You are on page 1of 8

TECHNICAL & FINANCIAL

PROPOSAL FOR PLUMPING


FIRE FIGHTING AND
MECHANICAL WORK FOR
MYSERU MULTI-USE
BULDING (3B+G+15)
Contents

1. General...................................................................................................................... 3

2. Plumbing................................................................................................................... 3

3. Firefighting system....................................................................................................4

4. Storm Water Drainage...............................................................................................4

5. Ventilation and air conditioning system......................................................................4

6. Design Standards and Codes....................................................................................4

7. Design guide lines.....................................................................................................5

8. Drawings................................................................................................................... 5

9. Financial proposal.....................................................................................................5

11. Completion Time.......................................................................................................6

BRAND ENGINERING PLC

2
TECHNICAL & FINANCIAL PROPOSAL FOR PLUMPING & MECHANICAL WORK 3

1. General
The mechanical Firefighting and plumbing design work shall follow the requirements
given on the Ethiopian Building Code standard, plumbing services of buildings (ES-
3960, British (BS) or similar codes and standards.

The envisaged service in preview form is:

a) Carryout detailed engineering design.

b) Preparing relevant drawing and documents.

c) Preparing technical specification and bill of quantities and cost estimate.

2. Plumbing

2.1. Design Aspects

The main important design aspects to be considered are:

a) Pipe materials – The plumbing piping system shall be from durable material, free
from defective workmanship and so designed as to give satisfactory service for its
expected life.

Recommended pipe materials are:

i) Water supply – a - Galvanized steel for fire fighting

b - PPR for branch/horizontal and riser water supply


pipes.

ii) Drainage - uPVC pipes

b) Drainage system – The drainage system will be designed to guard against fouling,
deposit of solids and closing, and with adequate clean out so arranged that the

BRAND ENGINERING

3
pipes shall be readily cleaned. The drainage pipe layouts shall also be designed,
in such a way that it will be accessible for maintenance and replacement.

c) Water supply - Water source to the new Apartment shall be from municipal water
supply system. Municipal water will be stored for min. two days’ water demand &
water distribution to the internal fixtures shall be from bedrooms with automatic
booster pumps/with pressure vessel/ to be installed in the basement.

2.2. Plumbing systems

2.2.1. Internal hot & cold water supply

Individual storage electric water heater will be designed. Municipal cold water will be
treated with filtration & chlorination to meet standard or requirement.

Cold water distribution shall be as described in item 2.1.c above. Approved quality
isolating & control valves, drain and safety valves, air release valves, etc will be
provided as required.

2.2.2 Drainage system

All drainage pipes including venting pipes will be sized as per the requirements given
in ES-3960 or approved standards and cods /Depending of the position of fixtures
and drainage pipe connection.

Two drainage systems namely liquid & solid waste will be designed.

a) Liquid waste system - Hand wash basins, showers, laundry machines & etc
wastes shall be drained to directly to filtration pit though sedimentation tank.

b) Solid waste - All water closets & urinals will be drained to directly to
cesspool/septic tank.

BRAND ENGINERING PLC

4
TECHNICAL & FINANCIAL PROPOSAL FOR PLUMPING & MECHANICAL WORK 5

3. Firefighting system
One automatic fire booster pumps with diesel stand-by pump & adequate for min. two
hours water reservoir will be designed. The pump house, water reservoir & fire
hydrant locations will be coordinated with the architect before the design is
completed.

The designed will include:

a- Internal hose reels & hydrants as required

4. Storm Water Drainage


IDF curve of Addis Ababa is used to specify rainfall intensities. Catchments
characteristics are used to estimate the volume and flow rate of the runoff from the
rainfall using the rational formula. The manning equation is used to calculate pipe
and or channel size necessary to convey the calculated rate of flow.

5. Ventilation and air conditioning system


5.1. Ventilation system
The ventilation system shall be for toilets, stores car parking and kitchen areas these
areas appropriately rated with exhaust fans that will discharge to roof.

6. Design Standards and Codes


a. HVAC
o Ethiopian building code standard (ES-3960, & 3962)

o Chartered Institute of Building Service Engineers Guide


(CIBSE),

o British standard (BS) and relevant standard codes of practice


will be adopted for designing the HVAC system depending on
the specific requirement. ASHARE Standards

b. Plumbing

BRAND ENGINERING

5
- Ethiopian building code standard (ES-3960, & 3962)

- British Standard (BS) and relevant standard codes

c. Fire protection system


- Ethiopian building code standard (ES-3960, & 3964),

- Recommendation of National fire protection association (NFPA)

7. Design guide lines

i) Geographical data as per CIBSE


Location of site……………Addis Ababa Ethiopia
Latitude ……………. 9020’N
Longitude ………….380 45’E
Elevation …………. 2400m
ii) Outdoor Design Conditions
Summer ……………..290C DB and 18.90C WB
Winter ………………50C
iii) Indoor Design Conditions: for offices
a. Temperature ………….230C±10C
iv) Ventilation
a. Toilet: 5-10 air changes per hour,
b. Other service areas such as store, corridor, janitor room etc no temperature
controls only ventilation.
v) Potable cold water supply
Pressure: min 0.5 bars residual pressure at the critical fixtures outlet.
vi) Waste water drainage system
Waste water drainage system with vent rack
vii) Storm water drainage system
Peak storm water intensity 100mm/hr

BRAND ENGINERING PLC

6
TECHNICAL & FINANCIAL PROPOSAL FOR PLUMPING & MECHANICAL WORK 7

8. Drawings
Drawings will be prepared for floor plans, riser diagrams, site works, and for all other
necessary details in 1:50 scale and as required.

9. Financial proposal
The consultancy fee for the scope of services shown on the technical proposal shall
be: -

9.1. Mechanical (ventilation & Air Conditioning)

a) Ventilation:

i. Toilets ventilation……………....................................................15,000.00
ii. Parking ventilation……………...................................................10,000.00
iii. Kitchens ventilation…………….................................................15,000.00
b) Stair case air pressurization. ……………..………………………….…….5,000.00

c) Smoke extraction…………………………………….………………….…….5,000.00

Sub-total..………............................................................................50,000.00

9.2. Fire fighting system including fire pumps, piping & water reservoirs for
all buildings

a. Fire hose reel system……………………...............................................10,000.00


b. Sprinkler system to all basements, Apartment and shop areas.............25,000.00
Sub-total…………………………………………………….....35,000.00

9.3. Plumbing

a- Water supply system with automatic water booster pumps,...................25,000.00


b- Waste water drainage (gray and black water)...……..............................25,000.00
c- Roof & site storm water collection & disposal ……................................15,000.00
Subtotal…………….…….....65,000.00

BRAND ENGINERING

7
Total of items 10.1, 10.2 & 10.3 of above.……..……..……....…… 150,000.00

The total consultancy fee for the above mechanical & plumbing technical proposal
shall be Birr 150,000.00 / One Hundred Fifty Thousand Birr / excluding VAT.

10. The payment terms shall be as follows: -


a) 80% shall be paid after the submission of the design and documents.

b) 20% shall be paid after approval of the design and documents.

11. Completion Time


Completion time is 10 working days.

BRAND ENGINERING PLC