Professional Documents
Culture Documents
For
At
Prepared by
Olympic Designs
55 Olympic Parade
HOMEBUSH NSW 2140
Tel: 1234 5678
Fax: 1234 5679
Proposed Factory Units & Office Space 7 Layland Way, Banksia
TABLE OF CONTENTS
1262R_2 Spec 3
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 4
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 5
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 6
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 7
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 8
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1. GENERAL CONDITIONS
1.1. SPECIFICATION
This document shall form part of the contract. Where any variation exists
between the drawings and this specification the contract will include the
greatest number of articles and the largest amount of superior quality of
labour and/or materials specified or shown.
1.2. PRICES
Unless otherwise stated, pricing shall be held to include for the conveyance
and delivery, unloading, hoisting, all labour, setting, fitting and fixing in
position, lapping of materials, straight cutting and waste, return of packing’s,
establishment charges, Awards and conditions payable to workmen, profit
and the supply of all necessary material, and the builder is to allow for same
in his prices.
1.6. DOCUMENTS
Figured dimensions on drawings, unless otherwise shown, are to the faces of
structural materials and figured dimensions shall be followed in preference to
scaled dimensions. Large scale drawings shall take precedence over those
of smaller scale.
All dimensions are to be checked and verified on site prior to construction.
Should there be any discrepancy between the drawings and specification,
such discrepancy is to be brought to the attention of the Architect with a view
to equitable interpretation. Otherwise, the Contract shall be deemed to cover
the alternative which involves the greater cost.
1262R_2 Spec 9
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1.8. VARIATIONS
Variations are to be approved by the Architect in writing prior to any work
being done or materials being ordered for the variation. Failure to obtain
written approval will result in the variation not being allowed.
1262R_2 Spec 10
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1.10. INSPECTIONS
The Architect is to be given at least three (3) days notice to inspect or
arrange for an inspection of any item required to be inspection prior to
concealment.
1.11. SERVICES
All services are to be extended from Authorities supply with all required extra
equipment and operations to ensure satisfactory completion and compliance.
Temporary services are to be made available to all subcontractors. Install all
necessary equipment and pay all fees associated with the provision of all
temporary services. Comply with all regulations and Authorities
requirements.
1262R_2 Spec 11
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1.14. SIGNBOARD
Provide, erect and maintain a signboard in a location to be determined by the
Architect until completion of the Works.
The board is to be approximately 1500 x 2400 and bear the name of the job
and the names, addresses and Proprietor, Builder, Architect and Engineers.
1.16. ON COMPLETION
On completion of the works prior to handing over to the Proprietor the
following is to be carried out:
1. Clean and remove all surplus materials, rubbish and dirt.
2. Make good all damage, stains and blemishes and replace materials
where necessary.
3. Clean all surfaces, including vacuum cleaning of carpeted areas and
clean and polish glass (both sides).
4. Ease all doors, windows, drawers and check, oil and adjust all locks
and closers.
5. Check test and ensure that all services and equipment are functioning
efficiently and satisfactorily.
6. Label all keys with suitable label and hand over to the Proprietor.
7. Provide the Proprietor with all required guarantees, warranties,
brochures, tests, drawings, surveys, manuals, service agreements,
certificates, as built hydraulic drawings and the like.
1.17. COMPLIANCE
All work shall comply with the requirements of the Building code of Australia,
latest edition of relevant Australian Standards and all Authority Regulations
having jurisdiction over the works.
1262R_2 Spec 12
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 13
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 14
Proposed Factory Units & Office Space 7 Layland Way, Banksia
3. CONCRETE
3.1. GENERALLY
All reinforced concrete is to be in strict accordance with the Engineer’s details
and specification. All of the concrete used in the Works shall conform to the
standards and requirements of the current SAA Code AS 1480 and the ACSE
Concrete Specification as amended.
Where a discrepancy exists between the Engineer’s documentation and this
specification, the Architect is to be notified immediately for interpretation.
Where this is not feasible the Engineer’s documentation shall take priority
over this specification.
All of the concrete used in the Works, shall be placed and finished by
experienced and competent tradesmen, using the best trade practises and
the appropriate plant and equipment. The Builder shall be responsible for
supervising and the execution of all on site functions associated with the on
site concrete work and shall ensure that he or an appointed competent
representative familiar with the Codes and Standards described hereafter, is
in attendance during all concreting operations to direct the actual execution of
the Work.
3.3. DRAWINGS
Before commencing each separate stage of the work detailed drawings shall
be issued to the Builder setting out the dimensions of the components, the
required type, strength and consistency of the concrete and the size, grade
and position of all reinforcing. The information shown on the details shall be
strictly adhered to except where the Architect or Engineer to the contrary
issues specific directions.
3.4. INSPECTION
The architect’s approval shall be obtained at the completion of each stage of
construction.
1262R_2 Spec 15
Proposed Factory Units & Office Space 7 Layland Way, Banksia
The Engineer shall inspect all reinforcement prior to pouring of concrete. The
Builder shall give sufficient notice, not less than 48 hours, to permit an
inspection to be carried out without delaying the progress of the work on site.
At time of concrete placement, all formwork shall be clean and free of wood
shaving, sawdust, loose reinforcement or tie wire and all other refused and
deleterious matter.
3.6. MATERIALS
All materials shall conform to the relevant SAA Code or Specification, or
where no such code exists to the relevant ASTM Code. In particular the
following materials shall comply with the respective Codes as scheduled;
• Chemical Admixtures, AS 1478 & 1479
• Portland Cement, ACSE Specification Type A, AS 1379
• Aggregates for Concrete (Grading), AS 1465, 1466, 1467
• Plain Steel Reinforcing Bars, AS 1302
• Hard Drawn Steel Reinforcing Wire, AS 1303
• Hard Drawn Steel Wire Reinforcing Fabric, AS 1304
• Methods of Testing Portland Cement Concrete, AS 1012
Copies of SAA Code AS 1480 and ACSE Specification (as amended) shall
be kept on site at all times.
No admixtures other than those shown on the Engineer’s drawings shall be
included in the concrete mix without the express approval of the Engineer.
Generally
The cost of all sampling and test procedures shall be borne by the Builder.
An approved NATA Laboratory shall carry out the sampling of all concrete
and the making, transporting and testing of all specimens of structural
concrete. Test cylinder samples shall be made and cured in accordance with
AS 103 (1957) and shall be properly stored on site under reasonably
controlled conditions. The moulds shall be carefully transported to the testing
1262R_2 Spec 16
Proposed Factory Units & Office Space 7 Layland Way, Banksia
laboratory and the subsequent curing, capping and testing shall be performed
in the laboratory. All test cylinders shall be clearly marked and true copies of
all test results shall be given to the Architect as soon as possible after their
receipt by the builder.
