One DepEd. One PAMPANGA.

DEPARTMENT OF EDUCATION
DMEPA
MEPA
ISSUES AND RESOLUTIONS BY
CATEGORY
MEPA STATUS OF FD's PROGRAMS
& PROJECTS
*PHYSICAL ACCOMPLISHMENTS
LESSONS LEARNED
STATUS OF PROGRAMS
AND PROJECTS’ BALANCE
FOR THE QUARTER EDUCATION RESOURCE
SUPPORT
VALUE-ADDED CONTRIBUTIONS
FOR THE QUARTER UTILIZATION OF SDO MOOE & GAA FUNDS
for SPECIAL PROGRAMS
& PROJECTS

DEPARTMENT OF EDUCATION
VALUE-ADDED

MEPA
STATUS OF FD's
LESSONS LEARNED
PROGRAMS & PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
FOR THE QUARTER RESOLUTIONS SUPPORT

Monitoring, Evaluation, & • Provides the division


Plan Adjustment (MEPA) management:
 is both a strategy and a  information on the
implementation of the
mechanism, is participative
programs and projects which
and collaborative, and serve as basis for plan adjustment
involves the collection,
 information on the
validation, analysis, and organizational health and
reporting of appropriate, performance which serve as
relevant, and accurate basis in determining appropriate
information necessary for the strategies and interventions to
adjustment of work plans and improve organizational
strategies. effectiveness & resource support
DEPARTMENT OF EDUCATION
MEPA

In line with the MEPA system institutionalization


in the department, the periodic (quarterly) monitoring
and evaluation of the progress of the division using
the MEPA Technology is necessary to continuously
improve the delivery of education services to
achieve desired results and sustainability of education
outcomes, and to enhance organizational
performance for effective and efficient fulfillment of
the division mandate.

DEPARTMENT OF EDUCATION
• Individual,
Organizational
team, &
Effectiveness organizational
effectiveness

DEPARTMENT OF EDUCATION 7
• Availability
Organizational
Resource and adequacy
Support of resource
requirements

DEPARTMENT OF EDUCATION 8
Physical Accomplishments

Pre- DMEPA Post


DMEPA Proper DMEPA

DEPARTMENT OF EDUCATION
Pre-DMEPA DMEPA Proper Post DMEPA

• Data collection • Validation of • Adjustment of


• Consolidation of quantitative & Plans
FD’s qualitative • Report writing
accomplishments information
• Reporting of gathered by the
Balances, Reasons IMET
for Variance • Reporting
• Value -Added
Contributions
• Lessons Learned

DEPARTMENT OF EDUCATION
STATUS OF FD's PROGRAMS & VALUE-ADDED
LESSONS LEARNED
PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
RESOLUTIONS SUPPORT
FOR THE QUARTER

ORGANIZATIONAL
EFFECTIVENESS
STATUS OF FD's PROGRAMS & VALUE-ADDED
LESSONS LEARNED
PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
FOR THE QUARTER RESOLUTIONS SUPPORT

STATUS OF FD's
PROGRAMS & PROJECTS
*PHYSICAL
ACCOMPLISHMENTS
Physical Accomplishments

Regulatory
Service & Developmental
Curriculum
Delivery Services to
Private Schools

DEPARTMENT OF EDUCATION
STATUS OF FD's VALUE-ADDED
LESSONS LEARNED
PROGRAMS & PROJECTS CONTRIBUTIONS
MEPA STATUS OF PROGRAMS
AND PROJECTS’ BALANCE
ISSUES AND EDUCATION RESOURCE
UTILIZATION OF SDO
MOOE & GAA FUNDS Physical Accomplishments
FOR THE QUARTER RESOLUTIONS SUPPORT

Curriculum

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Education Policy
Development Program
Objective: Ensured the full implementation of the
articulated basic education curriculum including its
contextualization , indigenization, integration and
innovation by leading in the validation and
production of at least 16 learning materials in the
different learning areas/curricular/special programs
in Grades 3 and 4 and in anchoring instruction on
learners' creativity at the end of FY

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Creation of localized, indigenized,


contextualized materials in Grades 3 & 4 (16)

DEPARTMENT OF EDUCATION 16
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
16

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Education Policy
Development Program

Objective: Managed the monitoring


and evaluation of division learning
outcomes, SHS learners' higher
education and employability
readiness of 84 Senior High Schools

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Validation of 83 4th Quarter


Periodic Tests across 8 learning
areas

DEPARTMENT OF EDUCATION 19
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
254 83 83 83 83 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Monitoring of Quarterly Examination


Results

DEPARTMENT OF EDUCATION 21
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
4 2 2 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Validation of Least Mastered Skills


and Test Item Analysis in 83
subjects of EPSs

DEPARTMENT OF EDUCATION 23
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
249 83 83 83 83 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Validation of low performing


schools within the district / cluster
for appropriate actions /
interventions

DEPARTMENT OF EDUCATION 25
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
120 120 120 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Collation of competencies difficult to


teach in elementary and secondary
across 8 learning areas for
appropriate actions

DEPARTMENT OF EDUCATION 27
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
83 83 83 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Development of interventions by
subject-focused for EPSs

DEPARTMENT OF EDUCATION 29
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
80 8 8 11 10 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Development of interventions by
subject-focused for PSDSs

DEPARTMENT OF EDUCATION 31
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
99 33 57 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:


Tracer Study:
NC Holder (3783)
Work (3369)
College (13 876)
Entrepreneurship (70)
School Leavers (140)
Graduates (17 454)

DEPARTMENT OF EDUCATION 33
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Education Policy
Development Program
Objective: Approved educational research
(applied and action) that are anchored to the
Reformulated Regional Research Agenda V
2 to improve teacher quality, instruction,
school management and leadership of 438
public elementary schools, 117 junior high
schools, and 87 senior high schools

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:


• Conduct of action /applied research

DEPARTMENT OF EDUCATION 36
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
5 1 1 4 2 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Validation / approval of action /


applied researches on curriculum

DEPARTMENT OF EDUCATION 38
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 29 25 29 25 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Evaluation of educational
researchers (applied and action)
submitted to the division office to
improve learning outcomes
DEPARTMENT OF EDUCATION 40
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 33 33 180 84 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:


• Submission of Research Proposals
for BERF

DEPARTMENT OF EDUCATION 42
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
20 5 5 5 5 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:


• Evaluation of Innovations

DEPARTMENT OF EDUCATION 44
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 4 4 5 6 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Education Policy
Development Program
Objective: Approved the coordination and
integration of the provision of Technical Assistance
to facilitate the improvement of teacher quality,
instruction, school management and leadership
and the development of better schools to 438 public
elementary schools, 117 junior high schools, and 87
senior high schools at the end of the FY

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Technical Assistance on
Instructional Supervision /
Curriculum Implementation / SIP /
AIP / resource generation for EPSs

DEPARTMENT OF EDUCATION 47
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
900 200 200 261 422 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Technical Assistance on
Instructional Supervision /
Curriculum Implementation / SIP /
AIP / resource generation for
PSDSs
DEPARTMENT OF EDUCATION 49
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
2,970 660 660 833 864 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Crafting of training proposals and


oversee the implementation

DEPARTMENT OF EDUCATION 51
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
22 2 13 2 13 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Monitoring of special programs (SSES /


SSC, SPFL, SPS, DAP-ELLN, SPED,
Multigrade, ALIVE / Madrasah,
IPED,KCEP, SPJ, OHS, Phil-IRI, YDS,
Best-Math, Gulayan sa Paaralan) for
EPSs
DEPARTMENT OF EDUCATION 53
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
132 33 33 60 194 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Monitoring of special programs (SSES / SSC,


SPFL, SPS, DAP-ELLN, SPED, Multigrade,
ALIVE / Madrasah, IPED, KCEP, SPJ,
OHS,YDS,Best-Math) for PSDSs, Brigada
Eskwela, Phil-IRI, YDS,Best-Math, Gulayan sa
Paaralan) for PSDSs

