separated
8
Axle Load survey has been conducted along the project corridor in order
Vehicle
damage factors. The summary of the Vehicle Damage Factors for various ca
are presented in Table
Table 4.92: below and adopted for calculation of MSA for various
MSA values
y at two major junctions has been carried out.
he findings based on traffic movement at
ad traffic.
e crossing of pedestrians.
At
Batavadi
Km
66.000
397
1778
1E+09
oll Plaza for Freight Vehicles, Paid Half Toll Rates (For
Rock Coring
Heavy duty rotary drilling rig having the capacity to drill up to 60 m ha
through the rocky stratum. Tungsten Carbide (TC) / Diamond bits we
through weathered
rock / hard rock stratum. Recovered cores were measured and perce
has been calculated as under:
ficient design. The necessary surveys and
the ToR.
areare
h termed as Permanent
in terms BenchMarks
of GTS Bench Marks
The SPT, UDS and rock core samples, core sampling depth percenta
each core drill run has been mentioned in the respective bore log.
Standard Penetration Test (SPT)
Standard Penetration Test (SPT) to determine penetration resist
in the boreholes generally up to refusal depth using the procedure d
In this method, driving bit is replaced by split spoon sampler (50.8 m
and the sampler is driven by dropping 63.5 kg hammer on the top of
free fall of 75 cm. The length of the sampler is 60 cm.
The sampler is first driven through 15 cm as “Seating Drive”. It is furth
cm. The number of blows required to drive the sampler for 30 cm bey
termed as “Penetration Resistance, N”.
Where it was not possible to penetrate the full length of SPT sampler
reached earlier, N values are generally observed to be greater than 1
Recorded ‘N’ values are mentioned in the respective bore log sheet a
Investigation
The objective of pavement investigation is to develop pavement desig
existing ground and road conditions, available construction materials
loading and to confirm sources of pavement construction materials.
This section presents and discusses the field investigations of the ex
and field investigations of ground conditions for proposed new road a
collected were analyzed to obtain characteristic values that were utili
design parameters.
Pavement Investigations and Testing
Pavement Condition Survey was undertaken to obtain an initial evalu
along the project roads, with particular emphasis on the condition of t
pavement. From the results of the Pavement Condition Survey, Pav
testing (Benkelman Beam) was carried out. Subsequently a program
testing was undertaken using the samples
obtained from the above investigation.
Pavement Condition Survey
The objective of the pavement condition survey was to get an understanding o
condition of the pavement through visual observation and simple manual meas
has been conducted based on the specification mentioned in clause 4.2 of IRC
survey was conducted in January 2012 by recording observations made f
vehicle while travelling along the length of the project road. At a regular interva
pavement condition survey has been carried out and basic parameters like wid
defects were recorded by visual observations.
The data collected for every 1.0 km comprised of five categories, these
Characteristics, Pavement Condition, Shoulder Condition, Embankment and Dr
The full record of the Pavement Condition Survey regarding the existing pavem
attached as Annexure 2.02.
Pavement Structural Strength (Falling weight Deflectometer Tests)
The project road traverses through plain terrain. For the entire length, the
carriageway with BC/AC surfacing. The structural strength survey for existing s
carriedout using Falling Weight Deflectometer (FWD) technique in accorda
procedure given in IRC: 115-2014 (“Guidelines for Structural Evaluation and St
Flexible Road Pavements using Falling Weight Deflectometer-FWD Technique
The objective of this pavement-testing programme was to measure the residua
be mobilized from the existing pavement. In Falling Weight Deflectometer (FWD
load is applied on the road surface. The magnitude of the load, duration and ar
adjusted that it corresponds to the effect of loading due to standard axle on in-
The deflection of the road surface is measured at a number of points at differe
outward from the centre of the falling weight. Thus, the shape of deflection bow
stiffness values can be studied over a period to time to assess the trend in the
deterioration of pavement and overlay thickness can be designed. For design o
the existing pavement structure (with the stiffness values estimated by FWD) a
overlay thickness can be analysed to obtain the critical strain value(s). Results
are enclosed in Annexure 8.01.
5.3 Subgrade Investigation for Pavements
Understanding of subgrade or basement soil is very important in the des
structures for Highways. Subgrade is normally defined as the supporting structu
pavement surface and its special under courses rest. In cut sections, it is origin
base material and in fills, subgrade consists of uppermost materials placed in e
Increased vehicle speed and axle load has now resulted in the necessity
investigation of subgrade soil to achieve satisfactory performance under v
conditions. Subgrade soil sometimes is also referred to as “basement soil.” Gen
subgrade material and hence the characteristics of soil found in different region
studied and analysed.
Such soil generally consists of mineral matter formed by disintegration of rocks
water, wind, pressure, temperature etc. All soils generally contain water in vary
free or absorbed form. In most cases, soils are heterogeneous blends of partic
shapes and parent material. Structural design of flexible pavement consists of e
total thickness above subgrade and sub-dividing it economically into
materials so that subgrade and paving layers are not stressed beyon
bearing capacities due to the traffic loads.IRC 37 is generally based o
design for evaluating subgrade strength, in the 4 day soaked conditio
Soil Classification for Highway Purposes
Certain characteristics such as grain size are useful in classifyin
predicting the behaviour. Grain size classification as per IS 1498 w
followed is described below:
Soils are generally divided into three divisions namely, coarse graine
highly organic soils and other miscellaneous soil materials.
Coarse Grained Soils
The coarse grained soils are divided into two sub-divisions, namely:
Gravel
In these soils, more than half the coarse fraction (+75 micron) is large
Sieve size. This subdivision includes gravel and gravelly soils.
Sand
In these soils, more than half the coarse fraction (+75 micron) is sma
Sieve size. This subdivision includes sand and sandy soils.
Fine Grained Soils
The fine-grained soils shall be further divided into three sub divisions
following values of liquid limit:
Silts and Clays of low compressibility- LL < 35(represented by Symbol L).
Silts and Clays of medium compressibility- LL 35- 50(represented by Symbo
Silts and Clays of high compressibility -LL>50 (represented by Symbol H).
Particle Size based Definition of Soil Components
Boulders -Average diameter of particles: > 300 mm
Cobble - Average diameter of particles: 300 mm -75 mm
Coarse Gravel - Average diameter of particles: 75 - 20 mm
Fine Gravel - Average diameter of particles: 20 mm - 4.75 mm
Coarse Sand - Average diameter of particles: 4.75 mm - 2.0 mm
Medium Sand - Average diameter of particles:2.0 mm - 425
Fine Sand - Average diameter of particles: 425µ - 75µ. (0.425mm
Silt - Average diameter of particles: 0. 075 mm - 0.002 mm
Clay - Average diameter of particles: < 0.002 mm
Since soils generally consist of one or more of above constituents, th
divided into various groups as fine and coarse-grained soils (general
category). Various other classifications such as Unified soil classifica
AASHTO classifications are
also useful.
Based on trial pit excavation & subsequent visual classification, subg
identified.
Factors influencing behaviour of Subgrade Soils
Moisture plays a very important role on the behaviour of soils. Soils th
strength and supporting power under one set of moisture conditions p
unsatisfactory due to seasonal moisture changes. Subgrade soils are
moisture changes and wherever possible, the design should ensure s
performance of subgrade under varying moisture conditions with suit
Properties of soils composed largely of coarse materials are primarily
sizes of particles while for soils composed largely of clays and colloid
influenced by surface charges and captions.
Density of soil affects its behaviour. In coarse-grained soils, increase
decreased moisture due to compaction increases the strength of the
other hand, over compaction of clays that has high affinity for water is
Compaction characteristics for subgrade soil is estimated by conduct
compaction test.
Sub grade Investigation Programme
Evaluation of Subgrade soil characteristics by collecting representativ
the existing alignment along the entire length. Collection of bulk sam
km along the carriageway (existing). For all soil samples, in-situ field
bulk density was calculated in the field using standard core cutter me
Laboratory Tests
The following laboratory tests were performed on representative
pits to evaluate characteristics of subgrade soil.
Grain size analysis - Wet Sieve analysis and Hydrometer analysis
Atterberg’s limits - liquid limit, plastic limit and plasticity index
Bulk & Dry Density
Specific Gravity
Modified Proctor compaction test
Preparation of samples at 97% MDD for conducting un-soaked an
CBR test
The test procedures for grain size analysis, Atterberg’s limits, B
Specific Gravity, tests have already been explained earlier in this sec
methodology for Modified Proctor Compaction and CBR tests is expla
Modified Proctor Compaction Test Procedure
About 6 kg of sample was taken for light compaction. The comp
1000 cm3 capacity with base plate attached is weighed to the neare
of the wet soil compacted in three equal layers using the rammer of m
fall 310mm with 25 evenly distributed blows in each layer for 100mm
blows for 150mm diameter mould). The second and third layers are s
The loose soil from the outside and
base of the mould was cleaned. The mould with the soil is finally weig
(w2).
The procedure was repeated for six to seven times using a fresh soil
adding higher water content then the proceeding one till there is eithe
change in the mass of the wet compacted soil in the mould. Densities
of compactive efforts are plotted against moisture contents. The Posi
on this curve has been determined. The dry density have been repor
and moisture contest to the nearest 0.2 for values below 5% & 0.5 fo
CBR values for Soaked Samples
The mould containing the test specimen is placed on the lower plate
with the base plate in position and the top surface exposed. Surcharg
to produce an intensity of loading equal to the weight of the base mat
pavement is placed on the specimen (if the soaking had been done e
then shall be equal to that used during the soaking). To prevent “hea
hole of the surcharge weights, a 2.5 kg annular mass is placed on the
seating the penetration plunger after which the remainder of surcharg
placed. The plunger shall be kept under a load of about 4 kg so that f
between the surface of the specimen and the plunger. The stress and
are set to initial zero reading. The initial load applied to the plunger is
while determining the load-penetration relation. Load is applied to the
at the rate of penetration equal to 1.25 mm per minute. The load is re
of 0.0, 0.5, 1.0, 1.5, 2.0, 2.5, 4.0, 5.0, 7.5, 10.0 and 12.5 mm. The ma
penetration is recorded for a maximum penetration of 12.5 mm. The p
completion of test is raised and the mould is detached from the loadin
50-100 g of soil is taken immediately below the plunger for water con
The undisturbed test specimen should be examined carefully after th
for specimen the presence of any oversize particles as it could affect
Hence CBR should not be considered meaningful for application to p
soil like sands. If penetration test is to be performed on both ends of
base plate from the lower end of the mould and fix it on the upper end
and conduct the test on other end of specimen. In that case, sam
ends is taken for water content determination. The load penetratio
This curve is generally convex upwards, although the initial portion of
concave upwards due to surface irregularities. A correction shall the
drawing a tangent to the upper curve at the point of contraflexu
curve shall be taken to be this tangent plus the convex portion of the
origin of strains shifted to the point where the tangent cuts the horizo
Thus the penetration of plunger shall be read from this shifted zero p
zero. Accordingly the corrected load shall be read corresponding to th
Laboratory Test Results of Subgrade Soil
The testing programme is based on the concept of project road being
series of homogenous lengths. Each of these homogenous lengths w
that idealized soil parameters could be adopted for this stretch. Base
condition survey it was inferred that the project road is more or le
most of its length. All samples were generally air-dried followed b
testing. Modified proctor compaction test was
performed on representative samples. CBR test on individual sample
97%
Length of core x100 Length of run
Length of core in pieces of 101.6 mm ( 4inches and above) Length
of run
x 100
The SPT, UDS and rock core samples, core sampling depth percentage CR and RQD for
each core drill run has been mentioned in the respective bore log.
Standard Penetration Test (SPT)
Standard Penetration Test (SPT) to determine penetration resistance was conducted
in the boreholes generally up to refusal depth using the procedure described in IS: 2131.
In this method, driving bit is replaced by split spoon sampler (50.8 mm OD and 35 mm ID)
and the sampler is driven by dropping 63.5 kg hammer on the top of the driving collar with
free fall of 75 cm. The length of the sampler is 60 cm.
