Prepared by:
• Roberto Ambriz Cisneros
• Daniel Hernandez Bonel
• Nikolai Biriukov
• Steave Arthur Meguebtchie Tchouamo
Last Revised On: 21/7/2019
CONTENTS
1
SCHEDULE MANAGEMENT PLAN
MANAGEMENT APPROACH
The purpose of this schedule management plan is to establish the criteria and the activities for developing,
monitoring and controlling the project schedule regarding the Christmas Party for OBS Business School employees.
When this plan is approved, no schedule changes will be permitted unless a request for change is processed in
accordance with the procedures set forth in the change management plan.
The project manager will assume overall responsibility for schedule management. The people listed below will
assume the following schedule management responsibilities:
SCHEDULING METHOD
For this event we will be using CPM as the method to calculate minimum project duration and determine the
flexibility on the path of the activities.
SCHEDULING TOOL
The tool for this Schedule will be MS Excel.
Availability:
• Read Only
o Managers
o All team members
• Modification
o Scheduler
2
SCHEDULE PROCESSES
DEFINE ACTIVITIES
ACTIVITY LIST
MILESTONE LIST
SEQUENCE ACTIVITIES
Project manager will be in charge of sequencing activities and relating them on this Event planning
SCHEDULE CONSTRAINTS
ACTIVITY ATTRIBUTES
Units of Measurement
The estimated resource requirements for each activity are set forth below in Attachment D/E., Activity Attributes.
Resource Requirements
3
ESTIMATE ACTIVITY DURATIONS
DEVELOP SCHEDULE
For this Event Project Manager will be in charge of developing schedule baseline, it will be approved by General
Manager.
CONTROL SCHEDULE
SCHEDULE BASELINE
The schedule baseline is included below as Attachment E. After this version of the schedule is approved, the
schedule can only be changed through the formal change control procedures set forth in the change management
plan. The schedule baseline will be used throughout the project as a basis for comparison to actual results.
ASSUMPTIONS
While planning and managing the project schedule, it’s possible that assumptions will be made. All assumptions
regarding the project schedule are documented here then transferred to the Risk Management Plan for further
management.
4
PLAN APPROVAL
Name:
Title:
________________________________________ ______________________________
Signature Date Approved
5
ATTACHMENTS
A. ACTIVITY LIST
Number
1.1 Plan development Develop Time and cost Plan for Event Project Manager
1.3 Plan Approval General Manager Receive Plan for approval General Manager
2 Restaurant
2.3 Selection of provider Select best option in price and location Purchasing 2
2.5 Catering Service Selection Review Meal options for dinner and select Human Resources 1
3 Transportation
3.3 Selection of provider Select best option in price and location Purchasing 2
4 Music/Entertainment
4.3 Selection of provider Select best option in price and location Purchasing 2
6
5 Decoration
5.1 Theme Selection Review options on theme for the party Marketing
5.2 Material Purchase Get BOM for theme and purchase Purchasing 2
5.3 Decoration on site Assign 5 operations members for Operations Ctrl by Marketing
Decorations Task
6 Gifts
6.2 Material Purchase Get BOM for theme and purchase Purchasing 3
6.3 Gift Assemble Assign 5 operations members for Assemble Operations Ctrl by Marketing
Gift
B. MILESTONE LIST
C. ACTIVITY ATTRIBUTES
1 Plan
2 Local/Restaurant
7
4 2.1 Survey Human Resources 1 1
3 Transportation
4 Music/Entertainment
5 Decoration
6 Gifts
1.2
8
1.1 1.3 FS
1.2 FS
9
D. ACTIVITY DURATION ESTIMATES
10
4.2 Receive Quotation 1 1 1
4.3 Selection of provider 1 1 1
4.4 Contract 1 1 1
5 Decoration
5.1 Theme Selection 5 1 5
5.2 Material Purchase 1 4 4
5.3 Decoration on site 5 4 20
6 Gifts
6.1 Gift Definition 5 1 5
6.2 Material Purchase 1 3 3
6.3 Gift Assemble 5 4 20
E. SCHEDULE BASELINE
11