1. with the approved material submittal Check the size of ducts & accessories are 2. installed as per approved shop drawing. Check hangers and supports are provided at 3. correct size and specified intervals and as per approved drawing. Check the access doors are provided as per 4. approved shop drawing. Check the installation of duct work is 5. coordinated with other work. Check the installation of VCD, FD & MSFD 6. are installed as per the approved shop drawing. Check the joints are properly cleated / 7. bolted / riveted. Check the sealant applications are provided 8. properly and neatly Check the insulation thickness and aluminum 9. foil tape is provided properly for all joints. Check duct supports are installed without 10. compressing the insulation