The sampler is first driven through 15 cm as “Seating Drive”. It is further driven through 30
cm. The number of blows required to drive the sampler for 30 cm beyond seating drive is
termed as “Penetration Resistance, N”.
Where it was not possible to penetrate the full length of SPT sampler and “refusal” was
reached earlier, N values are generally observed to be greater than 100.
Recorded ‘N’ values are mentioned in the respective bore log sheet attached. Pavement
Investigation
The objective of pavement investigation is to develop pavement designs that reflect the
existing ground and road conditions, available construction materials and expected traffic
loading and to confirm sources of pavement construction materials.
This section presents and discusses the field investigations of the existing road pavement
and field investigations of ground conditions for proposed new road alignment. The data
collected were analyzed to obtain characteristic values that were utilized as pavement
design parameters.
Pavement Investigations and Testing
Pavement Condition Survey was undertaken to obtain an initial evaluation of conditions
along the project roads, with particular emphasis on the condition of the existing
pavement. From the results of the Pavement Condition Survey, Pavement strength
testing (Benkelman Beam) was carried out. Subsequently a programme of laboratory
testing was undertaken using the samples
obtained from the above investigation.
Pavement Condition Survey
objective of the pavement condition survey was to get an understanding of the overall
dition of the pavement through visual observation and simple manual measurements. The survey
been conducted based on the specification mentioned in clause 4.2 of IRC: 81-1997. The
ey was conducted in January 2012 by recording observations made from a slowly moving
cle while travelling along the length of the project road. At a regular interval of 1.0 km each,
ement condition survey has been carried out and basic parameters like width and surface
cts were recorded by visual observations.
data collected for every 1.0 km comprised of five categories, these being Road
racteristics, Pavement Condition, Shoulder Condition, Embankment and Drainage Condition.
full record of the Pavement Condition Survey regarding the existing pavement composition is
ched as Annexure 2.02.
Pavement Structural Strength (Falling weight Deflectometer Tests)
project road traverses through plain terrain. For the entire length, the road is a 6-lane
ageway with BC/AC surfacing. The structural strength survey for existing six-lane pavement is
edout using Falling Weight Deflectometer (FWD) technique in accordance with the
edure given in IRC: 115-2014 (“Guidelines for Structural Evaluation and Strengthening of
ible Road Pavements using Falling Weight Deflectometer-FWD Technique”).
objective of this pavement-testing programme was to measure the residual strength that could
mobilized from the existing pavement. In Falling Weight Deflectometer (FWD) test, an impulsive
is applied on the road surface. The magnitude of the load, duration and area of loading is so
sted that it corresponds to the effect of loading due to standard axle on in- service pavement.
deflection of the road surface is measured at a number of points at different distances radially
ward from the centre of the falling weight. Thus, the shape of deflection bowl is obtained. The
ness values can be studied over a period to time to assess the trend in the structural
rioration of pavement and overlay thickness can be designed. For design of overlay thickness,
existing pavement structure (with the stiffness values estimated by FWD) along with the tentative
lay thickness can be analysed to obtain the critical strain value(s). Results of the FWD Tests
enclosed in Annexure 8.01.
Subgrade Investigation for Pavements
erstanding of subgrade or basement soil is very important in the design of pavement
ctures for Highways. Subgrade is normally defined as the supporting structure on which the
ement surface and its special under courses rest. In cut sections, it is original soil below sub-
e material and in fills, subgrade consists of uppermost materials placed in embankments.
eased vehicle speed and axle load has now resulted in the necessity of thorough
stigation of subgrade soil to achieve satisfactory performance under various service
ditions. Subgrade soil sometimes is also referred to as “basement soil.” Generally, soil is used as
grade material and hence the characteristics of soil found in different regions have to be carefully
ied and analysed.
h soil generally consists of mineral matter formed by disintegration of rocks due to action of
er, wind, pressure, temperature etc. All soils generally contain water in varying amount and in
or absorbed form. In most cases, soils are heterogeneous blends of particles of many sizes,
pes and parent material. Structural design of flexible pavement consists of establishing its
total thickness above subgrade and sub-dividing it economically into layers of different
materials so that subgrade and paving layers are not stressed beyond their respective
bearing capacities due to the traffic loads.IRC 37 is generally based on the CBR method of
design for evaluating subgrade strength, in the 4 day soaked condition.
Soil Classification for Highway Purposes
Certain characteristics such as grain size are useful in classifying soils and
predicting the behaviour. Grain size classification as per IS 1498 which is generally
followed is described below:
Soils are generally divided into three divisions namely, coarse grained, fine-grained and
highly organic soils and other miscellaneous soil materials.
Coarse Grained Soils
The coarse grained soils are divided into two sub-divisions, namely:
Gravel
In these soils, more than half the coarse fraction (+75 micron) is larger than 4.75 mm IS
Sieve size. This subdivision includes gravel and gravelly soils.
Sand
In these soils, more than half the coarse fraction (+75 micron) is smaller than 4.75 mm IS
Sieve size. This subdivision includes sand and sandy soils.
Fine Grained Soils
The fine-grained soils shall be further divided into three sub divisions on the basis of the
following values of liquid limit:
Silts and Clays of low compressibility- LL < 35(represented by Symbol L).
Silts and Clays of medium compressibility- LL 35- 50(represented by Symbol I).
Silts and Clays of high compressibility -LL>50 (represented by Symbol H).
Particle Size based Definition of Soil Components
Boulders -Average diameter of particles: > 300 mm
Cobble - Average diameter of particles: 300 mm -75 mm
Coarse Gravel - Average diameter of particles: 75 - 20 mm
Fine Gravel - Average diameter of particles: 20 mm - 4.75 mm
Coarse Sand - Average diameter of particles: 4.75 mm - 2.0 mm
Medium Sand - Average diameter of particles:2.0 mm - 425
Fine Sand - Average diameter of particles: 425µ - 75µ. (0.425mm - 0.075mm)
Silt - Average diameter of particles: 0. 075 mm - 0.002 mm
Clay - Average diameter of particles: < 0.002 mm
Since soils generally consist of one or more of above constituents, they are generally
divided into various groups as fine and coarse-grained soils (generally 9 groups for each
category). Various other classifications such as Unified soil classification system and
AASHTO classifications are
also useful.
Cobble - Average diameter of particles: 300 mm -75 mm
Coarse Gravel - Average diameter of particles: 75 - 20 mm
Fine Gravel - Average diameter of particles: 20 mm - 4.75 mm
Coarse Sand - Average diameter of particles: 4.75 mm - 2.0 mm
Medium Sand - Average diameter of particles:2.0 mm - 425
Fine Sand - Average diameter of particles: 425µ - 75µ. (0.425mm - 0.075mm)
Silt - Average diameter of particles: 0. 075 mm - 0.002 mm
Clay - Average diameter of particles: < 0.002 mm
Since soils generally consist of one or more of above constituents, they are generally
divided into various groups as fine and coarse-grained soils (generally 9 groups for each
category). Various other classifications such as Unified soil classification system and
AASHTO classifications are
also useful.
Based on trial pit excavation & subsequent visual classification, subgrade soils were
identified.
Factors influencing behaviour of Subgrade Soils
Moisture plays a very important role on the behaviour of soils. Soils that have adequate
strength and supporting power under one set of moisture conditions prove to be
unsatisfactory due to seasonal moisture changes. Subgrade soils are influenced by
moisture changes and wherever possible, the design should ensure satisfactory
performance of subgrade under varying moisture conditions with suitable methods.
Properties of soils composed largely of coarse materials are primarily controlled by the
sizes of particles while for soils composed largely of clays and colloids, the properties are
influenced by surface charges and captions.
Density of soil affects its behaviour. In coarse-grained soils, increased density and
decreased moisture due to compaction increases the strength of the pavement. On the
other hand, over compaction of clays that has high affinity for water is not desirable.
Compaction characteristics for subgrade soil is estimated by conducting Modified Proctor
compaction test.
Sub grade Investigation Programme
Evaluation of Subgrade soil characteristics by collecting representative soil samples along
the existing alignment along the entire length. Collection of bulk samples generally at 3
km along the carriageway (existing). For all soil samples, in-situ field moisture content and
bulk density was calculated in the field using standard core cutter method.
Laboratory Tests
The following laboratory tests were performed on representative samples from trial
pits to evaluate characteristics of subgrade soil.
Grain size analysis - Wet Sieve analysis and Hydrometer analysis
Atterberg’s limits - liquid limit, plastic limit and plasticity index
Bulk & Dry Density
Specific Gravity
Modified Proctor compaction test
Preparation of samples at 97% MDD for conducting un-soaked and 4 days soaked
CBR test
The test procedures for grain size analysis, Atterberg’s limits, Bulk & Dry Density,
Specific Gravity, tests have already been explained earlier in this section. The brief
methodology for Modified Proctor Compaction and CBR tests is explained below.
Modified Proctor Compaction Test Procedure
About 6 kg of sample was taken for light compaction. The compaction mould of
1000 cm3 capacity with base plate attached is weighed to the nearest 1gm (w1). One part
of the wet soil compacted in three equal layers using the rammer of mass 2.6kg and free
fall 310mm with 25 evenly distributed blows in each layer for 100mm diameter mould (56
blows for 150mm diameter mould). The second and third layers are similarly compacted.
The loose soil from the outside and
base of the mould was cleaned. The mould with the soil is finally weighed nearest to 1gm
(w2).
The procedure was repeated for six to seven times using a fresh soil specimen after
adding higher water content then the proceeding one till there is either a decrease or no
change in the mass of the wet compacted soil in the mould. Densities obtained in a series
of compactive efforts are plotted against moisture contents. The Position of maximum point
on this curve has been determined. The dry density have been reported to nearest 0.01%
and moisture contest to the nearest 0.2 for values below 5% & 0.5 for values of 5 to 10%.
CBR values for Soaked Samples
The mould containing the test specimen is placed on the lower plate of the testing machine
with the base plate in position and the top surface exposed. Surcharge masses, sufficient
to produce an intensity of loading equal to the weight of the base material (in field) and
pavement is placed on the specimen (if the soaking had been done earlier, the surcharge
then shall be equal to that used during the soaking). To prevent “heave” of soil into the
hole of the surcharge weights, a 2.5 kg annular mass is placed on the soil surface prior to
seating the penetration plunger after which the remainder of surcharge weights shall be
placed. The plunger shall be kept under a load of about 4 kg so that full contact is ensured
between the surface of the specimen and the plunger. The stress and strain dial gauges
are set to initial zero reading. The initial load applied to the plunger is termed as zero load
while determining the load-penetration relation. Load is applied to the penetration plunger
at the rate of penetration equal to 1.25 mm per minute. The load is recorded at penetration
of 0.0, 0.5, 1.0, 1.5, 2.0, 2.5, 4.0, 5.0, 7.5, 10.0 and 12.5 mm. The maximum load and
penetration is recorded for a maximum penetration of 12.5 mm. The plunger, after the
completion of test is raised and the mould is detached from the loading equipment. About
50-100 g of soil is taken immediately below the plunger for water content determination.
The undisturbed test specimen should be examined carefully after the test is completed,
for specimen the presence of any oversize particles as it could affect the test results.
Hence CBR should not be considered meaningful for application to purely cohesion less
soil like sands. If penetration test is to be performed on both ends of specimen, remove the
base plate from the lower end of the mould and fix it on the upper end. Invert the mould
and conduct the test on other end of specimen. In that case, sample from both the
ends is taken for water content determination. The load penetration curve is drawn.
This curve is generally convex upwards, although the initial portion of the curve may be
concave upwards due to surface irregularities. A correction shall then be applied by
drawing a tangent to the upper curve at the point of contraflexure. The corrected
curve shall be taken to be this tangent plus the convex portion of the original curve with the
origin of strains shifted to the point where the tangent cuts the horizontal strain axis.
Thus the penetration of plunger shall be read from this shifted zero point instead of original
zero. Accordingly the corrected load shall be read corresponding to this penetration value.
Laboratory Test Results of Subgrade Soil
The testing programme is based on the concept of project road being composed of a
series of homogenous lengths. Each of these homogenous lengths was assumed such
that idealized soil parameters could be adopted for this stretch. Based on pavement
condition survey it was inferred that the project road is more or less homogenous for
most of its length. All samples were generally air-dried followed by oven drying prior to
testing. Modified proctor compaction test was
performed on representative samples. CBR test on individual samples was carried out at
97%
MDD conditions. CBR test was performed both in un-soaked and
condition. Relevant engineering parameters such as liquid limit and plas
also be evaluated.
Based on testing, complete details with regard to index & Engineering p
grade soil are presented in Table 5.2 below
Table 5.2: Index and Engineering Parameters of Subgrade Soil
Specific gravity G
Sand (%) Silt Clay
(%) (%)
Gravel (%)
MDD(g/cc)
OMC (%)
Medium
Coarse
PI (%)
Fine
bgrade Soil
CBR (%)
Unsoaked
Soaked
28.6 10.4
24.6 8.8
22.8 8.1
BR of 8% can be considered for design
Q = KV
Where Q = Volume
K = Density
V = Speed
Maximum volume that can be accommodated on the road (Qmax, or
time) is considered to be the road capacity. From the idealised relatio
that the maximum volume occurs at half the free speed (maximum sp
jamming density, meaning thereby that
Qmax = (0.5 V ) x (0.5 K )
f j
= (0.25 x V * K )
f j
Equivalency Factors
The need of expressing capacity in passenger car units has trig
studies for establishing appropriate Passenger Car Equivalency (PC
types of vehicles. Notable among the studies carried out in India are
Studies (RUCS) by the CRRI and the MORTH. It has been recognise
vary under different traffic and roadway conditions for any given type
Equivalency Factors are factors to convert the mixed flow of traffic in
express the capacity of road. The unit generally employed is the Pas
(PCU).
The maximum service flow in terms of PCU’s per day in rolling and h
upon the extent of trucks and buses present in the traffic stream, thei
the grades of the alignment, PCU for commercial vehicles vary with t
grade. Further, the passenger car equivalent factor decreases for
with the increase in the
percentage of commercial vehicles.
Construction)
icles
ays
Standards as per IRC: SP: 87-2019 “Manual of
Highways” and IRC: 73-1980 “Geometric Design
have been generally followed. Based on these
Design Standards are given below.
To enable the design of above components, design standards adopte
following paragraphs.
6.4 Classification of Roads
For the purpose of geometric design, rural roads are classified into five main cate
National Highways
State Highways
Major District Roads
Other District Roads
Village Roads
The present road falls under the category of National Highways.
6.5 Terrain
The classes of various terrains as IRC standards are given below in Table 6.2. The
sections varying from Plain to rolling.
Table 6.2: Terrain Classifications as per IRC
hways.
254 f
Where,
V = Design speed in km/hr
t = Perception & break reaction time (taken as 2.5 sec.)
f = Co-efficient of longitudinal friction varying from 0.40 a
0.35 At 100 km/h
es
ows
Radius for some selected design speeds are given in Table 6.7 as per
Table 6.7: Minimum Radii of Horizontal Curves
Nature of Terrain Desirable Minimum Absolute Minimum
Plain and Rolling 400m 250m
Mountainous and Steep 150m 75m
Based on IRC the absolute minimum radius to be provided for a design speed of
m. The minimum radius used for the project road is 145 m.
6.9.2 Super Elevation
As per IRC: SP: 87-2019 Super elevation shall be limited to 7%, if the radius of th
desirable minimum radius. It shall be limited to 5%, if radius is more than
The radius of curve for different speed are given in Table 6.8 below
Table 6.8: Radius beyond which Super Elevation not required
i) Ls = 0.0215 V 3
and ii) Ls =
Where, CR R
Ls = Length of transition in meters V = speed in km/hr
R = Radius of Circular Curve in meter
C = 80 / (75+V), Subject to a maximum of 0.8 and minimum of 0.5
Minimum transition length for some radii is given in Table 17 of IRC: 73-1980.
6.10 Vertical Alignment
Different parameters for vertical alignment are as follows.
6.10.1 Gradients
Ruling gradient will be as a matter of course in design. Limiting gradient will be us
unavoidable circumstances such as topography, cost, etc. Minimum gradient
embankment near level grades are not objectionable when the pavement has suf
drain the storm water laterally. However, in cut sections minimum gradient
considerations is 0.5% if the side drains are lined and 1.0% if these are unlined. T
adopted.
The gradients to be maintained in the design are as per IRC: SP: 87-2019, given
Table 6.9: Gradients for Different Terrain
hr
imum 0.07) ratio in meter per meter. f = co-efficient of side
design speeds are given in Table 6.7 as per IRC: SP: 87-2019
orizontal Curves
2.7 V 2
R
in meters V = speed in km/hr
urve in meter
to a maximum of 0.8 and minimum of 0.5
ses
earance at Vehicular underpasses shall be at least 5.5 m and Light
sed for the feasibility study which is given in Table 6.11 below.
Table 6.11: Relevant Codes for Roads
Ref. No. Title of Standards
IRC:8-1980 Type Designs for Highway Kilometre Stones (Second Revision)
IRC:25-1967 Type Design for Boundary Stones
IRC:31-1969 Route Marker Signs for State Routes
IRC:35-2015 Code Of Practice for Road Markings (Second Revision)
IRC:38-1988 Guidelines for Design of Horizontal Curves for Highways and Design Tables
(First
Revision)
IRC:54-1974 Lateral and Vertical Clearance at Underpasses for Vehicular Traffic
IRC:64-1990 Guidelines for Capacity of Roads in Rural Areas
IRC:66-1976 Recommended Practice for Sight Distance on Rural Highways
IRC:67-2012 Code Of Practice for Road Signs
IRC:73-1980 Geometric Design Standard for Rural (Non-Urban) Highways
IRC:79-2019 Recommended Practice for Road Delineators
IRC:80-1981 Type Designs for Pick-Up Bus Stops on Rural (I.E., Non-Urban) Highways
IRC: 93-1985 Guidelines on Design and Installation of Road Traffic Signals.
IRC:99-2018 Guidelines for Traffic Calming Measures in Urban and Rural Areas
IRC:SP:87-2019 Manual of Specifications & Standards for six laning of Highways
IRC SP:23-1983 Vertical Curves for Highways
IRC SP:41-1994 Guidelines on Design of At-Grade Intersections in Rural and Urban Areas
IRC: SP: 42 –2014 Guidelines for Road Drainage.(First Revision)
MoRTH Specifications for Roads & Bridge Works
Manual for Safety in Road Design
6.12 Design of Bridges, Viaduct, Grade Separators and Railway over Bridges
Design standards that have been followed are:
The bridges and Slab/Box culverts with non perennial flow are provided with
bottom.
The Bridges with vertical clearance more than 2m is accommodated for light
movement
The structures in design chainage Km 29.435 to 61.782 (bridges & culverts) h
with three lane of total width 16.0 m [i.e. carriage way 10.50m + 3.50m (paved sho
(shy off) + 0.50 m x 2 (crash barrier)]. The service road shall be of total width of 1
carriage way + 1.75 m foot path +1.50 m paved shoulder +
0.25 m x 2 shy off 0.50 x 2 crash barriers] along with utility duct for structures.
The design has been based on relevant IRC codes of practice of latest revisio
the IRC codes are not applicable or silent, appropriate BIS, other international cod
as British / American/ Australian codes based on sound engineering practice
The Railway Bridges are proposed as per the RDSO standards, RDSO
RDSO/B-10418.
Codes:
IRC:05-2015 General Details
IRC:06-2017 Loads and Stresses
IRC 112-2020 Code of Practice for Concrete Road Bridge
IRC:78-2014 Design of Substructure
IRC:83-2018 (part-III) Pot, Pot-cum-PTFE, Pin and metallic Guid
2002 Design of Earthquake resistant structures
IRC SP: 87-2019 Manual of Specification & Standards for Si
Highways
IRC: 83-2018 (Part-II) Standard Specifications and code of prac
Bridges: IX Bearing Part II: Elastomeric Bearings. IRC SP-13: 2004
design of small Bridges and culverts
Approach Slab
Concrete Grade : M30
Reinforcement : HYSD steel of grade Fe41
Clear cover to any reinforcements are followed as below:
over Bridges
: 2.5 t/m 3
: 2.2 t/m3
30/M35
SD of grade Fe415/500
30/M35
SD of grade Fe415/500
40
SD of grade Fe500
Nos. of 12T13, 1 No’s 19T13 cable in each
40
SD steel of grade Fe500
30
SD steel of grade Fe415/500
wed as below:
a)Pier, Pier
cap, Abutment,
Abutment Cap
b)PSC Girder and PSC Box Girder : 40mm
c)RCC Desk Slab : 25mm Clear cover to any cables:
a)PSC Girder : 75mm
Bearings: Pot-cum-PTFE bearings will be used.
Wearing Coats: 65 mm thick bituminous wearing coat is provided as per
Specification, consisting of 40mm thick bituminous concrete outlaid with 25mm th
Expansion Joint: Elastomeric strip steel type expansion joints have been consi
Approach Slab: Approach slab containing entire width of the road way (total wid
slab) has been provided with M30 grade R.C.C. (Reinforced Cement Concrete), a
MORTH. The thickness has been considered as 300mm over 100mm thick PCC M
minimum 3.50 m width with one end resting on the dirt wall of the abutment.
6.13 Design of Box Culverts Design Standards
1. The Widening of existing Slab Culvert is done by Box culvert and the length of
upon the existing length of culvert and the total width of proposed roadway.
2. A meeting was held on 10 , 11th and 21 September 2012, at SECON Private
th st
site visit on 24 September with NHAI team. It was decided that where the culvert
th
clearance of more than 2m it shall be used for the pedestrian/light vehicular cross
hence the service road is provided at the bottom
3. The design is based on relevant IRC codes of practice.
4. Live load:
One lane of class 70 R Bogie or 1 lane of 70R Track, whichever is critical. Dead Lo
The Dead loads are computed based on the following unit weights. Reinforced co
2.50 t/m3
F T 1
I
T t 1
c
S
(i) Estimate TD = ( LLc/ )0.434 where L is the length (km) of the
length, Lc
is the distance along the longest stream (km) from a point opposite th
the point of drainage and S is the slope of the stream (m/ Km) of the
Round off TD to nearest full hour
(ii) Locate the bridge on the iso-fluvial map of the specified frequenc
obtain the point rainfall.
(iii) Obtain the storm depth for TD hours by interpolation from the m
rainfall for various duration for the specified frequency.
(iv) Convert the point rainfall (of TD hours duration) to area rainfall (
factor converting point rainfall to area rainfall)
(v) Obtain 1 hour time distribution of the storm in step (iv) by using t
specific duration for the specified period/
(vi) Obtain hourly rainfall and effective rain fall (use specified infiltrat
(vii) Derive 1 hour synthetic unit hydrograph
: 50mm
ox Girder : 40mm
: 25mm Clear cover to any cables:
: 75mm
FE bearings will be used.
m thick bituminous wearing coat is provided as per MORTH
f 40mm thick bituminous concrete outlaid with 25mm thick mastic asphalt.
omeric strip steel type expansion joints have been considered.
ch slab containing entire width of the road way (total width, end to end of
with M30 grade R.C.C. (Reinforced Cement Concrete), as specified in
as been considered as 300mm over 100mm thick PCC M10 grade for
h one end resting on the dirt wall of the abutment.
s Design Standards
ng Slab Culvert is done by Box culvert and the length of widening depends
f culvert and the total width of proposed roadway.
10 , 11th and 21 September 2012, at SECON Private Limited followed with
th st
r with NHAI team. It was decided that where the culverts are having vertical
m it shall be used for the pedestrian/light vehicular crossing the roads and
provided at the bottom
n relevant IRC codes of practice.