Samples shall be taken in accordance with the ACSE Specification and as
noted on the Engineer’s drawings. The slump test from each sample shall be
made in accordance with AS 1012.
Number of Samples
The sampling shall be distributed evenly throughout the number of trucks or
site batches necessary for any pour, and in pours of over three truck loads
not more than one sample shall be taken from each ruck or each site batch.
Where the source of supply, or the specified quality changes during the pour,
then the ACSE Specification shall be used to determine the number of
samples required from each section of the pour.
Rejection
Formed and hardened concrete shall be rejected at the Site if:
1. It is porous, segregated, or honeycombed.
2. A construction joint has been made at a location or in a manner not in
accordance with the Engineer’s drawings.
3. If the reinforcing steel has been disturbed.
4. The construction tolerances have not been achieved.
5. The required surface finish has not been achieved.
6. The test strength is below that specified.
7. The concrete does not meet other requirements of this specification.
3.10. FORMWORK
The Builder shall allow for the supply and erection of all recoverable, non
recoverable, slab joint and other forming as required to form the in-situ
concrete elements shown on the accompanying drawings, and shall
dismantle and remove same on completion.
It shall be the Builder’s responsibility to ensure that the formwork is of
adequate strength to properly support all dead and live loads imposed during
construction without unacceptable deflection. Formwork joints between
decking units shall be sufficiently tight to prevent the excessive leakage of
1262R_2 Spec 17
Proposed Factory Units & Office Space 7 Layland Way, Banksia
wet concrete from formwork. The formwork shall be of the respective types
to yield, after tripping, the quality and type of finish as specified elsewhere.
Provide all necessary dressed timber block outs and strips to form the
rebates, recesses, fillets, splays groves required by the drawings. Timber
strips forming grooves are to be splayed and sealed to prevent swelling.
Splays to be 1:4 or as detailed.
3.12. REINFORCEMENT
Fabricate, supply, deliver and install the rod and fabric reinforcement for all
concrete elements of the types, grades, sizes and spacings shown on the
Engineer’s drawings and specification.
All reinforcement shall be accurately placed, securely tied and adequately
supported clear of the forms to provide the required cover and prevent
displacement of the reinforcing during the concrete placement, compaction
and finishing. Reinforcement in slabs on ground or fill shall be supported on
bar chairs on pie plates. Reinforcement to wall panels shall be supported on
approved plastic bar chairs.
All reinforcement shall be clean and free of oil loose rust and scale and other
bond inhibiting matter.
When the reinforcement is completed and before the concrete is placed the
Engineer shall inspect the reinforcement any necessary adjustments made
prior to concrete placement.
1262R_2 Spec 18
Proposed Factory Units & Office Space 7 Layland Way, Banksia
The Builder shall provide adequate runways where necessary and supported
soundly off the formwork and clear of reinforcement for the transport of
concrete over formwork.
The tops of all hobs, kerbs, toes pedestals and footings to be built upon or to
provide fixings for following trades shall be accurately screeded off to a true
and level face, except those to receive surface finishes.
3.14. COMPACTION
Concrete shall be thoroughly compacted by mechanically activated vibrators
operated only by experienced tradesmen. The vibration of concrete must not
be prolonged such as would cause the separation of the ingredients. Where
the throat dimensions of the forms prevents its internal use, the vibrator shall
be applied to the external faces of the formwork.
3.16. STRIPPING
Formwork shall not be disturbed until the concrete has hardened sufficiently
to withstand such action without damage. The formwork shall be uniform and
progressively removed so as to avoid creating uneven stresses in the
concrete.
3.17. JOINTING
Provide the slip joints and similar between concrete elements and masonry
walls as shown on the Engineer’s drawings.
Where concrete slabs on fill or natural ground butt walls or columns, insert a
strip of approved 3 ply bituminous felt “road jointing”, equal in width to the
depth of the slab and butt jointed between lengths. Excess jointing material
projecting above the slab surface shall be trimmed off on completion.
1262R_2 Spec 19
Proposed Factory Units & Office Space 7 Layland Way, Banksia
Form up all keyed construction joints and sawn or formed weakened plane
joints as shown on the Engineer’s details.
1262R_2 Spec 20
Proposed Factory Units & Office Space 7 Layland Way, Banksia
4. STRUCTURAL STEELWORK
4.1. EXTENT OF THE WORK
The work shall consist of the supply, fabrication and erection of all steelwork
indicated on the drawings and shall include surface treatment, storage,
delivery, off loading erection, on site welding, all connections and fastenings,
miscellaneous attachments, anchor bolts, wedging, permanent grouting and
necessary repairs to surface treatments.
4.4. ATTENDANCE
The Contractor shall perform all works in association with the erection of the
structural steel roof framing which shall include but not be restricted to the
following:
a) Prepare the concrete elements to receive the steel beams and columns.
b) Provide hold down bolts and other necessary fixings and accurately
position same for carrying in concrete elements in accordance with the
shop drawings.
4.5. ATTACHMENTS
The Contractor shall arrange an allow for the necessary drilling’s and cleats
to support and connect finishes and structure as shown on the drawings.
1262R_2 Spec 21
Proposed Factory Units & Office Space 7 Layland Way, Banksia
5. METALWORK
5.1. GENERALLY
All mild steel specified in this section shall be of uniform section and free from
pitting and other blemishes. Any metal components which are cut, pierced or
trimmed by mechanical saw or oxy-acetylene torch shall be ground after each
process to remove the rough cut edges.
Except in structural components or as otherwise specified, all welds shall be
6mm continuous fillet welds. Welds, which are uniform in contour and
dimension for their entire length, shall require no further treatment unless
otherwise specified. Inconsistent welds shall e ground back flush.
5.2. MATERIALS
Unless otherwise specified, metals shall be suitable to their required function,
finish and method of fabrication and comply with the relevant standards.
Sections shall be of adequate strength and stiffness for their purposes.
Extrusions shall be straight, with sharply defined profiles, free from all defects
impairing appearance or durability.
Prepainted steel sheets shall be equal to “Lysaght Colorbond” in all respects
and shall be suitable for exterior or interior use as recommended by the
manufacturer.
Aluminium sections and components shall be of B 6063 or KE 45 allows and
have minimum 0.02mm thick clear anodised finish to all exposed surfaces,
unless otherwise specified.
All extrusions shall be of smooth finish and free of excessive die lines.
Galvanised components shall be hot dip galvanised after fabrication, unless
otherwise specified.
5.3. WORKMANSHIP
Fabricate and assemble in the workshop wherever practicable. Use metals
suited to the process or finish specified. Match colours of sheet metals and
extrusions in colour finished work.
Cut edges, drilled holes, riveted joints, and flat sheets shall be clean, neat
free from burrs and indentations. Remove sharp edges without excessive
reducing. Fit mitred joints accurately to a fine hairline.
Form bends in steel tubing without deforming the true cross section, using
methods recommended by the tube manufacturer.
Items to be assembled and erected on site shall be preassembled in the
workshop and match marked. During assembly and erection, do not strain,
twist, bend or open such items to bring them to their true positions.
Use and mark proprietary items in accordance with the manufacturer’s
recommendations.
1262R_2 Spec 22
Proposed Factory Units & Office Space 7 Layland Way, Banksia
5.4. FASTENINGS
Generally
Fixings, fastenings, anchors, lugs and the like shall ensure the rigidity of the
assembly. All metal fixing components are to be of non-corroding materials
or are to be hot dip galvanised or electroplated.
All fixings are to be located and spaced as detailed, specified or
recommended by the manufacturer of the item that is to be fixed and to the
satisfaction of the Architect.
Pop rivets are not to be used on any item unless approved for each specific
use.
Unless otherwise specified masonry anchors shall be of the patent expansion
type of approved manufacture.
Unless otherwise specified exposed metal thread screws shall have
countersunk Philip heads. Countersinking for screws shall be of the exact
size of the screw head that shall finish flush.
Aluminium Fastenings
Fastenings to aluminium or alloys shall be aluminium alloy or non magnetic
stainless steel unless otherwise specified. Cadmium-plated steel fastenings
shall not be used except in protected situations subject to approval. Visible
fastenings shall be colour matched to adjacent aluminium work.
5.5. PROTECTION
All finished metalwork exposed to view on completion of the works shall be
adequately protected during installation and for the duration of the works. On
completion of the contract remove all protective materials, clean down all
surfaces and leave whole in first class order.
Do not weld previously galvanised members unless unavoidable. In such
cases, hot zinc spray or redip the whole item on completion. If neither is
practicable subject to approval, cold galvanise with an approval zinc rich
epoxy based paint to manufacturers recommendation.
1262R_2 Spec 23
Proposed Factory Units & Office Space 7 Layland Way, Banksia
5.7. ANODISING
Aluminium to be anodised shall be given a matt surface by caustic etching or
polishing, chemically cleaned and given an anodised coating in accordance
with AS 1231 or AS 1956 as appropriate. Thickness shall be 0.20 – 0.25mm
unless otherwise specified.
Colour anodised finishes shall be prepared by an approved process using
suitable dye pigments, or special alloys, or special hard coat alloys and
electrolytes or a combination of all of these. Colour shall be equal to
approved samples.
1262R_2 Spec 24
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 25
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 26
Proposed Factory Units & Office Space 7 Layland Way, Banksia
6. MASONRY
6.1. GENERALLY
Pre plan all work, confer, co-operate and execute to suit the needs of all
trades and services. Determine the locations of all openings and items to be
built in prior to commencement.
All of the work specified in this section shall be executed by experienced
tradesmen using the best trade practices and first quality materials.
6.2. STANDARDS
The materials and methods employed shall conform to the most recent
published standards of the relevant SAA Specifications and Codes.
AS 1640 Brickwork in Buildings
AS 1225 & 1226 Burnt Clay and Shale Building Bricks
AS 1475 Concrete Blockwork
AS 1500 Concrete Building Blocks
ASA 123 Mortar for Masonry Construction
AS 1315 Portland Cement
AS 1316 Masonry Cement
ISO 324 Metal Wall Ties in Brickwork
ISO 325 Lightweight Reinforcement for Brick and Blockwork
ISO 326 Bitumenous Damp Proof Courses with Metal Core
6.4. MATERIALS
Common Bricks
Shall be of nominal 230 x 150 x 76mm dimensions, free of callows and
clinkers and having a minimum compressive strength of 20 MPa (equal to
Boral PW76).
Concrete Blocks
Shall conform to AS 1500 and shall be machine made as supplied by Boral
Besser or other approved manufacturer. Blocks shall be of standard sizes
which conform to 100 module, allowing for 10mm joint, and shall be sound
with sharp arris and free of cracks and other defects. All blocks shall be
standard natural grey unless otherwise specified and shall be high pressure
cured by autoclave method.
1262R_2 Spec 27
Proposed Factory Units & Office Space 7 Layland Way, Banksia
Where concrete blocks are used in face work, in addition to clean sharp
arrises and expose faces shall be of uniformly fine textures and free of any
blemishes. All blocks shall be delivered to site on pallets, PVC wrapped and
properly covered until their use.
Cement
For use in masonry mortars shall be fresh Portland Cement conforming to AS
131.
Lime
Shall be supplied ready for use from an approved source and shall comply
with the relevant SAA standard.
Sand
Shall be washed, free from excessive clay, saline, organic and other
deleterious substances and shall comply with the relevant SAA standards.
Water
Shall be clean, portable and drawn from and uncontaminated source.
Concrete
Concrete infill to reinforced concrete block retaining walls where required by
the Engineer’s drawings, is to be of the strength nominated by the Engineer
and is to be supplied, mixed and placed to the standards as specified under
“Concrete”.
All materials and components to comply with BCA Specification C1.10
regarding Fire Hazard Properties.
6.5. MORTARS
Pre mixed and site mixed mortars shall comply with AS 1640 Brickwork Code
and AS 123 Mortar for Masonry Construction.
Site mixed mortars for use in concrete block retaining walls shall be
Engineer’s details.
Site mixed mortar for use in all other clay bricks shall be composed of 1 part
Portland Cement, 1/10 part slaked lime and 6 parts sand. No plasticiser shall
be used without the supervisor’s specific approval, and where such approval
is given, the plasticiser shall be mixed in accordance with the manufacturers r
recommendations and given an equivalent strength.
6.6. LAYING
All block and brickwork shall be laid on full beds of mortar, in true and level
runs, with all vertical joints fully pointed. No section of work shall be carried
up more than 1500 above the proceeding work. All work shall be in straight
wall lengths, and shall be accurately gauged.
Cores in hollow blocks which are hereafter specified, to be reinforced and
concrete filled shall be kept free of excess mortar and droppings. All
1262R_2 Spec 28
Proposed Factory Units & Office Space 7 Layland Way, Banksia
6.9. JOINTING
Brickwork joints are to be left ready for render. Blockwork joints are to be
lightly ironed.
1262R_2 Spec 29
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 30
Proposed Factory Units & Office Space 7 Layland Way, Banksia
7.2. DOORS
All doors to be approved manufacture and shall comply with AS 1980 and AS
1909.
Solid core doors shall comply in all respects with the requirements of the
relevant standards. Internal doors 35mm, external doors 40mm with marine
ply.
Hardware shall be provided to suit the required purpose and shall be fixed
strictly in accordance with the requirements of the manufacturer, and comply
with BCA NSW in all respects.
The Builder is to allow for the supply, delivery and fixing of hardware,
complete with all necessary suiting and master keying of locks, sampling of
cylinders, tagging of keys and similar for handover to the Proprietor.
Glass sliding egress doors must comply with section D2.19 of the BCA, and
be provided with a failsafe automatic reset mechanism. All required exit door
hardware to comply with clause D2.21 of the BCA regarding operation of
latches.
1262R_2 Spec 31
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 32
Proposed Factory Units & Office Space 7 Layland Way, Banksia
Compliance
All work is to comply with AS 1668 Parts 1 and 2/1991/, BCA, Sydney
Ventilation Code and all other relevant codes and regulations.
Associated Work
a) Support platforms for condenser units, including all penetrations and
flashings.
b) Relief air grilles to doors and ceilings.
c) Sub-mains, switchboards, control gear and wiring from the units
distribution board.
d) Condensate drainage.
e) All other works necessary for a complete installation.
f) Refer to Mechanical Specification for “Work by Others” for mechanical
services.
“As-Built” Drawings
On completion provide “as-built” drawings of all systems, including wiring
diagrams, equipment specifications and manufacturers maintenance
manuals.
1262R_2 Spec 33
Proposed Factory Units & Office Space 7 Layland Way, Banksia
4. supply and installation of conduits, draw wires, frames and the like
required by Telstra, to enable telephone installation to factory.
5. supply and installation of a tw0 (2) channel perimeter wall duct in the
office area equal to ESCO AS 100 extruded aluminium with selected
marviplate cover piece.
6. supply and installation of external flood lights located on parapet
7. supply and installation of wiring to the stormwater pump
8. testing and commissioning
9. payment of all authority fees and charges
These services shall include the above general provisions as well as all
others necessary to satisfy the requirements of the Energy Authority and the
relevant Council.
The Builder shall allow for attendance upon the subcontractor performing
these works, including the forming of openings or recesses required, the
formation of any platforms that may be required, the making good of surfaces
and any other attendance necessary to complete the subcontract.
The Builder is to arrange with the contractor, on completion, for the
production of all “as built” drawings, circuit diagrams, equipment and light
fitting guarantees and similar that may be necessary.
1262R_2 Spec 34
Proposed Factory Units & Office Space 7 Layland Way, Banksia
9. ROOFING
9.1. EXTENT
The extent of the work comprises all roofing, roof plumbing and associated
work including miscellaneous metal trim to make the whole building entirely
waterproof, weather tight and birdproof on completion.
9.2. SUBCONTRACTORS
An approved specialist subcontractor, who shall be fully experienced in the
fixing, flashing and the like of the roofing specified, shall install the complete
roof and associated works.
1262R_2 Spec 35
Proposed Factory Units & Office Space 7 Layland Way, Banksia
9.7. GUTTERS
Box gutters to the above roof shall unless otherwise noted be formed as
shown on the detail drawings out of 1.0mm zincalume to be laid on support
decking as specified below, turned up against gutter purlins and carried
under roof sheeting as shown. All joints to be lapped, sealed and pop
riveted. Form expansion joints as a stop end where shown with zinc saddles.
Gutters to be of sizes as shown on the drawings, by Hydraulic consultant.
Provide 300x100mm overflow spouts in locations shown. Leave the whole of
the box gutter in a thoroughly water tight condition.
Fall gutters from a high end to sump. Sides of gutters are to have tops
horizontal and trimmed flush with tip of gutter purlin as detailed.
1262R_2 Spec 36
Proposed Factory Units & Office Space 7 Layland Way, Banksia
9.9. SUMPS
Provide zincalume sheet steel sumps, 500mm long, full width of gutter and
200mm deep. Lap seal and pop rivet all joints. Fit sump guards of 6mm
galvanised steel mesh, spacings 50x50mm over sumps.
9.11. ROOFLIGHTS
The Translucent Sheeting shall be Ampelite industrial quality sheeting type
SC as manufactured by Ampelite Fibreglass Pty ltd or similar to comply with
AS 2376 Part 2, Licence No 986. The weight of the sheet shall be *2400g/m2
and shall be manufactured to conform with the Trimdek profile and Opal
colour sheeting shall be installed in accordance with Ampelite fixing
instructions and with the Plastics Building Sheets – General Installation
Requirements and Design of Roofing Systems AS 2424, 1991.
1262R_2 Spec 37
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 38
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 39
Proposed Factory Units & Office Space 7 Layland Way, Banksia
10.4. DRAWINGS
All pipe runs, branches, levels and the like, shown on the drawings are
diagrammatic and are included for tender purposes only and as being
indicative of preferred routes of pipes.
The Hydraulic Contractor shall be entirely responsible for the design of the
respective reticulations and for the accuracy of all as built drawings
submitted.
10.5. MATERIALS
Generally
All pipes and fittings and other materials shall be of the best quality of their
respective kinds and must comply with the requirements of the responsible
authority and be in accordance with their respective SAA specifications.
Drainage pipes
All soil and sullage pipes shall conform with Australian Standards for vitreous
clay pipes or such higher standards as may be required by the Water Board.
UPVC and polypropylene pipes shall be manufactured in accordance with AS
1435 for Sewer Waste and Vent applications.
Where required as agricultural drains they shall be slotted with a 4mm saw at
150mm spacings and wrapped in woven “Geofabric” or other approved filter
sock.
Plumbing pipes
All copper pipes shall be solid drawn tube in accordance with AS 1432.
Gauges of tubing shall be in accordance with:
10 to 15mm diameter 0.9mm
18 to 20mm diameter 1.0mm
25 to 65mm diameter 1.2mm
80 to 125mm diameter 1.6mm
Brass tubing shall be 70/30 quality gauge, conforming to Type 5, AS 1432.
1262R_2 Spec 40
Proposed Factory Units & Office Space 7 Layland Way, Banksia
Drainage works
All stormwater and sewerage lines shall be laid in straight runs, with uniform
gradients bedded solidly on the barrel on a 75mm minimum sand bed. Join
sewerage and stormwater pipes with approved rubber rings.
Provide and lay all necessary traps, sealed gulleys, radiussed bends, vents,
slope junctions, tapered reducers, induct pipe fittings and other accessories
required to complete the service in accordance with the Water Board and
local Council requirements. Induct pipes are to be provided with approved
brass covers.
All frames to covers and gratings are to be built in to the manufacturer’s
specification and all covers and gratings are to be fitted, protected and where
necessary filled in wit concrete in accordance with the manufacturer’s
specifications.
Sanitary plumbing
Generally work is to be carried out to all sanitary fittings shown on drawing
and referred to in this Specification. All fabrication in an approved manner
and to the complete satisfaction of the Water Board requirements and in
accordance with relevant by-laws.
Unless otherwise specified clips and brackets for copper pipework shall be
galvanised mild steel separated from the copper by PVC strip or similar
approved materials. Fixings required for chrome plated pipework shall be
themselves chrome plated.
1262R_2 Spec 41
Proposed Factory Units & Office Space 7 Layland Way, Banksia
Water services
All copper tube to be Table 3, type 3 tube or of other tubing approved by the
Architect and the Water board. Tubes 25mm and less are to be of capillary
fitting type. No tubes are to be less than 12mm outside diameter for cold
water.
Supply and install all necessary control valves and cocks, reducers, elbows
couplings, tees, nipples, brushes, unions and other fittings necessary to
complete the service and to effect the connection of satisfactory water flow to
all sanitary fixtures, equipment and faucets or other outlets as shown on the
drawings or as specified herein.
No pipes or fittings shall be cast into concrete slabs. Pipes passing through
slabs shall be fed through oversized cores or sleeves.
The whole of the service shall be pressure tested on completion of each
stage and before service is concealed Rectify any faults discovered.
Pay all fees, arrange for extension from existing supply main or where
necessary obtain a new tapping in the Board’s mains as agreed to by the
Water Board.
From the new supply, extend the water service reticulation service in
appropriate minimum diameters to all fixtures, fittings, hosecocks and the like
shown on the drawings, schedule in an specified hereunder, all requiring
supply.
Hot water
Supply and fix hot water units to locations as shown on hydraulic drawings.
1262R_2 Spec 42
Proposed Factory Units & Office Space 7 Layland Way, Banksia
10.8. TESTING
Prior to any backfilling or building in, carry out all tests as before specified
and as required by Authorities and rectify any rejected, faulty or
unsatisfactory work.
10.9. SINKS
Supply and install 1200 long single bowl and drainer stainless steels ink
equal to Clarke.
1262R_2 Spec 43
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 44
Proposed Factory Units & Office Space 7 Layland Way, Banksia
11.5. WATERPROOFING
Waterproofing of all wet areas to be undertaken in accordance with AS 3740
(clause F1.7).
1262R_2 Spec 45
Proposed Factory Units & Office Space 7 Layland Way, Banksia
Membrane
Provide a proprietary liquid applied or sheet membrane system which:
• has a current Australian Building Products and Systems Certification
Scheme certificate; or
• has a current technical opinion issued by the Australian Building
Systems Appraisal Council stating that the system is suitable for use
as a waterproofing system for use in wet areas and associated floors
and wall/floor junctions which are to be tiled
Hob installation
Extend membrane over the hob and into the room at least 50mm.
External tiling
Provide a waterproof membrane under external floor tiling, to balconies and
over habitable rooms, which forms a drained tank suitable for continuous
immersion. Do not run under bounding walls.
Curing
Allow membrane to cure fully before tiling.
1262R_2 Spec 46
Proposed Factory Units & Office Space 7 Layland Way, Banksia
12.2. GENERALLY
The whole of the work shall be carried out by competent tradesmen under the
supervision of a foreman who is responsible to the respective subcontractor.
All material such as cement, and water shall comply with the specification as
under “Concrete”.
12.5. RENDER
Render to be minimum 12mm thick. Prepare sub-base as required to ensure
a good bond and finish render ready for painting.
1262R_2 Spec 47
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 48
Proposed Factory Units & Office Space 7 Layland Way, Banksia
13. CEILINGS
13.1. SUSPENDED CEILINGS
Suspended ceilings to be drop in panel type support on a 600x1200 T bar
suspension system, ceiling panels to be equivalent to “Freshtone” vinyl
coated plasterboard tile by “Gyprock”. Suspension system to be exposed
grid suspended from roofing purlins/concrete slab soffit as applicable. All
exposed grids to be prefinished in white complete with all matching
accessories and trims. All materials and fixings to be in complete
accordance with manufacturer’s recommendations.
Marked or damaged panels or grids are to be replaced or painted as required
by the Architect.
Setout for the grids to be in accordance with the drawings. Ensure that grids
align with window mullions and provide necessary cuts and infills. All cut tiles
to have rebated edges.
Ceilings to amenities area are to be have vinyl faced plasterboard tiles.
1262R_2 Spec 49
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 50
Proposed Factory Units & Office Space 7 Layland Way, Banksia
14. GLAZING
14.1. GENERALLY
This part comprises all glass and glazing, including factory glazing of
windows, doors, balconies and the like items specified in other parts, shown
on the drawings and as necessary.
14.2. MATERIALS
Glass shall comply generally with BS 952, be the kinds and grades specified
or shown on the drawings, and shall be free from cracks, scratches, bubbles,
blisters, and other defects which will interfere with the appearance or service.
Glazing not otherwise specified shall be float glass of thickness complying
with the requirements of AS 1288 for a basic design wind velocity of 40
metres/second and the applicable terrain category stated in AS 1170 Part 2.
External glazing to aluminium framed doors, windows and balconies to be of
“Pilkington Light Green” in the appropriate grades.
Mirrors are to be 6mm polished float, after cutting silvered by process equal
to copper back. Edges to be polished before coating. Provide semi
concealed approved fixing clips spaced at maximum 900 centres.
14.3. WORKMANSHIP
Glass to be cut smooth with straight edge and the full size required by the
various openings but maintaining clearances. Nipping to reduce oversized
dimensions, flares and the like will not be permitted. Where glass edges but
at mitred corners and at butted junctions edges shall be ground to provide
true straight edges.
Sealants to be fixed strictly to manufacturer’s written instructions. Glass to
be cleaned and sealant trimmed off to approval.
14.5. ON COMPLETION
Just prior to practical completion replace all scratched and broken glass and
thoroughly clean and polish all glass provided in whole contract.
1262R_2 Spec 51
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 52
Proposed Factory Units & Office Space 7 Layland Way, Banksia
15. PAINTING
15.1. GENERALLY
All materials used in the painting trade shall be of the best quality available
and shall conform to their respective standards.
All materials in this trade shall be delivered fresh to the site in sealed
containers bearing the name and brand of an approved manufacturer. No
trade lines will be accepted.
The respective manufacturer’s instructions and specification for the
preparation of surfaces and the preparation and application of the materials
shall be strictly adhered to. Breaking down and thinning of materials, unless
recommended by the manufacturer is not permitted.
Supply, maintain and remove on completion all necessary masking, drop
sheets or other protective measures required to prevent the permanent
disfigurement of prefinished surfaces and equipment or surfaces to which no
other finish is to be applied.
Any spillage, splash or spray marks shall be removed immediately to the
Proprietor’s satisfaction. If removal and cleaning is not acceptable the whole
section of the affected area is to be retreated, painted or replaced to the
Proprietor’s satisfaction.
The medium for application of the paints and other applied films, shall be a
type recommended or stipulated by the respective manufacturer. Irrespective
of the medium employed, the finished film or coat shall be homogeneous and
of uniform coverage, free from gaps, and semi bare patches and other
blemishes.
Allow for neatly cutting in, on straight lines between different materials and/or
colours and at the natural junction between planes.
Paint coats or films shall be free of runs or sags. No painting shall be
executed on improperly prepared surfaces or under atmospheric conditions
which would be detrimental to the quality of the finishing coat.
Generally undercoats and pre finishing coats shall be applied in varying
shades of the final coat. Final colours will be as selected, colours shall be of
the manufacturer’s standard architectural colour range but the painter will be
expected to tint colours not available or not standard. Any work not bearing
out to this or the paint manufacturer’s specification is to be given an
additional finishing coat.
The Builder is to provide all scaffolding, assistance and attendance for this
trade. The contractor is to allow for and provide samples of finishes or
colours as requested.
15.2. PREPARATION
Suitably prepare substrates to receive the painting system specified including
but not necessarily limited to the following:
• clean down,
1262R_2 Spec 53
Proposed Factory Units & Office Space 7 Layland Way, Banksia
• remove loose and foreign matter including grease, oil, laitance, dust,
dirt and the like,
• fill cracks and holes,
• sand down, and
• leave smooth
Unless otherwise specified the surface shall be dry before painting
commences. If there is mould or moss on the surface, treat it with an
appropriate fungicide in accordance with the manufacturer’s
recommendations and treat efflorescence if present.
Internal plasterboard
All cavities shall be stopped as required with approved plaster filler, the whole
rubbed down to remove all extraneous material and irregularities.
Apply:
• one coat sealer
• one coat undercoat
• two coats satin acrylic
Painted woodwork
Internal joinery items to be painted, shall be sanded smooth, all holes and
cavities shall e stopped, any knots shall be sealed with knotting varnish, the
whole sanded smooth and cleaned.
Apply:
• one coat undercoat
• two coats full gloss enamel
1262R_2 Spec 54
Proposed Factory Units & Office Space 7 Layland Way, Banksia
15.6. ON COMPLETION
Do all making good and cleaning, patching and touching up to match
adjacent surfaces and colours.
1262R_2 Spec 55
Proposed Factory Units & Office Space 7 Layland Way, Banksia
1262R_2 Spec 56
Proposed Factory Units & Office Space 7 Layland Way, Banksia
Roller Shutter
Colour B: “Fremantle
Sails WH” Solargard
1262R_2 Spec 57
1262R/2 Pg 1 of 31
Notes
2000
18500
Amendments Date
19 x ps
5 4 3 2 1
5400
Plant Schedule
2500
ps pennisetum setaceum
(Crimson Fountain Grass)
ll lomandra longifolia cv Katrinus
WAY
ap acer palmatum
1 x ap 3 x ll
(Japanese Maple)
Boundary 73200 90°0'00"
LAYLAND
Note: All garden beds to have
7 x ta 100mm layer of hard wood
3 x ll chip mulch
1 x ap
19 x ps
OLYMPIC DESIGNS
6 7 8 9 10 *************************************************
Existing dwelling to
be demolished
T7 T8
T6 All existing trees &
shrubs to be removed Amendments Date
212
T9
LOT
TREE GIRTH (mm)
1 1150
T5
2 500
3 550
4 550
5 750
WAY
6 600
Boundary 73200 90°0'00"
T4
7 300
8 450
43
9 350
T3
LOT
LAYLAND
T2
42
Existing shed to OLYMPIC DESIGNS
T1
be demolished
*************************************************
LOT
Homebush NSW 2140 Fax: 1234 5679
D D D D D
25 16 15 10 1
RC precast wall panels to eng. FRL 90/90/90 wall RC precast wall panels to eng.
details details
FRL 90/90/90 wall u/s of roof FRL 90/90/90 wall u/s of roof
Amendments Date
sheets sheets
150 150
2875 2500 2500 2875 4620 1275
150
4620 4620
90 90 90 90 90 90
150 90
1060 1595 2450 2450 1595 1060
1250 1370 1910
90 90 150 90 90
1250 1280 1910 1910 1280 1250
175 150 175
2525 2675 2675 2525
350 typ
175
90
5
90
4
1250
1250
3 2 1
90
1250
1250
1250
350 typ
1425
1425
350 typ
1425
TEA TEA TEA 600 625
100
2120
2120
2120
3175
3175
350 typ
350 typ
2475
2475
D D D
1200
1200
300
90
LOADING LOADING LOADING 14 9 LOADING LOADING 2
90
90
CL CL CL
6835
6835
3575
3575
1490
1490
3575
1490
BAY BAY BAY D D BAY BAY D
D D UP UP D D precast concrete
1310
1310
D D
4905
4905
13 8 3
4905
4830
90
22 21 20 19
wheel stop
90
23 18
90
90
3485
3485
90
2450
CL TEA TEA CL D D D
2450
1200
UP UP UP
1910
1910
1505
1505
1
1505
12 7 4
300
750
150
150
150
150
150
150
150
W W W W
1650
5 4 3 2
4050
4050
4050
4050
3850
3950
terra cotta pavers on
2100
D D D D D 300 225
sand and cement bed
24 17 11 6 5
150
150
150
DP
150
150
600
900
600
600
600
600
600
RS B B RS RS B B RS RS B
DP
650
DP
5 4 3 2 1
B B B DP B B B
3425 1200 600 600 1200 3425 2125 1200 1350 1200 2125 150
150 150
150
OLYMPIC DESIGNS
150
5500
over
*************************************************
B B B DP B B B
RS RS RS RS RS
650
DP DP
600
600
600
600
600
6 B B 7 8 B B 9 10 B
900
600
150
150
DP
150
150
150
D D D D D
2100
300 225
36 41 46 51 56
terra cotta pavers on
3950
3850
4050
4050
4050
4050
sand and cement bed
1650
W W W W
Amendments Date
150
150
150
150
150
26 27 28 29
150
150
750
300
1505
1505
1505
1910
1910
D D D W
1200
2450
2450
2450
UP UP UP
CL TEA M/DIS M/DIS TEA CL 48 M/DIS M/DIS 53 58 M/DIS 30
3485
3485
90
90
90
D D
4830
90
4905
4905
4905
D D D D precast concrete
90
1310
1310
38 43 D D D
40 45
39 UP UP 44
wheel stop
3575
1490
3575
3575
1490
1490
BAY BAY BAY 49 54 BAY BAY 59
6835
6835
CL CL CL
90
90
LOADING LOADING LOADING D D LOADING LOADING
90
D
1200
1200
300
2475
2475
350 typ
50 55 60
350 typ
3175
3175
2120
2120
2120
100
1425
1425
1425
1250
1250
1250
TEA TEA 350 typ TEA 600 625
8 9 10
350 typ
6 7
90
1250
1250
350 typ
90
90
175
200
175
350 typ 1425 3195
150
3195 1425
1425 3195
2525 2675 2675 2525
175 150 175
1250 1280 1910 1910 1280 1250
90 90 150 90 90
1250 1370 1910
1060 1595 2450 2450 1595 1060
150 90 90 90
90 90 90 90
4620 4620
150
2875 2500 2500 2875 4620 1275
150 150
5375 5375
150
FRL 90/90/90 wall u/s of roof FRL 90/90/90 wall u/s of roof
sheets sheets
37 42 47 52 57
OLYMPIC DESIGNS
FRL -/60/30 fire exit FRL -/60/30 fire exit FRL -/60/30 fire exit FRL -/60/30 fire exit
*************************************************
150 150
605 3370 1900
705 3370 3370 705
150
150 1250 1375 1995 1995 1375 1250
5375 5375 1250 1375 1995 150
150
250 3825 3825 250
150 250
250 W 5125 5125
W 250 250
3660
65 150
1650
600
200
200
100
25 18
600
180
180
600
100
1250
1250
1250
1250
1250
1250
1250
1250
1250
W W UP UP UP
1500
1500
285
100
100
24 19
100
2475
2475
1200
1200
1200
4
W
3
WC D D WC WC D
2 1
100
30 28 27 6
3025
3025
3025
3025
3025
100
100
UP D D
UP W
1300
1300
D D
100
7
34 33
35 32
100
100
100
100
900
900
900
WC WC
10835
10835
11420
11420
11420
11420
11420
11685
11685
2000
2000
W W
8735
8735
1800
1800
1800
10130
9560
17 12 11
100
100
8630
8630
8630
6055
6055
OFFICE OFFICE OFFICE OFFICE OFFICE
6905
6905
6905
RL 24.67 RL 24.67 RL 24.67 RL 24.67 RL 24.67
3355
3355
3355
4760
4760
W
8
150
150
150
150
W W W W W W W W W W
23 22 21 20 16 15 14 13 10 9
900
900
900
900
RS RS RS RS RS
100
5 4 3 2 1
100
285
100
285
100
100
285
285
100
285
100
285
100
100
150
OLYMPIC DESIGNS
5375 5375 150
4075 4075 6025
*************************************************
285
285
285
285
285
285
100
100
100
100
100
100
100
100
RS RS RS RS RS
100
900
900
900
900
6 W W W W 7 8 W W W W 9 10 W W
31 32 35 36 39 40 42 43 45 46
150
150
150
150
W
47
4760
4760
3355
3355
3355
Amendments Date
RL 24.67 RL 24.67 RL 24.67 RL 24.67 RL 24.67
6905
6905
6905
OFFICE OFFICE OFFICE OFFICE OFFICE
6055
6055
8630
8630
8630
100
100
10130
9560
W W W
1800
1800
1800
8735
8735
41 44 50
11685
11685
11420
11420
11420
11420
11420
2000
2000
10835
10835
900
900
900
100
100
100
WC WC W
100
D D 48
100
D D
1300
1300
61 64
62 63
UP UP
100
100
3025
3025
3025
3025
3025
10
W
7 8
D D
9 D
100
6
1200
1200
1200
WC WC WC 49
2475
2475
65 67 69
100
W W
100
100
1500
1500
285
1250
1250
1250
1250
1250
1250
1250
1250
33 37
UP UP UP
1250
1250
D D D
600
600
100
180
180
66 68 70
200
200
W W
100
600 1500 775 775 1500
600
3660 1650
250 34 5125
150
5125 38 250 250 65 150 250
100 150
100 150 100
1250 2000 3120
100 100 100
WORKSHOP 2875 2500
150
2500 WORKSHOP
2875 WORKSHOP 1250
100
2000
100
1170
150
1170
100
2000
100 WORKSHOP
1250
WORKSHOP
5375 5375 1250 1375 1995 150
150 1250 1375 1995 1995 1375 1250
150
OLYMPIC DESIGNS
*************************************************
150
4620 1275
Amendments Date
90
1250 1370 1910
1425 3195
dashed
90
1250
350 typ TEA
1425
600 625
100
tiles
2120
350 typ
C C
300
D
2
shelf
90
CL
tiles over
3575
1490
D
fw
3
4905
4830
90
D
4
M/DIS
2450
1200
UP tiles W
1
1505
fw
300
750
C
150
150
150
WORKSHOP
3850
3950
precast conc.
1 wheel stops
as specified
300 225
D OLYMPIC DESIGNS
150
600
C *************************************************
RS DP
600
1
B
55 Olympic Parade Ph: 1234 5678
650
Homebush NSW 2140 Fax: 1234 5679
B steel bollard
as specified
PROPOSED FACTORY UNITS
5500
150
& OFFICE SPACE
for
Tasmegs Development Pty Ltd
7 Layland Way
Banksia
Amendments Date
150
4620 4620
90 90 150 90 90
1250 1280 1910 1910 1280 1250
C C
150
1425 3195 3195 1425
first floor over
dashed
90
90
1250
1250
TEA TEA
1425
1425
350 typ
tiles tiles
2120
2120
350 typ
C C
D D
13 treads @ 275mm
14 9
14 risers @ 175mm stairs
90
similar
CL CL
90
shelf to Unit
tiles tiles
3575
3575
1490
1490
over
D 3
fw fw D
13
8
4905
4905
90
90
D D
12 7
M/DIS M/DIS
2450
2450
UP tiles tiles UP
1505
1505
fw fw
150
150
W W
3 2
WORKSHOP WORKSHOP
4050
4050
3 precast conc.
2 OLYMPIC DESIGNS
wheel stops *************************************************
as specified
55 Olympic Parade Ph: 1234 5678
Homebush NSW 2140 Fax: 1234 5679
150
150
D D
11 6
RS RS
600
600
B B
3
DP
2
PROPOSED FACTORY UNITS
B DP B
& OFFICE SPACE
steel bollard for
150 2125 1200 1350 1200 2125 150
as specified Tasmegs Development Pty Ltd
7 Layland Way
Banksia
150
5375 5375
150
2875 2500 2500 2875
90 90 90 90 90 90
150
1060 1595 2450 2450 1595 1060
175 C C C C
150 175 Amendments Date
2525 2675 2675 2525
175
200
350 typ
175
C C
1250
1250
WORKSHOP WORKSHOP
5 4
3175
3175
2475
2475
rc columns to
1200
1200
eng. details
6835
6835
C C
UP UP
1310
1310
D
D 10 risers @ 175mm D D
D
23
22
9 treads @ 275mm 20 19
18
90
3485
3485
CL D
CL
90
tiles
M/DIS 21 M/DIS tiles
TEA tiles tiles TEA shelf
1910
1910
fw tiles fw fw tiles fw
over
150
150
W W
1650
5 4
4050
4050
precast conc.
wheel stops
2100
as specified
D D
24 steel bollard 17
150
150
900 as specified RS
600
600
B B
OLYMPIC DESIGNS
RS 4
5
DP
*************************************************
B B
150
150 150
3425 1200 600 600 1200 3425
B B
DP
RS
600
600
RS
6 B B
900
steel bollard 7
150
150
Amendments Date
D as specified D
36 41
2100
precast conc.
wheel stops
as specified
4050
4050
1650
150
W W
26 27
150
1910
1910
over
fw tiles fw fw tiles fw
TEA tiles tiles TEA shelf
tiles tiles
M/DIS M/DIS
3485
3485
D
90
CL 40 CL
90
D D 9 treads @ 275mm D D
D
43
1310
1310
38 39
10 risers @ 175mm 45 44
UP UP
6835
6835
C C
rc columns to
1200
1200
2475
2475
eng. details
3175
3175
WORKSHOP WORKSHOP
6
7
1250
1250
350 typ
C C
175
200
175
first floor over
dashed 350 typ
2875 2500
150
2500 2875
55 Olympic Parade Ph: 1234 5678
steel bollard
150 2125 1200 1350 1200 2125 150
as specified
B DP B
DP Amendments Date
600
600
RS RS
B B
8 9
D D
150
150
46 51
precast conc.
WORKSHOP wheel stops WORKSHOP
4050
4050
as specified
8 9
150
W W
28 29
150
1505
1505
fw fw
2450
2450
UP tiles tiles UP
90
4905
4905
90
D
D 54
3575
3575
1490
1490
fw fw
49
over
tiles tiles stairs
shelf
90
CL CL similar
90
to Unit
D D
3
350 typ
50 55
C C
2120
2120
1425
1425
tiles tiles
1250
1250
TEA TEA 350 typ
90
90
first floor over
dashed
1425 3195 3195 1425
C 150 C
4620
150
4620
55 Olympic Parade Ph: 1234 5678
Homebush NSW 2140 Fax: 1234 5679
150
10800
Amendments Date
steel bollard
B as specified
650
600
RS
B DP
600
10 C
150
56
300 225
precast conc.
wheel stops
3950
3850 as specified
WORKSHOP
150 10
150
150
750
300
1505
fw
1200
2450
W
UP tiles 30
D M/DIS
58
90
4830
4905
D
3575
1490
fw
59
tiles over
90
CL shelf
D
300
60
350 typ
C
C
2120
tiles
100
1425
1250
600 625
TEA
350 typ
90
1425 3195
55 Olympic Parade Ph: 1234 5678
Homebush NSW 2140 Fax: 1234 5679
1250 1370 1910
90
4620 1275
PROPOSED FACTORY UNITS
150
& OFFICE SPACE
for
Tasmegs Development Pty Ltd
7 Layland Way
Banksia
150
605 3370 1900
Amendments Date
100 100 100
1250 2000 3120
100
100 5825
C C
15 1617 18 19 20
1250
1250
1250
UP
285
D
14
26
13
100
C
12 W
1200
D
11 FWC 6
27
10 tiles
fw
9
3025
3025
8
100
7
6
5
stairs similar
4
3
to Unit 6
W
2 7
100
900
1
11420
OFFICE
W
1800
10130
9560
11
carpet
8630
6055
6905
3355
OLYMPIC DESIGNS
RS *************************************************
150
1 W
8 55 Olympic Parade Ph: 1234 5678
DP W
W
Homebush NSW 2140 Fax: 1234 5679
900
10
C 9 C
100
285
& OFFICE SPACE
for
Hi-light sunscreen in
steel frame over
to detail
6025 Tasmegs Development Pty Ltd
7 Layland Way
Banksia
150
705 3370 3370 705
150
1250 1375 1995 1995 1375 1250
150
250 3825 3825 250
C C
C C
15 1617 18 19 20 20 19 18 171615
1250
1250
1250
1250
1250
UP UP
100
100
D D
14 31 29 14
13 13
stairs
13 treads @ 275mm
similar
14 risers @ 175mm
12 12
1200
1200
D D
100 11 FWC 30 28
FWC 11 to Unit 6
10
fw tiles tiles fw
10
9 9
3025
3025
3025
8 8
100
7 7
6 6
5 5
acoustic
100
4 4
3 fibreglass 3
100
2 insulation 2
900
900
1 1
11420
11420
OFFICE OFFICE
W
1800
1800
W
12
17
3 2
8630
8630
carpet carpet
6055
6905
6905
3355
3355
RS RS OLYMPIC DESIGNS
3 2
150
*************************************************
16 W 13
C 15 DP 14 C Homebush NSW 2140 Fax: 1234 5679
100
100
100
285
285
100
Hi-light sunscreen in
& OFFICE SPACE
steel frame over
150 for
to detail 4075 4075