DEPARTMENT OF EDUCATION 55
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1089 363 867 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Technical Assistance on 10 Special Co-


Curricular Competitions within the fiscal year
with at least 20 winnings in regional / national
competitions

DEPARTMENT OF EDUCATION 57
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
10 4 1 4 1 100% 100%

20 9 16 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Coordination of service requests for technical


support of DCP equipment to warranty
providers

DEPARTMENT OF EDUCATION 59
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 2 2 2 2 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Processing of requests for DepEd Email


Accounts

DEPARTMENT OF EDUCATION 61
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 352 352 #DIV/0! 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Provision of technical assistance to Division


Office and schools in the different ICT
programs and projects

DEPARTMENT OF EDUCATION 63
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 22 22 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Preparation of Memorandum of Agreement


(MOA) between Donor and Donee as
requested

DEPARTMENT OF EDUCATION 65
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Assistance in the conduct of Nutritional


Assessment

DEPARTMENT OF EDUCATION 67
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 1 1 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Assistance in the conduct of School-Based


Deworming Program

DEPARTMENT OF EDUCATION 69
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Assistance in the conduct of School-based


Immunization (SBI) Program

DEPARTMENT OF EDUCATION 71
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Education Policy
Development Program

Objective: Ensured the integration of


the themes of the creative school
framework across all learning areas

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:


• 1. Creation of Creative/Innovative Programs of EPSs
1.1 Project TEKNO
1.2 Project CITIZEN
1.3 Project MATH/BEST Math School Program
1.4 Project E-Makabasa
1.5 Balanced Reading Program for English & Filipino
1.6. Putting up of SPJ for Secondary
1.7 Investigatory Projects in Science & Lesson Exemplars
1.8 E-Summer Youth Camp for Select Junior & Senior HS
students
1.9 3 ACTS of Goodness/Tindahan ng Katapatan (EsP)
2.0 Project (-TEACH
2.1 EPP Model School /TLE Model Schools
TLE Teachers' Qulalifications (NC II)/Integration of Organic Farming
Practices in Agriculture
2.2 Takbo Para sa Libro (LRMS)
DEPARTMENT OF EDUCATION 74
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
12 3 6 3 6 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Integration of creative schools framework in all


elementary & secondary schools

DEPARTMENT OF EDUCATION 76
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
557 557 557 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Attendance to convergence / advocacy


programs for strategies, alternative delivery
models, etc.

DEPARTMENT OF EDUCATION 78
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
8 7 7 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Organized Convergence with TEIs to produce


better teachers

DEPARTMENT OF EDUCATION 80
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
STATUS OF FD's VALUE-ADDED
LESSONS LEARNED
PROGRAMS & PROJECTS CONTRIBUTIONS
MEPA STATUS OF PROGRAMS
AND PROJECTS’ BALANCE
ISSUES AND EDUCATION RESOURCE
UTILIZATION OF SDO
MOOE & GAA FUNDS Physical Accomplishments
FOR THE QUARTER RESOLUTIONS SUPPORT

Service
Delivery

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support

Objective: Facilitated the budget preparation to


support the implementation of the K to 12
curriculum and operations of the division office by
obtaining the 100% level of approval for
endorsement to Department of Budget and
Management (DBM)

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Submission of FARS and BEDS online thru the


http://urs.dbm.gov.ph

DEPARTMENT OF EDUCATION 84
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 4 4 4 4 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:


• Consolidation of Budget Proposal for the
ensuing year

DEPARTMENT OF EDUCATION 86
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Preparation of Special Budget Request for


unfunded filled positions

DEPARTMENT OF EDUCATION 88
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 2 2 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Coordination with all Program takers the


budget allocation received from Regional &
Central office and the evaluation of their Work
& Financial Plan (as they come)

DEPARTMENT OF EDUCATION 90
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 6 11 6 11 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Stage 1:
Awareness & Foundation Course for ISO
9001:2015

DEPARTMENT OF EDUCATION 92
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 5 5 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support

Objective: Ensured the maintenance of the


effectiveness and continual improvement of the
SDO QMS by achieving the ISO Certification at
the end of the FY

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:


• Stage 1:
Awareness & Foundation Course for ISO
9001:2015

DEPARTMENT OF EDUCATION 95
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Stage 2: Documentation System for ISO


9001:2015

DEPARTMENT OF EDUCATION 97
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Stage 3: Risk Assessment for QMS & Practice


for Good Housekeeping

DEPARTMENT OF EDUCATION 99
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Stage 4: Internal Quality Audit

DEPARTMENT OF EDUCATION 101


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Stage 4: Internal Quality Audit

DEPARTMENT OF EDUCATION 103


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Stage 5: Final Audit for ISO Alignment

DEPARTMENT OF EDUCATION 105


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Stage 6: Surveillance Audit

DEPARTMENT OF EDUCATION 107


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Stage 7: Surveillance Audit with Harmonized


Internal Auditing with IQA Team

DEPARTMENT OF EDUCATION 109


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Stage 8: Surveillance Audit

DEPARTMENT OF EDUCATION 111


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
3

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Facilitation in the creation and validation of


PMs and WIMs

DEPARTMENT OF EDUCATION 113


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
219

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support

Objective: Evaluated and approved the


establishment of public schools learning centers
of the based on the R.A. 9155 at the end of the
FY

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Recommendation for the establishment of


public schools

DEPARTMENT OF EDUCATION 116


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 5 5 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support

Objective: Improved the relevance of the


implementation of policies by releasing four (4)
localized policies on the improvement of teacher
quality, instruction, school management
and leadership in the SDO at the end of the FY

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Criteria for OIC (Secondary Schools) /


Designation of OIC in schools

DEPARTMENT OF EDUCATION 119


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• New policy on receiving documents (Records


Unit)

DEPARTMENT OF EDUCATION 121


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Submission of liquidation directly to the


Accounting Unit

DEPARTMENT OF EDUCATION 123


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Directive on preparation of Financial Data


Entry System or FINDES (Cashier)

DEPARTMENT OF EDUCATION 125


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support

Objective: Ensured compliance with national


standards in recruitment, selection and training of
staff and performance evaluation of SDO
employees at the end of FY

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Evaluation and open-ranking of applicants for


hiring / promotion (Non-teaching, MTs, HTs,
related teaching)

DEPARTMENT OF EDUCATION 128


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 2 4 2 4 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Publication of Vacant Positions

DEPARTMENT OF EDUCATION 130


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 35 64 35 64 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of Initial Evaluation of Qualification of


Applicants for Division Personnel Selection
Board (PSB) Deliberation and Open Ranking

DEPARTMENT OF EDUCATION 132


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 6 4 6 4 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Processing of Appointments of Teaching and


Non-teaching Personnel:
● Original
● Promotion
● Transfer
● Re-appointment
● Re-employment.

DEPARTMENT OF EDUCATION 134


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 455 1209 455 1209 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Preparation of memoranda and advisory


pertaining to human resource actions

DEPARTMENT OF EDUCATION 136


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 11 31 11 31 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Personnel Action on Requests for ERF and


Reclassification

DEPARTMENT OF EDUCATION 138


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 207 207 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Updating of PSIPOP in the Government


Manpower Information System (GMIS): No. of
teachers included in the plantilla

DEPARTMENT OF EDUCATION 140


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 285 1137 285 38 100% 3%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Cleansing of all elementary schools' plantilla

DEPARTMENT OF EDUCATION 142


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
33 33 33 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Processing of monetary and non-monetary


benefits. (Salaries, PBB, PIB, PEI, Step
Increment, Phil health, etc.)

