PROJECT CONCEPT
I. IDENTIFYING INFORMATION:
A. PROJECT TITLE: PROPOSED COVERED GYM
B. PROJECT SITE/LOCATION: CALABACLABACAN ELEMENTARY SCHOOL
TRINIDAD, GUIHULNGAN CITY, NEG. OR.
C. PROJECT PROPONENT: JUDITHA B.PAUNILLAN
D. CONTACT PERSON: JUDITHA B. PAUNILLAN
E.TOTAL PROJECT COST: Php.1,599,270.99
F.PROJECT COUNTERPART: LABOR
G. AMOUNT REQUESTED: Php.1,600,000.00
H.PROJECT DURATION: 5 YEARS
B. SPECIFIC OBJECTIVES:
1. To solicit alumni from this school for any donation for the realization of
this project.
2. To construct the proposed covered gym by phase depending on the
amount donated by alumni.
IV. STRATEGIES FOR IMPLEMENTATION:
PHASE I
1. Gather list of successful alumni and send them solicitation letter asking
for their donation for the construction of covered gym.
2. Allocate budget from MOOE for repair of school facilities and purchase
materials every release of the said fund.
3. Purchase materials based on the amount received from alumni’s
donations.
4. Send letter to the LGU for any support that can be offered for the
realization of this proposed project.
PHASE II
1. Start the construction of the foundation layout after a year of gathering
resources for this project.
2. Continue the activities in PHASE I as the construction of the project is
still going on until its full completion.
PERSONS
OBJECTIVES ACTIVITIES
INVOLVED
PERSONS
OBJECTIVES ACTIVITIES
INVOLVED