Sand blasting & primer per day = 60 Sq.

M/day

Fabrication/beveling/marking,cutting per day= 5 plates/15 labor 50 Sq.meter approxy

Bottom & Roof plates fabrication= 80 sq.M/15 labor

Erection of shell plates= 5 plates /day

Erection of roof & bottom plates= 10 plates/day


50 Sq.meter approxy
Task Discription Plan Start Plan End Plan Days

(a) Award of contract


(b) Issuence of IFC drawings
(c) Mobilization activities
(d) Formation of fab-shop and sand blasting yard
1 Mechanical Works
1.1 Marking of PMG Tank-1

Marking 1/5/2017 10/5/2017 10


1.2 Cutting & grinding of PMG Tank-1

Cutting & grinding of PMG Tank-1 1/5/2017 10/5/2017 10


1.3 Rollingof PMG Tank-1

Rollingof PMG Tank-1 3/5/2017 11/5/2017 8


1.4 Shell pair making & stiffner of PMG Tank-1

Shell pair making & stiffner of PMG Tank-1 4/5/2017 16-5-2017 12


1.5 Saddle plate Fitup & Welding of PMG Tank-1

Saddle plate Fitup & Welding of PMG Tank-1 5/5/2017 6/5/2017 2


1.6 Laying & fitup of PMG Tank-1

Laying & fitup of PMG Tank-1 6/5/2017 18-5-2017 12


1.7 Angle Bracing of PMG Tank-1

Angle Bracing of PMG Tank-1 16-5-2017 18-5-2017 3


1.8 Welding of PMG Tank-1

Welding of PMG Tank-1 19-5-2017 24-5-2017 6


1.9 End cap installation of PMG Tank-1

End cap installation of PMG Tank-1 5/22/2017 5/23/2017 2

1.10
Saddle Channel fitup & welding 5/25/2017 5/26/2017 2
Saddle Channel fitup & welding
1.11 Nozzels & manhole marking/Cutting/Grinding of PMG Tank-1

Nozzels & manhole marking/Cutting/Grinding of PMG Tank-1 27-5-2017 28-5-2017 2


1.12 Nozzels & manhole Installation of PMG Tank-1

Nozzels & manhole Installation of PMG Tank-1 29-5-2017 30-5-2017 2


1.13 Fixture Removal / Grinding & Built up
Fixture Removal / Grinding & Built up 29-5-2017 1/6/2017 3
1.14 Saddle/ Cantilever Welding of PMG Tank-1

Saddle/ Cantilever Welding 29-5-2017 30-5-2017 2


1.15 Testing
Pnumetic Testing 2/6/2017 2/6/2017 1
Hydrotesting 3/6/2017 5/6/2017 3
Sand blasting 6/6/2017 6/8/2017 2
Painting 6/9/2017 6/12/2017 4
Diesel Cleaning 6/13/2017 6/14/2017 2

2 Mechanical work
2.1 Marking of PMG Tank-2

Marking 11/5/2017 20/5/2017 10


2.2 Cutting & grinding of PMG Tank-2

Cutting & grinding of PMG Tank-2 11/5/2017 5/20/2017 10


2.3 Rollingof PMG Tank-2

Rollingof PMG Tank-2 05-14-2017 5/21/2017 8


2.4 Shell pair making & stiffner of PMG Tank-2

Shell pair making & stiffner of PMG Tank-2 5/15/2017 5/26/2017 12


2.5 Saddle plate Fitup & Welding of PMG Tank-2

Saddle plate Fitup & Welding of PMG Tank-2 5/15/2017 16/5/2017 2


2.6 Laying & fitup of PMG Tank-2

Laying & fitup of PMG Tank-2 5/17/2017 5/29/2017 12


2.7 Angle Bracing of PMG Tank-2

Angle Bracing of PMG Tank-2 19-5-2017 24-5-2017 5


2.8 Welding of PMG Tank-2

Welding of PMG Tank-2 5/30/2017 6/5/2017 6


2.9 End cap installation of PMG Tank-2

End cap installation of PMG Tank-2 6/3/2017 6/4/2017 2

2.10
Saddle Channel fitup & welding 6/5/2017 6/6/2017 2
Saddle Channel fitup & welding
2.11 Nozzels & manhole marking/Cutting/Grinding of PMG Tank-2
Nozzels & manhole marking/Cutting/Grinding of PMG Tank-2 6/5/2017 6/6/2017 2
2.12 Nozzels & manhole Installation of PMG Tank-2

Nozzels & manhole Installation of PMG Tank-2 6/6/2017 7/6/2017 2


2.13 Fixture Removal / Grinding & Built up

Fixture Removal / Grinding & Built up 6/6/2017 8/6/2017 3


2.14 Saddle/ Cantilever Welding of PMG Tank-2

Saddle/ Cantilever Welding 4/6/2017 5/6/2017 2


2.15 Testing
Pnumetic Testing 9/6/2017 9/6/2017 1
Hydrotesting 10/6/2017 12/6/2017 3
Sand blasting 6/12/2017 6/14/2017 2
Painting 6/15/2017 6/18/2017 4
Diesel Cleaning 6/19/2017 6/20/2017 2
3 Mechanical work
3.1 Marking of PMG Tank-3

Marking 05-21-2017 5/30/2017 10


3.2 Cutting & grinding of PMG Tank-3

Cutting & grinding of PMG Tank-3 05-21-2017 5/30/2017 10


3.3 Rollingof PMG Tank-3

Rollingof PMG Tank-3 05-22-2017 1/6/2017 8


3.4 Shell pair making & stiffner of PMG Tank-3

Shell pair making & stiffner of PMG Tank-3 5/18/2017 5/29/2017 12


3.5 Saddle plate Fitup & Welding of PMG Tank-3

Saddle plate Fitup & Welding of PMG Tank-3 5/17/2017 5/18/2017 2


3.6 Laying & fitup of PMG Tank-3

Laying & fitup of PMG Tank-3 5/20/2017 6/1/2017 12


3.7 Angle Bracing of PMG Tank-3

Angle Bracing of PMG Tank-3 5/25/2017 5/29/2017 5


3.8 Welding of PMG Tank-3

Welding of PMG Tank-3 6/2/2017 6/7/2017 6


3.9 End cap installation of PMG Tank-3

End cap installation of PMG Tank-3 6/4/2017 6/5/2017 2


3.10
Saddle Channel fitup & welding 6/5/2017 6/6/2017 2
Saddle Channel fitup & welding
3.11 Nozzels & manhole marking/Cutting/Grinding of PMG Tank-3

Nozzels & manhole marking/Cutting/Grinding of PMG Tank-3 6/7/2017 6/8/2017 2


3.12 Nozzels & manhole Installation of PMG Tank-3

Nozzels & manhole Installation of PMG Tank-3 6/9/2017 6/10/2017 2


3.13 Fixture Removal / Grinding & Built up

Fixture Removal / Grinding & Built up 6/11/2017 6/13/2017 3


3.14 Saddle/ Cantilever Welding of PMG Tank-3

Saddle/ Cantilever Welding 6/11/2017 6/12/2017 2


3.15 Testing
Pnumetic Testing 6/13/2017 6/13/2017 1
Hydrotesting 6/14/2017 6/16/2017 3
Sand blasting 6/17/2017 6/18/2017 2
Painting 6/19/2017 6/22/2017 4
Diesel Cleaning 6/23/2017 6/24/2017 2
4 Mechanical work
4.1 Marking of PMG Tank-4

Marking 6/1/2017 6/10/2017 10


4.2 Cutting & grinding of PMG Tank-4

Cutting & grinding of PMG Tank-4 6/1/2017 6/10/2017 10


4.3 Rollingof PMG Tank-4

Rollingof PMG Tank-4 6/3/2017 6/11/2017 8


4.4 Shell pair making & stiffner of PMG Tank-4

Shell pair making & stiffner of PMG Tank-4 6/4/2017 6/13/2017 12


4.5 Saddle plate Fitup & Welding of PMG Tank-4

Saddle plate Fitup & Welding of PMG Tank-3 6/6/2017 6/7/2017 2


4.6 Laying & fitup of PMG Tank-4

Laying & fitup of PMG Tank-4 6/6/2017 6/17/2017 12


4.7 Angle Bracing of PMG Tank-4

Angle Bracing of PMG Tank-4 6/18/2017 6/22/2017 5


4.8 Welding of PMG Tank-4

Welding of PMG Tank-4 6/12/2017 6/18/2017 6


4.9 End cap installation of PMG Tank-4
End cap installation of PMG Tank-4 6/16/2017 6/17/2017 2

4.10
Saddle Channel fitup & welding 6/18/2017 6/19/2017 2
Saddle Channel fitup & welding
4.11 Nozzels & manhole marking/Cutting/Grinding of PMG Tank-4

Nozzels & manhole marking/Cutting/Grinding of PMG Tank-4 6/20/2017 6/21/2017 2


4.12 Nozzels & manhole Installation of PMG Tank-4

Nozzels & manhole Installation of PMG Tank-4 6/22/2017 6/23/2017 2


4.13 Fixture Removal / Grinding & Built up

Fixture Removal / Grinding & Built up 6/23/2017 6/25/2017 3


4.14 Saddle/ Cantilever Welding of PMG Tank-4

Saddle/ Cantilever Welding 6/24/2017 6/25/2017 2


4.15 Testing
Pnumetic Testing 6/26/2017 6/26/2017 1
Hydrotesting 6/27/2017 6/29/2017 3
Sand blasting 6/30/2017 7/1/2017 2
Painting 7/2/2017 7/5/2017 4
Diesel Cleaning 7/6/2017 7/7/2017 2
5 Mechanical Work
5.1 Marking of PMG Tank-5

Marking 6/12/2017 6/21/2017 10


5.2 Cutting & grinding of PMG Tank-5

Cutting & grinding of PMG Tank-5 6/12/2017 6/21/2017 10


5.3 Rollingof PMG Tank-5

Rollingof PMG Tank-5 6/14/2017 6/22/2017 8


5.4 Shell pair making & stiffner of PMG Tank-5

Shell pair making & stiffner of PMG Tank-5 6/16/2017 6/26/2017 12


5.5 Saddle plate Fitup & Welding of PMG Tank-5

Saddle plate Fitup & Welding of PMG Tank-5 6/10/2017 6/11/2017 2


5.6 Laying & fitup of PMG Tank-5

Laying & fitup of PMG Tank-5 6/12/2017 6/23/2017 12


5.7 Angle Bracing of PMG Tank-5

Angle Bracing of PMG Tank-5 6/24/2017 6/28/2017 5


5.8 Welding of PMG Tank-5

Welding of PMG Tank-5 6/29/2017 7/4/2017 6


5.9 End cap installation of PMG Tank-5

End cap installation of PMG Tank-5 7/5/2017 7/6/2017 2

5.10
Saddle Channel fitup & welding 7/7/2017 7/8/2017 2
Saddle Channel fitup & welding
5.11 Nozzels & manhole marking/Cutting/Grinding of PMG Tank-5

Nozzels & manhole marking/Cutting/Grinding of PMG Tank-5 7/9/2017 7/10/2017 2


5.12 Nozzels & manhole Installation of PMG Tank-5

Nozzels & manhole Installation of PMG Tank-5 7/11/2017 7/12/2017 2


5.13 Fixture Removal / Grinding & Built up

Fixture Removal / Grinding & Built up 7/13/2017 7/15/2017 3


5.14 Saddle/ Cantilever Welding of PMG Tank-5

Saddle/ Cantilever Welding 13-72017 7/14/2017 2


5.15 Testing
Pnumetic Testing 7/15/2017 7/16/2017 1
Hydrotesting 7/17/2017 7/19/2017 3
Sand blasting 7/20/2017 7/21/2017 2
Painting 7/22/2017 7/25/2017 4
Diesel Cleaning 7/26/2017 7/27/2017 2
6 Mechanical Work
6.1 Marking of PMG Tank-6

Marking 6/23/2017 7/3/2017 10


6.2 Cutting & grinding of PMG Tank-6

Cutting & grinding of PMG Tank-6 6/23/2017 7/3/2017 10


6.3 Rollingof PMG Tank-6

Rollingof PMG Tank-6 6/26/2017 7/4/2017 8


6.4 Shell pair making & stiffner of PMG Tank-6

Shell pair making & stiffner of PMG Tank-6 6/27/2017 7/8/2017 12


6.5 Saddle plate Fitup & Welding of PMG Tank-6

Saddle plate Fitup & Welding of PMG Tank-6 6/24/2017 6/25/2017 2


6.6 Laying & fitup of PMG Tank-6
Laying & fitup of PMG Tank-6 7/5/2017 7/16/2017 12
6.7 Angle Bracing of PMG Tank-6

Angle Bracing of PMG Tank-6 7/17/2017 7/21/2017 5


6.8 Welding of PMG Tank-6

Welding of PMG Tank-6 7/22/2017 7/27/2017 6


6.9 End cap installation of PMG Tank-6

End cap installation of PMG Tank-6 7/25/2017 7/26/2017 2

6.10
Saddle Channel fitup & welding 7/27/2017 7/28/2017 2
Saddle Channel fitup & welding
6.11 Nozzels & manhole marking/Cutting/Grinding of PMG Tank-6

Nozzels & manhole marking/Cutting/Grinding of PMG Tank-6 7/29/2017 7/30/2017 2


6.12 Nozzels & manhole Installation of PMG Tank-6

Nozzels & manhole Installation of PMG Tank-6 7/31/2017 8/1/2017 2


6.13 Fixture Removal / Grinding & Built up

Fixture Removal / Grinding & Built up 8/1/2017 8/3/2017 3


6.14 Saddle/ Cantilever Welding of PMG Tank-6

Saddle/ Cantilever Welding 8/2/2017 8/3/2017 2


6.15 Testing
Pnumetic Testing 8/4/2017 8/4/2017 1
Hydrotesting 8/5/2017 8/7/2017 3
Sand blasting 8/8/2017 8/9/2017 2
Painting 8/10/2017 8/13/2017 4
Diesel Cleaning 8/14/2017 8/15/2017 2

7 PMG Tank Piping Installation


7.1 Piping Installation of PMG Tank 1,2,3,4,5,6 8/16/2017 8/21/2017 6