Framing and Bracing


 Print

Details Category: Framing and Bracing Published: July 31, 2012 Hits: 11538

These labour constants refer to un-automated Tradesman Labourer


Descrip on Unit
methads of construc on Hours Hours
Heavy sections,

including

connections—UB,

UC, RSJ and RSC

Fabrication tonne 23.00

Erection tonne 7.00

Light sections—

angles etc.

Fabrication tonne 40.00

Erection tonne 20.00

Hollow sections,

including

connections

Large sections, fabrication tonne 30.00

Large sections, erection tonne 10.00

Small sections, fabrication tonne 35.00

Small sections, erection tonne 15.00

Trusses, including

connections

Up to 10m span, fabrication tonne 50.00

Up to 10m span, erection tonne 10.00

Over 10m span, fabrication tonne 35.00

Over 10m span, erection tonne 6.00

Proprietary purlins

and girts

Up to 150mm high m 0.09

Over 150mm high m 0.12

https://www.methvin.org/construction-production-rates/engineering/framing-and-bracing?tmpl=component&print=1 1/2
03/01/2021 Framing and Bracing

Surface Treatment

Sand blast and paint

Light sections tonne 8.00

Heavy sections tonne 5.00