- 2.20 t/m
3
the following:-
s wearing coat is provided as per MORTH specification, consisting of 40mm
overlaid with 25mm thick mastic asphalt.
rade
nts are of M-30 RCC unless otherwise specified.
ent
ment has been considered as HYSD bars (Fe-415) conforming to IS 1786.
Joint
slab span less than 20 m, compression seal type expansion joints (40 mm
een considered.
ation
e of discharge data, the flood estimation is carried out using empirical
tional method and unit hydrograph method
y and hydraulic analysis is required for
the effective linear waterway for bridges and culverts
he adequacy of existing vent way
for bridges and culverts and capacity of drains is a function of the flood
ucture needs to cater. The various analyses are:
stimation
ay and afflux for bridges and culverts
ge capacity of bridges
of analysis as specified in IRC. Special publication No.13 is described below:
e of discharge data, the flood estimation is carried out using empirical
tional method and unit hydrograph method. These methods are as follows:
quation
mmon empirical equations used are:
ormula; Q = C1 A ½
Formula; Q = C2 A ¾
C2 are local (Regional) constants and A is the catchment area
constants in these equations are not related to any frequency of occurrence
hod
method is based on simple concept that a rainfall of constant intensity over a
e of concentration produces the maximum discharge, the time of
being defined as the time taken by the water falling at the remote corner of
t to reach the
nt. The maximum discharge is computed by a simple equation.
he maximum discharge
mum intensity of precipitation over the period of time of concentration.
ment area
unit conversion constant.
ec and I in cm / hr and A in hectares, C= 0.028. The time of concentration tc = (0.87L ¾ ) 0.385
ength of longest stream in km and H is the difference in elevation (m).
m intensity of rainfall over a period of time of concentration is
measured and is to be computed from the intensity of rainfall for other
is computed
F T 1
I
T t 1
c
l and medium catchments and the fluvial maps provided there in. The
in the computation are
2g
Where Q = discharge (m /sec) Cw = a coefficient
3
2g L.D (h 1 e
Q = Co
d
Afflux
This has been calculated using discharge formula through bridge ope
continuity equation.
Scour Depth
The scour depth is computed assuming the scoured bed and comput
area velocity method and correcting the scoured bed profile if necess
Hydraulics of pipe and box culverts
These are designed assuming that they function with inlet submerged
discharge the extent of upstream heading depends on the vent way a
be chosen so that the water do not over top the road.
Relevant IRC Codes
IRC codes deal with design of RCC and Prestressed concrete bridge
The relevant codes are as mentioned above.
7 ALIGNMENT AND ENGINEERING
7.1 Geometric Design
Geometric design deals with features linked with the movement of vehicles in a hi
geometric design results in economical operation of vehicles and safety. Geometr
costly and sometimes impossible to rectify later on due to the subsequent
development. Geometric design is influenced by a number of factors among whic
type, composition and volume of traffic, operating speed, land-use characteristics
important. Therefore, it is essential that geometric requirements be adhered to ke
future developments.
7.2 Existing Alignment
The alignment of the Project Highway traverses generally through plain terrain. Se
are situated on either side of the alignment. In rural areas there are private agricu
sides of the road. Due to less rainfall and poor irrigation facilities the cultivation is
road alignment has been designed for 80 kmph speed and it is proposed to be im
The proposed alignment has been generally planned along the existing roa
improvements. Details of the existing alignment are given below. Chainages men
subsequent paragraphs are design chainages as shown in the alignment plan.
7.3 Horizontal Alignment
As per discussions with NHAI, the proposed alignment actually starts at Existing chainage k
29.500. Since the NAVYUG project Road ends at Km 29.435 thus the difference of 65 m is inc
Road.
The proposed alignment starts at km 29.435 and traverses in the North-West dire
Toll plaza at km 30.000.
The alignment traverses in North West direction for about 3.360 km. Further the a
with curve of radius of 800 m and travels in same direction towards T. Begur at km
existing alignment is divided into two separate left and right carriageways. In betw
there is existing built up of T. Begur. The maximum distance between the left and
about 160m. Further the alignment has merged at chainage km 36.100 with a me
The alignment continues in the North West direction with straight alignment upto k
crosses Dodderi village. The alignment is straight up to km 42.240 where it takes
1200m.
The alignment crosses two major junctions viz. Sompura Industrial Area an
47.720 and km 49.280 respectively. The alignment passes through plain te
Land use is generally built up and Industrial areas are present on either side of th
Dobbaspet, there exists a flyover, which starts at km 48.560 and ends at km
49.84. This is a major junction, where NH-207 (which connects to Devanahalli) an
connects to Madugiri) meet NH-4.
The alignment crosses South Western Railway Mainline with a ROB at km 50.360
m. Railway line traverses closely on the left side of the alignment from km
55.640 and built-up areas of Halenijagal, Rayaraplaya and Nandihalli Villages occ
the alignment.
The existing alignment traverses further with a curve of radius 500m at km 55.720
South Western Railway Mainline with a ROB at km 55.800. From Km 56.240 to K
is located very close and parallel to right side of the alignment. At km 57.68, Hireh
located very close to right side of the alignment; approximately 2m from the edge
is built up of Hirehalli Village.
Further the alignment crosses a 4-legged junction where left side connects to Hire
and right side connects to Panditanahalli village at km 59.400. The alignment then
Manchakalkuppe village at km 60.360, where built-up areas are there on b
alignment. The alignment crosses the existing toll plaza at km 61.478.
At km 62.280, 6 lane main carriageway with service road starts and at km 62.320
joins the NH 4. Two vehicular underpasses exist at km 62.520 and km 63.160.
Further the alignment continues in the North West direction with service roads on
crosses Kyatsandra Junction at chainage km 63.750 (4-Legged) with sharp c
radius, here SH-94 existis onthe right side and connects to Siddangamutt and left
Kesaramadu. The area is developed extensively on either side of Kyatsandra Jun
NH 4 and SH 94, it is noticed that pedestrian movement is very high whic
isolation of fast moving traffic from the local traffic by grade separation.
Further the alignment crosses South Western Railway Mainline with a ROB at km
Batavadi with built up area on both sides. NH-206 joins Project road at km 65.440
Shimoga.
Two more vehicular underpasses exist at km 66.115 and km 66.920 with service
the alignment. From km 66.920 to km 68.640 the land use is generally built-up on
built-up on the right side with service road on the either side of the alignment. The
turn with a curve of radius 1500 m at 70.76 and crosses SH 33 to Koratag
Tumkur city on the left with a vehicular underpass at 71.480 and km 72.920 respe
from km 71.480 to end of the Project road is generally built- up (industrial areas) o
alignment. At km 73.160 the Tumkur Bypass ends and merges with old NH-4 from
The project stretch ends at existing km 75.000 stone, which is placed 624 m befo
existing chainage of km 74.376.
7.4 Design Standards
The standards adopted are based on six Laning of Highways through PPP
Specifications and Standards”, IRC 73:1980, MORTH and other internationally
design codes/ practices.
tic unit hydrograph ordinates to give maximum discharge and obtain maximum
discharge.
Design Flood
ood is 50 years. The highest of the floods from different methods is generally
st flood exceeds a limiting value of 1.5 times the next magnitude it is limited to
the limiting value.
Waterway
ridges in non alluvial channels are fixed by W = 9.84(Q50)1/3
erway and Q50 is the discharge curves of 50 years return period.
Discharge through bridge:
This is calculated by
(i) Area velocity method
ed on Manning’s equation for steady uniform flow Q = A 1/n R S 2/3 1/2
2g
= discharge (m /sec) Cw = a coefficient
3
1/2
)
2g
re Co and e = coefficients function of L/W L = Bridge span (m)
= unobstructed width (m)
= downstream depth of flow (m)
U2 = upstream energy head (m)
oject Highway traverses generally through plain terrain. Several major towns
de of the alignment. In rural areas there are private agriculture fields on both
o less rainfall and poor irrigation facilities the cultivation is very low. The existing
n designed for 80 kmph speed and it is proposed to be improved to 100 kmph.
nt has been generally planned along the existing road with some
f the existing alignment are given below. Chainages mentions in the
are design chainages as shown in the alignment plan.
nt
AI, the proposed alignment actually starts at Existing chainage km 29.435 instead of km
project Road ends at Km 29.435 thus the difference of 65 m is included in the Project
in North West direction for about 3.360 km. Further the alignment takes a turn
00 m and travels in same direction towards T. Begur at km 34.900. Here the
ded into two separate left and right carriageways. In between the carriageways
of T. Begur. The maximum distance between the left and right carriageway is
alignment has merged at chainage km 36.100 with a median of width 4.8m.
s in the North West direction with straight alignment upto km 39.640, where it
The alignment is straight up to km 42.240 where it takes a turn with a radius of
raverses further with a curve of radius 500m at km 55.720 and crosses the
Mainline with a ROB at km 55.800. From Km 56.240 to Km 58.120 Railway line
d parallel to right side of the alignment. At km 57.68, Hirehalli Railway station is
ht side of the alignment; approximately 2m from the edge of road and left side
age.
osses a 4-legged junction where left side connects to Hirehalli Industrial Area
o Panditanahalli village at km 59.400. The alignment then crosses
e at km 60.360, where built-up areas are there on both sides of the
nt crosses the existing toll plaza at km 61.478.
in carriageway with service road starts and at km 62.320 Tumkur Ring road
cular underpasses exist at km 62.520 and km 63.160.
ntinues in the North West direction with service roads on both sides and
nction at chainage km 63.750 (4-Legged) with sharp curve of 145 m
is onthe right side and connects to Siddangamutt and left cross road is towards
s developed extensively on either side of Kyatsandra Junction. At junction of
s noticed that pedestrian movement is very high which necessitates
raffic from the local traffic by grade separation.
osses South Western Railway Mainline with a ROB at km 64.640 and crosses
ea on both sides. NH-206 joins Project road at km 65.440 which connects to
erpasses exist at km 66.115 and km 66.920 with service road on both sides of
66.920 to km 68.640 the land use is generally built-up on left side and partially
with service road on the either side of the alignment. The alignment takes a
adius 1500 m at 70.76 and crosses SH 33 to Koratagere to the right and to
ith a vehicular underpass at 71.480 and km 72.920 respectively. The land use
f the Project road is generally built- up (industrial areas) on both sides of the
the Tumkur Bypass ends and merges with old NH-4 from Tumkur city.
at existing km 75.000 stone, which is placed 624 m before the actual length, at
74.376.
Sl.
No. Particulars Details
1 Name of Road NH 4
2 Type of Terrain Plain/Rolling
3 Type of Road National Highway Standard
4 Proposed Cross Section
a) Carriageway 10.5 m (three lane)
b) Paved Shoulders 3.5 m on either side
5 a)Service Road 7m on either side
b)Cross fall/camber 1.5 m on either side
c) On carriageway 2.5%
d) On paved shoulders 2.5%
e) Earthen Shoulders -
6 Design Speed
a) Ruling 100 kmph
b) Minimum 80 kmph
7 Minimum Design speed for Service Road 40 kmph
8 Radius
a) Absolute Minimum radius for circular curves 250 m
b) Desirable Minimum radius for circular curves 400 m
9 Radii beyond which no superelevation is required 1800 m
10 Super Elevation 7% (If curve radius is less than
desirable minimum)
5% (If radius is more than desirable
minimum)
11 Limiting Gradient 3.3%
12 Maximum Gradient change not requiring a vertical 0.5%
13 curve
Minimum Length of Vertical curve 60 m
14 Side Slopes
a) Embankment 1V:2H
b) Cut 1V:2H
7.6 Proposed Alignment
The existing horizontal alignment is proposed to be improved to 6 lane with servic
side for a design spered of 100 kmph, with improvements at existing horizontal cu
radius and transition lengths and also at location of Toll Plaza which are t
per traffic studies. As per provisions of IRC-SP-87-2019 the minimum radius of h
plain and rolling terrain with design speed 100 Km per hour is 400m.
