Company Name: Document No:
Mecha Ton Engineering Plc OF/MT /….
Title: Issue No. Page No.
Inspection Checklist 1 Page 1 of ..
1. Name of the Project:
2. Address: Sub City Kebele Telephone Fax
Contact Person Email
3. Project Life Received Date Submission Date : -
4. Building type Residence No. of stores : -
Office Building No. of stores :
-
Other ( Specify) :- No. of stores : -
5. CHECKLIST FOR DUCT
WORK
Parameters Checked Requirement as per Contract Actual Remarks Signature of Auth.
Specifications/ Approved Observation Engineer with Date
Drawings
Shop Drawing of
HVAC Ducting layout
for that Floor
Material from each lot It was
to approved
be sent for laboratory GI Sheet to confirm IS: 277 before our
test (latest revision) involvement
Required Thickness
of sheet to be used in Up to 350mm - 0.60 mm GI
Ducting as per duct 400 to 660mm – 0.70mm GI
sizes. 670 to 910 mm – 0.9mm GI
920 & above – 1.0mm GI Approved
Flanges / Supports / Before jointing of ducts, gasket
Nut to be fixed
bolts / gasket on one side flange. Approved
Duct hanger supports Before installation of M.S. Approved
angle support
primer coating shall be done
and sizes as
under.
Duct size M.S. Angle
Rod dia
Up to 1000 mm – 40x40x3 mm
- 10 mm
1001 to 1500 mm - 40x40x5
mm - 10 mm
Larger than 1500 - 50x50x6
mm – 10 mm
Anchor / dash
fastener
Prepared Name:
Designation: Signature: Date:
PLEASE MAKE SURE THAT THIS IS THE CORRECT ISSUE BEFORE USE
Company Name: Document No:
Mecha Ton Engineering Plc OF/MT /….
Title: Issue No. Page No.
Inspection Checklist 1 Page 2 of ..
Shall be coordinated at site
Levels with RCP
6. CHECKLIST FOR DUCT INSULATION WORK
Parameters Checked Requirement as per Contract Actual Remarks Signature of Auth.
Specifications Observation Engineer with Date
Before insulation on
duct, Duct
measurements shall
be completed.
Approved / not approved
Technical data of
insulation material
Checked for leakage If leakage found has been
in duct sealed by sealant.
Cold setting
compound properly
applied
If yes, additionally covered with
Is duct exposed to one layer of tar felt, stuck with
weather bitumen.
All joints properly
sealed
Insulation blanket
properly wrapped with
polythene sheet and
fixed with adhesive
tape
Insulation Reinforced
and tied with
GI wire of 1 mm
at intervals of 450 mm
7. CHECKLIST FOR ELECTRICAL CABLING WORK
Parameters Checked Requirement as per Actual Remarks Signature of Auth.
Contract Specifications Observation Engineer with Date
Prepared Name:
Designation: Signature: Date:
PLEASE MAKE SURE THAT THIS IS THE CORRECT ISSUE BEFORE USE
Company Name: Document No:
Mecha Ton Engineering Plc OF/MT /….
Title: Issue No. Page No.
Inspection Checklist 1 Page 3 of ..
Cable schedule of
HVAC Approved / not approved
Supply of Cable Sizes As per approved make list
Supports/Tray
properly fixed
Clamping of cables
properly
done
Cable Termination
(Thimbles/lugs etc.
Provided)
Insulation Resistance
Test
Continuity Test
Prepared Name:
Designation: Signature: Date:
PLEASE MAKE SURE THAT THIS IS THE CORRECT ISSUE BEFORE USE