DEPARTMENT OF EDUCATION 144


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 1562 1562 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of Division Seminar on SBM:


Higlighting the Key Elements of Effective
Leadership & Governance

DEPARTMENT OF EDUCATION 146


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Issuance of permit to conduct need-based


trainings at the end of the calendar year

DEPARTMENT OF EDUCATION 148


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 54 67 54 67 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of one (1) leadership development


training for school heads within the calendar
year: Leadership and Management in the 21st
Century Series: The School Head as Effective
Communicator

DEPARTMENT OF EDUCATION 150


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Facilitation and conduct of Youth Leadership


Camp and Indoor Youth Leadership Training
for Teachers

DEPARTMENT OF EDUCATION 152


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
2 2 2 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• District and Cluster Adopt-a-School Program


Coordinators Conference

DEPARTMENT OF EDUCATION 154


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• District and Cluster Brigada Eskwela (BE)


Coordinators Conference

DEPARTMENT OF EDUCATION 156


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Provision of seminar / training on research

DEPARTMENT OF EDUCATION 158


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
2 1 1 1 1 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of Division Research Congress

DEPARTMENT OF EDUCATION 160


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of Induction Program for Non-


teaching personnel (SDO Proper & schools)

DEPARTMENT OF EDUCATION 162


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Seminar on CAV for Private Schools

DEPARTMENT OF EDUCATION 164


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support

Objective: Recommended for


approval the reclassification /
conversion / upgrading of items of
teachers and officials at the district
and division levels at the end of FY

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Processing of reclassification, conversion, &


upgrading of items

DEPARTMENT OF EDUCATION 167


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 93 84 93 84 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Preparation of appointments of personnel


whose items were converted, reclassed, &
updated

DEPARTMENT OF EDUCATION 169


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 53 53 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support
Objective: Managed education data needed in
planning by monitoring the updating of the learners'
profile in the EBEIS both for public and private
schools and by attaining 100% completion of the
learners' profile of the438 public elementary
schools, 117 junior high schools, and 87 senior high
schools at the beginning and end of the school year

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Completion of updated learner's profile of 438


public elementary, 117 public secondary
(JHS/SHS), 172 private schools and 2 SUCs
for End Of School Year (EOSY) 2017-2018
inventory in the LIS

DEPARTMENT OF EDUCATION 172


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
727 727 727 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support
Objective: Managed effective
allocation and utilization of
human, physical and financial
resources of the SDO within the
prescribed period

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Identification of competencies

DEPARTMENT OF EDUCATION 175


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of training needs assessment

DEPARTMENT OF EDUCATION 177


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Updating of 201 files

DEPARTMENT OF EDUCATION 179


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Agreement on percentage of performance


KRAs & designation

DEPARTMENT OF EDUCATION 181


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Deployment of employees

DEPARTMENT OF EDUCATION 183


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Monitoring of the construction of classroooms


under 2018 Basic Education Facilities Fund
(BEFF) for 40 schools

DEPARTMENT OF EDUCATION 185


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 6 6 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Evaluated the Repair of Classrooms for 66


schools under 2018 DepEd BEFF

DEPARTMENT OF EDUCATION 187


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 60 60 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Crafting & implementation of Div. ICT Plan

DEPARTMENT OF EDUCATION 189


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Crafting & implementation of Div. Physical


Facilities Plan

DEPARTMENT OF EDUCATION 191


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Crafting & implementation of Maintenance


Plan for Equipment, Furniture & Fixtures

DEPARTMENT OF EDUCATION 193


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Crafting & implementation of Maintenance


Plan for Service Vehicles

DEPARTMENT OF EDUCATION 195


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• 5S Implementation

DEPARTMENT OF EDUCATION 197


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Utilization of Notice of Cash Allocation (NCA)


received and payment of Obligated amount

DEPARTMENT OF EDUCATION 199


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 5 9 5 9 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Submission of Bank Reconciliation Statement


to Commission on Audit (COA) within 10 days
upon receipt of bank statement from the
Authorized Government Depository Bank
(AGDB)

DEPARTMENT OF EDUCATION 201


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 3 3 0 0 0% 0%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Consolidation and submission of Quarter,


Semi-Annual and Annual Financial Reports to
Deped Regional Office Proper

DEPARTMENT OF EDUCATION 203


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
6 1 2 1 2 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Preparation of Special Budget Request for


unfunded filled positions

DEPARTMENT OF EDUCATION 205


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 2 2 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Efficient Budget Utilization

DEPARTMENT OF EDUCATION 207


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
6600 1650 1650 1822 2319 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support
Objective: Established and
maintained systems for
accountability in utilizing
resources of the SDO within the
prescribed period

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Release of Salaries, Allowances and other


benefits of employees

DEPARTMENT OF EDUCATION 210


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 651 1023 651 1023 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Record and update daily cash records

DEPARTMENT OF EDUCATION 212


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
48 12 12 12 12 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Receipt and Deposit Collection

DEPARTMENT OF EDUCATION 214


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 258 411 258 411 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Prepare and Submit reports:


Collection & deposit (Bureau of Treasury,
Centrally-managed Project, Provident Fund)
Checks / ADA issued
Report of Accountability for Accountable
Forms

DEPARTMENT OF EDUCATION 216


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 39 411 39 411 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Remittance of Government / Personal share to


GSIS

DEPARTMENT OF EDUCATION 218


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 22 115 22 115 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:


• Conduct of procurement and acquisition of
goods and services:
Agency Procurement Request (APR)
Purchase Request(PR)
Purchase Order (P.O)
Memorandum of Agreement/Contract
Job Orders

DEPARTMENT OF EDUCATION 220


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 40 166 43 166 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Receipt & inspection of supply / ies by the end


users to be delivered within the target date.
Inspection and Acceptance Report (IAR)

DEPARTMENT OF EDUCATION 222


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 40 45 41 45 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Issuance and distribution of deliveries within


the target date
Requisition and Issue Slip(RIS)
Report of Supplies and Materials Issued
(RSMI)

DEPARTMENT OF EDUCATION 224


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 450 476 457 476 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Maintenance of updated inventory record of


properties within the prescribed period
(Report on Physical Count of Inventory or
RPCI / Report on Physical Count of Property
Plant & Equipment or RPCPPE) district /
cluster

DEPARTMENT OF EDUCATION 226


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
160 40 40 40 40 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Management of disposal of unserviceable


materials and properties as per request by the
accountable officer within the target date
(Ispection & Inventory Report on
Unserviceable Property or IIRUP)

DEPARTMENT OF EDUCATION 228


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 10 7 10 7 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• 100% of Total MOOE Allocation of Non-


Implementing Units is downloaded thru Cash
Advance

DEPARTMENT OF EDUCATION 230


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
2308 577 577 570 544 99% 94%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• 100% of Total downloaded cash advance is


fully liquidated

DEPARTMENT OF EDUCATION 232


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
2308 577 577 456 427 79% 74%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support
Objective: Performed oversight functions in
the implementation of laws, policies,
programs, rules and regulations of 438 public
elementary schools, 117 junior high schools,
and 87 senior high schools within DepEd
responsibility in the SDO at the end of the FY

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Technical Assistance in the Conduct of PISA


Main Survey:
Testing of Computer Units
Acted as Technical Staff during Main Survey

DEPARTMENT OF EDUCATION 235


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
6 6 6 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Monitoring of Programme for International


Student Assessment (PISA) 2018 Main Survey

DEPARTMENT OF EDUCATION 237


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Preparation of School Report Card (SRC)


Report

DEPARTMENT OF EDUCATION 239


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1110 555 555 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Monitoring of Division Oplan Balik Eskwela


(OBE)

DEPARTMENT OF EDUCATION 241


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• NAT 12 Monitoring

DEPARTMENT OF EDUCATION 243


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• QATAME of Division trainings, seminars

DEPARTMENT OF EDUCATION 245


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 17 17 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Crafting of Assessment Test monitoring tool

DEPARTMENT OF EDUCATION 247


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Consolidation and Submission of Adopt-a-