The Project road starts at design chainage km 29.435 and ends at design chainag
total length of the Project road is 44.733 km.
The existing alignment is designed for 80kmph speed and proposed is designed f
horizontal and vertical alignment, which has lead to more filling at some places on
surface.
lignment and vertical profile are as given in
ed to 6 lane with service road on the either
t existing horizontal curves with deficient
oll Plaza which are to be constructed as
e minimum radius of horizontal curves for
is 400m.
ends at design chainage km 74.168. The
kur-Nelamangala direction.
Sl. Design Chainage (km) Length (m) Typical Cross Section as per
No. From To manual
1 29.435 30.420 985.00 Figure 2.7A
2 30.420 30.593 173.00 Figure 2.7I
3 30.593 30.607 14.00 Figure 7.8(A)
4 30.607 30.730 123.00 Figure 2.7I
5 30.730 31.550 820.00 Figure 2.7H
6 31.550 32.092 542.00 Figure 2.7I
7 32.092 32.109 17.00 Figure 7.8(A)
8 32.109 32.208 99.00 Figure 2.7I
9 32.208 32.216 8.00 Figure 7.3(A)
10 32.216 32.400 184.00 Figure 2.7I
11 32.400 33.344 944.00 Figure 2.7J
12 33.344 33.357 13.00 Figure 7.8(A)
13 33.357 33.840 483.00 Figure 2.7J
14 33.840 34.237 397.00 Retained
15 34.237 34.249 12.00 Retained
16 34.249 34.599 350.00 Retained
17 34.599 34.691 92.00 Figure 2.7A
18 34.691 34.713 22.00 Figure 7.3(A)
19 34.713 35.240 527.00 Figure 2.5A
20 35.240 35.759 519.00 Figure 2.7J
21 35.759 35.772 13.00 Figure 7.8(A)
22 35.772 36.440 668.00 Figure 2.7J
23 36.440 36.930 490.00 Figure 2.7A
24 36.930 37.294 364.00 Figure 2.7J
25 37.294 37.307 13.00 Figure 7.8(A)
26 37.307 37.900 593.00 Figure 2.7J
27 37.900 38.900 1000.00 Figure 2.7A
28 38.900 39.193 293.00 Figure 2.7I
29 39.193 39.207 14.00 Figure 7.8(A)
30 39.207 39.440 233.00 Figure 2.7I
31 39.440 39.800 360.00 Figure 2.7C
32 39.800 39.971 171.00 Figure 2.7E
33 39.971 39.989 18.00 Figure 7.3(A)
34 39.989 40.300 311.00 Figure 2.7E
35 40.300 40.748 448.00 Figure 2.7I
36 40.748 40.762 14.00 Figure 7.8(A)
37 40.762 41.190 428.00 Figure 2.7I
38 41.190 41.300 110.00 Figure 2.7A
39 41.300 41.600 300.00 Figure 2.7C
40 41.600 42.870 1270.00 Figure 2.7A
41 42.870 43.045 175.00 Figure 2.7I
42 43.045 43.065 20.00 Figure 7.8(A)
43 43.065 43.257 192.00 Figure 2.7F
44 43.257 43.269 12.00 Figure 7.3(A)
45 43.269 43.393 124.00 Figure 2.7F
46 43.393 43.407 14.00 Figure 7.8(A)
47 43.407 43.560 153.00 Figure 2.7F
48 43.560 44.012 452.00 Figure 2.7A
49 44.012 44.312 300.00 Retained
50 44.312 44.324 12.00 Retained
51 44.324 44.604 280.00 Retained
52 44.604 45.089 485.00 Figure 2.7A
53 45.089 45.097 8.00 Figure 7.3(A)
54 45.097 45.560 463.00 Figure 2.7A & 2.7G
55 45.560 45.743 183.00 Figure 2.7I
56 45.743 45.757 14.00 Figure 7.8(A)
57 45.757 46.980 1223.00 Figure 2.7I
58 46.980 47.020 40.00 Figure 7.8(A)
59 47.020 47.240 220.00 Figure 2.7I
60 47.240 47.500 260.00 Figure 2.7C
61 47.500 47.820 320.00 Figure 2.7A
62 47.820 48.083 263.00 Figure 2.7J
63 48.083 48.117 34.00 Figure 7.8(A)
64 48.117 48.560 443.00 Figure 2.7J
65 48.560 48.731 171.00 Retained
66 48.731 48.739 8.00 Figure 7.3(A)
67 48.739 48.956 217.00 Retained
68 48.956 49.044 88.00 Retained
69 49.044 49.236 192.00 Retained
70 49.236 49.364 128.00 Retained
71 49.364 49.814 450.00 Retained
72 49.814 50.000 186.00 Figure 2.7C
73 50.000 50.237 237.00 Figure 2.5A
74 50.237 50.249 12.00 Figure 7.3(C)
75 50.249 50.321 72.00 Figure 7.8(E)
76 50.321 51.040 719.00 Figure 7.8(A)
77 51.040 51.051 11.00 Figure 7.3(A)
78 51.051 51.200 149.00 Figure 2.7B
79 51.200 51.500 300.00 Figure 2.5A
80 51.500 52.100 600.00 Figure 2.7A
81 52.100 52.660 560.00 Figure 2.7I
82 52.660 52.700 40.00 Figure 7.8(A)
83 52.700 53.320 620.00 Figure 2.7I
84 53.320 53.432 112.00 Figure 2.7A
85 53.432 53.440 8.00 Figure 7.3(A)
86 53.440 54.760 1320.00 Figure 2.7A
87 54.760 55.152 392.00 Figure 2.7I
88 55.152 55.169 17.00 Figure 7.8(A)
89 55.169 55.380 211.00 Figure 2.7I
90 55.380 55.500 120.00 Figure 2.7C
91 55.500 55.924 424.00 Figure 2.5A
92 55.924 55.997 73.00 Figure 7.8(E)
93 55.997 56.003 6.00 Retained
94 56.003 57.180 1177.00 Figure 2.5A
95 57.180 57.593 413.00 Figure 2.7I
96 57.593 57.607 14.00 Figure 7.8(A)
97 57.607 58.060 453.00 Figure 2.7I
98 58.060 58.400 340.00 Figure 2.7D
99 58.400 58.980 580.00 Figure 2.7A
100 58.980 59.439 459.00 Figure 2.7J
101 59.439 59.452 13.00 Figure 7.8(A)
102 59.452 59.720 268.00 Figure 2.7J
103 59.720 60.320 600.00 Figure 2.7C
104 60.320 60.753 433.00 Figure 2.7I
105 60.753 60.767 14.00 Figure 7.8(A)
106 60.767 60.976 209.00 Figure 2.7I
107 60.976 60.984 8.00 Figure 7.3(A)
108 60.984 61.000 16.00 Figure 2.7I
109 61.000 62.040 1040.00 Toll Plaza
110 62.040 62.218 178.00 Figure 2.8A
111 62.218 62.238 20.00 Figure 7.3(A)
112 62.238 62.317 79.00 Figure 2.8A
113 62.317 62.547 230.00 Retained
114 62.547 62.569 22.00 Retained
115 62.569 62.809 240.00 Retained
116 62.809 63.084 275.00 Figure 2.8A
117 63.084 63.204 120.00 Retained
118 63.204 63.216 12.00 Retained
119 63.216 63.296 80.00 Retained
120 63.296 63.545 249.00 Figure 7.8(B)
121 63.545 63.975 430.00 Figure 7.8(B)
122 63.975 64.300 325.00 Figure 7.8(B)
123 64.300 64.523 223.00 Figure 2.7I
124 64.523 64.548 25.00 Figure 7.8(C)
125 64.548 64.614 66.00 Figure 7.8(C)
126 64.614 64.686 72.00 Figure 7.8(E)
127 64.686 64.813 127.00 Figure 7.8(C)
128 64.813 64.838 25.00 Figure 7.8(C)
129 64.838 65.100 262.00 Figure 2.7I
130 65.100 65.71 610.00 Figure 2.8A
131 65.713 66.113 400.00 Retained
132 66.113 66.155 42.00 Retained
133 66.155 66.645 490.00 Retained
134 66.645 66.828 183.00 Figure 2.8A
135 66.828 66.848 20.00 Figure 7.3(B)
136 66.848 66.878 30.00 Figure 2.8A
137 66.878 66.928 50.00 Retained
138 66.928 66.942 14.00 Retained
139 66.942 67.172 230.00 Retained
140 67.172 67.300 128.00 Figure 2.8A
141 67.300 67.437 137.00 Figure 2.8A
142 67.437 67.453 16.00 Figure 7.3(B)
143 67.453 67.700 247.00 Figure 2.8A
144 67.700 67.820 120.00 Figure 2.8A
145 67.820 67.830 10.00 Figure 7.3(B)
146 67.830 67.978 148.00 Figure 2.8A
147 67.978 68.098 120.00 Retained
148 68.098 68.119 21.00 Retained
149 68.119 68.309 190.00 Retained
150 68.309 68.754 445.00 Figure 2.8A
151 68.754 68.770 16.00 Figure 7.3(B)
152 68.770 68.897 127.00 Figure 2.8A
153 68.897 68.907 10.00 Figure 7.3(B)
154 68.907 69.345 438.00 Figure 2.8A
155 69.345 69.357 12.00 Figure 7.3(B)
156 69.357 69.859 502.00 Figure 2.8A
157 69.859 69.919 60.00 Retained
158 69.919 69.933 14.00 Retained
159 69.933 70.003 70.00 Retained
160 70.003 71.179 1176.00 Figure 2.8A
161 71.179 71.197 18.00 Figure 7.3(B)
162 71.197 71.267 70.00 Figure 2.8A
163 71.267 71.497 230.00 Retained
164 71.497 71.519 22.00 Retained
165 71.519 71.639 120.00 Retained
166 71.639 72.805 1166.00 Figure 2.8A
167 72.805 72.935 130.00 Retained
168 72.935 72.977 42.00 Retained
169 72.977 73.247 270.00 Retained
170 73.247 73.460 213.00 Figure 2.8A
171 73.460 73.789 329.00 Figure 2.7I
172 73.789 73.812 23.00 Figure 7.8(B)
173 73.812 74.020 208.00 Figure 2.7I
174 74.020 74.168 148.00 Figure 2.8A
TOTAL LENGTH, m 44733
TOTAL LENGTH IN KM 44.733
tion of Project Highway is generally 6 lane on either side with
Remarks
Approach
VUP
Approach
Approach
VUP
Approach
MNB (Reconstruction)
Approach
Approach
VOP
Approach
Approach
VUP Retained
Approach
MNB (widening)
Approach
VOP
Approach
Approach
VOP
Approach
Approach
LVUP
Approach
MNB (widening)
Approach
LVUP
Approach
Approach
VUP
Approach
MNB (Reconstruction)
Approach
LVUP
Approach
Approach
VUP Retained
Approach
MNB (Widening)
Approach
LVUP
Approach
Flyover
Approach
Approach
VOP
Approach
Approach
MNB (widening)
Approach
Existing Fly Over
Approach
Existing Fly Over
Approach
MNB (widening)
ROB
Approach
MNB (Reconstruction)
Approach
VUP
Approach
MNB (widening)
Approach
VUP
Approach
ROB
VUP Retained
Approach
LVUP
Approach
Approach
VOP
Approach
Approach
LVUP
Approach
MNB
Approach
Toll
MNB (widening)
Approach
Grade Separator Retained
Approach
Approach
Non VUP Retained
Approach
Approach
Fly Over
Approach
Approach
VUP
Approach
ROB
Approach
VUP
Approach
Approach
Grade Separator Retained
Approach
MNB (Widening)
Type 3
Approach
Non VUP Retained
Approach
MNB (Widening)
MNB (Widening)
Approach
VUP (Existing)
Approach
MNB (widening)
MNB (widening)
MNB (widening)
Approach
Non VUP Retained
Approach
MNB (widening)
Approach
VUP Retained
Approach
Approach
Grade Separator Retained
Approach
Approach
LVUP
Approach
7.8 Proposed Widening
The option of widening is based on the existing ground features viz. settlements,
tanks, water bodies, existing curve direction, bridges, rock outcrop, utilities etc.
Since the widening is from 4 lanes to six lanes, major portion of the Project road i
widened on the either side of the road with existing centreline. However, where ad
available some of the alternative measures have been proposed such as realignm
Flyover/VUPs. The proposed widening schedule is given below in the Table 7.4.
Table 7.4: Proposed Widening Schedule
In the existing ROB, left carriageway is two lanes and right carriageway is three la
older of the two. In order to provide a six lane ROB, it has been decided by NHAI
lane ROBs for the right carriageway and to use the existing two lane ROB as Serv
Details of Realignments at the ROBs and other locations are given below:
7.9.1 Realignment at T. Begur (km 34.800 to km 36.150)
The existing alignment at this stretch is divided into two separate carriageways as
between left and right carriageway. It is observed that both sides of left carriagew
partial built-up area exists on right carriageway. Development of 6 lanes with serv
involves large demolition of buildings and land acquisition. Hence, 6 lane with pav
and earthen shoulder is developed on existing right carriageway and left ca
proposed to be used as service road on left side.
provided.
o km 51.500)
alignment is shifted towards right
lose to railway line which is parallel to
ay (ROW) of 60m should be
Sl. Location of Service road Right hand side (RHS)/ Left Length (km) of
No. From (km) To (km) hand side (LHS)/ or Both sides service road
(km 64.200-65.100)
een proposed on the right side of existing ROB, necessitating
towards right side.
Remarks
Service Road on RHS
varies from 5.50m upto
7.00m due to Protected
Forest Land on RHS
(Ref.:- Figure - 2.7H)
Existing Dabaspet
Flyover
Proposed Flyover at
Kyatsandra
sidered for:
road pavement
n either side
r Construction)
cial Vehicles has been considered as per ToR
Since the directional distribution of vehicles is in the range of
ution has been considered in design
The present section between Nelamangala (km 29.435) to Tumkur to
is having 4 lane divided carriageway with paved shoulder and from k
74.168 is having six lane without paved shoulder. It is decided to prov
carriageway with paved shoulder from km 29.435 to km 61.146 and f
74.168 shall be retained with overlay on main carriageway. Consider
parameters and the expected MSA along the corridor is estimated
lane configurations with estimated Vehicle Damage Factors and pr
below.
Following are the details considered in calculation of MSA for various
the Parameters and the MSA calculations based on the present
sections are presented in Table 8.1 and Table 8.2 below.
Table 8.1: Design Details for Calculation of MSA
Details
2-Axle Trucks
3-Axle Trucks
MAV (4 to 6
Wheelers
Wheelers
(Above 6
Axles)
Axles)
LCV-4
LCV-6
Govt Bus
MAV
Pvt Bus
Lane Distribution D= 60% 60% 60% 60% 60% 60% 60% 60%
Factor
Vehicle Damage F= 0.602 0.602 1.083 1.083 4.512 6.730 6.697 9.227
Factor
Traffic Distribution Td = 50% 50% 50% 50% 50% 50% 50% 50%
Table 8.2: Summary of the Design MSA at all Locations for different Durations
Year/ VC-1 at Km VC-4 at Km VC-7 at Km Remarks
Locations 30.600 62.000 74.000
2012 6.61 7.15 6.18 Present MSA
2015 20.85 22.54 19.47 MSA by Opening to Traffic
2019 63.15 68.27 58.97 MSA for 5 Years after Opening to Traffic
2024 117.14 126.64 109.38 MSA for 10 Years after Opening to Traffic
2029 186.04 201.13 173.73 MSA for 15 Years after Opening to Traffic
2034 273.98 296.20 255.85 MSA for 20 Years after Opening to Traffic
8.1.3 CBR of Existing Soil
Subgrade investigations have been undertaken for the project road. It can be note
CBR values at 97% MDD condition is generally 8-10. This satisfies the minimum r
value of 8%.
CBR of 8% has been adopted for the pavement design. Based on all the paramet
the new pavement composition as per IRC 37-2018 is furnished in Table 8.3.
8.2 Sub Grade Characteristics
8.2.1 New Carriageway and Alignment
For the purpose of this report it has been assumed that all new carriagew
alignments will be constructed such that the final grade is minimum of 1.4 m abov
level in flat terrain & will follow gradient as per design in sloping ground, generally
order of 2.5%. Minimum CBR value of 8% has been assumed for the general fill.
ferent Durations
ect road. It can be noted that 4 day soaked
satisfies the minimum required design CBR
From IRC: 37-2018, for a CBR of 8% the following design has been d
Table 8.3
below
Table 8.3: Pavement Composition for New Carriageway
Shoulder Designs
As per IRC the shoulders is to consist of a total outer shoulder of 3.5
comprising 3.5 m of paved shoulder. The design adopted for the sam
Hard Shoulders
Hard shoulders are to be constructed of the same pavement layers a
carriageways such that the pavement layers under the main carriage
to the hard shoulder. This design allows for vehicles to use the h
running service in times of maintenance, or accidents, on the main
also facilitates any future widening of the road in that the hard sho
have to be rebuild to be incorporated in the main carriageway.
Service Road Pavement Thickness
The expected traffic on the service road is negligible, to provide bette
cross road traffic and the built up areas, the service road is designed
CBR of 8% are adopted and the following pavement thickness as giv
Table 8.6: Service Road Pavement Thickness
cedure described in IRC 37-2018. Since
t has been designed using IIT
37-2018.
Suggested
Overlay,
Desig mm
Check
n msa DB
BC M
217.08 SAFE 50 90
sub base is recommended. A subgrade CBR of 8% was adopted for all new pave
the k values to CBR relationship given in the standard; this is equi
approximately 5. Hence, it has been assumed that a DLC sub base
As recommended in the standard the following design values were
IRC:58- 2015
Flexural Strength of concrete = Not less than 45kg/cm
Modulus of elasticity of concrete = 3 X 10 kg/cm
5 2
esign
ations (straight portion), rigid pavement is proposed to withstand the
and heavy traffic.
oped in response to changes in legal truck loading limits and to update the code
tices. The standard derives the capacity of a particular design pavement through
gue Analysis. For given set of design parameters the standard generates a
epetition of a particular load applied at the edge of the pavement, the edge
predictions of the actual repetitions at given load level are less than the limits
eptable. Based on work performed by the Portland Cement Association (PCA),
ed to be capable of sustaining an infinite number of repetitions if the ratio of the
he load is less than 0.45 of the flexural strength of the concrete.
uires that the combination of the edge stress generated by a combination of
erature changes do not exceed the flexural strength of the concrete.
a sub-base to the pavement if the modulus of sub-grade reaction (k) is less than
nds that if the above applies, then a Dry Lean Concrete (DLC)
nded. A subgrade CBR of 8% was adopted for all new pavements, using
alues to CBR relationship given in the standard; this is equivalent to a k value of
mately 5. Hence, it has been assumed that a DLC sub base will be required.
ommended in the standard the following design values were adopted as per
- 2015
l Strength of concrete = Not less than 45kg/cm at 28 days.
2
esigned thickness of rigid pavement for Toll Plaza, obtained from IRC:58-
s presented in Table 8.8.
8: Proposed Rigid Pavement Design for Toll Plaza
Material Type Layer Thickness in mm
Pavement Quality Concrete (M-40) 300 mm
Dry Lean Concrete (M-10) 150 mm
9 DESIGN OF TRAFFIC CONTROL AND OTHER FACILITIES
9.1 Road Furniture
Road furniture consists of road signs, road markings, arrow marking, road delinea
and boundary stones which are provided at locations adding to the road user safe
9.1.1 Road Signs
Cautionary, mandatory and informatory signs are provided depending on the
function they perform in accordance with the IRC: 67-2012 guidelines for R
different types of road signs are categorized and provided are:
i. Mandatory / Regulatory
ii. Cautionary / Warning
iii. Directional
iv. Hazard Markers
v. Informatory
The Code of Practice for Road Signs, IRC: 67-2012, is followed for sizes, configu
location of all road signs.
9.1.2 Road Markings
Road markings perform the important function of guiding and controlling traffic on
markings serve as psychological barriers and signify the delineation of traffic path
clearance from traffic hazards for safe movement of traffic. Road markings are the
ensure smooth and orderly flow of traffic and to promote road safety. The Code o
Markings, IRC: 35-2015 has been used in the study as the design basis. Schedul
are included in contract drawings.
The following road markings are provided:
Longitudinal markings : Center Line
: Edge Lines
Intersections : Stop Lines
: Word “STOP”
: Pedestrian Crossing
: Approach to Intersection
: Direction Arrows
: Continuity Lines
: Traffic island
Parking : Bus Stop
: Emergency Parking
The road marking material will be hot applied thermoplastic reflective as per C
Specifications.
OL AND OTHER FACILITIES
Lines
Stop
are in accordance with IRC: 8-1980 guidelines. Both ordinary and fifth
as per the schedule given in tender drawings. Kilometre stones are
the road as one proceeds from the station from which the Kilometre
shall be fixed at right angles to the centre line of the carriageway.
undary Stones (RBS)
d boundary stones conform to IRC: 26-1967 and IRC: 25-1967. 200m
e side of the road as the kilometre stones. The inscription on the stones
nd 8 marked in an ascending order in the direction of increasing
g station. The numerals shall be 80mm high. The colour of the
hite background. Boundary stones shall be located on either side of the
e and kilometre stone. In addition these shall be fixed at all angular
the boundary is on a curve or the land is of significant value and likely
undary stones, as required, shall be installed at closer intervals.
boundary, shall be inscribed on each stone and below it the name of the
s i.e., NH.
e of Intersections, Channelising and Divisional Islands.
mination have been provided in the built up areas on both sides above
kerbs. The width of sidewalk is 1.5m. The footpath shall be provided at
able 9.2 below:
nd Street Lights
st lighting proposed to be provided at junctions keeping in view the
operative Highway Patrol unit at the Toll plaza locations, which shall
y and remain in contact with control room. The patrol Vehicle shall be
sonnel besides the driver and space to carry essential traffic and
fety tools.
nd a siren on board and fitted with a GPS based vehicle tracking system
hr x 7 days of a week basis. It shall be equipped with
ories for traffic control which are fully visible during night time. Each
owing equipments:
glass(2 no)
er container with fresh water (1 no) and funnel
oves(1 pair each)
t(4 pairs), Blanket(1 no)
t (4 pairs), Blanket(1 no)
Batteries, Flashing light(1 no)
n, Animal hook, rope
tape
encils, folders
r proof sheets, stretchers(2 nos)
a
ments
es
etting up medical aid posts. Ambulance shall be provided at the toll
at least two trained paramedics shall be available on the Project
ime is not more than 10 minutes of call. Each ambulance shall be
aving medical services and support system implements for
nearest trauma hospitals, and providing emergency medical aid during
ccident site to the nearest trauma hospital. It shall have a light on its top
with a GPS based vehicle tracking system to monitor its movement on
The vehicle shall be Matador/Swaraj Mazda/Tempo Traveller of white
stretchers.
quate capacity (minimum 20 MT) at each toll plaza location with all
can reach the site of the incident within 30 minutes of call and clear the
shall also be fitted with a GPS based Vehicle Tracking system to
days of a week basis.
nt System (ATMS)
nd the clock shall be established for informing the road users of the
tions on the Project Highway, for making interventions as required for
c operation and for providing rescue and relief to the users in distress.
f
ous sources such as the road, the users, the maintenance and
e, and the intervention team
(ii) Three way communication between the data source and a Central Control Roo
and the data sources and display units, and between the maintenance and opera
transmission system
(iii) A Central Control Room to process all data and control the highway operation
9.7.1 Data acquisition system
This shall consist of
(a) Automatic Traffic Counter and Classifier (ATCC), with an in-road loop detector
(b) Video cameras installed on road with such pan and tilts that a length of 2 km r
video monitoring of traffic
(c) Emergency Call Boxes installed at every 2 km to enable any user to be instant
Control Room,
(d) Meteorological sensors for capturing data on temperature, weather, wind
(e) Mobile radios for patrol vehicles and ambulances to be in communication with
Room and among themselves
9.8 Variable Message Signs (VMS)
Variable message signs will be modular with sign panels using LEDs/High Gain tr
for outdoor ambient lights. The sign panel should be such that a display is liable fr
200m.The minimum height of the characters shall be 300 mm. The equipment sha
storing minimum 10 frames that can be triggered on receiving the tele command.
clearance available at VMS shall be 5.5m from the road surface. The driver can s
road conditions like
Situation of upcoming traffic and alternate routes
Traffic deviations
Road work warnings
Level of air pollution
Potential road closure advice
Emergency situations
General traffic conditions or speed variations
Public transportation availability and real-time information
Date, time and temperature
Road hazards including fog, ice, incident etc
Speed Limit Signs
Messages of public utility
The locations for VMS shall be given in the Table 9.3 below:
Table 9.3: Location of VMS
unter and Classifier (ATCC), with an in-road loop detectors and treadles.
ed on road with such pan and tilts that a length of 2 km road is captured for
c
es installed at every 2 km to enable any user to be instantly in contact with the
re advice
ns
tions or speed variations
n availability and real-time information
erature
ding fog, ice, incident etc
utility
hall be given in the Table 9.3 below:
m
ntrol room where all the data acquired from field and their processing, storing
all be operated and maintained from central control room. CCR shall have
software:
erver with integrated ATMS and ATMS software.
erminal for operation of the integrated traffic management system.
nt comprising operator PC along sub systems and digital voice recorder
comprising operator PC and engineering terminal
k Management system for fiber optic communication system.
ment
AVCC, Traffic control
Length minimum 3000 mm and Height minimum 1200 mm)
back up system.
enance
on and maintenance center at toll plaza for various operation and
h following minimum facilities:
administrative block Workshop
air shop Testing laboratory
n and maintenance
g
roposed on the project corridor with a capacity of 100 trucks. Facilities like Dhaba
tions etc shall be provided. Location of Parking is given in Table 9.5 below.
pment and industrial development in the project stretch is vast. The day to day
uch more than expected. The proposed truck parking at design chainage km
S was feasible based on the site visits carried out before submission of Draft
But during the course of time, a building is under construction for a proposed
e at this location. Considering the development, the location becomes non- feasible.
ovide truck parking behind the BPCL petrol bunk which is adjacent to land identified
e chain age, after considering the legal and socio economic issues.
submission of Final Feasibility Report, a site visit was organised along with the
013 followed with review by CGM at NHAI RO on 18 October 2013 In the meeting it
provide amenities at the existing Toll plaza-1 as it will be dismantled hence a truck
d at the location. Also a truck parking has been proposed at 46.950 beside the
rovided at locations of existing and proposed service road and the locations given in
n
designed with consideration of service road. These
ned with a minimum entry and exit radii as per IRC
ovided with deceleration and acceleration lanes to facilitate
or from the highway traffic. These intersections have also
signed Channelising and Divisional Islands as per IRC
movement of various turning traffic with easy manoeuvres.
Table 9.8) and fifty seven minor junctions (Table 9.9) where
per access to various directions are designed.
s
Cross Road
To Shivaganga (L)
To Dabaspete (R)
To Nijagal (R)
To Siddaganga Matt (R)
To Kyatasandra (L)
To Arakere (R) To
Tumakuru (L)
s
Sl. No. Existing Chainage Type
(Km) Junction Cross Road
20 43.00 T Junction To Hanumanthapura
21 43.40 T Junction To Gundenahalli
22 43.40 T Junction To Aladahalli
23 44.48 T Junction To Thyamagondlu
24 44.48 T Junction To Village
25 45.58 T Junction To Hosahalli
26 46.10 Y To Kengal Kempahalli
27 46.20 junction
T Junction To Avverahalli & Gottigere
28 46.55 Y To K G Srinivasapura
29 47.00 junction
Y To Bharathipura
30 47.69 junction
T Junction To Sompura Industrial Area
31 48.20 T Junction To Village
32 49.32 Y To Devara Hosahalli
33 49.95 junction
T Junction To Village
34 51.21 T Junction To Muddanayakanahalli
35 52.03 T Junction To Hosanijagal
36 52.67 T Junction To Rayanapalya
37 54.30 T Junction To Hale Nijagal
38 55.31 T Junction To Nandihalli
39 56.50 Y To Devarahalli
40 56.83 junction
T Junction To Chikkahalli
41 58.10 T Junction To Kodihalli
42 58.23 T Junction To Vrdigere
43 59.04 Y To Factories
44 59.36 junction
T Junction To Singanahalli Colony
45 59.36 T Junction To Urdigere
46 59.88 T Junction To Factories
47 60.40 T Junction To Village
48 60.40 T Junction To Village
49 61.35 T Junction To Machanahalli
50 62.95 T Junction To Mydala
51 63.90 Y To Kyatsandra Town
52 65.30 junction
Y To APMC Yard, Tumkur
53 65.89 junction
Y Junction City
To Devarayapattana
54 69.00 T Junction To Vaddarahalli
55 72.40 T Junction Inside Industrial Area
56 72.60 T Junction Inside Tumkur City
57 73.73 T Junction To Industrial Area, Tumkur
Typical intersections are presented in Drawings as Volume IV.
9.17 Median Openings
Median openings of length 20 m shall be provided for emergency and for repair/ m
with detachable guard barrier. Zebra crossing shall be provided at all median ope
of median openings are given in the Table 9.10 below:
Table 9.10: List of Median Opening
Sl. No of
No Type of Structure Structures
Proposed
1 Minor Bridges 18
2 Major Bridges 04
3 Fly Over 03
4 Road Over Bridges 03
5 VUP/LVUP 18
6 Vehicular Overpass 05
7 Cross Drainage Structures 73
8 Foot Over Bridge 02
Total 126
10.1 Improvement Proposals and New Proposals
New structures for bridges and culverts are planned in advance duly considering
investigations already conducted and the data collected. Most of the existing struc
condition which will be retained. Few Culverts are choked with silt and vegetation
to structural components which will be retained by cleaning. The following guide l
have direct bearing in preparing the proposals for alternative designs for the vario
Hydraulics, i.e. to satisfy the linear water way and the required vertical clearan
Existing bridges are widened to accommodate 3 lane carriage way with servic
The widened bridges are provided with one span for faster construction.
Improvement to riding quality i.e., providing minimum number of expansion joi
Durability in terms of quality during construction.
Construction facility for fast progress ascertaining quality to confirm dura
modular approach with central casting yard.
Safety and economy.
Based on the observations made during inventory and condition survey new struc
listed and submitted in Indicative General Arrangement Drawings (GAD) report. F
on 17 Apr 2012 with NHAI officials, few of the proposed locations were approved
suggested by the team. The same was submitted in the DFR. Also the meeting he
September, changes in structure location, proposal of new ROB, re- location of fe
additional underpass, change in the span arrangement, location of the service roa
bridges were suggested. A brief note on all the type of existing and proposed stru
same is incorporated in the FFR.
Minor Bridges and Major Bridges:
There are about 18 minor bridges in the project Highway. The widening of the brid
by providing dry joint without affecting existing structure. Foundations of new struc
placed without affecting existing foundations.
The existing bridges have been proposed with rehabilitation measures such
clearing, cleaning of expansion joints, painting on super structure and crash barrie
superstructure and substructure wherever necessary.
2 bridges at 32.212, 43.263 and 60.980 are suggested for reconstruction due to p
VUP’s the RE wall approaches will be on these bridges. The concessionaire shall
adequacy of bridge for the load bearing and can take appropriate decision during
Further it is to be noted that across the tanks Minnor Bridges are proposed. Howe
law, major bridges are to be proposed. In this regard Major Briges are proposed a
The list of the major bridges proposed are provided below
The list of the Minor Bridges is given in Table 10.13
AND STRUCTURES
oad crosses few streams, nalas and major roads for which bridges and grade
e been provided free movement of the traffic. There are 3 Railway Over Bridges in the
y.
ntory and condition survey was carried out as per the requirements of the
d mandated by Terms of Reference (TOR). The details are attached as Annexure
respectively. The information collected has been analyzed and used for assessing
rovement needed for the structure. Details of Inventory and existing condition have been
port on Indicative GAD of Structures, submitted on 22 March 2012.
nd
the discussion with NHAI at RO Bangalore on 10 and 11 January 2019, the proposals
ere modified. The documents were further modified as per the review meeting and site
Sep 2020 Further, it was informed to NHAI that there is no standard RDSO drawings
OB with 72 m span for 6 lane and hence 2 bridges of 72 m span with 4 lane
e proposed. Also, during the video conference held with member technical on 24
s suggested to propose the project in single package with 2 phases. The cross sections
dges were modified.Further Major bridges were provided in the tank area at the service
accordance with KTCDA laws.
f service roads from design chainage from 29.435 to 74.168 and construction of main
om design chainage 61.520 to 74.168 including Tumkur bypass
f main carriage way from design chainage 29.435 to 61.520 excluding Tumkur bypass
ing and proposed structures are given in Table 10.12 below.
mary of Proposed Structures
ment Proposals and New Proposals
for bridges and culverts are planned in advance duly considering the various
already conducted and the data collected. Most of the existing structures are in good
h will be retained. Few Culverts are choked with silt and vegetation without any damage
mponents which will be retained by cleaning. The following guide lines are considered to
aring in preparing the proposals for alternative designs for the various bridges.
i.e. to satisfy the linear water way and the required vertical clearance.
dges are widened to accommodate 3 lane carriage way with service roads.
d bridges are provided with one span for faster construction.
nt to riding quality i.e., providing minimum number of expansion joints.
terms of quality during construction.
n facility for fast progress ascertaining quality to confirm durability through
ach with central casting yard.
economy.
observations made during inventory and condition survey new structures proposed were
mitted in Indicative General Arrangement Drawings (GAD) report. Further site visit made
2 with NHAI officials, few of the proposed locations were approved and changes were
he team. The same was submitted in the DFR. Also the meeting held on 10 , 11 and 21
th th st
anges in structure location, proposal of new ROB, re- location of few structures,
erpass, change in the span arrangement, location of the service road to the minor
uggested. A brief note on all the type of existing and proposed structure is given and the
orated in the FFR.
d Major Bridges:
ut 18 minor bridges in the project Highway. The widening of the bridges has been done
y joint without affecting existing structure. Foundations of new structures have been
affecting existing foundations.
bridges have been proposed with rehabilitation measures such as vegetation
ng of expansion joints, painting on super structure and crash barrier, jacketing in
and substructure wherever necessary.
.212, 43.263 and 60.980 are suggested for reconstruction due to proposal of additional
wall approaches will be on these bridges. The concessionaire shall check for the
idge for the load bearing and can take appropriate decision during the time of execution
be noted that across the tanks Minnor Bridges are proposed. However as per KTCDA
ges are to be proposed. In this regard Major Briges are proposed at the tank location.
major bridges proposed are provided below
Minor Bridges is given in Table 10.13
Table 10.13: Proposed Span Arrangement and widening width for Minor Bridge
Details of Minor Bridges to be Reconstruction.
Remarks
Reconstruction
Reconstruction
Reconstruction
repairs
Right
SR
11.75
11.75
-
Below
Existing
Flyover
-
11.75
11.75
11.75
11.75
11.75
11.75
11.75
11.75
11.75
11.75
h rehabilitation as the bridge comes under
es
Remarks, if any
lverts.
