ON EPC MODE FOR PACKAGE IV, FROM KM. 162+667 TO KM. 217+023, (Section - Village Donad Bk. to Village Januna Kh.) in District Washim
12 NMSCEW/P-IV/HW/2021/35118 Checking pouring concrete (M-20) for channel kerb laying shoulder side Kerb Km 208+470 Km 208+700 RHS 2:00 PM
13 NMSCEW/P-IV/HW/2021/35119 Checking line and level for PCC(M-15) top shoulder kerb Kerb Km 208+710 Km 208+900 RHS 2:15 PM
14 NMSCEW/P-IV/HW/2021/35120 Checking shuttering and line for pouring concrete M-20 of lined toe drain raft & wall (Type-2) lined Toe drain Km 204+400 Km 204+500 RHS 5:00 PM
15 NMSCEW/P-IV/HW/2021/35121 Checking aligment of un-lined Toe drain with excavated bed level (Type-1) Un-lined Toe drain Km 201+300 Km 201+600 11:50 AM
16 NMSCEW/P-IV/HW/2021/35122 Checking aligment of un-lined Toe drain with excavated bed level (Type-1) Un-lined Toe drain Km 200+400 Km 200+800 12:25 PM
27 NMSCEW/P-IV/HW/2021/35133 Checking of layout,line,level,excavation,reinforcement ,shuttering and pouring concrete (M-20) for compound column footing ( 60 Nos footings) Boundry wall Km 179+000 Km 179+200 RHS 10:55 AM
28 NMSCEW/P-IV/HW/2021/35134 Checking of layout,line,level,excavation,reinforcement ,shuttering and pouring concrete (M-20) for compound column footing ( 606 Nos footings) Boundry wall Km 175+200 Km 176+200 BHS 10:00 AM
29 NMSCEW/P-IV/HW/2021/35135 Checking shuttering and line for pouring concrete M-20 of lined toe drain raft & wall (Type-2) lined Toe drain Km 191+710 Km 191+730 LHS 3:00 PM
30 NMSCEW/P-IV/HW/2021/35136 Checking shuttering and line for pouring concrete M-15 of Median lined drain raft & wall (Type-2A) Median lined drain Km 195+160 Km 195+180 3:55 PM
31 NMSCEW/P-IV/HW/2021/35137 Checking aligment of lined Toe drain with excavated bed level (Type-2) lined Toe drain Km 194+510 Km 194+570 LHS 4:20 PM
32 NMSCEW/P-IV/HW/2021/35138 Laying of PCC (M-10) for lined toe drain with top level checking (Type-2) lined Toe drain Km 194+510 Km 194+570 LHS 5:35 PM
33 NMSCEW/P-IV/HW/2021/35139 Checking shuttering and line for pouring concrete M-20 of lined toe drain raft & wall (Type-2) lined Toe drain Km 194+645 Km 194+660 RHS 11:11 AM
34 NMSCEW/P-IV/HW/2021/35140 Checking shuttering and line for pouring concrete M-20 of lined toe drain raft & wall (Type-2) lined Toe drain Km 194+550 Km 194+565 LHS 11:44 AM
35 NMSCEW/P-IV/HW/2021/35141 Checking aligment of median lined drain with excavated bed level (Type-2A) Median lined drain Km 196+190 Km 196+250 2:22 PM
36 NMSCEW/P-IV/HW/2021/35142 Laying of PCC (M-10) for median lined drain with top level checking (Type-2A) Median lined drain Km 196+190 Km 196+250 3:35 PM
37 NMSCEW/P-IV/HW/2021/35143 Checking pouring concrete (M-20) for channel kerb laying shoulder side at SH-212 Kerb Km 01+187 Km 01+525 LHS 11:25 AM
38 NMSCEW/P-IV/HW/2021/35144 Checking line and level for PCC(M-15) top shoulder kerb at SH-212 Kerb Km 01+550 Km 01+590 LHS 12:18 PM
1 NMSCEW/P-IV/STR/2021/15759 Checking of layout,level,structural excavation & laying PCC for U trough Box culvert Km 192+039 LHS 12:30 PM
2 NMSCEW/P-IV/STR/2021/15760 Checking of layout,level,structural excavation & laying PCC for U trough Box culvert Km 192+039 RHS 1:30 PM
3 NMSCEW/P-IV/STR/2021/15761 Checking reinforcement,shuttering and Pouring concrete (M-50) for intermediate CROSS girder-1 of span-1 VOP Km 194+805 2:00 PM
4 NMSCEW/P-IV/STR/2021/15762 Checking reinforcement,shuttering and Pouring concrete (M-50) for intermediate CROSS girder-1 of span-2 VOP Km 194+805 2:30 PM
5 NMSCEW/P-IV/STR/2021/15763 Checking reinforcement,shuttering and Pouring concrete for median crash barrier W1 PUP Km 212+080 5:00 PM
6 NMSCEW/P-IV/STR/2021/15764 Checking of stressing for boundary wall panel (2485-2592) 108 nos panel at precast yard Ch-206+650 Boundry Wall Panel Km 206+650 6:00 PM
7 NMSCEW/P-IV/STR/2021/15765 Checking of Shuttering,concrete for boundary wall panel (2485-2592) 108 nos panel at precast yard Ch-206+650 Boundry Wall Panel Km 206+650 7:00 PM
8 NMSCEW/P-IV/STR/2021/15766 Checking of stressing for boundary wall column (1201-1320) 120 nos column at precast yard Ch-206+650 Boundry Wall column Km 206+650 5:45 PM
9 NMSCEW/P-IV/STR/2021/15767 Checking of Shuttering,concrete for boundary wall column (1201-1320) 120 nos column at precast yard Ch-206+650 Boundry Wall column Km 206+650 6:30 PM
10 NMSCEW/P-IV/STR/2021/15768 Checking of stressing for boundary wall panel (11893-12092) 200 nos panel at precast yard-2 camp-2 Boundry Wall Panel Km 200+200 LHS 1:00 PM
11 NMSCEW/P-IV/STR/2021/15769 Checking of Shuttering,concrete for boundary wall panel (11893-12092) 200 nos panel at precast yard-2 camp-2 Boundry Wall Panel Km 200+200 LHS 1:30 PM
12 NMSCEW/P-IV/STR/2021/15770 Checking of stressing for boundary wall column (1845- 1912) 68 nos column at precast yard Ch-202+190 Boundry Wall column Km 202+190 2:00 PM
13 NMSCEW/P-IV/STR/2021/15771 Checking of Shuttering,concrete for boundary wall column (1845- 1912) 68 nos column at precast yard Ch-202+190 Boundry Wall column Km 202+190 2:30 PM
14 NMSCEW/P-IV/STR/2021/15772 Checking of stressing for boundary wall panel (8200-8319) 120 nos panel at precast yard Ch-202+190 Boundry Wall Panel Km 202+190 3:10 PM
15 NMSCEW/P-IV/STR/2021/15773 Checking of Shuttering,concrete for boundary wall panel (8200-8319) 120 nos panel at precast yard Ch-202+190 Boundry Wall Panel Km 202+190 3:50 PM
16 NMSCEW/P-IV/STR/2021/15774 Checking Layout, Level, Excavation And Laying PCC for U-Trough(M-10) and Curtain Wall(M-15) Box culvert Km 187+677 RHS 3:22 PM
17 NMSCEW/P-IV/STR/2021/15775 Checking of stressing for boundary wall column (361-420) 60 nos column at precast yard CH2+460 Boundry Wall column Km 02+460 2:00 PM
18 NMSCEW/P-IV/STR/2021/15776 Checking of Shuttering,concrete(M-40) for boundary wall column (361-420) 60 nos column at precast yard CH2+460 Boundry Wall column Km 02+460 2:45 PM
19 NMSCEW/P-IV/STR/2021/15777 Checking of stressing for boundary wall panel (31- 90) 60 nos panel at bed no-1, precast yard CH2+460 Boundry Wall Panel Km 02+460 4:00 PM
20 NMSCEW/P-IV/STR/2021/15778 Checking of Shuttering,concrete(M-40) for boundary wall panel (31-90) 60 nos panel at precast yard CH2+460 Boundry Wall Panel Km 02+460 4:50 PM
21 NMSCEW/P-IV/STR/2021/15779 Checking of stressing of 2nd stage PSC girder no. G1 & G2 of span RP1 to RP2 VOP Km 181+420 RHS 10:00 AM
22 NMSCEW/P-IV/STR/2021/15780 Checking of reinforcement, shuttering & pouring concrete(M-40) for crash barrier of span RA1 to RP1 at deck width 13.665m ROB Km 180+529.146 RHS 11:00 AM
23 NMSCEW/P-IV/STR/2021/15781 Checking of reinforcement, shuttering & pouring concrete(M-40) for end cross girder(G1 to G5) of span RA1 to RP1 VUP Km 181+420 RHS 9:00 AM
24 NMSCEW/P-IV/STR/2021/15782 Checking Reinforcement, Shuttering and Pouring Concrete (M-30) for Side wall A1/A2 with Haunch 1st lift of U-Trough Box culvert Km 184+490 RHS 11:55 AM
SURVEY
1 NMSCEW/P-IV/SUR/2021/524 TBM Fly Levelling GPS-9B to GPS -10B TBM BHS 9:00 AM
QUALITY CONTROL
1 NMSCEW/P-IV/QC/2021/000
This is to certify that I hereby Acknowledge the Receipt of above listed RFI 's
Name: Name:
Signature: Signature: