Professional Documents
Culture Documents
DISCHARGE BY IMPOSSIBILITY OF
PERFORMANCE
/. Introduction
2. Theories ofFrustration
(i) Theory ofImplied term
(ii) Theory ofJust solution
(Hi) Theory of foundation of the Contract
(iv) Construction theory
(v) Failure of Consideration theory
Practical Importance
Frustration and Mistake.
3. Indian Contract Act & Discharge by Impossibility
4. Supervening Impossibility -
(A) An Excuse
(a) Destruction ofsubject matter
(b) Non-existing of a state of things.
(c) Death or incapacityfor personal services.
(d) Change ofLaw.
(e) Out breach of War.
(B) Not An Excuse
(a) Difficulty of performance.
(b) Commercial impossibility.
(c) Failure of a thirdparty.
(d) Strikes, lockout and civil distrubance.
(e) SelfInduced impossibility.
5. Distinction between English & Indian Law.
CHATPER - V
DISCHARGE BY IMPOSSIBILITY
OF PERFORMANCE
1. INTRODUCTION
2. THEORIES OF FRUSTRATION
5. Denny, Mott Case [1944] AC. 265, 275; cf. Shell U. K. Ltd. v.
Lostock Garages Ltd., [1976) 1 W.L.R. 1187, 1196.
6. [1916)2 A.C. 397, 404.
[153]
13. [1916]2 A.C. 397; 406. Lord Haldane's was a dissenting speech.
14. [1939]1 K.B. 132, 137.
[155]
All the theories so far stated depend in the last resort on the
construction of the contract: to this extent, they "shade into one
another." '^ After stating the implied term theory, Lord Lorebum
proposed, as the ultimate test: "what, in fact, is the true meaning
of the contract?"*'^ Similarly, in Taylor v. Caldwell, Blackburn J.
said "the contract is not to be construed as a positive contract,
but as subject to an implied condition that the parties shall be
excused in case, before breach, performance becomes
impossible...."'^ Construing the contract and implying a term are in
these cases only alternative ways of describing the same process.
the contract is. And Lord Wright, in the course of stating the
"just solution" theory, said: "What happens is that the contract is
held on its true construction not to apply at all from the time
when the frustrating circumstances supervene."^' It seems that this
is the most satisfactory explanation of the doctrine of frustration.
Practical Importance
(3) In the Fareham case, Lord Reid also said that there
might be a practical difference between the "implied term" and
"construction" theories. On the latter theory "there is no need to
consider what the parties thought or how they or reasonable men
in their shoes would have dealt with the new situation if they had
foreseen it. The question is whether the contract which they did
make is, on its true construction, wide enough to apply to the new
situation: if not, then it is at an end."'" But in construing the
contract the court does not wholly disregard the intention of the
parties. The court may not have to ask: what would the parties
have said, had they thought of the frustrating event? But it does
have to ask in what circumstances did the parties intend the
contract to operate? It is only after this question has been
answered that the intention of the parties becomes irrelevant: that
is, it is not necessary to go on and ask whether they would have
agreed to discharge or to some compromise. But this question
does not arise under the implied term theory either, as fiiistration
at common law always results in total discharge of the contract.
Illustration :
ship should sail on a particular date and the covenant itself was
entered into after that date is meaningless and unenforceable/^
T.P. Act for in the latter the words are 'destroyed wholly or
rendered substantially and permanently unfit, while the phrase used
in Section 56 is 'an act becoming unlawful or impossible.' What
is 'impossible' is merely instanced in Section 108 (e). Section 56
gives the positive law while Section 108 (e) gives an option to the
lease.
' .... It was not this that I promised to do.' There is, however, no
uncertainty as to the materials upon which the Court must proceed.
'The data for decision, on the one hand, the terms and conditions
of the contract, read in the light of the then circumstances and, on
the other hand, the events which have occurred.' In the nature of
thing there is often no need for any elaborate enquiry. The Court
must act upon a general impression of what its rule requires. It is
for that reason that special importance is necessarily attached to
the occurrence of an unexpected event that, as it were, change the
face of the things. But even so, it is not hardship or inconvenience
or material loss itself which calls the principle of frustration into
play."^i
explanation."^^
whether or not frustration has occurred. Where after the firm price
contract for supply of transformers there was a subsequent 400%
rise in price of transformer oil due to the war, there was
frustration of contract. The abnormal increase in price due to war
condition, was an untoward event or change of circumstances
which "totally upset the very foundation upon which the parties
rested their bargain." Therefore, supplier could, be said to be
finding itself impossible to supply the transformers which it
promised to do.'^'^
78. J.L. V. Bihar State Co-op. Bank Ltd., AIR 1959 Pat 477
79. CA.G.Co. V. K.R.L. Narsimhan, AIR 1954 Mad 119
[180]
The provision under the New Act that the award to become
a decree naturally without in the context of building and engineering
contracts, frustration will normally arise by reason of some
supervening event such as destruction of the entire site by fire or
flood, or the passage of legislation rendering the work illegal. It is
important to appreciate that the supervening event must so
unexpected and beyond the control of the parties, even as a
possibility, that neither party can be said to have accepted the risk
of the event taking place when contracting. It is precisely for this
reason that frustration can only rarely come about in building and
engineering contracts, since their performance is, as a matter of
reasonable foresight, hedged about with many uncertainties and far
80. Ram Kumar v. P.C. Roy & Co., AIR 1952 Cal 335
[181]
Where the appellant had bid for the coal under the honest
and reasonable impression that he would be allowed to transport
the coal to Ferozabad, that this was thwarted by the attitude of
the coal commissioner, that later on the parties proceeded on the
basis that the auction sale was to be cancelled and the appellant
refunded his money. But apparently because by that time much of
the coal had been lost and the Railways would have been in
difficulty to explain the loss they chose to deny the appellant's
claim. Alagiriswami J. pollinated out that, "he can see no justification
on facts for such a denial and the defendants cannot refuse to
refund the plaintiffs amount. The contract had become clearly
fhistrated. We must make it clear that we are not referring to the
refusal to supply wagons but the refusal of the coal commissioner
to allow the movement of coal to Ferozabad inspite of the fact
that it was not one of the conditions of the auction. The appellant
is therefore, clearly entitled to the refund of his money. Furthermore,
the contract itself not being in accordance with Section 175 of the
Government of India Act is void and the appellant is entitled to
the refund of his money."^"*
4. SUPERVENING IMPOSSIBILITY
A) An Excuse
93. P.O. Mehta & Sons v. Ram Chand Om Prakash, AIR 1952 Punj
34, 38.
[187]
d) Change of law
98. Storey v. Fulham Steel Works Co. Ltd., (1907) TLR 89.
99. Shiam Sunder v. Durga, AIR 1966 All 185.
100. H.R. & G Industries v. State of Rajasthan, AIR 1964 Raj 205.
101. Man Singh v. Khazan Singh, AIR 1961 Raj 277.
102. Metropolitan Water Board v. Dick Kerr i& Co., ^C 119 (1916-17)
[191]
e) Outbreak of war :
103. AIR 1954 SC 44 : 1954 SCR 310; 1954 SCJ I; 1954 SCA 187.
[192]
B) Not An Excuse
a) Difficulty of performance :
b) Commercial impossibility :
126. Raja Dhruv Dev Chand v. Raja Harmohinder Singh & Anr., AIR
1968 SC 1024
127. Sushila Devi & Am. v. Hari Singh & Ors., AIR 1971 SC 1756
[201]
128. Mugneeram Bangur & CO., (P) Ltd. v. Gurbachan Singh, AIR
1965 SC 1523.
[203]
131. Sushila Devi & Am. v. Hari Singh & Ors., AIR 1971 SC 1756.
132. AIR 1969 SC 110
[205]
that it could have carried out some job as pointed out by AWHO
would depend upon the commercial viability as a large number of
workmen were to be engaged although it cannot carry out the
major construction work., which was a relevant factor for determining
the quantum of damages. Sumangal might have been partially liable
but it cannot be faulted when it refused to carry out any
constructional work in violation of the stop work notice which
would attract the penal provisions of Section 440 of the West
Bengal Municipal Act, 1993. The Arbitrators were also bound to
take into consideration this aspect of the matter. They failed to do
so and misdirected themselves in law.
This theory would mean that the court has inherent jurisdiction
to go behind the express Words of the Contract and attribute to
the Court the absolving power, a power consistently held not to
be inherent in it. But this theory was discarded by the House of
Lords in the appeal. In more recent times the theory of a change
in the obligation has come to be more and more generally
accepted. In Davis Contrctors v. Farehan U.D.C.,^** Lord Radcliffe
stated it as under :