Professional Documents
Culture Documents
Develop Project Develop Project Send PMP &/or Schedule Update PMP &
Management Plan Schedule for Review & Approval Schedule
PM
Project
Project Schedule
Management Plan
Yes
Conduct Kickoff File The PMP And/or
Conduct Preparatory Request Project Request Project Review PMP &/or
Project Manager
Meeting Schedule
Meeting PMP Management Plan Schedule Schedule With SME Comments End
Start Yes
Required? ? Duration: 1 Duration: 3
Duration: 1 Duration: 1 Duration: 1 Duration: 3
MoM Form
No
No
Management
Manager
Project
No Approval? Yes
Page 1 of 3
Project Management Office (PMO)
PMO Methodology
D. The Vendor / contractor PM sends the Schedule and/or PMP to the Project
Manager.
E. The Project Manager and the SME review the submitted plans and provide their
comments to be reflected by the Vendor / contractor PM. In coordination with
Requesting Dept. Manager if required.
F. Project Management Manager reviews the PMP / Schedule, if not approved he
will return them back to the PM for update.
G. If approved, the Project Manager requests a kickoff meeting with the project
stakeholders to present the project scope approach as defined in the project
schedule and/or project management plan and address their concerns and
expectations.
The Project stakeholders are:
o Project Manager
o PMO Officer
o SME
o Vendor Project Manager
Note: for internal projects, the Vendor PM is replaced by the project
implementation manager
1.1.6. Responsibility Assignment Matrix (RAM):
Vendor / Project
Project
Responsibility Contractor Management
Manager
Project Manager Manager
Conduct preparatory meeting with
O
vendor / contractor
Develop Project Schedule and/or PMP O
Review Project Schedule and/or PMP O O
Approve PMP / Schedule O
Conduct Kickoff Meetings O
File the PMP and/or Schedule O
Table 1 – Project Planning Process (RAM)
Page 2 of 3
Project Management Office (PMO)
PMO Methodology
Page 3 of 3