• Resist the use of W8's, and certainly create questions about acceptable fab-
E very fabricator and erector has
a long list of ideas on what design W6's, as structural columns. W10's are the smallest column size offering any hope of reasonable room for connec- rication and erection techniques (for example, what welding procedures are compatible with the non-standard engineers can do to reduce the cost tions and minimizing expensive blocks, material?). of building a steel structure. What etc. W12's are better still. follows are some thoughts gathered • Call for partial pen column splices, don't automatically indicate full pens. From Mike N. Wagoner, P.E., Vice in the field: President of Engineering, Contract • Design in sufficient gaps or adjust- ments between structural framing and Steel Sales, Inc.: the finish materials to accomodate the From John E. Quinn, Vice frame's dimensional tolerance before • Eliminate full penetration welds on President/Operations, Zimkor telegraphing into finish. stiffeners by oversizing stiffeners and using partial penetration welds. Industries, Inc.: • Wherever possible, involve the fabrica- tor and erector early in the design • Show beam and column sizes on the • Structural drawings should be fully process so they can help develop the planand not a schedule on another checked for completeness, dimensional most economical details. This will save sheet; show dimensions on all draw- accuracy, layout geometry closure etc the engineer's time as well, particularly ings, not just foundation drawings. prior to issuance. The "second set of in developing the secondary framing • Allow the fabricator to use the struc- eyes" review check should be done by details. tural drawings an an erection plan. the preparing firm, not the end users. • Size columns receiving moment con- • Be realistic when specifying camber. • Reactions should always be listed per nections to avoid or minimize expen- • Use one-sided connections when possi- member and identified as service or sive continuity plates and doublers. ble. factored loads. • As always, keep the specialty details to • Use field applied screed and shelf • Use of two or three story tiered a minimum; full pens, slip critical, angles. Clearly show on the drawings columns is more economical than milled surfaces etc what weld is required. "stacked" columns of only single floor height. From Brett R. Manning, S.E., Chief • Wherever appropriate, limit amount of From Ken Saucier, Cives Steel Engineer, The Herrick Corporation: welding at baseplates to the two flange Company: faces as suggested in the AISC Manual • Complete and coordinate design docu- of Steel Construction. • Clean up generic specifications to make ments. • Consider ¼" fillet as the largest single them more project specific. • Special details should be referenced pass weld, not 5/16" as traditionally • All connections should be Engineer where applicable on design drawings— thought. Unless a shop's standard mandated and available at bid. davits, bent plate, screen walls, precast welder setup is aimed at large welds, • Specifically locate painted/galvanized connections, etc. ¼” is the largest practical size for all steel on structural drawings similar to • Allow the fabricator to suggest connec- setups and all welders. the manner studs or camber are identi- tion alternates; seek fabricator input • Don't require paint on framing fied. on complicated framing issues. enclosed in building envelope. • Eliminate references to architectural • Don't specify camber to be "in-place" drawings; provide information on camber. Call for camber only if ¾" or structural drawings. From Ted Totten, Cives Steel more. • Provide floor and roof openings infor- Company: • Specify that the fabricator can select mation early on in steel detailing stage. • Allow single angle/shear plate connec- the standardized AISC connection type • If specialty item (davits, widgets, etc) tions where these connections satisfy (single plate, single angle, seated, end provide manufacturer and catalog the design requirement. plate etc) that meets the reactions list- information. • Eliminate column web doublers at ed on the plans and best suits the fab- • Be specific of slab edge requirements at moment connections, where possible, ricator's equipment and his erector's roofs as well as floors. and if required show on the bid draw- preference. • Show deck support requirements, espe- ings. • Limit stiffener welding to what's need- cially at depressed slab areas. ed. Two stiffeners in a W24x55 will require 10ft of weld if called to be all From Terry M. Zwick, Vice around both sides. From Keith Landwehr, Quality President/General Manager, Atlas • When sloped secondary angle kickers Control Manager, Schuff Steel Iron Works: are used from beam to beam or to a Company: joist, call for the length of weld • Show loads on connections • Specify A992 for wide flange members. • Only use “weld all around” symbols required rather than showing the angle • Do NOT specify a material with fitted into the web/flange fillet and when necessary. requirements outside of ASTM. This • Do not specify Gr. 50 material for any- welded all around. will increase project costs and will also
Modern Steel Construction / April 2000
thing other than wide flange. Specify • Provide all calculations to the • Consider zinc-rich paint on exteri- A992 for wide flange shapes. detailer. or brick relieving angles in lieu of • Consider using HP sections for columns • Include any steel components from galvanizing. This would allow the where the thicker webs could elimi- the architectural drawings on the shop attachment of the angle and nate the need for web stiffeners and/or structural drawings. hanging system instead of a more doubler plates. costly field installation. Edge con- • Try to avoid moment connections to From Tony Auciello, Auciello Iron ditions at the perimeter of the HSS columns; they tend to be very Works: building should be kept as simple expensive. as possible. • Use duplication whenever possible. • If beams are used for lintels (technical- • Structural drawings should not be With mill requirements on bundle ly, loose lintels), note if the structural released for construction until co- quantities you may be increasing costs or the miscellaneous metals subs ordination has been completed when you design for minimum weight should include them in their bids. for the elevators and mechanical by having different sizes. • Spec out standard gratings (and avoid openings. • Do not specify any non-standard paint special fabricated grating) whenever • Loads for bracing should be shown for bar joists. The cost of special clean- possible. on the bid drawings. ing and painting can almost double the cost. From Robert J. Petroski, P.E., Vice • Do not specify a primer coat on steel Preident, General Manager/Chief From Edward Fink, Jr, Drake- unless necessary. Engineer, Hercules Steel Co., Inc.: Williams Steel, Inc.: • Show the required uplift, snow and ponding loads on roofs so the joist • Rolling to a tight radius can result in • For wide flange and channel shapes engineers can easily identifiy them and some member distortions under nor- rolled the easy way, lighter is not bet- include the necessary forces in their mal curving processes. More sophisti- ter. Thicker webs help hold the cross member designs. cated curving is very expensive. sectional shape better while rolling; • Do NOT issue “canned specs” listing • Don’t require pretensioning of connec- i.e., the flanges stay perpendicular to requirements, conditions or work that tion bolts when “snug tight” will suf- the web and the web bows less. does not exist on a particular project. fice. • HSS, particularly the square and rec- • Always consult a local fabricator or • The lightest beams for composite con- tangular sections, also benefit from AISC regional engineer with questions struction with substantial camber is not thicker walls. Architects don't like all on material availability. necessarily the most cost effective. those ripples and bulges from using • Be aware of availability and costs when sections with walls that are too thin. using a small quantity or a uncommon • Find out what the minimum radius is From Eric Tessmer, Cives Steel for the required section. If the HSS Company: member size. Check with a local fabri- cator about availability. member is shown with too short a • Coordinate systems attaching to the • When possible, use a heavier member radius then the member will be fabri- structure to work with fabrication/ to eliminate the need for column web cated from four plates. The magnitude erection tolerances. All too often the doublers and/or continuity plates. of the extra expense of cutting to fabricator is asked to include attach- • Use “thru plates” for HSS only when radius two side plates and rolling the ments from the shop, and later faces absolutely necessary. top and bottom plates to two different charges from another contractor radii and of four continuous welds and because his connections did not allow the associated grinding/finishing is for fabrication/erection tolerances. From Terry Vallely, President, usually unbelievable to the Per section 7.11.3 of the "Commentary General Steel Fabricators: Architect/Engineer. Getting those on The Code of Standard Practice for welds finished to the comparable HSS • Columns should be spliced as infre- shape are not always easy. And the Steel Buildings and Bridges", Ninth quently as possible—shop and field appearance is not always acceptable. edition, these connections should pro- labor costs associated with WF, S, C, and MC shapes have similar vide for 3" of adjustment. splicing can be excessive - particularly caveats. splices designed to transmit moment. From Morgan L. Steele, Sr. Vice • Columns should be sized to minimize President/COO, Globe Iron: web stiffeners and doublers—the cost to From Walt Willard, Cives Steel develop a three level system typically Company: • Locate all members with dimensions to allows significant column upsizing. column grids or reference points and • Use deep profile decks to maximize • Structural revisions should not be provide elevations for both ends of beam spacing. made during the approval process of members. shop drawings. If there is a required • Coordinate between the architectural design change noted on the approval and structural drawings below releas- From Dominic Centofanti, Cives returns, it should always be followed ing them for construction. Steel Company: up with a revised structural drawing, • Respond quickly and completely to with the revisions clearly noted. • Complete the structural steel drawings Similarly, if an RFI response revises or RFIs. before going out for bids. adds a detail, this too should be fol- • Provide adequate details, sections, etc., • Get input from a fabricator before lowed by a revised structural drawing. to show intent. releasing bid drawings to review the design, details and welding procedures. From Ron Baskins, President, • When acceptable, consider galvanizing Chesapeake Bay Steel, Inc.: in lieu of multi-coat paint system.