School Program (ASP) Quarterly Report

DEPARTMENT OF EDUCATION 249


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
160 40 40 40 40 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Formalization of initial agreements and unities


with groups and organizations and other
external partners

DEPARTMENT OF EDUCATION 251


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Initiation of new partnership agreements with


external partners for joint undertakings

DEPARTMENT OF EDUCATION 253


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 2 2 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Meeting for partnership formation with


Academe and other institutions to develop
SDO capacity

DEPARTMENT OF EDUCATION 255


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
2 2 2 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Capacity building project of SDO registered


guidance counselors and designated guidance
teachers

DEPARTMENT OF EDUCATION 257


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Refinement of School DRRM monitoring tool


that focuses on data related to the 3 pillars

DEPARTMENT OF EDUCATION 259


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of quarterly multi-hazard drills

DEPARTMENT OF EDUCATION 261


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Revision of the SDO-formulated DRRM


Orientation module by merging it with the
DRRMS -related modules

DEPARTMENT OF EDUCATION 263


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of Bantay Presyon Para Sa Guro


Project in schools

DEPARTMENT OF EDUCATION 265


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
555 150 150 150 150 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of Health and Nutrition Education


through trainings, orientations and lectures on
different health and nutrition-related issues like
HIV, AIDS, NDEP, Teenage Pregnancy, Mental
Health, Feminine Hygiene, Deworming and
Essential Health Care

DEPARTMENT OF EDUCATION 267


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
9 2 3 2 3 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Monitoring of the implementation of different health and nutrition


programs:
SBFP
NDEP (Barkada Kontra Droga, Random Drug Test)
ARH
WinS
Tobacco Control Program
UMDC
Bantay Presyon Para Sa Guro Project
Teachers Health Welfare Enhancement Program
School-based Deworming
School-based Immunization
Weekly Iron Folic Acid
Physical Examination (delegates, newly-hired teachers, etc.)
DEPARTMENT OF EDUCATION 269
Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
48 12 12 12 12 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of tooth extraction / treatment (as


requested)

DEPARTMENT OF EDUCATION 271


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 40 40 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of Dental Health Education & Check


Up

DEPARTMENT OF EDUCATION 273


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
350 105 35 180 49 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Coordination of GSP activities

DEPARTMENT OF EDUCATION 275


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
135 45 45 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Coordination of BSP activities

DEPARTMENT OF EDUCATION 277


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
180 45 45 45 45 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Administration of national, regional, & division


assessment tests

DEPARTMENT OF EDUCATION 279


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 1 4 1 2 100% 50%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• 2018 Brigada Eskwela (BE) Advocacy and


Promotion (BE Kick-off Ceremony and
Caravan)

DEPARTMENT OF EDUCATION 281


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Search for Division BE Best Implementers

DEPARTMENT OF EDUCATION 283


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
1 1 1 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of Universal Medical and Dental


Check-up (UMDC)

DEPARTMENT OF EDUCATION 285


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
80 40 40 40 40 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of Vision and Auditory Examination

DEPARTMENT OF EDUCATION 287


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
80 40 40 40 40 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of Tooth Extraction

DEPARTMENT OF EDUCATION 289


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 40 8 40 8 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of the Orientation on School Based


Feeding Program School Year 2017-2018

DEPARTMENT OF EDUCATION 291


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
33 33 33 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Validation of Annual Physical Examination


Results

DEPARTMENT OF EDUCATION 293


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
40 40 40 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

General Administration
and Support

Objective: Resolved cases involving


teachers, school officials and staff
serving in the SDO

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Evaluation of administrative complaints /


grievances filed in the SDO and provision of
appropriate action as prescribed by rules

DEPARTMENT OF EDUCATION 296


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 20 15 20 15 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Issuance of certification of no pending


administrative case for various purposes

DEPARTMENT OF EDUCATION 298


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 412 1157 412 1157 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Issuance of Special Orders (CNM/CSM/


CNNM/ CSNM) as requested

DEPARTMENT OF EDUCATION 300


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 33 80 33 80 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of fact finding, preliminary and formal


investigations within the period prescribed by
the rules

DEPARTMENT OF EDUCATION 302


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 10 3 10 3 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Conduct of grievance hearings

DEPARTMENT OF EDUCATION 304


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 7 5 7 5 100% 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Performance of on-site investigations

DEPARTMENT OF EDUCATION 306


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 3 1 3 1 100% 100%

DEPARTMENT OF EDUCATION
STATUS OF FD's VALUE-ADDED
LESSONS LEARNED
PROGRAMS & PROJECTS CONTRIBUTIONS
MEPA STATUS OF PROGRAMS
AND PROJECTS’ BALANCE
ISSUES AND EDUCATION RESOURCE
UTILIZATION OF SDO
MOOE & GAA FUNDS Physical Accomplishments
FOR THE QUARTER RESOLUTIONS SUPPORT

Regulatory
& Developmental
Services to Private
Schools

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Basic Education Inputs


Program

Objective: Evaluated and


recommended for approval the
request for schedule of fees of the 166
private schools in the SDO.

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Endorsement of Application for Increase in


School Fees

DEPARTMENT OF EDUCATION 310


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 30 30 100%

DEPARTMENT OF EDUCATION
Physical
Accomplishments

Program / Project / Activity:

• Approval of Notation for School Fees

DEPARTMENT OF EDUCATION 312


Physical
Accomplishments

PHYSICAL
TARGETS
ACCOMPLISHMENTS
% ACCOMPLISHED VS.
ANNUAL TARGET
TARGET (No. of Planned Outputs (No. of Outputs
per Quarter) Achieved to Date)

Q1 Q2 Q1 Q2 Q1 Q2
100% 177 177 100%

DEPARTMENT OF EDUCATION
Physical Accomplishments

STATUS OF PHYSICAL ACCOMPLISHMENTS BY FDs

PHYSICAL
TARGETS ACCOMPLISHMENTS
%
FUNCTIONAL (No. of ACCOMPLISHED
(No. of Outputs
DIVISION Planned VS. TARGETS
Achieved to
Outputs per
Date)
Quarter)
Q1 Q2 Q1 Q2 Q1 Q2
CID 2036 1357 2814 1971 100% 100%
OSDS 5979 11379 6031 10763 97.81% 88.71%
SGOD 1217 1504 1440 1569 100% 99.87%
Total 9232 14252 10285 14315
(131) (1287) 98.58% 90.96%

DEPARTMENT OF EDUCATION
CONSOLIDATED STATUS
OF PHYSICAL
ACCOMPLISHMENTS BY FD

Chart Title
12000

10000

8000

6000

4000

2000

0
Q1 Q2 Q1 Q2 Q1 Q2
(No. of Planned Outputs per Quarter) (No. of Outputs Achieved to Date)
TARGETS PHYSICAL ACCOMPLISHMENTS % ACCOMPLISHED VS. TARGETS

CID OSDS SGOD

DEPARTMENT OF EDUCATION
STATUS OF FD's PROGRAMS & VALUE-ADDED
LESSONS LEARNED
PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
AND PROJECTS’ BALANCE
ISSUES AND EDUCATION RESOURCE
RESOLUTIONS SUPPORT
FOR THE QUARTER

STATUS OF PROGRAMS
AND PROJECTS’ BALANCE
FOR THE QUARTER
VALUE-ADDED
STATUS OF PROGRAMS
STATUS OF FD's
LESSONS LEARNED
PROGRAMS & PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
AND PROJECTS’ BALANCE
FOR THE QUARTER
ISSUES AND
RESOLUTIONS
EDUCATION RESOURCE
SUPPORT
MOOE & GAA FUNDS
AND PROJECTS’ BALANCE

TABLE 1-F: STATUS OF PROGRAMS & PROJECTS’ BALANCE FOR THE QUARTER

NAME OF STATUS OF THE


UNACCOMPLISHE REASONS FOR THE
PROGRAMS BALANCE TO
OBJECTIVES D OUTPUTS BALANCE
AND DATE*
PROJECTS Q1 Q2 Q1 Q2 Q1 Q2
Ensured Updating of 1099 Problem with the Forwarded
compliance with PSIPOP in the system (System to the next
national Government owned by DBM; quarter
standards in Manpower Depends on the
recruitment, Information availablity of the
selection and System (GMIS): system)
training of staff No. of teachers
and included in the
performance plantilla
evaluation of
SDO employees
at the end of FY.

DEPARTMENT OF EDUCATION
STATUS OF PROGRAMS
AND PROJECTS’ BALANCE

NAME OF STATUS OF THE


UNACCOMPLISHE REASONS FOR THE
PROGRAMS BALANCE TO
OBJECTIVES D OUTPUTS BALANCE
AND DATE*
PROJECTS Q1 Q2 Q1 Q2 Q1 Q2
8. managed Submission of Bank 3 3 Late issuance of Late issuance of Forwarded Forwarded to
effective allocation Reconciliation bank statement bank statement by to the next the next
and utilization of Statement to by Landbank Landbank quarter quarter
human, physical Commission on Audit (Depends on (Depends on
and financial (COA) within 10 days the the availability
resources of the upon receipt of bank availability of of bank
SDO within the statement from the bank statement)
prescribed period. Authorized statement)
Government
Depository Bank
(AGDB)

DEPARTMENT OF EDUCATION
STATUS OF PROGRAMS
AND PROJECTS’ BALANCE

NAME OF STATUS OF THE


UNACCOMPLISHE REASONS FOR THE
PROGRAMS BALANCE TO
OBJECTIVES D OUTPUTS BALANCE
AND DATE*
PROJECTS Q1 Q2 Q1 Q2 Q1 Q2
9. established 100% of Total 7 33 Some school July MOOE was Forwarded Forwarded to
and maintained MOOE Allocation heads do not downloaded in Q2 to the next the next
systems for of Non- liquidate on time (bec. of the new quarter quarter
accountability in Implementing Units despite the process on
utilizing is downloaded thru SDO's disbursement, i.e.
resources of the Cash Advance interventions to Use of checks
SDO within the encourage on- instead of ATM)
prescribed time liquidation
period.

DEPARTMENT OF EDUCATION
STATUS OF PROGRAMS
AND PROJECTS’ BALANCE

NAME OF STATUS OF THE


UNACCOMPLISHE REASONS FOR THE
PROGRAMS BALANCE TO
OBJECTIVES D OUTPUTS BALANCE
AND DATE*
PROJECTS Q1 Q2 Q1 Q2 Q1 Q2
9. established 100% of Total 121 150 Previous cash Previous cash Forwarded Forwarded to
and maintained downloaded cash advance not advance not to the next the next
systems for advance is fully liquidated liquidated quarter quarter
accountability in liquidated
utilizing
resources of the
SDO within the
prescribed
period.

DEPARTMENT OF EDUCATION
STATUS OF PROGRAMS
AND PROJECTS’ BALANCE

NAME OF STATUS OF THE


UNACCOMPLISHE REASONS FOR THE
PROGRAMS BALANCE TO
OBJECTIVES D OUTPUTS BALANCE
AND DATE*
PROJECTS Q1 Q2 Q1 Q2 Q1 Q2
10. performed Administration of 2 Few registrants Examiners
oversight functions in national, regional, & (Recommended to already
the implementation of division assessment take the exam in SDO- endorsed to
laws, policies, tests City of San Fernando) another division
programs, rules and
regulations of 438
public elementary
schools, 117 junior
high schools, and 87
senior high schools
within DepEd
responsibility in the
SDO at the end of the
FY.

DEPARTMENT OF EDUCATION
STATUS OF FD's PROGRAMS & VALUE-ADDED
LESSONS LEARNED
PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
AND PROJECTS’ BALANCE
ISSUES AND EDUCATION RESOURCE
RESOLUTIONS SUPPORT
FOR THE QUARTER

VALUE-ADDED
CONTRIBUTIONS
FOR THE QUARTER
VALUE-ADDED
STATUS OF FD's VALUE-ADDED
LESSONS LEARNED
PROGRAMS & PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
AND PROJECTS’ BALANCE
ISSUES AND
RESOLUTIONS
EDUCATION RESOURCE
SUPPORT
MOOE & GAA FUNDS
CONTRIBUTIONS
FOR THE QUARTER

VALUE-ADDED CONTRIBUTIONS

FD / VALUE-ADDED CONTRIBUTIONS REASONS FOR ACHIEVING THEM


ADMIN
& BFD Q1 Q2 Q1 Q2
CID Hiring of Teachers, Checking of School Sacrificing other Interfacing with
Interview & Forms tasks/time SGOD; Support to
Observation in the management in CO's activities
Demo-Teaching Basic Education
Monitoring other Screening and Hiring Being results- Time management
programs (SBM) & of Teachers focused
SHDP Application
Projects Validation
Team

DEPARTMENT OF EDUCATION
VALUE-ADDED
CONTRIBUTIONS

FD / VALUE-ADDED CONTRIBUTIONS REASONS FOR ACHIEVING THEM


ADMIN
& BFD Q1 Q2 Q1 Q2
Resource speakership in Speakership on CO,RO Self-management Self Management and
the Regional Level and Division Trainings Leadership Skills
Monitoring of private Speakerships in RO & Time management Interfacing activity /
schools SDO Support to other functional
divisions

Serving as member of the Screening and Hiring of Passion for service & Time management
PRAISE Committee Teachers teamwork

DEPARTMENT OF EDUCATION
VALUE-ADDED
CONTRIBUTIONS

FD / VALUE-ADDED CONTRIBUTIONS REASONS FOR ACHIEVING THEM


ADMIN
& BFD Q1 Q2 Q1 Q2
Checking of class programs Analysis of Low Performing Passion for service & Interfacing activity / Support to
Schools and Least Mastered teamwork other functional divisions
Skills for Interventions
SBM Validation and SHDP Interfacing activity / Support to
Application Project, PRAISE other functional divisions
Committee

Oplan Balik-Eskwela Interfacing activity / Support to


Monitoring and Brigada other functional divisions
Eskwela Best Implementers

DEPARTMENT OF EDUCATION
VALUE-ADDED
CONTRIBUTIONS

FD / VALUE-ADDED CONTRIBUTIONS REASONS FOR ACHIEVING THEM


ADMIN
& BFD Q1 Q2 Q1 Q2
Monitoring of Private Interfacing activity / Support to
Schools other functional divisions

Memberships in SGLC, Time management


LCPC, Co-Chairs of LSB
etc.
Attendance to Provincial Time management
Council for SPED and
Kindergarten Teachers

Attendance to Regional Interfacing activity / Support to


Convergence other functional divisions

DEPARTMENT OF EDUCATION
VALUE-ADDED
CONTRIBUTIONS

FD / VALUE-ADDED CONTRIBUTIONS REASONS FOR ACHIEVING THEM


ADMIN
& BFD Q1 Q2 Q1 Q2
OSDS Submission of the AIP for Availability of records
Admin. SEF on time
Services
Submission of Status of Compliance of concerned
Implementation Report for officials
SEF on time for SGLG
Submission of Agency Approval of the SDS,
Action Plan on AOMs leadership fo the ASDS
recommendations for CY (Elem.) cooperation of
2017 concerned school officials,
teachers and PTAs

DEPARTMENT OF EDUCATION
VALUE-ADDED
CONTRIBUTIONS

FD / VALUE-ADDED CONTRIBUTIONS REASONS FOR ACHIEVING THEM


ADMIN
& BFD Q1 Q2 Q1 Q2
Admin. Conduct of on-site Availability of Committee
Services
validation activities for Members and support of
school heads and the Supply Unit
designated TICs for
possible reclassification
of positions
Conduct of disposal Availability of Committee
activities Members and support of
the Supply Unit
Preparation of Special Interfacing and consultation
Orders, Plans, etc. for the with Division document
ISO certification of the controller
SDO

DEPARTMENT OF EDUCATION
VALUE-ADDED
CONTRIBUTIONS

FD / VALUE-ADDED CONTRIBUTIONS REASONS FOR ACHIEVING THEM


ADMIN
& BFD Q1 Q2 Q1 Q2
HRMU DIVISION WORKSHOP ON Interfacing with Other Units
THE USE OF ENTERPRISE (Supply, Admin. Office, ITO, HRD);
HUMAN RESOURCE Support from the Agency Head
INFORMATION SYSTEM (E-
HRIS) AND ENCODING OF
Epds OF SCHOOL
PERSONNEL
DISTRICT PERSONNEL Teamwork from the technical
AUDIT, RECONCILIATION AND working group who conducted
UPDATING OF THE validation and personnel audit;
REMAINING UNFILLED ITEMS Support from the Agency Head,
OF THE PERSONAL AO-V and ASDS (Elem)
SERVICES ITEMIZATION AND
PLANTILLA OF PERSONNEL
(PSIPOP) UNDER THE WEB-
BASED APPLICATION
SYSTEM (GMIS)

DEPARTMENT OF EDUCATION
VALUE-ADDED
CONTRIBUTIONS

FD / VALUE-ADDED CONTRIBUTIONS REASONS FOR ACHIEVING THEM


ADMIN
& BFD Q1 Q2 Q1 Q2
LEGAL Resource Speakership APPSHP invitation during
their capacity building
Procedure Manuals for ISO
ISO

Quality Forms for ISO ISO

New PDFs for ISO ISO

DEPARTMENT OF EDUCATION
VALUE-ADDED
CONTRIBUTIONS

FD / VALUE-ADDED CONTRIBUTIONS REASONS FOR ACHIEVING THEM


ADMIN
& BFD Q1 Q2 Q1 Q2
ICT Acted as Resource Speaker Provided resources and
in the Division Roll-Out in information to participants in
the Implementation of the the said Division Roll-Out.
Enterprise Human Resource
Information System.
SGOD Checking of School Forms Checking of School Forms Interfacing with CID; Interfacing with CID; Support
SMM&E Support to FD's activities to FD's activities

HRDSSpeakerships in RO & SDO Review of Revised Interfacing activity / Support Updating of SBM Framework
Assessment Tool on SBM; to other functional divisions & Assessment Tool
Crafting of standards & tool
on Leadership

DEPARTMENT OF EDUCATION
VALUE-ADDED
CONTRIBUTIONS

FD / VALUE-ADDED CONTRIBUTIONS REASONS FOR ACHIEVING THEM


ADMIN
& BFD Q1 Q2 Q1 Q2
RESEARCHConduct of GAD and Values Review of Procedural Manuals Coordination with requesting International Organization for
Formation-Related Seminars (PMs) & Work Instruction school for needs assessment as Standardization (ISO) Certification
Manuals (WIMs) basis for the provision of
seminars/talks, 2. Preparation of
powerpoint presentations
SocMobPerformance of functions in the Speakerships in SDO Support to the procurement Interfacing activity / Support to
BAC activities as Secretariat activities of the office other functional divisions
member

Checking of School Forms Interfacing with CID; Support to Preparation of slide decks
FD's activities

Performance of functions in the Support to the procurement


BAC activities as Secretariat activities of the office
member

DEPARTMENT OF EDUCATION
STATUS OF FD's PROGRAMS & VALUE-ADDED
LESSONS LEARNED
PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
RESOLUTIONS SUPPORT
FOR THE QUARTER

ISSUES AND RESOLUTIONS


BY CATEGORY
ISSUES
STATUS OF FD's VALUE-ADDED
LESSONS LEARNED
PROGRAMS & PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO

AND RESOLUTIONS
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
FOR THE QUARTER RESOLUTIONS SUPPORT

ISSUES AND RESOLUTIONS BY CATEGORY


2ND QUARTER
ISSUES FOR
PROPOSED
ATTENTION OF
ISSUES WITHIN RESOLUTION
PROPOSED HIGHER
CATEGORY OF ISSUES THE UNIT'S OR ACTION
RESOLUTION MANAGEMENT /
CONTROL SOUGHT FROM
EXTERNAL
MGT
STAKEHOLDERS
TECHNICAL Difficulty in collating / Improve processes,
analyzing data coordination and
particularly in late communication plan
submission of (E.g. Use of ICT in
schools and other submission of
functional units. reports)

Feedback in LR Creation of feedback


Portal utilization. feature in LR portal.

DEPARTMENT OF EDUCATION 334


ISSUES
AND RESOLUTIONS

ISSUES FOR
PROPOSED
ATTENTION OF
ISSUES WITHIN RESOLUTION
PROPOSED HIGHER
CATEGORY OF ISSUES THE UNIT'S OR ACTION
RESOLUTION MANAGEMENT /
CONTROL SOUGHT FROM
EXTERNAL
MGT
STAKEHOLDERS
TECHNICAL Internet reliability problem I.T.O shall take
action
Unavailability of Connect to other Request for online
internet connection unit/office billing statement from
due to late issuance the service provider
of billing statement
from the service
provider
Lack of Personnel To hire or assign
personnel with
computer skills
DEPARTMENT OF EDUCATION 335
ISSUES
AND RESOLUTIONS

ISSUES FOR
PROPOSED
ATTENTION OF
ISSUES WITHIN RESOLUTION
PROPOSED HIGHER
CATEGORY OF ISSUES THE UNIT'S OR ACTION
RESOLUTION MANAGEMENT /
CONTROL SOUGHT FROM
EXTERNAL
MGT
STAKEHOLDERS
TECHNICAL No buildable space for Replace dilapidated
other schools with classrooms to High Rise
classroom shortage buildings to maximize
utilization of limited
space
Limited budget allocation for To increase the
the schools needing additional budgetary allocation
classrooms and major repair intended for classroom
construction and repair
Right of way problems To provide hauling cost
on the location of other in the Program of Works
schools sites for projects
implementation
DEPARTMENT OF EDUCATION 336
ISSUES
AND RESOLUTIONS
ISSUES FOR
PROPOSED
ATTENTION OF
ISSUES WITHIN RESOLUTION
PROPOSED HIGHER
CATEGORY OF ISSUES THE UNIT'S OR ACTION
RESOLUTION MANAGEMENT /
CONTROL SOUGHT FROM
EXTERNAL
MGT
STAKEHOLDERS
TECHNICAL Limited number of Ensure sufficiency of
Textbooks and Answer test materials
Sheets provided (NAT
12)
Exam rescheduled; Gr. Test administration
12 students already should be done
graduated) during the school
year
Updating of the PSIPOP Subscribe to a faster
depends on the internet connectivity
availability of the GMIS (higher MBPS)
and internet connection
DEPARTMENT OF EDUCATION 337
ISSUES
AND RESOLUTIONS

ISSUES FOR
PROPOSED
ATTENTION OF
ISSUES WITHIN RESOLUTION
PROPOSED HIGHER
CATEGORY OF ISSUES THE UNIT'S OR ACTION
RESOLUTION MANAGEMENT /
CONTROL SOUGHT FROM
EXTERNAL
MGT
STAKEHOLDERS
INSTITUTIONAL More focused Adjustment of Prioritization of mandates Consideration in
attention to value number of TA during (Agreement is 70% KRA adjusting targets.
added contributions. sumer and June. & 30% other designation)
Poor time Coaching of
management of concerned school
school heads heads
Poor planning w/c Reprimand
results to poor concerned SHs
procurement

DEPARTMENT OF EDUCATION 338


ISSUES
AND RESOLUTIONS

ISSUES FOR
PROPOSED
ATTENTION OF
ISSUES WITHIN RESOLUTION
PROPOSED HIGHER
CATEGORY OF ISSUES THE UNIT'S OR ACTION
RESOLUTION MANAGEMENT /
CONTROL SOUGHT FROM
EXTERNAL
MGT
STAKEHOLDERS
FINANCIAL Late CO downloading of PMPP and Project Partnership with LGUs / NGOs Appeal to CO for earlier
funds. Proposals should be ready for project implementation. downloading of ALS/ IPED
for implementation once funds.
CO-funds are
downloaded.
ENVIRONMENTAL / Lesser number of ALS mobile teachers are Partnership with external Inclusion in the SDO /
INFRASTRUCTURE Community Learning requested to go to gasak stakeholders for funding of LGUs / NGOs budget in
Centers to accommodate farms / homes where the CLCs. buildig CLCs.
ALS learners. ALS learners are.
Stock room for delivered Building of store room and Inclusion of building of store Building of store room/ big
instructional materials from implementation of stock room/ big room for LRMDS in room for LRMDS.
RO, CO. plan the AIP, PPMP and request of
SDO to CO.

DEPARTMENT OF EDUCATION 339


ISSUES
AND RESOLUTIONS

ISSUES FOR
PROPOSED
ATTENTION OF
ISSUES WITHIN RESOLUTION
PROPOSED HIGHER
CATEGORY OF ISSUES THE UNIT'S OR ACTION
RESOLUTION MANAGEMENT /
CONTROL SOUGHT FROM
EXTERNAL
MGT
STAKEHOLDERS

ENVIRONMENTAL / No enough storage


INFRASTRUCTURE for document
safekeeping

DEPARTMENT OF EDUCATION 340


STATUS OF FD's PROGRAMS & VALUE-ADDED
LESSONS LEARNED
PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
RESOLUTIONS SUPPORT
FOR THE QUARTER

LESSONS
LEARNED
STATUS OF FD's VALUE-ADDED
LESSONS LEARNED
PROGRAMS & PROJECTS CONTRIBUTIONS
MEPA STATUS OF PROGRAMS
AND PROJECTS’ BALANCE
ISSUES AND EDUCATION RESOURCE
UTILIZATION OF SDO
MOOE & GAA FUNDS LESSONS LEARNED
FOR THE QUARTER RESOLUTIONS SUPPORT

LIST OF LESSONS LEARNED


2ND QUARTER
DIVISIONS LESSONS LEARNED
OSDS The ISO journey of the SDO is not just for fulfillment
of a mandate but a commitment of the entire
organization to improve processes and systems to
provide quality service.
The ISO certification is the answer to the quest for
organizational alignment (of purpose, people, &
processes)
CID Prioritization of mandates is necessary over the
value added contribution to improve schools'
curriculum implementation and delivery of basic
education services.

DEPARTMENT OF EDUCATION 342


LESSONS LEARNED

DIVISIONS LESSONS LEARNED


Technical Assistance (TA) should be provided to
schools and learning centers.
Interfacing is necessary for analysis of data gathered
to craft better interventions to address schools' poor
learning outcomes
Work beyond the call of duty in order to submit real
and on-time data to other functional divisions.
OSDS Availability of data facilitate preparation of reports.
ADMIN. SERVICES
Early compliance of concerned officials/employees
contribute to meeting time frames.

DEPARTMENT OF EDUCATION 343


LESSONS LEARNED

DIVISIONS LESSONS LEARNED


RECORDS ISO is vital to the improvement of records and file
management through the implementation of document
tracking system.
HRMO Remove all excuses for failure.
Build a gung-ho culture of learning and innovation.
Interfacing is necessary to improve the delivery of
education services.
Find ways to share the helm.
Human resources are the most important resources of an
organization, hence, there is a need to take care of and
build our people while taking care of the organizational
health.
DEPARTMENT OF EDUCATION 344
LESSONS LEARNED

DIVISIONS LESSONS LEARNED


ICT There is a need to improve the technological
infrastructure and process, systems related to ICT
ICT is an integral part of an organization's life.
PROPERTY & SUPPLY Effective procurement results from effective planning.
ICT plays a vital role in supply & inventory management.
SMM&E ISO contributes to the success of an organization.
Work is overwhelming; Be responsible.
Assist co-workers; Never make them feel you're
superior.

DEPARTMENT OF EDUCATION 345


LESSONS LEARNED

DIVISIONS LESSONS LEARNED


HRD There’s a lot of work to be done, take each work one at a time.
Plan and prepare ahead of time.
We should always strive for quality output.
PHYSICAL FACILITTIES There is a need for effective and efficient project monitoring to
ensure the structurally and physically safe buildings.
Accurate and updated data from schools should be provided for
the purpose of analyzing school needs.
RESEARCH In the face of the huge tasks of evaluating research / inovation
studies, both proposed and completed, it is important to stop
once in a while and smell the flowers along the way.
Research & innovation contribute to the improvement of
teaching-learning processes and governance,

DEPARTMENT OF EDUCATION 346


LESSONS LEARNED

DIVISIONS LESSONS LEARNED


YFP Proper coordination is vital in conducting Division
wide youth activity.
The best way to prepare the leaders of tomorrow is to
prepare the young of today.
Collaboration and cooperation is essential in the
success of the activity.

DEPARTMENT OF EDUCATION 347


LESSONS LEARNED

LESSONS LEARNED COMMON TO ALL THE DIVISIONS


2ND QUARTER
The ISO journey of the SDO is not just for fulfillment of a mandate but a
commitment of the entire organization to improve processes and systems to
provide quality service.
The ISO certification is the answer to the quest for organizational alignment
(of purpose, people, & processes)
Availability of data facilitates preparation of reports.
ICT is an integral part of an organization's life.
Prioritization of mandates is necessary over the value added contribution.

DEPARTMENT OF EDUCATION 348


STATUS OF FD's PROGRAMS & VALUE-ADDED
LESSONS LEARNED
PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
FOR THE QUARTER RESOLUTIONS SUPPORT

EDUCATION
RESOURCE
SUPPORT
STATUS OF FD's VALUE-ADDED
PROGRAMS & PROJECTS CONTRIBUTIONS
LESSONS LEARNED
UTILIZATION OF SDO UPDATE OF PERSONNEL
REQUIREMENTS
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
FOR THE QUARTER RESOLUTIONS SUPPORT

Status of Personnel
Requirements
and Deployment

DEPARTMENT OF EDUCATION
UPDATE OF PERSONNEL
REQUIREMENTS

STATUS OF PERSONNEL REQUIREMENT AND DEPLOYMENT

No. of Personnel with No. of Personnel Detailed Casual/Contractual/JO


Plantilla for the Division in the Division Employees
Total
Technical Support Technical Support Technical Support
DO FUNCTIONAL UNITS 3rd Level 3rd Level 3rd Level
Staff Staff Staff Staff Staff Staff

OSDS 3 12 18 0 0 0 0 0 0 33

1 73 0 0 0 0 0 7 81
▪ ADMINISTRATIVE SERVICE 0

0 27 0 0 0 0 0 2 29
▪ FINANCE 0

SGOD 49 0 0 0 0 0 0 1 50
0

CID 51 1 0 0 0 0 0 0 52
0

TOTAL 1 109 114 0 0 0 0 0 10 234

DEPARTMENT OF EDUCATION
UPDATE OF PERSONNEL
REQUIREMENTS

DEPARTMENT OF EDUCATION
UPDATE OF PERSONNEL
REQUIREMENTS

No. of Personnel with Plantilla for the Division


120

100

80

60

40

20

0
OSDS SGOD CID
3rd Level 3 0 0
Technical Staff 12 49 51
Support Staff 113 1 1

DEPARTMENT OF EDUCATION
UPDATE OF PERSONNEL
REQUIREMENTS

No.
18
of Personnel Detailed in the Division
16
14
12
10
8
6
4
2
0
OSDS SGOD CID
3rd Level 0 0 0
Technical Staff 0 0 0
Support Staff 16 0 0

DEPARTMENT OF EDUCATION
UPDATE OF PERSONNEL
REQUIREMENTS

Casual/Contractual/JO Employees
16
14
12
10
8
6
4
2
0
OSDS SGOD CID
3rd Level 0 0 0
Technical Staff 0 0 0
Support Staff 14 1 0

DEPARTMENT OF EDUCATION
• Enrolment:

KINDER – 33, 605


ELEM. – 173, 526
JHS – 104, 446
SHS – 24, 601

Total: 336, 178

DEPARTMENT OF EDUCATION 356


• TEACHERS:

ELEM. – 7, 041
JHS – 4, 198
SHS – 1, 031

Total: 12, 270

DEPARTMENT OF EDUCATION 357


• NO. OF SCHOOLS:

ELEM. – 438
JHS – 117
SHS – 87

DEPARTMENT OF EDUCATION 358


• NO. OF SCHOOL HEADS:

ELEM. – 376
JHS – 115

Total: 491

DEPARTMENT OF EDUCATION 359


STATUS OF FD's PROGRAMS & VALUE-ADDED
LESSONS LEARNED
PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
RESOLUTIONS SUPPORT
FOR THE QUARTER

UTILIZATION OF SDO
MOOE & GAA FUNDS
for SPECIAL PROGRAMS
& PROJECTS
Current
Appropriations
CURRENT
APPROPRIATIONS

DEPARTMENT OF EDUCATION
STATUS OF FD's VALUE-ADDED
PROGRAMS & PROJECTS CONTRIBUTIONS
LESSONS LEARNED
UTILIZATION OF SDO CURRENT
APPROPRIATIONS
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
FOR THE QUARTER RESOLUTIONS SUPPORT

Appropriation /
Project / Program / Activities Obligations Unobligated Balance BUR
Allotment

1 General Management & Supervision - DO 24,063,000.00 1,620,381.82 22,442,618.18 7%

2 Human Resource Development for 9,388,000.00 2,337,544.00 7,050,456.00 25%


Teaching & Non-Teaching

3 Elementary 171,953,000.00 53,174,257.99 118,778,742.01 31%

4 Secondary 33,435,000.00 9,603,408.36 23,831,591.64 29%

5 planning, monitoring, evaluation of schools 195,600.00 195,600.00 0%


to be conducted by DRRM Coordinators

DEPARTMENT OF EDUCATION
CURRENT
APPROPRIATIONS

Appropriation /
Project / Program / Activities Obligations Unobligated Balance BUR
Allotment
6 Board & lodging : Finalization of 2018 plans 264,000.00 264,000.00 - 100%
2019-2021 3 year agenda

7 Conduct of random drug testing in schools 154,400.00 124,760.00 29,640.00 81%

8 Repair of classrooms 93,417,529.91 - 93,417,529.91 0%

9 Conduct of 2017 Nat'l Competition on 10,000.00 - 10,000.00 0%


Storybook writing for K-Grade 3 teachers

10 MOOE-SHS 38,122,000.00 12,794,547.91 25,327,452.09 34%

DEPARTMENT OF EDUCATION
CURRENT
APPROPRIATIONS

Appropriation / Unobligated
Project / Program / Activities Obligations BUR
Allotment Balance

11 Conduct of Contingency Planning 27,667.00 27,667.00 0%


Workshop for DRRM -
Coordinators of Division

12 Capital Outlay 1,000,000.00 249,860.00 750,140.00 25%

TOTAL 372,030,196.91 80,168,760.08 291,861,436.83 22%

DEPARTMENT OF EDUCATION
CURRENT
APPROPRIATIONS

DEPARTMENT OF EDUCATION
CURRENT
STATUS OF FD's VALUE-ADDED
LESSONS LEARNED
PROGRAMS & PROJECTS CONTRIBUTIONS
UTILIZATION OF SDO

APPROPRIATIONS
MEPA STATUS OF PROGRAMS
MOOE & GAA FUNDS
ISSUES AND EDUCATION RESOURCE
AND PROJECTS’ BALANCE
FOR THE QUARTER RESOLUTIONS SUPPORT

Project / Program / Appropriation / Unobligated


Obligations BUR
Activities Allotment Balance

1 General Management & Supervision - 24,063,000.00 7,527,153.22 16,535,846.78 31%


DO
2 Human Resource Development for 9,388,000.00 4,776,220.70 4,611,779.30 51%
Teaching & Non-Teaching

3 Elementary 171,953,000.00 92,003,331.79 79,949,668.21 54%


4 Secondary 33,435,000.00 18,200,740.97 15,234,259.03 54%
5 planning, monitoring, evaluation of 195,600.00 6,084.00 189,516.00 3%
schools to be conducted by DRRM
Coordinators

DEPARTMENT OF EDUCATION
CURRENT
APPROPRIATIONS

Appropriation / Unobligated
Project / Program / Activities Obligations BUR
Allotment Balance

6 board & lodging : Finalization of 2018 264,000.00 264,000.00 - 100%


plans 2019-2021 3 year agenda
7 conduct of random drug testing in 154,400.00 132,852.00 21,548.00 86%
schools
8 repair of classrooms 93,417,529.91 88,267,208.96 5,150,320.95 94%
9 conduct of 2017 Nat'l Competition on 10,000.00 - 10,000.00 0%
Storybook writing for K-Grade 3
teachers
10 MOOE-SHS 38,122,000.00 19,511,636.03 18,610,363.97 51%

DEPARTMENT OF EDUCATION
CURRENT
APPROPRIATIONS

Appropriation / Unobligated
Project / Program / Activities Obligations BUR
Allotment Balance

11 Conduct of Contingency Planning 27,667.00 - 27,667.00 0%


Workshop for DRRM Coordinators of
Division
12 Capital Outlay 1,000,000.00 997,270.00 2,730.00 100%
13 Maintenance of Nurseries, Crop 1,140,000.00 850,000.00 290,000.00 75%
Museums
14 Cash Allowance 29,046,500.00 28,845,500.00 201,000.00 99%
15 IPED 657,000.00 9,865.00 647,135.00 2%
16 50% SBFP SY 2018-2019 30,383,640.00 30,383,640.00 0%

DEPARTMENT OF EDUCATION
CURRENT
APPROPRIATIONS

Project / Program / Activities Appropriation / Obligations Unobligated BUR


Allotment Balance

17 repair & rehab of San Pedro II ES 1,195,200.00 1,195,200.00 0%

18 teaching aid & transpo allowance for 2,647,400.00 2,647,400.00 0%


ALS MT & DALSC for FY 2018 (DepEd
Order No. 50, s.2017)

19 SHA Fiscal Year 2018 11,016,556.02 947,989.07 10,068,566.95 9%

20 50% SBFP SY 2018-2019 30,383,640.00 30,383,640.00 0%

Total 448,116,492.93 262,339,851.74 185,776,641.19 59%

DEPARTMENT OF EDUCATION
 MEPA provides objective
information on the status of
implementation of PAPs,
performance, progress, &
accomplishments of the
FDs / SDO necessary for
 The institutionalization of MEPA plan adjustment.
(system, process, tools) promotes
the culture of quality and
accountability in the division.

DEPARTMENT OF EDUCATION
 Division MOOE needs to
be judiciously, effectively
& efficiently managed.

 Results should be communicated


to all functional / support divisions
to develop a sense of ownership
and to sustain efforts for
continuous development.

DEPARTMENT OF EDUCATION
QUALITY POLICY
 DepEd Pampanga is committed to own our QMS as our way of life and
enliven our organizational identity by:
1. Conforming with the regulatory and all applicable ISO 9001:2015
requirements.
2. Providing quality services to our customers inspired by our Happy Galing
Lingkod advocacy.
3. Addressing and resolving all external and internal issues relevant to our
operations and strategic directions, thus, creating on-standard results.
4. Determining and conforming with the applicable regulatory requirements
of interested parties to sustain customer’s satisfaction.
5. Improving continually our QMS by eliminating operational inefficiencies
to best serve our purpose.