You are on page 1of 11

OML 30 (ERIEMU)

ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT


Detailed Engineering

Site Visit Report


page: 1/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A

Site Visit Report

Remarks:

1.0 04-12-2020 Issued for Review Azumara V. Azumara V. Ngwuli S.

Rev. Date Description Issued by Reviewed by Approved by

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.
OML 30 (ERIEMU)
ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Detailed Engineering

Site Visit Report


page: 2/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A

TABLE OF CONTENTS

1. PRESENTATION .....................................................................................................................3

2. PURPOSE ...............................................................................................................................3

3. LIST OF ITEMS .......................................................................................................................3

4. SITE FINDING ........................................................................................................................4

5. RECOMMENDATION & ACTIONS ...........................................................................................5

6. SITE PICTURES ......................................................................................................................6

7. APPENDIX (ES) ..................................................................... ERROR! BOOKMARK NOT DEFINED.

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.
OML 30 (ERIEMU)
ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Detailed Engineering

Site Visit Report


page: 3/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A
1. Presentation
SITE: OML 030 SECTOR: ERIEMU
SMR/SOR n°: and issue date: 13/12/2020
Description: ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Reporting by: Victor AZUMARA Date of Visit: 09-12- 2020 to 11-12-2020
Present: Name Entity / Position
Jude Wilson HEOSL
Ambrose Okudu HEOSL Project Coordinator
Moses Oliseh HEOSL
HEOSL
Victor Azumara Sanaglobe Nigeria Limited Project Manager
Tunmi Olugbile Sanaglobe Nigeria Limited Engineering Lead
Alozie Enyinnah Sanaglobe Nigeria Limited Construction Supervisor
Emmanuel Sanaglobe Nigeria Limited Fitter

2. Purpose

The purpose of this site visit was to gather site as-built information and compare basic engineering
studies with existing facilities that will be used to carry out the detailed engineering studies and
constructability analysis for the ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION
PROJECT.

3. List of Items

Below are the following activities that were planned to verify on site during the site visit:
Confirm the feasibility of proposed extension of the existing LACT unit deck, structure, cage
enclosure walls, roof and gantry crane, perimeter lighting, and piping tie-ins to accommodate as
well as cater for the new metering streams.
Confirm and mark-up connection points for the two new metering streams to be tied to existing
Eriemu LACT Metering Skid and configured to utilise the existing Jiskoot auto sampling system,
meter prover/master meter and spare run as indicated in the P & ID.
Confirm and mark-up connections points and access feasibility of the Afiesere and Kokori
pipeline re-route at Eriemu Manifold to the LACT Metering Skid Inlet.
To identify possible position for installation (mounting) of New Metering Panel in the existing
LACT control room.
Confirm the feasibility of proposed tie-in connections to the existing tie-ins as per drawings.

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.
OML 30 (ERIEMU)
ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Detailed Engineering

Site Visit Report


page: 4/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A
Confirm tie-in points on the existing LACT unit to new metering streams as well as
interconnecting pipes, the air and drain piping according to drawings from EMERSSON.
Confirm and mark-up for replacement existing 12” pipeline and valve on skid manifold header to
Eriemu LACT unit tie-in points of in and out, for possible installation of new 16” pipeline spools
with valve as manifold header to tie-in points both in and out.
Confirm and mark-up existing Jiskoot sampling system for adaptation to new 16” sampling
system spool.
To obtain site sketches for mark-up of As-built piping general arrangement, PID drawings and
drawings for structural, civil and piping documentation for detailed engineering.
Confirm tie-in points on the existing LACT unit for all interconnecting pipes.
Confirm piping class and flange rating on the lines.
To estimate the quantity of materials that will be required to execute this project.
Take necessary site measurements and pictures.
To identify any potential safety concern associated to the implementation of the extension and
modification works.

4. Site Finding

Possible tie-in positions for pipe routing from each line of Afiesere and Kokori facilicities at the
Eriemu manifold to the LACT metering skid inlet was identified. This shall be achieved by
installing a new header on both lines from Afiesere & Kokori and tied-in to existing 12” lines
connected to the manifold header on the unit skid inlet. See picture 01 ~ picture 03 below.
Proposed New Metering Panel position in the existing LACT Control Room was identified.
Observed and identified the possibility of the proposed extension to accommodate and cater for
the two new metering streams. Extension to be carried out on;
o LACT Unit Deck
o LACT Unit Structure
o Cage Enclosure Walls
o LACT Unit Structure Roof
o Gantry Crane Rail
o Perimeter Lighting and,
o Piping tie-ins – drain piping system to drain pit, airline tubing connection to air compressor
& the new 16” manifold header.

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.
OML 30 (ERIEMU)
ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Detailed Engineering

Site Visit Report


page: 5/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A
Proposed changeout of existing 12” pipeline & valves on manifold header to Eriemu LACT unit
tie-in points in & out and installation of new 16” manifold header as indicated on engineering
P&ID’s and PGA’s was identified. See sketch 1 below.
Proposed installation of new 16” sampling system spools to new 16” manifold header as
indicated on engineering P&ID’s and PGA’s was identified. See picture 04.
Existing trench for underground routing of instrument signal cables from LACT Unit to LACT
Control Room identified. See picture 05.
Proposed 2-nos. 135KVA Diesel Generator at Eriemu Manifold for servicing and synchronization
was also identified.
Tie-in of newly installed 16” manifold header and pipeline to the existing 12” pipelines
downstream Eriemu Manifold shall be achieved using a 12” x 16” Eccentric Reduced as indicated
in the preliminary MTO. See picture 06.

5. Recommendation & Actions

Proposed new extension of the existing LACT unit deck, structure, cage enclosure walls, roof,
gantry crane and perimeter lighting should be carried out also to accommodate the New Bi-Di
Prover. This is as indicated on engineering P&ID’s and PGA’s from Emerson. Refer to drawings.
Position of existing access stairs from North of LACT Unit deck should be relocated during
extension to accommodate the New Bi-Di Prover to prevent from being obstructed by the server
pit to the Eriemu Manifold. See picture 07.
As much as possible, new pipe re-routing shall be made to follow existing pipe route to eliminate
the need for new supports as existing supports shall be used and some to be modified by
extending to accommodate new pipe re-routing.
A complete replacement from 12” pipeline to 16” pipeline from tie-in point of the newly installed
16” manifold header from the LACT unit skid both inlet & outlet downstream to the 24” pipeline in
Eriemu Manifold to avoid pressure build up due to installation of 2-nos new metering streams.
This is as indicated on site by the operation team.

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.
OML 30 (ERIEMU)
ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Detailed Engineering

Site Visit Report


page: 6/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A

6. Site Pictures
Picture 01

Proposed tie-in point on Aiesere Line in


Eriemu Manifold area.
This shall be achieved using a 12” Proposed tie-in point on Kokori Line in
equal tee to be installed as tie-in to the Eriemu Manifold area.
line and connected to a common This shall be achieved by tie-in to
header with pipeline from Kokori line existing 12” equal tee on the line and
to be connected to the LACT Skid Inlet connected to new common header
manifold header. with pipeline from Aiesere line to be
connected to the LACT Skid Inlet
manifold header.

Pictures 2 & 3

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.
OML 30 (ERIEMU)
ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Detailed Engineering

Site Visit Report


page: 7/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A
Sketch 1

Existing 12” outlet header


to be changed.
Existing 12” inlet
header to be changed
and new 16” inlet
Existing 12” outlet header
header to be installed.
to be changed and new 16”
outlet header to be
installed.

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.
OML 30 (ERIEMU)
ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Detailed Engineering

Site Visit Report


page: 8/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A

Picture 4

Existing 12” sampling system


spool shall be replaced with new
16” sampling system spool for tie-
ins of existing two lines to the
Jiskoot Auto Sampling System.

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.
OML 30 (ERIEMU)
ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Detailed Engineering

Site Visit Report


page: 9/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A

Picture 05

Existing trench for underground


routing of instrument signal
cables from LACT Unit to LACT
Control Room

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.
OML 30 (ERIEMU)
ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Detailed Engineering

Site Visit Report


page: 10/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A

Picture 6

Tie-in of new 16” pipeline from


LACT unit inlet manifold header to
existing 12” pipeline to Eriemu
Maniold shall be achieved using a
12” x 16” Eccentric reducer.

Picture 7

If extension of LACT unit structure,


cage and deck to accommodate Bi-
Di Prover, access stairs is to be
relocated to avoid obstruction of
server pit shown.

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.
OML 30 (ERIEMU)
ERIEMU LACT UNIT-1 EXTENSION SITE INSTALLATION PROJECT
Detailed Engineering

Site Visit Report


page: 11/11
Rev. Status Rev. date Discipline PJM
Document Number:
1.0 IFR 04-12-2020 Doc. Type REP
Ref. Number: -- -- -- (Syst.) Unit N/A

This document is the property of SANAGLOBE and must not be reproduced, stored or disclosed without permission from COMPANY.

You might also like