Design Span /
S. No. Chainage Opening (m) Proposal Remarks, if any
(Km)
59 63.167 3 x1.2m dia Widening Pipe
60 64.099 1x6x2 Reconstruction Box Flyover approach
61 65.031 2 x 0.9m dia Widening Pipe
62 68.09 1 x 1m dia Widening Pipe
63 68.121 1 x 1m dia Widening Pipe
64 68.997 3 x 1.2m dia Widening Pipe
65 69.07 1 x 1m dia Widening Pipe
66 70.373 1 x 1m dia Widening Pipe
67 70.389 1 x 1m Widening Pipe
dia,
68 70.811 1 x 54.0m
0.9m dia Widening Pipe
69 71.464 2 x 0.9m dia Widening Pipe
70 71.519 1 x 0.9m dia Widening Pipe
71 72.584 3 x 1m dia Widening Pipe
72 73.536 1x2x2 Reconstruction Box LVUP approach
73 73.658 1 x 3.6 Reconstruction Box LVUP approach
Table 10.17: List of Proposed Flyovers
Sl. Chainage (km) Length Span Arrangement Remark/Town
No. From To (m) (No. X Span, m) Name
1 46.980 47.020 20 2 x 20 x 5.5 -
2 52.660 52.700 20 2 x 20 x 5.5 -
3 63.545 63.975 430 13 x 30 + 1 x 40 -
Table 10.18: List of Proposed Foot Over Bridge
Design Chainage Span Arrangement Deck width Remarks
Sl. No. in Km Location (No. x Length m) (m)
Culverts:
Box culverts have been provided to widen the existing slab culverts. E
levels of pipe culvert at upstream or downstream sides have been ma
flow of water from end to end, depending upon the total length of pipe
length in multiple of 2.500m length is proposed for widening with requ
pipe culvert with diameter less than 0.9m is replaced with 1.2m diame
The other pipe culverts of diameter 0.9m and above are extended wit
diameter as per IRC SP 87:2019. Detail Investigation to be done by t
before construction for ascertaining strength of existing structure and
based on which the proposal
may be modified according to requirement.
Remarks
To be Extended as
per site condition
ed.
icular/Subways).
or the existing bridges.
habilitated as follows.
d and corroded will be cleaned and
and covered with epoxy mortar.
mantled and re-constructed as crash
to Tumkur including Tumkur By pass and stretch pass through major built-up like
and Kyatasandra.
Karnataka - General
As per details from Census 2011, Karnataka has population of 6.11 Crores, an inc
5.29 Crore in 2001 census. Total population of Karnataka as per 2011 cen
which male and female are 30,966,657 and 30,128,640 respectively. In 2001, tota
52,850,562 in which males were 26,898,918 while females were 25,951,644. The
growth in this decade was 15.60 percent while in previous decade it was 17.25 pe
population of Karnataka forms 5.05 percent of India in 2011. In 2001, the figure w
5.14 percent.
a. Cereals = 87.37
b. Pulses = 20.28
c. Total food grains = 107.65
d. Oil seeds = 9.70
e. Cotton = 12.24
f. Sugar Cane = 315.00
g. Tobacco = 0.89
D. Industries (2009-10)
1. Small Scale industries = 17195
2. Factories = 12559
E. Education (2009-10)
1. Number of primary schools = 58000
2. Number of High Schools = 11763
F. Road and Transport (2009)
1. National highways = 4491 Km
2. State Highways = 20905 Km
3. Major District Roads = 47836 Km
[Source: Govt of Karnataka, Dept of Economics & Statics]
11.2 Analysis, Mitigation and Suggestions for Alternatives Potential environmental impac
The environmental impacts of a project depend both on the nature & type of the p
the background environmental setting of affected region. The data collected for en
screening has been analyzed and the relevant environmental impacts have been
Types of Impact
The types of environmental impacts of road construction / strengthening can be id
(a) construction phase, and (b) operational phase
The environmental impacts may be (i) direct (ii) Indirect or (iii) cumulative.
The Direct Impacts
The most important direct impacts of the present project are:
1 The felling of trees and removal of vegetation cover
2 The loss of crop-producing agricultural land
3 The impact on ambient air quality
4 The impact on soil quality
5 The impact on noise level
Potential environmental impacts
n the nature & type of the project and on
n. The data collected for environmental
mental impacts have been assessed.
t or (iii) cumulative.
ct are:
er
6 The impact on water quality
7 The impact of high temperature
8 The generation of waste and its impact
The Indirect Impacts
These are long-term impacts and should be studied carefully. Many
nature may not be identified easily. A detailed Environmental Manag
required for identifying individual impacts. However, some possible i
1. The soil erosion due to cutting of trees and removal of herbal co
2. Accumulation of water in borrow pits
The Cumulative Impacts
1. Contamination of food-chain due to short changes in environmen
the construction phase
2. Effect on human and cattle health
Socio-Economic Impacts
The following issues are of no significance while considering the imp
1. There are no archaeological monuments which are going to be a
present project.
2. The impact of widening / new construction and its potential might
from individual to individual or from family to family, but no specific et
be culturally affected.
Along the stretch few built-up structures, religious structures and pett
be relocated for the proposed widening.
The Types of Impact
Assessment of the types of impacts on socio-economic conditions of
and as a member of community is a tough job and requires a deep an
However, some of the immediate direct impacts could be enumerated
1. Impacts on cultural heritage
The social, religious and historical monuments are of social importan
not have many such structures. The temples present along the align
small. Such structures can be relocated, if required, with consultation
communities. The
Table 11.1 below gives the list of such small religious structures which
as they fall within the ROW.
community. Besides, they will also draw benefits from the economic activities as a
traffic flow and movement of vehicles.
Further, increase in the width of the road would provide better road safety and go
between the towns.
11.5 Summary and Conclusion
Discussion in this section reveals that the project area under consideration is not
social impacts.The widening is proposed by adding the new carriageway either on
right or concentric, depending on the site condition.However there is require
acquisition,Rehabilitation of Structures and few religious structures will have to be
cattle health
eligious structures
uisition of shops
e shopping complexes, shops, small sale outlets, temporary
k shop etc. are seen along the road. There are some portion of
eing affected.
and Acquisitions and Resettlements
have to be cut due to widening. This has been kept to the bare
nd Mitigation
f trees falling in ROW, a massive plantation program should be
entation of the project.
ree rows of trees should be planted in such a way that, one row
r rows are of flowering trees. In the above scheme the selection
s may be intermixed (it should be noted that large, shady
s regard, plant nurseries should be developed at selected sites
e should also be taken to protect the trees in their initial stage of
nes used for the purpose should be in good order to avoid any
egative impacts
ostly environmental and social impacts will be mitigated
n of replacement value of the property lost due to or in the
t-affected persons (PAPs) will receive additional supports and
their livelihood and the quality of life.
ing
etch has many industrial clusters and the list of the industries are
Environmental Analysis
The most important biotic factors of the environment, which are likely
project, include soil, water, air, and noise level. Samples of soil and w
from different places along the road. The noise and air monitoring als
in different places along the road.
Soil Analysis
The main objective of interpreting soil for engineering purposes is to
for various engineering practices on a sustained basis. But under the
only environmental properties of soil have been studied.
Soil Sampling Locations
Table 12.4: Standard Soil classification as per ICAR
ies in the Dobbaspet Industrial Area
nds
n identified on either side of the highway throughout its entire
ping Pattern
e major cereal crops of the region and groundnut, sunflower and
sh crops. List of different agricultural crops grown in the vicinity are
24 hours 30 µg/m 3
120 µg/m 3
90 µg/m 3
24 hours 30 µg/m 3
120 µg/m 3
90 µg/m 3
24 hours 75 µg/m 3
150 µg/m 3
100 µg/m 3
struction Machinery
ndards.
Table12.7: Emission factors of different vehicles (g/Km)
Types of Vehicle CO HC NOx SOx TSP
Two Wheeler 8.3 5.16 - 0.013 -
Cars 24.03 3.57 1.57 0.053 -
Three Wheelers 12.25 7.77 - 0.029 -
Buses-Urban 4.381 1.327 8.281 1.441 0.275
oleum,1985
nes
ayer of green plantation with small leaves acting as noise
may be planted just inside and adjacent to the wall. Contractors
e implementation of the civil work. Tree plantation will be
st department under the tree-planting scheme of the project.
ects are provided in the EMP. In addition to the noise mitigation,
t as an air quality filter for vehicular emissions. A typical green
ill have 200 trees in
Table 12.8: Noise Barrier locations
Sl. Design Side Silent Receptors Remarks
No Chainage
1 31.300 RHS Bommanahalli Forest Area Vegetative Barrier
2 50.100 RHS Forest Area, Nijagal Vegetative Barrier
3 55.300 RHS Nandihalli Vegetative Barrier
4 58.100 LHS Hirehalli Vegetative Barrier
5 63.300 LHS Kyathasandra Vegetative Barrier
National Noise Standards
The Central Pollution Control Board has specified ambient noise leve
uses for day and night times. Importance was given to the timing of e
designated as
sensitive. Table 12.9 gives the noise standards set.
Table 12.9: National ambient noise level standards
Area Category Limits in Decibels (dB A)
Code Day Time Night Time
A Industrial 75 70
B Commercial 65 55
C Residential 55 45
D Silence Zones 50 40
Note: (1) Daytime: 6 AM to 9 PM., Night-time 9 PM to 6 AM; (2) Silence zone
around premises as hospitals, educational institutions and courts.
Source: Central Pollution Control Board, New Delhi
Reference Noise Levels
The vehicular noise emission levels significantly vary with vehicle spe
necessary that speed dependency of noise emissions for various cat
taken into account while using the model for noise prediction due to t
work the speed-noise relations presented by National Environmental
Research Institute (NEERI) in their
report on Environmental and Social Assessment Delhi - NOIDA
have been adopted (Table 12.10).
se standards set.
vel standards
c animals.
disposal of bituminous materials in the
ogy and enter surrounding water bodies
on Phase
ce, longer travel time and higher cost. The
crease the dust generation in the
ease due to traffic disruption.
ents
m with paved shoulders of 1.5 m on both sides of the road from
10.5m carriageway, 1.5m paved shoulder with service road on
68. Since the Proposed Road is widening to six lanes, 10.5 m wide
ers, 7.0m of service road and and 1.5m paved Shoullder and 1.5m
arriage way and Service Road and 1.0m RCC Drain in Service
. For the development of 6 lane highway minimum 60m ROW
s required for widening at locations where existing ROW is less
68 comes under urban stretch there shall be the improvements
idening schedule is given in the Table 7.4 of chapter 7
e as below:
l utilities: -
HT/ LT Lines)
(ii) Public Health utilities (Water/Sewage Pipe Lines)*
The site includes the following Public Health utilities:-
Existing Length (in Km) Crossings Dia in mts /
Chainage Casing in mm
Water Supply Water Supply
S Pipeline Pipeline
With Gravity
No Gas Gas
With Gravity
From To
Pipeline Pipeline
Flow
Pumping
Pumping
Flow
With
With
1
46.300 47.580 1.280 @ 47.580 120/315
2
47.700 48.800 1.100 @ 48.800 100/315
3
48.800 48.900 0.100
4
50.300 55.890 5.590
5
58.860 59.290 0.430 @ 58.860 508,324
/500
6
59.800 75.000 15.200 @71.700 150/300
7
62.700 62.950 0.250 @62.950 250/600
8
63.425 63.600 0.175 @63.600 200/600
9
63.600 64.050 0.450 200
10 64.030 64.290 0.260 @64.290 250/600
11 64.290 64.301 0.011 250
12 68.450 68.920 0.470 @ 68.920 508
13 68.920 70.080 1.160 @ 68.920 508,711
/1200
14 68.940 69.065 0.125 @68.940 300/711
15 68.940 69.440 0.500 250
16 69.250 69.452 0.202 250
17 69.250 69.300 0.050 250
18 71.360 71.930 0.570 @71.360 350/711
19 71.360 71.410 0.050 @73+910 200/600
20 73.910 74.290 0.380 200
21 73.860 73.910 0.050 200
h utilities:-
Remarks
RHS
RHS
LHS
RHS
LHS
LHS
RHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS