Professional Documents
Culture Documents
University of Gondar
University of Gondar
INSTITUTE OF TECHNOLOGY
During the completion of this internship report different necessary methods and procedures from
these; interview of concerned bodies of the company, company documents revisions, company
manuals and operation sheet formats reference etc. Using these sources I have compile this final
internship report through detail explanation.
The first part of report, described the background of my hosting company including the history and
objective of the company, its main product and service and the overall organization flow of the
company as well as general description of the project.
The second part of my report, is explains the overall internship experience I have gained during my
practical period. I started by telling how I get into the company, in which section of the company I
have been working in and the work piece I have been executing. I also explained clearly what the
general workflow in our section look like.
The third part, there are some introduction about head work which describe the function of diversion
headwork, location of project area. I tried to explain criteria for selection types of weir. Next, I briefly
explained planning and hydraulic design of head work. Lastly, I tried to describe design of broad crest
weir.
The fourth part of my report, is discussing about the challenges I have faced during my internship
period. I explain briefly the challenges and the taken measurements to overcome these challenges.
The fifth part of my report, explains about the overall benefits I gained from my internship in terms of
improving my practical skills, interpersonal communication skills, team playing skills, leadership
skills, upgrading my theoretical knowledge and work ethics.
Finally, the report finalized with deals about conclusion and recommendation of the project.
CHAPTER ONE
1 INTRODUCTION
Irrigation is one of the improved technologies that increase production by efficient utilization of
water resource irrespective of rainfall availability; it is to meet this objective that this small scale
irrigation project is identified. The main economic base for the area is agriculture, in which both crop
production and animal rearing is practical.
Most of Ethiopian’s cultivated land is under rain feed agriculture due to spatial and temporal in
rainfall distribution and lack of water storage, there is not enough water for most farmers to produce
more than one times per year and hence there are frequent crop failures. As a result of dry spells and
droughts, in this part of the region is phenomenon.
For such problems irrigation is vital solution for agricultural leading economy to ensure sustainable
food security. That is why Irrigation becomes a common practice in our farmers with different scales.
Traditionally farmers try to divert different water sources by constructing a barrier across the river
with local material and traditional ditches to convey to their farm land so as to support the rain feed
agriculture and they are trying to cultivate more than one time per year.
Since they are using their local knowledge, they cannot keep the contour line of the land and canal
bed slope which is not proportional. Most of the main canal rout is earthen, so percolation and seepage
problems affect the capacity of the command area to be irrigated. The other problem is that the
construction is being carried out every year with local materials; that the farmers should maintain the
structure every year.
Therefore to increase command area and irrigation efficiency as well as to address a number of
beneficiaries, to improve traditional irrigation practices by incorporating canal infrastructures; we can
overcome percolation and seepage water losses. Constructing permanent structure has a significant
effect in alleviating every year maintenance cost and labor expenses. Hence constructing different
canal crossing structures for easy irrigation water application to the irrigable land are modern
irrigation practice, and also the beneficiaries have to cover the operation and maintenance
From irrigation and drainage study and design core process points of view:
It performs study and design works of small scale irrigation scheme to cultivate command
area twice and more per year
Irrigation construction
From water supply and sanitation core process of
Identifies and selects potential water source areas in north Gondar zone.
Study and design work of the water distribution system.
Super vision and supporting work in different construction activities like reservoir, during
well drilling and spring development.
Water quality and risk assessment work.
Operation and maintenance work of non –functional water institute
It collects data of different water institute, metrological data, measure seasonal and perennial
discharge of surface water source /river/
supply drinking water in quality &quantity
operating and maintenance
To make water supply service potable, permanent, reliable by increasing the capacity of the
correlated demand progressive demand
Water supply constriction
The objective of the project to maximize the crop production and to ensure food security through the
people and also used to product forage for animals that lives around the project area
This is the department that stands tries to avoid poverty and hunger, to address water coverage and
water quality of the zone 100%, to insure food security, to create job opportunities for non-employers
and to bring sustainable development by performing the following activities.
From irrigation and drainage study and design core process points of view; it performs
study and design works of small scale irrigation schemes to cultivate command areas
twice and more per year.
From mine and energy core process point of view
It prevents over use of different mines and it also creates job opportunities for non-
employers.
It also performs promotion supply and distribution works of different technologies
associated with energies like solar energy and biogas technology.
To cultivate climate change.
Generally the department is a part of water resource and development bureau executes law and
rules of the federal/ministry of water, irrigation, energy and water resource development bureaus. It
also gives long-term and short-term trainings for expects in all division of the department by
collaborating with water resource and development.
Department head
secratary
geologist
socio-
economist secratary
surveyor
secratary technician
agronomist
geologist
1.5.Different divisions of the company
CHAPTER TWO
Based on the new curriculum, I was doing internship for one full semester at Centeral Gondar Smal
Scale Irrigation ,Water Resource and Development Department (CGWRDD). I have gained a lot of
understanding and experiences on practical application of water construction in a well-organized and
effective manner. While I was staying there, I have got several opportunities to visit project frequently
to observe the progress and to see the related activities. Within a fourth month stay in this
organization, I have spent ample time with site engineers, office engineers and quantity surveyors with
sufficient orientation and practical involvement on the site and office work.
In this report, I have included insights that I have gained during the internship time both site and
office work knowledge. Off course it is difficult to report all what I have seen, though I have tried to
highlight the main points.
I had been working in Small Scall irrigation Project in Construction part .
2.3 Challenges
Due to Shortage of cars and disallowance of the head, I was not lucky to visit the project site.
Shortage of computers and internet access in the enterprise.
Supervisors were busy and unfortunately they went to site so, they couldn’t advise properly.
There is no finical support from the computer.
The majority of the rural people in the region depend on rain fed agriculture for their
livelihoods. Farmers earn their livelihoods from the available land resources while
manipulating elements of the natural environment. Most farmers in the region do not use
improved technologies or inputs. Both crop and animal production are carried out according to
centuries old traditions. As a result, agricultural production in the country has remained at a
subsistence level and is highly influenced by occasional and frequent droughts and other local
conditions. Therefore, irrigation plays a major role in sustaining and achieving higher food and
fiber production to satisfy the increasing demand for food. Hence, it is the right time for the
Amhara National Regional Government to initiate integrated agricultural development program
in the region, with the aim of increasing agricultural output which can be achieved through
better agricultural practices and intensified irrigation systems within the context of a sound
environmental management. On this basis, the EIA study is carried out to identify impacts and
to propose possible mitigation measures or enhancement mechanisms of the Gabikura
diversion irrigation scheme.
The design and study of Gabikura irrigation project under modern irrigation scheme will
enable the farmers to use the available water and land resources efficiently and get themselves
food secured by increasing productivity. Designers have identified the weir site location by
choosing at different sites depending on geographical /geomorphological and geological
condition of the rive.
Gabikura irrigation project will enable the farmers of the project area to positive economic
change and improve their life standard by producing different crops using advanced irrigation.
The project is designed for the development of an irrigable land of 21.5 hectares.
The design and study of Gabikura irrigation project under modern irrigation scheme will
enable the farmers to use the available water and land resources efficiently and get themselves
food secured by increasing productivity. Designers have identified the weir site location by
choosing at different sites depending on geographical /geomorphological and geological
condition of the river.
Gabikura irrigation project will enable the farmers of the project area to positive economic
change and improve their life standard by producing different crops using advanced irrigation.
The project is designed for the development of an irrigable land of 21.5 hectares.
Problems
o Excavation depth without recommended
o Retaining wall construction is simply constructing without zero elevation to the ground.
o Under sluice gate is no provided
o Canal off take site is providing without its operating head.
o Downstream retaining wall length is less than with its apron length.
o Transportation system from the farmer area to the site.
Solution for the problem
o By using a profile for the canal and the weir foundation is redesigned its dimension
then after excavated
o Retaining wall is constructed to the embankment until it comes zero elevation.
o During design the under sluice is not provide but when come to construction the
supervisor engineer is provide the under sluice gate because without it the weir body is
not functional.
o During construction the canal operating head should be add because of the driving the
water to the off taking canal.
o The downstream retaining wall should be increasing its length to the minimum of the
apron length to protect the scour.
o The woreda committee and kebele committee meet and solve the transport system and
then the construction material is transported.
3.3 Objective of the project
Other benefits that can be expected from the project are:
Efficiency of water use improvement;
Improved local nutrition/food security gains;
Improved management of scarce natural resources (land and water);
Rationale for the intensification and modernization of small-holder agriculture and rural
lifestyles.
The engineering study and design enables the realization of the project by the provision
of engineering structures that will allow the appropriate abstraction of the river water
for delivery in to the identified irrigation fields of the study area. Hence, this
engineering design is specifically targeted to:
Hydrologic requirements of the project and engineering structures;
The formulation of sound and stable structure, with necessary provisions that allow
safe, easy and low-maintenance operation in the service life of the project;
Prepare working Analyze drawing.
3.4 methodology
3.4.1Location
The Gabikura diversion small scale irrigation scheme is one of the proposed irrigation
developments in Amhara national regional state, North Gondar Zone, Dembia Woreda,
Buasmano kebele. Gabikura is referenced about in the south 3km from the road Azezo Asphalt
road passing to Chilga. The elevation of project site is 1894m a.s.l at the point of the top river
rich.
Wuibul
Descen Formula
Max RF ding Rank (Xi- Y= log (R/(N+1))
S.No. Year (xi) Order (m) X')^2 xi (Y-Y')^2 (Y-Y')^3 *100
1 1983 65.4 72.3 4 206.28 1.816 0.014 0.001624 16.667
2 1984 43.9 70.5 18 50.94 1.642 0.003 -0.000172 75.000
3 1985 47.8 69.4 14 10.48 1.679 0.000 -0.000006 58.333
4 1986 47.1 65.4 15 15.50 1.673 0.001 -0.000016 62.500
5 1987 41.3 63 19 94.82 1.616 0.007 -0.000553 79.167
6 1988 51.3 60.2 10 0.07 1.710 0.000 0.000002 41.667
7 1989 47.9 58.3 13 9.84 1.680 0.000 -0.000006 54.167
8
In our case Cs = -0.016 i.e. between -0.4<Cs< 0.4 so check for both higher and lower outlier.
X=
∑ RF =
N 51.04mm
−
√ ∑ ( X i− X )2 1224 . 9
σ n−1=
( N−1)
=
√ 24−1
=11.15
∑ Y =40.75mm
−
Y=
∑ Y = 40. 75 =1. 698
N 24
−
∑ (Y −Y )2=0 . 21
−
∑ (Y −Y )3=−0. 0003
−
√ ∑ ( Y i−Y )2 0 . 21
S y=
( N −1)
−
=
√ 24−1
=0 .096
N ∑ (Y i −Y )3 24∗0 . 0003
C s= = =−0 . 016
(N −1)( N −2)S 3 ( 24−1)(24−2 )∗(0 . 096 )3
y
Depth = 10YH
10^1.939= 86.97 > 72.3 it is OK!
The largest recorded value (72.3mm) is less than higher outlier (86.97). Hence, there is no
higher outlier.
−
Depth = 10YH
−
10^1.457= 28.622 < 30.9 it is OK! Y m = mean of data in log unity
K n = from table for sample size N
−
Depth = 10YH
10^1.939= 86.97 > 72.3 it is OK!
The largest recorded value (72.3mm) is less than higher outlier (86.97). Hence, there is no
higher outlier.
−
Depth = 10YH
3.4.2.6 Design rainfall analysis
After checking the consistency of the data for higher and lower outlier of the data, all the 24
years data is obtained as representative for the analysis .The probability of occurrence of
maximum probable rain fall is estimated by Gumble method.
Y T −Y n
− K T=
X T =X +K T σ n−1 Where Sn
[(
Y T =− ln ln ( ))]
T
T −1
.Where Y n = Reduced mean in Gumbl’s Extreme Value
Distribution for N sample size from table
S n = Reduced standard deviation in Gumbl’s Extreme Value Distribution for N sample
[(
Y T =− ln ln ( T T−1 ))]=−[( ln (ln ( 5050−1 )))]=3. 902
N Yn Sn
24 0.529 1.082
Y T −Y n −0.529
−
KT= = 1.082 = 3.118 and X T =X + K T σ n−1 = 51.04+3.118 x
Sn
11.15= 85.79
Table 3.3 maximum storm values for different return periods (T)
T(Return Y T −Y n −
K T= YT X T (mm )= X + K T σ n−1
Period) Sn
2 -0.150 0.367 49.366
5 0.897 1.500 61.046
10 1.591 2.250 68.779
20 2.256 2.970 76.196
30 2.639 3.384 80.464
40 2.909 3.676 83.472
50 3.117 3.902 85.798
60 3.287 4.086 87.694
70 3.431 4.241 89.295
80 3.555 4.376 90.681
90 3.665 4.494 91.902
100 3.763 4.600 92.993
100
90
Maximum Storm (mm)
80
70
60
50
40
30
20
10
0
0 10 20 30 40 50 60 70 80 90 100
Retun period
The canal head regulator is located on the right side of the weir body. The purpose of this
regulator is for delivering the maximum irrigation water desired for the command area by
controlling the amount of flow in to the main canal. The gate of the off take canal is to be
vertical sheet metal (trash rack) of 0.6m x 0.6m for closure of the opening space providing
some extra dimensions for groove insertion.
Conclusion: From stability analysis, the designed weir section is safe and to be economical,
Provide 1m top width and 3.5m bottom width.
3.8 Design of Weir Protection / RCC
In order to avoid cracking and shearing of the weir, apron and under sluice during
overflowing and incoming of boulders, RCC of thickness 200 mm was provided with proper
capping. The nominal reinforcement is taken as 0.15% of the concrete cross sectional area
per meter width.
The minimum reinforcement area is taken as 0.90% of the strength of steel.
Hence, A steel per unit length = RCC Thickness / Minimum percentage of steel area in %
= 90/fy% = 0.3 , where fy steel strength in N/mm2 and fy =300N/mm2
= 200mm/0.3 = 600mm2
Spacing (S) = (ast/A steel)*1000) where ast = πD2/4 =3.14*142/4 =153.86 then,
Spacing (S) = (153.86mm2/600 mm2)*1000=256mm.
Therefore the actual provided steel area is 600 mm2/m i.e. > 461.58 , so Provide
reinforcement bars Diameter 14mm @ 250mm C/C in both directions, which has yield
strength of 300 N/mm2 for both weir and apron cupping. This capping detail is provided for
the weir and apron the design drawing for further information.
The off take is to be vertical sheet metal of 0.6 m x 0.75m for the closure of the opening space.
Providing some extra dimensions for groove insertion. Gross area of sheet metals for the under
sluice gate will be 0.7 m x 0.8m (allowing 5 cm insertion for grooves). The grooves are to be
provided on the walls using angle iron frames at the two sides of the gate openings. The gate
(sheet metals) is provided with stiffening angle irons. A vertical raised gate is designed for the
head regulator. Since the gate is a simple Shatter Gate it can be operated easily by farmers.
0.5
kp a2
Thickness of gate was calculated by t= (
100∗δ ) where,
Off takes are used to direct water from supply canal into Field canals; usually these structures
consist of an inlet, to convey water beneath the canal bank and outlet. These are provided to off
take water from main to field canals and Turn outs was set at chainge 0+125m and 0+375m at
the main canal.
CHAPTER FOUR
4 OVER ALL INTERNSHIP BENEFITS
I bear witness for this in the Gondar Town water supply projects have been beneficiary
in upgrading the theoretical knowledge having some vision in water supply, ground water,
construction materials etc.
I also have enhanced the theoretical knowledge having from supplementary courses like
writing skill, entrepreneurship for engineers and the likes.
Building self-confidence.
Maximizing of the commitment with persons and increasing the positive feedback.
In general acquiring adequate experience which can be used in my future career is the
major once.
I myself as one of the interns have tried to enhance my capability in solving problems
which were encountered in the project work.
Generally I have improved my team work playing skill I was working, going, sharing
and high commitment with other team work I have gained the ability to work to gather
with other workers which increased our efficiency of workers.
Being responsible
During the internship, I have tried to imitate some entrepreneurial characteristics from
those who are professional in the project work.
Self confidence
CHAPTER FIVE
CONCLUSION AND RECOMMENDATION
5.1 Conclusion
The internship semester makes the new curriculum so good to give real practical skills
and make the students familiar to the outside world. Even though there was a gap between the
things which we know in the class with the outside world environment, I got practical work
experiences and benefits at the Central Gondar Small-scale Irrigation Project. Some of the
benefits the internship offered to me include;
Preparation of report
Leadership skills
Work ethics
During the internship I also develop and enhance employability skills and great sense of
responsibility and personal direction.
5.2 Recommendation
The problems to be recommended in Central Gondar Small Scale Irrigation Project are the
followings
Since there is a shortage of transport services in the company the material and
equipment office should work hard to solve this problem.
There should be enough stationary materials and access computers for the internship
students.
There should be good health center for the workers with good facilities and qualified
professional person.
There should be a psychologist in the company who can communicate or advise People.
The consultants and site engineers should agree in a diplomatic way when there is a problem
on construction aspects.
The construction should progress to be completed in a desired period.